JP2513376B2 - How to build a building - Google Patents
How to build a buildingInfo
- Publication number
- JP2513376B2 JP2513376B2 JP18641191A JP18641191A JP2513376B2 JP 2513376 B2 JP2513376 B2 JP 2513376B2 JP 18641191 A JP18641191 A JP 18641191A JP 18641191 A JP18641191 A JP 18641191A JP 2513376 B2 JP2513376 B2 JP 2513376B2
- Authority
- JP
- Japan
- Prior art keywords
- building
- crane
- core
- construction
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は原子炉格納容器やター
ビンの設置と躯体の構築に先立って原子炉建屋やタービ
ン建屋等の架構を構築する、建屋の構築方法に関するも
のである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a building construction method for constructing a structure such as a reactor building or a turbine building prior to installation of a reactor containment vessel or turbine and construction of a frame.
【0002】[0002]
【従来技術及び発明が解決しようとする課題】原子炉建
屋やタービン建屋等では、建屋とその内部に設置される
格納容器等の構築は従来、建屋の周辺に複数箇所設置さ
れる小型や大型のタワークレーンを利用し、揚重能力に
応じて小型のタワークレーンが建屋用建設資材等を、大
型のタワークレーンが格納容器のユニット等をそれぞれ
受け持ちながら、基礎スラブ側から屋根側へ順次、積み
上げる要領で行われるため、建屋内の作業環境は屋根の
架設まで常に天候に支配される状況に置かれている。2. Description of the Related Art In a reactor building, a turbine building, etc., a building and a containment vessel or the like installed inside the building have conventionally been constructed in a small or large size in a plurality of places around the building. Using a tower crane, a small tower crane is responsible for building materials and other materials for building, and a large tower crane is responsible for the storage container units, etc., while sequentially stacking from the foundation slab side to the roof side. The working environment inside the building is always controlled by the weather until the roof is erected.
【0003】加えて、運転操作床上の機器や圧力容器内
の機器の搬入及びその据付けは屋根の下に架設される天
井走行クレーンを利用して行われるが、従来の施工要領
では、建屋の構築が完了するまで天井走行クレーンを設
置することができないため、作業の遅延を招いており、
天候の影響とともに工期の長期化は避けられないのが実
情である。In addition, the loading and installation of the equipment on the operation floor and the equipment in the pressure vessel are carried out by using an overhead traveling crane erected under the roof, but in the conventional construction procedure, a building is constructed. Since the overhead traveling crane cannot be installed until the completion of
In reality, it is inevitable that the construction period will be prolonged with the influence of the weather.
【0004】また分担する部材や資材,あるいは格納容
器や圧力容器等に応じて規模が異なる多種のタワークレ
ーンや据付治具を必要とし、これらは長期に亘って使用
されるため工費が増大する傾向にある。Further, various tower cranes and installation jigs of different scales are required depending on the members and materials to be shared, the containment vessel, the pressure vessel, etc., and these tend to be used for a long period of time, so the construction cost tends to increase. It is in.
【0005】この発明はこうした原子炉建屋が施工時に
抱える問題を踏まえてなされたもので、工期の短縮化と
工費の節減,及び施工環境の改善を図る構築方法を新た
に提案しようとするものである。The present invention was made in view of the problems that such a reactor building has during construction. It is intended to newly propose a construction method for shortening the construction period, reducing the construction cost, and improving the construction environment. is there.
【0006】[0006]
【課題を解決するための手段】本発明では建屋の架構を
躯体工事等に先行して組み立て、屋根架構を架設するこ
とにより建屋内の天候の影響を回避し、また建屋の架構
の構築と同時に天井走行クレーンを設置することにより
その稼働時期を早め、建屋内での作業の進捗を図り、工
期の短縮化を実現する。[Means for Solving the Problems] According to the present invention, the structure of the building is assembled prior to the frame work and the roof structure is installed to avoid the influence of the weather inside the building, and at the same time the building structure is constructed. By installing an overhead traveling crane, the operating time will be accelerated, the work in the building will be progressed, and the construction period will be shortened.
【0007】また天井走行クレーンの早期の設置によっ
て稼働率を高めることにより必要クレーン数を削減し、
工費の節減を図る。Also, the number of required cranes is reduced by increasing the operating rate by installing the overhead traveling crane early.
Aim to reduce construction costs.
【0008】建屋の架構は、基礎スラブ上の四隅位置に
構築される中空断面のコア柱と、その1方向に対向する
コア柱間に架設される梁とから構成され、梁上に、これ
に平行にクレーンガーダーが敷設され、その上に天井走
行クレーンが設置される。コア柱は軸方向に複数個に分
割され、ユニット化されたコア柱ユニットを積み上げな
がら互いに接続することにより構築される。The structure of the building is composed of core pillars of hollow cross section constructed at four corners on the foundation slab and beams installed between the core pillars facing each other in one direction. A crane girder is laid in parallel, and an overhead traveling crane is installed on it. The core pillar is divided into a plurality of core pillars in the axial direction, and the core pillar units are connected to each other while being stacked.
【0009】クレーンガーダーは梁の対向する側に、梁
の長さ方向に間隔をおいて設置される支持材に支持され
て敷設され、天井走行クレーンはクレーンガーダー間に
架設される、並列する走行レール上に載置される。屋根
架構は天井走行クレーンの設置後に、梁上に架設され
る。The crane girders are laid on opposite sides of the beams, supported by support members installed at intervals in the length direction of the beams, and the overhead traveling cranes are installed between the crane girders and run in parallel. It is placed on the rail. The roof frame is erected on the beams after the overhead traveling crane is installed.
【0010】天井走行クレーンは建屋内に設置される機
器や,格納容器等のユニットの搬入の他、建屋の、架構
回りの躯体の構築に先行して設置されることにより建屋
用建設資材の吊り込み等に使用され、従来の建屋の構築
とその内部への部材の搬入に使用されていた大型タワー
クレーンや圧力容器据付け用治具,及び小型タワークレ
ーンを不要化し、また遮蔽壁の鉄筋ユニットや格納容器
の組み立て、ユニットの大型化等を可能にし、躯体工事
の工程が短縮される。[0010] The overhead traveling crane is used for suspending construction materials for a building by installing equipment installed in the building and a unit such as a storage container, as well as being installed prior to the construction of a frame around the frame of the building. It eliminates the need for large tower cranes, pressure vessel installation jigs, and small tower cranes that have been used for building buildings and loading members into the interior of conventional buildings. It enables the assembling of the storage container and the enlargement of the unit, which shortens the process of the skeleton work.
【0011】天井走行クレーンの設置後に、屋根架構が
建屋の躯体の構築に先立って架設されることにより建屋
内の作業環境は全天候状態となり、躯体の構築や部材の
搬入が天候に支配されることなく遂行され、天井走行ク
レーンの早期稼働とともに建屋内の作業が効率的に進行
することになる。After the installation of the overhead traveling crane, the roof frame is erected prior to the construction of the building frame, so that the working environment in the building is in an all-weather condition, and the construction of the frame and the loading of members are controlled by the weather. The work inside the building will proceed efficiently with the early operation of the overhead traveling crane.
【0012】[0012]
【実施例】以下本発明を一実施例を示す図面に基づいて
説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the drawings showing an embodiment.
【0013】この発明は図1に示すように建屋B全体の
躯体の構築や,格納容器等の設置に先立って柱・梁の架
構のみを構築し、同時にこの架構上に天井走行クレーン
10と屋根架構Rを架設する方法であり、屋根架構Rによ
って天候の影響を回避しながら、天井走行クレーン10を
早期に稼働させることによって遮蔽壁等の躯体の構築
と、資材や機器及び格納容器のユニット等の搬入作業の
円滑化を図るものである。実施例では原子炉建屋の構築
例を示しているが、建屋Bはタービン建屋の他、各種の
建屋を含む。As shown in FIG. 1, the present invention constructs only the frame of columns and beams prior to the construction of the skeleton of the entire building B and the installation of the storage container, and at the same time, the overhead traveling crane is mounted on this frame.
10 is a method of constructing the roof frame R and the roof frame R to avoid the influence of the weather, and by operating the overhead traveling crane 10 at an early stage, constructing a frame such as a shielding wall, materials, equipment, and a storage container. It is intended to facilitate the work of carrying in the units and the like. Although the example shows the construction of the reactor building, the building B includes various buildings in addition to the turbine building.
【0014】図2〜図11により施工手順を説明する。The construction procedure will be described with reference to FIGS.
【0015】まず図2に示すように建屋Bの岩盤上に均
しコンクリートMを構築しておく。First, as shown in FIG. 2, a leveled concrete M is constructed on the bedrock of the building B.
【0016】この均しコンクリートM上に基礎スラブF
が構築されるが、それに先立って均しコンクリートMの
四隅位置にコア柱脚部ユニットc1を設置する。On this leveled concrete M, a foundation slab F
The core column base unit c 1 is installed at the four corners of the leveling concrete M prior to that.
【0017】次に図3に示すようにコア柱脚部ユニット
c1上に中空断面のコア柱C,Cを構築する一方、作業が
錯綜しないよう安全性を考慮しながら基礎スラブFの工
事を施工する。コア柱Cは図示するようにコア柱脚部ユ
ニットc1を含め、軸方向に複数個に分割されたコア柱ユ
ニットcを積み上げながら互いに接続することにより構
築される。Next, as shown in FIG. 3, the core column base unit
While constructing the core pillars C with a hollow cross section on c 1 , construct the foundation slab F while considering safety so that the work will not be complicated. As shown in the figure, the core pillar C is constructed by including the core pillar leg unit c 1 and connecting the core pillar units c that are axially divided into a plurality of core pillars while stacking them.
【0018】コア柱ユニットcは図4に示すように並列
する鋼板間にコンクリートを充填した鋼板コンクリート
造や鉄筋コンクリート造の他、トラス構造の鉄骨造等に
より構成され、上下に隣接するコア柱ユニットc,cの
接続は構造に応じてボルト,または溶接により、もしく
は主筋の継手により、あるいはその組み合わせにより行
われる。As shown in FIG. 4, the core pillar unit c is made of steel plate concrete or reinforced concrete, in which concrete is filled between parallel steel plates, or a steel structure of truss structure, and the vertically adjacent core pillar units c. , C are connected by bolts or welding depending on the structure, by joints of main bars, or by a combination thereof.
【0019】均しコンクリートM上に設置されるコア柱
脚部ユニットc1には図4,図5に示すように基礎スラブ
F中に埋設される上端及び下端の主筋1が貫通して配筋
され、この主筋1を配筋した状態で、図6に示すように
コア柱脚部ユニットc1の鋼板間と内部にコンクリートが
打設される。コア柱脚部ユニットc1の鋼板間や内周と外
周には図5に示すようにスタッドボルト3が突設されて
いる。As shown in FIGS. 4 and 5, the core column base unit c 1 installed on the leveled concrete M is penetrated by the upper and lower main bars 1 embedded in the foundation slab F and arranged. Then, with the main bars 1 arranged, concrete is placed between the steel plates and inside the core column base unit c 1 as shown in FIG. As shown in FIG. 5, stud bolts 3 are projectingly provided between the steel plates of the core column base unit c 1 and between the inner and outer peripheries.
【0020】図6は最下部のコア柱脚部ユニットc1と基
礎スラブFとの接続の様子を示しているが、ここに示す
ようにコア柱脚部ユニットc1は基礎スラブF中に、双方
のスラブ筋1,2を機械式継手等により接続し、コンク
リート4を打設することにより一体化される。FIG. 6 shows the connection between the lowermost core column base unit c 1 and the foundation slab F. As shown here, the core column base unit c 1 is located in the foundation slab F. Both slab muscles 1 and 2 are connected by a mechanical joint or the like, and concrete 4 is poured to integrate them.
【0021】コア柱Cの構築後、図7に示すように1方
向に対向するコア柱C,C間に梁Gを架設してコア柱
C,Cに接合し、梁G,Gを対向させる。このとき、コ
ア柱Cと梁Gの天端は連続する。各梁Gはコア柱ユニッ
トcと同様にユニット化され、鋼板コンクリート造等か
らなる、並列する梁ユニットG1,G1から構成されてい
る。After the core pillar C is constructed, as shown in FIG. 7, a beam G is installed between the core pillars C and C facing each other in one direction and joined to the core pillars C and C so that the beams G and G face each other. . At this time, the top ends of the core pillar C and the beam G are continuous. Each beam G is unitized similarly to the core pillar unit c, and is composed of parallel beam units G 1 and G 1 made of steel plate concrete or the like.
【0022】引き続き、この梁G,Gの対向する側の側
面、具体的には対向する梁ユニットG1,G1の側面に図8
に示すようにクレーンガーダー6を支持する支持材5
を、柱Cと梁ユニットG1に連続して梁Gの長さ方向に適
当な間隔をおいて突設する。この支持材5は梁Gの架設
前に予め梁ユニットG1と柱Cに突設しておく場合もあ
る。Next, the side surfaces of the beams G, G facing each other, specifically, the side surfaces of the beam units G 1 , G 1 facing each other are shown in FIG.
Supporting material 5 for supporting the crane girder 6 as shown in FIG.
Are provided so as to be continuous with the pillar C and the beam unit G 1 and project at appropriate intervals in the length direction of the beam G. The support member 5 may be preliminarily provided on the beam unit G 1 and the pillar C before the beam G is installed.
【0023】次に図9に示すように各梁G,Gの支持材
5,5上にクレーンガーダー6,6を敷設するととも
に、屋根架構Rを支持する支柱7,7、及び隣接する支
柱7,7を連結する壁板8をクレーンガーダー6,6の
両外側の柱Cと梁Gの天端上に立設する。Next, as shown in FIG. 9, crane girders 6, 6 are laid on the supporting members 5, 5 of the respective beams G, G, and the supporting columns 7, 7 for supporting the roof frame R and the adjacent supporting columns 7 are provided. , 7 are connected to the crane girders 6 and 6 so as to stand on the tops of the pillars C and the beams G on both outer sides.
【0024】更に図10に示すように対向するクレーンガ
ーダー6,6間にその上を走行する、並列する走行レー
ル9,9を架設し、この走行レール9,9上にその上を
走行する天井走行クレーン10を設置する。Further, as shown in FIG. 10, parallel traveling rails 9 and 9 traveling above the crane girders 6 and 6 are installed, and a ceiling traveling above the traveling rails 9 and 9 is installed. Install traveling crane 10.
【0025】クレーンガーダー6は場合に応じ、図1,
図8〜図11に示すように各梁Gの上下位置に2段に敷設
され、その一方に建設工事用の走行クレーンを追加して
設置することにより、建設時の天井走行クレーン10の稼
働効率を高めることができる。The crane girder 6 is shown in FIG.
As shown in FIG. 8 to FIG. 11, the operation efficiency of the overhead traveling crane 10 at the time of construction is improved by installing two traveling cranes at the upper and lower positions of each beam G and additionally installing a traveling crane for construction work on one of them. Can be increased.
【0026】天井走行クレーン10は建屋内に設置される
機器や,格納容器のユニットの搬入の他、遮蔽壁の吊り
込み等に使用され、この天井走行クレーン10によって建
屋B内では躯体の構築と格納容器の組み立て等、複数の
工程を並行して進行させることが可能となる。The overhead traveling crane 10 is used not only for loading equipment installed in the building and units for a storage container but also for suspending a shielding wall. With the overhead traveling crane 10, the construction of a skeleton in the building B is possible. It is possible to carry out a plurality of processes in parallel such as assembling the storage container.
【0027】天井走行クレーン10の設置後、図11に示す
ように対向する支柱7,7及び壁板8,8間に屋根架構
Rを架設して建屋Bの架構の構築は終了し、建屋Bの内
部の環境は全天候状態となる。屋根架構Rは例えば図示
するようにトラス構造で構成され、予め地組みされて吊
り上げられることにより、もしくは適当な大きさに分割
されたユニットを吊り上げて接続することにより架設さ
れる。After the overhead traveling crane 10 is installed, as shown in FIG. 11, the roof frame R is erected between the supporting columns 7 and the wall plates 8 and 8 facing each other, and the construction of the frame of the building B is completed. The environment inside is in all weather conditions. The roof frame structure R is constituted by, for example, a truss structure as shown in the drawing, and is erected by being preliminarily ground and hoisted, or by hoisting and connecting units divided into appropriate sizes.
【0028】以上の工程中、コア柱ユニットcを始め、
梁ユニットG1やクレーンガーダー6等、各部材の吊り込
みは建屋Bの周辺に設置されるクローラクレーンやトラ
ッククレーンによって行われる。During the above steps, starting with the core pillar unit c,
The suspension of each member such as the beam unit G 1 and the crane girder 6 is performed by a crawler crane or a truck crane installed around the building B.
【0029】建屋Bの架構の構築後の、遮蔽壁等の躯体
の構築や,格納容器の搬入と構築、及び機器や資材の搬
入は天井走行クレーン10によって行われ、状況に応じて
中空のコア柱Cの上部に図1に示すようにタワークレー
ン11を組み立て、これを利用する。コア柱Cの内部の空
間は階段,エレベータ,資材搬出入用のシャフト等に活
用される。After the construction of the structure of the building B, the construction of the skeleton such as the shielding wall, the loading and construction of the storage container, and the loading of the equipment and materials are carried out by the overhead traveling crane 10, and a hollow core is provided depending on the situation. The tower crane 11 is assembled on the upper part of the pillar C as shown in FIG. 1 and used. The space inside the core pillar C is utilized for stairs, elevators, shafts for carrying in and out materials, and the like.
【0030】図12, 図13は遮蔽壁を構築し、格納容器を
組み立てた、建屋Bの完成状態を示したものである。12 and 13 show a completed state of the building B in which the shielding wall is constructed and the storage container is assembled.
【0031】[0031]
【発明の効果】この発明は以上の通りであり、建屋の架
構を躯体に先行して組み立て、その上部に天井走行クレ
ーンを設置するとともに、屋根架構を架設するものであ
るため、架構の構築直後から天候の影響を受けることな
く、天井走行クレーンを稼働させることができ、この結
果、躯体工事と格納容器や機器等の搬入を並行して遂行
することが可能となり、建屋内での作業が大幅に進捗
し、工期の短縮化を実現することができる。The present invention is as described above. Since the structure of the building is assembled prior to the frame and the overhead traveling crane is installed on the upper part of the structure, the roof frame is installed. It is possible to operate the overhead traveling crane without being affected by the weather, and as a result, it is possible to carry out the skeleton work and the carrying-in of storage containers and equipment in parallel, and the work inside the building is greatly improved. It is possible to reduce the work period by progressing to.
【0032】また天井走行クレーンの早期稼働により稼
働率が高まり、クレーンを部材毎に分担させる必要がな
く、クレーン数を削減することができ、工費の節減を図
ることが可能である。Further, the operation rate is increased by early operation of the overhead traveling crane, it is not necessary to share the crane for each member, the number of cranes can be reduced, and the construction cost can be reduced.
【0033】更に天井走行クレーンは建築用タワークレ
ーンに比べて揚重能力が高いため、鉄筋ユニットを始
め、ユニットの大型化を可能にし、躯体工事の工程を短
縮することができる。Further, since the overhead traveling crane has a higher lifting capacity than that of the building tower crane, it is possible to increase the size of the unit including the reinforcing bar unit, and to shorten the skeleton construction process.
【図1】原子炉建屋の架構を示した斜視図である。FIG. 1 is a perspective view showing a frame of a reactor building.
【図2】架構構築の最初の手順を示した斜視図である。FIG. 2 is a perspective view showing a first procedure for constructing a frame.
【図3】図2の次の手順を示した斜視図である。FIG. 3 is a perspective view showing the next procedure of FIG.
【図4】コア柱脚部ユニットを示した斜視図である。FIG. 4 is a perspective view showing a core column base unit.
【図5】コア柱脚部ユニットを設置した様子を示した断
面図である。FIG. 5 is a cross-sectional view showing how the core column base unit is installed.
【図6】コア柱脚部ユニットと基礎スラブとの接合の様
子を示した断面図である。FIG. 6 is a sectional view showing how the core column base unit and the foundation slab are joined.
【図7】図3の次の手順を示した斜視図である。FIG. 7 is a perspective view showing the next procedure of FIG.
【図8】図7の次の手順を示した斜視図である。FIG. 8 is a perspective view showing the next procedure of FIG.
【図9】図8の次の手順を示した斜視図である。FIG. 9 is a perspective view showing the next procedure of FIG.
【図10】図9の次の手順を示した斜視図である。FIG. 10 is a perspective view showing the next procedure of FIG.
【図11】図10の次の手順を示した斜視図である。FIG. 11 is a perspective view showing the next procedure of FIG.
【図12】原子炉建屋の完成状態を示した縦断面図であ
る。FIG. 12 is a vertical cross-sectional view showing a completed state of the reactor building.
【図13】図12の横断面図である。13 is a cross-sectional view of FIG.
B……原子炉建屋、C……コア柱、c1……コア柱脚部ユ
ニット、c……コア柱ユニット、1……スラブ筋、M…
…マットスラブ、F……基礎スラブ、2……スラブ筋、
3……スタッドボルト、4……コンクリート、G……
梁、G1……梁ユニット、5……支持材、6……クレーン
ガーダー、7……支柱、8……壁板、9……走行レー
ル、10……走行クレーン、11……タワークレーン、R…
…屋根架構。B ...... reactor building, C ...... core pillars, c 1 ...... core column base unit, c ...... core pillars unit, 1 ...... slab muscle, M ...
… Mat slab, F …… Basic slab, 2 …… Slab muscle,
3 ... Stud bolt, 4 ... Concrete, G ...
Beam, G 1・ ・ ・ Beam unit, 5 ・ ・ ・ Support material, 6 …… Crane girder, 7 …… Pillar, 8 …… Wall plate, 9 …… Travel rail, 10 …… Travel crane, 11 …… Tower crane, R ...
… Roof frame.
Claims (1)
数個に分割され、ユニット化されたコア柱ユニットを積
み上げながら互いに接続して中空断面のコア柱を構築し
た後、その1方向に対向するコア柱間に梁を架設すると
ともに、この梁の対向する側にクレーンガーダーを支持
する支持材を梁の長さ方向に間隔をおいて設置し、この
支持材上にクレーンガーダーを敷設し、対向するクレー
ンガーダー間に、天井走行クレーンが載置された、並列
する走行レールを架設した後、梁上に屋根架構を架設し
て建屋の架構を構築する建屋の構築方法。1. A core pillar having a hollow cross-section is constructed by connecting core pillar units, which are divided into a plurality of pieces in the axial direction at the four corners of a foundation slab and are unitized, to each other while stacking the core pillar units. A beam is installed between the core pillars facing each other, and support materials for supporting the crane girder are installed on the opposite sides of the beam at intervals in the length direction of the beam, and the crane girder is laid on this support material. A method for constructing a building, in which a roof traveling frame is placed between the opposing crane girders and parallel traveling rails are installed, and then a roof frame is installed on a beam to construct a building frame.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18641191A JP2513376B2 (en) | 1991-07-25 | 1991-07-25 | How to build a building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18641191A JP2513376B2 (en) | 1991-07-25 | 1991-07-25 | How to build a building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0533515A JPH0533515A (en) | 1993-02-09 |
| JP2513376B2 true JP2513376B2 (en) | 1996-07-03 |
Family
ID=16187951
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP18641191A Expired - Fee Related JP2513376B2 (en) | 1991-07-25 | 1991-07-25 | How to build a building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2513376B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2777515B2 (en) | 1993-03-04 | 1998-07-16 | 新日本製鐵株式会社 | Method of constructing high-rise structure with closed cross section using steel element |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2576035B2 (en) * | 1993-05-14 | 1997-01-29 | 三菱重工業株式会社 | Zone module construction method for steel structure construction |
-
1991
- 1991-07-25 JP JP18641191A patent/JP2513376B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2777515B2 (en) | 1993-03-04 | 1998-07-16 | 新日本製鐵株式会社 | Method of constructing high-rise structure with closed cross section using steel element |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0533515A (en) | 1993-02-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| LU501348B1 (en) | METHOD FOR CONSTRUCTING LARGE-SPAN THIN-WALLED CONCRETE SOUND BARRIER WITH POURING TROLLEY | |
| CN104520521B (en) | Concept of high-rise building elevation | |
| US20130298496A1 (en) | Method for assembling shell segments for forming tower sections of a hybrid wind turbine tower | |
| US3726053A (en) | Method and apparatus for erecting modular high-rise building | |
| CN114059758A (en) | Assembled double-layer integral elevator shaft platform | |
| JP7548869B2 (en) | How to build structures | |
| CN212336080U (en) | Assembled tower crane foundation structure | |
| JP2513376B2 (en) | How to build a building | |
| JP6736226B2 (en) | Structure and construction method of the structure constructed on the tower-shaped building | |
| US3631648A (en) | Method of erection of high-rise building structure formed of modular units | |
| CN112112283A (en) | Layered flow structure installation method matched with fabricated building jacking construction method | |
| CN211340847U (en) | Precast beam of underground structure in reverse construction method | |
| JPH1136232A (en) | Composite column base structure and method of constructing the same | |
| RU2442868C1 (en) | Method for constructing building addition | |
| US3435583A (en) | Method of forming buildings | |
| JPH08270081A (en) | Construction method of frame structure | |
| CN221646160U (en) | Open pit mine elevated unloading room support structure | |
| JP3192543B2 (en) | Building demolition method | |
| CN215168311U (en) | Temporary supporting structure for reinforcing and reforming cultural relics | |
| JP2025152882A (en) | Frame structures for large-scale buildings | |
| FI89397B (en) | Foer farer Foer construct with stormodulators and modules to be used with foar farande | |
| JPS6358197A (en) | A block body for constructing a nuclear reactor containment vessel, a construction method using the same, and its manufacturing device | |
| JPH1181679A (en) | Construction for building | |
| JP2025152883A (en) | Construction methods for frame structures in large-scale buildings | |
| JP2017172262A (en) | Construction method of building |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19960312 |
|
| LAPS | Cancellation because of no payment of annual fees |