JP2954418B2 - Underwater work equipment - Google Patents
Underwater work equipmentInfo
- Publication number
- JP2954418B2 JP2954418B2 JP4046903A JP4690392A JP2954418B2 JP 2954418 B2 JP2954418 B2 JP 2954418B2 JP 4046903 A JP4046903 A JP 4046903A JP 4690392 A JP4690392 A JP 4690392A JP 2954418 B2 JP2954418 B2 JP 2954418B2
- Authority
- JP
- Japan
- Prior art keywords
- equipment
- work
- shaft
- ground support
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Lining And Supports For Tunnels (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は大深度地下空間を構築
するに当たって水没環境下で遠隔操作され、無人で稼動
する水中作業機に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an underwater working machine which is remotely operated in a submerged environment and operates unmannedly when constructing a deep underground space.
【0002】[0002]
【従来の技術】トンネルをはじめとして地下空間を構築
するに当たっては、一般に、大気中における掘削が行わ
れるが、掘削による掘削壁面の応力開放によって掘削壁
面にクラックが入り壁面の崩落につながる危険性がある
場合には、気圧、泥水、土圧などを高くするなどして掘
削することもある。2. Description of the Related Art When constructing an underground space, such as a tunnel, excavation is generally performed in the atmosphere. In some cases, excavation may be performed by increasing the air pressure, muddy water, earth pressure, etc.
【0003】掘削壁面は掘削後に早急にコンクリートな
どを用いて覆工することは不可欠の技術とされ、掘削作
業と同時進行的に掘削壁面の覆工が行われる。この掘削
壁面の一般的な覆工方法としては、作業者の手作業によ
って掘削壁面と所定の距離を隔てて型枠を組みながらバ
ッチ的にコンクリート、モルタルなどのライニング材料
(以下、ライニング材料という)を打設して後、一定期
間を放置・養生(硬化)を待ってから型枠を取り外し、
場所を移動して再組み立てを行ってライニング材料を打
設する手法や、掘削壁面に対してライニング材料を吹き
付けて打設するなどの手法が採用されている。It is indispensable to immediately cover the excavated wall with concrete or the like after the excavation, and the excavated wall is covered simultaneously with the excavation work. As a general method of lining this excavation wall, a lining material such as concrete or mortar (hereinafter, referred to as a lining material) is batched while assembling a formwork at a predetermined distance from the excavation wall by an operator. After setting, leave for a certain period of time and wait for curing (hardening), then remove the formwork,
A method of moving the place, reassembling and placing the lining material, and a method of spraying and placing the lining material on the excavated wall surface are adopted.
【0004】[0004]
【発明が解決しようとする課題】ところで、大深度地下
(一般に、地下50m以上をいう)にドーム状の大きな
自由空間を構築するには、空間構築場所まで立坑を設
け、一度に空間全体を掘削するのではなく、空間の天盤
とされる立坑下部から立坑を中心に予定する深さのドー
ム状空間を縦方向に段階状に分けた掘削、いわゆるベン
チカット段を下方に向けて順次に掘削していき、各掘削
ベンチカット段ごとに掘削と壁面覆工を繰り返しながら
構築する施工法が提案されている。By the way, in order to construct a large dome-shaped free space deep underground (generally 50 m or more underground), a shaft is provided up to the space construction place, and the entire space is excavated at once. Instead of excavating the dome-shaped space of the planned depth centered on the shaft from the bottom of the shaft, which is considered as the top of the space, excavating the so-called bench cut step downward in the vertical direction A construction method has been proposed in which the drilling and wall lining are repeatedly performed for each drilling bench-cut step to construct the building.
【0005】上記するような大深度地下空間を構築する
のに、大気中において掘削するとなると、たとえ、ベン
チカット段の掘削であっても深度的に掘削壁面の崩落の
危険性が大きくなるため、水没環境下における掘削が有
効とされる。すなわち、水没環境下における掘削では、
水圧によって掘削壁面に内圧が掛けられて地下水位との
バランスを保つことができて壁面の崩落を防止する効果
があり、さらに泥水条件では地下水位との圧力差が大き
くなり、大気中における掘削に比べて安全性が高くな
る。When excavating in the atmosphere to construct such a deep underground space as described above, even when excavating a bench-cut step, the danger of collapse of the excavated wall surface increases in depth. Excavation under submerged environment is considered effective. That is, in excavation under submerged environment,
Internal pressure is applied to the excavation wall surface by water pressure to maintain the balance with the groundwater level, which has the effect of preventing collapse of the wall surface.In muddy water conditions, the pressure difference with the groundwater level increases, and drilling in the atmosphere The safety is higher than that.
【0006】しかし、水没環境下、特に高水圧とされる
大深度の地下空間の掘削現場には、作業者が直接に出入
りして掘削作業や掘削壁面の覆工作業に従事することは
きわめて困難な面があるので、水中、泥水中における遠
隔操作による無人状態での施工が求められる。However, it is extremely difficult for an operator to directly enter and exit to engage in excavation work and lining of excavated walls in a submerged environment, particularly in a deep underground space where high water pressure is applied. Therefore, it is required to perform unmanned construction by remote control underwater and muddy water.
【0007】この発明は上述の点に鑑みなされたもので
あって、大深度地下空間を構築するに当たって水没環境
下における無人化施工を可能にし、地質上の制限幅を拡
大した水中作業設備を提供することを目的とする。The present invention has been made in view of the above points, and provides an underwater working facility which enables unmanned construction in a submerged environment when constructing a deep underground space and has an increased geological limit. The purpose is to do.
【0008】[0008]
【課題を解決するための手段】上記の目的を達成するた
めのこの発明の要旨とするところは、空間の天盤とされ
る立坑下部から立坑を中心に予定する深さのドーム状空
間を縦方向に段階状に分けて掘削し、この掘削壁面にコ
ンクリート・モルタルなどのライニング材料を打設し、
このようにして、各掘削ベンチカット段ごとに掘削と壁
面覆工を繰り返す工法に用いる水中作業設備であって、
予め設けた立坑上部の地上に設置される地上支援設備
と、立坑を介して地下空間に投入および揚収がなされ、
水没環境下で稼動可能な作業機からなり、地上支援設備
は主要装備として、位置移動可能な固定台車上に旋回台
が装着され、該旋回台に、作業機を懸架索を介し懸架し
て昇降動させるウインチ機構、作業機の各動作部を遠隔
操作する操作機構、作業機間に物を流通させる物流機構
を備え、作業機は主要装備として、作業機器が取着され
る伸縮・起伏自在なブーム機構、各動作部を動作させる
動作機構を備え、前記地上支援設備の各装備と作業機の
各装備は、作業機を地上支援設備から遠隔操作可能に各
種ケーブル、物の流通に用いる各種可撓性配管からなる
連係機構で連係したことを特徴とする水中作業設備であ
る。SUMMARY OF THE INVENTION In order to achieve the above object, the gist of the present invention is to vertically extend a dome-shaped space having a predetermined depth from the lower part of the shaft, which is the top of the space, to the center of the shaft. Excavation is divided into stages in the direction, and lining materials such as concrete and mortar are cast on the excavation wall,
In this way, the underwater work equipment used in the method of repeating excavation and wall lining for each excavation bench cut step,
Ground support equipment installed on the top of the shaft previously provided, and input and extraction into the underground space via the shaft,
It consists of a working machine that can be operated under submerged environment.The ground support equipment is equipped with a swivel base on a fixed bogie that can be moved as a main equipment. It is equipped with a winch mechanism for moving, an operating mechanism for remotely operating each operating part of the working machine, and a logistics mechanism for circulating goods between the working machines. A boom mechanism and an operating mechanism for operating each operating unit are provided.Each equipment of the ground support equipment and each equipment of the work equipment are provided with various cables and various kinds of equipment that can be used for distribution of various cables and objects so that the work equipment can be remotely controlled from the ground support equipment. An underwater working facility characterized by being linked by a linking mechanism comprising a flexible pipe.
【0009】[0009]
【作用】立坑および立坑下部の空間構築現場は水没状態
とし、空間構築現場への作業機の投入および揚収は作業
機全体の平面の投影面積を最小にして地上支援設備に懸
吊した状態で立坑を介して行われる。作業機は立坑直下
に旋回中心制御可能にセットしてライニング打設のため
の作業に供せられ、地上支援設備からの遠隔操作で稼動
し、ブーム機構先端の作業機器が作業位置において所定
の作業を的確に遂行する。[Function] The space construction site below the shaft and under the shaft is submerged, and the loading and unloading of the working machine to the space building site is performed while the projected area of the entire working machine is minimized and suspended on the ground support equipment. This is done through a shaft. The work machine is set directly beneath the shaft so that the center of rotation can be controlled, and the lining is installed
, And is operated by remote control from the ground support equipment, and the work equipment at the end of the boom mechanism accurately performs a predetermined work at the work position.
