JP2932970B2 - Existing building seismic isolation structuring method - Google Patents
Existing building seismic isolation structuring methodInfo
- Publication number
- JP2932970B2 JP2932970B2 JP14608195A JP14608195A JP2932970B2 JP 2932970 B2 JP2932970 B2 JP 2932970B2 JP 14608195 A JP14608195 A JP 14608195A JP 14608195 A JP14608195 A JP 14608195A JP 2932970 B2 JP2932970 B2 JP 2932970B2
- Authority
- JP
- Japan
- Prior art keywords
- upper structure
- seismic isolation
- isolation device
- column
- superstructure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は非免震構造の既設建物
を免震構造物に改修する既設建物の免震構造化方法に関
するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of converting an existing building having a non-seismic isolation structure into a seismic isolation structure.
【0002】[0002]
【従来技術及び発明が解決しようとする課題】非免震構
造の既設建物を免震装置を用いて免震構造物に改修する
場合、免震装置は柱の位置に設置されなければならない
ことから、免震装置設置位置の柱の回りにジャッキを設
置し、その柱が負担している荷重分をジャッキに負担さ
せた状態で柱を免震装置の高さ分切断して除去し、その
空間に免震装置を設置する作業を柱毎に繰り返して施工
する方法が考えられる。2. Description of the Related Art When retrofitting an existing non-seismic structure to a seismic isolation structure using a seismic isolation device, the seismic isolation device must be installed at the position of the pillar. A jack is installed around the pillar at the position where the seismic isolation device is installed, and the column is cut by the height of the seismic isolation device and removed while the jack bears the load that the column bears. It is conceivable to repeat the work of installing the seismic isolation device on each pillar.
【0003】この各柱毎に免震装置を設置する方法では
免震装置を挟んで下部構造から分離する上部構造の嵩上
げがないことから、上部構造の最下層の天井高を免震装
置の高さ分減少させることになる。また施工時は狭い空
間内での作業になるため施工性が悪い上、作業効率が低
下し、工期が長引くことになる。In the method of installing a seismic isolation device for each pillar, there is no rise in the upper structure separating the lower structure with the seismic isolation device interposed therebetween. It will be reduced. In addition, during construction, work is performed in a narrow space, so workability is poor, work efficiency is reduced, and the construction period is prolonged.
【0004】更に各柱毎に免震装置を設置するため免震
装置に荷重をかけたときの各免震装置の沈み込み量に差
が生じ易く、上部構造の水平精度が合わせにくい。Further, since a seismic isolation device is installed for each column, a difference is easily generated in the amount of sinking of each seismic isolation device when a load is applied to the seismic isolation device, and it is difficult to adjust the horizontal accuracy of the upper structure.
【0005】この発明は上記方法の問題を解消する免震
構造化の方法を提案するものである。[0005] The present invention proposes a method of seismic isolation structuring which solves the problems of the above method.
【0006】[0006]
【課題を解決するための手段】本発明では上部構造の梁
の下に上部構造を支持するジャッキを持つ架台を設置
し、架台で上部構造全体を支持したまま柱を切断し、ジ
ャッキで上部構造全体を上昇させて下部構造の柱と上部
構造の柱間に免震装置を設置した後、上部構造を支持し
ながら降下させることにより、各柱毎に免震装置を設置
する方法の問題を解消する。According to the present invention, a pedestal having a jack for supporting the upper structure is installed under a beam of the upper structure, a column is cut while the entire upper structure is supported by the gantry, and the upper structure is jacked. After installing the seismic isolation device between the lower structure column and the upper structure column by raising the whole, lowering while supporting the upper structure eliminates the problem of installing the seismic isolation device for each column I do.
【0007】架台で上部構造全体を支持したまま柱を切
断し、ジャッキで上部構造全体を上昇させて免震装置を
設置することにより免震装置の高さ分柱を除去すること
がなく、上部構造の最下層の天井高を減少させることが
ない。上部構造の最下層に新たに梁とスラブを構築する
場合にも天井高の減少は梁成以下に抑えられる。[0007] The pillar is cut while the entire upper structure is supported by the gantry, and the entire upper structure is lifted with a jack to install the seismic isolation device. It does not reduce the ceiling height at the bottom of the structure. Even when a new beam and slab is constructed on the lowermost layer of the superstructure, the decrease in ceiling height is suppressed to less than the beam height.
【0008】柱を上部構造の最下層の脚部に梁を含むレ
ベルで切断すれば、下部構造から分離した上部構造に手
を加えることなく、上部構造が免震装置の高さ分嵩上げ
された形で施工が完了する。この場合、下部構造の柱の
頂部に梁が接続しない状態になるため下部構造の剛性を
確保する必要があれば、下部構造の柱の頂部間に新たに
梁が架設される。If the pillar is cut at the level including the beam in the lowermost leg of the upper structure, the upper structure is raised by the height of the seismic isolation device without modifying the upper structure separated from the lower structure. The construction is completed in the form. In this case, the beams are not connected to the tops of the pillars of the lower structure, so if it is necessary to ensure the rigidity of the lower structures, new beams are erected between the tops of the pillars of the lower structure.
【0009】柱を下部構造の最上層の頂部に梁を含むレ
ベルで切断すれば、下部構造の柱の頂部に梁が接続する
が、上部構造の最下層の柱の脚部に梁が接続しなくなる
ため上部構造の柱の脚部間に新たに梁が架設される。If the pillar is cut at a level including a beam at the top of the uppermost layer of the lower structure, the beam is connected to the top of the column of the lower structure, but the beam is connected to the leg of the lowermost column of the upper structure. Because of this, a new beam is erected between the legs of the column of the superstructure.
【0010】施工時には上部構造全体の上昇により上部
構造と下部構造間に作業空間が確保されるため施工性が
向上する。また上部構造全体を上昇させて全免震装置を
設置した後に降下させることにより免震装置の設置効率
が上がり、工期の短縮が図られる。At the time of construction, a work space is secured between the upper structure and the lower structure by raising the entire upper structure, so that the workability is improved. In addition, by raising the entire superstructure, installing the seismic isolation device, and then lowering it, the installation efficiency of the seismic isolation device is increased, and the construction period is shortened.
【0011】加えて全免震装置を設置した後に上部構造
の降下が行われることにより各免震装置に均等に荷重を
加えることが可能で、上部構造の水平精度が確保され
る。水平精度は施工中も常に確保されるため既設建物を
使用状態においたまま施工を遂行することが可能にな
る。In addition, since the upper structure is lowered after all the seismic isolation devices are installed, it is possible to apply a load evenly to each seismic isolation device, and horizontal accuracy of the upper structure is ensured. Horizontal accuracy is always ensured during construction, so construction can be performed with existing buildings in use.
【0012】上部構造全体の上昇により上部構造と下部
構造間に一層分新たな躯体を構築することも可能にな
る。この場合、上部構造の最下層の脚部に梁を含むレベ
ルで柱が切断され、ジャッキで上部構造全体が少なくと
もその一層分上昇させられる。The rise of the entire upper structure makes it possible to construct a new frame between the upper structure and the lower structure. In this case, the pillar is cut at a level including the beam in the lowermost leg of the upper structure, and the entire upper structure is raised at least by the jack with the jack.
【0013】その後、下部構造の柱上に免震装置を設置
する一方、既設の上部構造の柱の下に、その柱に連続す
る柱とその脚部間に架設される梁を新たに構築した後、
新たに構築された柱・梁の躯体を含む上部構造を支持し
ながら降下させて施工が完了する。Thereafter, the seismic isolation device was installed on the lower structure column, and a beam continuous between the column and the leg was newly constructed below the existing upper structure column. rear,
The construction is completed by lowering while supporting the superstructure including the newly constructed columns and beams.
【0014】[0014]
【実施例】請求項1記載発明は図1〜図3に示すように
柱の切断によって既設建物を上部構造2と下部構造3に
区分し、上部構造2を上昇させた状態で両構造2,3間
に免震装置1を設置して上部構造2を免震構造化し、そ
のまま施工を完了させる方法である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS As shown in FIGS. 1 to 3, the present invention divides an existing building into an upper structure 2 and a lower structure 3 by cutting off pillars. This is a method in which the seismic isolation device 1 is installed between the three to make the upper structure 2 a seismic isolation structure and the construction is completed as it is.
【0015】図1は既設建物とその柱の切断位置を示す
が、この発明では上部構造2と下部構造のいずれにも新
たに躯体を付加しないため少なくとも上部構造2の剛性
を確保する必要から、梁22が上部構造2の柱21に接続し
た形になるよう、上部構造2の梁22の下端のレベルのよ
うに、上部構造2の最下層の脚部に梁22を含むレベルで
柱が切断される。FIG. 1 shows the existing building and the cutting positions of the pillars. In the present invention, since no new frame is added to either the upper structure 2 or the lower structure, it is necessary to secure at least the rigidity of the upper structure 2. The pillar is cut at the level including the beam 22 at the lowermost leg of the upper structure 2, such as at the lower end level of the beam 22 of the upper structure 2, so that the beam 22 is connected to the column 21 of the upper structure 2. Is done.
【0016】柱の切断に先立ち、免震装置1が設置され
る、上部構造2の一部となる柱21の近傍の梁22の下に上
部構造2を支持するジャッキ4を持つ架台5が設置され
る。Prior to cutting the columns, a gantry 5 having a jack 4 for supporting the upper structure 2 is installed under a beam 22 near a column 21 which is a part of the upper structure 2 where the seismic isolation device 1 is installed. Is done.
【0017】架台5の設置後、架台5で上部構造2の全
体を支持したまま柱を切断して上部構造2と下部構造3
の柱21,31に分離させ、既設建物を上部構造2と下部構
造3に区分する。After the gantry 5 is installed, the pillars are cut while supporting the entire upper structure 2 with the gantry 5 and the upper structure 2 and the lower structure 3 are cut.
The existing building is divided into an upper structure 2 and a lower structure 3.
【0018】続いて図2に示すように免震装置1の高さ
以上で、施工に必要な高さ分ジャッキ4で上部構造2全
体を上昇させ、上部構造2の柱21と下部構造3の柱31間
の空間に免震装置1を設置し、これを下部構造3の柱31
に接続する。その後、図3に示すように上部構造2を架
台5で支持したまま降下させ、上部構造2の柱21の下端
を免震装置1に接続し、施工が終了する。この方法では
上部構造2は免震装置1の高さ分上昇して免震構造化さ
れる。Subsequently, as shown in FIG. 2, the entire upper structure 2 is raised by the jack 4 by the height required for construction above the height of the seismic isolation device 1, and the columns 21 of the upper structure 2 and the lower structure 3 The seismic isolation device 1 is installed in the space between the pillars 31, and the
Connect to Thereafter, as shown in FIG. 3, the upper structure 2 is lowered while being supported by the gantry 5, the lower end of the column 21 of the upper structure 2 is connected to the seismic isolation device 1, and the construction is completed. In this method, the upper structure 2 is raised by the height of the seismic isolation device 1 to form a seismic isolation structure.
【0019】請求項2記載発明は図4に示すように請求
項1記載発明において、下部構造3の剛性を確保する目
的で、下部構造3の柱31,31の頂部間に新たに梁6を架
設して施工を完了させる方法である。梁6のみでは下部
構造3の剛性が不足する場合は梁6に加えてスラブ7も
構築される。In the second aspect of the present invention, as shown in FIG. 4, in order to secure the rigidity of the lower structure 3, a beam 6 is newly provided between the tops of the columns 31 of the lower structure 3 in order to secure the rigidity of the lower structure 3. It is a method to complete construction by erection. If the rigidity of the lower structure 3 is insufficient with only the beam 6, a slab 7 is also constructed in addition to the beam 6.
【0020】この発明では請求項1記載発明の下部構造
3に梁6、または梁6とスラブ7を付加する形であるた
め、柱の切断位置と、免震装置1の設置までの施工は請
求項1記載発明と同じである。In this invention, since the beam 6 or the beam 6 and the slab 7 are added to the substructure 3 according to the first aspect of the present invention, the cutting position of the column and the construction up to the installation of the seismic isolation device 1 are required. Same as the invention described in Item 1.
【0021】請求項3記載発明は図5に示すように下部
構造3の柱31の頂部に梁32が接続する位置で既設建物を
区分し、上部構造2の柱21の脚部に梁6、または梁6と
スラブ7を付加する方法である。柱21は下部構造3の梁
32の上端のレベルのように、下部構造3の最上層の頂部
に梁32を含むレベルで切断される。According to the third aspect of the present invention, as shown in FIG. 5, the existing building is divided at the position where the beam 32 is connected to the top of the column 31 of the lower structure 3, and the beam 6 is attached to the leg of the column 21 of the upper structure 2. Alternatively, a beam 6 and a slab 7 are added. Pillar 21 is the beam of substructure 3
The lower structure 3 is cut at a level that includes the beam 32 at the top of the uppermost layer, such as at the top level.
【0022】この発明では上部構造2の柱21の脚部が梁
に接続しなくなるため、免震装置1を設置し、免震装置
1を下部構造3の柱31に接続する一方、上部構造2の柱
21,21の脚部間に梁6、または梁6とスラブ7が架設さ
れる。梁6、または梁6とスラブ7の構築後、上部構造
2を支持しながら降下させ、上部構造2の柱21の下端を
免震装置1に接続して、もしくは上部構造2を支持しな
がら降下させ、上部構造2の柱21の下端を免震装置1に
接続した後、梁6、または梁6とスラブ7の構築によっ
て施工が完了する。In the present invention, since the legs of the column 21 of the upper structure 2 are not connected to the beam, the seismic isolation device 1 is installed, and the seismic isolation device 1 is connected to the column 31 of the lower structure 3 while the upper structure 2 is connected. Pillar
The beam 6 or the beam 6 and the slab 7 are erected between the legs 21 and 21. After constructing the beam 6, or the beam 6 and the slab 7, lower it while supporting the upper structure 2, and connect the lower end of the column 21 of the upper structure 2 to the seismic isolation device 1 or lower while supporting the upper structure 2. After the lower end of the column 21 of the upper structure 2 is connected to the seismic isolation device 1, the construction is completed by building the beam 6, or the beam 6 and the slab 7.
【0023】請求項4記載発明は図6に示すように上部
構造2の下に一層分の柱8と梁6からなる躯体を構築
し、上部構造2を一層分上昇させた状態で完成させる方
法である。この発明でも躯体の構築時にスラブ7が構築
される場合がある。According to a fourth aspect of the present invention, as shown in FIG. 6, a method of constructing a skeleton including one layer of columns 8 and beams 6 under the upper structure 2, and completing the upper structure 2 in a state where the upper structure 2 is further raised. It is. Also in the present invention, the slab 7 may be constructed at the time of constructing the skeleton.
【0024】柱は請求項1記載発明と同じく上部構造2
の最下層の脚部に梁21を含むレベルで切断される。柱の
切断後、ジャッキ4で上部構造2全体を少なくともその
一層分上昇させて下部構造3の柱31上に免震装置1を設
置し、下部構造3の柱31に接続する。The column is the same as the first aspect of the present invention.
The lowermost leg is cut at a level including the beam 21. After the column is cut, the entire upper structure 2 is raised at least one layer by the jack 4, the seismic isolation device 1 is installed on the column 31 of the lower structure 3, and connected to the column 31 of the lower structure 3.
【0025】その後、上部構造2の柱21の下に新たに柱
8を連続して構築し、その新設の柱8の脚部間に梁6、
または梁6とスラブ7を構築した後、新たに構築された
柱8と梁6からなる躯体を含む上部構造2を支持しなが
ら降下させ、その柱8の下端を免震装置1に接続して施
工が終了する。この発明でも請求項2記載発明と同様に
下部構造3の柱31,31の頂部間に梁6、または梁6とス
ラブ7を新たに構築する場合がある。Thereafter, a new column 8 is continuously constructed under the column 21 of the upper structure 2, and the beam 6 is inserted between the legs of the newly provided column 8.
Alternatively, after the beam 6 and the slab 7 are constructed, the beam is lowered while supporting the newly constructed upper structure 2 including the frame composed of the column 8 and the beam 6, and the lower end of the column 8 is connected to the seismic isolation device 1. Construction ends. In this invention, the beam 6 or the beam 6 and the slab 7 may be newly constructed between the tops of the columns 31, 31 of the lower structure 3 in the same manner as the second aspect of the invention.
【0026】[0026]
【発明の効果】上部構造の梁の下に上部構造を支持する
ジャッキを持つ架台を設置し、架台で上部構造全体を支
持したまま柱を切断し、ジャッキで上部構造全体を上昇
させて下部構造の柱と上部構造の柱間に免震装置を設置
した後、上部構造を支持しながら降下させて上部構造を
免震構造化する方法であるため、免震装置の高さ分上部
構造の柱を除去することがなく、上部構造の最下層の天
井高を減少させることがない。上部構造の最下層に新た
に梁とスラブを構築する場合にも天井高の減少は梁成以
下に抑えられる。According to the present invention, a gantry having a jack for supporting the upper structure is installed under the beam of the upper structure, the pillar is cut while the entire upper structure is supported by the gantry, and the entire upper structure is raised by the jack, thereby lowering the lower structure. After installing the seismic isolation device between the pillars of the upper structure and the columns of the upper structure, the upper structure is lowered by supporting the upper structure and the upper structure is seismically isolated. And the ceiling height of the lowermost layer of the upper structure is not reduced. Even when a new beam and slab is constructed on the lowermost layer of the superstructure, the decrease in ceiling height is suppressed to less than the beam height.
【0027】柱を上部構造の最下層の脚部に梁を含むレ
ベルで切断すれば、下部構造から分離した上部構造に手
を加えることなく上部構造が免震装置の高さ分嵩上げさ
れた形で施工が完了するため、簡単に上部構造を免震構
造化することができる。If the column is cut at the level including the beam at the lowermost leg of the upper structure, the upper structure is raised by the height of the seismic isolation device without modifying the upper structure separated from the lower structure. Since the construction is completed, the upper structure can be easily made into a seismic isolation structure.
【0028】施工時には上部構造全体を上昇させるため
上部構造と下部構造間に作業空間を確保でき、施工性が
向上する。また上部構造全体を上昇させて全免震装置を
設置した後に降下させるため免震装置の設置効率がよ
く、工期の短縮が図られる。At the time of construction, since the entire upper structure is raised, a work space can be secured between the upper structure and the lower structure, and workability is improved. In addition, since the entire upper structure is raised and all the seismic isolation devices are installed and then lowered, the installation efficiency of the seismic isolation devices is good and the construction period is shortened.
【0029】加えて全免震装置を設置した後に上部構造
の降下が行われることにより各免震装置に均等に荷重を
加えることが可能で、上部構造の水平精度が確保され
る。水平精度は施工中も常に確保されるため既設建物を
使用状態においたまま施工を遂行することが可能にな
る。In addition, since the upper structure is lowered after all the seismic isolation devices are installed, a load can be applied evenly to each seismic isolation device, and the horizontal accuracy of the upper structure is ensured. Horizontal accuracy is always ensured during construction, so construction can be performed with existing buildings in use.
【0030】更に上部構造全体の上昇により上部構造と
下部構造間に一層分新たな躯体を構築することも可能に
なる。Further, the rise of the entire upper structure makes it possible to construct a new frame between the upper structure and the lower structure.
【図1】既設建物とその切断位置を示した立面図であ
る。FIG. 1 is an elevation view showing an existing building and its cutting position.
【図2】上部構造を上昇させた様子を示した立面図であ
る。FIG. 2 is an elevation view showing a state where the upper structure is raised.
【図3】免震装置を設置した様子を示した立面図であ
る。FIG. 3 is an elevation view showing a state where a seismic isolation device is installed.
【図4】請求項2記載発明で免震装置を設置した様子を
示した立面図である。FIG. 4 is an elevation view showing a state where a seismic isolation device is installed according to the second aspect of the invention.
【図5】請求項3記載発明で免震装置を設置した様子を
示した立面図である。FIG. 5 is an elevation view showing a state in which a seismic isolation device is installed according to the third aspect of the present invention.
【図6】請求項4記載発明で免震装置を設置した様子を
示した立面図である。FIG. 6 is an elevation view showing a state in which a seismic isolation device is installed according to the invention described in claim 4;
1……免震装置、2……上部構造、21……柱、22……
梁、3……下部構造、31……柱、32……梁、4……ジャ
ッキ、5……架台、6……梁、7……スラブ、8……
柱。1 ... seismic isolation device, 2 ... superstructure, 21 ... pillar, 22 ...
Beam, 3 ... Lower structure, 31 ... Column, 32 ... Beam, 4 ... Jack, 5 ... Stand, 6 ... Beam, 7 ... Slab, 8 ...
Pillar.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 上野 薫 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (72)発明者 斉藤 一 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (72)発明者 荻原 行正 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (56)参考文献 特開 平2−20767(JP,A) 特開 平2−104833(JP,A) 特開 昭62−121281(JP,A) 特開 平2−70831(JP,A) 実開 昭62−69555(JP,U) (58)調査した分野(Int.Cl.6,DB名) E04H 9/02 E04G 23/02 ──────────────────────────────────────────────────続 き Continued on the front page (72) Kaoru Ueno, Inventor Kaoru 1-2-7 Motogasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Kazuto Saito 1-2-7 Motomoto Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Yukimasa Ogihara 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (56) References JP-A-2-20767 (JP, A) JP-A-2 -104833 (JP, A) JP-A-62-121281 (JP, A) JP-A-2-70831 (JP, A) JP-A-62-69555 (JP, U) (58) Fields investigated (Int. . 6 , DB name) E04H 9/02 E04G 23/02
Claims (4)
し、両構造間に免震装置を設置して上部構造を免震構造
化する方法であり、上部構造の梁の下に上部構造を支持
するジャッキを持つ架台を設置し、架台で上部構造全体
を支持したまま上部構造の最下層の脚部に梁を含むレベ
ルで柱を切断し、ジャッキで上部構造全体を上昇させて
下部構造の柱と上部構造の柱間に免震装置を設置した
後、上部構造を支持しながら降下させる既設建物の免震
構造化方法。1. A method of dividing an existing building into an upper structure and a lower structure, and installing a seismic isolation device between the two structures to convert the upper structure into a seismic isolation structure. Install a frame with a jack to support, cut the pillar at the level including the beam on the lowermost leg of the upper structure while supporting the entire upper structure with the frame, raise the entire upper structure with the jack, A seismic isolation structuring method for an existing building in which a seismic isolation device is installed between the pillar and the pillar of the superstructure, and then lowered while supporting the superstructure.
し、両構造間に免震装置を設置して上部構造を免震構造
化する方法であり、上部構造の梁の下に上部構造を支持
するジャッキを持つ架台を設置し、架台で上部構造全体
を支持したまま上部構造の最下層の脚部に梁を含むレベ
ルで柱を切断し、ジャッキで上部構造全体を上昇させて
下部構造の柱と上部構造の柱間に免震装置を設置した
後、上部構造を支持しながら降下させる一方、下部構造
の柱の頂部間に梁を架設する既設建物の免震構造化方
法。2. A method for dividing an existing building into an upper structure and a lower structure, and installing a seismic isolation device between the two structures to convert the upper structure into a seismic isolation structure. Install a base with a jack to support, cut the pillar at the level including the beam on the lowermost leg of the upper structure while supporting the entire upper structure with the base, raise the entire upper structure with the jack, A seismic isolation structuring method for an existing building in which a seismic isolation device is installed between a column and a superstructure column, and then lowered while supporting the superstructure, while a beam is erected between the tops of the lower structure columns.
し、両構造間に免震装置を設置して上部構造を免震構造
化する方法であり、上部構造の梁の下に上部構造を支持
するジャッキを持つ架台を設置し、架台で上部構造全体
を支持したまま下部構造の最上層の頂部に梁を含むレベ
ルで柱を切断し、ジャッキで上部構造全体を上昇させて
下部構造の柱と上部構造の柱間に免震装置を設置した
後、上部構造を支持しながら降下させる一方、上部構造
の柱の脚部間に梁を架設する既設建物の免震構造化方
法。3. A method of dividing an existing building into an upper structure and a lower structure, and installing a seismic isolation device between the two structures to convert the upper structure into a seismic isolation structure. Install a gantry with a jack to support, cut the pillars at the level including the beam at the top of the uppermost layer of the lower structure while supporting the entire upper structure with the gantry, and raise the entire upper structure with the jack to raise the pillars of the lower structure After installing a seismic isolation device between the pillars of the superstructure and lowering it while supporting the superstructure, a method of seismic isolation of an existing building in which a beam is erected between the legs of the columns of the superstructure.
し、両構造間に免震装置を設置して上部構造を免震構造
化する方法であり、上部構造の梁の下に上部構造を支持
するジャッキを持つ架台を設置し、架台で上部構造全体
を支持したまま上部構造の最下層の脚部に梁を含むレベ
ルで柱を切断し、ジャッキで上部構造全体を少なくとも
上部構造の一層分上昇させ、下部構造の柱上に免震装置
を設置する一方、既設の上部構造の柱の下に、上部構造
の柱に連続する柱とその柱の脚部間に架設される梁を新
たに構築した後、新たに構築された柱・梁の躯体を含む
上部構造を支持しながら降下させる既設建物の免震構造
化方法。4. A method of dividing an existing building into an upper structure and a lower structure, and installing a seismic isolation device between the two structures to convert the upper structure into a seismic isolation structure. Install a gantry with a jack to support, cut the pillar at the level including the beam on the lowermost leg of the upper structure while supporting the entire upper structure with the gantry, and jack the entire upper structure at least one layer of the upper structure Raise and install the seismic isolation device on the pillars of the substructure.On the other hand, under the columns of the existing superstructure, add a column connected to the column of the superstructure and a beam to be installed between the legs of the column. After building, a seismic isolation structuring method for an existing building that is lowered while supporting the superstructure including the newly constructed columns and beams.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14608195A JP2932970B2 (en) | 1995-06-13 | 1995-06-13 | Existing building seismic isolation structuring method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14608195A JP2932970B2 (en) | 1995-06-13 | 1995-06-13 | Existing building seismic isolation structuring method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH08338155A JPH08338155A (en) | 1996-12-24 |
| JP2932970B2 true JP2932970B2 (en) | 1999-08-09 |
Family
ID=15399693
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP14608195A Expired - Fee Related JP2932970B2 (en) | 1995-06-13 | 1995-06-13 | Existing building seismic isolation structuring method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2932970B2 (en) |
Families Citing this family (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2916674B2 (en) * | 1995-10-06 | 1999-07-05 | 株式会社総研設計 | Seismic isolation repair method for existing buildings |
| JPH10121746A (en) * | 1996-10-23 | 1998-05-12 | Okumura Corp | Seismic isolation structure of existing building |
| JP2001182371A (en) * | 1999-12-24 | 2001-07-06 | Mitsubishi Heavy Ind Ltd | Installation method for seismic isolator to base isolation steel tower and existing steel tower |
| KR20030073280A (en) * | 2002-03-09 | 2003-09-19 | 오원균 | A system for increase of Heigrt a concrete building. |
| JP5800570B2 (en) * | 2011-05-18 | 2015-10-28 | 住友不動産株式会社 | Intermediate seismic isolation structure using flat reverse beams |
| CN102864943B (en) * | 2012-10-11 | 2016-08-03 | 北京筑福国际工程技术有限责任公司 | Shock isolating pedestal brick is mixed fixing structure and installs support and change method |
| JP6543143B2 (en) * | 2015-09-08 | 2019-07-10 | 株式会社竹中工務店 | Seismic isolation repair structure of existing building, and seismic isolation repair method of existing building |
| JP6706472B2 (en) * | 2015-09-09 | 2020-06-10 | 大成建設株式会社 | Seismic isolation repair method for existing buildings |
| CN106436747A (en) * | 2016-11-11 | 2017-02-22 | 中铁三局集团广东建设工程有限公司 | Full-automatic pile foundation underpinning device and construction method |
-
1995
- 1995-06-13 JP JP14608195A patent/JP2932970B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH08338155A (en) | 1996-12-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2932970B2 (en) | Existing building seismic isolation structuring method | |
| CN112681525B (en) | Jacking and supporting system and method for large-span steel structure | |
| JP3186519B2 (en) | Lift-up method | |
| JP2979039B2 (en) | Large space building construction equipment | |
| JP3246287B2 (en) | Jack-up method for existing buildings | |
| JPH09242191A (en) | Construction of large span structure | |
| JP2002235446A (en) | Demolition method of building | |
| JP2890341B2 (en) | Method and apparatus for lifting up top-level frame for structure construction | |
| JP2003328587A (en) | Seismic isolation method for existing buildings | |
| JP2547920B2 (en) | Push-up method and equipment for large span structures | |
| JPH08270081A (en) | Construction method of frame structure | |
| JP2793053B2 (en) | Building construction method | |
| JP2871468B2 (en) | How to build a building | |
| JP2595614Y2 (en) | Push-up rack for large span structures | |
| JP3416759B2 (en) | Underground structure frame building equipment | |
| JP2003343092A (en) | Seismic isolation method for existing buildings | |
| JPH07259191A (en) | All-weather construction method for structures | |
| JP2696486B2 (en) | Building construction method | |
| JP2791749B2 (en) | Method and apparatus for lifting up top-level frame for structure construction | |
| JP2006022557A (en) | Base isolating technique for existing building | |
| JP2592980B2 (en) | Construction method of steel frame material for high-rise structure | |
| JPH0762896A (en) | Upper part extension method for building | |
| JP3139854B2 (en) | Collapse prevention frame | |
| JP3125205B2 (en) | Construction method of temporary side wall | |
| JP2019070298A (en) | Building construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19990427 |
|
| LAPS | Cancellation because of no payment of annual fees |