Beam-to-column connection method for precast reinforced concrete structures

Info

Publication number
JP2915500B2
JP2915500B2 JP15373090A JP15373090A JP2915500B2 JP 2915500 B2 JP2915500 B2 JP 2915500B2 JP 15373090 A JP15373090 A JP 15373090A JP 15373090 A JP15373090 A JP 15373090A JP 2915500 B2 JP2915500 B2 JP 2915500B2
Authority
JP
Japan
Prior art keywords
column
reinforced concrete
joint
precast reinforced
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP15373090A
Other languages
Japanese (ja)
Other versions
JPH0444543A (en
Inventor
安治 前田
武穂 池田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP15373090A priority Critical patent/JP2915500B2/en
Publication of JPH0444543A publication Critical patent/JPH0444543A/en
Application granted granted Critical
Publication of JP2915500B2 publication Critical patent/JP2915500B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明はプレキャスト鉄筋コンクリート構造物の柱
梁接合工法、特に梁下端筋の改良に関するものである。
Description: FIELD OF THE INVENTION The present invention relates to a method of joining a precast reinforced concrete structure to a column and a beam, and more particularly to an improvement in a lower end bar of a beam.

「従来の技術、発明が解決せんとする問題点」 従来、柱間の梁中央部に梁筋の接合箇所を設けるプレ
キャスト鉄筋コンクリート構造物の柱梁接合工法とし
て、第4図に示すように柱頭部上に一段の梁下端筋によ
って互いに連結されたX方向の一対のプレキャスト梁の
端部を載せた後、同様のY方向の一対のプレキャスト梁
の端部を載せて相互の梁下端筋を交差させ、次いでXY両
方向の梁上端筋を配筋して柱梁接合部に接合コンクリー
トを打設することにより、接合する工法が実施されてい
る。
[Prior art and problems to be solved by the invention] Conventionally, as shown in Fig. 4, a column head is used as a beam-column joint method of a precast reinforced concrete structure in which a beam reinforcing portion is provided at a beam center portion between columns. After placing the ends of a pair of precast beams in the X direction that are connected to each other by a single-stage beam bottom reinforcement, the other ends of the pair of precast beams in the same Y direction are placed on each other to cross each other. Then, a jointing method is carried out by arranging a beam top reinforcing bar in both XY directions and placing joint concrete at a beam-column joint.

しかしながら、前記従来工法では、XY方向の梁を直交
させて相互の下端筋同士を交差状に重ねるため、最初に
載せたX方向の梁下端筋を上下二段に配筋すると、Y方
向の梁を載せる際にその梁筋がX方向の梁の上側の下端
二段筋に引っかかってY方向の梁を所定位置まで下ろす
ことができず、X方向の梁の下端筋は一段配筋とせざる
を得なかった。
However, in the conventional method, the beams in the X and Y directions are perpendicular to each other, and the lower wires in the X direction overlap each other. When placing the beam, the beam streak is caught by the upper two-step lower streaks of the beam in the X direction and the beam in the Y direction cannot be lowered to a predetermined position, and the lower end streaks of the beam in the X direction must be arranged in one step. I didn't get it.

そのため、多くの梁筋を必要とする高層建築物には適
応できない等の制約があった。
Therefore, there is a restriction that it cannot be applied to a high-rise building requiring many beam reinforcements.

「問題点を解決するための手段」 この発明は前記従来の課題を解決するために、相対す
る接合端面の下部間において相互に連続一体の下端一段
筋によって連結され、かつ前記下端一段筋の上方におけ
る接合端面に短尺な下端二段筋を突設してなる水平X方
向に相対した一対のプレキャスト鉄筋コンクリート梁の
接合端部を、柱の頭部上に載せ、次いで相対する接合端
面の下端部において相互に連続一体の上下二段に配した
下端一段筋及び下端二段筋によって連結された水平Y方
向に相対した一対のプレキャスト鉄筋コンクリート梁の
接合端部を、柱の頭部上に載せ、前記X方向の下端二段
筋の先端にL型鉄筋をその先端部を上向きにして接合す
るようにしたプレキャスト鉄筋コンクリート構造物の柱
梁接合工法を提案するものである。
"Means for Solving the Problems" In order to solve the above-mentioned conventional problems, the present invention relates to a structure in which lower portions of opposed joint end faces are connected to each other by a lower continuous step which is continuous and integral with each other, and The joint ends of a pair of precast reinforced concrete beams facing each other in the horizontal X direction, which are formed by projecting short short two-step bars on the joint end surfaces of the above, are placed on the heads of the columns, and then at the lower ends of the opposed joint end surfaces. The joint ends of a pair of precast reinforced concrete beams facing each other in the horizontal Y direction, which are connected by a lower-end first step and a lower-end step, which are continuously and integrally integrated with each other, are placed on the head of a column. The present invention proposes a beam-to-column joining method for a precast reinforced concrete structure in which an L-shaped reinforcing bar is connected to the tip of a lower-end double-stepped bar in the direction with the tip facing upward.

「作用」 Y方向の梁を載せるとき、X方向の下端二段筋が短尺
に突設されているため、Y方向の下端一段筋はX方向の
梁の下端二段筋に引っかかることなくその先端間の間隙
を通過し、その結果Y方向の梁を柱上に支障なく載せる
ことができる。
[Operation] When the beam in the Y direction is placed, the lower step in the X direction is protruded short, so that the lower step in the Y direction does not catch on the lower step in the X direction. The beam in the Y direction can be placed on the pillar without any trouble.

Y方向の梁を載せた後にX方向の下端二段筋は、その
先端にL型鉄筋をその先端屈曲部を上向きにして接合す
るため、その後において柱梁接合部に打設したコンクリ
ートに確実に定着される。
After placing the beam in the Y direction, the lower two-step bar in the X direction joins the L-shaped reinforcing bar to the tip with the bent end of the tip facing upward, so that it is surely attached to the concrete cast at the beam-column joint. Be established.

従って、X方向の梁の下端二段筋の先端にL型鉄筋を
接合することにより、下端筋を上下二段に背筋すること
が可能となる。
Therefore, by joining the L-shaped reinforcing bar to the tip of the lower two-step bar of the beam in the X direction, the lower bar can be backed up and down in two steps.

「実施例」 以下この発明を図面に示す実施例について説明する
と、水平X方向に所要間隔で相対して配置する一対のプ
レキャスト鉄筋コンクリート梁1,1は、その相対する接
合端面の下部間において、相互に連続一体の下端一段筋
2によって連結されおり、この下端二段筋2の上方にお
ける接合端面にはそれぞれ少なくとも接合に最低必要な
突出長さを持った下端二段筋3,3が、後述のY方向の梁
1′,1′を直交状に配置するときにその下端筋にオーバ
ーラップしないように短尺に突設されている。
[Embodiment] The present invention will be described below with reference to an embodiment shown in the drawings. A pair of precast reinforced concrete beams 1 and 1 which are arranged at a required interval in the horizontal X direction are connected to each other between the lower portions of the opposing joint end faces. The lower end two-step streaks 3, 3 having at least the minimum required projection length for joining are respectively provided on the joint end faces above the lower end two-step streaks 2, which will be described later. When the beams 1 ', 1' in the Y direction are arranged orthogonally, they are shortly projected so as not to overlap the lower end muscle thereof.

水平Y方向に相対して配置する一対のプレキャスト鉄
筋コンクリート梁1′,1′は、その接合面間の下部間に
おいて上下二段の下端一段筋2′及び下端二段筋3′に
よって連結されている。
A pair of precast reinforced concrete beams 1 ′, 1 ′ arranged opposite to each other in the horizontal Y direction are connected by a lower two-step lower bar 2 ′ and a lower two-step bar 3 ′ in the lower part between the joint surfaces. .

柱梁の接合に際しては、まず第1図に示すように、上
方に柱筋5を突設したプレキャストコンクリートまたは
現場打ちコンクリートからなる柱4の頭部上にX方向の
梁1,1の端部を載せ、次いでY方向の梁1′,1′の端部
を柱4の頭部上に載せ、相互の下端一段筋2,2′同士を
直交上に重ねる。
When joining columns and beams, first, as shown in FIG. 1, the ends of the beams 1 and 1 in the X direction are placed on the heads of columns 4 made of precast concrete or cast-in-place concrete having column reinforcements 5 projecting upward. Then, the ends of the beams 1 ′, 1 ′ in the Y direction are placed on the head of the column 4, and the lower-end single-step streaks 2, 2 ′ are overlapped on each other at right angles.

Y方向の梁1′,1′を載せるとき、X方向の下端二段
筋3,3′が短尺に突設されているため、Y方向の下端一
段筋2′はその下端二段筋3′,3′に引っかかることな
くその先端間の間隙を通過するため、Y方向の梁1′,
1′を柱4上に支障なく載せることができる。
When the beams 1 ', 1' in the Y direction are placed, since the lower two-step reinforcements 3, 3 'in the X direction protrude in a short length, the lower one-step reinforcement 2' in the Y direction becomes the lower two-step reinforcement 3 '. , 3 'without passing through the gap between the tips, so that the beam 1' in the Y direction
1 'can be placed on the pillar 4 without any trouble.

次いでこの状態においてX方向の梁1,1の下端二段筋
3、3の先端にそれぞれL型鉄筋6をその屈曲先端部を
上向きにして溶接またはジョイントにより接合する。
Next, in this state, the L-shaped reinforcing bar 6 is joined to the distal ends of the lower two-step bars 3, 3 of the beams 1, 1 in the X direction by welding or joint with their bent distal ends facing upward.

このようにしてXY両方向の梁1,1′の下端筋をそれぞ
れ上下二段に配筋した後、第3図に示すように梁1,1′
上に上端筋7を配筋して、柱梁接合部及び梁1,1′の上
部に接合コンクリートを一体に打設すると共に、梁1,1
及び1′,1′の中間の接合部に接合コンクリートを一体
に打設する。
After arranging the lower end bars of the beams 1 and 1 ′ in both the XY directions in the upper and lower stages in this way, as shown in FIG.
Reinforcing the upper end bar 7 and casting concrete joints integrally on the beam-column joint and the upper part of the beam 1, 1 '.
And a joint concrete is integrally cast at the joint between 1 'and 1'.

なお、柱筋5はその突出先端を梁上面位置にとどめて
あるため、下端二段筋3,3とL型筋6の接合作業を柱筋
5が障害となることなく容易に行うことができることが
できる。
In addition, since the projecting end of the column bar 5 is kept at the upper surface of the beam, the joining work between the lower-end double-step bars 3, 3 and the L-shaped bar 6 can be easily performed without the column bar 5 becoming an obstacle. Can be.

「発明の効果」 以上の通りこの発明によれば、Y方向の梁を載せると
き、X方向の梁の接合端面間には下端二段筋が配筋され
ていないため、Y方向梁の上下二段の下端一段筋及び下
端二段筋をX方向の梁の下端一段筋に直交上に重ねて、
Y方向の梁を柱頭部上に支障なく載せることができる。
[Effects of the Invention] As described above, according to the present invention, when a beam in the Y direction is placed, no two-step lower reinforcement is provided between the joining end faces of the beam in the X direction. The lower end first step and the lower second step of the step are superimposed orthogonally on the lower step of the beam in the X direction,
The beam in the Y direction can be mounted on the column capital without any trouble.

また、X方向の下端二段筋は、その先端にL型鉄筋を
接合し、その屈曲先端部を上向きとするので、柱梁の接
合部に打設したコンクリートに確実に定着され、梁筋と
しての補強効果を達成することができる。
In addition, since the lower end double bar in the X direction has an L-shaped reinforcing bar joined to its tip and its bent tip facing upward, it is securely fixed to the concrete cast at the joint of the column and beam, and as a beam reinforcing bar Can achieve the reinforcing effect.

従って、柱梁接合部に梁下端筋を二段に配して柱梁接
合部の強度を制約なく強化することができる。
Therefore, it is possible to reinforce the strength of the beam-column joint without restriction by arranging the beam bottom reinforcement in two steps at the beam-column joint.

【図面の簡単な説明】[Brief description of the drawings]

第1図、第2図及び第3図はこの発明による柱梁接合工
程を順に示す側面図、第4図は従来の柱梁接合部の配筋
状態を示す側面図である。 1……X方向の梁、1′……Y方向の梁、2,2′……下
端一段筋、3,3′……下端二段筋、4……柱、5……柱
筋、6……L型鉄筋、7……梁上端筋。
1, 2 and 3 are side views sequentially showing a beam-to-column joining process according to the present invention, and FIG. 4 is a side view showing a state of reinforcing bars at a conventional beam-to-column joint. 1 ... beam in the X direction, 1 '... beam in the Y direction, 2,2' ... lower step first step, 3,3 '... lower step 2 step, 4 ... column, 5 ... column streak, 6 ... L-shaped reinforcing bar, 7.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】相対する接合端面の下部間において相互に
連続一体の下端一段筋によって連結され、かつ前記下端
一段筋の上方における接合端面に短尺な下端二段筋を突
設してなる水平X方向に相対した一対のプレキャスト鉄
筋コンクリート梁の接合端部を、柱の頭部上に載せ、次
いで相対する接合端面の下部間において相互に連続一体
の上下二段に配した下端一段筋及び下端二段筋によって
連結された水平Y方向に相対した一対のプレキャスト鉄
筋コンクリート梁の接合端部を、前記柱の頭部上に載
せ、前記X方向の下端二段筋の先端にL型鉄筋をその先
端屈曲部を上向きにして接合することを特徴とするプレ
キャスト鉄筋コンクリート構造物の柱梁接合工法。
A horizontal X which is connected between lower portions of opposing joint end surfaces by a continuous lower end single step, and has a short lower end double step protruding from the joint end surface above the lower end single step. The joint ends of a pair of precast reinforced concrete beams facing in the direction are placed on the head of the column, and then the lower end single streaks and the lower end two steps are arranged in a continuous two-step manner between the lower parts of the opposing joint end faces. A joint end of a pair of precast reinforced concrete beams opposed in the horizontal Y direction connected by a streak is placed on the head of the column, and an L-shaped reinforcing bar is bent at the tip of the two-step bar at the lower end in the X direction. A beam-to-column connection method for precast reinforced concrete structures, characterized in that they are joined with their faces facing upward.
JP15373090A 1990-06-12 1990-06-12 Beam-to-column connection method for precast reinforced concrete structures Expired - Fee Related JP2915500B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15373090A JP2915500B2 (en) 1990-06-12 1990-06-12 Beam-to-column connection method for precast reinforced concrete structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15373090A JP2915500B2 (en) 1990-06-12 1990-06-12 Beam-to-column connection method for precast reinforced concrete structures

Publications (2)

Publication Number Publication Date
JPH0444543A JPH0444543A (en) 1992-02-14
JP2915500B2 true JP2915500B2 (en) 1999-07-05

Family

ID=15568844

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15373090A Expired - Fee Related JP2915500B2 (en) 1990-06-12 1990-06-12 Beam-to-column connection method for precast reinforced concrete structures

Country Status (1)

Country Link
JP (1) JP2915500B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104164920A (en) * 2014-07-23 2014-11-26 南京长江都市建筑设计股份有限公司 Bottom steel bar connecting structure of key groove node precast frame beam

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3261089B2 (en) * 1997-12-29 2002-02-25 ボーグ・ワーナー・オートモーティブ株式会社 Link plate for silent chain
JP3470036B2 (en) * 1998-01-29 2003-11-25 ボルグワーナー・モールステック・ジャパン株式会社 Silent chain transmission

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104164920A (en) * 2014-07-23 2014-11-26 南京长江都市建筑设计股份有限公司 Bottom steel bar connecting structure of key groove node precast frame beam

Also Published As

Publication number Publication date
JPH0444543A (en) 1992-02-14

Similar Documents

Publication Publication Date Title
JP3712694B2 (en) Precast concrete joint structure
JP2915500B2 (en) Beam-to-column connection method for precast reinforced concrete structures
JP2001342679A (en) CONNECTING METHOD FOR PCa BEAM MEMBER AT COLUMN/BEAM JUNCTION AND PCa BEAM MEMBER FOR IT
JP2915498B2 (en) Beam-to-column connection method for precast reinforced concrete structures
JP2915499B2 (en) Beam-to-column connection method for precast reinforced concrete structures
JPH0673788A (en) Method of joining PC beams at column and beam joints
JP2976255B2 (en) Column and beam joint structure
JP2758208B2 (en) Joint method between column and steel reinforced concrete beam
JPH02252830A (en) Pre-assembled cross beam construction method
JP2729132B2 (en) How to join columns and precast concrete beams
JP2998450B2 (en) Connection method between PC beam and column
JP2004052389A (en) Panel zone construction method and precast beam
JPH07252882A (en) Construction method of construction frame
JPH0621470B2 (en) Lap joint method of main bars in column and beam joints
JPH0633513A (en) How to join columns and beams
JP2722209B2 (en) Precast concrete beams
JP2716634B2 (en) Column-beam joint structure
JPS61250240A (en) Connection of pc pillar and beam
JPS63251542A (en) Column and beam joint structure
JPH01187237A (en) Method for beam-column joining in precast reinforced concrete structure
JPH0830360B2 (en) Connection method for columns and beams
JP2572805Y2 (en) Precast reinforced concrete column and beam joint structure
JPH05331908A (en) How to join precast concrete beams
JPH05179698A (en) Construction of pc column and beam
JPH0438341A (en) Connection section structure of post beam

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees