AU2015207927B2 - A building element - Google Patents
A building element Download PDFInfo
- Publication number
- AU2015207927B2 AU2015207927B2 AU2015207927A AU2015207927A AU2015207927B2 AU 2015207927 B2 AU2015207927 B2 AU 2015207927B2 AU 2015207927 A AU2015207927 A AU 2015207927A AU 2015207927 A AU2015207927 A AU 2015207927A AU 2015207927 B2 AU2015207927 B2 AU 2015207927B2
- Authority
- AU
- Australia
- Prior art keywords
- building element
- foundation
- rib
- ground
- pod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
- E02D27/013—Shuttering specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
- E02D27/016—Flat foundations made mainly from prefabricated concrete elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/34—Foundations for sinking or earthquake territories
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
- E04B5/36—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Foundations (AREA)
Abstract
A building element for forming a slab or a foundation with a settable material includes a body having an upper surface, a bottom, and sidewalls extending from the upper surface to the bottom. A hole is defined in the body. At least one rib-forming channel extends across the upper surface and intersects with the hole. Cavities are formed in the bottom of the body.
Description
2015207927 06 Feb 2017 1 A Building Element
FIELD
[0001] Various exemplary embodiments of building elements for forming a slab or foundation are described in this specification. The building elements are commonly referred to as cavity formers or pods.
SUMMARY
[0002] Various exemplary embodiments of a building element for forming a slab or a foundation with a settable material include a body having an upper surface, a bottom, and sidewalls extending from the upper surface to the bottom; a hole defined in the body, the hole being an aperture which extends completely through the body from the upper surface to the bottom, wherein the bottom of the body around the aperture is configured to rest on the ground in operation; at least one rib-forming channel which extends across the upper surface and intersects with the hole; and cavities formed in the bottom of the body.
[0003] The body may have a central aperture which extends through the body from the upper surface to the bottom. The central aperture may be configured to receive a pile. The rib forming channel(s) may intersect the central aperture.
[0004] The body may be generally rectangular in top plan view, and the sidewall may extend along the perimeter of the body.
[0005] The rib-forming channel(s) may extend diagonally across the upper surface from corner to corner, and the upright channel(s) may be at the corners of the body.
[0006] The rib-forming channel(s) may extend from side to side, with the upright channel(s) at the sides of the body.
[0007] Two upright channels and the rib-forming channel may together form one continuous channel.
[0008] Various exemplary embodiments of a building element system may include two or more of the building elements as described above placed side by side so that an 2015207927 06 Feb 2017 2 upright channel of one of the building elements is in register with an upright channel of the adjacent building element.
[0009] Various exemplary embodiments of a foundation are formed using the building elements of any one of the preceding claims, the foundation including: a generally flat slab portion formed on the upper surfaces of the bodies of the building elements; a number of reinforcement ribs on the underside of the slab portion which is suspended above the surface on which the foundation is formed, the reinforcement ribs being formed in the rib-forming channels; and a number of feet extending downwardly from the underside of the slab portion past the reinforcement ribs, the feet formed in the upright channels.
[0010] The foundation may include an edge beam depending downwardly from the slab portion, the edge beam having a void or cavity formed in a foot of the edge beam where the edge beam is supported on the surface on which the foundation is formed.
[0011] Various exemplary embodiments of a method of forming a foundation include the steps of: positioning a number of building elements, as described above, on a substrate to form the building element system; displacing a settable material onto the building element system so that at least the upright channels and rib-forming channels are at least partially filled with the settable material; and allowing the settable material to harden.
[0012] Reinforcing elements may be positioned in the rib-forming channels prior to displacing the settable material. Reinforcing elements may also be positioned in the upright channels prior to displacing the settable material.
[0013] Piles may be driven through the central apertures.
[0014] The reinforcing elements that are positioned in the upright channels may be tied to the piles prior to displacing the settable material.
[0015] Various exemplary embodiments of a building element for forming a slab or a foundation with a settable material include 2015207927 06 Feb 2017 3 a body having an upper surface, a bottom, and sidewalls extending from the upper surface to the bottom; a hole defined in the body; at least one rib-forming channel which extends across the upper surface and intersects with the hole; and cavities formed in the bottom of the body.
[0016] The pod may be shaped so that the cavities are in fluid communication with each other when the pod is placed on substantially level ground.
[0017] The sidewalls may have recesses extending upwardly from ground bearing surfaces of the sidewalls.
[0018] The hole may be a central aperture which extends through the body from the upper surface to the bottom.
[0019] The body may be generally rectangular in top plan view, with four sidewalls, each sidewall extending along a perimeter of the body.
[0020] The building element may include two rib-forming channels, each extending between opposite sidewalls and intersecting the hole.
[0021] The body may include a ground bearing projection that is substantially coplanarwith the ground bearing surfaces of the sidewalls, the hole being defined in the ground bearing projection.
[0022] Various exemplary embodiments of a building element system comprise two or more of the building elements as described above placed side by side so that at least one sidewall of one of the building elements is contiguous with at least one sidewall of an adjacent building element.
[0023] Various exemplary embodiments of a foundation formed using the building elements described above include: a generally flat slab portion formed on the upper surfaces of the bodies of the building elements; a number of reinforcement ribs on the underside of the slab portion which is suspended above the surface on which the foundation is formed, the reinforcement ribs being formed in the rib-forming channels; and 2015207927 06 Feb 2017 4 a number of feet extending downwardly from the underside of the slab portion past the reinforcement ribs, the feet formed in the holes.
[0024] The foundation may include an edge beam depending downwardly from the slab portion, the edge beam having a void or cavity formed in a foot of the edge beam where the edge beam is supported on the surface on which the foundation is formed.
[0025] Various exemplary embodiments of a method of forming a foundation include the steps of: positioning a number of the building elements on a substrate to form the building element system; displacing a settable material onto the building element system so that at least the rib-forming channels are at least partially filled with the settable material; and allowing the settable material to harden.
[0026] Reinforcing elements may be positioned in the rib-forming channels prior to displacing the settable material.
[0027] Piles may be driven through the hole defined in the building elements. DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 shows a top perspective view of an exemplary embodiment of a building element in the form of a pod.
[0029] Figure 2 shows a bottom perspective view of the pod of figure 1.
[0030] Figure 3 shows a side perspective view, from below, of the pod of figure 1.
[0031 ] Figure 4 shows a side view of the pod of figure 1.
[0032] Figure 5 shows a plan view of a number of pods of figure 1 arranged side by side to form part of a building element system.
[0033] Figure 6 shows a top view of another exemplary embodiment of a building element in the form of a pod.
[0034] Figure 7 shows a bottom view of the pod of figure 7.
[0035] Figure 8 shows a perspective view of the bottom of the pod of figure 7. 2015207927 06 Feb 2017 5 [0036] Figure 9 shows a perspective view of the top of the pod of figure 7.
[0037] Figure 10 shows a side view of the pod of figure 7.
[0038] Figure 11 shows a top plan view of a number of pods of figure 7 arranged side by side to form part of a building element system.
[0039] Figure 12 shows a perspective view of two of the pods of figure 7 arranged side by side.
[0040] Figure 13 shows a top plan view of a number of the pods of figure 7 arranged side by side and including reinforcement bars located in the rib-forming panels of the pods to form a building element system.
[0041] Figure 14 shows a top plan view of a number of the pods of figure 7 arranged side by side and including a reinforcement mesh located on top of the pods to form a building element system.
[0042] Figure 15 shows a sectional view of a foundation formed by pouring concrete on the pods of figure 1.
[0043] Figure 16 shows a top plan view of an exemplary embodiment of a building element in the form of a pod.
[0044] Figure 17 shows a bottom plan view of the pod of figure 16.
[0045] Figure 18 shows a detailed view of a central aperture of the pod of figure 16.
[0046] Figure 19 shows a three-dimensional view, from underneath, of the pod of figure 16.
DESCRIPTION OF THE EMBODIMENTS
[0047] In figures 1 to 5 of the drawings, reference numeral 10 generally indicates an exemplary embodiment of a building element. The building element is a pod, also known as a cavity or void former.
[0048] The pod 10 is a space filling element when pouring wet concrete to form a slab or foundation. Reference in this specification to a “foundation” includes reference to a “slab” and vice versa. The pod 10 is configured to not be removed once the concrete 2015207927 06 Feb 2017 6 has set. However, the inventor envisages that, in certain applications, the pod 10 could be removed once the concrete has set.
[0049] A number of pods are placed side by side in a pattern over an area where the concrete for the foundation is to be poured. The pod 10 has features and design elements for forming a foundation as described in the following paragraphs. Reference is made in the specification to “concrete”. However, it is to be appreciated that other settable materials suitable for forming foundations or slabs can also be used with the pods. Also, the term “concrete” is to be understood as including various forms of cementitious material that are suitable for construction. Apart from the traditional or conventional concrete, this material could include fibre-reinforced cementitious material, and other lightweight materials that are used in specialised fabrication.
[0050] The pod 10 comprises a body 12 having an upper surface 14, a bottom 16, and a sidewall 18 extending from the upper surface 14 to the bottom 16. The pod 10 is generally rectangular, more specifically square, in top plan view. The upper surface 14 and the bottom 16 are generally parallel to each other.
[0051] The sidewall 18 has four sides 20.1, 20.2, 20.3 and 20.4 depending from the periphery of the upper surface 14. The sides 20 can be between 800mm and 1500mm long, for example 1145mm long. The sidewall 18 can be between 200mm and 400mm high, for example 300mm high. The distance from the upper surface 14 to the bottom 16 of the body 12 can thus be between 200mm and 400mm, for example 300mm. The body 12 may be of any suitable material, including polystyrene, recycled cardboard, plastic, rubber, metal (such as folded or pressed sheet metal), saw dust or any other suitable material. The body 12 can also be fabricated in a number of different ways. For example, the body 12 can be moulded, milled, folded from sheet material, such as metal sheeting, and in other suitable ways.
[0052] The inventor envisages that the pod 10 can be infinitely variable in dimensions, to suit ground conditions and any other environments and applications in which the pod 10 is to be used.
[0053] A central aperture, cavity or opening, for example in the form of a hole 22 capable of receiving a pile, extends through the body 12 from the upper surface 14 to the bottom 16. The hole 22 is generally cylindrical. The hole 22 is at the centre of the 2015207927 06 Feb 2017 7 body 12. The hole 22 has a bore that is the same as, or slightly larger than, the width of a floor 28 of rib-forming channels 26 in the upper surface 14. The inventor envisages that the hole 22 need not always be used for receiving a pile and need not always extend through the body 12.
[0054] The rib-forming channels 26 extend across the upper surface 14 from side 20 to opposite side 20. The channels 26 intersect the holes 22 where the channels 26 cross. The channels 26 are orthogonal relative to each other. The channels 26 break the upper surface 14 of the body into four quadrants.
[0055] The rib-forming channels 26 have sides 27 and a floor 28. The sides 27 diverge from the floor 28 to the upper surface 14, as can be seen in figure 4. The ribforming channels 26 thus narrow from top to bottom. The width of the floor 28 of the ribforming channels 26 may be between 70mm and 130mm, for example 100mm. The distance between the sides 27 of the forming channels 26 at the upper surface 14 may be a multiple of between 1.2 and twice the width of the floor 28, for example a multiple of 1.6. The inventor envisages that the channels could be significantly larger when used for heavy industrial applications, such as airport runways, bridges, railway lines, heavy industry factories, and the like.
[0056] The floor 28 is spaced from the bottom 16 of the body 12. The spacing, or thickness of the body 12, between the bottom 16 of the body 12 and the floor 28 of the rib-forming channels 26 may be between 40mm to 100mm, for example 70mm. In the example wherein the sidewall is 300mm high and the spacing between the bottom 16 of the body 12 and the floor 28 of the rib-forming channels 26 is 70mm, the rib-forming channels 26 are 230mm deep measured from the upper surface 14.
[0057] The body 12 has an upright channel 30 formed in each side 20 of the pod 10. The upright channels 30 have a generally U-shaped profile. The upright channels 30 are open to the rib-forming channels 26. The upright channels 30 are continuous with the rib forming channels 30. Each rib-forming channel 26 terminates at an upright channel 30 at its respective ends. The upright channels 30 are depressions in the respective sidewalls 18. The upright channels 30 are located midway along each of the sides 20. 2015207927 06 Feb 2017 8 [0058] The bottom 16 of the body 12 is generally planar. Four cavities 34 are formed in the bottom 16 of the body 12. Strengthening ribs 36 extend across the cavities 34.
[0059] The pods 10 are arranged side by side with respective sides 20 of adjacent pods 10 in abutment with each other, in use. Figure 5 shows a pod system 48 comprising three pods 10 placed side by side. It will be appreciated that a number of pods 10 are placed side by side to cover the area between the perimeter footing or edge beams of the foundation.
[0060] The sides 20 of the pods 10 abut in a manner wherein the upright channel 30 of one pod 10 is in register with the upright channel 30 of an adjacent pod 10. The upright channels 30 of adjacent pods align to together form a foot cavity 40 extending from the joint upper surfaces 14 to the joint bottom 16 of adjacent pods.
[0061] In figures 6 to 12, reference numeral 100 generally indicates another exemplary embodiment of a building element in the form of a pod. With reference to the preceding drawings, like reference numerals refer to like parts, unless otherwise specified. The use of common reference numerals is intended to be for convenience only and should not be regarded as limiting. It is to be appreciated that characteristics, such as dimensions and materials of fabrication or manufacture that are described with reference to the pod 10, are equally applicable to the pod 100, where possible and appropriate.
[0062] The pod 100 has crosswise rib-forming channels 126 which extend between corners 102 of a body 112 of the pod 100. The rib-forming channels 126 are the same as, or similar to, the rib-forming channels 26 of the pod 10. Each rib-forming channel 126 extends from one corner 102 to an opposite corner 102. The rib-forming channels 126 intersect at the pile-receiving hole 22.
[0063] Upright channels 130 of the pod 100 are formed at the corners 102 of the body 112. The upright channels 130 are defined by a semi-circular wall or depression. The upright channels 130 have a quarter circular profile.
[0064] Figure 11 shows a pod system 108 comprising four pods 100 placed side by side. A cylindrical foot cavity 140 is formed where the four corners 102 of the pods 100 meet. Figure 12 shows half a foot cavity 140 where two corners 102 of adjacent pods 2015207927 06 Feb 2017 9 100 meet. The upright channels 130 are complementary to each other to form the foot cavity 140.
[0065] The pods 10, 100 are arranged in-situ with their bottoms 16 resting on the ground or surface on which the foundation or slab is to be formed. The floor 28 of the rib-forming channels 26, 126 are elevated above the ground or surface. When wet concrete is poured on the pods 10, elevated ribs or beams are formed in the rib-forming channels 26, 126. The formed ribs may be supported relative to the ground by piles received in the central holes 22 and the foot cavity 140. Alternatively, the wet concrete can be poured to be received in the central holes 22, in some cases, to form a foot or pile.
[0066] The formed ribs are also supported relative to the ground by feet or pillars formed in the foot cavities 40, 140. The foot cavities 40, 140 fill with concrete as the concrete is poured into the rib-forming channels 26. The feet formed in the foot cavities 40, 140 extend from the ground to the ribs formed in the rib forming channels 26, 126.
[0067] Piles or piers (not shown) may be driven into the ground to support the foundation. The piles may extend through the holes 22, in some cases. The piles may also extend through the foot cavities 40, 140. The concrete poured into the rib-forming channels 26, 126 flows into the holes 22 and/or the foot cavities 40, 140 to form a support collar around the pile.
[0068] Figure 13 shows a side-by-side arrangement of pods 100. A number of reinforcement bars 104 are placed in the rib-forming channels 126. The reinforcement bars 104 may be supported in the channels 126 at a height above the floor 28.
[0069] Figure 14 shows the arrangement of pods 100 including the reinforcement bars and further including a reinforcement mesh 106 placed on top of the pods. The reinforcement mesh 106 may be elevated above the upper surface 14 of the pods 100 by spacers such as chairs or saddles. The reinforcement mesh 106 strengthens the foundation formed by pouring wet concrete on the pods 100.
[0070] Figure 15 shows a foundation 200 formed by pouring concrete on the pods 10. One of the pods 10 is adjacent formwork to form a perimeter footing or edge beam 208 of the foundation 200. The concrete for the edge beam is poured at the same time 2015207927 06 Feb 2017 10 as pouring the concrete on top of the pods 10, 100 to form a foundation with an integral edge beam and suspended rib beams.
[0071] The foundation 200 comprises a generally flat slab portion 202 formed on the upper surfaces 14 of the pods 10. A number of criss-crossing reinforcement ribs 204 extend downwardly from the underside 203 of the slab portion 202. The reinforcement ribs 204 are is suspended above the ground surface 206 on which the foundation 200 is formed. The reinforcement ribs 204 are formed in the rib-forming channels 16 of the pods 10. The reinforcement ribs 204 are elevated above the ground surface 206 due to the spacing between the floor 28 of the rib-forming channels 26 and the bottom of the pods 10, 100.
[0072] A number of feet 212 extend downwardly from the underside 203 of the slab portion 202. The feet 212 extend past the lowest point of the reinforcement ribs 204 to be supported on the ground surface 206. The feet 212 are formed in the central apertures 22 and upright channels 30, 130 of the pods 10, 100.
[0073] The reinforcement ribs 204 are supported relative to the ground by the edge beams 208 and the concrete formed feet 212 in the central holes 22 and the foot cavities 40, 140. The concrete formed feet 212 may include piles extending upwardly from the ground and into the central holes 22 and/or the foot cavities 40, 140.
[0074] The edge beam 208 depends downwardly from the slab portion 202. The edge beam has a void or cavity 210 formed in the foot 212 of the edge beam 208 where the edge beam 208 is supported on the ground surface 206. The cavity 210 is formed by placing a void or cavity former 214 on the ground surface where the edge beam is to be formed before pouring the concrete. The cavity former 214 is generally elongate and triangular in cross-section. The cavity former extends to the same height as the floor of the rib forming channel 28.
[0075] The foundation 200 has a number of benefits over traditional waffle foundations. A traditional waffle foundation is formed by placing cavity formers spaced from each other. Crisscrossing internal beams or strip footings on the underside of the foundation slab thus extend all the way from the slab portion of the foundation down to the ground along the whole length of the strip footings. When the ground on which the 2015207927 06 Feb 2017 11 foundation is supported rises or falls, forces are transmitted through the strip footings to the slab and may lead to weakening or cracking of the slab.
[0076] The feet 212 of the foundation 200 accommodate the rising of ground around a foot 212 rather than transferring the upward load onto the reinforcement rib 204 and slab portion 202. The ground can rise to a height at which the reinforcement ribs 204 are suspended above the ground.
[0077] Although the rib-forming channels 26, 126 and upright channels 30, 130 are shown to meet each other at a right angles, there may be a curved transition between the upright channels 30, 130 and the rib forming channels 26, 126. In one embodiment, the upright channels 30, 130 and the rib forming channels 26, 126 may together form one continuous curved channel. This can optimise the strength of the junction between the feet formed in the channels 30, 130 and the reinforcement ribs 204.
[0078] The pods 10, 100 can have any number of uses. These uses can range from application in domestic housing right up to heavy duty applications such as airport runways, and the like, as described above. In addition, the uses can include use as a flotation device with the pods 10, 100 providing the necessary buoyancy where they are fabricated of a material such as polystyrene, or any other expanded plastics material.
For example, the pods 10, 100 could also be fabricated so that they define internal closed volumes. In that embodiment, the pods 10, 100 could define buoyancy chambers so that the slab formed with the points 10, 100 may float. In that application, structures could be formed or built on the resultant slab so that the structures can float.
[0079] The pods 10, 100, can also be used for forming slabs in multi-storey buildings. In that application, suitable support structures could be provided to support the feet 212.
[0080] In use, a number of the pods 10, 100 are positioned on a substrate, such as the ground to form a building element system such that the upright channels 30, 130 of at least one of the pods 10, 100 are in register with the upright channels 30, 130 so that an upright passage is formed. Also, the rib forming channels 26, 126 can be in register with each other to form elongate channels intersecting with the upright passages.
[0081] Reinforcing elements such as the reinforcement bars 104, or the like, are positioned in the elongate channels, as shown in figures 13 and 14. It is optional that 2015207927 06 Feb 2017 12 further reinforcing elements such as reinforcing bars, or the like, also positioned in the upright passages. Those could be tied to the reinforcing elements in the channels.
[0082] Piles can be driven through the central apertures. The reinforcing elements could be tied to the piles.
[0083] Concrete is then displaced or poured onto the building element system so that the upright passages and the elongate channels are filled with concrete with the concrete extending above the pods 10, 100. The concrete can then be finished in a conventional manner to form the foundation.
[0084] In figures 16 to 19, reference numeral 110 generally indicates an exemplary embodiment of a building element in the form of a pod. With reference to the preceding drawings, like reference numerals refer to like parts, unless otherwise specified. The use of common reference numerals is intended to be for convenience only and should not be regarded as limiting. It is to be appreciated that characteristics, such as dimensions and materials of fabrication or manufacture that are described with reference to the pod 10, 100 are equally applicable to the pod 110, where possible and appropriate.
[0085] The pod 110 has a body 111. The body 111 has a square opening 113. In this example, the opening is square in order to achieve a ground contact area that is larger than that which could be achieved with casting the concrete in a round passage or opening. Also, as can be seen in figure 18, lower edges 114 and corners 116 are chamfered so as to reduce stresses once the concrete is cast. It will be appreciated that the opening 113 can also be circular or rectangular. It can also be of varying dimensions depending on the particular application.
[0086] The pod 110 is shaped so that the cavities 34 are in fluid communication with each other when the pod 110 is placed on the ground. Also, a bottom surface 122 of each floor 28 has a curved transverse profile and is recessed from lower edges 114 of sidewalls 116. This allows fluidised soil or ground and liquid to pass between the cavities 34. This serves to inhibit the build-up of pressure within the cavities 34.
[0087] The pod 110 includes a ground bearing projection 124 that is coplanarwith ground bearing surfaces 118 of the sidewalls 116. The ground bearing projection can be centrally positioned, round, rectangular or square. Thus, when the pod 110 is placed on the ground, the sidewalls 116 and the ground bearing projection 124 support the pod 2015207927 06 Feb 2017 13 110. At the same time, passage of fluidised ground or soil and liquid is permitted between the cavities 34.
[0088] The sidewalls 116 have recesses 126 extending upwardly from the surfaces 118. These allow passage of fluidised ground or soil and liquid out of the cavities.
[0089] It will be appreciated that when a plurality of the pods 110 are placed in a configuration similar to that shown in figure 5, fluidised ground or soil and liquid is permitted to move about beneath the pods 110 thereby inhibiting the build-up of pressure and being able to drain. Thus, once the concrete slab has been formed, in the manner described above with reference to the pods 10, 100, such fluidised ground or soil and liquid can move about beneath the concrete slab without the build-up of excess pressure and possible damage to the slab.
[0090] As can be seen, the pod 110 does not include the channels 30, 130. However, given that the pod 110 can be of polystyrene or any other relatively soft material, it would be a relatively simple matter to cut out the channels in the pod 110. Alternatively, the pod 110 can be supplied with the channels 30, 130.
[0091] A property of polystyrene is that it can be compressed into a relatively thin condition in which it has properties similar to that of a high-density plastics material, such as polypropylene or HDPE. Thus, it is envisaged that the opening 112 can be replaced by a hole that is terminated at a lower end by a portion 120, indicated in dotted lines to show that it is optional, of the polystyrene or other expanded plastics material of the pod 110. Thus, when the concrete slab is formed on the pod 110, a weight of the concrete compresses the portion 120 into a layer or element of such high-density plastics material. As a result, the concrete can be protected from damp.
[0092] The pod 110 can be used in conjunction with a support pile, the position of which is indicated at 128. The pile can either go to ground or it can be driven further into the ground.
[0093] In a method of forming a slab or the foundation, the edge beam and the slab portion is continuously cast at the time of slab pour and become integrated with each other. This, together with the reinforcing in the rib channels provides a resultant floor system with significant strength. 2015207927 06 Feb 2017 14 [0094] Services can added into the beam (water, power, effluent and in-floor heating) with a flexible hose or conduit at the exit of the slab. The services can extend through the pods, which are frangible, and, when the concrete sets, those services are protected by the resultant slab. As a result, broken services under the house slab are minimised or inhibited. This can result in a large cost saving since repair of such issues can be costly, given the work and time component. This is useful for earthquake hit areas and highly reactive soil sites.
[0095] A resultant foot through the hole or central aperture, or the pile, suspends the edge or structural beam and floor slab above the ground. The foot can either go to ground or can be integrated with an in ground pile/pier of concrete, steel or timber.
[0096] This foot pile is the only element of the system that requires a plastic on ground separation membrane. As mentioned above, this can be provided by the material of the pod being compressed.
[0097] The floor being suspended does not require a plastic underlay as it is spaced up off the ground. The pod itself acts as a water resistant membrane as the pod will not transfer any moisture to the slab.
[0098] The cavities underneath the pod allow for land rise when the reactive soils expand as a result of heavy, heavy prolonged rain that can take the soils from a dry condition to wet. Heave is the common term used for this phenomenon. There is also the potential for the pod to self-sacrifice in the case of limited very highly reactive soils, so not to apply pressure on the underside of the beam and slab.
[0099] The strengthening ribs underneath the pods act as stiffeners to protect the pods when the concrete is poured.
[0100] The inventor envisages that the pods can be used for forming or fabrication of a slab that can float. This would be useful for areas prone to flooding, floating buildings and boat marina projects.
[0101] The inventor envisages that the pods can be fabricated from various materials. For example, the pods can be fabricated by pressing or folding steel sheet or any other malleable sheet, metal or otherwise. Other materials for fabrication of the pods might be recycled rubber. That would be suitable for heavy industry and base isolators. 2015207927 06 Feb 2017 15 [0102] The pods can be used for multi-level structures, particularly with the pressed or folded version.
[0103] It is to be understood that the terminology employed above is for the purpose of description and should not be regarded as limiting. The described embodiments are intended to be illustrative of the invention, without limiting the scope thereof. The invention is capable of being practised with various modifications and additions as will readily occur to those skilled in the art.
[0104] Variations, modifications and/or enhancements of one or more embodiments described herein might become apparent to those of ordinary skill in the art upon reading this application. Such variations are therefore to be considered as covered by the appended claims. Moreover, every combination of the various combinations described in this specification are, where practical, covered by the attached claims.
[0105] The use of words that indicate orientation or direction of travel is not to be considered limiting. Thus, words such as “front”, “back”, “rear”, “side”, “up”, “upright”, “down”, “upper”, “lower”, “top”, “bottom”, “forwards”, “backwards”, “towards”, “distal”, “proximal”, “in”, “out” and synonyms, antonyms and derivatives thereof have been selected for convenience only, unless the context indicates otherwise. The inventor envisages that various exemplary embodiments of the claimed subject matter can be supplied in any particular orientation and the claimed subject matter is intended to include such orientations.
[0106] When any number or range is described herein, unless clearly stated otherwise, that number or range is approximate. Recitation of ranges of values herein are merely intended to serve as a shorthand method of referring individually to each separate value falling within the range, unless otherwise indicated herein, and each separate value and each separate sub range defined by such separate values is incorporated into the specification as if it were individually recited herein. For example, if a range of 1 to 10 is described, that range includes all intermediate values, for example, 1.1,2.5, 3.335, 5, 6.179, 8.9999, etc., and includes all subrings there between, such as for example, 1 to 3.65, 2.8 to 8.14, 1.93 to 9, etc.
Claims (13)
1. A building element for forming a slab or a foundation with a settable material includes a body having an upper surface, a bottom, and sidewalls extending from the upper surface to the bottom; a hole defined in the body, the hole being an aperture which extends completely through the body from the upper surface to the bottom, wherein the bottom of the body around the aperture is configured to rest on the ground in operation; at least one rib-forming channel which extends across the upper surface and intersects with the hole; and cavities formed in the bottom of the body.
2. The building element as claimed in claim 1, in which the pod is shaped so that the cavities are in fluid communication with each other when the pod is placed on substantially level ground.
3. The building element as claimed in claim 1 or 2, in which the sidewalls have recesses extending upwardly from ground bearing surfaces of the sidewalls.
4. The building element as claimed in claim 3, in which the hole is centrally located in the body. .
5. The building element as claimed in claim 3 or 4, in which the body is generally rectangular in top plan view, with four sidewalls, each sidewall extending along a perimeter of the body.
6. The building element as claimed in any one of claims 3 to 5, which includes two rib-forming channels, each extending between opposite sidewalls and intersecting the hole.
7. The building element as claimed in any one of claims 3 to 6, in which the body includes a ground bearing projection that is substantially coplanarwith the ground bearing surfaces of the sidewalls, the hole being defined in the ground bearing projection.
8. A building element system comprising two or more of the building elements as claimed in any one of the preceding claims placed side by side so that at least one sidewall of one of the building elements is contiguous with at least one sidewall of an adjacent building element.
9. A foundation formed using the building elements of any one of the preceding claims, the foundation including: a generally flat slab portion formed on the upper surfaces of the bodies of the building elements; a number of reinforcement ribs on the underside of the slab portion which is suspended above the surface on which the foundation is formed, the reinforcement ribs being formed in the rib-forming channels; and a number of feet extending downwardly from the underside of the slab portion past the reinforcement ribs, the feet formed in the holes, and located on the ground; and wherein the ribs extend between each of the feet.
10. The foundation of claim 9, including an edge beam depending downwardly from the slab portion, the edge beam having a void or cavity formed in a foot of the edge beam where the edge beam is supported on the surface on which the foundation is formed.
11. A method of forming a foundation, the method including the steps of: positioning a number of building elements, as claimed in any one of claims 1 to 7, on a substrate to form a building element system as claimed in claim 8; displacing a settable material onto the building element system so that at least the rib-forming channels are at least partially filled with the settable material; and allowing the settable material to harden.
12. The method as claimed in claim 11, in which reinforcing elements are positioned in the rib-forming channels prior to displacing the settable material.
13. The method as claimed in claim 11 or 12, in which piles are driven through the hole defined in the building elements.
Priority Applications (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| AU2015207927A AU2015207927B2 (en) | 2014-11-20 | 2015-07-30 | A building element |
| NZ769232A NZ769232A (en) | 2014-11-20 | 2015-11-20 | A building element |
| PCT/AU2015/050733 WO2016077890A1 (en) | 2014-11-20 | 2015-11-20 | A building element |
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| AU2014265077 | 2014-11-20 | ||
| AU2014265077A AU2014265077B2 (en) | 2014-11-20 | 2014-11-20 | A Building Element |
| AU2015207927A AU2015207927B2 (en) | 2014-11-20 | 2015-07-30 | A building element |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| AU2014265077A Division AU2014265077B2 (en) | 2014-11-20 | 2014-11-20 | A Building Element |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| AU2015207927A1 AU2015207927A1 (en) | 2016-06-09 |
| AU2015207927B2 true AU2015207927B2 (en) | 2017-03-02 |
Family
ID=56012970
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| AU2015207927A Active AU2015207927B2 (en) | 2014-11-20 | 2015-07-30 | A building element |
Country Status (2)
| Country | Link |
|---|---|
| AU (1) | AU2015207927B2 (en) |
| WO (1) | WO2016077890A1 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2022073258A1 (en) * | 2020-10-09 | 2022-04-14 | 王修江 | Hollow formwork for use in construction |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN207363014U (en) * | 2017-10-11 | 2018-05-15 | 庞众 | Civilian assembling, assembled building |
| US12054905B2 (en) * | 2019-02-01 | 2024-08-06 | Jan Gerhardus Ehlers | Floating foundation |
| CN113585580A (en) * | 2021-06-28 | 2021-11-02 | 宁波工程学院 | Prefabricated cavity component for spatial structure floor and spatial structure floor |
| NL2037445B1 (en) * | 2024-04-12 | 2025-11-03 | Kingspan Unidek B V | Soil element, foundation formwork and methods for their production |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6550207B1 (en) * | 1999-03-03 | 2003-04-22 | Valerio Pontarolo | Modular element for crawl spaces and floor structures |
| WO2003044305A1 (en) * | 2001-11-22 | 2003-05-30 | Donatella Sinigaglia | Modular element to support building products, such as flooring, floors or similar |
| CN101487315A (en) * | 2008-01-17 | 2009-07-22 | 邱则有 | Cast-in-situ concrete hollow slab |
| US20110120036A1 (en) * | 2009-11-23 | 2011-05-26 | Superslab Tech Pty Ltd | Environmentally Degradable Void Former |
| USD717971S1 (en) * | 2013-07-17 | 2014-11-18 | Knew Foundation Systems Pty Ltd. | Foundation element |
-
2015
- 2015-07-30 AU AU2015207927A patent/AU2015207927B2/en active Active
- 2015-11-20 WO PCT/AU2015/050733 patent/WO2016077890A1/en not_active Ceased
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6550207B1 (en) * | 1999-03-03 | 2003-04-22 | Valerio Pontarolo | Modular element for crawl spaces and floor structures |
| WO2003044305A1 (en) * | 2001-11-22 | 2003-05-30 | Donatella Sinigaglia | Modular element to support building products, such as flooring, floors or similar |
| CN101487315A (en) * | 2008-01-17 | 2009-07-22 | 邱则有 | Cast-in-situ concrete hollow slab |
| US20110120036A1 (en) * | 2009-11-23 | 2011-05-26 | Superslab Tech Pty Ltd | Environmentally Degradable Void Former |
| USD717971S1 (en) * | 2013-07-17 | 2014-11-18 | Knew Foundation Systems Pty Ltd. | Foundation element |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2022073258A1 (en) * | 2020-10-09 | 2022-04-14 | 王修江 | Hollow formwork for use in construction |
Also Published As
| Publication number | Publication date |
|---|---|
| AU2015207927A1 (en) | 2016-06-09 |
| WO2016077890A1 (en) | 2016-05-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU2015207927B2 (en) | A building element | |
| US8128312B2 (en) | Support members and methods for the installation of brick patios, decks and paths | |
| AU2010217205B2 (en) | Building construction method and system | |
| JP6830260B2 (en) | Sheet pile wall buried structure | |
| KR20150135659A (en) | slope retaing wall using precast concrete and method therefore | |
| JP2015151684A (en) | Floating body-type artificial ground | |
| WO2008095247A1 (en) | Building method and apparatus for use therein | |
| US9915064B1 (en) | Method and apparatus for reducing propagation of cracks in concrete | |
| JP2018091047A (en) | Artificial ground and its construction method | |
| CN112627208B (en) | Assembled cofferdam suitable for rock foundation and construction method thereof | |
| AU2014265077B2 (en) | A Building Element | |
| AU2008201825A1 (en) | Method of constructing building slabs and pavements and storing water | |
| US9505468B2 (en) | Floating platform | |
| TWI631050B (en) | Movable equipment base plate structure | |
| AU2010201613A1 (en) | Methods of constructing buildings and components therefor | |
| AU2007237161B2 (en) | Building Method and Apparatus for Use Therein | |
| JP2015161065A (en) | Liquefaction prevention structure for housing ground | |
| JP5244576B2 (en) | Foundation structure | |
| KR20100033453A (en) | The soil retaining plate | |
| KR100583007B1 (en) | Prefab pier wharf | |
| CN207672931U (en) | A kind of terrace with width adjusting function | |
| AU2021257981B2 (en) | Apparatus and elements for use in building construction | |
| NL2029543B1 (en) | foundation assembly of a plurality of buoyant bodies | |
| JP5620850B2 (en) | Rainwater storage and infiltration facilities | |
| JP4528176B2 (en) | Lightweight embankment structure with buoyancy countermeasure structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FGA | Letters patent sealed or granted (standard patent) |