Girder for bridge erection

Info

Publication number
JP2585682B2
JP2585682B2 JP63027294A JP2729488A JP2585682B2 JP 2585682 B2 JP2585682 B2 JP 2585682B2 JP 63027294 A JP63027294 A JP 63027294A JP 2729488 A JP2729488 A JP 2729488A JP 2585682 B2 JP2585682 B2 JP 2585682B2
Authority
JP
Japan
Prior art keywords
girder
erection
bridge
pier
portal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP63027294A
Other languages
Japanese (ja)
Other versions
JPH01203505A (en
Inventor
正久 上野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yamaha Marine Co Ltd
Original Assignee
Sanshin Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanshin Kogyo KK filed Critical Sanshin Kogyo KK
Priority to JP63027294A priority Critical patent/JP2585682B2/en
Publication of JPH01203505A publication Critical patent/JPH01203505A/en
Application granted granted Critical
Publication of JP2585682B2 publication Critical patent/JP2585682B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] この発明は橋梁架設に使用する架設機械等の運搬に利
用される橋梁架設ガーダーに関するものである。
Description: TECHNICAL FIELD The present invention relates to a bridge erection girder used for transporting an erection machine or the like used for erection of a bridge.

[発明の背景] 一般に、橋梁の架設に使用される架設ガーダーは、橋
梁構築用部材(構築用PC桁など)を運搬台車に載せ、そ
して、所定の位置で吊上げ、所定の架設箇所まで運搬す
る等の走行路となるものであり、この架設ガーダーの走
行路としての使用状況は様々である。
BACKGROUND OF THE INVENTION Generally, an installation girder used for erection of a bridge mounts a bridge construction member (a PC girder for construction, etc.) on a transport trolley, lifts it at a predetermined position, and transports it to a predetermined erection location. Etc., and there are various uses of the erected girder as a traveling path.

この発明はかかる架設ガーダーの改良に係るものであ
り、この発明により前記走行作業等の安全性を向上しう
ると共に前記の機能を有する架設ガーダーのコストを低
廉化できるものとしている。
The present invention relates to the improvement of such an installation girder. According to the invention, it is possible to improve the safety of the traveling work and the like and to reduce the cost of the installation girder having the above function.

[従来技術] 従来より、橋梁の架設装置としては、橋梁の構築用PC
桁等を架設ガーダー上に載せて運搬し、次いで所定の位
置まで運搬したPC桁等を門型状の架設機により吊り上
げ、所定の据え付け位置に架設するいわゆる上路式の架
設装置が一般に知られている。
[Prior art] Conventionally, a bridge construction PC has been used as a bridge erection device.
There is generally known a so-called upper road type erection device in which a girder or the like is carried on an erecting girder and transported, and then a PC girder or the like conveyed to a predetermined position is lifted by a portal type erecting machine and installed at a predetermined installation position. I have.

この装置は構築用PC桁が極めて長尺でその幅が幅狭と
なっているために横ゆれする構築用PC桁を、橋脚上で横
移動させることなく吊った状態で横移動するので、安全
な橋梁架設作業ができるものとなっている。
This equipment is safe because the building PC girder is extremely long and its width is narrow, so the building PC girder that sways is moved without hanging on the pier. Bridge construction work can be performed.

しかしながら、前記のいわゆる上路式架設装置では、
本来構築用PC桁の運搬などの安全作業を目的として設置
される架設機(門型状架設機)自体を橋梁の架設状態に
伴なって移動設置しなければならないが、その移動設置
が大きな問題とされていた。
However, in the so-called road-type erection device,
The erection machine (portal erection machine) originally installed for the purpose of safe work such as transporting the PC girder for construction must be moved and installed according to the erection state of the bridge, but the moving installation is a major problem And it was.

すなわち、第1図、第3図等で示すように門型状架設
機4を架設ガーダー2上の運搬台車5に裁置し、次の橋
脚3あるいは橋脚8まで運搬する際に、門型状架設機4
と運搬台車5の全体重心はきわめて高く不安定であるた
め、微かな風の影響でも横転してしまうことがある。
That is, as shown in FIG. 1, FIG. 3, etc., when the portal-type erection machine 4 is placed on the transport trolley 5 on the erection girder 2, and transported to the next pier 3 or pier 8, Construction machine 4
And the overall center of gravity of the transport vehicle 5 is extremely high and unstable, so that it may roll over even under the influence of a slight wind.

この横転事故の対策として、運搬台車5上にジャッキ
17などの昇降装置を設け、横脚8をかわした箇所で前記
ジャッキ17を降下させてジャッキ17の降下分だけ門型状
架設機4を降ろし、その安定度を増量させたり、または
前記状態でさらに運搬台車5にカウンターウエイトを載
せたりして、全体重心を少しでも下げる対策がとられて
いる。
As a countermeasure against this rollover accident, a jack
A lifting device such as 17 is provided, and the jack 17 is lowered at a location where the side legs 8 are dodged, and the gate-shaped erection machine 4 is lowered by the amount of the jack 17 to be lowered, and its stability is increased, or in the state described above. In addition, countermeasures are taken to lower the overall center of gravity even slightly by placing a counterweight on the transport vehicle 5.

しかしながら、いずれの対策も最終的には万全とは言
えず、施工作業の安全性などの面からの対策が望まれて
いた。
However, none of these measures can be said to be perfect at the end, and measures from the viewpoint of safety of construction work have been desired.

[発明の目的] この発明は、前記従来の問題点に鑑みて創案されたも
のであり、架設用構築部材を運搬台車に載せて運搬する
際に、その走行性の安定を図るためには、一般にはその
重心を下げるか、または運搬台車が走行するレールとレ
ールとの間の間隔、すなわちその支持間隔を広げるかの
2通りの思想があるが、本発明はその後者の技術思想に
つき創案されたものである。
[Purpose of the Invention] The present invention has been made in view of the above-mentioned conventional problems, and in order to stabilize the traveling property when transporting a erection construction member on a transport trolley, In general, there are two ideas, that is, lowering the center of gravity or increasing the distance between rails on which the transport trolley travels, that is, increasing the supporting distance. The present invention was created based on the latter technical idea. It is a thing.

即ち構築物の運搬に使用される架設ガーダーはその使
用目的から横幅は出来るだけ狭い方が望ましいが、橋梁
構築用PC桁等の運搬走行を充足しうる耐力からすると一
般に1mないし1.5mの幅の架設ガーダーが使用されてお
り、またその上面に敷設されるレールのレール幅は0.8m
ないし1.2mとなっている。
In other words, it is desirable that the width of the erection girder used for transporting the structure is as narrow as possible for the purpose of use.However, in general, the erection girder with a width of 1 m to 1.5 m is considered to be able to satisfy the transportation traveling such as the PC girder for bridge construction. Girder is used, and the rail width laid on the upper surface is 0.8 m
Or 1.2m.

そこで本発明は、橋梁構築用PC桁等の運搬時並びに横
移動時に許される横幅で、その作業終了後、次の橋脚に
門型状架設機を移動させるときに一時的に補助レールが
設けられ、その門型状架設機の移動を安全に、かつ迅速
に行なえる架設ガーダーを提供することを目的とするも
のである。
Accordingly, the present invention provides an auxiliary rail that is temporarily allowed when the bridge-type PC girder or the like is transported and laterally moved, and after the work is completed, the portal-type erection machine is moved to the next pier. It is another object of the present invention to provide an installation girder that can move the portal-type installation machine safely and promptly.

[発明の構成] この発明による橋梁架設ガーダーは、 長尺に延出するガーダー本体の上面に橋梁架設用構築
部材の運搬台車レールが敷設されてなる橋梁架設用ガー
ダーであり、 前記ガーダー本体の両側面には、該両側面より外方に
張り出すとともに、この両側面側に折りたたみ可能とさ
れた張出部材上に補助レールが敷設されていることを特
徴とするものである。
[Constitution of the Invention] A bridge erection girder according to the present invention is a bridge erection girder in which a transport trolley rail of a bridge erection construction member is laid on an upper surface of a girder main body that extends long, and both sides of the girder main body. On the surface, an auxiliary rail is laid out on an overhanging member which projects outwardly from the both side surfaces and which is foldable on the both side surfaces.

[発明の実施例] 以下この発明を図面に示す実施例に基づいて説明す
る。
[Embodiments of the Invention] The present invention will be described below based on embodiments shown in the drawings.

まず始めに一実施例としてのPC桁1・・の架設状態に
つき説明をする。
First, an installation state of PC girder 1 as one embodiment will be described.

第2図に示すように後方で組み立てられた橋梁架設用
ガーダー2を前方に送り出し、それと同時にあらかじめ
前方側に所定の間隔をおいて立設された橋脚3上に門型
状架設機4を組み立てるべく、送り出し部6に該門型状
架設機4を移動できるように用意しておく。
As shown in FIG. 2, the bridge erection girder 2 assembled on the rear side is sent forward, and at the same time, the portal erection machine 4 is assembled on the pier 3 erected in advance at a predetermined interval on the front side. For this purpose, the portal-type erection machine 4 is prepared so as to be able to be moved to the delivery section 6.

次に前方に送り出された橋梁架設用ガーダー2を橋脚
3上に高さ調整部材18を介して載せ、その状態から前方
の門型状架設機4をガーダー2上において運搬台車5に
載せて運搬し、橋脚3上に据えつける(第4図(A)参
照)。
Next, the bridge erection girder 2 sent forward is placed on the pier 3 via the height adjusting member 18, and from this state, the front portal type erection machine 4 is placed on the carriage 5 on the girder 2 and transported. Then, it is installed on the pier 3 (see FIG. 4 (A)).

なお、送りだし部6においては後方に位置する門型状
架設機16を組み立てて据えつける。
In the feeding section 6, a portal type erection machine 16 located at the rear is assembled and installed.

そして第4図(A)に示すようにガーダー2を再度小
幅だけ前方に送り出し、送り出し部6と橋脚3の所定の
据えつけ位置で停止させ、前後の門型状架設機4、16の
吊り装置19でこのガーダー2を所定の位置まで降下させ
据えつける。
Then, as shown in FIG. 4 (A), the girder 2 is again sent forward by a small width, stopped at a predetermined installation position of the sending portion 6 and the pier 3, and the suspension device of the front and rear portal-type erection machines 4, 16 is stopped. At 19, the girder 2 is lowered to a predetermined position and installed.

この状態から第5図に示すようにガーダー2上におい
てPC桁1・・を運搬し、そのPC桁1・・の架設作業を開
始する。
From this state, the PC girder 1 is carried on the girder 2 as shown in FIG. 5, and the work of erection of the PC girder 1 is started.

次に第7図(A)、(B)に示すように架設したPC桁
1・・上にレール7を敷設し、このレール7上にPC桁用
運搬台車5を載置する。
Next, as shown in FIGS. 7 (A) and 7 (B), rails 7 are laid on the installed PC girders 1..., And the PC girders 5 are placed on the rails 7.

そしてガーダー2の後部にこの台車5を利用して吊り
下げ、敷設されたレール7上を通過して前方の橋脚8に
送り出す(第7図(B)参照)。
Then, the trolley 5 is used to suspend the girder 2 at the rear portion thereof, and the suspension is passed over the laid rail 7 and sent to the front pier 8 (see FIG. 7 (B)).

前方の橋脚8に送り出されたガーダー2を所定の位置
に据えつけ、既に架設したPC桁1・・上に設置したレー
ル7を使用して残りのPC桁1・・を運搬して架設する
(第8図(A)、(B)参照)。
The girder 2 sent to the front pier 8 is installed at a predetermined position, and the remaining PC girder 1 is transported and erected using the rails 7 installed on the PC girder 1 that has already been installed ( (See FIGS. 8A and 8B).

よって第9図(B)に示すようにA1からP1までのスパ
ンのPC桁1・・の架設が完了する。
Therefore, as shown in FIG. 9 (B), the installation of the PC girder 1 of the span from A1 to P1 is completed.

その後、第10図(A)、(B)に示すように、前方の
門型状架設機4はガーダー2の利用し橋脚8側に運搬す
る。
Thereafter, as shown in FIGS. 10 (A) and 10 (B), the front portal erection machine 4 is transported to the pier 8 side by using the girder 2.

なお、後方の門型状架設機16は架設完了した複数のPC
桁1・・上を利用して運搬し、橋脚3上に据えつける。
In addition, the rear gate-shaped erection machine 16 has a plurality of PCs
It is transported using girder 1 ... and installed on pier 3.

次に第11図に示すように橋脚3から橋脚8までのスパ
ンのPC桁1・・の据えつけが開始されることとなる(第
10図(C)参照)。
Next, as shown in FIG. 11, the installation of the PC girder 1 of the span from the pier 3 to the pier 8 is started (see FIG. 11).
(See FIG. 10 (C)).

ところで本発明は、前記の手順に示した第3図(A)
並びに第10図(A)に示す、前方の門型状架設機4の運
搬に関するものであり、前方の門型状架設機4は狭幅の
橋梁架設用ガーダー2上を移動するに際し、重心の高い
位置でこの架設機4を移動させると転倒あるいは横倒し
等の障害が生ずる。
By the way, according to the present invention, FIG.
In addition, the present invention relates to the transportation of the front portal erection machine 4 shown in FIG. 10 (A), and the front portal erection machine 4 moves the center of gravity when moving on the narrow bridge girder 2 for bridge construction. If the erection machine 4 is moved at a high position, obstacles such as overturning or overturning occur.

そこで本発明では、前記橋梁架設用ガーダー2の両側
面に、各々外方に張り出すとともにこの両側面側に折り
たたみ可能とされた張出部材12を設けたものである。
Therefore, in the present invention, on both side surfaces of the bridge erection girder 2, projecting members 12 are provided which project outward and are foldable on both side surfaces.

更にこの張出部材12上にレール幅を広くし安定度を高
めた補助レール15、15を敷設したものである(第1図、
第12図参照)。
Further, auxiliary rails 15, 15 having a wider rail and higher stability are laid on the overhang member 12 (FIG. 1,
(See Fig. 12).

即ち、第12図に示すように長尺に延出するガーダー本
体10の上面には既設の運搬台車レール11、11が敷設され
ている。
That is, as shown in FIG. 12, existing transporter rails 11, 11 are laid on the upper surface of the girder main body 10 which extends long.

このレール幅は前述したように0.8mから1.2mの間隔と
されている。そしてこのガーダー本体10の両側面には各
々張出部材12が設けられている。この張出部材12の構成
についての一実施例を説明すると、まず側面には連結部
13が設けられ、この連結部13には張出部材12の支持材14
・・が各々回動可能に取りつけられている。
The rail width is set at a distance of 0.8 m to 1.2 m as described above. On both side surfaces of the girder main body 10, overhang members 12 are provided. One embodiment of the structure of the overhang member 12 will be described.
The connecting portion 13 has a support member 14 for the overhanging member 12.
. Are mounted rotatably.

そして前記張出部材12の上面には補助レール15が敷設
されており、その補助レール15、15間のレール幅は2mな
いし2.5mとなっている。即ち、前述したように前方側の
門型状架設機4の移動運搬に際しては、架設ガーダー2
上に設けられた運搬台車レール11、11のレール間隔では
安定性が悪いために、両側面から張出部材12、12を外側
に張り出し、その張出部材12、12上に設けられた補助レ
ール15、15上に運搬台車5を載置し、この運搬台車5上
に門型状架設機4を載せて運搬するものとしている。
An auxiliary rail 15 is laid on the upper surface of the overhang member 12, and a rail width between the auxiliary rails 15 is 15 to 2.5 m. That is, as described above, when the front gate-type erection machine 4 is moved and transported, the erection girder 2
Because the stability is poor at the rail spacing of the transport trolley rails 11 provided on the upper side, the overhang members 12, 12 are extended outward from both side surfaces, and the auxiliary rails provided on the overhang members 12, 12 are provided. The transport trolley 5 is placed on 15 and 15, and the portal erection machine 4 is placed on the transport trolley 5 for transport.

この様な運搬方法であれば、移動時における門型状架
設機4の転倒あるいは横倒し等を防止でききわめて安定
度が高い移動方法がとれることになる。
With such a transporting method, the portal type erection machine 4 can be prevented from overturning or overturning at the time of moving, and a moving method with extremely high stability can be obtained.

さらに、門型状架設機4の移動が終了した後には、こ
の架設ガーダー2の両側面において外側に張り出した張
出部材12、12を前記連結部13を支点にして折りたたむこ
とが出来る(第14図参照)。
Further, after the movement of the gate-shaped erection machine 4 is completed, the projecting members 12, 12 projecting outward on both side surfaces of the erection girder 2 can be folded with the connecting portion 13 as a fulcrum (fourteenth). See figure).

この様に折りたためば、PC桁1・・の架設作業中にお
いても前記張出部材12、12が邪魔となるということはな
い。
By folding in this manner, the projecting members 12, 12 do not become an obstacle during the work of erection of the PC girder 1.

[発明の効果] この発明は以上の構成よりなり、この発明による橋梁
架設用ガーダーであれば、門型状架設機4の移動運搬に
際し、従来に比較してきわめて安定度が高く、かつその
コストを低廉化した橋梁架設ガーダーを提供できること
になる。
[Effects of the Invention] The present invention has the above-described configuration, and the bridge girder according to the present invention has extremely high stability and cost in moving and transporting the portal-type erection machine 4 as compared with the related art. It is possible to provide a bridge erection girder at a lower cost.

【図面の簡単な説明】[Brief description of the drawings]

第1図はこの発明による橋梁架設用ガーダーの使用状態
を示す概略図、第2図ないし第11図は、PC桁等の架設手
順を示す概略図、第12図、第13図はこの発明による架設
ガーダーを示す正面図、平面図、第14図は張出部材を折
り畳んだ状態を示す平面図である。 1……PC桁 2……橋梁架設用ガーダー 3……橋脚 4……前方の門型状架設機 5……運搬台車 6……送り出し部 7……レール 8……橋脚 10……ガーダー本体 11……運搬台車レール 12……張出部材 13……連結部 14……支持材 15……補助レール 16……後方の門型状架設機 17……ジャッキ 18……高さ調整部材 19……吊り装置
FIG. 1 is a schematic view showing a use state of a bridge erection girder according to the present invention, FIGS. 2 to 11 are schematic views showing a procedure for erection of a PC girder, etc. FIG. 12 and FIG. FIG. 14 is a front view, a plan view, and a plan view showing the construction girder, showing a state in which the overhanging member is folded. DESCRIPTION OF SYMBOLS 1 ... PC girder 2 ... Girder for bridge erection 3 ... Bridge pier 4 ... Front gate type erection machine 5 ... Carriage truck 6 ... Delivery part 7 ... Rail 8 ... Bridge pier 10 ... Girder body 11 … Transportation trolley rail 12… Extending member 13… Connecting part 14… Supporting material 15… Auxiliary rail 16… Rear gate-type erection machine 17… Jack 18 …… Height adjusting member 19… Suspension device

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】橋梁架設方向に向かって長尺に延出するガ
ーダー本体の上面に、架設用構築部材の運搬台車レール
が敷設され、かつガーダー本体の両側面には、この両側
面より外側方向に張り出し可能とされていると共に該両
側面側に折りたたみ可能とされた張出部材が取付けら
れ、 この張出部材の上面には前記運搬台車用の既設レールと
面一をなす補助レールが敷設されていることを特徴とす
る橋梁架設用ガーダー。
A girder main body extending long in the bridge erection direction is provided with a trolley rail of a construction member for erection, and both side surfaces of the girder main body extend outward from the both side surfaces. An overhang member that is foldable and is foldable is attached to both side surfaces, and an auxiliary rail is provided on an upper surface of the overhang member so as to be flush with the existing rail for the carriage. A girder for bridge erection, characterized in that:
JP63027294A 1988-02-08 1988-02-08 Girder for bridge erection Expired - Lifetime JP2585682B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63027294A JP2585682B2 (en) 1988-02-08 1988-02-08 Girder for bridge erection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63027294A JP2585682B2 (en) 1988-02-08 1988-02-08 Girder for bridge erection

Publications (2)

Publication Number Publication Date
JPH01203505A JPH01203505A (en) 1989-08-16
JP2585682B2 true JP2585682B2 (en) 1997-02-26

Family

ID=12217069

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63027294A Expired - Lifetime JP2585682B2 (en) 1988-02-08 1988-02-08 Girder for bridge erection

Country Status (1)

Country Link
JP (1) JP2585682B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015137697A (en) * 2014-01-22 2015-07-30 トヨタ自動車株式会社 Clutch control device

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3711355B2 (en) * 1996-12-11 2005-11-02 東急建設株式会社 Bridge erection method
JPH10219627A (en) * 1997-02-07 1998-08-18 Kawada Kensetsu Kk Pc girder erection device
JP6794235B2 (en) * 2016-12-06 2020-12-02 三井住友建設株式会社 How to erection a bridge
CN110904863B (en) * 2019-12-09 2021-06-25 中铁第五勘察设计院集团有限公司 Beam changing method with foldable beam changing machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015137697A (en) * 2014-01-22 2015-07-30 トヨタ自動車株式会社 Clutch control device

Also Published As

Publication number Publication date
JPH01203505A (en) 1989-08-16

Similar Documents

Publication Publication Date Title
JPH0579018A (en) Bridge girder laying device
CA1135222A (en) Cantilever straddle carrier
JP5769961B2 (en) Construction method and removal method of structure
JPH08245161A (en) Track-running movable crane
JP2585682B2 (en) Girder for bridge erection
JP3207777B2 (en) Quay crane
JP4551037B2 (en) Large-scale PC slab erection method and apparatus
JP3884689B2 (en) Mobile trolley for erection of members and bridge member erection method using the same
US5433150A (en) Traveling crane
CN114250711B (en) Highway bridge girder erection machine and hole passing method
JPH0335156B2 (en)
JP3276308B2 (en) Container crane
JPH1111871A (en) Traversing device for cargo handling machinery
JPH09209312A (en) Bridge erecting device
CN111576218A (en) Method for rapidly transferring segment box girder on land
JP2788170B2 (en) Automatic traveling concrete bucket landing position adjustment device
JPS6344884B2 (en)
JPH01313300A (en) Container handling system
CN114808563B (en) Suspension type monorail girder erecting system
JP4961268B2 (en) Precast floor slab transport method and transport mechanism
JP3728432B2 (en) Supporting built-in device
CN110904810B (en) Rapid erecting system for high-speed railway box girder
JP3052630B2 (en) Rail tunneling equipment for shield tunnel
JP2004068477A (en) Work transport cart
JP2012116649A (en) Container crane for quay