【0010】[0010]
【実施例】以下、この発明の実施例を図面に基づいて説
明する。Embodiments of the present invention will be described below with reference to the drawings.
【0011】図1はこの発明の概略全体図、図2はこの
発明を構成する地上支援設備の概略全体斜視図、図3は
この発明を構成する作業機の概略全体斜視図である。FIG. 1 is a schematic general perspective view of the present invention, FIG. 2 is a schematic general perspective view of a ground support facility of the present invention, and FIG. 3 is a schematic general perspective view of a working machine of the present invention.
【0012】この発明の基本構成としては、予め設けた
立坑A上部の地上に設置される地上支援設備1と、立坑
Aを介して立坑下部の地下空間Bに投入される作業機2
からなる。As a basic configuration of the present invention, a ground support facility 1 which is provided in advance on the ground above a shaft A, and a work machine 2 which is put into an underground space B below the shaft via the shaft A
Consists of
【0013】前記地上支援設備1は、地面に敷設したレ
ール3上を位置移動可能な固定台車4上に旋回可能に旋
回台5が装着され、この旋回台5の中央部には立坑Aに
対応して通穴6が設けられ、旋回台5上に作業機2の各
動作部を遠隔操作する制御機構7をはじめ、懸架索8を
介して作業機2を懸架するウインチ機構9、作業機2と
の間に物を流通させる物流機構10などを主要設備とし
て備えている。The ground support equipment 1 has a turntable 5 mounted on a fixed truck 4 movable on a rail 3 laid on the ground so that the turntable 5 can rotate, and a central portion of the turntable 5 corresponds to a shaft A. A through-hole 6 is provided, and a control mechanism 7 for remotely controlling each operation unit of the work implement 2 on the swivel table 5, a winch mechanism 9 for suspending the work implement 2 via a suspension cable 8, a work implement 2 A logistics mechanism 10 for distributing goods between them is provided as main equipment.
【0014】前記作業機2は水没環境下で稼動し、ライ
ニング打設専用に設計されており、立坑A直下の地底に
固定的にセットするためのアウトリガー11を備えた基
台12上に全周を旋回動自在に作業機本体2aが装着さ
れ、この作業機本体2aに伸縮・起伏自在で先端に作業
機器14が取着されるブーム13をはじめ、各動作部を
動作させる動作機構(図示せず)などを主要設備として
備え、作業機2の全ての動作は地上支援設備1からの遠
隔操作で行われるようになっている。The work machine 2 operates in a submerged environment , and
The work machine main body 2a is mounted on a base 12 provided with an outrigger 11 to be fixedly set on the ground directly below the shaft A, and is rotatable around the entire circumference. An operating mechanism (not shown) for operating each operating unit is provided as a main facility, including a boom 13 having a working device 14 attached to a tip thereof which can be extended and retracted and raised and lowered on the machine main body 2a. The operation is performed by remote control from the ground support equipment 1.
【0015】地上支援設備1から作業機2を遠隔操作す
るために、前記の地上支援設備1の各装備と作業機2の
各装備は作業機2の各動作部を動作を司る各種ケーブ
ル、物の流通に用いる各種可撓性配管からなる連係機構
15で連係しており、この連係機構15とされるケーブ
ルとしては、作業機2の各種電源とされる動力用電線や
制御用通信線などがあり、可撓性配管としては作業機2
の各動作部を構成する油圧装置へ動作油を供給する油管
や作業機器14へ作業用物資を供給する供給管などがあ
る。実施例のように作業機器14として壁面覆工作業を
施工する型枠機構14′が取着してある場合は、この型
枠機構14′に対してライニング材料を供給する供給管
がこれに相当する。In order to remotely control the work equipment 2 from the ground support equipment 1, the equipment of the ground support equipment 1 and the equipment of the work equipment 2 are composed of various cables and objects for controlling the operation parts of the work equipment 2. Are connected by a linking mechanism 15 composed of various flexible pipes used for the distribution of the power, and a cable used as the linking mechanism 15 is a power wire or a control communication wire serving as various power sources of the working machine 2. There is a working machine 2 as flexible piping.
