JP2782283B2 - Manhole cover height adjustment method - Google Patents
[go: Go Back, main page]

JP2782283B2 - Manhole cover height adjustment method - Google Patents

Manhole cover height adjustment method

Info

Publication number
JP2782283B2
JP2782283B2 JP2313370A JP31337090A JP2782283B2 JP 2782283 B2 JP2782283 B2 JP 2782283B2 JP 2313370 A JP2313370 A JP 2313370A JP 31337090 A JP31337090 A JP 31337090A JP 2782283 B2 JP2782283 B2 JP 2782283B2
Authority
JP
Japan
Prior art keywords
height
receiving frame
block
manhole
lid receiving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2313370A
Other languages
Japanese (ja)
Other versions
JPH04185827A (en
Inventor
民朗 富樫
康弘 柳岡
宣勝 池
謙二 大島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Gas Co Ltd
Original Assignee
Tokyo Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Gas Co Ltd filed Critical Tokyo Gas Co Ltd
Priority to JP2313370A priority Critical patent/JP2782283B2/en
Publication of JPH04185827A publication Critical patent/JPH04185827A/en
Application granted granted Critical
Publication of JP2782283B2 publication Critical patent/JP2782283B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、道路下等に敷設されたガス管路等の経路に
設置されているマンホールの口蓋を、路面レベルに対応
する高さに嵩上げするマンホールの蓋高さ調整工法に関
する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention raises a palate of a manhole installed on a route such as a gas pipeline laid under a road or the like to a height corresponding to a road surface level. To adjust the height of the manhole cover.

〔従来の技術〕[Conventional technology]

従来、この種のマンホールの蓋高さ調整工法として実
施されている工法は、マンホール本体の上部に接合され
た中蓋ブロックを基盤として、その上に、調整する嵩上
げ高さに対応して、 .予め用意された各種高さの調整ブロックの中から、
所要高さの調整ブロックを単数または複数組合せ選択し
て、これを中蓋ブロックの上面にインサートされている
埋込ボルトに挿通して所要高さに積み重ね、 .その上に、微調整用として所要厚さの鉄片ライナー
を単数または複数,選択してこれを上段の調整ブロック
と、その上に載置させる蓋受枠との間に介在させること
によりマンホール口蓋の蓋受枠を、その上面が調整する
路面高さに対応する関係に位置合せし、 .その位置合せ後、再度,蓋受枠を取外して鉄片ライ
ナーを介在させた微調整間隙部の平面内に必要量のモル
タル(セメント・レジン)を敷き、 ,再び蓋受枠を載せ、その蓋受枠のフランジに設けた
ボルト孔を埋込ボルトの頭部に嵌合してナットにて締付
け固定するように施工してなるものである。
Conventionally, this type of manhole cover height adjustment method is based on an inner cover block joined to the upper part of the manhole body, and further, on the base, corresponding to the raised height to be adjusted. From the prepared adjustment blocks of various heights,
Selecting one or a plurality of adjustment blocks of the required height, inserting them into embedded bolts inserted into the upper surface of the inner lid block, and stacking them at the required height; On top of that, one or more iron piece liners of the required thickness are selected for fine adjustment, and this is interposed between the upper adjustment block and the lid receiving frame to be placed thereon, so that the manhole cover Positioning the receiving frame in a relationship whose upper surface corresponds to the road surface height to be adjusted; After the alignment, remove the lid receiving frame again, spread the required amount of mortar (cement resin) in the plane of the fine adjustment gap with the iron piece liner interposed, put the lid receiving frame again, and place the flange on the lid receiving frame. The bolt holes provided in the above are fitted to the heads of the embedded bolts and tightened and fixed with nuts.

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

このような従来の調整工法では、次に説明する問題点
があった。
Such a conventional adjustment method has the following problems.

まず嵩上げ用として中蓋ブロックの上に積み重ねる調
整ブロックは、これが、基盤となる中蓋ブロックに立設
された埋込ボルトに貫通されてはいるものの、その嵌合
はルーズに貫通されているだけなので、調整ブロック
は、マンホール口蓋の上を通行する車両荷重や,地震,
路面の温度変化等により影響を受ける水平方向,垂直方
向の荷重に対してブロック相互間に位置ズレが起り易
く、これによりガタ付きが発生し、また調整ブロックの
位置ズレにより積み重ね状態も変化して路面との間に段
差を生じる現象が派生する。
First, although the adjustment block stacked on the inner lid block for raising is penetrated by the embedded bolt erected on the inner lid block serving as the base, its fitting is only loosely penetrated Therefore, the adjustment block is used for vehicle load passing over the manhole palate, earthquake,
Horizontal and vertical loads, which are affected by changes in the temperature of the road surface, are likely to cause misalignment between the blocks, resulting in rattling and a change in the position of the adjustment block, which may alter the stacking condition. A phenomenon that causes a step with the road surface is derived.

また微調整用として介在される鉄片ライナーについて
も、これは、埋込ボルトに螺合されるナットの締付けで
固定されてはいるものの、ナットが上述のマンホール口
蓋上を通行する車両荷重等により振動を受けて緩んだ
際、鉄片ライナーも位置ズレを起して落ち込み、路面と
の間に段差を生じる現象も派生する。
Also, the iron piece liner interposed for fine adjustment is fixed by tightening the nut screwed to the embedded bolt, but the nut vibrates due to the vehicle load passing over the manhole cover described above. When loosened due to the impact, the iron piece liner also shifts in position and falls, causing a phenomenon that a step is formed between the liner and the road surface.

さらにナットによる締付け部は、これが上述の振動で
緩み易く、これにより蓋受枠が早期にガタ付いて車両通
行の際などにガタつき音を発するという問題点もある。
Further, there is a problem that the tightening portion by the nut is easily loosened due to the above-mentioned vibration, whereby the lid receiving frame rattles early and generates a rattling sound when the vehicle passes.

加えて微調整用として鉄片ライナーを介在する工法な
ので、鉄片ライナーの介在作業に手間がかかり、作業性
が悪く、嵩上げ工事に時間を要してコスト高となる問題
点もあった。
In addition, since the iron piece liner is interposed for fine adjustment, the work of interposing the iron piece liner is troublesome, the workability is poor, and there is a problem that time is required for the raising work and the cost is increased.

本発明は、上述の問題点を解消したマンホールの嵩高
さ調整工法を提供することを目的とするものである。
An object of the present invention is to provide a method for adjusting the bulkiness of a manhole, which solves the above-mentioned problems.

〔課題を解決するための手段〕[Means for solving the problem]

この目的を達成するため、本発明による調整工法は、
道路下に埋設されているマンホール本体の上部に中蓋ブ
ロックが接合され、該中蓋ブロックを基盤として上方に
固定されるマンホール口蓋の蓋受枠を路面レベルに対応
する高さに嵩上げ調整するに際し、 中蓋ブロックの上面に、調整する嵩上げ高さに対応し
て、所定高さ寸法を有する単数または複数の調整ブロッ
クを、中蓋ブロックの上面にインサートされた埋込ボル
トに貫通して積み重ね、その上に、埋込ボルトに挿通し
たコイルばねにより所要の微調整空間をあけて蓋受枠
を、上方からナットの締付けにより間隔調整することで
蓋受枠の上面を路面レベルに対応した高さに位置合せ
し、 その位置合せ後に、中蓋ブロックと蓋受枠との間のマ
ンホール内側,外側に内枠,外枠を嵌着して上記微調整
空間および調整ブロックによる嵩上げ調整部の内側,外
側を密閉させ、この密閉状態で、その外枠と蓋受枠との
間より流動性を有する樹脂モルタルを、埋込ボルトのナ
ット締付け部を覆う高さ位置まで注入充填させて硬化す
るように施工することを特徴とする。
To achieve this object, the adjustment method according to the present invention is:
An inner lid block is joined to the upper part of the manhole body buried under the road, and when adjusting the height of the lid receiving frame of the manhole palate fixed upward based on the inner lid block to a height corresponding to the road surface level, On the upper surface of the inner lid block, corresponding to the raised height to be adjusted, one or more adjusting blocks having a predetermined height dimension are stacked by penetrating the embedding bolts inserted on the upper surface of the inner lid block, and The top of the lid receiving frame is adjusted to the height corresponding to the road surface level by adjusting the distance of the lid receiving frame by tightening nuts from above, leaving a required fine adjustment space with a coil spring inserted through the embedded bolt. Then, after the alignment, the inner frame and the outer frame are fitted inside and outside the manhole between the inner lid block and the lid receiving frame, so that the fine adjustment space and the raising of the height by the adjustment block are performed. The inside and outside of the part are sealed, and in this sealed state, resin mortar having fluidity between the outer frame and the lid receiving frame is injected and filled up to the height position covering the nut tightening part of the embedded bolt and cured. It is characterized by being constructed so that

〔作用〕[Action]

このような調整工法では、樹脂モルタルを外枠と蓋受
枠との間より注入充填する際、中蓋ブロックの上に積み
重ねられる調整ブロック,微調整空間等の嵩上げ調整部
は、その内側,外側が、マンホール口部に嵌着する内
枠,外枠により密閉された状態であるので、樹脂モルタ
ルが、微調整空間内,調整ブロックに挿通された埋込ボ
ルトの挿通孔内,その挿通孔を介して調整ブロック相互
の接合面内に充分,浸透充填されるようになる。
In such an adjustment method, when the resin mortar is injected and filled from between the outer frame and the lid receiving frame, the inner and outer portions of the adjusting blocks, fine adjustment spaces, etc., which are stacked on the inner lid block, are raised. Since the resin mortar is sealed by the inner frame and the outer frame fitted to the manhole opening, the resin mortar is inserted into the fine adjustment space, through the insertion hole of the embedding bolt inserted into the adjustment block, and through the insertion hole. As a result, the adjusting blocks are sufficiently permeated and filled in the joint surfaces.

この結果、調整ブロック,微調整空間等の嵩上げ調整
部は、これが一体の樹脂硬化物として硬化されることに
より、マンホール口蓋上を通行する車両荷重,地震,路
面の温度変化等により作用する水平方向,垂直方向の荷
重に対し充分な位置ズレ防止の強度が得られ、調整ブロ
ック相互間や微調整空間内に位置ズレが起らないことに
より、その等の位置ズレに起因して派生する種々な不都
合が解消される。
As a result, the raising block of the adjustment block, the fine adjustment space, etc., is hardened as an integral resin cured product, so that the horizontal direction acting due to the vehicle load passing on the manhole cover, an earthquake, a temperature change of the road surface, etc. , Sufficient strength to prevent misalignment against vertical load is obtained, and no misalignment occurs between the adjustment blocks or in the fine adjustment space. The inconvenience is resolved.

また、樹脂モルタルは、その充填レベルが埋込ボルト
のナット締付け部を覆う高さ位置まで充填されているの
で、その樹脂モルタルの一体硬化によりナットの緩みも
防止され、蓋受枠のガタ付きも防止できる作用が併せ得
られる。
In addition, the resin mortar is filled to a level that covers the nut tightening part of the mounting bolt, so the resin mortar prevents the nut from loosening due to the integral curing of the resin mortar and prevents the lid receiving frame from rattling An effect that can be obtained is also obtained.

さらに、その調整工法は、蓋受枠の嵩上げ高さを微調
整する手段として、コイルばねに支持された蓋受枠を、
上方からナットの締付けにより間隔調整して位置合せす
る手段としたから、従来の鉄片ライナーの介在による位
置合せに比して作業性が良くなり、短時間で嵩上げ工事
を実施できるようになる。
In addition, the adjusting method is a method of finely adjusting the raised height of the lid receiving frame, the lid receiving frame supported by the coil spring,
Since the means for adjusting the gap by tightening the nut from above is used for the alignment, workability is improved as compared with the conventional alignment using an iron piece liner, and the raising work can be performed in a short time.

〔実施例〕〔Example〕

以下、図面を参照して本発明による嵩高さ調整工法の
一実施例を説明する。
Hereinafter, an embodiment of a bulkiness adjusting method according to the present invention will be described with reference to the drawings.

第1図は本発明による調整工法を適用したマンホール
口部の一部を断面して示すもので、図において、1は道
路下等に埋設,設置されているコンクリート製のマンホ
ール本体、2は同マンホール本体1の上部に接合された
中蓋ブロック、3は中蓋ブロック2に支持された中蓋を
示す。なお中蓋ブロック2はマンホール本体1に対して
その接合面同士を含浸工法等により接着した状態で重合
されている。
FIG. 1 is a cross-sectional view of a part of a manhole opening to which an adjustment method according to the present invention is applied. In the figure, reference numeral 1 denotes a concrete manhole body buried and installed under a road or the like, and 2 denotes a manhole body. An inner lid block 3 joined to the upper portion of the manhole body 1 indicates an inner lid supported by the inner lid block 2. The inner lid block 2 is superposed on the manhole body 1 in a state where the joining surfaces thereof are bonded to each other by an impregnation method or the like.

(嵩上げ高さの位置合せ工程) 本発明による調整工法は、マンホール口蓋4の嵩上げ
工法を実施する際、上述の中蓋ブロック2の上面を基盤
とするもので、中蓋ブロック2の上面レベルCと、調整
する路面の高さレベルGLとの間が嵩上げ高さの寸法Hと
なる。
(Step of Positioning Raising Height) The adjusting method according to the present invention is based on the upper surface of the inner lid block 2 when the raising method of the manhole palate 4 is performed. And the height level GL of the road surface to be adjusted is the dimension H of the raised height.

上記中蓋ブロック2の上面には、その円周方向の4等
分箇所に埋込ボルト5がインサートによって立設されて
おり、この埋込ボルト5に貫通させた状態で中蓋ブロッ
ク2の上に、所定の高さ寸法を有する複数の調整ブロッ
ク6,6aが積み重ねられる。
An embedding bolt 5 is erected by an insert on the upper surface of the inner lid block 2 at four equally-spaced portions in the circumferential direction. Then, a plurality of adjustment blocks 6, 6a having a predetermined height are stacked.

この調整ブロック6,6aは、前述の嵩上げ高さ寸法Hに
対応して、予め用意されている各種高さの調整ブロック
中から任意のものを選択し、その選択,組合せにより調
整ブロック6,6aの積み重ね高さが、所望の高さ寸法hに
なるように重合させるものである。その個数は単数でも
よく、または3個以上であってもよい。
The adjustment blocks 6, 6a select an arbitrary one of various prepared height adjustment blocks corresponding to the above-mentioned raised height dimension H, and select and combine the adjustment blocks 6, 6a. Are superimposed so that the stacking height of each of them becomes a desired height dimension h. The number may be singular or three or more.

上述の埋込ボルト5は、調整ブロック6,6aを積み重ね
た高さレベルhよりも上方へ突出する長さを有し、この
埋込ボルト5の突出部分に、本実施例では、上部に至る
に従ってコイル径が小径となり撓み量が十分に得られる
円錐コイルばね7が挿着され、この円錐コイルばね7に
より所要の微調整空間aをあけた状態で蓋受枠8の円周
フランジ8aを、ナット5aの締付けにより間隔調整するこ
とで、蓋受枠8の上面(蓋受枠に嵌合支持されたマンホ
ール口蓋4の上面)が、調整する路面高さレベルGLに対
応するよう位置合せされる。
The above-mentioned embedded bolt 5 has a length protruding above the height level h in which the adjusting blocks 6, 6a are stacked, and reaches the upper portion in this embodiment to the projected portion of the embedded bolt 5. A conical coil spring 7 having a small coil diameter and a sufficient amount of deflection is inserted in accordance with the above-mentioned formula, and the circumferential flange 8a of the lid receiving frame 8 is fixed to the nut with the necessary fine adjustment space a opened by the conical coil spring 7. By adjusting the gap by tightening 5a, the upper surface of the lid receiving frame 8 (the upper surface of the manhole cover 4 fitted and supported by the lid receiving frame) is positioned so as to correspond to the road surface level GL to be adjusted.

(嵩上げ調整部の密閉工程) この位置合せ後に、中蓋ブロック2と蓋受枠8との間
のマンホール口部内側,外側にそれぞれ所要高さを有す
る円環状の内枠10,外枠11を嵌着させ、これにより、調
整ブロック6,6a、微調整空間aによる嵩上げ調整部の内
側,外側を密閉した状態とする。
(Sealing Step of Raising Adjustment Section) After this alignment, annular inner frames 10 and outer frames 11 having required heights are fitted inside and outside the manhole opening between the inner lid block 2 and the lid receiving frame 8, respectively. Thus, the inside and the outside of the raising adjustment section by the adjustment blocks 6, 6a and the fine adjustment space a are sealed.

ここに内枠10,外枠11は、特に図示していないが径方
向に拡径,縮径できる形態に構成されたものが望まし
く、その内枠10は、縮径した状態でマンホール口部内に
挿入した後に外側へ拡径して内側面に密着させ、また外
枠11は、拡径した状態でマンホール口部の外周に装着し
た後に内側へ縮径して外側面に密着させるようにして、
上述の密閉効果を高めるようにする。
Here, the inner frame 10 and the outer frame 11 are not particularly shown, but are desirably configured so as to be capable of expanding and reducing the diameter in the radial direction. After being inserted, the diameter is increased outward and adheres to the inner surface, and the outer frame 11 is attached to the outer periphery of the manhole opening in a state where the diameter is increased, so that the diameter is reduced inward and adheres to the outer surface,
The above-mentioned sealing effect is enhanced.

(樹脂モルタルの充填工程) 上述の内枠10,外枠11により上記の嵩上げ調整部を密
閉した状態で、その外枠11と蓋受枠8との間より、エポ
キシ系樹脂と砂とを混合して生成した流動性を有する樹
脂モルタル12を注入する。
(Filling step of resin mortar) In a state where the above-mentioned raised portion is sealed by the inner frame 10 and the outer frame 11, an epoxy resin and sand are mixed between the outer frame 11 and the lid receiving frame 8. The resulting resin mortar 12 having fluidity is injected.

この樹脂モルタル12は、埋込ボルト5のナット5aを覆
う高さ位置まで充填され、その充填圧により、樹脂モル
タル12が、密閉された微調整空間a内に充満され、この
充満モルタルの一部が空間a内より調整ブロック6,6aに
貫通された埋込ボルト5と挿通孔との間隙内に浸透し、
さらに挿通孔を介して調整ブロック6,6aの接合面間にも
浸透充填されるようにする。
The resin mortar 12 is filled up to a position covering the nut 5a of the embedding bolt 5, and the filling pressure causes the resin mortar 12 to be filled in the closed fine adjustment space a, and a part of the filled mortar. Penetrates from the space a into the gap between the embedding bolt 5 penetrated through the adjustment blocks 6, 6a and the insertion hole,
Further, the space between the joining surfaces of the adjustment blocks 6, 6a is also filled with the penetration through the insertion holes.

(内枠10,外枠11の撤去工程) 上記の樹脂モルタル12の充填後、充填された樹脂モル
タル12が所定時間の経過により硬化された後に、上述の
内枠10および外枠11を撤去し、蓋受枠8の周辺を埋め戻
して蓋高さの調整工法が完了される。
(Removal process of inner frame 10 and outer frame 11) After filling the above-mentioned resin mortar 12, after the filled resin mortar 12 is cured after a predetermined time, the above-mentioned inner frame 10 and outer frame 11 are removed. Then, the periphery of the lid receiving frame 8 is backfilled to complete the lid height adjusting method.

〔発明の効果〕〔The invention's effect〕

本発明によるマンホールの蓋高さ調整工法によれば、
上述したように、蓋受枠8の嵩上げ位置を位置合せした
後、中蓋ブロック2の上に積み重ねられる調整ブロック
6,6a,微調整空間a等の嵩上げ調整部が、マンホール口
部の内側,外側に嵌着させた内枠10,外枠11により密閉
された状態とし、この密閉状態で樹脂モルタル12を、外
枠11と蓋受枠8との間より注入充填するから、樹脂モル
タル12が、微調整空間a内,調整ブロック6,6aに挿通さ
れた埋込ボルト5の挿通孔内,その挿通孔を介して調整
ブロック6,6a相互の接合面間に充分,浸透充填されるよ
うになる。
According to the manhole cover height adjusting method according to the present invention,
As described above, after adjusting the raised position of the lid receiving frame 8, the adjustment block stacked on the inner lid block 2.
6, 6a, the fine-adjustment space a and the like are adjusted by the inner frame 10 and the outer frame 11 fitted inside and outside the manhole opening, and the resin mortar 12 is sealed in this sealed state. Since the resin mortar 12 is injected and filled from between the outer frame 11 and the lid receiving frame 8, the resin mortar 12 is inserted into the fine adjustment space a, through the insertion hole of the embedding bolt 5 inserted through the adjustment blocks 6, 6a, and through the insertion hole. As a result, the adjusting blocks 6, 6a can be sufficiently filled with permeation between the joint surfaces.

この結果、調整ブロック6,6a、微調整空間a等の嵩上
げ調整部は、これが一体の樹脂硬化物として硬化される
ことにより、マンホール口蓋4上を通行する車両荷重,
地震,路面の温度変化等により作用する水平方向,垂直
方向の荷重に対し充分な位置ズレ防止の強度が得られ、
調整ブロック相互間や微調整空間内の介在物に位置ズレ
が起らないことより、従来のような位置ズレに起因して
派生する種々な不都合を解消することができる。
As a result, the raised portions of the adjustment blocks 6, 6a, the fine adjustment space a, and the like are cured as an integral resin cured product, so that the vehicle load passing through the manhole cover 4 can be reduced.
Sufficient displacement prevention strength is obtained for horizontal and vertical loads acting due to earthquakes, road surface temperature changes, etc.
Since no displacement occurs between the adjustment blocks or the inclusions in the fine adjustment space, it is possible to eliminate various inconveniences caused by the conventional displacement.

また樹脂モルタル12は、その充填レベルが埋込ボルト
5のナット締付け部を覆う高さ位置まで充填されている
ので、樹脂モルタル12の一体硬化によりナット5aの緩み
も防止され、蓋受枠のガタ付きも防止できる等の効果が
併せ得られる。
In addition, since the resin mortar 12 is filled to a level where the filling level covers the nut tightening portion of the embedding bolt 5, the resin mortar 12 is integrally hardened to prevent the nut 5a from being loosened, and the lid receiving frame is loose. Can also be prevented.

さらに本発明によれば、蓋受枠8の嵩上げ高さを微調
整する手段として、コイルばね7に支持された蓋受枠8
を、上方からナット5aの締付けにより間隔調整して位置
合せする手段としたから、従来の鉄片ライナーの介在に
よる位置合せに比して作業性が良くなり、短時間で嵩上
げ工事を実施できる効果も得られる。
Further, according to the present invention, as means for finely adjusting the raised height of the lid receiving frame 8, the lid receiving frame 8 supported by the coil spring 7 is used.
Is a means for adjusting the distance by tightening the nut 5a from above, so that the workability is improved as compared with the conventional alignment with the interposition of the iron piece liner, and the effect that the lifting work can be carried out in a short time is also achieved. can get.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本発明によるマンホールの嵩高さ調整工法を適
用したマンホール口部の一部を示す断面図、第2図はマ
ンホール口部の一部を破断して示す横断面図である。 1……マンホール本体、2……中蓋ブロック、3……中
蓋、4……マンホール口蓋、5……埋込ボルト、5a……
ナット、6,6a……調整ブロック、7……コイルばね、8
……蓋受枠、8a……蓋受枠の円周フランジ、10……内
枠、11……外枠、a……微調整空間。
FIG. 1 is a cross-sectional view showing a part of a manhole opening to which a manhole bulkiness adjusting method according to the present invention is applied, and FIG. 2 is a cross-sectional view showing a part of the manhole opening cut away. 1 ... manhole body, 2 ... inner lid block, 3 ... inner lid, 4 ... manhole palate, 5 ... embedded bolt, 5a ...
Nut, 6, 6a ... Adjustment block, 7 ... Coil spring, 8
... lid receiving frame, 8a ... circumferential flange of lid receiving frame, 10 ... inner frame, 11 ... outer frame, a ... fine adjustment space.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 大島 謙二 神奈川県大和市代官3丁目18番地の4 株式会社ハッコー開発技術研究所内 (56)参考文献 実開 昭61−146548(JP,U) 実公 昭54−20839(JP,Y2) (58)調査した分野(Int.Cl.6,DB名) E02D 29/12──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Kenji Oshima 3-18-18 Daikan, Yamato-shi, Kanagawa Prefecture Inside HAKKO Development Technology Research Institute Co., Ltd. (56) References Jikaichi Sho 61-146548 (JP, U) 54-20839 (JP, Y2) (58) Fields investigated (Int. Cl. 6 , DB name) E02D 29/12

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】道路下に埋設されているマンホール本体の
上部に中蓋ブロックが接合され、該中蓋ブロックを基盤
として上方に固定されるマンホール口蓋の蓋受枠を路面
レベルに対応する高さに嵩上げ調整するに際し、 中蓋ブロックの上面に、調整する嵩上げ高さに対応し
て、所定高さ寸法を有する単数または複数の調整ブロッ
クを、中蓋ブロックの上面にインサートされた埋込ボル
トに貫通して積み重ね、その上に、埋込ボルトに挿通し
たコイルばねにより所要の微調整空間をあけて蓋受枠
を、上方からナットの締付けにより間隔調整することで
蓋受枠の上面を路面レベルに対応した高さに位置合せ
し、 その位置合せ後に、中蓋ブロックと蓋受枠との間のマン
ホール内側,外側に内枠,外枠を嵌着して上記微調整空
間および調整ブロックによる嵩上げ調整部の内側,外側
を密閉させ、この密閉状態で、その外枠と蓋受枠との間
より流動性を有する樹脂モルタルを、埋込ボルトのナッ
ト締付け部を覆う高さ位置まで注入充填させて硬化する
ように施工することを特徴としたマンホールの蓋高さ調
整工法。
1. An inner lid block is joined to an upper part of a manhole body buried under a road, and a lid receiving frame of a manhole palate fixed upward on the basis of the inner lid block to a height corresponding to a road surface level. At the time of raising the height, one or more adjusting blocks having a predetermined height are passed through the embedding bolts inserted into the upper surface of the inner lid block, on the upper surface of the inner lid block, according to the raised height to be adjusted. The upper surface of the lid receiving frame was adjusted to the road surface level by adjusting the distance between the lid receiving frame and the upper part of the lid receiving frame by tightening nuts from above, leaving a required fine adjustment space with a coil spring inserted through the embedded bolt. After the alignment, the inner frame and the outer frame are fitted inside and outside the manhole between the inner lid block and the lid receiving frame to fit the fine adjustment space and the adjustment block. The inside and outside of the raised portion are sealed, and in this sealed state, the resin mortar having fluidity between the outer frame and the lid receiving frame is injected and filled to the height position covering the nut tightening portion of the embedded bolt. The method of adjusting the height of the manhole cover, characterized in that it is constructed so that it hardens when it is set.
JP2313370A 1990-11-19 1990-11-19 Manhole cover height adjustment method Expired - Fee Related JP2782283B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2313370A JP2782283B2 (en) 1990-11-19 1990-11-19 Manhole cover height adjustment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2313370A JP2782283B2 (en) 1990-11-19 1990-11-19 Manhole cover height adjustment method

Publications (2)

Publication Number Publication Date
JPH04185827A JPH04185827A (en) 1992-07-02
JP2782283B2 true JP2782283B2 (en) 1998-07-30

Family

ID=18040444

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2313370A Expired - Fee Related JP2782283B2 (en) 1990-11-19 1990-11-19 Manhole cover height adjustment method

Country Status (1)

Country Link
JP (1) JP2782283B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102241624B1 (en) 2020-09-28 2021-04-19 주식회사 지오이엔비 Manhole using rc, pc-supporting block and lifting, falling method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102241624B1 (en) 2020-09-28 2021-04-19 주식회사 지오이엔비 Manhole using rc, pc-supporting block and lifting, falling method thereof

Also Published As

Publication number Publication date
JPH04185827A (en) 1992-07-02

Similar Documents

Publication Publication Date Title
JP2782283B2 (en) Manhole cover height adjustment method
JP6905398B2 (en) Joining structure of foundation pile and steel foundation beam and its joining method
JP3362809B2 (en) Pillar support device
JP2623491B2 (en) Cutting overlay method
JP2964924B2 (en) Piles and column base joints
JP3171675U (en) Anti-sinking floor slab with maneuvering prevention function
JPH093913A (en) Column base fixing method for steel pipe column
JP2782278B2 (en) Manhole bulk height adjustment method
JP3504747B2 (en) Nut with flange for anchor bolt
JP2979114B2 (en) Existing foundation structure reinforcement method
JP5139377B2 (en) Manhole floating prevention structure
JPS59122625A (en) Fitting device for columnar leg of structure
JP3236950B2 (en) Embedded column base and method of construction
JP3031253B2 (en) Adjustable column base
JP3455286B2 (en) Manhole cover height adjustment method
JP2001107498A (en) Precast slab laying structure and method of laying precast slab
JP2979122B2 (en) How to install anchor bolts for seismic isolation devices
JP2818814B2 (en) Manhole cover height adjustment method
JPH07158095A (en) Cover height adjusting method for manhole
JP2727433B2 (en) Fixing device for frame base for underground structures
JP3074063B2 (en) Manhole cover height adjustment method
JPH09165767A (en) Device technology for adjusting height of cover for manhall therefor
JP2000192488A (en) Manhole-cover applying device in concrete connecting pit
JP2818818B2 (en) Manhole cover height adjustment device
JP2852577B2 (en) Square manhole cover height adjustment method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090522

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090522

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100522

Year of fee payment: 12

LAPS Cancellation because of no payment of annual fees