JP2843364B2 - Switching method for low-voltage side of distribution transformer - Google Patents
Switching method for low-voltage side of distribution transformerInfo
- Publication number
- JP2843364B2 JP2843364B2 JP1183202A JP18320289A JP2843364B2 JP 2843364 B2 JP2843364 B2 JP 2843364B2 JP 1183202 A JP1183202 A JP 1183202A JP 18320289 A JP18320289 A JP 18320289A JP 2843364 B2 JP2843364 B2 JP 2843364B2
- Authority
- JP
- Japan
- Prior art keywords
- voltage
- low
- circuit
- load
- switching
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000000034 method Methods 0.000 title claims description 12
- 238000001514 detection method Methods 0.000 claims description 15
- 238000010276 construction Methods 0.000 description 6
- 238000007796 conventional method Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000016507 interphase Effects 0.000 description 1
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Description
【発明の詳細な説明】 [産業上の利用分野】 本発明は変圧器の低圧側負荷切替方法に関するもので
ある。Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for switching a low-voltage side of a transformer.
[従来の技術] 高度情報社会の進展に伴い、電力の安定供給に対する
要請が高まっている。そして、工事停電についても年々
困難になり、需要家を停電させることなく工事を行うこ
とが提案、実施されている。例えば、第3図に示すよう
にA,B両バンクのうち一方のBバンクの柱上変圧器Trbの
取替え工事を行う場合、Bバンクの負荷LBをAバンクへ
切替えてBバンクの工事中もBバンクの負荷LBにAバン
クから、電力を供給し、工事終了後に負荷LBをBバンク
に切戻すようにしている。[Prior Art] With the development of an advanced information society, demands for stable supply of electric power are increasing. In addition, it is becoming difficult year after year for the power outage of the construction, and it is proposed and implemented that the construction be performed without causing the power outage of the customer. For example, as shown in FIG. 3, when replacing the pole transformer Trb of one of the banks B of the banks A and B, the load LB of the bank B is switched to the bank A and the construction of the bank B is performed. Power is supplied from the bank A to the load LB of the bank B, and the load LB is switched back to the bank B after the construction is completed.
前記Bバンクの負荷LBをAバンクへ切替える方法とし
て、Bバンクの低圧側に接続され、三相一括に開閉でき
るようにした低圧開閉器LSに対して、負荷側が無電圧に
なるとそれに対応して開閉部が三相一括で自動的(10ms
ec以内)に閉じる作用を為す切替開閉器S1を接続し、A,
B両バンクの分枝転に前記と同様な構成の切替開閉器S2
を接続した後、次の操作に従い切替えを行う方法があ
る。As a method of switching the load LB of the B bank to the A bank, a low voltage switch LS connected to the low voltage side of the B bank and capable of opening and closing all three phases collectively corresponds to the case where the load side becomes no voltage. Opening / closing part is automatic in three phases at once (10ms
(within ec) by connecting a switching switch S1 that closes
Switching switch S2 of the same configuration as above for branching of both B banks
After connection, there is a method of performing switching according to the following operation.
1.切替開閉器S1を手動操作によりON状態にする。2.低
圧開閉器LSを手動操作によりOFF状態にする。3.切替開
閉器S1を手動操作によりOFF状態にする。4.切替開閉器S
2が負荷LB側が無電圧になったことを検出し、瞬時(10/
msec以内)にON状態となり、負荷LB側へAバンクから電
流IAが流れるようになる。1. Turn ON the switch S1 manually. 2. Turn off the low-voltage switch LS by manual operation. 3. Turn off the switching switch S1 manually. 4.Switch S
2 detects that the load LB side has become no voltage, and instantaneously (10 /
(within msec), and the current IA flows from the bank A to the load LB side.
[発明が解決しようとする課題] ところが、前記の方法では変圧器の2次側(低圧側)
に低圧開閉器(低圧分岐箱)が必要なため、変圧器の低
圧側に低圧開閉器(低圧分岐箱)がない系統ではこの方
法を実施することができないという問題がある。また、
切替開閉器が2台必要となり、切替開閉器の接続および
工事終了後の取り外し作業に手間がかかるという問題が
ある。[Problems to be Solved by the Invention] However, in the above method, the secondary side (low voltage side) of the transformer is used.
Therefore, there is a problem that this method cannot be performed in a system without a low-voltage switch (low-voltage branch box) on the low-voltage side of the transformer. Also,
There is a problem in that two switching switches are required, and it takes time to connect the switching switches and to remove them after the construction is completed.
本発明は、前記の問題点に鑑みてなされたものであっ
て、その目的は変速機の低圧側に低圧開閉器(低圧分岐
箱)がない系統でも実施できるとともに、切替開閉器1
を1台しか必要とせず、しかも、負荷切替を瞬時に行う
ことができる配電変圧器の低圧側切替方法を提供するこ
とにある。SUMMARY OF THE INVENTION The present invention has been made in view of the above-described problems, and an object of the present invention is to provide a system that does not have a low-pressure switch (low-pressure branch box) on the low-pressure side of a transmission.
It is an object of the present invention to provide a low-voltage side switching method of a distribution transformer that requires only one unit and that can perform load switching instantaneously.
[課題を解決するための手段] 上記の目的を達成するために本願発明は、高圧配電線
にそれぞれプライマリーカットアウト及び変圧器を介し
て接続された2箇所の低圧配電線の負荷切替を電圧及び
位相の同期と協調とを確保しながら行う変圧器の低圧側
負荷切替方法において、前記両低圧配電線の各相間に
は、一方の低圧配電線の相の無電圧を検出したときにそ
れらの相間を接続するスイッチと、前記無電圧の検出か
ら相間の接続までの間、無電圧にしようとする負荷側の
配電変圧器の低圧側の各相に電力を供給する予備電源供
給回路とを有する切替装置を接続し、一方の低圧配電線
の負荷を他方の低圧配電線へ切替える際、無電圧にしよ
うとする負荷側の配電変圧器の高圧側の各相に接続され
ているプライマリーカットアウトを一つずつ順次解放す
ることをその要旨とする。[Means for Solving the Problems] In order to achieve the above object, the present invention provides a method for switching the load of two low-voltage distribution lines connected to a high-voltage distribution line via a primary cutout and a transformer, respectively. In the transformer low-voltage side load switching method performed while ensuring phase synchronization and coordination, between the phases of the two low-voltage distribution lines, when no voltage of one of the low-voltage distribution lines is detected, the phase between those phases is detected. And a backup power supply circuit for supplying power to each low-voltage side phase of the load-side distribution transformer that is to be set to no voltage during the period from the detection of no voltage to the connection between the phases. When connecting the equipment and switching the load on one low-voltage distribution line to the other low-voltage distribution line, identify the primary cutouts connected to each high-side phase of the load-side distribution transformer that is to be de-energized. One by one The gist is to release them next.
[作用] したがって、両低圧配電線の各相間に切替装置を接続
し、一方の低圧配電線のプライマリーカットアウトを開
放する。そして、切替装置が無電圧を検出すると、同装
置のスイッチが投入されるまで予備電源供給回路は電力
を供給し、その後スイッチが投入されたあとで予備電源
供給回路は電力の供給を停止して負荷の切替が行われ
る。[Operation] Therefore, a switching device is connected between each phase of both low-voltage distribution lines, and the primary cutout of one low-voltage distribution line is opened. When the switching device detects no voltage, the standby power supply circuit supplies power until the switch of the device is turned on, and thereafter, the standby power supply circuit stops supplying power after the switch is turned on. Switching of the load is performed.
[実施例] 以下、本発明を具体化した一実施例を図面に従って説
明する。[Embodiment] An embodiment of the present invention will be described below with reference to the drawings.
第1図に示すように、A,B両バンクに設けられた変圧
器Tra,Trbの高圧側の配電線Lには各相U,V,W毎にそれぞ
れプライマリーカットアウトPCが接続されている。ま
た、A,B両バンクの低圧側間にはバイバスケーブルKを
介して切替装置Yが接続されている。As shown in FIG. 1, a primary cutout PC is connected to each of the phases U, V, and W to the distribution line L on the high voltage side of the transformers Tra and Trb provided in both banks A and B. . A switching device Y is connected via a bypass cable K between the low voltage sides of both the A and B banks.
第1,2図に示すように、前記切替装置Y内には両配電
線Lの各相U,V,W間をそれぞれバイパスケーブルKで接
続されるとともに、同バイパスケーブルKには常時解放
形のスイッチSU,SV,SWが設けられている。そして、スイ
ッチSU,SV,SWよりもBバンク側においてバイパスケーブ
ルKのU,V相間には第1の補償回路Q1が接続されるとと
もに、スイッチSV,SWよりもBバンク側間においてバイ
パスケーブルKのU,W相間には第2の補償回路Q2がそれ
ぞれ接続されている。As shown in FIGS. 1 and 2, in the switching device Y, the respective phases U, V, and W of both distribution lines L are connected by bypass cables K, and the bypass cables K are always open. Switches SU, SV, and SW are provided. A first compensation circuit Q1 is connected between the U and V phases of the bypass cable K on the B bank side of the switches SU, SV and SW, and the bypass cable K is connected on the B bank side of the switches SV and SW. The second compensating circuit Q2 is connected between the U and W phases.
前記、両補償回路Q1,Q2内にはBバンク側のU,V相間及
びV,W相間の無電圧を検出する検出回路1がそれぞれ設
けられ、検出回路1には高速切替スイッチ回路2および
駆動回路3がそれぞれ接続されている。前記高速切替ス
イッチ回路2はサイリスタなどの無接点素子によって構
成されている。そして、検出回路1はBバンク側の無電
圧を検出すると検出信号を高速切替スイッチ2および駆
動回路3にそれぞれ出力するようになっている。In the two compensation circuits Q1 and Q2, there are provided detection circuits 1 for detecting no voltage between the U and V phases and between the V and W phases on the B bank side, respectively. Circuits 3 are respectively connected. The high-speed changeover switch circuit 2 is configured by a non-contact element such as a thyristor. The detection circuit 1 outputs a detection signal to the high-speed changeover switch 2 and the drive circuit 3 when detecting no voltage on the B bank side.
前記第1の補償回路Q1の駆動回路3には継電器MCU,MC
Vが接続されるとともに、前記第2の補償回路Q2の駆動
回路3には継電器MCWが接続されている。The drive circuit 3 of the first compensation circuit Q1 has relays MCU, MC
V is connected, and a relay MCW is connected to the drive circuit 3 of the second compensation circuit Q2.
第1図の補償回路Q1の駆動回路3は前記検出回路1の
検出信号に基づいて継電器MCU,MCVを駆動制御するよう
になっているとともに、第2の補償回路Q2の駆動回路3
は前記検出回路1の検出信号に基づいて継電器MCWを駆
動制御するようになっている。そして、この継電器MCU,
MCV,MCWは前記スイッチ、SU,SV,SWをそれぞれ投入開放
するようになっているとともに、投入信号を各遅延回路
5に出力するようになっている。The drive circuit 3 of the compensation circuit Q1 shown in FIG. 1 drives and controls the relays MCU and MCV based on the detection signal of the detection circuit 1, and the drive circuit 3 of the second compensation circuit Q2.
Drives the relay MCW based on the detection signal of the detection circuit 1. And this relay MCU,
MCV and MCW open and close the switches, SU, SV and SW, respectively, and output a closing signal to each delay circuit 5.
また、前記高速切替スイッチ回路2には予備電源供給
回路としての電源回路4が接続され、この電源回路4内
には図示しない充電回路,バッテリー,周知の同調回路
およびインバータ回路が内蔵され、Bバンク側の配電線
Lが無電圧となったとき、電源回路4から高速切替スイ
ッチ回路2を通してBバンクの負荷LB側へ電力を電圧及
び位相の協調を確保しながら瞬時に、かつ一時的に供給
するようになっている。A power supply circuit 4 as a standby power supply circuit is connected to the high-speed changeover switch circuit 2. In the power supply circuit 4, a charging circuit (not shown), a battery, a well-known tuning circuit, and an inverter circuit are incorporated. When the distribution line L on the side has no voltage, the power is instantaneously and temporarily supplied from the power supply circuit 4 to the load LB side of the B bank through the high-speed switch circuit 2 while ensuring the coordination of the voltage and the phase. It has become.
なお、このように異なるバンクから電力の供給を受け
る場合、電圧や位相の協調を図ることは周知事項であ
る。When power is supplied from different banks in this way, it is a well-known matter to cooperate in voltage and phase.
さらに、各駆動回路3の駆動制御により継電器MCU,MC
V,MCWを介してスイッチSU,SV,SWを投入するとともに、
投入信号が遅延回路5に入力される。各遅延回路5はス
イッチSU,SV,SWの投入の完了後高速切替スイッチ回路2
に切替信号を出力し、バッテリーによるBバンク側の負
荷LBへ電力の供給の停止し、バッテリーの充電を開始す
るようになっている。Further, the relays MCU, MC
While turning on the switches SU, SV, SW via V, MCW,
An input signal is input to the delay circuit 5. Each of the delay circuits 5 is a high-speed changeover switch circuit 2 after the switches SU, SV, and SW are turned on.
, The supply of power to the load LB on the B bank side by the battery is stopped, and charging of the battery is started.
次に、Bバンクの負荷LBをAバンクへ切替える場合に
ついて説明する。Next, a case where the load LB of the B bank is switched to the A bank will be described.
まず、Bバンクの高圧側のプライマリーカットアウト
PCを順次開放していく。すなわち、Bバンクの配電線L
のU相のプライマリーカットアウトPCUを開放する。す
ると、配電線U,V相間が無電圧になり第1の補償回路Q1
の検出回路1がこれを検出して高速切替スイッチ回路2
および駆動回路3に検出信号をそれぞれ出力する。First, the primary cutout on the high pressure side of bank B
Open PCs sequentially. That is, distribution line L of bank B
Release the U-phase primary cutout PCU. Then, there is no voltage between the U and V phases of the distribution line, and the first compensation circuit Q1
Detection circuit 1 detects this, and the high-speed changeover switch circuit 2
And a detection signal to the drive circuit 3.
高速切替スイッチ回路2はこの検出信号に基づいて電
源回路4のバッテリー,同調回路およびインバータ回路
により、Bバンクの配電線LのU,V相間に出力を供給す
る。一方、駆動回路3は前記検出回路1の検出信号に基
づいて継電器MCU,MCVを駆動制御してスイッチSU,SVを投
入する。The high-speed changeover switch circuit 2 supplies an output between the U and V phases of the distribution line L of the B bank by the battery, tuning circuit and inverter circuit of the power supply circuit 4 based on the detection signal. On the other hand, the drive circuit 3 drives and controls the relays MCU and MCV based on the detection signal of the detection circuit 1 to turn on the switches SU and SV.
そして、遅延回路5は各駆動回路3の投入指令信号に
基づいて所定時間後、高速切替スイッチ回路2切替えて
電源回路4によるBバンク側のU,V相間負荷LBへの電力
の供給を停止し、電源回路4への充電状態に切替る。The delay circuit 5 switches the high-speed switching circuit 2 after a predetermined time based on the input command signal of each drive circuit 3 to stop the supply of power to the U- and V-phase load LB on the B bank side by the power supply circuit 4. , The state of the power supply circuit 4 is switched.
したがって、Bバンクの低圧側U,V相間にはAバンク
の低圧側U,V相間から電力が供給される。Therefore, power is supplied between the low-voltage side U and V phases of the bank B from the low-voltage side U and V phases of the bank A.
次に、BバンクのプライマリーカットアウトPCVを開
放する、すると、Bバンクの低圧側V,W相間が無電圧と
なるため、第2の補償回路Q2の検出回路1はこの無電圧
を検出して高速切替スイッチ回路2を切替えて電源回路
4のバッテリー,同調回路およびインバーター回路によ
りBバンクの低圧側V,W相間に電力を供給する。Next, when the primary cutout PCV of the bank B is released, there is no voltage between the low-voltage side V and W phases of the bank B. Therefore, the detection circuit 1 of the second compensation circuit Q2 detects this non-voltage. The high-speed changeover switch circuit 2 is switched to supply power between the low voltage side V and W phases of the B bank by the battery, tuning circuit and inverter circuit of the power supply circuit 4.
また、駆動回路3により継電器MCWを介してスイッチS
Wの投入を完了する。一方、遅延回路5は所定時間後、
高速切替スイッチ回路2を介して電源回路4によるV,W
相間の負荷LBへの電力の供給を停止し、電源回路4への
充電状態に切替える。In addition, the switch S is connected to the drive circuit 3 via the relay MCW.
Complete the W input. On the other hand, after a predetermined time, the delay circuit 5
V, W by power supply circuit 4 via high-speed changeover switch circuit 2
The supply of power to the inter-phase load LB is stopped, and the power supply circuit 4 is switched to a charged state.
したがって、Bバンクの低圧側V,W相間にはAバンク
の低圧側V,W相間から電力が供給される。Therefore, electric power is supplied between the low-voltage side V and W phases of the bank B from the low-voltage side V and W phases of the bank A.
最後にW相のプライマリーカットアウトPCWを開放す
ると、Bバンクの負荷LBをAバンクへ切替る動作の完了
となる。Finally, when the W-phase primary cutout PCW is released, the operation of switching the load LB of the B bank to the A bank is completed.
したがって、以上の切替方法においては、従来とは異
なり切替開閉器を2台設ける必要がなく、切替装置Yを
1台にすることができるとともに、低圧開閉器のない系
統にも適用することができる。Therefore, in the above switching method, unlike the conventional method, there is no need to provide two switching switches, and the number of switching devices Y can be reduced to one, and the present invention can be applied to a system without a low-voltage switch. .
また、切替装置Y内に補償回路Q1,Q2を設け、スイッ
チSU,SV,SWが投入されるまでバッテリーにより電力を供
給するため完全な無瞬断切替えにすることができる。さ
らに、スイッチSU,SV,SWの投入時間は非常に短時間であ
るため、補償回路Q1,Q2の容量は小さくてすむ。Further, since the compensation circuits Q1 and Q2 are provided in the switching device Y and the power is supplied from the battery until the switches SU, SV and SW are turned on, it is possible to perform complete instantaneous interruption switching. Further, since the switches SU, SV, and SW are turned on for a very short time, the capacity of the compensation circuits Q1 and Q2 can be small.
また、本実施例においてはU相からの負荷切替を行っ
たが、W相からの負荷切替を行うように切替装置Yを構
成してもよい。Further, in the present embodiment, the load switching is performed from the U phase, but the switching device Y may be configured to perform the load switching from the W phase.
なお、本実施例においては2つの補償回路Q1,Q2によ
って単相補償としたが、補償回路3相式に構成して補償
回路を1つにすることも可能である。In the present embodiment, single-phase compensation is performed by the two compensation circuits Q1 and Q2. However, it is also possible to configure the compensation circuit in a three-phase system and use only one compensation circuit.
なお、この発明は前記実施例に限定されるものではな
く、この発明の趣旨から逸脱しない範囲内で任意に変更
することも可能である。Note that the present invention is not limited to the above-described embodiment, and can be arbitrarily changed without departing from the spirit of the present invention.
[発明の効果] 以上、詳述したように本発明によれば、変圧器の低圧
側に低圧開閉器(低圧分岐箱)がない系統でも、一方の
バンクの負荷を他方のバンクへ切替えることができる。
また、切替作業時に必要とする切替装置が1台でよいた
め、切替装置の接続作業や工事終了後の取り外し作業の
手間が少なくなる。[Effects of the Invention] As described above in detail, according to the present invention, even in a system without a low-voltage switch (low-voltage branch box) on the low-voltage side of the transformer, the load of one bank can be switched to the other bank. it can.
In addition, since only one switching device is required at the time of the switching operation, the labor of connecting the switching device and removing it after the completion of the construction is reduced.
また、スイッチの投入完了するまで一方のバンクの電
力の供給を補償回路が補償するため、負荷切替を瞬時に
行うことができる。Further, since the supply of power to one bank is compensated by the compensation circuit until the switch is completely turned on, the load can be switched instantaneously.
第1図は本発明を具体化した一実施例を示すものであっ
て、第1図は両バンク間に切替装置を接続した状態を示
す電気回路図、第2図は切替装置内の回路構成を示すブ
ロック配線図、第3図は従来の方法を示す電気回路図で
ある。 A,B……バンク、SU,SV,SW……スイッチ、PC,PCU,PCV,PC
W……プライマリーカットアウト、Y……切替装置、LA,
LB……負荷、Q1,Q2……補償回路。FIG. 1 shows an embodiment of the present invention. FIG. 1 is an electric circuit diagram showing a state in which a switching device is connected between both banks. FIG. 2 is a circuit configuration in the switching device. FIG. 3 is an electric circuit diagram showing a conventional method. A, B …… Bank, SU, SV, SW …… Switch, PC, PCU, PCV, PC
W: Primary cutout, Y: Switching device, LA,
LB: Load, Q1, Q2: Compensation circuit.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 伊藤 正芳 愛知県犬山市字上小針1番地 エナジー サポート株式会社内 (72)発明者 渡辺 弘 愛知県犬山市字上小針1番地 エナジー サポート株式会社内 (58)調査した分野(Int.Cl.6,DB名) H02J 3/00 - 5/00────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Masayoshi Ito 1st character small needle in Inuyama City, Aichi Prefecture Energy Support Corporation (72) Inventor Hiroshi Watanabe 1st character small needle in Inuyama City, Aichi Prefecture Energy Support Corporation ( 58) Field surveyed (Int.Cl. 6 , DB name) H02J 3/00-5/00
Claims (1)
アウト及び変圧器を介して接続された2箇所の低圧配電
線の負荷切替を電圧及び位相の同期と協調とを確保しな
がら行う変圧器の低圧側負荷切替方法において、 前記両低圧配電線の各相間には、一方の低圧配電線の相
の無電圧を検出したときにそれらの相間を接続するスイ
ッチと、前記無電圧の検出から相間の接続までの間、無
電圧にしようとする負荷側の配電変圧器の低圧側の各相
に電力を供給する予備電源供給回路とを有する切替装置
を接続し、一方の低圧配電線の負荷を他方の低圧配電線
へ切替える際、無電圧にしようとする負荷側の配電変圧
器の高圧側の各相に接続されているプライマリーカット
アウトを一つずつ順次開放する変圧器の低圧側負荷切替
方法。1. A low-voltage side of a transformer for switching loads of two low-voltage distribution lines connected to a high-voltage distribution line via a primary cutout and a transformer, respectively, while ensuring voltage and phase synchronization and coordination. In the load switching method, between the phases of the two low-voltage distribution lines, a switch that connects between the phases when detecting no-voltage of one of the low-voltage distribution lines, from the detection of the no-voltage to the connection between the phases. A switching device having a backup power supply circuit for supplying power to each phase on the low voltage side of the distribution transformer on the load side which is to be set to no voltage, and connecting the load on one low voltage distribution line to the other low voltage. A low-voltage side load switching method for a transformer in which, when switching to a distribution line, primary cutouts connected to the respective high-side phases of a load-side distribution transformer to be set to no voltage are sequentially opened one by one.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1183202A JP2843364B2 (en) | 1989-07-15 | 1989-07-15 | Switching method for low-voltage side of distribution transformer |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1183202A JP2843364B2 (en) | 1989-07-15 | 1989-07-15 | Switching method for low-voltage side of distribution transformer |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0349530A JPH0349530A (en) | 1991-03-04 |
| JP2843364B2 true JP2843364B2 (en) | 1999-01-06 |
Family
ID=16131561
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1183202A Expired - Lifetime JP2843364B2 (en) | 1989-07-15 | 1989-07-15 | Switching method for low-voltage side of distribution transformer |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2843364B2 (en) |
-
1989
- 1989-07-15 JP JP1183202A patent/JP2843364B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0349530A (en) | 1991-03-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP4125601B2 (en) | A system that supplies reliable power to important loads | |
| JP3248111B2 (en) | Uninterruptible power supply system | |
| JP2843364B2 (en) | Switching method for low-voltage side of distribution transformer | |
| CN211377605U (en) | Uninterrupted parallel operation grid-connected system of medium-voltage power supply vehicle | |
| JP2000083330A (en) | Distributed power supply installation | |
| JP2845279B2 (en) | Low-side load switching method for distribution transformers in different banks | |
| JPH038037Y2 (en) | ||
| JP2804097B2 (en) | Low-side load switching system of distribution transformer between different banks | |
| JPH06113489A (en) | Bypass circuit for maintenance of uninterruptible power supply | |
| JP2940137B2 (en) | Distribution line phase detector | |
| JP2842896B2 (en) | Low-side load switching method of transformer between different banks | |
| JPS61157280A (en) | Operating apparatus of plural motors | |
| JP2738446B2 (en) | Switching method of low-voltage side load switching of transformer | |
| CN216086256U (en) | Automatic power switching system | |
| CN215498369U (en) | Power supply system bus-tie control circuit | |
| JP3079610B2 (en) | Power supply unbalance countermeasure device | |
| JPH0245419B2 (en) | ||
| JP2745838B2 (en) | Power generation system | |
| JP3438448B2 (en) | Ground fault protection device for power supply equipment for distribution line construction | |
| JPH0436208Y2 (en) | ||
| JP2857263B2 (en) | Low-voltage uninterruptible switching device for transformer and method for switching and switching back | |
| JPS61227636A (en) | Power source switchgear | |
| JPS61102123A (en) | Method of changing over two system incoming power supply | |
| JP2781416B2 (en) | Method of switching back the load on the low voltage side of the distribution transformer | |
| JP2842895B2 (en) | Low-side load switching method of transformer between different banks |