JP3028053B2 - Joining method between building and diaphragm wall - Google Patents
Joining method between building and diaphragm wallInfo
- Publication number
- JP3028053B2 JP3028053B2 JP7318113A JP31811395A JP3028053B2 JP 3028053 B2 JP3028053 B2 JP 3028053B2 JP 7318113 A JP7318113 A JP 7318113A JP 31811395 A JP31811395 A JP 31811395A JP 3028053 B2 JP3028053 B2 JP 3028053B2
- Authority
- JP
- Japan
- Prior art keywords
- underground
- joint
- wall
- continuous wall
- skeleton
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION
【0001】[0001]
【発明の属する技術分野】本発明は、LNG地下タン
ク、地下倉庫などの大型地下構造物における、躯体と地
中連続壁の接合工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining a skeleton and an underground continuous wall in a large underground structure such as an LNG underground tank or an underground warehouse.
【0002】[0002]
【従来の技術】大型地下構造物の施工法として従来か
ら、地中連続壁によって山留壁(場合によっては止水壁
を兼用)を施工し、その内部を掘削したのち躯体を施工
する方法が用いられている。2. Description of the Related Art Conventionally, as a method of constructing a large underground structure, there has been a method of constructing a retaining wall (also used as a water stop wall in some cases) with a continuous underground wall, excavating the inside thereof, and then constructing a skeleton. Used.
【0003】地下水位以下に構築され、浮力が作用する
地下タンク等の地下構造物の部材寸法は、浮力に対する
安全性や強度面からの安全性の点から決められるが、高
強度コンクリートが比較的安価に使用できるようになっ
てきたこと、および、構造物の大型化、大深度化にとも
なって、強度面より浮力に対する安全性の面から部材の
寸法が定まるようになってきた。[0003] The dimensions of underground structures such as underground tanks, which are constructed below the groundwater level and act on buoyancy, are determined in terms of safety against buoyancy and safety in terms of strength. With the ability to be used at a low cost, and with the increase in size and depth of structures, the dimensions of members have come to be determined from the viewpoint of safety against buoyancy rather than strength.
【0004】そのため、躯体重量のみではなく、地中連
続壁の重量も浮力に抵抗させることがコスト、工期的に
有利であることが分かってきており、地中連続壁に躯体
を接合させることが提案されている。For this reason, it has been found that it is advantageous in terms of cost and construction period to make the weight of the underground continuous wall not only the weight of the underground continuous wall, but also the weight of the underground continuous wall, and it is advantageous to join the frame to the underground continuous wall. Proposed.
【0005】浮力に対する躯体重量の不足重量を地中連
続壁に伝達するのには、地中連続壁で少なくとも、躯体
からの上向きの力を拘束すればよいが、LNG地下タン
クを例にとると、内容液(LNG)が−162 °と超低温
であり、躯体が温度収縮することから、前記接合のため
の構造として、躯体の温度収縮を拘束せず、躯体と地中
連続壁の接合によって躯体に温度変化にともなう応力
(温度応力)を発生させないように、躯体の半径方向、
上下方向への収縮が自由であることが必要となる。In order to transmit the insufficient weight of the skeleton against the buoyancy to the underground continuous wall, it is sufficient to restrain at least the upward force from the skeleton by the underground continuous wall. In the case of an LNG underground tank, for example, Since the content liquid (LNG) is at an extremely low temperature of -162 °, and the temperature of the frame shrinks, the structure for joining is not restricted by the temperature shrinkage of the frame, and the frame and the underground continuous wall are joined together. In order not to generate stress (temperature stress) due to temperature change in the radial direction of the frame,
It is necessary that the contraction in the vertical direction is free.
【0006】このような要求を満足させるものとして、
出願人は先に特願平3-135743号(特開平4-337200号公
報、特公平6-103080公報)として、図3に示すような浮
力を受ける地下構造物接合工法を出願し、特許(特許第
1975773 号)を取得している。In order to satisfy such demands,
The applicant has previously filed a Japanese Patent Application No. Hei 3-135743 (Japanese Patent Application Laid-Open No. 4-337200, Japanese Patent Publication No. Hei 6-30080) and applied a method for joining underground structures receiving buoyancy as shown in FIG. Patent No.
1975773).
【0007】地中連続壁1内には上下方向の中間部に鉄
板2をベースとして埋設し、連続地中壁1の内側を掘削
したのち、この鉄板2から支持部材としての短尺な鋼管
3を水平方向に突設した。さらに、底版の外周からは上
方に側壁6を立ち上げる。In the underground continuous wall 1, a steel plate 2 is buried in the middle part in the vertical direction on the basis of an iron plate 2, and the inside of the continuous underground wall 1 is excavated. Then, a short steel pipe 3 as a support member is removed from the iron plate 2. It protruded horizontally. Further, the side wall 6 is raised upward from the outer periphery of the bottom plate.
【0008】この側壁6は前記した地中連続壁1に近接
して形成するが、側壁6の外周面には鉄板2をベースと
して埋設し、この鉄板2から支持部材としての短尺な鋼
管7を水平方向に突設させておき、前記鋼管3内に遊嵌
させた。The side wall 6 is formed close to the underground continuous wall 1, and is buried on the outer peripheral surface of the side wall 6 based on the iron plate 2, and a short steel pipe 7 as a support member is formed from the iron plate 2. It was projected in the horizontal direction, and was loosely fitted into the steel pipe 3.
【0009】鋼管3は鋼管7よりも大径のもので、前記
遊嵌は側壁6側の沈下で鋼管7の下降を許容する隙間を
確保するものとした。また、鋼管7はコンクリート8で
充填しておく。さらに、鋼管7の外周部付近に鋼管3は
鋼管7間に開口するグラウトホース9を側壁6側に埋設
する。The steel pipe 3 has a larger diameter than the steel pipe 7, and the loose fitting secures a gap that allows the steel pipe 7 to descend when the side wall 6 sinks. The steel pipe 7 is filled with concrete 8. Further, in the vicinity of the outer peripheral portion of the steel pipe 7, the grout hose 9 opening between the steel pipes 7 is embedded in the side wall 6 side.
【0010】側壁6を順次立上げてさらに底版を施工し
て躯体を構築していくが、この躯体の自重で地盤が沈下
し、側壁6が地中連続壁1に対して下降すると、鋼管7
の位置も鋼管3内で上方から下方へ移動する。When the side walls 6 are sequentially raised and a bottom slab is constructed to construct a skeleton, the ground sinks due to the weight of the skeleton, and when the side walls 6 descend with respect to the underground continuous wall 1, a steel pipe 7 is formed.
Also moves from above to below within the steel pipe 3.
【0011】躯体完成後、前記グラウトホース9より鋼
管3は鋼管7間にグラウト4を注出してこのグラウト4
で鋼管3と鋼管7とを固定する。After completion of the frame, the steel pipe 3 is poured out of the grout hose 9 between the steel pipes 7 and the grout 4 is poured out.
To fix the steel pipe 3 and the steel pipe 7.
【0012】以上のように地中連続壁1から突設した鋼
管3と側壁6から突出した鋼管7によって鉛直方向の力
を伝達する支承が形成され、躯体の浮力に対し連続地中
壁1の重量が抵抗として利用できる。As described above, the steel pipe 3 protruding from the underground continuous wall 1 and the steel pipe 7 protruding from the side wall 6 form a bearing for transmitting a vertical force. Weight is available as resistance.
【0013】[0013]
【発明が解決しようとする課題】この図3に示す接合方
法は、側壁からの上向きの力より下向きの力が大きい場
合で、躯体の支持地盤が弱い場合には有効である。しか
し、後からグラウトホース9を介してグラウト4を充填
するなど構造的にも施工的にも複雑であり、手間とコス
トがかかる。The joining method shown in FIG. 3 is effective when the downward force is greater than the upward force from the side wall and the supporting ground of the frame is weak. However, since the grout 4 is later filled with the grout 4 via the grout hose 9, the structure and the construction are complicated, and it takes time and cost.
【0014】さらに、実験結果の一例として図4に示す
ように、靭性(粘り)が小さく、浮力がかかり始めてか
ら破壊するまでの変位追従性能が小さい。そのため施工
誤差等による抵抗力のアンバランスを加味して大きめの
せん断力伝達部材の構造、数を設置する必要があり、無
駄がある。Further, as an example of the experimental results, as shown in FIG. 4, the toughness (stickiness) is small, and the displacement follow-up performance from the start of applying buoyancy to breaking is small. For this reason, it is necessary to set the structure and number of the large shear force transmitting members in consideration of the unbalance of the resistance force due to the construction error and the like, which is wasteful.
【0015】本発明の目的は前記従来例の不都合を解消
し、浮力に対する躯体重量の不足分を地中連続壁の重量
を利用するようにしてコストダウンを実現できるように
する場合に、靭性の大きい接合構造とすることができ、
しかも、簡単かつ安価の構造で接合できる躯体と地中連
続壁の接合工法を提供することにある。An object of the present invention is to solve the disadvantages of the prior art and to reduce the cost of the buoyancy by using the weight of the underground continuous wall to make up for the shortage of the skeleton weight. It can be a large joint structure,
Moreover, it is an object of the present invention to provide a joining method of a skeleton and an underground continuous wall which can be joined with a simple and inexpensive structure.
【0016】[0016]
【課題を解決するための手段】本発明は前記目的を達成
するため、第1に、先に施工される地中連続壁に連結鉄
筋結合用の埋め込みアンカーを予め取付け、地中連続壁
の前面を掘削後、前記埋め込みアンカーに連結鉄筋を取
付け、さらに、連結鉄筋にかご鉄筋を取付けた後、コン
クリートを打設して鉄筋コンクリート製の接合部を地中
連続壁面に一体に突設し、この接合部を取込むようにし
て躯体を施工すること、第2に、接合部は上面には緩衝
材を配設し、この緩衝材付きの接合部を取込むようにし
て躯体を施工すること、第3に、接合部は横方向に連続
させることを要旨とするものである。According to the present invention, in order to achieve the above object, firstly, an embedded anchor for connecting a connecting reinforcing bar is previously attached to an underground continuous wall to be constructed, and a front surface of the underground continuous wall is installed. After excavating, a connecting rebar is attached to the embedded anchor, and further, a cage rebar is attached to the connecting rebar, and concrete is cast, and a joint made of reinforced concrete is integrally protruded from the continuous underground wall surface. Secondly, the joint is provided with a cushioning material on the upper surface, and the joint is constructed so as to incorporate the joint with the cushioning material. Third, the joining is performed. The gist of the section is to be continuous in the lateral direction.
【0017】堅固な地盤に支持されている場合には、タ
ンク自重+液重による沈下は2,3cm程度であり、浮力
による上向きの力が作用した場合、沈下した量だけ浮き
上がった後せん断力伝達機構が機能し、浮力に抵抗する
ことになる。この程度の動きであれば、タンクとして機
能上何ら問題はない。When supported by solid ground, the subsidence due to the tank's own weight + the liquid weight is about 2 to 3 cm. When an upward force due to buoyancy acts, it is lifted up by the amount of subsidence and then transmitted to the shear force. The mechanism will work and resist buoyancy. With this degree of movement, there is no problem in function as a tank.
【0018】請求項1記載の本発明によれば、コンクリ
ートを打設して形成した接合部は、実験結果の一例とし
て図2に示すように、靭性の大きい鉄筋コンクリート構
造であるため、せん断力伝達構造には上向きの力に対し
てせん断力伝達構造にほぼ均等に力が作用するため、上
向き力を割り増しした設計とする必要はない。さらに、
簡単な構造であり、金物を使わないことから安価なもの
ですむ。According to the first aspect of the present invention, as shown in FIG. 2 as an example of an experimental result, a joint formed by casting concrete has a tough reinforced concrete structure. Since the force acts on the structure almost equally to the shear force transmitting structure with respect to the upward force, it is not necessary to design the upward force extra. further,
It has a simple structure and is inexpensive because no hardware is used.
【0019】請求項2記載の本発明によれば、前記作用
に加えて、躯体が沈下するという下向きの力はせん断力
伝達構造に作用せず、接合部の緩衝材の圧縮変位で吸収
してしまうため、せん断力伝達機構には上向きの力のみ
を考慮すればよく、経済的である。According to the second aspect of the present invention, in addition to the above-mentioned action, the downward force that the skeleton sinks does not act on the shear force transmission structure, but is absorbed by the compression displacement of the cushioning material at the joint. Therefore, only the upward force needs to be considered for the shear force transmission mechanism, which is economical.
【0020】請求項3記載の本発明によれば、前記作用
に加えて、接合部は横方向に連続させることにより、バ
ーや嵌合の金物を適宜間隔で埋設して接合する場合に比
べてこれらを多数密に並べるのと同様の結合効果が得ら
れる。According to the third aspect of the present invention, in addition to the above-described operation, the joining portion is made continuous in the lateral direction, so that a bar or fitting metal is buried at appropriate intervals and joined. The same coupling effect can be obtained as when many of them are densely arranged.
【0021】[0021]
【発明の実施の形態】以下、図面について本発明の実施
形態を詳細に説明する。図1は本発明の躯体と地中連続
壁の接合工法の1実施形態を示す要部の縦断側面図で、
図中1は地中連続壁、10は地下タンク等の大型地下構造
物の躯体である。Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a longitudinal sectional side view of an essential part showing one embodiment of a jointing method of a skeleton and an underground continuous wall of the present invention,
In the figure, 1 is an underground continuous wall, and 10 is a frame of a large underground structure such as an underground tank.
【0022】地中連続壁1は躯体10の施工に先立ち予め
施工するものであり、連続地中壁1は止水と土留を行う
ものとして下端は不透水層まで到らせる。The underground continuous wall 1 is to be constructed in advance prior to the construction of the skeleton 10. The continuous underground wall 1 is to be used for water stoppage and soil retention, and the lower end is extended to an impermeable layer.
【0023】かかる地中連続壁1を施工するに際し、後
述の連結鉄筋12の結合用の埋め込みアンカー11を予め取
付けておく。When the underground continuous wall 1 is constructed, an embedded anchor 11 for connecting a connecting reinforcing bar 12 described later is attached in advance.
【0024】本実施形態では埋め込みアンカー11は、ネ
ジ継手13にネジ鉄筋14を螺合し、このネジ鉄筋14の端部
に定着板15を定着ナット16で固定して形成した。図中17
は地中連続壁1を形成する鉄筋である。In this embodiment, the embedded anchor 11 is formed by screwing a threaded reinforcing bar 14 to a threaded joint 13 and fixing a fixing plate 15 to an end of the threaded reinforcing bar 14 with a fixing nut 16. In the figure 17
Is a reinforcing bar forming the underground continuous wall 1.
【0025】このようにして地中連続壁1を施工し、そ
の前面を掘削後、前記埋め込みアンカー11を検出してこ
こに連結鉄筋18を取付ける。この連結鉄筋18もネジ鉄筋
を使用してネジ継手13に螺合し、端部に定着板15を定着
ナット16で固定した。The underground continuous wall 1 is constructed in this way, and after excavating the front surface thereof, the embedded anchor 11 is detected and the connecting reinforcing bar 18 is attached thereto. The connecting rebar 18 was also screwed to the screw joint 13 using a screw rebar, and a fixing plate 15 was fixed to an end with a fixing nut 16.
【0026】さらに、前記連結鉄筋18にかご鉄筋21を取
付けた後、型枠で囲撓し、コンクリートを打設して鉄筋
コンクリート製の接合部19を地中連続壁1の面に一体に
突設するように形成する。そしてこの接合部19の上面に
は発泡スチロール等の剛性の小さい(変形しやすい)緩
衝材20を配設する。Further, after the cage bar 21 is attached to the connecting bar 18, the cage bar 21 is bent around by a formwork, and concrete is cast to form a reinforced concrete joint 19 integrally with the surface of the underground continuous wall 1. It is formed so that On the upper surface of the joint 19, a cushioning material 20 having a small rigidity (easy to deform) such as styrene foam is provided.
【0027】このような緩衝材20付きの接合部19を取込
むようにして、躯体10側の鉄筋を組み立て、コンクリー
トを打設して躯体10を施工する。The reinforcing bar on the side of the skeleton 10 is assembled so as to take in such a joint 19 with the cushioning material 20, and concrete is cast to construct the skeleton 10.
【0028】なお、前記接合部19は断続的なものでもよ
いが、横方向に、例えば、地下タンクの場合は周方向に
直線状に長く連続させる。The connecting portion 19 may be intermittent, but it is long and continuous in the horizontal direction, for example, in the case of an underground tank, in the circumferential direction.
【0029】また、他の実施形態として支持地盤が極め
て良質で、躯体側重量による沈下量が極めて小さい場合
には前記緩衝材20を取り付けずに躯体10を施工すること
もできる。Further, as another embodiment, when the supporting ground is very good and the amount of settlement due to the weight on the skeleton side is extremely small, the skeleton 10 can be constructed without attaching the cushioning material 20.
【0030】以上のように地中連続壁1から突設した接
合部19によって鉛直方向の力を伝達する支承が形成さ
れ、躯体10の浮力に対し地中連続壁1の重量が抵抗とし
て利用できる。As described above, the joint 19 projecting from the underground continuous wall 1 forms a bearing for transmitting a vertical force, and the weight of the underground continuous wall 1 can be used as resistance against the buoyancy of the frame 10. .
【0031】[0031]
【発明の効果】以上のべたように本発明の躯体と地中連
続壁の接合工法は、浮力に対する躯体重量の不足分を地
中連続壁の重量を利用するようにしてコストダウンを実
現できるようにする場合に、靭性の大きい接合構造とす
ることができ、しかも、簡単かつ安価の構造で接合でき
るものである。As described above, the method for joining a skeleton and a diaphragm wall according to the present invention can reduce costs by utilizing the weight of the diaphragm wall for the shortage of the skeleton weight with respect to buoyancy. In this case, it is possible to obtain a joining structure having a large toughness, and to join with a simple and inexpensive structure.
【図1】本発明の躯体と地中連続壁の接合工法の1実施
形態を示す要部の縦断側面図である。FIG. 1 is a longitudinal sectional side view of a main part showing one embodiment of a joining method of a skeleton and an underground continuous wall of the present invention.
【図2】本発明でのせん断力とずれ変位の関係を示すグ
ラフである。FIG. 2 is a graph showing a relationship between a shear force and a displacement in the present invention.
【図3】従来例を示す要部の縦断側面図である。FIG. 3 is a vertical sectional side view of a main part showing a conventional example.
【図4】従来例でのせん断力とずれ変位の関係を示すグ
ラフである。FIG. 4 is a graph showing a relationship between a shearing force and a displacement in a conventional example.
1…地中連続壁 2…鉄板 3…鋼管 4…グラウト 6…側壁 7…鋼管 8…コンクリート 9…グラウトホース 10…躯体 11…埋め込みアンカー 13…ネジ継手 14…ネジ鉄筋 15…定着板 16…定着ナット 17…鉄筋 18…連結鉄筋 19…接合部 20…緩衝材 21…かご鉄筋 DESCRIPTION OF SYMBOLS 1 ... Underground continuous wall 2 ... Iron plate 3 ... Steel pipe 4 ... Grout 6 ... Side wall 7 ... Steel pipe 8 ... Concrete 9 ... Grout hose 10 ... Building body 11 ... Embedded anchor 13 ... Screw joint 14 ... Screw reinforcement 15 ... Fixing plate 16 ... Fixation Nut 17 ... Reinforcing bar 18 ... Connected reinforcing bar 19 ... Junction 20 ... Cushioning material 21 ... Cage bar
───────────────────────────────────────────────────── フロントページの続き (72)発明者 田口 勝則 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (56)参考文献 特開 平7−62647(JP,A) 特開 平4−337200(JP,A) 特開 平6−108460(JP,A) 特開 平5−321245(JP,A) 実公 昭48−14883(JP,Y1) (58)調査した分野(Int.Cl.7,DB名) E02D 29/00 - 29/04 E02D 5/00 - 5/20 ──────────────────────────────────────────────────続 き Continuation of front page (72) Inventor Katsunori Taguchi 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (56) References JP-A-7-62647 (JP, A) 4-337200 (JP, A) JP-A-6-108460 (JP, A) JP-A-5-321245 (JP, A) Jiko 48-14883 (JP, Y1) (58) Fields investigated (Int. Cl. 7 , DB name) E02D 29/00-29/04 E02D 5/00-5/20
Claims (3)
合用の埋め込みアンカーを予め取付け、地中連続壁の前
面を掘削後、前記埋め込みアンカーに連結鉄筋を取付
け、さらに、連結鉄筋にかご鉄筋を取付けた後、コンク
リートを打設して鉄筋コンクリート製の接合部を地中連
続壁面に一体に突設し、この接合部を取込むようにして
躯体を施工することを特徴とした躯体と地中連続壁の接
合工法。1. An embedded anchor for connecting a reinforcing bar is previously attached to an underground continuous wall to be constructed first, and after excavating the front surface of the underground continuous wall, a connecting reinforcing bar is attached to the embedded anchor. After installing the cage bar, concrete is cast and a reinforced concrete joint is protruded integrally with the continuous underground wall, and the skeleton is constructed so as to incorporate this joint. Continuous wall joining method.
緩衝材付きの接合部を取込むようにして躯体を施工する
請求項1記載の躯体と地中連続壁の接合工法。2. The method according to claim 1, wherein a cushioning material is provided on an upper surface of the joint, and the frame is constructed so as to take in the joint with the cushioning material.
たは請求項2記載の躯体と地中連続壁の接合工法。3. The method according to claim 1, wherein the joint is continuous in a lateral direction.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7318113A JP3028053B2 (en) | 1995-12-06 | 1995-12-06 | Joining method between building and diaphragm wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7318113A JP3028053B2 (en) | 1995-12-06 | 1995-12-06 | Joining method between building and diaphragm wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH09158171A JPH09158171A (en) | 1997-06-17 |
| JP3028053B2 true JP3028053B2 (en) | 2000-04-04 |
Family
ID=18095644
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP7318113A Expired - Lifetime JP3028053B2 (en) | 1995-12-06 | 1995-12-06 | Joining method between building and diaphragm wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3028053B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6374762B2 (en) * | 2014-11-04 | 2018-08-15 | 鹿島建設株式会社 | Shear force transmission structure group, construction method of shear force transmission structure |
| CN106120857B (en) * | 2016-06-22 | 2018-06-22 | 上海建工七建集团有限公司 | A kind of connection pipeline construction method |
| CN113529766B (en) * | 2021-06-26 | 2022-10-11 | 广东中城建设集团有限公司 | Underground continuous wall stable in application and construction method thereof |
-
1995
- 1995-12-06 JP JP7318113A patent/JP3028053B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH09158171A (en) | 1997-06-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109024679A (en) | A kind of supporting and the integrated system of Pipe rack and construction method | |
| JP3028053B2 (en) | Joining method between building and diaphragm wall | |
| JP6860895B2 (en) | Retaining wall and its construction method | |
| JP2006291575A (en) | Retaining wall and method of constructing the same | |
| JP2009007865A (en) | Building structure | |
| JP2004238863A (en) | Lightweight banking construction and construction method therefor | |
| JP3641227B2 (en) | Construction method of underground structure | |
| KR100400853B1 (en) | Removable soil nailing method and its nail assembly | |
| JP2004044303A (en) | Connection structure for foundation pile and superstructure, pile head joint member, and connecting method for foundation pile and superstructure | |
| KR100401237B1 (en) | Soil improvement technique for foundation applied to reinforced earth theory using reinforcing rod-band-types anchor | |
| JP4684479B2 (en) | Structure of the connection between the pile and the pile head structure | |
| KR200214387Y1 (en) | Building Anchoring structure by friction | |
| JPH0324541B2 (en) | ||
| KR100827202B1 (en) | Construction method of site-cast concrete underground structure, panel member for formwork frame used in this construction method and installation method | |
| KR20040050137A (en) | Panel Assembly A Breast Wall to increase supporting power | |
| JPH11280063A (en) | Pile head structure and pile head hardware | |
| KR100767953B1 (en) | Separating method of Monowall with spandrel girders | |
| JP2002309883A (en) | Propulsion shaft support structure | |
| JP7314432B1 (en) | Foundation structure of building and construction method of foundation structure | |
| JP3678290B2 (en) | High earthquake resistance foundation | |
| JP2876434B2 (en) | Joint structure of underground structures subject to buoyancy | |
| KR200205781Y1 (en) | Nail assembly for removable soil nailing method | |
| KR20000059203A (en) | Retaining Wall Construction Method | |
| JPH09228395A (en) | Retaining wall structure | |
| JP2001288758A (en) | Basic seismic structure and foundation seismic reinforcement method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090204 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120204 Year of fee payment: 12 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160204 Year of fee payment: 16 |
|
| EXPY | Cancellation because of completion of term |