JP2946372B2 - Construction method of structure - Google Patents
Construction method of structureInfo
- Publication number
- JP2946372B2 JP2946372B2 JP20234392A JP20234392A JP2946372B2 JP 2946372 B2 JP2946372 B2 JP 2946372B2 JP 20234392 A JP20234392 A JP 20234392A JP 20234392 A JP20234392 A JP 20234392A JP 2946372 B2 JP2946372 B2 JP 2946372B2
- Authority
- JP
- Japan
- Prior art keywords
- shaft
- ground
- construction
- building
- work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims description 33
- 238000000034 method Methods 0.000 claims description 17
- 230000003028 elevating effect Effects 0.000 claims description 6
- 230000001174 ascending effect Effects 0.000 claims 1
- 229910000831 Steel Inorganic materials 0.000 description 9
- 239000000463 material Substances 0.000 description 9
- 239000010959 steel Substances 0.000 description 9
- 229910000906 Bronze Inorganic materials 0.000 description 4
- 239000010974 bronze Substances 0.000 description 4
- KUNSUQLRTQLHQQ-UHFFFAOYSA-N copper tin Chemical compound [Cu].[Sn] KUNSUQLRTQLHQQ-UHFFFAOYSA-N 0.000 description 4
- 230000007774 longterm Effects 0.000 description 4
- 239000011521 glass Substances 0.000 description 3
- 230000002093 peripheral effect Effects 0.000 description 3
- 239000004567 concrete Substances 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000005304 joining Methods 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は、中,高層の構造物を
高所作業なしで行なう場合に好適に実施される建築方法
に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method which is preferably carried out when a middle or high-rise structure is to be carried out without working at a high place.
【0002】[0002]
【従来の技術】従来、構造物や建物を建築する場合は、
それが低層物であるか高層物であるかの別なく、先ず地
盤上に基礎を構築し、この基礎の上に構造物や建物の躯
体を下から上方へ順に積み重ねる方式で建方を進めるの
が一般的である。2. Description of the Related Art Conventionally, when building a structure or a building,
Regardless of whether it is a low-rise building or a high-rise building, first build a foundation on the ground, and proceed with the construction method by stacking structures and building frames on this foundation in order from bottom to top. Is common.
【0003】[0003]
【本発明が解決しようとする課題】 基礎の上に構造物や建物の躯体を下層から上層へ順
に積み重ねて建方を進める建築方法の場合は、建築の進
捗に伴って高い足場や養生の仮設が必要である。また、
高所作業用のクレーン等の重機が必要となる。そして、
ほとんどの建築作業が高所作業となって安全性の確保が
難しい。更に、人員や資材類の垂直運搬がくり返し必要
となり、そのための輸送費や仮設費が嵩むことになる。
勿論、建築の終了後には仮設物の撤去のための作業工程
も不可欠である。 従来一般の積み重ね方式の建築を進める場合、構造
物躯体に加わる長期鉛直荷重は、建築の進捗と共に増加
し、歪みも増大する。従って、サッシュやガラス等を取
付ける外装、仕上げの工事の精度、品質を確保するため
には、躯体を最上層まで完成し、長期鉛直荷重及び歪み
の大きさがほぼ確定した後でなければ、実際上作業を開
始できない。更に、外装材、仕上げ材の重量まで厳格に
考慮すると、外装、仕上げ工事は構造物の最上層から下
層に向かって下向きに進めるべきであるから作業工程が
煩雑になるという問題点があった。 従って、本発明の目的は、躯休の建方から外装、仕
上げ工事まで全ての作業工程を地上レベルでの地上作業
として、しかも精度、品質を確保して行なうことがで
き、危険な高所作業が発生せず、高い足場や養生の仮
設、あるいは高所作業のためのクレーン等の重機が不要
な建築方法を提供することである。[Problems to be solved by the present invention] In the case of a building method in which structures and buildings of a building are sequentially stacked from the lower layer to the upper layer on a foundation and the building is advanced, a temporary mounting of a high scaffolding and curing with the progress of the building. is necessary. Also,
Heavy equipment such as cranes for working at heights is required. And
Most construction work is performed at heights, making it difficult to ensure safety. Furthermore, vertical transportation of personnel and materials is required repeatedly, which increases transportation costs and temporary costs.
Of course, after the construction is completed, a work process for removing the temporary structure is indispensable. When a conventional stack-type building is advanced, the long-term vertical load applied to the structural body increases with the progress of the building, and the distortion also increases. Therefore, in order to secure the accuracy and quality of the exterior and finishing work for attaching sash and glass, etc., it is necessary to complete the frame up to the uppermost layer and actually determine the magnitude of long-term vertical load and strain until it is almost determined. Can not start work on. Furthermore, when the weight of the exterior material and the finishing material is strictly considered, there is a problem that the exterior and finishing work must proceed downward from the uppermost layer of the structure to the lower layer, so that the work process becomes complicated. Therefore, an object of the present invention is to perform all work processes from the construction of the building suspension to the exterior and finishing work as ground work at the ground level, and with accuracy and quality assured, and dangerous high-place work. An object of the present invention is to provide a construction method which does not generate heavy scaffolding and curing, and does not require heavy equipment such as a crane for working at heights.
【0004】[0004]
【課題を解決するための手段】上記した従来技術の課題
を解決するための手段として、この発明に係る構造物の
建築方法は、図面に実施例を示したとおり、少なくとも
構造物10の地上高さと同等な深さ及び水平断面形状と
同等な口径及び平面形状の縦坑2を、構造物の建設予定
地の地盤に掘削し構築する段階と、構造物10の躯体1
0’を地上1階部分から高層部分への順序で、前記縦坑
2の開口面上の地上作業としてモジュール単位毎の建方
を行ない、前記モジュール単位の建方を終了する度に同
モジュール単位の高さ分ずつ縦坑2内に下降させる工程
のくり返しにより構造物の躯体10’を最上層まで建方
を行う段階と、次に躯体10’の最上層部分から外装、
仕上げ工事を地上作業として行ない、この外装、仕上げ
工事の進捗に従って縦坑2内の躯体10’を施工単位の
高さ分ずつ上昇させる段階と、構造物10がその地上1
階部分まで上昇した段階で地盤への定着を行なうこと、
を特徴とする。As a means for solving the above-mentioned problems of the prior art, a method of building a structure according to the present invention is to use at least a ground clearance of the structure 10 as shown in the embodiment in the drawings. Excavating and constructing a shaft 2 having a diameter and a plane shape equivalent to a depth and a horizontal cross-sectional shape equivalent to the above, on the ground at the site where the structure is to be constructed, and the skeleton 1 of the structure 10
0 ′ is set in the order from the first floor to the high-rise part, and the construction of each module is performed as ground work on the opening surface of the shaft 2, and each time the construction of the module is completed, A step of constructing the skeleton 10 ′ of the structure to the uppermost layer by repeating the process of descending into the shaft 2 by the height of
The finishing work is performed as ground work, and the building 10 ′ in the shaft 2 is raised by the height of the construction unit according to the progress of the exterior and finishing work.
To settle on the ground at the stage where it has risen to the floor,
It is characterized by.
【0005】本発明の建築方法において、構造物の躯体
10’の建方は、縦坑2の口縁部に設置した昇降機構5
で縦坑2内に支持された受けステージ4の上で行ない、
前記昇降機構5による前記受けステージ4の下降又は上
昇の操作によって構造物の躯体10’を縦坑2内へ下降
させ又は上昇させること、及び、構造物の躯体10’の
建方を縦坑2内で完成した後、この躯体10’を施工単
位の高さ分ずつ上昇させる工程に追従して縦坑2内の下
底面から上方に向かって順に反力基礎3を段階的に構築
してゆき、最終的に構造物10は前記反力基礎3を利用
して地盤への定着を行なうこと、もそれぞれ特徴とす
る。In the construction method of the present invention, the construction of the frame 10 ′ of the structure is performed by the lifting mechanism 5 installed at the edge of the shaft 2.
On the receiving stage 4 supported in the shaft 2
The structure 10 'is lowered or raised into the shaft 2 by the operation of lowering or raising the receiving stage 4 by the elevating mechanism 5, and the construction of the structure 10' is changed to the shaft 2 After completion within the shaft, the reaction foundation 3 is gradually built up from the lower bottom surface of the shaft 2 following the process of raising the frame 10 'by the height of the construction unit. Finally, the structure 10 is also characterized in that it is fixed to the ground using the reaction force foundation 3.
【0006】[0006]
【作用】構造物の躯体10’をモジュール単位で建方す
る度に同モジュール単位の高さ分ずつ縦坑2内に下降さ
せるので、前記の建方作業は常に地上レベルの地上作業
として行なえ、高い足場等や養生を仮設する必要がない
ことは勿論のこと、人員や資材類の運搬、移動も常に水
平方向だけで済む。[Effect] Each time the structural body 10 'is constructed in units of module, it is lowered into the shaft 2 by the height of the same module unit, so that the above-mentioned construction work can always be performed as ground work at the ground level. Of course, there is no need to temporarily mount high scaffolds or cures, and personnel and materials can always be transported and moved only in the horizontal direction.
【0007】構造物10の最上層まで建方した段階にお
いても、その最上層はやはり地上レベルに位置するの
で、そのまま直ちに最上層部分から外装、仕上げ工事を
地上作業として理想的に開始できる。即ち、以後の外
装、仕上げ工事は、全て構造物の各層における長期鉛直
荷重及び歪みの大きさが完成状態と同一の条件に確定し
た状態で行なわれ、品質、精度の確保が容易である。[0007] Even when the uppermost layer of the structure 10 is erected, the uppermost layer is also located at the ground level, so that the exterior and finishing work can be ideally started immediately from the uppermost layer as ground work. In other words, the subsequent exterior and finishing works are all performed in a state where the magnitude of the long-term vertical load and strain in each layer of the structure is determined under the same conditions as in the completed state, and quality and accuracy can be easily secured.
【0008】[0008]
【実施例】次に、図示した本発明の実施例を説明する。
図1は、建築をほぼ完成した構造物の全景を示してい
る。この構造物は、2本一組のタワー構造物10、10
の上端部に平版状の盤体12が架設された構成である。
タワー構造物10は、地上からの高さが約80mぐらい
の鋼構造躯体から成り、外周面はガラス面として仕上げ
られている。盤体12は、せいの高さが5.7m、幅は
32m位で、スパンは約300mもある長大な鋼構造躯
体から成り、その外周面は青銅パネル又はブロンズパネ
ル仕上げとされている。盤体12の鋼構造躯体には、ス
パン方向にPC鋼材を配置し、プレストレスを導入して
水平なレベル出しを行ない、且つ変形を防ぐ構成とされ
ている。BRIEF DESCRIPTION OF THE DRAWINGS FIG.
FIG. 1 shows a full view of a structure in which the building has been almost completed. The structure comprises a pair of tower structures 10, 10
A planographic board 12 is erected at the upper end of the slab.
The tower structure 10 is made of a steel structure having a height from the ground of about 80 m, and its outer peripheral surface is finished as a glass surface. The disk body 12 is composed of a long steel structural body having a height of 5.7 m, a width of about 32 m and a span of about 300 m, and its outer peripheral surface is finished with a bronze panel or a bronze panel. A PC steel material is arranged in the steel structure skeleton of the board body 12 in the span direction, pre-stress is introduced to perform horizontal leveling, and deformation is prevented.
【0009】次に、図2〜図4は上記構造物の建築を開
始した初期の段階を示している。なお、本実施例は、建
設予定地の地理的交通事情が悪いため、人員や資材類の
輸送を地下に構築したトンネル13,14で行なう場合
を示しているが、この点はケースバイケースで実施され
るものと理解されたい。図3によれば、境界線15で表
示した比較的狭く限られたヤードの中で、盤体12の地
組みが、クローラクレーン16と、溶接養生用の移動上
屋17を利用した全天候型作業として行なわれている。
そして、盤体12の両端部の位置には、前記のタワー構
造物10を構築するために利用される縦坑2が構築され
たことを示している。図2と図4によれば、前記縦坑2
は、タワー構造物10の躯体構築に利用するため、タワ
ー構造物10の建設予定地の地盤に、タワー構造物10
の地上高さ(約80m)と略同じ深さ及び同タワー構造
物10の水平断面形状(たてが約3m,よこが約18m
ぐらいの長方形が2個並列)と同等な口径及び平面形状
(短径が20m、長径が42mぐらいの長円形状)に掘
削し構築されている。と云うのも、縦坑2の底には前述
のトンネル13が接続され、該トンネル13を通じて輸
送されてきた人員及び資材類は、縦坑2の両サイドの半
円部を揚重用仮設開口として利用し、ここに揚重用クロ
ーラクレーン18を設置して資材類19の揚重を行なう
からである。Next, FIGS. 2 to 4 show an initial stage of starting construction of the above-mentioned structure. This embodiment shows a case where transportation of personnel and materials is performed in tunnels 13 and 14 constructed underground due to poor geographical traffic conditions at the construction site. This point is a case-by-case basis. It should be understood that it is implemented. According to FIG. 3, in the relatively narrow and limited yard indicated by the boundary line 15, the terrain of the board body 12 is a crawler crane 16 and an all-weather operation using a moving shed 17 for welding curing. It has been done as.
And it has shown that the shaft 2 used for constructing the said tower structure 10 was constructed in the position of both ends of the board body 12. According to FIGS. 2 and 4, the shaft 2
Is used on the ground at the site where the tower structure 10 is to be constructed, in order to use the building for the tower structure 10.
And the horizontal cross-sectional shape of the tower structure 10 (vertical approximately 3 m, horizontal approximately 18 m)
It is constructed by digging into a bore and a plane shape (an elliptical shape with a minor axis of about 20 m and a major axis of about 42 m) equivalent to two parallel rectangles. This is because the tunnel 13 described above is connected to the bottom of the shaft 2, and personnel and materials transported through the tunnel 13 use the semicircular portions on both sides of the shaft 2 as temporary openings for lifting. This is because the material 19 is lifted by using the crawler crane 18 for lifting.
【0010】図2と図4によれば、前記縦坑2の開口面
であって前記2個のタワー構造物10を建設すべき位置
に、同タワー構造物10の躯体の下底部を受ける広さと
形状の受けステージ4が、同縦坑2の口縁部に設置した
昇降機構5に両端支持された形で水平に設置されてい
る。昇降機構5の詳細は、図5〜図7に示した。図7で
明らかなように、縦坑2の覆工コンクリート2aより少
しせり出す配置とし後部を反力用の地盤アンカー51で
固定された受台50の前端部に、能力が例えば500ト
ン級のセンターホール型の油圧ジャッキ52が垂直下向
きに設置され、この油圧ジャッキ52で駆動されるリフ
ティング用の長いPC鋼より線53の先端を前記の受け
ステージ4に連結した構成とされている。図中54は受
台50上に設置した地盤アンカー51の緊結具である。
図5、図6で明らかなように、前記油圧ジャッキ52
は、縦坑2の口縁部に例えば14台を1ユニットとして
設置され、4ユニットで1個の受けステージ4を水平な
平行移動としてリフティングする構成とされている。According to FIGS. 2 and 4, a wide area for receiving the lower bottom portion of the frame of the tower structure 10 is provided at the opening surface of the shaft 2 at a position where the two tower structures 10 are to be constructed. A receiving stage 4 having a flat shape is horizontally installed in a form supported at both ends by an elevating mechanism 5 installed at the edge of the shaft 2. Details of the lifting mechanism 5 are shown in FIGS. As is clear from FIG. 7, the rear shaft is arranged so as to protrude slightly from the lining concrete 2 a of the shaft 2, and the rear portion is provided at the front end of the cradle 50 fixed by the ground anchor 51 for reaction force, and the center has a capacity of, for example, 500 tons. A hole-type hydraulic jack 52 is installed vertically downward, and the tip of a long PC steel stranded wire 53 for lifting driven by the hydraulic jack 52 is connected to the receiving stage 4. In the figure, reference numeral 54 denotes a fastener for the ground anchor 51 installed on the receiving table 50.
5 and 6, the hydraulic jack 52
Is configured such that, for example, 14 units are set as one unit at the edge of the shaft 2, and one receiving stage 4 is lifted as a parallel translation by four units.
【0011】図4に示したように、前記盤体12の地組
みは、地面上に設置した地組み構台20の上で行なわれ
る。また、前記の地組み構台20の地面下には地下空洞
11が設けられ、ここに縦坑2の内側口縁部の昇降機構
5が、前記地組み構台20と上下に分かれて支障なく設
置され、しかも前記の油圧ジャッキ52により駆動され
る80m以上の長いPC鋼より線53を長々と伸ばした
状態で放置可能とされている。As shown in FIG. 4, the erection of the board 12 is performed on an erection gantry 20 installed on the ground. In addition, an underground cavity 11 is provided below the ground of the erection gantry 20, and an elevating mechanism 5 at an inner edge of the shaft 2 is installed in the upper and lower parts of the erection gantry 20 without any trouble. Moreover, the PC steel wire 53 driven by the hydraulic jack 52 and having a length of 80 m or longer can be left in a state where it is elongated.
【0012】次に、図8によれば、前記縦坑2の開口面
に昇降機構5によってリフティング可能に支持された受
けステージ4の上で、同開口面上の地上作業として、タ
ワー構造物10の躯体10’が地上1階部分から高層部
分への順序でモジュール単位毎の建方が行なわれ、前記
モジュール単位の建方を完成する度に、同モジュール単
位の高さ分ずつ前記昇降機構5を操作して受けステージ
4を下降させる工程がくり返され、タワー躯体10’の
建方が最上層まで進んだ段階を示している。タワー躯体
10’はほぼ完全に縦坑2内に収納され沈み込んでい
る。盤体12の地組みもほぼ完成している。なお、タワ
ー躯体10’及び盤体12は共に鋼構造であり、鉄骨加
工量と溶接量が著しく多いため、輸送可能な大きさのモ
ジュール単位の製作を工場生産として行ない、現地では
モジュールの接合と組立てに限る作業として工期の短縮
と省人化及び現地作業の能率化が図られる。このあと、
盤体12の端部が、図8中の左端に点線図示した如くタ
ワー躯体10’の上端とのつなぎ部分として構築され、
かくして盤体12とタワー躯体10’との一体化接合も
地上作業として行なわれる。この段階までに、盤体12
の外周面の青銅パネル又はブロンズパネルによる外装、
仕上げ工事も地上作業として完全に行なわれる。Next, according to FIG. 8, a tower structure 10 is placed on a receiving stage 4 supported on the opening surface of the shaft 2 by a lifting mechanism 5 so as to be liftable. The building 10 ′ is constructed in units of modules in the order from the ground floor to the high-rise part, and each time the building in units of the module is completed, the lifting mechanism 5 is incremented by the height of the module. Is repeated, and the step of lowering the receiving stage 4 is repeated, and the stage in which the tower frame 10 'is built reaches the uppermost layer is shown. The tower body 10 ′ is almost completely housed in the shaft 2 and sinks. The structure of the board 12 is almost completed. In addition, since the tower body 10 'and the board body 12 are both steel structures and the amount of steel frame processing and welding is remarkably large, the production of modules that can be transported is carried out as factory production. As work limited to assembling, shortening of construction period, labor saving, and efficiency of on-site work are achieved. after this,
The end of the board 12 is constructed as a connecting portion with the upper end of the tower body 10 'as shown by a dotted line at the left end in FIG.
Thus, the integrated joining of the panel body 12 and the tower body 10 'is also performed as a ground operation. By this stage, the board 12
Exterior with bronze or bronze panels on the outer surface of the
Finishing work is also done completely as ground work.
【0013】図9と図10は、図8の状態で地上レベル
に露出しているタワー躯体10’の外周面のガラスによ
る外装、仕上げ工事を地上作業として開始し、その進捗
にしたがって前述の昇降機構5を駆動して受けステージ
4と共にタワー躯体10’を施工単位の高さ分(例えば
3mぐらい)ずつ上昇させ、全て地上作業として前記外
装、仕上げ工事を行なっている途中の段階を示してい
る。この上昇工程は、盤体12の水平を保ちながら注意
深く行なわれる。一方、縦坑2内では、その下底面から
順次積み上げる方式で反力基礎3の構築が受けステージ
4の下面の直下まで構築されている。反力基礎3の具体
的構造としては、鉄鋼製又はプレキャストコンクリート
製のセグメントを組立て、必要に応じて受けステージ4
及びその上のタワー躯体10’の一時的な仮受け支持あ
るいは転倒防止の反力を付与する構造などが実施され
る。FIG . 9 and FIG. 10 show the exterior and finishing work of glass on the outer peripheral surface of the tower body 10 'exposed at the ground level in the state of FIG. The mechanism 5 is driven to raise the tower skeleton 10 ′ together with the receiving stage 4 by the height of the construction unit (for example, about 3 m), and the exterior and finishing work are all being performed as ground work. . This lifting step is performed carefully while maintaining the level of the board 12. On the other hand, in the shaft 2, the reaction force foundation 3 is constructed up to immediately below the lower surface of the receiving stage 4 by a method of sequentially stacking from the lower bottom surface. The concrete structure of the reaction force foundation 3 is to assemble a segment made of steel or precast concrete, and to receive a stage 4 if necessary.
In addition, a structure for providing a temporary temporary support of the tower body 10 'thereon or a reaction force for preventing the tower body 10' from falling down is implemented.
【0014】こうして、図11はタワー躯体10’の上
昇工程と、地上レベルでの外装、仕上げ工事とが全て終
了し、タワー構造物10の下部は地面レベルで施工され
た定着用基礎21で強固に固定され、既に図1において
説明した構造物の建築が完成した状態を示している。な
お、縦坑2の跡は、反力基礎3が構築された内部及びそ
れ以外の既述した揚重仮設開口の部分は、トンネル13
と連絡された垂直方向のアクセス手段として、又は大深
度の駐車スペース等として有効利用することが可能であ
る。 FIG. 11 shows the completion of the raising process of the tower body 10 ′, the exterior and finishing work on the ground level, and the lower part of the tower structure 10 is firmly fixed by the anchoring foundation 21 constructed on the ground level. , And shows a state where the construction of the structure already described in FIG. 1 is completed. In addition, the trace of the shaft 2 shows the inside of the building where the reaction foundation 3 was constructed and the other part of the above-mentioned lifting temporary opening in the tunnel 13.
It can be effectively used as a vertical access means in contact with the vehicle, or as a deep parking space or the like.
【0015】[0015]
【本発明が奏する効果】本発明に係る構造物の建築方法
によれば、全ての建築作業を地面レベルで地上作業とし
て行なうことができ、高い足場や養生の仮設、あるいは
高所作業用のクレーン等の重機が必要でない。勿論、高
所作業がないから安全性の確保が容易である。また、人
員や資材類の移動が水平方向だけで済み、極めて能率的
である。According to the method of building a structure according to the present invention, all building work can be performed as ground work at the ground level, and a crane can be used for temporary installation of high scaffolds and curing, or for working at heights. No heavy equipment such as is required. Of course, safety is easy to secure because there is no work at height. In addition, it is extremely efficient to move the personnel and materials only in the horizontal direction.
【0016】更に、外装、仕上げ作業も全て地上作業と
して行なえるし、その上、タワー構造物10の最上層部
分から開始して、長期鉛直荷重と歪がほぼ確定した完成
状態での下層部分に向かって順に進められるので、品
質、精度の高い外装、仕上げが出来る。Further, the exterior and finishing operations can all be performed as ground operations, and further, starting from the uppermost layer of the tower structure 10 and extending to the lower layer in a completed state in which the long-term vertical load and strain have been substantially determined. As it proceeds in order, the exterior and finish can be made with high quality and accuracy.
【図1】完成した構造物の全景を示した斜視図である。FIG. 1 is a perspective view showing an entire view of a completed structure.
【図2】建築を開始した初期段階の全景を示した斜視図
である。FIG. 2 is a perspective view showing a whole view of an initial stage of starting construction.
【図3】建築現場の平面図である。FIG. 3 is a plan view of a construction site.
【図4】建築を開始した初期段階の垂直断面図である。FIG. 4 is a vertical sectional view of an initial stage of starting construction.
【図5】昇降機構と受けステージの平面図である。FIG. 5 is a plan view of a lifting mechanism and a receiving stage.
【図6】昇降機構の拡大した平面図である。FIG. 6 is an enlarged plan view of the lifting mechanism.
【図7】昇降機構の立面図である。FIG. 7 is an elevation view of a lifting mechanism.
【図8】躯体の構築がほぼ完了した段階の垂直断面図で
ある。FIG. 8 is a vertical cross-sectional view at a stage when the construction of the skeleton is almost completed.
【図9】躯体の上昇工程と反力基礎の構築が進められる
途中の段階の正面方向の断面図である。FIG. 9 is a cross-sectional view in the front direction at a stage during which the building process of the skeleton and the construction of the reaction force foundation are in progress.
【図10】躯体の上昇工程と反力基礎の構築が進められ
る途中の段階の側面方向の断面図である。 Fig. 10 Construction process of building body and construction of reaction base
FIG. 6 is a side sectional view of a stage in the middle of the process.
【図11】FIG. 11
構造物の建築を完成した段階の垂直断面図でIn a vertical sectional view of the stage when the construction of the structure was completed
ある。is there.
10 タワー構造物 10’ 躯体 2 縦坑 5 昇降機構 4 受けステージ 3 反力基礎 DESCRIPTION OF SYMBOLS 10 Tower structure 10 'Frame 2 Vertical shaft 5 Elevating mechanism 4 Receiving stage 3 Reaction force foundation
───────────────────────────────────────────────────── フロントページの続き (72)発明者 河野 浩司 大阪市中央区本町四丁目1番13号 株式 会社竹中工務店大阪本店内 (72)発明者 原 径一 大阪市中央区本町四丁目1番13号 株式 会社竹中工務店大阪本店内 (72)発明者 日元 正 大阪市中央区本町四丁目1番13号 株式 会社竹中工務店大阪本店内 (58)調査した分野(Int.Cl.6,DB名) E04G 21/14 E04B 1/35 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Koji Kono 4-1-1-13 Honcho, Chuo-ku, Osaka-shi Inside Takenaka Corporation, Osaka Main Store (72) Inventor Shuichi Hara 4-1-1, Honcho, Chuo-ku, Osaka-shi No. 13 Takenaka Corporation Osaka Main Branch (72) Inventor Tadashi Nimoto 4-1-1 Hommachi Chuo-ku Osaka City Osaka Main Store (58) Fields surveyed (Int.Cl. 6 , (DB name) E04G 21/14 E04B 1/35
Claims (3)
及び水平断面形状と同等な口径及び平面形状の縦坑を、
構造物の建設予定地の地盤に掘削し構築する段階と、 構造物の躯体を地上1階部分から高層部分への順序で、
前記縦坑の開口面上の地上作業としてモジュール単位毎
の建方を行ない、前記モジュール単位の建方を終了する
度に同モジュール単位の高さ分ずつ前記縦坑内に下降さ
せる工程のくり返しにより、構造物の躯体を最上層まで
建方を行う段階と、 次に躯体の最上層部分から外装、仕上げ工事を地上作業
として行ない、この外装、仕上げ工事の進捗に従って縦
坑内の躯体を施工単位の高さ分ずつ上昇させる段階と、 構造物がその地上1階部分まで上昇した段階で地盤への
定着を行なうことを特徴とする、構造物の建築方法。A vertical shaft having a bore and a plane shape at least equivalent to a depth and a horizontal sectional shape equivalent to a ground height of the structure,
Excavating and constructing the ground at the site where the structure is to be constructed; and
Performing the construction of each module unit as ground work on the opening surface of the shaft, and repeating the step of descending into the shaft by the height of the same module unit each time the construction of the module unit is completed, The stage of constructing the skeleton of the structure up to the top layer, and then the exterior and finishing work are performed as ground work from the top layer of the skeleton, and the skeleton in the shaft is set to the height of the construction unit according to the progress of this exterior and finishing work. A method of building a structure, comprising: ascending the structure one by one; and fixing the structure to the ground when the structure has risen to the first floor above the ground.
置した昇降機構で縦坑内に支持された受けステージの上
で行ない、前記昇降機構による前記受けステージの下降
又は上昇の操作によって構造物の躯体を縦坑内へ下降さ
せ又は上昇させることを特徴とする、請求項1記載の構
造物の建築方法。2. The structure of the frame of the structure is constructed on a receiving stage supported in the shaft by an elevating mechanism installed at the edge of the shaft, and the elevating mechanism lowers or raises the receiving stage. The method for building a structure according to claim 1, wherein the skeleton of the structure is lowered or raised into the shaft by the operation of (1).
後、この躯体を施工単位の高さ分ずつ上昇させる工程に
追従して縦坑内の下底面から上方に向かって順に反力基
礎を段階的に構築してゆき、最終的に構造物は前記反力
基礎を利用して地盤への定着が行なわれることを特徴と
する、請求項1又は2に記載した構造物の建築方法。3. After the construction of the frame of the structure is completed in the vertical shaft, the reaction force is sequentially increased upward from the lower bottom surface in the vertical shaft following the process of raising the frame by the height of the construction unit. 3. The method for building a structure according to claim 1, wherein the foundation is gradually built, and the structure is finally fixed to the ground using the reaction force foundation. .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP20234392A JP2946372B2 (en) | 1992-07-29 | 1992-07-29 | Construction method of structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP20234392A JP2946372B2 (en) | 1992-07-29 | 1992-07-29 | Construction method of structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0649998A JPH0649998A (en) | 1994-02-22 |
| JP2946372B2 true JP2946372B2 (en) | 1999-09-06 |
Family
ID=16455971
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP20234392A Expired - Fee Related JP2946372B2 (en) | 1992-07-29 | 1992-07-29 | Construction method of structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2946372B2 (en) |
-
1992
- 1992-07-29 JP JP20234392A patent/JP2946372B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0649998A (en) | 1994-02-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US10829927B2 (en) | Vertical slip form construction system with multi-function platform, and method of constructing a building therewith | |
| JP2946372B2 (en) | Construction method of structure | |
| JPH1061193A (en) | Method of building steel frame structure and device therefor | |
| JP3453181B2 (en) | Working steel stand and method of assembling tower-like structure using the working steel stand | |
| JP2536249B2 (en) | Lift-down underground structure construction method | |
| JPH03125755A (en) | Constructing method for cylindrical multistoried structure | |
| JP3416759B2 (en) | Underground structure frame building equipment | |
| CN116335283B (en) | Method for installing arch structure | |
| JP2696486B2 (en) | Building construction method | |
| JP2000248632A (en) | Floor climbing method of tower crane | |
| JP2884396B2 (en) | Construction method of building structure and lifting device of building structure | |
| CN211421802U (en) | High-rise building construction machinery | |
| JPH06200626A (en) | Jacking-up method for building | |
| JP2793053B2 (en) | Building construction method | |
| JP3439545B2 (en) | Construction method of multi-story parking lot | |
| JP2884398B2 (en) | Construction method of building structure and lifting device of building structure | |
| JPH0874278A (en) | Construction method for large underground space | |
| JP3139854B2 (en) | Collapse prevention frame | |
| JP2761528B2 (en) | How to build structures | |
| JP2761527B2 (en) | How to build structures | |
| JPH0437897B2 (en) | ||
| JPH0874279A (en) | Construction method for large underground space | |
| JPH1181679A (en) | Construction for building | |
| JP2761526B2 (en) | How to build structures | |
| JP2939752B2 (en) | Lift-up method in which an outer wall plate is attached to the floor plate |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |