JP2709433B2 - Horizontal embedding method of strip-shaped sheet material in the ground - Google Patents
[go: Go Back, main page]

JP2709433B2 - Horizontal embedding method of strip-shaped sheet material in the ground - Google Patents

Horizontal embedding method of strip-shaped sheet material in the ground

Info

Publication number
JP2709433B2
JP2709433B2 JP33241992A JP33241992A JP2709433B2 JP 2709433 B2 JP2709433 B2 JP 2709433B2 JP 33241992 A JP33241992 A JP 33241992A JP 33241992 A JP33241992 A JP 33241992A JP 2709433 B2 JP2709433 B2 JP 2709433B2
Authority
JP
Japan
Prior art keywords
slot
sheet material
ground
shaped sheet
pull
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP33241992A
Other languages
Japanese (ja)
Other versions
JPH06158632A (en
Inventor
進 村上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP33241992A priority Critical patent/JP2709433B2/en
Publication of JPH06158632A publication Critical patent/JPH06158632A/en
Application granted granted Critical
Publication of JP2709433B2 publication Critical patent/JP2709433B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は埋立地や造成地等の軟弱
地盤の改良用シート材、或いは、盛土や切土の地盤補強
用シート材を該地盤中に水平に埋設する方法に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for burying a sheet material for improving soft ground such as a landfill or a landfill, or a sheet material for reinforcing a ground such as embankment or cut soil in the ground horizontally. is there.

【0002】[0002]

【従来の技術】従来から、例えば軟弱地盤を改良するた
めのドレーン材の敷設方法としては、軟弱地盤中にドレ
ーン材を垂直に敷設する方法と水平に敷設方法とが実施
されているが、水平方向にドレーン材を敷設する方が地
盤の圧密効果が期待できて好ましいものであり、又、盛
土地盤や切土地盤の斜面部分の補強においても、補強用
のシート材を地盤中に水平層状に埋設することにより、
該地盤の安定化や支持力の増大を図ることができる。
2. Description of the Related Art Conventionally, as a method of laying drain materials for improving soft ground, for example, a method of vertically laying drain materials in soft ground and a method of laying horizontally have been practiced. Laying drain material in the direction is preferable because the effect of consolidation of the ground can be expected, and also in reinforcing the slope part of embankment ground and cutting ground, the reinforcing sheet material is formed in a horizontal layer in the ground. By burying,
The ground can be stabilized and the supporting force can be increased.

【0003】このようにシート材を地中に水平埋設する
方法としては、埋設範囲の地盤を根切りしたのちシート
材を敷設し、シート材層と土層とを互層に形成する方法
が採用されている。又、盛土や切土等の地山地盤の斜面
部に補強用のシート材を埋設する方法としては、例え
ば、特開平1ー190825号公報に開示されているよ
うに、チエーンソーや鋸体を使用して斜面から地盤に向
かって一定幅、一定長さの帯状切削溝を水平方向に削成
したのち、該溝内にシート材を挿入することが行われて
いる。
As a method of burying the sheet material horizontally in the ground, a method of cutting the ground in the buried area, laying the sheet material, and forming the sheet material layer and the soil layer alternately is adopted. ing. Further, as a method of embedding a sheet material for reinforcement on a slope of the ground such as an embankment or cut, a chain saw or a saw body is used as disclosed in, for example, JP-A-1-190825. After a band-shaped cutting groove having a fixed width and a fixed length is cut in the horizontal direction from the slope to the ground, a sheet material is inserted into the groove.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、前者の
方法によれば、根切り工事に多大な労力と時間とを必要
とし、施工上および経済的にも問題があって、従来から
地中の所望深さに達する適宜区域の地盤の改良方法とし
ては適当な方法が開発されていないのが現状である。一
方、後者のように、地山地盤の斜面部に補強用シート材
を埋設する方法では、チエーンソーや鋸体の挿入長さに
は限界があって、斜面周辺部の地盤にシート材を埋設し
得るに止まり、しかも、該シート材を斜面に対してシー
ト幅毎に埋設していくものであるから、斜面の横幅全長
に亘ってシート材を埋設するにはその作業を多数回、繰
り返し行わなければならず、その上、切削溝孔の掘削作
業とシート材挿入作業、鋸体等の引き抜き作業を必要と
して作業が煩雑化するばかりでなく長期間の工期を要す
るという問題点があった。
However, according to the former method, a great deal of labor and time are required for the excavation work, and there are problems in construction and economics. At present, no suitable method has been developed as a method of improving the ground in an appropriate area reaching the depth. On the other hand, in the latter method of embedding the reinforcing sheet material on the slope of the ground, there is a limit to the length of the chain saw or saw body, and the sheet material is embedded in the ground around the slope. In order to embed the sheet material over the entire width of the slope, the work must be repeated many times since the sheet material is buried in the slope every sheet width. In addition, there is a problem in that not only the work for excavating the cutting slot, the work for inserting the sheet material, and the work for pulling out the saw body and the like become complicated, but also a long construction period is required.

【0005】本発明はこのような問題点に鑑みてなされ
たもので、地表面下の軟弱地盤や盛土等の地山地盤の所
望部分にドレーン材や補強材、遮水材等の帯状シート材
を一度で広範囲に亘って能率よく敷設することができる
帯シート材の水平埋設方法を提供することを目的とする
ものである。
The present invention has been made in view of such problems, and a belt-like sheet material such as a drain material, a reinforcing material, and a water-blocking material is provided on a desired portion of a soft ground or an embankment below the ground surface. It is an object of the present invention to provide a method of horizontally burying a band sheet material that can be efficiently laid over a wide range at a time.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明による地盤への帯状シート材の水平埋設方法
は、ワイヤソー等のエンドレスカッターを用いて地盤中
の適宜深さ部分に所望長さ区間に亘って水平溝孔を穿設
して該溝孔内に第1の引込用ロープを水平に挿入する工
程と、エンドレスカッターを該溝孔が拡幅する方向に横
移動させて水平拡幅溝孔を形成する工程と、この水平拡
幅溝孔の他側部内に上記第1の引込用ロープに平行して
第2の引込用ロープを配設する工程と、水平拡幅溝孔の
一端側から地盤外に延出しているこれらの第1、第2引
込用ロープに帯状シート材の先端を連結したのち、水平
拡幅溝孔の他端側から地盤外に延出している第1、第2
引込用ロープを引っ張って、帯状シート材を水平拡幅溝
孔内に引き込み敷設する工程とからなるものである。
In order to achieve the above object, a method for horizontally embedding a belt-like sheet material in the ground according to the present invention uses an endless cutter such as a wire saw to a desired length in the ground to a desired length. Forming a horizontal slot through the section and horizontally inserting a first pull-in rope into the slot, and horizontally moving an endless cutter in a direction in which the slot widens. Forming a hole, arranging a second pull-in rope parallel to the first pull-in rope in the other side of the horizontal widening slot, and ground from one end of the horizontal widening slot. After connecting the tip of the strip-shaped sheet material to these first and second pull-in ropes extending outside, the first and second extending outside the ground from the other end side of the horizontal widening slot.
Pulling the pull-in rope and pulling and laying the belt-like sheet material in the horizontal widening slot.

【0007】又、請求項2に記載した方法は、上記方法
において、エンドレスカッターの横移動による所望幅の
水平拡幅溝孔の形成工程と、該水平拡幅溝孔の両側端に
並設した引込用ロープに溝孔一端側の地盤外で一定幅の
帯状シート材の先端を連結したのち溝孔他端側の地盤外
から引込用ロープ材を引っ張って帯状シート材を水平拡
幅溝孔内に引き込み敷設する工程とを繰り返し行うこと
を特徴とするものである。
According to a second aspect of the present invention, in the above method, a step of forming a horizontal widening slot having a desired width by laterally moving an endless cutter, and a draw-in port provided on both side ends of the horizontal widening slot are provided. After connecting the tip of the band-shaped sheet material of a fixed width to the rope outside the ground at one end of the slot, pull the rope material for pulling in from the outside of the ground at the other end of the slot to draw the band-shaped sheet material into the horizontal widening slot and lay it And the step of performing the above steps repeatedly.

【0008】[0008]

【作用】エンドレスカッターによって改良或いは補強す
べき地盤の所望深さ部分に所望長さ区間に亘って溝孔を
掘削する。この場合、エンドレスカッターを地表面から
所望深さに達するまで地盤を掘削しながら降下させるこ
とによって、溝孔の掘削が行われる。この溝孔の底面に
第1の引込用ロープを挿入すると共に該ロープを溝孔の
両端側から地表面側に延出させておく。さらにエンドレ
スカッターを溝孔底部から横移動させることによって溝
孔を水平方向に拡幅し、その水平拡幅溝孔の拡幅端に上
記第1の引込用ロープに平行する第2の引込用ロープを
配設する。
A slot is excavated in a desired depth section of the ground to be improved or reinforced by an endless cutter over a desired length section. In this case, the excavation of the slot is performed by lowering the endless cutter while excavating the ground until reaching a desired depth from the ground surface. A first pull-in rope is inserted into the bottom surface of the slot, and the rope is extended from both ends of the slot toward the ground surface. Furthermore, the slot is widened in the horizontal direction by moving the endless cutter laterally from the bottom of the slot, and a second pulling rope parallel to the first pulling rope is disposed at the wide end of the horizontal widening slot. I do.

【0009】この水平拡幅溝孔の溝幅は、埋設すべき帯
状シート材の幅寸法と同等あるいはそれ以上であればよ
い。次いで、溝孔の一端側から地盤外に延出させている
これらの第1、第2引込用ロープに帯状シート材の先端
両側部を連結したのち、溝孔の他端側から地盤外に延出
させている第1、第2の引込用ロープを引っ張ると、帯
状シート材はその先端部から拡幅溝孔内に引き込まれ、
該拡幅溝孔内に全長に亘って挿入、敷設されるものであ
る。
The width of the horizontal widening groove may be equal to or greater than the width of the band-shaped sheet material to be embedded. Next, after connecting both ends of the strip-shaped sheet material to the first and second pull-in ropes extending out of the ground from one end of the slot, the ropes extend out of the ground from the other end of the slot. When the first and second pull-in ropes are pulled out, the belt-shaped sheet material is drawn into the widening slot from the tip end thereof,
It is inserted and laid over the entire length in the widening slot.

【0010】このような帯状シート材の埋設方法におい
て、第2の引込用ロープの中間部を帯状シートの先端部
に連結させた状態で拡幅溝孔内に帯状シート材を引き込
むと、該帯状シート材の側端縁に沿って引込用ロープを
拡幅溝孔の側端部に配設しておくことができる。従っ
て、一定幅を有する拡幅溝孔内に帯状シート材を挿入、
敷設したのち、エンドレスカッターを横移動させて該拡
幅溝孔の一側端に水平に連通する次の拡幅溝孔を形成
し、この拡幅溝孔内に次の帯状シート材を引き込む際に
該引込用ロープを第1の引込用ロープとして使用するこ
とができる。そして、この一定幅を有する拡幅溝孔の形
成と、帯状シート材の挿入敷設作業とを順次繰り返し行
うことにより、改良又は補強すべき地盤の所望面積に亘
って一連のシート材を埋設することができるものであ
る。
In such a method of embedding a band-shaped sheet material, when the band-shaped sheet material is drawn into the widening slot with the intermediate portion of the second pull-in rope connected to the leading end of the band-shaped sheet, the band-shaped sheet is A pull-in rope can be arranged along the side edge of the material at the side end of the widening slot. Therefore, the band-shaped sheet material is inserted into the widened slot having a certain width,
After laying, the endless cutter is laterally moved to form a next widened slot horizontally communicating with one end of the widened slot, and when the next strip-shaped sheet material is drawn into the widened slot, the pull-in is performed. Rope can be used as the first pull-in rope. Then, by successively repeating the formation of the widened slot having a certain width and the work of inserting and laying the band-shaped sheet material, it is possible to bury a series of sheet materials over a desired area of the ground to be improved or reinforced. You can do it.

【0011】[0011]

【実施例】次に、本発明の一実施例として、軟弱地盤中
にドレーン材となる帯状シート材を敷設する方法につい
て説明する。まず、図1、図2に示すように、軟弱地盤
Aに一定の長さ間隔を存して互いに平行な側溝1、2を
適宜な溝掘削装置(図示せず)によって所望深さまで掘
削したのち、図2、図3に示すように、両側溝1、2の
一端間の地盤に地表面からチエーンワイヤソー等のエン
ドレスカッター3を巡回駆動しながら水平方向に走行す
るカッター部を地盤中に降下させていくことによって両
端がこれらの側溝1、2の所望深さ部分に連通した狭幅
の溝孔4を掘削する。
Next, as one embodiment of the present invention, a method of laying a band-shaped sheet material serving as a drain material in soft ground will be described. First, as shown in FIG. 1 and FIG. 2, after digging parallel gutters 1 and 2 with a certain length interval in the soft ground A to a desired depth by an appropriate ditch excavator (not shown). As shown in FIG. 2 and FIG. 3, the cutter part which travels in the horizontal direction is lowered into the ground while driving endless cutters 3 such as a chain wire saw from the ground surface on the ground between the two ends of the grooves 1 and 2 on both sides. By drilling, a narrow slot 4 whose both ends communicate with the desired depths of these side grooves 1 and 2 is excavated.

【0012】しかるのち、図4、図5に示すようにエン
ドレスカッター3を僅かに側溝1、2の長さ方向に水平
に横移動させ、その溝孔4の底面に第1の引込用ロープ
5を挿入、配設すると共に該引込用ロープ5を溝孔4の
底面から両側溝1、2を通じて地盤A外である地表面に
延出させておく。なお、溝孔4内にこの引込用ロープ5
を配設するには、地上から該溝孔4内に投入することに
よって行ってもよいが、エンドレスカッター3による溝
孔4の掘削後に、該エンドレスカッター3の適所にロー
プ端を連結したのち、このエンドレスカッター3を一方
の側溝1から他方に側溝2に向かって巡回する方向に駆
動すれば、容易且つ確実に引き込み、配設することがで
きる。
Thereafter, as shown in FIGS. 4 and 5, the endless cutter 3 is slightly moved horizontally in the longitudinal direction of the side grooves 1 and 2, and the first pulling rope 5 is inserted into the bottom of the slot 4. Is inserted and arranged, and the pull-in rope 5 is extended from the bottom surface of the slot 4 to the ground surface outside the ground A through the side grooves 1 and 2. The pull-in rope 5 is inserted into the slot 4.
May be installed by putting into the slot 4 from the ground, but after excavation of the slot 4 by the endless cutter 3, after connecting the rope end to a suitable place of the endless cutter 3, If the endless cutter 3 is driven in a direction in which the endless cutter 3 circulates from one side groove 1 to the other side groove 2, the endless cutter 3 can be easily and reliably pulled in and disposed.

【0013】溝孔4内に対する第1引込用ロープ5の引
き込み配設後、エンドレスカッター3を側溝1、2の他
端側に向かって水平方向に横移動させながら側溝1、2
間の所望深さ部分の地盤Aを掘削することにより、図
6、図7に示すように、該溝孔4を拡幅させて帯状シー
ト材6が引き込み可能な幅を有する拡幅溝孔4aを形成す
る。この拡幅溝孔4aの形成のち、上記と同様に、地上に
おいてエンドレスカッター3の適所に第2の引込用ロー
プ7の先端を連結し、図8、図9に示すように、エンド
レスカッター3を一方の側溝1から他方の側溝2に向か
って巡回、駆動することにより、該第2の引込用ロープ
7を拡幅溝孔4aの掘削端側である他側部に上記第1引込
用ロープ5と平行して配設する。
After the first pull-in rope 5 has been drawn into the slot 4, the endless cutter 3 is horizontally moved toward the other end of the side grooves 1 and 2 while the side grooves 1 and 2 are being moved.
6 and 7, by excavating the ground A at a desired depth portion therebetween, to form a widened slot 4a having a width that allows the strip-shaped sheet material 6 to be drawn in, as shown in FIGS. I do. After the widening slot 4a is formed, similarly to the above, the end of the second pull-in rope 7 is connected to an appropriate position of the endless cutter 3 on the ground, and as shown in FIGS. The second pulling rope 7 is parallel to the first pulling rope 5 on the other side, which is the excavation end side of the widening slot 4a, by circulating and driving from the side groove 1 toward the other side groove 2. And arrange them.

【0014】この第2の引込用ロープ7も第1の引込用
ロープ5と同じく、両側溝1、2を通じて地上側に延出
させておく。また、他方の側溝2から地上に延出させて
いるこれらの両引込用ロープ5、7の先端側は、該側溝
2の開口端近傍に設置した巻取装置8、9に夫々巻き付
ける。
The second pulling rope 7 also extends to the ground side through the grooves 1 and 2 on both sides in the same manner as the first pulling rope 5. The leading ends of the pull-in ropes 5 and 7 extending from the other side groove 2 to the ground are wound around winding devices 8 and 9 installed near the opening ends of the side grooves 2, respectively.

【0015】次いで、一方の側溝1から延出している第
1の引込用ロープ5の他端部と第2の引込用ロープ7の
中間部とを地上において帯状シート材6の先端部両側端
に夫々連結する。この場合、図10、図11に示すように、
帯状シート材6の先端に、先端縁が山形状の掘削刃10a
に形成した固定板10の基端部に設けている細溝形状の凹
部10b 内に帯状シート材6の先端を挿入して挟着、固定
する。固定手段としては、凹部10b の対向内面に帯状シ
ート材6に食い込ませる多数の係止突起(図示せず)を
突設しておき、固定板10の凹部10b を形成する表裏面板
のうち、一方の面板を開閉自在として両面板間に着脱自
在に挟持させる間を挟着させるか、或いは固定板10の表
裏面間に帯状シート材6の先端部を貫通する複数の螺子
等を取付けることによって行うことができる。
Next, the other end of the first pull-in rope 5 extending from the one side groove 1 and the intermediate portion of the second pull-in rope 7 are attached to both ends of the front end of the belt-shaped sheet material 6 on the ground. Connect each one. In this case, as shown in FIGS. 10 and 11,
At the tip of the band-shaped sheet material 6, the tip edge has a mountain-shaped excavating blade 10a.
The distal end of the strip-shaped sheet material 6 is inserted into a narrow groove-shaped concave portion 10b provided at the base end portion of the fixing plate 10 formed as described above, and is clamped and fixed. As the fixing means, a large number of locking projections (not shown) which bite into the strip-shaped sheet material 6 are protruded from the inner surface opposite to the concave portion 10b, and one of the front and back plates forming the concave portion 10b of the fixing plate 10 is provided. This is performed by sandwiching the space between the two side plates so that the front plate can be freely opened and closed, or by attaching a plurality of screws or the like penetrating the tip of the belt-shaped sheet material 6 between the front and back surfaces of the fixed plate 10. be able to.

【0016】また、固定板10の両側端には引込用ロープ
固定筒部10c 、10d が一体的に設けられてあり、一方の
固定筒部10c に第1の引込用ロープ5の端部を挿入状態
で挟着、固定させると共に、他方の固定筒部10d に第2
の引込用ロープ7の中間部を挿通状態で挟着、固定して
ある。さらに、図12に示すように、両側溝1、2に連通
した拡幅溝孔4aの両開口端における側溝1、2の内壁面
と、一方の側溝1の開口上端とに引込用ロープのガイド
ローラ11、12、13を設置しておく。
At both ends of the fixing plate 10, pull-in rope fixing tubular portions 10c and 10d are integrally provided, and one end of the first pull-in rope 5 is inserted into one of the fixing tubular portions 10c. In the fixed state, and the second fixed cylindrical portion 10d
The intermediate portion of the pull-in rope 7 is clamped and fixed in an inserted state. Further, as shown in FIG. 12, the guide rollers of the pull-in ropes are provided on the inner wall surfaces of the side grooves 1 and 2 at both open ends of the widened groove 4a communicating with both side grooves 1 and 2 and the upper end of the opening of one side groove 1. Install 11, 12, and 13 in advance.

【0017】この状態で、他方の側溝2側の地上に設置
している上記両巻取装置8、9を駆動して引込用ロープ
5、7を巻き取っていくと、その巻き取りに従って帯状
シート材6の先端が図13に示すように、一方の側溝1の
上端開口部から該側溝1内に引き込まれたのち、拡幅溝
孔4aの一端開口部から該拡幅溝孔4a内を挿通し、他方の
側溝2から巻取装置8、9側にまで移動して帯状シート
材6が拡幅溝孔4a内に水平状態で敷設されると共に両側
溝1、2を通じて地上側に引き出されて状態となる。こ
の際、帯状シート材6の先端に固着している固定板10が
帯状シート材6に先行するようにして移動し、その山形
状の先端掘削刃10a によって拡幅溝孔4a内に存在する土
砂等を排除しながら帯状シート材6の引き込みが円滑に
行われるものである。
In this state, when the above-mentioned winding devices 8 and 9 installed on the ground on the side of the other side groove 2 are driven to wind the pull-in ropes 5 and 7, the belt-shaped sheet is wound according to the winding. As shown in FIG. 13, after the tip of the material 6 is drawn into the side groove 1 from the upper end opening of the one side groove 1, it is inserted through the widening groove 4a from the one end opening of the widening groove 4a. The belt-like sheet material 6 moves from the other side groove 2 to the winding devices 8 and 9 side, is laid horizontally in the widening slot 4a, and is pulled out to the ground side through both side grooves 1 and 2 to be in a state. . At this time, the fixing plate 10 fixed to the leading end of the band-shaped sheet material 6 moves so as to precede the band-shaped sheet material 6, and the soil or the like existing in the widening slot 4a by the mountain-shaped leading edge excavating blade 10a. , And the strip-shaped sheet material 6 is smoothly drawn in.

【0018】こうして、一定幅の帯状シート材6を拡幅
溝孔4a内に敷設したのち、その先端に固着している固定
板10を帯状シート材6の先端から取り外すと共に拡幅溝
孔4aから一方の側溝1側に延長している帯状シート材6
の適所を切断し、その切断端に固定板10を取付けて次の
敷設に備える。また、上記帯状シート材6の引き込み作
業中に再びエンドレスカッター3を駆動しながら水平方
向に横移動させて上記拡幅溝孔4aに連続して帯状シート
材6が挿入可能な幅を有する拡幅溝孔4bを掘削する。な
お、エンドレスカッター3によって地盤に溝孔を掘削す
る際に、水をエンドレスカッター3に供給しながら行
う。この供給は、エンドレスカッター3の適宜箇所に水
を吹き付け等によって付与すれば、エンドレスカッター
3に水が付着した状態で巡回する。
After the band-shaped sheet material 6 having a constant width is laid in the widening slot 4a, the fixing plate 10 fixed to the end thereof is removed from the front end of the band-shaped sheet material 6, and one of the fixing plates 10 is removed from the widening slot 4a. Strip-shaped sheet material 6 extending to the side groove 1
Is cut in place and the fixed plate 10 is attached to the cut end to prepare for the next laying. Further, during the operation of pulling in the band-shaped sheet material 6, the endless cutter 3 is again moved in the horizontal direction while being driven so as to be continuously moved in the horizontal direction so that the band-shaped sheet material 6 can be inserted into the widened groove 4a. Drill 4b. In addition, when excavating a slot in the ground by the endless cutter 3, water is supplied to the endless cutter 3. If this supply is provided by spraying water on an appropriate portion of the endless cutter 3 or the like, the endless cutter 3 circulates in a state where water is attached to the endless cutter 3.

【0019】この拡幅溝孔4bの掘削後、その掘削端側の
溝孔他側部内に上記同様にして引込用ロープ7aを挿入、
配設し、この引込用ロープ7aの中間部と上記第2引込用
ロープ7の端部とを帯状シート材6の先端固定板10の両
側端固定筒部10c 、10d に夫々挿着し、第1引込用ロー
プ5の巻取装置8を引込用ロープ7aの巻取用として移設
したのち、両巻取装置8、9を駆動することにより拡幅
溝孔4a内に帯状シート材6を挿通状態に敷設するもので
ある。
After the widening slot 4b is excavated, the pull-in rope 7a is inserted into the other end of the excavation end side in the same manner as described above.
The intermediate portion of the pull-in rope 7a and the end of the second pull-in rope 7 are respectively inserted into both end fixed cylindrical portions 10c and 10d of the end fixing plate 10 of the belt-shaped sheet material 6, and (1) After the winding device 8 of the pull-in rope 5 is transferred for winding the pull-in rope 7a, the band-shaped sheet material 6 is inserted into the widening slot 4a by driving both the winding devices 8, 9. It is to be laid.

【0020】このように、両側溝1、2の長さ方向に沿
って、地表面から地中の所望の深さ位置に配設している
エンドレスカッター3を帯状シート材6が敷設可能な一
定距離毎に横移動させて拡幅溝孔4a、4b・・・を順次掘
削、形成していく工程と、その形成に従って、帯状シー
ト材6の先端を一対の引込用ロープによって引っ張りな
がら拡幅溝孔4a、4b・・・に順次該帯状シート材6を引
き込み埋設する工程とを繰り返し行って両側溝1、2間
における所望深さ位置の地盤中にドレーン材としての一
連の水平帯状シート材6、6・・・を敷設するものであ
る。
As described above, the endless cutter 3 disposed at a desired depth from the ground surface to the ground along the length direction of the side grooves 1 and 2 can be laid on the strip-shaped sheet material 6. .. Are successively excavated and formed by laterally moving each distance, and in accordance with the formation, the widening slots 4a are pulled while pulling the tip of the strip-shaped sheet material 6 with a pair of pull-in ropes. , 4b... Are successively drawn and buried, and a series of horizontal belt-like sheet materials 6, 6 as drain materials are placed in the ground at a desired depth position between the side grooves 1, 2. ... is laid.

【0021】また、その敷設状態もエンドレスカッター
3の配設深さ位置を順次代えることによって、図15に示
すように、地盤A中に多層の水平帯状シート材6よりな
るドレーン層を形成することができる。なお、帯状シー
ト材6の両端は、図16に示すように両側溝1、2に達す
る長さに切断しておいてもよい。このようにしてドレー
ン材となる水平帯状シート材6を改良すべき地中に埋設
したのち、盛土14の載荷荷重等により地盤Aを圧密させ
るものである。
In addition, as shown in FIG. 15, a drain layer composed of a multi-layered horizontal band-shaped sheet material 6 is formed in the ground A by sequentially changing the installation depth position of the endless cutter 3 in the laid state. Can be. Incidentally, both ends of the belt-shaped sheet material 6 may be cut to a length reaching the side grooves 1 and 2 as shown in FIG. After the horizontal strip-shaped sheet material 6 serving as the drain material is buried in the ground to be improved in this way, the ground A is compacted by the load of the embankment 14 or the like.

【0022】次に、図17、図18は、上記エンドレスカッ
ター3を横移動させて地盤中の所望深さ部分に水平拡幅
溝孔4a、4bを掘削可能とした装置の具体例を示すもの
で、両側溝1、2の内壁面上端部にこれらの側溝1、2
の長さ方向に水平ガイドレール15、16を固定すると共に
これらの水平ガイドレール15、16に両側移動架台17、18
を水平移動自在に取付け、該移動架台17、18に回転自在
に軸支している複数個のガイドプーリ20〜23に地上に配
設したワイヤソーからなるエンドレスカッター3の駆動
装置24を介してエンドレスカッター3を掛け渡してなる
ものである。
Next, FIGS. 17 and 18 show a specific example of an apparatus in which the endless cutter 3 is laterally moved so that horizontal widening slots 4a and 4b can be excavated at a desired depth in the ground. , These side grooves 1, 2
The horizontal guide rails 15, 16 are fixed in the length direction of the
Is mounted on a plurality of guide pulleys 20 to 23 rotatably supported on the movable bases 17 and 18 through a drive device 24 of an endless cutter 3 comprising a wire saw disposed on the ground. It is obtained by hanging the cutter 3.

【0023】即ち、エンドレスカッター3は、駆動装置
24から両側移動架台17、18の前端上面に軸支されている
プーリ20、20に掛け渡したのち、両側移動架台17、18の
外側面上下部に軸支されたプーリ21、22に掛け渡され、
さらに、後端下面に軸支されたプーリ23、23間に掛け渡
されているもので、このプーリ23、23間を走行するエン
ドレスカッター3部分によって地中に上記拡幅溝孔4a、
4b・・・を掘削するものである。
That is, the endless cutter 3 is a driving device.
After being extended from 24 to pulleys 20 and 20 which are pivotally supported on the front end upper surfaces of the both-side movable frames 17 and 18, are extended to pulleys 21 and 22 which are pivotally supported on the upper and lower outer surfaces of the both-side movable frames 17 and 18. And
Further, the endless cutter 3 running between the pulleys 23 and 23 is extended between the pulleys 23 and 23 pivotally supported on the rear end lower surface.
4b ... is to be excavated.

【0024】拡幅溝孔4aを掘削するに先立って、上述し
たように、その拡幅溝孔4aの深さまで垂直な溝孔4を掘
削しなければならないが、この掘削は水平ガイドレール
15、16や移動架台17、18の配設前に、エンドレスカッタ
ー3を駆動しながら地表面から降下させてその水平走行
部により掘削すればよい。この溝孔4の掘削後、駆動装
置24によってエンドレスカッター3を一方向に巡回走行
させると共に両側移動架台17、18をガイドレール15、16
に沿って適宜な駆動手段を介して積極的に移動させ、そ
れに同調させて駆動装置24も地上でガイドレール等を介
して同一方向に移動させる。また、両側移動架台17、18
に配設している上下プーリ20、23間の長さを適宜に変更
することによって、その長さに応じた深さ位置に拡幅溝
孔を掘削し得るものである
Prior to excavating the widening slot 4a, as described above, the vertical slot 4 must be excavated to the depth of the widening slot 4a.
Before the disposition of the movable frames 15, 16 and the movable frames 17, 18, the endless cutter 3 may be driven down from the ground surface and excavated by the horizontal traveling portion. After the excavation of the slot 4, the endless cutter 3 is circulated in one direction by the driving device 24 and the both-side movable mounts 17 and 18 are moved by the guide rails 15 and 16.
Is moved positively along appropriate driving means along with, and the driving device 24 is also moved in the same direction on the ground via a guide rail or the like in synchronization therewith. In addition, the two-sided mobile mounts 17, 18
By appropriately changing the length between the upper and lower pulleys 20 and 23 provided in the above, a widening slot can be excavated at a depth position corresponding to the length.

【0025】以上の実施例においては、軟弱地盤中に地
上からドレーン材としての帯状シート材6を層状に埋設
する方法について説明したが、同様な方法によって盛土
内に補強用の帯状シート材26を埋設することができる。
即ち、図19は盛土Bの両側部に全長に亘って複数層の補
強用帯状シート材26を埋設してなる断面図、図20はその
側面図を示すものであって、このような補強用帯状シー
ト材26を埋設するには、まず、盛土Bから底面に達する
側溝31を全長に亘って掘削する。この場合、上記実施例
においては適宜間隔を存して両側溝1、2を掘削した
が、盛土Bの側面は空間に露出しているので、他方には
側溝を設けることなく該空間を利用する。
In the above embodiment, the method of embedding the strip-shaped sheet material 6 as a drain material in a layered manner from the ground in the soft ground has been described, but the strip-shaped sheet material 26 for reinforcement is embedded in the embankment by the same method. Can be buried.
That is, FIG. 19 is a cross-sectional view in which a plurality of layers of reinforcing strip-like sheet members 26 are embedded on both sides of the embankment B over the entire length, and FIG. In order to embed the band-shaped sheet material 26, first, a trench 31 extending from the embankment B to the bottom surface is excavated over the entire length. In this case, in the above embodiment, the side grooves 1 and 2 are excavated at appropriate intervals. However, since the side surface of the embankment B is exposed to the space, the space is used without providing the other side groove. .

【0026】それ以後の工程は上記実施例と同様であ
り、盛土Bの一端部において、盛土Bの斜面Cと該側溝
31との間にエンドレスカッター3で拡幅溝孔を掘削した
のち、該拡幅溝孔の両端縁に引込用ロープを並設し、該
引込用ロープの一端側を巻き取ることによって他端側に
連結している帯状シート材26を拡幅溝孔内に引き込み埋
設し、これを盛土Bの長さ方向に順次繰り返す行うもの
である。同様に、盛土Bの他側面側の地盤においても、
側溝32を掘削して該側溝32と他側面との間の地盤中に帯
状シート材26を埋設することができる。また、この方法
を利用して切土に地盤補強用帯状シート材の埋設も行う
ことができるものである。
The subsequent steps are the same as those in the above embodiment. At one end of the embankment B, the slope C of the embankment B and the gutter are used.
After the widening slot is excavated with the endless cutter 3 in between, the pull-in ropes are juxtaposed at both ends of the widening slot, and one end of the pull-in rope is wound up and connected to the other end. The strip-shaped sheet material 26 is drawn and buried in the widening slot, and this is sequentially repeated in the length direction of the embankment B. Similarly, in the ground on the other side of the embankment B,
By excavating the side groove 32, the band-shaped sheet material 26 can be embedded in the ground between the side groove 32 and the other side surface. In addition, it is possible to embed a ground reinforcing band-like sheet material in a cut by using this method.

【0027】なお、軟弱地盤中に埋設するドレーン材と
しての帯状シート材6としては、ペーパドレーン、プラ
スチックドレーン、ジオテキスタイル等があり、盛土等
の地盤補強用帯状シート材26としては、鋼板、鋼網、パ
ンチングメタル、ジオテキスタイル、その他、合成樹脂
帯状材等を使用することができる。また、本発明によれ
ば、地中に遮水壁となる帯状シート材を埋設することも
できる。さらに、上記のような補強用帯状シート材や遮
水壁形成用帯状シート材等を埋設する方法において、両
側溝1、2内に泥水等の安定液を充満させておけば、両
側溝1、2の掘削面に安定液の膜層が形成されて溝の崩
壊を防止できるものであり、同様に、エンドレスカッタ
ー3による溝孔掘削時に、泥水等の安定液を供給すれ
ば、溝孔の掘削面を安定液の膜層によって保護すること
ができ、帯状シート材が円滑に挿通し得る溝孔が形成で
きるものである。
The belt-shaped sheet material 6 as a drain material buried in the soft ground includes paper drain, plastic drain, geotextile, and the like. , Punched metal, geotextile, and other synthetic resin strips. Further, according to the present invention, it is possible to bury a belt-like sheet material serving as a water impervious wall in the ground. Further, in the method of embedding the reinforcing strip-shaped sheet material or the impermeable wall-forming strip-shaped sheet material as described above, if both sides grooves 1 and 2 are filled with a stable liquid such as muddy water, the two side grooves 1 2, a stable liquid film layer is formed on the excavation surface to prevent collapse of the groove. Similarly, when a stable liquid such as muddy water is supplied when the endless cutter 3 excavates the groove, the excavation of the groove is performed. The surface can be protected by a film layer of a stabilizing liquid, and a slot can be formed through which the belt-shaped sheet material can be smoothly inserted.

【0028】[0028]

【発明の効果】以上のように本発明によれば、地盤の適
宜深さ部分を一定長さ区間に亘ってエンドレスカッター
により溝孔を掘削すると共に該エンドレスカッターを横
移動させることにより拡幅溝孔を形成し、この拡幅溝孔
の両側端に引込用ロープを配設して地盤外に延出したこ
れらの引込用ロープに地盤改良用又は補強用の帯状シー
ト材を連結したのち、引込用ロープの先端を地盤外から
引っ張ることにより帯状シート材を拡幅溝孔内に引き込
み埋設するものであるから、従来のような根切り工事な
どの煩雑な作業を排して地盤の所望深さ部分に能率よく
帯状シート材を水平状態に埋設することができると共
に、長尺の帯状シート材を該拡幅溝孔内に挿入するもの
であるから、拡幅溝孔の長さの大小に拘わらず、該拡幅
溝孔内に帯状シート材を確実に埋設させることができ、
一度で広範囲に亘ってシート材の水平埋設作業が可能と
なるものである。
As described above, according to the present invention, an appropriate depth portion of the ground is excavated by an endless cutter over a predetermined length section, and the endless cutter is laterally moved to widen the slot. After connecting the pull-in ropes on both sides of the widening slot and connecting the strip-like sheet material for ground improvement or reinforcement to these pull-in ropes extending out of the ground, the pull-in ropes The belt-like sheet material is pulled into the widening slot by embedding the tip of the ground from the outside of the ground, and buried in it. Since the strip-shaped sheet material can be buried in a horizontal state well, and the long strip-shaped sheet material is inserted into the widening slot, the widening groove can be used regardless of the length of the widening slot. Belt sheet in the hole It can be reliably embedded,
The sheet material can be buried horizontally over a wide area at one time.

【0029】さらに、拡幅溝孔はワイヤーソー等のエン
ドレスカッターによって切削、形成されるものであるか
ら、軟弱地盤は勿論、比較的硬質の地盤であっても円滑
に掘削し得るものであり、その上、該エンドレスカッタ
ーを水平方向に横移動させるので、一定幅を有する拡幅
溝孔を順次、連続的に精度よく形成することができて該
拡幅溝孔に応じた幅を有する帯状シート材の挿入、敷設
作業が容易に行えるものである。又、拡幅溝孔に対する
帯状シート材の敷設作業に先行しながらエンドレスカッ
ターの横移動による次の拡幅溝孔の掘削作業を行うこと
ができるので、作業性並びに施工性が向上して工期の短
縮を図ることができるものである。
Furthermore, since the widened slot is cut and formed by an endless cutter such as a wire saw, it is possible to excavate not only soft ground but also relatively hard ground smoothly. Since the endless cutter is moved horizontally in the horizontal direction, widened slots having a constant width can be sequentially and accurately formed, and a strip-shaped sheet material having a width corresponding to the widened slots can be inserted. And laying work can be easily performed. In addition, the excavation work of the next widening slot by the lateral movement of the endless cutter can be performed before the work of laying the band-shaped sheet material in the widening slot, so that workability and workability are improved, and the construction period is shortened. It can be planned.

【図面の簡単な説明】[Brief description of the drawings]

【図1】地盤に掘削した側溝の縦断正面図、FIG. 1 is a longitudinal sectional front view of a gutter excavated in the ground,

【図2】その平面図、FIG. 2 is a plan view thereof,

【図3】ワイヤーソーによる溝孔掘削状態を示す断面
図、
FIG. 3 is a cross-sectional view showing a state of excavation of a slot by a wire saw;

【図4】第1の引込用ロープを配設している状態を示す
平面図、
FIG. 4 is a plan view showing a state where a first pull-in rope is provided.

【図5】その縦断側面図、FIG. 5 is a longitudinal side view thereof,

【図6】拡幅溝孔の形成工程を示す平面図、FIG. 6 is a plan view showing a step of forming a widened slot;

【図7】その縦断側面図、FIG. 7 is a longitudinal side view thereof,

【図8】拡幅溝孔の他側端に引込用ロープを配設する状
態を示す平面図、
FIG. 8 is a plan view showing a state in which a pull-in rope is provided at the other end of the widening slot.

【図9】その縦断側面図、FIG. 9 is a longitudinal side view thereof,

【図10】引込用ロープと帯状シート材との連結部を示
す平面図、
FIG. 10 is a plan view showing a connecting portion between the pull-in rope and the belt-shaped sheet material,

【図11】その縦断正面図、FIG. 11 is a longitudinal sectional front view thereof,

【図12】ガイドローラ配設部の縦断正面図、FIG. 12 is a vertical front view of a guide roller disposition portion,

【図13】帯状シート材の引込工程を示す平面図、FIG. 13 is a plan view showing a drawing process of the band-shaped sheet material,

【図14】その縦断側面図、FIG. 14 is a longitudinal side view thereof,

【図15】地盤中に帯状シート材を複数層、埋設した状
態の縦断正面図、
FIG. 15 is a longitudinal sectional front view of a state in which a plurality of layers of a belt-like sheet material are buried in the ground,

【図16】その変形例を示す縦断正面図、FIG. 16 is a longitudinal sectional front view showing a modified example thereof;

【図17】拡幅溝孔の掘削装置を示す簡略縦断正面図、FIG. 17 is a simplified vertical sectional front view showing an excavating device for a widened slot;

【図18】その平面図、FIG. 18 is a plan view thereof,

【図19】盛土に補強用帯状シート材を埋設した状態の
縦断正面図、
FIG. 19 is a longitudinal sectional front view showing a state in which a reinforcing band-like sheet material is embedded in an embankment;

【図20】その側面図。FIG. 20 is a side view thereof.

【符号の説明】[Explanation of symbols]

1、2 側溝 3 エンドレスカッター 4 溝孔 4a、4b 拡幅溝孔 5、7 引込用ロープ 6 帯状シート材 1, 2 side groove 3 endless cutter 4 slot 4a, 4b widening slot 5, 7, pull-in rope 6 belt-shaped sheet material

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 ワイヤソー等のエンドレスカッターを用
いて地盤中の適宜深さ部分に所望長さ区間に亘って溝孔
を穿設して該溝孔内に第1の引込用ロープを水平に挿入
する工程と、エンドレスカッターを該溝孔が拡幅する方
向に横移動させて水平拡幅溝孔を形成する工程と、この
水平拡幅溝孔の他側部内に上記第1の引込用ロープに平
行して第2の引込用ロープを配設する工程と、水平拡幅
溝孔の一端側から地盤外に延出しているこれらの第1、
第2引込用ロープに帯状シート材の先端を連結したの
ち、水平拡幅溝孔の他端側から地盤外に延出している第
1、第2引込用ロープを引っ張って、帯状シート材を水
平拡幅溝孔内に引き込み敷設する工程とからなることを
特徴とする地盤への帯状シート材の水平埋設方法。
1. Using an endless cutter such as a wire saw, a slot is drilled at an appropriate depth in the ground over a desired length section, and a first pull-in rope is horizontally inserted into the slot. Forming a horizontal widening slot by laterally moving the endless cutter in the direction in which the slot widens, and in the other side of the horizontal widening slot parallel to the first pull-in rope. Arranging a second pull-in rope; and first and second extending ropes extending from one end of the horizontal widening slot to the outside of the ground.
After connecting the tip of the strip-shaped sheet material to the second pull-in rope, the first and second pull-in ropes extending out of the ground from the other end side of the horizontal widening slot are pulled to horizontally widen the strip-shaped sheet material. And laying the belt-shaped sheet material in a slot.
【請求項2】 エンドレスカッターの横移動による所望
幅の水平拡幅溝孔の形成工程と、該水平拡幅溝孔の両側
端に並設した引込用ロープに溝孔一端側の地盤外で一定
幅の帯状シート材の先端を連結したのち溝孔他端側の地
盤外から引込用ロープ材を引っ張って帯状シート材を水
平拡幅溝孔内に引き込み敷設する工程とを繰り返し行う
ことを特徴とする請求項1記載の地盤への帯状シート材
の水平埋設方法。
2. A step of forming a horizontal widening slot having a desired width by lateral movement of an endless cutter, and a pulling rope provided side by side at both ends of the horizontal widening slot having a predetermined width outside the ground at one end side of the slot. A step of connecting the leading end of the strip-shaped sheet material, and then pulling the pull-in rope material from outside the ground at the other end side of the slot, drawing the strip-shaped sheet material into the horizontal widening slot, and laying the same. The method for horizontally burying a belt-shaped sheet material in the ground according to claim 1.
JP33241992A 1992-11-17 1992-11-17 Horizontal embedding method of strip-shaped sheet material in the ground Expired - Fee Related JP2709433B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33241992A JP2709433B2 (en) 1992-11-17 1992-11-17 Horizontal embedding method of strip-shaped sheet material in the ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33241992A JP2709433B2 (en) 1992-11-17 1992-11-17 Horizontal embedding method of strip-shaped sheet material in the ground

Publications (2)

Publication Number Publication Date
JPH06158632A JPH06158632A (en) 1994-06-07
JP2709433B2 true JP2709433B2 (en) 1998-02-04

Family

ID=18254762

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33241992A Expired - Fee Related JP2709433B2 (en) 1992-11-17 1992-11-17 Horizontal embedding method of strip-shaped sheet material in the ground

Country Status (1)

Country Link
JP (1) JP2709433B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101638479B1 (en) * 2014-07-04 2016-07-11 이근호 Construction method for underground structure

Also Published As

Publication number Publication date
JPH06158632A (en) 1994-06-07

Similar Documents

Publication Publication Date Title
US10232292B2 (en) Method and apparatus for placement of a subterranean curtain below the face of the earth
JP2709433B2 (en) Horizontal embedding method of strip-shaped sheet material in the ground
WO1992021826A1 (en) Wire saw excavator, cut-off wall or landslide protection construction constructed thereby and construction method thereof
CN115992519A (en) Excavation method and excavation device for hard rock layer of foundation pit
US6948886B1 (en) System and method for preventing bluff erosion
KR101430426B1 (en) Installation apparatus for fiber sheet, construction machine having the same and installation method for fiber sheet
JP3248146B2 (en) Construction method of impermeable wall
JPH08319618A (en) Civil engineering equipment, excavating equipment, earth retaining equipment, and civil engineering method
JP2879116B2 (en) Construction method and construction device of water stop wall
JPS5920820B2 (en) Method for creating trenches for underground walls
JP2002201632A (en) Water-impervious retaining wall with groundwater flow protection function and its groundwater flow protection method
JP3427644B2 (en) Underground diaphragm wall construction equipment
JP3773386B2 (en) Construction method of underground continuous wall in boulder intervening ground
JPH0621453B2 (en) Construction method of continuous underground wall
JP2876274B2 (en) Pipe burial method and apparatus
JPH10280396A (en) Construction method of continuos underground water shielding wall with water shielding sheet embedded therein and continuos underground shielding wall structure with water shielding sheet spread therein
JPH0574647B2 (en)
JP2002167754A (en) Water blocking wall below culvert and method of construction
JP2010133247A (en) Reaction device
JP4961155B2 (en) Drilling device and pile burying method
JP4504166B2 (en) Reaction force device
JP3178319B2 (en) Underground installation method of bottom impermeable structure and bottom impermeable structure
JPH09228378A (en) Water-stop wall construction method and excavation equipment used in the method
JP3926818B2 (en) Installation method of concrete box
JPH0771036A (en) Vertical slope construction method