JP2661452B2 - Construction method of reinforced concrete columns and beams - Google Patents
Construction method of reinforced concrete columns and beamsInfo
- Publication number
- JP2661452B2 JP2661452B2 JP4033223A JP3322392A JP2661452B2 JP 2661452 B2 JP2661452 B2 JP 2661452B2 JP 4033223 A JP4033223 A JP 4033223A JP 3322392 A JP3322392 A JP 3322392A JP 2661452 B2 JP2661452 B2 JP 2661452B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- column
- main
- hollow portion
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Rod-Shaped Construction Members (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明はプレキャストコンクリ
ート柱および梁の施工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing precast concrete columns and beams.
【0002】[0002]
【従来の技術】従来 コンクリート柱の施工に用いるハ
ーフメイドの表層部と中空部からなるプレキャストコン
クリート柱材としては、図9に示す、かぶりコンクリー
トタイプと図10に示すフープ筋打込みタイプと図11
に示すフープ筋および主筋打込みタイプとがあった。か
ぶりコンクリートタイプは、フープ筋1、主筋2がいず
れも表層部3のコンクリート内にはなく、中空部4内に
位置する。このためかぶりコンクリートタイプは配筋さ
れていない無筋部分の断面積が大きくなるため、柱径が
通常より大きくなる。フープ打込みタイプは主筋が内側
の中空部4に追込まれ、断面性能が落ちるため、これも
柱径が通常より大きくなる。フープ筋および主筋打込み
タイプは主筋が中空部4内で継がれるため内側に追込ま
れ、断面性能が落ちるので、柱径が通常よりも大きくな
る。またコンクリート打設時にコンクリートの側圧がか
かるため、板の厚さを厚くし、コンクリートの強度を上
げなければならない。2. Description of the Related Art Conventionally, a half-made precast concrete column material having a surface layer portion and a hollow portion used for the construction of a concrete column includes a cover concrete type shown in FIG. 9, a hoop stud type shown in FIG.
And the hoop muscle and main muscle driving type shown in FIG. In the cover concrete type, neither the hoop bar 1 nor the main bar 2 is located in the hollow part 4 but in the concrete of the surface part 3. For this reason, in the cover concrete type, since the cross-sectional area of the unreinforced portion where no reinforcing bars are provided increases, the column diameter becomes larger than usual. In the hoop driving type, the main bar is driven into the inner hollow portion 4 and the cross-sectional performance is reduced, so that the column diameter is also larger than usual. In the hoop streak and main stud driving type, the main streak is connected inside the hollow portion 4 so that the main streak is driven inward, and the cross-sectional performance is reduced. In addition, since the lateral pressure of concrete is applied when concrete is poured, the thickness of the plate must be increased to increase the strength of the concrete.
【0003】[0003]
【発明が解決しようとする課題】この発明は上記問題点
に着目しなされたものである。その目的はプレキャスト
柱材の全断面を有効に機能せしめ、柱径に比べ大きな耐
力を付与することができ、コンクリート柱の施工に際し
ては鉄筋、型枠の組立作業の省力化、揚重機の小型化を
図ることができ、かつ遠心成形法により能率よく製造で
きて、高品質、高強度を確保できるプレキャストコンク
リート柱および梁の施工法を提案するにある。SUMMARY OF THE INVENTION The present invention has been made in view of the above problems. The purpose is to make the entire cross section of the precast column material function effectively, and to provide greater strength than the column diameter, and to reduce the labor for assembling reinforcing bars and formwork when constructing concrete columns, and to reduce the size of the lifting machine. It is an object of the present invention to propose a method for constructing precast concrete columns and beams which can be manufactured efficiently by a centrifugal molding method and can ensure high quality and high strength.
【0004】[0004]
【課題を解決するための手段】請求項(1) のプレキャス
トコンクリート柱材は表層部と中空部とからなるプレキ
ャストコンクリート柱材において、中空部は断面円形を
なし、表層部内にフープ筋および表層部の隅角部に主筋
を配筋し、柱頭上面から主筋を突出させ、柱脚部の表層
部コンクリートを切欠して主筋の重ね継手用空間を設け
てある。The precast concrete column material according to claim 1 is a precast concrete column material having a surface layer and a hollow portion, wherein the hollow portion has a circular cross section, and a hoop streak and a surface layer are formed in the surface layer. The main reinforcement is arranged at the corners of the column, the main reinforcement protrudes from the upper surface of the column capital, and the surface layer concrete of the column base is cut out to provide a space for the lap joint of the main reinforcement.
【0005】請求項(2) のプレキャストコンクリート柱
材は表層部と中空部とからなるプレキャストコンクリー
ト柱材において、中空部は断面円形をなし、表層部内に
フープ筋および表層部の隅角部に主筋を配筋し、柱頭上
面から主筋を突出させ、柱脚の表層部下面に主筋下端に
固着したスリーブ継手が開口してあり、前記表層部コン
クリートの各中間側に切欠した梁接合部空間にプレキャ
スト梁材の端部を載置し、前記中空部に主筋・フープ筋
からなる鉄筋籠を吊下げて挿入することにより配筋し、
かつその中空部にコンクリートを打設して一体化するこ
とを特徴とする。The precast concrete column material according to claim (2) is a precast concrete column material having a surface portion and a hollow portion, wherein the hollow portion has a circular cross section, a hoop streak in the surface portion and a main bar in a corner portion of the surface portion. The main joint protrudes from the upper surface of the column cap, and a sleeve joint fixed to the lower end of the main bar is opened on the lower surface of the column base, and precast in the beam joint space cut out on each intermediate side of the surface layer concrete. Place the ends of the beam material, arrange reinforcing bars by hanging and inserting a reinforcing bar basket consisting of main bars and hoop bars into the hollow portion,
In addition, concrete is poured into the hollow portion to be integrated.
【0006】使用するプレキャストコンクリート柱材
は、表層部のコンクリート内にフープ筋および表層部の
隅角部のコンクリート内に主筋が配筋してあり、断面す
べてを有効に機能せしめることができ、従来のかぶりコ
ンクリートタイプあるいはフープ筋打込みタイプに比べ
断面性能が優れたコンクリート柱を構築できる。また柱
の鉄筋組立型枠組立の作業を省略でき、上下柱材間の主
筋を重ね継手、あるいはスリーブジョイントで連結で
き、コンクリートを打設するのみで施工できる。また断
面円形の中空部を有するこの柱材は遠心成形法により、
高品質のものを高い生産性をもって製造できる。また軽
量(例えば、1,000mm□、850mmφ、1=3,000
mmとしてW=3.0ton 程度)であり、揚重機を小形にで
きる。また中空部内に、梁筋を配筋し梁を固定したり、
組立鉄筋や鉄骨を配して補強ができる。またコンクリー
ト打設時のコンクリート側圧に対しても有利な形状であ
る。さらにこの施工法は、鉄筋籠の補強鉄筋で補強され
た高強度のコンクリート柱を能率よく施工することがで
きる。The precast concrete column material used has a hoop reinforcing bar in the surface layer concrete and a main reinforcing bar in the concrete at the corner portion of the surface layer, so that all cross sections can function effectively. It is possible to construct a concrete column having a superior cross-sectional performance as compared to a concrete cover type or a hoop driving type. In addition, the work of assembling the reinforcing bar and formwork of the columns can be omitted, the main reinforcing bar between the upper and lower columns can be connected by a lap joint or a sleeve joint, and the construction can be performed only by casting concrete. In addition, this column material having a hollow section with a circular cross section, by centrifugal molding method,
High quality products can be manufactured with high productivity. Light weight (for example, 1,000mm □, 850mmφ, 1 = 3,000
(W = 3.0 ton in mm), and the hoist can be downsized. In the hollow part, beam reinforcement is arranged to fix the beam,
Reinforcement can be achieved by arranging assembled steel bars and steel frames. It is also an advantageous shape against the lateral pressure of concrete during concrete casting. Further, this construction method can efficiently construct a high-strength concrete column reinforced with a reinforcing bar of a reinforcing bar cage.
【0007】[0007]
【実施例】図1、図2は(1) 項の発明で使用するプレキ
ャストコンクリート柱材5−1を示す。この柱材5−1
は正方形断面をなし、表層部3と断面円形の中空部4か
らなり、外縁に沿い螺旋状に連続するフープ筋1および
各隅部に配した3本の主筋2はいずれも表層部3内に配
筋され、主筋2は柱頭の上面から上方に突出させてあ
る。1 and 2 show a precast concrete column 5-1 used in the invention of item (1). This pillar 5-1
Has a square cross section, is composed of a surface layer portion 3 and a hollow portion 4 having a circular cross section. The hoop streaks 1 which are spirally continuous along the outer edge and the three main bars 2 arranged at each corner are all within the surface layer portion 3. The main bar 2 is arranged to protrude upward from the upper surface of the stigma.
【0008】柱頭表層部3の各側面の幅方向中央部分に
は方形に切欠いて、図2(a) に示す梁接合空間6が設け
てある。また、柱脚表層部3の各隅角部内側面には断面
略五角形に切欠いて、図2(c) に示す主筋の継手用空間
7が設けてあり、主筋2の下端部はこの空間7内に張り
出している。A beam joint space 6 shown in FIG. 2 (a) is provided at the center in the width direction of each side surface of the capital portion 3 and is notched in a rectangular shape. The inner surface of each corner of the column base surface layer portion 3 is notched in a substantially pentagonal cross-section, and a joint space 7 for the main reinforcement shown in FIG. 2 (c) is provided. Overhangs.
【0009】次にこの柱材5−1を用いたコンクリート
柱、梁および床の施工法の実施例をあげ説明する。Next, an embodiment of a concrete column, beam and floor construction method using the column member 5-1 will be described.
【0010】図3(a) は、コンクリート柱を構築すべき
コンクリートの床スラブ8を示し、下階部から主筋2'が
突出している。(b) 図において、柱材5−1の柱脚部分
を主筋2'の位置に揃えセットする。主筋2'は図4(a),
(b) に示すごとく、柱材5−1の継手用空間7内で主筋
2に添い配列させ重ね継手を構成させる。FIG. 3 (a) shows a concrete floor slab 8 on which a concrete pillar is to be constructed, and a main bar 2 'projects from the lower floor. (b) In the figure, the column base of the column member 5-1 is aligned and set at the position of the main bar 2 '. The main muscle 2 'is shown in FIG.
As shown in (b), the lap joint is formed by arranging along the main reinforcement 2 in the joint space 7 of the column member 5-1.
【0011】次に、図3(c) において、型枠兼用のプレ
キャスト梁部材9の端部を柱材5−1の梁接合空間6に
載置してセットし、(d) において、梁の主筋10を柱材
5−1の中空部4を横切り配筋した後、(e) において、
型枠兼用のプレキャストスラブ材11をセットし、スラ
ブ材上に上端筋12を配筋し、(f) において、柱材5−
1中空部4、梁部材9、およびスラブ材11上にコンク
リート13を打設し、コンクリート柱、梁および床スラ
ブを施工する。Next, in FIG. 3 (c), the end of the precast beam member 9 also serving as a mold is placed and set in the beam joining space 6 of the column member 5-1. After arranging the main reinforcing bar 10 across the hollow portion 4 of the column member 5-1, in (e),
A precast slab material 11 also serving as a formwork is set, and an upper end bar 12 is arranged on the slab material.
(1) Concrete 13 is cast on the hollow portion 4, the beam member 9, and the slab material 11, and concrete columns, beams and floor slabs are constructed.
【0012】このコンクリート柱の施工において、柱材
5−1に配筋してあるフープ筋1、主筋2のみでは耐力
が不足する場合は、図5(a),(b) のごとく中空部4内に
主筋2'およびフープ筋1'からなる補強鉄筋14あるいは
鉄骨15を入れる。In the construction of this concrete column, if the proof strength is insufficient only with the hoop bar 1 and the main bar 2 arranged on the column member 5-1, as shown in FIGS. A reinforcing bar 14 or a steel frame 15 composed of the main bar 2 'and the hoop bar 1' is put in the inside.
【0013】補強鉄筋14を重ね継手あるいはガス圧接
等の継手タイプで接合して配筋する。Reinforcing reinforcing bars 14 are joined by a joint type such as a lap joint or a gas pressure welding and arranged.
【0014】重ね継手の場合は図3(b) の工程の後に、
図6(a) のごとく、上方から中空部4に吊込み配置す
る。上下に位置する補強鉄筋14間は、場所打ちコンク
リート杭の杭筋(重ね継手)の要領で配筋できる。ガス
圧接等による継手タイプの場合は図3(a) の工程の後に
図6(a) のごとく、床スラブ8から突出した下階部の補
強鉄筋14'先端と補強鉄筋14を継いで補強鉄筋14の
上部を束ねてから図3(b) のごとくプレキャストコンク
リート柱材をセットする。鉄骨15の場合は図6(b),
(c) のごとく柱材5−1のセット前に、2〜3節の鉄骨
15を建込み、その外側に上方から柱材5−1を吊込み
セットする。図6(d) のように鉄骨梁16を接合するに
は、例えばパドル工法により固定する。In the case of a lap joint, after the step of FIG.
As shown in FIG. 6 (a), it is suspended in the hollow part 4 from above. Reinforcing bars between the upper and lower reinforcing bars 14 can be arranged in the manner of pile bars (lap joints) of cast-in-place concrete piles. In the case of the joint type by gas pressure welding or the like, as shown in FIG. 6A, after the step of FIG. After bundling the upper parts of the fourteen, a precast concrete column is set as shown in FIG. In the case of the steel frame 15, FIG.
As shown in (c), before setting the pillar 5-1, the steel frames 15 of two or three sections are erected, and the pillar 5-1 is suspended and set from above from outside. In order to join the steel beams 16 as shown in FIG. 6 (d), they are fixed by, for example, a paddle method.
【0015】図7、図8に(2) 項の発明になるプレキャ
ストコンクリート柱材の実施例を示す。この柱材5−2
は図1、図2に示す柱材5−1と比べ、柱脚部分に継手
用空間7がなく、これに代り、主筋2の下端にスリーブ
継手17を固着し、そのスリーブ継手17の開口端を柱
脚表層部に開口せしめてある。FIGS. 7 and 8 show an embodiment of the precast concrete column according to the invention of item (2). This pillar 5-2
Is different from the column member 5-1 shown in FIGS. 1 and 2 in that there is no joint space 7 in the column base, and instead, a sleeve joint 17 is fixed to the lower end of the main bar 2, and the open end of the sleeve joint 17 is opened. Is opened in the surface of the column base.
【0016】この柱材5−2を用いてコンクリート柱、
梁および床を施工するには、前記図3に示した施工の実
施例と略同様に施工できるが、主筋の継手が僅かに異な
る。A concrete column using the column member 5-2,
In order to construct the beam and the floor, it can be constructed in substantially the same manner as the embodiment of the construction shown in FIG.
【0017】すなわち、図3(b) にならい柱材5−2を
床スラブ8から突出した主筋2'位置に揃いセットする際
に、主筋2'をスリーブ継手17に挿通して配置する。そ
の後、図3と同様に梁部材9、梁主筋10、スラブ材1
1、スラブ上端筋12を配筋し、コンクリート13を打
設した後、スリーブ継手17内にグラウトを充填し、主
筋間を接合する。That is, when the column 5-2 according to FIG. 3 (b) is set at the position of the main bar 2 'protruding from the floor slab 8, the main bar 2' is inserted through the sleeve joint 17 and arranged. Thereafter, similarly to FIG. 3, the beam member 9, the beam main reinforcement 10, the slab material 1
1. After arranging the upper reinforcing bar 12 of the slab and placing concrete 13, grout is filled in the sleeve joint 17 and the main reinforcing bars are joined.
【0018】このプレキャストコンクリート柱材を製造
するには、遠心成形用の円筒形型枠内に断面正方形の中
子を取付け、その中にフープ筋および主筋を配置した
後、コンクリートを注入し、軸を中心に回転する遠心成
形法により製造できる。柱頭部の梁接合空間あるいは主
筋の重ね継手空間は型枠または発泡スチロール、等を用
い成形できる。In order to manufacture this precast concrete column material, a core having a square section is mounted in a cylindrical mold for centrifugal molding, a hoop bar and a main bar are disposed therein, and concrete is poured into the shaft. Can be manufactured by a centrifugal molding method that rotates about the center. The beam joint space of the column capital or the lap joint space of the main reinforcement can be formed using a mold or styrene foam.
【0019】なお上記実施例では螺旋状のフープ筋を用
いたが環状、不連続のフープ筋であってもよい。In the above embodiment, a spiral hoop streak is used, but an annular or discontinuous hoop streak may be used.
【0020】[0020]
【発明の効果】この発明は次の効果を奏する。The present invention has the following effects.
【0021】 表層部と中空部に後から打設するコン
クリートを一体化し、柱の全断面を有効に作用させ、柱
径に比べて大きな耐力を付与することができる。The concrete to be cast later is integrated into the surface layer portion and the hollow portion so that the entire cross section of the column can be effectively used, and a large proof stress can be given as compared with the column diameter.
【0022】 表層部の柱脚部でコンクリート打設時
にコンクリートの側圧に対して有利であり、ひび割れ、
崩壊の恐れがない。It is advantageous against lateral pressure of concrete at the time of placing concrete at the column base of the surface layer,
There is no fear of collapse.
【0023】 断面全てを有効に機能せしめることが
できる。[0023] All cross sections can function effectively.
【0024】 中空部の鉄筋を鉄筋籠に挿入すること
により後から配筋するので、設計変更も可能である。Since the reinforcing bars in the hollow portion are arranged later by inserting the reinforcing bars into the reinforcing bar cage, the design can be changed.
【0025】 プレキャストコンクリート部材表層部
の柱脚部が円形であるため、コンクリート打設時のコン
クリート側圧に対しても有利な形状であり、より長い柱
の施工が可能である。Since the column base of the surface layer of the precast concrete member is circular, it has an advantageous shape against the lateral pressure of concrete at the time of placing concrete, and a longer column can be constructed.
【0026】 柱頭を方形に切欠いて梁接合空間を設
け、この梁接合空間にプレキャスト梁材の端部を載置し
て接合するので、梁およびスラブの施工性が向上し、一
層好適である。The beam joint space is provided by notching the column capital, and the ends of the precast beam members are placed and joined in this beam joint space, so that the workability of the beam and the slab is improved, which is more preferable.
【0027】 柱脚において、その隅角部の内側面の
みを切欠いてあるので、断面性能を低下することなし
に、下階との重ね継手の施工性が容易となる。[0027] In the column base, only the inner surface at the corner is cut out, so that the workability of the lap joint with the lower floor becomes easy without lowering the cross-sectional performance.
【図1】(1) 項の実施例のプレキャストコンクリート柱
材の一部断面(D−D)で示す正面図である。FIG. 1 is a front view showing a partial section (DD) of a precast concrete column material according to the example of the item (1).
【図2】(a),(b),(c) はそれぞれ図1のA−A,B−
B,C−C断面図である。2 (a), 2 (b) and 2 (c) are AA and B- 1 of FIG. 1, respectively.
It is a B, CC sectional view.
【図3】(a),(b),(c),(d),(e),(f) はそれぞれコンクリ
ート柱施工実施例を工程順に示す説明図である。FIGS. 3 (a), (b), (c), (d), (e), (f) are explanatory diagrams showing concrete column working examples in the order of steps.
【図4】(a) は主筋を重ね継手で接合した実施例の柱材
の一部断面で示す正面図、(b)はC−C断面図である。FIG. 4 (a) is a front view showing a partial cross section of a column member of an embodiment in which main reinforcing bars are joined by lap joints, and FIG. 4 (b) is a CC cross sectional view.
【図5】(a) は中空部に補強鉄筋を、(b) は中空部に鉄
骨を配筋した柱材の横断面図である。FIG. 5 (a) is a cross-sectional view of a column member in which a reinforcing bar is provided in a hollow portion, and FIG. 5 (b) is a column member in which a steel frame is provided in a hollow portion.
【図6】(a) は柱材中空部に組立鉄筋を配筋する状態、
(b) は柱材のセットに先だち鉄骨を建込んだ状態、(c)
は建込んだ鉄骨の外側に柱材をセットした状態、(d) は
配筋した鉄骨に鉄骨梁を接合した状態、(e) は補強鉄筋
を先組した状態を示す説明図である。FIG. 6 (a) shows a state in which an assembling reinforcing bar is arranged in a hollow portion of a column member,
(b) is a state in which a steel frame is erected before the set of column members, (c)
FIG. 4 is an explanatory view showing a state in which a pillar is set outside a built-in steel frame, (d) shows a state in which a steel beam is joined to a reinforced steel frame, and (e) shows a state in which reinforcing steel is pre-assembled.
【図7】(2) 項の実施例のプレキャストコンクリート柱
材の一部断面(D−D)で示す正面図である。FIG. 7 is a front view showing a partial cross section (DD) of the precast concrete column material of the example of the item (2).
【図8】(a),(b),(c) はそれぞれ図7の柱材のA−A,
B−B,C−C断面図である。8 (a), (b) and (c) are columns AA and FIG. 7 of FIG. 7, respectively.
It is BB and CC sectional drawing.
【図9】従来のかぶりコンクリートタイプのプレキャス
トコンクリート柱材の横断面図である。FIG. 9 is a cross-sectional view of a conventional cast concrete type precast concrete column.
【図10】従来のフープ筋打込みタイプのプレキャスト
コンクリート柱材の横断面図である。FIG. 10 is a cross-sectional view of a conventional hoop stud driving type precast concrete column material.
【図11】従来のフープ筋および主筋打込みタイプのプ
レキャストコンクリート柱材の横断面図である。FIG. 11 is a cross-sectional view of a conventional precast concrete column member of a hoop and a main bar driving type.
1…フープ筋、2…主筋、3…表層部、4…中空部、5
…プレキャストコンクリート柱材、6…梁接合空間、7
…主筋の継手用空間、8…床スラブ、9…プレキャスト
梁部材、10…梁の主筋、11…プレキャストスラブ
材、12…スラブの上端筋、13…コンクリート、14
…補強鉄筋、15…鉄骨、16…鉄骨梁、17…スリー
ブ継手。DESCRIPTION OF SYMBOLS 1 ... Hoop muscle, 2 ... Main muscle, 3 ... Surface part, 4 ... Hollow part, 5
... precast concrete pillars, 6 ... beam joint space, 7
... space for joint of main bar, 8 ... floor slab, 9 ... precast beam member, 10 ... main bar of beam, 11 ... precast slab material, 12 ... upper end bar of slab, 13 ... concrete, 14
... reinforcing reinforcing bars, 15 ... steel frames, 16 ... steel beams, 17 ... sleeve joints.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 荻原 行正 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (56)参考文献 特開 平2−225737(JP,A) 特開 平2−232438(JP,A) 特公 昭49−44723(JP,B2) ──────────────────────────────────────────────────続 き Continuation of front page (72) Inventor Yukimasa Ogiwara Kashima Construction Co., Ltd. 1-2-7 Moto-Akasaka, Minato-ku, Tokyo (56) References JP-A-2-225737 (JP, A) JP Hei 2-232438 (JP, A) JP-49-44723 (JP, B2)
Claims (2)
コンクリート柱材を使用し前記表層部は断面方形に、中
空部は断面円形をなし、表層部にフープを配筋し、かつ
表層部の隅角部に主筋を配筋し、柱頭上面から前記主筋
を突出させ、柱頭の表層部コンクリートの各中間側面を
方形に切欠して梁接合空間を設け、その梁接合空間にプ
レキャスト梁材の端部を載置し、また柱脚の表層部コン
クリートの各隅角部内側面のみを切欠して主筋の継手空
間を設けてあり、前記中空部に主筋およびフープ筋から
なる鉄筋籠を吊下げて挿入することを特徴とするプレキ
ャストコンクリート柱。1. A precast concrete column having a surface portion and a hollow portion, wherein the surface portion has a rectangular cross section, the hollow portion has a circular cross section, a hoop is arranged in the surface portion, and a corner of the surface portion is provided. Reinforcing the main reinforcement at the corners, projecting the main reinforcement from the top of the capital, notching each intermediate side of the surface layer concrete of the capital with a square notch to provide a beam joint space, and the end of the precast beam material in the beam joint space In addition, a joint space for the main reinforcing bar is provided by notching only the inner surface of each corner of the surface layer concrete of the column base, and a reinforcing bar basket including a main reinforcing bar and a hoop reinforcing bar is suspended and inserted into the hollow portion. Precast concrete columns characterized by the following:
コンクリート柱材を使用し、前記表層部は断面方形に、
中空部は断面円形をなし、表層部内にフープ筋を配筋
し、かつ表層部の隅角部に主筋を配筋し、柱頭上面から
前記主筋を突出させ、柱頭の表層部コンクリートの各中
間側面を方形に切欠して梁接合部空間を設け、その梁接
合空間にプレキャスト梁材の端部を載置し、また柱脚の
表層部下面に主筋の下端に固着したスリーブ継手が開口
してあり、前記中空部に主筋およびフープ筋からなる鉄
筋籠を後から中空部に吊下げて挿入することにより配筋
しかつ中空部にコンクリートを打設して一体化とするこ
とを特徴とする柱と梁の施工法。2. A precast concrete column material comprising a surface portion and a hollow portion, wherein the surface portion has a rectangular cross section.
The hollow section has a circular cross section, hoop reinforcement is arranged in the surface layer, and main reinforcement is arranged at the corners of the surface layer, and the main reinforcement projects from the top of the capital, and each intermediate side surface of the concrete at the surface of the capital The beam joint space is provided by notching a square, the end of the precast beam material is placed in the beam joint space, and a sleeve joint fixed to the lower end of the main bar is opened in the lower surface of the column base. And a column characterized in that the reinforcing bar composed of a main bar and a hoop bar is hung in the hollow portion afterwards and inserted into the hollow portion to arrange the reinforcing bars, and concrete is cast in the hollow portion to be integrated. Construction method of beam.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4033223A JP2661452B2 (en) | 1992-02-20 | 1992-02-20 | Construction method of reinforced concrete columns and beams |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4033223A JP2661452B2 (en) | 1992-02-20 | 1992-02-20 | Construction method of reinforced concrete columns and beams |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH05230872A JPH05230872A (en) | 1993-09-07 |
| JP2661452B2 true JP2661452B2 (en) | 1997-10-08 |
Family
ID=12380454
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP4033223A Expired - Lifetime JP2661452B2 (en) | 1992-02-20 | 1992-02-20 | Construction method of reinforced concrete columns and beams |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2661452B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| ES2154986B1 (en) * | 1998-09-08 | 2001-12-01 | Sanchez Jaime Enrique Jimenez | PREFABRICATED PILLAR OF REINFORCED CONCRETE FOR BUILDING. |
| ES2230964B1 (en) * | 2002-11-18 | 2006-07-01 | Jaime Enrique Jimenez Sanchez | MANUFACTURING PROCEDURE OF PREFABRICATED PILLAR OF REINFORCED CONCRETE AND PILLAR SO OBTAINED. |
| CN108104372A (en) * | 2018-02-05 | 2018-06-01 | 天津城建大学 | For the precast combined constructional column and construction method of masonry structure |
| CN108952009A (en) * | 2018-09-07 | 2018-12-07 | 三筑工科技有限公司 | Prefabricated superposed column, reinforced column and assembled architecture body |
| CN114542126B (en) * | 2022-03-23 | 2024-07-23 | 中铁第一勘察设计院集团有限公司 | Embedded water stop belt fixing device and installation method thereof |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4944723A (en) * | 1972-08-31 | 1974-04-27 | ||
| JP2768380B2 (en) * | 1989-02-27 | 1998-06-25 | 大成建設株式会社 | Joining method for precast concrete columns |
| JPH0765332B2 (en) * | 1989-03-07 | 1995-07-19 | 住友建設株式会社 | PC pillar construction method |
-
1992
- 1992-02-20 JP JP4033223A patent/JP2661452B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH05230872A (en) | 1993-09-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2661452B2 (en) | Construction method of reinforced concrete columns and beams | |
| JP2000104336A (en) | Joint structure between pile and superstructure frame in structure and construction method of superstructure frame above pile | |
| JP3602429B2 (en) | Reinforced concrete columns | |
| JP3802996B2 (en) | Construction method of flat slabs using steel pipe concrete columns | |
| JP3062909B2 (en) | Construction method of composite underground wall using soil cement column wall | |
| JPS6321770B2 (en) | ||
| JPH06264411A (en) | Prefabrication method of bridge pier and bridge pier concrete block, reinforcing bar cage and inner form | |
| JPH04222742A (en) | Composite beam | |
| JPH0325103A (en) | Joint work for pc pillar and pc cap beam | |
| JPH0893137A (en) | Precast post serving as form and construction method therefor | |
| JP2769937B2 (en) | Steel tube concrete column in underground reverse driving method | |
| JP2514859B2 (en) | Precast Steel Reinforced Concrete Concrete Column | |
| JP2618841B2 (en) | Composite timber column method | |
| JP2001254367A (en) | Connection structure of pile and foundation beam | |
| JP2701650B2 (en) | PC column / beam frame structure and PC column / beam joint members | |
| JPH0765339B2 (en) | Concrete pillar construction method | |
| JPH0118229B2 (en) | ||
| JPH0949264A (en) | Constructing method for reinforced concrete framework and structure, and member therefor | |
| JP2910551B2 (en) | Lap joint method of main reinforcement of SRC column | |
| JPH10238133A (en) | Seismic reinforcement structure with K-shaped brace | |
| JPH0742762B2 (en) | Upper half PC concrete pillar and construction method of this pillar | |
| JPH04237731A (en) | Construction method of RC column with core reinforcement | |
| JPH0448136B2 (en) | ||
| JPH05133033A (en) | Construction method for reinforced concrete oblique roof and placing hollow form | |
| JPH07103636B2 (en) | Building structure building pillar member and manufacturing method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19970513 |