There is an oil pipe for supplying the operating oil to the hydraulic device constituting each operation unit, and a supply pipe for supplying the working materials to the work equipment 14. When a formwork mechanism 14 'for performing wall covering work is attached as the work equipment 14 as in the embodiment, a supply pipe for supplying a lining material to the formwork mechanism 14' corresponds thereto. I do.
【0016】前記作業機2を懸架する懸架索8は、ブー
ム13を前にして作業機本体2aの前後左右から4本の
吊り索8aを作業機本体2a上方の適当な高さ位置まで
延ばし、前後吊り索8a間に間隔保持金具16を架装し
て左右の吊り索8aをそれぞれ1つにして二点吊りと
し、ブーム13が起伏動するに際して相互干渉がないよ
うにするとともに、作業機2の投入および揚収時に水平
バランスを保つて昇降させられるようにしている。A suspension cable 8 for suspending the work machine 2 is provided by extending four suspension cables 8a from the front, rear, left and right of the work machine main body 2a to an appropriate height above the work machine main body 2a with the boom 13 in front. The spacing metal fitting 16 is mounted between the front and rear suspension cables 8a, and the left and right suspension cables 8a are respectively connected to each other so as to be suspended at two points, so that there is no mutual interference when the boom 13 moves up and down. When loading and unloading, it is possible to move up and down while maintaining horizontal balance.
【0017】なお、作業機2を懸架索8で懸架して懸架
索8だけでは作業機2の水平バランスが保てないような
時には、作業機2に対して適当なバランス調整部材を取
り付けることもある。また、地下空間構築において大深
度ほどでなく立坑の深さが浅い場合には、地上支援設備
1としては簡単に移動できるトラックや、簡単な移動台
車などを用いることもある。When the work machine 2 is suspended by the suspension cable 8 and the horizontal balance of the work machine 2 cannot be maintained by the suspension cable 8 alone, an appropriate balance adjusting member may be attached to the work machine 2. is there. In addition, when the depth of the shaft is shallow as well as at a large depth in the construction of the underground space, a track that can be easily moved, a simple movable cart, or the like may be used as the ground support equipment 1.
【0018】上記構成において、立坑A直下にドーム状
の大深度地下空間Bを構築するに当たって、作業機器1
4として形枠機構14′を用いて掘削壁面を覆工する場
合について、作業要領の概要を図4を参照しながら説明
する。In the above configuration, when constructing the dome-shaped deep underground space B immediately below the shaft A, the work equipment 1
The outline of the operation procedure for lining the excavation wall using the formwork mechanism 14 'as 4 will be described with reference to FIG.
【0019】図4 (a) , (b) , (c) はこの発明の
実施例を示す工程図である。FIGS. 4A, 4B and 4C are process diagrams showing an embodiment of the present invention.
【0020】(a) 作業機2は懸架索8により懸架さ
れて立坑Aを介して立坑下部の空間Bに投入される。(A) The work machine 2 is suspended by the suspension ropes 8 and put into the space B below the shaft through the shaft A.
【0021】この際、作業機2は全体として平面の投影
面積を最小にするために、図示のように、ブーム13は
最短に縮小され、かつ、最大起立位置におかれ、ブーム
13先端の型枠機構14′はブーム13にほぼ平行にな
るように折り畳まれて立坑Aを自由に昇降可能な形態を
採る。At this time, in order to minimize the projected area of the plane as a whole, the work machine 2 is configured such that the boom 13 is reduced to the shortest position and is positioned at the maximum standing position as shown in FIG. The frame mechanism 14 ′ is folded so as to be substantially parallel to the boom 13 and has a form capable of freely moving up and down the shaft A.
【0022】(b) 作業機2が空間Bに到達して立坑
A直下の地底に固定的にセットされる。(B) The work machine 2 reaches the space B and is fixedly set on the ground floor immediately below the shaft A.
【0023】ここで、作業機本体2の旋回中心を設定
し、基台12のアウトリガー11により地底へ固定する
際に、作業機本体2aの地底からの高さと水平位の調整
もアウトリガー11によって決める。Here, when the turning center of the work machine main body 2 is set and fixed to the ground bottom by the outrigger 11 of the base 12, adjustment of the height and horizontal position of the work machine main body 2a from the ground bottom is also determined by the outrigger 11. .
【0024】(c) 掘削壁面Cの覆工作業は、ブーム
13を伸長させて形枠機構14′を作業位置に到達さ
せ、型枠機構14′を掘削壁面Cに対面させて型枠内に
ライニング材料を投入してその硬化を図りつつ、形枠機
構14′を移動させる。ここで使用するライニング材料
としては、当然ながら水中ライニング材料が用いられ、
ブーム13先端部において形枠投入寸前に液状急結剤を
添加混合して硬化時間を短縮するようにしている。この
場合、急結剤を練り込んだ水中ライニング材料を地上か
ら圧送し、型枠投入後硬化が開始されるような材料であ
っても同様の機能が果たせる。(C) In the lining work of the excavation wall C, the boom 13 is extended to make the formwork mechanism 14 'reach the work position, and the formwork mechanism 14' is made to face the excavation wall C and into the formwork. The formwork mechanism 14 'is moved while the lining material is charged and hardened. As the lining material used here, naturally, an underwater lining material is used,
At the tip of the boom 13, a liquid quick-setting agent is added and mixed just before the form is charged so as to shorten the curing time. In this case, the same function can be performed even if the underwater lining material into which the quick-setting agent has been kneaded is pressure-fed from the ground and curing is started after the mold is put into the mold.
【0025】こうして、型枠内にライニング材料を供給
してその硬化を図りつつ、形枠機構14′を横移動させ
ることによって掘削壁面Cに対してリング状の単位覆工
体dが形成される。このようにして一つの単位覆工体d
が完成すると、この上に順次に必要な数の単位覆工体d
を積み重げ式に形成していき、複数の単位覆工体dによ
ってベンチカット段覆工壁D(図1参照)を構成する。In this way, the ring-shaped unit lining body d is formed on the excavation wall C by laterally moving the form mechanism 14 'while supplying the lining material into the form and hardening the lining material. . Thus, one unit lining body d
Is completed, the required number of unit linings d
Are formed in a stacking manner, and a bench cut step lining wall D (see FIG. 1) is constituted by a plurality of unit lining bodies d.
【0026】なお、上記する掘削壁面覆工作業中におけ
る作業機2の動き、特に作業機本体2aの旋回動に合わ
せて地上支援設備1の旋回台5も旋回動する。また、作
業中も懸架索8は弛みが生じない程度に軽く緊張した状
態におかれ、連係機構15を構成する各種ケーブルや各
種可撓性配管などは互いに絡んだり縺れたりしないよう
に適所に設けたガイドリングによって集括的に管理さ
れ、立坑A内中空に垂下し、ブーム13の伸縮に伴う長
さ調整は作業機本体2aに設けたリール機構に掛け渡す
などして吸収される。The turning table 5 of the ground support equipment 1 also turns in accordance with the movement of the working machine 2 during the above-mentioned excavation wall lining work, particularly the turning movement of the working machine main body 2a. Also, during the operation, the suspension cable 8 is kept in a lightly tensioned state so as not to be loosened, and various cables and various flexible pipes constituting the linking mechanism 15 are provided at appropriate places so as not to be entangled or entangled with each other. The length of the boom 13 is adjusted by the extension and contraction of the boom 13 and absorbed by a reel mechanism provided on the work machine main body 2a.
【0027】また、掘削壁面の崩落の危険がきわめて小
さいようなときは、必ずしも上記するような型枠機構1
4′を用いて単位覆工体dを積み重げ式に形成してベン
チカット段覆工壁Dを構成することなく、塗り付け工法
を採用することもできる。When the danger of collapse of the excavation wall surface is extremely small, the above-described formwork mechanism 1 is not necessarily required.
The coating method can also be adopted without forming the bench cut step lining wall D by forming the unit lining bodies d in a stacking manner using 4 ′.
【0028】[0028]
【発明の効果】上記構成からなるこの発明によれば、つ
ぎのような効果を奏する。According to the present invention having the above configuration, the following effects can be obtained.
【0029】(1) 立坑直下に大きな空間を構築する
のに、水中、泥水中における遠隔操作により無人状態で
のライニング打設作業を可能にしたから、作業者は快適
な環境下にあって、人間のアプローチできないような困
難な作業を、省力化して能率よく施工することができ
る。[0029] (1) to build a large space directly below the vertical shaft, underwater, because made it possible to lining striking setting work in the unmanned state by remote control in the muddy water, the worker was under a comfortable environment, Difficult work that cannot be approached by humans can be labor-saving and performed efficiently.
【0030】(2) 地下空間の工事対象物の状況や作
業機による作業状況は地上支援設備においてコンピュー
タによる画像処理によって判明できるから、地上支援設
備と立坑を介して地下空間に投入される作業機とは距離
的な隔たりに関係なく作業が的確に施工でき、場合によ
っては昼夜を問わずして連続作業を可能にする。(2) Since the condition of the object to be constructed in the underground space and the working condition of the working machine can be determined by image processing by the computer at the ground support facility, the working machine put into the underground space via the ground support facility and the shaft. Work can be performed accurately regardless of the distance, and in some cases, continuous work is possible regardless of day or night.
【0031】(3) 作業機による作業空間は水没下に
あるから、掘削壁面に内圧を掛けて地下水位とのバラン
スが保たれ壁面崩落が防止され、この面からの安全性を
高くして地質条件の制限を緩和し、大深度地下空間の構
築の適用場所の拡大が図られる。(3) Since the working space of the working machine is submerged, the internal pressure is applied to the excavated wall surface to maintain the balance with the groundwater level and prevent the wall surface from collapsing. The restrictions on conditions will be relaxed, and the application places for the construction of deep underground spaces will be expanded.
【図1】 この発明の全体概略図である。FIG. 1 is an overall schematic diagram of the present invention.
【図2】 この発明を構成する地上支援設備の概略全体
斜視図である。FIG. 2 is a schematic overall perspective view of the ground support equipment constituting the present invention.
【図3】 この発明を構成する作業機の概略全体斜視図
である。FIG. 3 is a schematic overall perspective view of a working machine constituting the present invention.
【図4】 (a) , (b) , (c) はこの発明の実施例
を示す工程図である。FIGS. 4 (a), (b) and (c) are process diagrams showing an embodiment of the present invention.
1…地上支援設備 2…作業機 5…旋回台 7…制御機構 8…懸架索 9…ウインチ機構 10…物流機構 11…アウトリガー 12…基台 13…ブーム 14…作業機器 15…連係機構 A…立坑 B…地下空間 C…掘削壁面 D…ベンチカット段覆工壁DESCRIPTION OF SYMBOLS 1 ... Ground support equipment 2 ... Working machine 5 ... Turning table 7 ... Control mechanism 8 ... Suspension line 9 ... Winch mechanism 10 ... Logistics mechanism 11 ... Outrigger 12 ... Base 13 ... Boom 14 ... Working equipment 15 ... Linkage mechanism A ... Shaft B: Underground space C: Excavated wall D: Bench cut step lining wall
───────────────────────────────────────────────────── フロントページの続き (72)発明者 百田 博宣 東京都港区芝浦1丁目2番3号 清水建 設株式会社内 (56)参考文献 特開 平2−112600(JP,A) 特開 平3−13696(JP,A) (58)調査した分野(Int.Cl.6,DB名) E02F 5/00 E21D 13/00 ──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Hironobu Momoda 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation (56) References JP-A-2-112600 (JP, A) JP-A 3-13696 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E02F 5/00 E21D 13/00
Claims (1)
中心に予定する深さのドーム状空間を縦方向に段階状に
分けて掘削し、この掘削壁面にコンクリート・モルタル
などのライニング材料を打設し、このようにして、各掘
削ベンチカット段ごとに掘削と壁面覆工を繰り返す工法
に用いる水中作業設備であって、予め設けた立坑上部の
地上に設置される地上支援設備と、立坑を介して地下空
間に投入および揚収がなされ、水没環境下で稼動可能な
作業機からなり、地上支援設備は主要装備として、位置
移動可能な固定台車上に旋回台が装着され、該旋回台
に、作業機を懸架索を介し懸架して昇降動させるウイン
チ機構、作業機の各動作部を遠隔操作する操作機構、作
業機間に物を流通させる物流機構を備え、作業機は主要
装備として、作業機器が取着される伸縮・起伏自在なブ
ーム機構、各動作部を動作させる動作機構を備え、前記
地上支援設備の各装備と作業機の各装備は、作業機を地
上支援設備から遠隔操作可能に各種ケーブル、物の流通
に用いる各種可撓性配管からなる連係機構で連係したこ
とを特徴とする水中作業設備。1. A dome-shaped space having a predetermined depth centered on a shaft from a lower part of a shaft, which is regarded as a roof of the space, is excavated in steps in a vertical direction, and a lining material such as concrete or mortar is formed on the excavated wall surface. In this way, the underwater work equipment used in the method of repeating the excavation and wall lining for each excavation bench cut step, ground support equipment installed on the ground above the shaft previously provided, It consists of a working machine that can be loaded and unloaded into the underground space through a shaft, and can be operated in a submerged environment. The ground support equipment is equipped with a swivel on a fixed bogie that can be moved as a main equipment. The platform is equipped with a winch mechanism that suspends and raises and lowers the work machine via a suspension cable, an operation mechanism that remotely controls each operation unit of the work machine, and a logistics mechanism that distributes goods between the work machines. As working equipment A telescopic boom mechanism that can be attached and retracted, and an operating mechanism that operates each operating unit.Each equipment of the ground support equipment and each equipment of the work equipment enable the work equipment to be remotely controlled from the ground support equipment. An underwater work facility, which is linked by a link mechanism comprising various cables and various flexible pipes used for distribution of goods.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4046903A JP2954418B2 (en) | 1992-03-04 | 1992-03-04 | Underwater work equipment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4046903A JP2954418B2 (en) | 1992-03-04 | 1992-03-04 | Underwater work equipment |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH05247967A JPH05247967A (en) | 1993-09-24 |
| JP2954418B2 true JP2954418B2 (en) | 1999-09-27 |
Family
ID=12760321
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP4046903A Expired - Fee Related JP2954418B2 (en) | 1992-03-04 | 1992-03-04 | Underwater work equipment |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2954418B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6398142B2 (en) * | 2013-11-07 | 2018-10-03 | 前澤工業株式会社 | Gate survey device |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH02112600A (en) * | 1988-10-19 | 1990-04-25 | Mitsui Miike Mach Co Ltd | How to excavate and construct a large underground cavern |
| JP2558163B2 (en) * | 1989-06-08 | 1996-11-27 | 株式会社フジタ | Construction method of underground cavity |
-
1992
- 1992-03-04 JP JP4046903A patent/JP2954418B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH05247967A (en) | 1993-09-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US12209422B2 (en) | Construction and/or materials-handling machine and method for guiding and moving a working head | |
| JP2954418B2 (en) | Underwater work equipment | |
| JP2618798B2 (en) | Multi-function excavator | |
| CN216428307U (en) | Underwater soil breaking robot | |
| RU2759467C1 (en) | Method for automated installation of the power structure of a gravitational energy storage device and a set of devices for its implementation | |
| JP2783686B2 (en) | Underground construction method by elevator | |
| JP3259237B2 (en) | Roof equipment for dam concrete casting | |
| JPS6245958B2 (en) | ||
| JP6620992B2 (en) | Building demolition machine and building demolition method | |
| JP2535118B2 (en) | Formwork equipment for excavated wall lining | |
| JP2003301683A (en) | Drilling rig | |
| JP3438208B2 (en) | Tunnel construction equipment | |
| AU2023262665B2 (en) | Modular platform system for vertical ore stope mining | |
| JPH0759831B2 (en) | Construction equipment | |
| JP2854389B2 (en) | Steel construction method | |
| JP2534691Y2 (en) | Drill jumbo with cage | |
| JPH08232579A (en) | Tunnel rig | |
| JP2886089B2 (en) | Soft ground improvement equipment | |
| JP2506526B2 (en) | Underground space excavation wall lining method | |
| JP3464054B2 (en) | Steel sheet pile driving machine | |
| JP7320410B2 (en) | guide instrument | |
| SU444853A1 (en) | Construction scaffolding | |
| JP2024087404A (en) | Remotely operated tunnel boring machine | |
| JPH0882185A (en) | Tunnel construction equipment | |
| CN120830522A (en) | An integrated trolley for inclined well drilling and protection |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |