Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
CN120487182A - Underground high-pressure gas storage and integrated construction method - Google Patents
[go: Go Back, main page]

CN120487182A - Underground high-pressure gas storage and integrated construction method - Google Patents

Underground high-pressure gas storage and integrated construction method

Info

Publication number
CN120487182A
CN120487182A CN202510991150.1A CN202510991150A CN120487182A CN 120487182 A CN120487182 A CN 120487182A CN 202510991150 A CN202510991150 A CN 202510991150A CN 120487182 A CN120487182 A CN 120487182A
Authority
CN
China
Prior art keywords
chamber
steel
gas storage
pressure gas
underground high
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202510991150.1A
Other languages
Chinese (zh)
Inventor
胡成果
李晓昭
贺立新
贾邦国
张凯
胡李华
季雨坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Deep Earth Science And Engineering Yunlong Lake Laboratory
Original Assignee
Deep Earth Science And Engineering Yunlong Lake Laboratory
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Deep Earth Science And Engineering Yunlong Lake Laboratory filed Critical Deep Earth Science And Engineering Yunlong Lake Laboratory
Priority to CN202510991150.1A priority Critical patent/CN120487182A/en
Publication of CN120487182A publication Critical patent/CN120487182A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to an underground high-pressure gas storage warehouse and an integrated construction method. The gas storage comprises a chamber in the surrounding rock, a steel fiber concrete lining layer on the inner wall of the chamber and a steel plate sealing layer on the inner side of the lining layer. During construction, 1) arc-shaped steel plates are installed in sections to form sealing layers, rapid positioning and movement of the steel plates are achieved through a symmetrical track system preset in a chamber, 2) grouting flanges with grouting channels are installed at the ends of the steel plates, steel fiber concrete is pumped into gaps between the steel plates and the chamber, a lining layer is formed through casting from bottom to top, and 3) casting pressure is resisted by adopting an inner supporting frame. The invention uses the steel plate sealing layer to bear pressure and prevent seepage, the lining layer enhances structural resistance, and combines the precise plate feeding, flange grouting and internal support technology of the rail, thereby simplifying the formwork support and obviously improving the tightness, the compression resistance and the construction efficiency.

Description

Underground high-pressure gas storage and integrated construction method
Technical Field
The invention belongs to the technical field of underground high-pressure gas reservoirs, and particularly relates to an underground high-pressure gas reservoir and an integrated construction method.
Background
Compressed air energy storage power stations often use underground salt caverns, abandoned mines or newly built rock caverns as gas storage spaces, wherein the newly built rock caverns gas storages (Lined Rock Cavern, LRC) become research hotspots due to flexible site selection and stable structure.
At present, reinforced concrete is adopted as a mainstream lining structure of the gas storage of the rock cavern, but obvious defects are exposed in long-term engineering practice. On the one hand, the internal gas pressure is usually 4.5-10MPa or even higher when the high-pressure gas storage warehouse runs, and the generated circumferential tensile stress far exceeds the tensile strength of concrete, so that microscopic cracks are easily generated even if high-grade concrete is adopted. Although the steel bar can limit the width of the crack, the crack cannot be prevented from penetrating through the lining structure to form a gas leakage channel, so that the energy storage efficiency is reduced, the economy is influenced, and the safety accident of the leakage of high-pressure gas is more likely to be caused. On the other hand, the traditional reinforced concrete lining is constructed according to the procedures of firstly supporting the formwork and then pouring, and comprises the steps of building a complex inner-layer formwork supporting system, binding reinforcing steel bars, pouring concrete, removing the formwork in the later period and the like, so that a large amount of formwork materials and scaffolds are required to be put into, intensive manual operation is also relied on, the construction period is prolonged, and the engineering cost is obviously increased. These problems severely limit the safety and economy of LRC gas reservoirs.
Therefore, an underground high-pressure gas storage and an integrated construction method are provided.
Disclosure of Invention
The invention aims to provide an underground high-pressure gas storage and an integrated construction method to solve the problems.
In order to achieve the above object, the present invention provides the following solutions:
an underground high-pressure gas storage warehouse comprises a chamber, a lining layer, a sealing layer and a sealing layer, wherein the chamber is arranged in surrounding rock, the lining layer is circumferentially arranged on the inner side wall of the chamber, and the sealing layer is circumferentially arranged on the inner side wall of the lining layer.
In the underground high-pressure gas reservoir of the invention, the thickness of the lining layer is 30cm-50cm.
In the underground high-pressure gas reservoir of the invention, the thickness of the sealing layer is 10mm-15mm.
An integrated construction method of an underground high-pressure gas storage warehouse comprises the following steps of 1, excavating a chamber in surrounding rock, 2, dividing the chamber into a plurality of construction sections along the length direction of the chamber, 3, sequentially conveying a plurality of steel rings into the chamber until the length sum of the steel rings is equal to the length of one construction section, welding two adjacent steel rings to form a sealing layer, forming a pouring space between the steel rings and the inner wall of the chamber, 4, arranging a grout stopping flange at the end part of the steel ring close to an opening of the chamber, pouring steel fiber concrete into the pouring space through a pouring channel on the grout stopping flange to form a lining layer, 5, removing the grout stopping flange after the steel fiber concrete is hardened, and 6, repeating the steps 3 to 5 until construction is completed.
In the integrated construction method of the underground high-pressure gas storage, in the step 3, a plurality of tracks are arranged in the chamber, the tracks are arranged along the length direction of the chamber, two tracks are symmetrically arranged at the lower part of the chamber, the other two tracks are symmetrically arranged at the middle part of the chamber, and the steel ring moves along the tracks.
In the integrated construction method of the underground high-pressure gas storage, the track comprises a plurality of brackets, the brackets are fixedly arranged on the inner side wall of the chamber, the brackets are arranged at equal intervals along the length direction of the chamber, one ends of the brackets in the chamber are fixedly connected with round steel, and the round steel is arranged along the length direction of the chamber.
In the method for integrally constructing the underground high-pressure gas storage tank, in the step 4, when the steel fiber concrete is injected, the steel fiber concrete is injected into the injection space from the lower injection channel to the upper injection channel in sequence.
In the integrated construction method of the underground high-pressure gas storage, in the step 4, an inner supporting frame is arranged in the steel ring before the steel fiber concrete is injected, and is used for supporting the steel ring and bearing the pressure of pouring the steel fiber concrete.
In the step 4, the inner support frame comprises a fixed ring, a plurality of connecting rods are fixedly connected to the outer side of the fixed ring at equal intervals in the circumferential direction, a supporting disc is fixedly connected to one end of each connecting rod, which is far away from the fixed ring, the supporting disc is abutted to the inner side wall of the steel ring, the supporting disc is matched with the inner side wall of the steel ring, reinforcing ribs are fixedly connected between two adjacent connecting rods, and the reinforcing ribs are positioned in the middle of the connecting rods.
In the integral construction method of the underground high-pressure gas storage, in the step 1, after the chamber is excavated, anchor rods are installed on the inner wall of the chamber according to preset positions, reinforcing steel meshes are paved, and then concrete is sprayed, so that temporary support of the chamber is completed.
Compared with the prior art, the invention has the following advantages and technical effects:
The invention relates to an underground high-pressure gas storage warehouse and an integrated construction method. The gas storage comprises a chamber in the surrounding rock, a steel fiber concrete lining layer on the inner wall of the chamber and a steel plate sealing layer on the inner side of the lining layer. During construction, 1) arc-shaped steel plates are installed in sections to form sealing layers, rapid positioning and movement of the steel plates are achieved through a symmetrical track system preset in a chamber, 2) grouting flanges with grouting channels are installed at the ends of the steel plates, steel fiber concrete is pumped into gaps between the steel plates and the chamber, a lining layer is formed through casting from bottom to top, and 3) casting pressure is resisted by adopting an inner supporting frame. The invention uses the steel plate sealing layer to bear pressure and prevent seepage, the lining layer enhances structural resistance, and combines the precise plate feeding, flange grouting and internal support technology of the rail, thereby simplifying the formwork support and obviously improving the tightness, the compression resistance and the construction efficiency.
Drawings
For a clearer description of an embodiment of the invention or of the solutions of the prior art, the drawings that are needed in the embodiment will be briefly described, it being obvious that the drawings in the following description are only some embodiments of the invention, and that other drawings can be obtained according to these drawings without inventive effort for a person skilled in the art:
FIG. 1 is a schematic diagram of the overall structure of the present invention;
FIG. 2 is a front view of an underground high pressure reservoir of the present invention;
FIG. 3 is a schematic view of the track layout of the present invention;
FIG. 4 is a schematic view of the structure of the chamber during grouting according to the present invention;
FIG. 5 is a schematic view of the structure of the inner support frame according to the present invention;
The grouting material comprises 1, a sealing layer, 2, a lining layer, 3, an anchor rod, 4, surrounding rock, 5, round steel, 6, a bracket, 7, a grout stopping flange plate, 8, a pouring channel, 9, an inner supporting bracket, 10, a chamber, 901, a fixing ring, 902, a connecting rod, 903, a supporting plate and 904, and reinforcing ribs.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
In order that the above-recited objects, features and advantages of the present invention will become more readily apparent, a more particular description of the invention will be rendered by reference to the appended drawings and appended detailed description.
Referring to fig. 1 to 5, the invention discloses an underground high-pressure gas storage warehouse, which comprises a chamber 10, a lining layer 2, a sealing layer 1 and a gas storage layer, wherein the chamber 10 is arranged in a surrounding rock 4, the lining layer 2 is circumferentially arranged on the inner side wall of the chamber 10, and the sealing layer 1 is circumferentially arranged on the inner side wall of the lining layer 2.
In an alternative, the thickness of the lining layer 2 is 30cm-50cm.
In an alternative, the thickness of the sealing layer 1 is 10mm-15mm.
An integrated construction method of an underground high-pressure gas storage warehouse is used for building the underground high-pressure gas storage warehouse, and comprises the following steps:
step1, excavating a chamber 10 in surrounding rock 4;
step 2, dividing the chamber 10 into a plurality of construction sections along the length direction of the chamber 10;
And 3, sequentially feeding a plurality of steel rings into the chamber 10 until the sum of the lengths of the steel rings is equal to the length of one construction section, welding two adjacent steel rings to form a sealing layer 1, forming a filling space between the steel rings and the inner wall of the chamber 10, wherein the sealing layer 1 is made of a steel plate with grade not lower than Q345R and used for forming sealing protection on high-pressure gas, and simultaneously serving as an internal mold supporting lining layer for pouring, and the sealing layer 1 is welded into an annular structure to wrap the inner surface of the whole lining layer 2, so that multiple sealing barriers are formed while the structural strength and stability are ensured, and the leakage resistance of the gas storage is improved.
And 4, arranging a grout stopping flange plate 7 at the end part of a steel ring close to the opening of the chamber 10, injecting steel fiber concrete into a pouring space through a pouring channel 8 on the grout stopping flange plate 7 to form a lining layer 2, wherein the aperture of the pouring channel 8 is about 10cm, and the pouring channel is used as a concrete pouring channel, so that the lining layer 2 is conveniently poured in a layered manner from bottom to top, the lining layer 2 adopts high-grade steel fiber concrete, the cracking resistance and the bearing capacity can be obviously improved, the lining layer 2 adopts self-compacting concrete with the reference number not lower than C40, the adding amount of the steel fiber is not lower than 40kg/m < 3 >, the cracking resistance and the bearing capacity are enhanced, the steel fiber adopts special-shaped structures such as prismatic steel fiber, wave-shaped steel fiber, hook-shaped steel fiber, large-head steel fiber, double-pointed steel fiber and the like, and the interfacial bonding performance of fiber and mortar or concrete is improved.
And 5, removing the grout stopping flange 7 after hardening the steel fiber concrete, and pumping the prepared steel fiber concrete grout into the lining cavity from the lower pouring channel 8 layer by layer upwards through a concrete pump in sequence, wherein each layer of grouting is vibrated to ensure the full compaction of the concrete. When the steel fiber concrete reaches 70 percent of the design strength, the inner support frame 9 and the grout stopping flange 7 are removed, the construction of the section of lining layer 2 is completed, the surface of the poured lining layer 2 is subjected to roughening treatment to improve the bonding performance between the subsequent concrete sections,
And step 6, repeating the steps 3 to 5 until the construction is completed.
In an alternative scheme, in step 3, a plurality of tracks are arranged in the chamber 10, the tracks are arranged along the length direction of the chamber 10, two tracks are arranged at the lower part of the chamber 10 and symmetrically arranged, the other two tracks are arranged at the middle part of the chamber 10 and symmetrically arranged, and the steel ring moves along the tracks.
In an alternative scheme, the track comprises a plurality of brackets 6, the brackets 6 are fixedly arranged on the inner side wall of the chamber 10, the brackets 6 are arranged at equal intervals along the length direction of the chamber 10, one ends of the brackets 6 in the chamber 10 are fixedly connected with round steel 5, and the round steel 5 is arranged along the length direction of the chamber 10.
In an alternative, in step 4, the steel fiber concrete is poured into the pouring space in the order from the lower pouring channel 8 to the upper pouring channel 8 when the steel fiber concrete is poured.
In an alternative, in step 4, an inner support 9 is provided in the steel ring for supporting the steel ring and for withstanding the pressure of the poured steel fibre concrete, before the steel fibre concrete is poured.
The inner support frame 9 ensures that the steel plate ring does not deform or displace during the casting construction process, thereby ensuring the accuracy of the shape and the size of the lining layer.
In an alternative scheme, in step 4, the inner support frame 9 includes a fixing ring 901, a plurality of connecting rods 902 are fixedly connected at equal intervals in the circumferential direction of the outer side of the fixing ring 901, a support plate 903 is fixedly connected at one end of the connecting rod 902 away from the fixing ring 901, the support plate 903 is abutted on the inner side wall of the steel ring, the support plate 903 is matched with the inner side wall of the steel ring, a reinforcing rib 904 is fixedly connected between two adjacent connecting rods 902, and the reinforcing rib 904 is located in the middle of the connecting rod 902.
In an alternative scheme, in step 1, after the excavation of the chamber 10 is completed, anchor rods 3 are installed on the inner wall of the chamber 10 according to preset positions, reinforcing mesh is laid, and then concrete is sprayed, so that temporary support of the chamber 10 is completed.
The temporary support is reinforced by adopting sprayed concrete combined with the anchor rods 3 and the reinforcing mesh, so as to control the deformation of surrounding rock and provide temporary support during construction.
The concrete construction method comprises the following steps:
1. Excavating and temporary supporting, namely excavating a circular section chamber 10 with a horizontal axis on the surrounding rock 4 by adopting a drilling and blasting method, driving anchor rods 3 into preset positions of the inner wall of the chamber 10 to anchor the chamber in the surrounding rock 4, paving reinforcing steel meshes on the inner wall of the chamber 10, hanging and fixing the reinforcing steel meshes on the installed anchor rods 3, and spraying concrete on the inner wall of the chamber 10 paved with the reinforcing steel meshes to form a temporary supporting layer.
2. The bottom support frame is that two rows of brackets 6 are arranged at the bottom of the chamber 10, the two rows of brackets 6 are arranged in parallel and are positioned at the horizontal diameter position of the chamber 10 and are symmetrical to each other, the two rows of brackets 6 are arranged at equal intervals along the length direction of the chamber 10, and round steel 5 extending along the length direction of the chamber 10 is fixedly arranged at the top of one end of each row of brackets 6, which is close to each other.
3. The construction section division and steel ring prefabrication are that the whole chamber 10 is divided into a plurality of construction sections along the length direction of the chamber 10 according to the arrangement of the support 6 and the round steel 5, the length of each construction section is set to be M, a steel plate is prefabricated into a steel ring, the shape of the steel ring is required to be matched with the space formed by the surrounding of the two round steels 5 and surrounding rocks at the bottom, and the length of each steel ring along the axial direction of the chamber 10 is set to be N. According to the lengths M and N, the number of steel rings to be installed in each construction section is calculated to be M/N.
4. And (3) installing and welding the steel rings, namely hoisting a prefabricated steel ring in place, placing the steel ring between two round steels 5 at the bottom, axially pushing the steel ring to a preset position inside the chamber 10 by using a jack, butting the currently installed steel ring with the installed steel ring in place, firmly connecting the two butted steel rings together by adopting a double-sided welding process, carrying out nondestructive detection on a welded interface by using a CT metal flaw detector, ensuring that the weld joint is defect-free, meeting the quality requirement, and repeating the steps of hoisting, pushing, butting, welding and flaw detection until all the steel rings in the current construction section are installed and welded, thereby finally forming a complete sealing layer 1.
5. And (3) end sealing die and inner support installation, namely installing a grout stopping flange 7 at the end of a steel ring which is finally installed near the opening end of the chamber 10, forming a template layer space for pouring concrete among the grout stopping flange 7, the inner wall of the sealing layer 1 and the surrounding rock/temporary support layer of the outer chamber 10, and installing an inner support frame 9 in the installed sealing layer 1 to provide inner support for subsequent concrete pouring.
6. And (3) pouring and maintaining lining concrete, namely pouring steel fiber concrete into a template layer space between the sealing layer 1 and the surrounding rock 4/temporary support layer through a pouring channel 8 reserved on the grout stopping flange plate 7, and in the pouring process, pouring the steel fiber concrete into the upper pouring channel 8 step by step according to the sequence from the lower pouring channel 8, and maintaining the steel fiber concrete until the steel fiber concrete reaches the structural strength required by design after the steel fiber concrete is poured.
7. And (3) removing the inner support frame 9 installed before the concrete reaches the design strength, removing the grout stop flange 7, solidifying steel fiber concrete to form the lining layer 2, and roughening the exposed end surface of the solidified lining layer 2 to provide a good bonding surface for combining new and old concrete in the next construction section.
8. Repeating the steps 2 to 7, and performing construction of the next construction section, and repeating the steps until all the construction sections are completed and the construction of the whole underground high-pressure gas storage warehouse is completed.
In the description of the present invention, it should be understood that the terms "longitudinal," "transverse," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like indicate or are based on the orientation or positional relationship shown in the drawings, merely to facilitate description of the present invention, and do not indicate or imply that the devices or elements referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present invention.
The above embodiments are only illustrative of the preferred embodiments of the present invention and are not intended to limit the scope of the present invention, and various modifications and improvements made by those skilled in the art to the technical solutions of the present invention should fall within the protection scope defined by the claims of the present invention without departing from the design spirit of the present invention.

Claims (10)

1.一种地下高压储气库一体化施工方法,其特征在于,步骤如下:1. A method for the integrated construction of an underground high-pressure gas storage, characterized by the following steps: 步骤1、在围岩(4)内开挖硐室(10);Step 1: excavating a chamber (10) in the surrounding rock (4); 步骤2、沿硐室(10)的长度方向将硐室(10)分为多个施工段;Step 2: Divide the chamber (10) into a plurality of construction sections along the length direction of the chamber (10); 步骤3、将多个钢环顺序送入硐室(10)内,直至多个钢环的长度之和与一个施工段的长度相等,焊接相邻的两个钢环以形成密封层(1),钢环与硐室(10)的内壁之间形成灌注空间;Step 3, sequentially feeding a plurality of steel rings into the chamber (10) until the sum of the lengths of the plurality of steel rings is equal to the length of one construction section, welding two adjacent steel rings to form a sealing layer (1), and forming a pouring space between the steel rings and the inner wall of the chamber (10); 步骤4、在靠近硐室(10)开口的钢环端部设置止浆法兰盘(7),通过止浆法兰盘(7)上的灌注通道(8)向灌注空间内注入钢纤维混凝土以形成衬砌层(2);Step 4: a grouting flange (7) is provided at the end of the steel ring near the opening of the chamber (10), and steel fiber concrete is injected into the injection space through the injection channel (8) on the grouting flange (7) to form a lining layer (2); 步骤5、钢纤维混凝土硬化后拆除止浆法兰盘(7);Step 5: After the steel fiber concrete hardens, the stop flange (7) is removed; 步骤6、重复步骤3至步骤5直至施工完成。Step 6. Repeat steps 3 to 5 until the construction is completed. 2.根据权利要求1所述的一种地下高压储气库一体化施工方法,其特征在于,在步骤3中,硐室(10)内设置有多条轨道,轨道沿硐室(10)的长度方向设置,其中两条轨道设置在硐室(10)的下部且对称设置,另两条轨道设置在硐室(10)的中部且对称设置,钢环沿着轨道移动。2. The method for constructing an integrated underground high-pressure gas storage facility according to claim 1, characterized in that, in step 3, a plurality of tracks are provided in the chamber (10), and the tracks are provided along the length direction of the chamber (10), wherein two tracks are provided at the lower part of the chamber (10) and are symmetrically provided, and the other two tracks are provided in the middle part of the chamber (10) and are symmetrically provided, and the steel ring moves along the tracks. 3.根据权利要求2所述的一种地下高压储气库一体化施工方法,其特征在于,轨道包括多个支架(6),支架(6)固定安装在硐室(10)的内侧壁上,多个支架(6)沿硐室(10)的长度方向等间隔设置,多个支架(6)位于硐室(10)内的一端均与圆钢(5)固接,圆钢(5)沿硐室(10)的长度方向设置。3. An integrated construction method for an underground high-pressure gas storage according to claim 2, characterized in that the track includes a plurality of brackets (6), the brackets (6) are fixedly mounted on the inner wall of the chamber (10), the plurality of brackets (6) are arranged at equal intervals along the length direction of the chamber (10), one end of the plurality of brackets (6) located in the chamber (10) is fixedly connected to the round steel (5), and the round steel (5) is arranged along the length direction of the chamber (10). 4.根据权利要求1所述的一种地下高压储气库一体化施工方法,其特征在于,在步骤4中,注入钢纤维混凝土时,按照由下部灌注通道(8)至上部灌注通道(8)的顺序将钢纤维混凝土注入灌注空间。4. The method for constructing an integrated underground high-pressure gas storage facility according to claim 1, wherein in step 4, when injecting the steel fiber concrete, the steel fiber concrete is injected into the injection space in the order from the lower injection channel (8) to the upper injection channel (8). 5.根据权利要求1所述的一种地下高压储气库一体化施工方法,其特征在于,在步骤4中,注入钢纤维混凝土之前,在钢环内设置内支撑架(9),用于支撑钢环以及承受浇筑钢纤维混凝土的压力。5. The method for constructing an integrated underground high-pressure gas storage facility according to claim 1, characterized in that, in step 4, before injecting the steel fiber concrete, an inner support frame (9) is provided in the steel ring to support the steel ring and withstand the pressure of pouring the steel fiber concrete. 6.根据权利要求5所述的一种地下高压储气库一体化施工方法,其特征在于,在步骤4中,内支撑架(9)包括固定环(901),固定环(901)的外侧周向等间隔固接有多个连接杆(902),连接杆(902)远离固定环(901)的一段固接有支撑盘(903),支撑盘(903)抵接在钢环的内侧壁上,支撑盘(903)与钢环的内侧壁相适配,相邻的两连接杆(902)之间固接有加强筋(904),加强筋(904)位于连接杆(902)的中部。6. An integrated construction method for an underground high-pressure gas storage according to claim 5, characterized in that, in step 4, the inner support frame (9) includes a fixed ring (901), a plurality of connecting rods (902) are fixedly connected to the outer side of the fixed ring (901) at equal intervals in the circumferential direction, a section of the connecting rod (902) away from the fixed ring (901) is fixedly connected to a support plate (903), the support plate (903) abuts against the inner side wall of the steel ring, the support plate (903) is adapted to the inner side wall of the steel ring, a reinforcing rib (904) is fixed between two adjacent connecting rods (902), and the reinforcing rib (904) is located in the middle of the connecting rod (902). 7.根据权利要求1所述的一种地下高压储气库一体化施工方法,其特征在于,在步骤1中,硐室(10)挖掘完成后,在硐室(10)的内壁上按照预设位置安装锚杆(3)并铺设钢筋网片,然后喷射混凝土,完成对硐室(10)的临时支护。7. An integrated construction method for an underground high-pressure gas storage according to claim 1, characterized in that, in step 1, after the excavation of the chamber (10) is completed, anchor rods (3) are installed on the inner wall of the chamber (10) according to preset positions and steel mesh is laid, and then concrete is sprayed to complete temporary support of the chamber (10). 8.一种地下高压储气库,根据权利要求1-7任一项所述的地下高压储气库一体化施工方法建造而成,其特征在于,包括:8. An underground high-pressure gas storage constructed according to the integrated construction method for an underground high-pressure gas storage according to any one of claims 1 to 7, characterized in that it comprises: 硐室(10),开设在围岩(4)内;A chamber (10) is provided in the surrounding rock (4); 衬砌层(2),周向设置在硐室(10)的内侧壁上;A lining layer (2) is circumferentially arranged on the inner wall of the chamber (10); 密封层(1),周向设置在衬砌层(2)的内侧壁上。The sealing layer (1) is circumferentially arranged on the inner side wall of the lining layer (2). 9.根据权利要求8所述的一种地下高压储气库,其特征在于,衬砌层(2)的厚度为30cm-50cm。9. An underground high-pressure gas storage according to claim 8, characterized in that the thickness of the lining layer (2) is 30 cm-50 cm. 10.根据权利要求8所述的一种地下高压储气库,其特征在于,密封层(1)的厚度为10mm-15mm。10. An underground high-pressure gas storage according to claim 8, characterized in that the thickness of the sealing layer (1) is 10 mm-15 mm.
CN202510991150.1A 2025-07-18 2025-07-18 Underground high-pressure gas storage and integrated construction method Pending CN120487182A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202510991150.1A CN120487182A (en) 2025-07-18 2025-07-18 Underground high-pressure gas storage and integrated construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202510991150.1A CN120487182A (en) 2025-07-18 2025-07-18 Underground high-pressure gas storage and integrated construction method

Publications (1)

Publication Number Publication Date
CN120487182A true CN120487182A (en) 2025-08-15

Family

ID=96675752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202510991150.1A Pending CN120487182A (en) 2025-07-18 2025-07-18 Underground high-pressure gas storage and integrated construction method

Country Status (1)

Country Link
CN (1) CN120487182A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115875079A (en) * 2022-11-16 2023-03-31 中国大唐集团科学技术研究总院有限公司 Compressed air energy storage artificial underground gas storage
US20230258085A1 (en) * 2022-02-14 2023-08-17 Shandong Jianzu University Composite support system based on steel-concrete support and shotcrete arch and construction process thereof
CN117090600A (en) * 2023-07-12 2023-11-21 长江勘测规划设计研究有限责任公司 Underground ultra-high pressure gas storage chamber lining and sealing structure and construction method
CN118929106A (en) * 2024-08-02 2024-11-12 中国葛洲坝集团勘测设计有限公司 Assembled metal steel plate transportation system and method
CN119825433A (en) * 2025-03-10 2025-04-15 中国矿业大学深圳研究院 Underground gas storage chamber and construction method thereof
CN119878297A (en) * 2024-12-27 2025-04-25 华电科工股份有限公司 Compressed air underground artificial chamber gas storage and construction method
CN120251888A (en) * 2025-04-14 2025-07-04 深地科学与工程云龙湖实验室 A prestressed lining structure and construction method for underground gas storage

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20230258085A1 (en) * 2022-02-14 2023-08-17 Shandong Jianzu University Composite support system based on steel-concrete support and shotcrete arch and construction process thereof
CN115875079A (en) * 2022-11-16 2023-03-31 中国大唐集团科学技术研究总院有限公司 Compressed air energy storage artificial underground gas storage
CN117090600A (en) * 2023-07-12 2023-11-21 长江勘测规划设计研究有限责任公司 Underground ultra-high pressure gas storage chamber lining and sealing structure and construction method
CN118929106A (en) * 2024-08-02 2024-11-12 中国葛洲坝集团勘测设计有限公司 Assembled metal steel plate transportation system and method
CN119878297A (en) * 2024-12-27 2025-04-25 华电科工股份有限公司 Compressed air underground artificial chamber gas storage and construction method
CN119825433A (en) * 2025-03-10 2025-04-15 中国矿业大学深圳研究院 Underground gas storage chamber and construction method thereof
CN120251888A (en) * 2025-04-14 2025-07-04 深地科学与工程云龙湖实验室 A prestressed lining structure and construction method for underground gas storage

Similar Documents

Publication Publication Date Title
CN110924961B (en) Construction method for starting shield tunneling machine to pass through existing station
CN112324475A (en) Method for reinforcing shield tunnel lining structure
CN104695968B (en) Method for in-tunnel starting of shield tunneling machine
CN103670446B (en) Circular diversion tunnel 2/3 circle concrete-liner construction method
CN113294166A (en) Large-section rectangular jacking pipe oblique starting method
CN117927270B (en) Mountain tunnel pre-assembled lining structure and construction method
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN210152316U (en) A prefabricated reinforcement device for reinforced concrete beams
CN113073982B (en) Mechanical dark excavation and jacking system and construction method for large-section rectangular segment segments of subway stations
CN111173004B (en) A construction method for a special-shaped prefabricated pile zipper support structure
CN107034916A (en) Glass fibre composite reinforced plastics prefabricated assembly structural
CN214836409U (en) Tunnel drainage type corrugated steel preliminary bracing structure
CN120487182A (en) Underground high-pressure gas storage and integrated construction method
CN120251888A (en) A prestressed lining structure and construction method for underground gas storage
CN110107319A (en) A method of utilizing embedding arch shotcrete composite structure Strengthening Tunnel lining cutting
CN114876526A (en) A kind of temporary side wall protection construction method of double side wall guide pit method
CN105133646A (en) Underground steel and concrete structure pipeline and manufacturing method thereof
CN113279787A (en) Construction method for building pipe curtain supporting structure of ultra-shallow buried large-section underground excavation subway station
CN117627053A (en) Construction method of jointly constructed structural system of subway open-cut section and underpass tunnel
CN114960675B (en) A combined support system for pipe gallery foundation pit support
CN116427966A (en) A safe and rapid construction structure and construction method of a broken rock mass tunnel
CN116025008A (en) Large-span underground space combined pipe-jacking pipe segment structure connecting system and construction method
CN215949502U (en) Be used for reinforced (rfd) cover arch structure of highway tunnel lining
CN112942259B (en) Assembled flexible panel structure for panel rock-fill dam and construction method
CN121250955A (en) Construction conversion method for cover excavation forward construction and reverse construction structure of hub station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20250815