JP3084253B2 - Construction method of base panel for steel frame building - Google Patents
Construction method of base panel for steel frame buildingInfo
- Publication number
- JP3084253B2 JP3084253B2 JP09120331A JP12033197A JP3084253B2 JP 3084253 B2 JP3084253 B2 JP 3084253B2 JP 09120331 A JP09120331 A JP 09120331A JP 12033197 A JP12033197 A JP 12033197A JP 3084253 B2 JP3084253 B2 JP 3084253B2
- Authority
- JP
- Japan
- Prior art keywords
- fixed
- base
- base panel
- bar
- panel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、施工現場で構築さ
れた鉄骨に、下地用パネルを固定する建築方法に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for fixing a base panel to a steel frame constructed at a construction site.
【0002】[0002]
【従来の技術】鉄骨造の建物は、施工現場で鉄骨を構築
した後、鉄骨に下地用パネルを固定し、その後、下地用
パネルの屋外側に外壁を固定して構築している。この工
法において、下地用パネルを短時間で鉄骨に固定するこ
とが大切である。それは、下地用パネルの固定された鉄
骨造建物は、雨風が侵入しないので、その後の施工を極
めて能率よくできるからである。2. Description of the Related Art A steel-frame building is constructed by constructing a steel frame at a construction site, fixing a base panel to the steel frame, and then fixing an outer wall to the outdoor side of the base panel. In this method, it is important to fix the base panel to the steel frame in a short time. The reason is that a steel frame building to which the base panel is fixed does not allow rain and wind to enter, so that subsequent construction can be performed extremely efficiently.
【0003】図1と図2の断面図は、従来の工法で構築
される、鉄骨造建物の垂直断面図を示している。図1の
鉄骨造建物は、下記の工程で構築される。 鉄骨の水
平構造材1、すなわち、梁の正確な位置に、施工現場
で、あるいは、工場でフラットバー2を溶接して固定す
る。 構築された鉄骨のフラットバー2に、鉄骨や木
製の胴ぶち3を固定する。 胴ぶち3の表面に、構造
用合板やコンパネ等のパネル4を固定する。 構造用
合板等のパネル4の内面に、断熱材5を固定する。The sectional views of FIGS. 1 and 2 show a vertical sectional view of a steel-frame building constructed by a conventional method. The steel frame building of FIG. 1 is constructed by the following steps. A flat bar 2 is welded and fixed at the exact position of the steel horizontal structure 1, that is, the beam, at the construction site or at the factory. A steel frame or a wooden tab 3 is fixed to the constructed steel flat bar 2. A panel 4 such as a structural plywood or a control panel is fixed to the surface of the trunk 3. The heat insulating material 5 is fixed to the inner surface of the panel 4 such as a structural plywood.
【0004】図2の鉄骨造建物は、下記の工程で構築さ
れる。 構築された鉄骨の水平構造材1、すなわち、
梁の正確な位置に、胴ぶち3を固定するための貫通孔を
開ける。 上下に平行に配設される水平構造材1であ
る梁の対向面に、胴ぶち3をボルト6で固定する。
胴ぶち3の表面に、構造用合板やコンパネ等のパネル4
を固定する。 構造用合板等のパネル4の内面に、断
熱材5を固定する。[0004] The steel frame building shown in FIG. 2 is constructed by the following steps. The constructed horizontal structure 1 of steel frame,
At a precise position of the beam, a through hole for fixing the toe 3 is opened. A toe 3 is fixed to an opposing surface of a beam, which is a horizontal structural member 1 arranged vertically in parallel with bolts 6.
Panels 4 of structural plywood, control panel, etc. on the surface of the toe 3
Is fixed. The heat insulating material 5 is fixed to the inner surface of the panel 4 such as a structural plywood.
【0005】以上の工程で、下地用パネルを鉄骨に固定
した後、下地用パネルの屋外側には、防水シート7が張
られ、さらに、防水シート7の上に外壁8が固定され
る。After the base panel is fixed to the steel frame in the above steps, a waterproof sheet 7 is stretched on the outdoor side of the base panel, and an outer wall 8 is fixed on the waterproof sheet 7.
【0006】[0006]
【発明が解決しようとする課題】図1と図2に示す鉄骨
造建物の建築方法は、フラットバー2を水平構造材であ
る梁に溶接して胴ぶちを固定し、あるいは、梁に貫通孔
を開けてパネル4を固定するので、高度な技術が要求さ
れると共に、胴ぶちとパネルを正確な位置に固定するの
が難しい。胴ぶちや貫通孔の位置がずれると、パネルを
正確な位置に固定でなきなくなるからである。胴ぶちと
パネルを正確な位置に固定するために、職人が慎重に、
フラットバーや胴ぶちを固定し、あるいは、貫通孔を開
けると、時間がかかって能率よく下地用パネルを固定で
きなくなる。とくに、この工法は、フラットバーおよび
胴ぶちの固定と、貫通孔の開口に相当な時間がかかるの
で、さらに、その作業を慎重にすると、時間が極めて長
くなり、能率よく施工できなくなってしまう。The construction method of a steel frame building shown in FIGS. 1 and 2 is to fix a body bar by welding a flat bar 2 to a beam which is a horizontal structural member, or to provide a through hole in the beam. Since the panel 4 is opened and the panel 4 is fixed, a high level of technology is required, and it is difficult to fix the body edge and the panel at an accurate position. This is because if the positions of the body edge and the through hole are shifted, the panel cannot be fixed at an accurate position. In order to fix the torso and panel in the correct position, the craftsman carefully
If the flat bar or the body edge is fixed, or if a through-hole is opened, it takes time, and the base panel cannot be fixed efficiently. In particular, this method requires a considerable amount of time to fix the flat bar and the body edge and to open the through hole, and if the work is carefully performed, the time becomes extremely long, so that the construction cannot be performed efficiently.
【0007】このため、図1と図2に示す鉄骨造建物の
建築方法は、現場職人の腕にたよるので品質にばらつき
があり、しかも、能率よく短期間で施工できない欠点が
ある。さらに、この建築方法は、構造用合板等を固定し
た後、その内面にグラスウール等の断熱材を固定するの
で、下記のような弊害もある。 断熱材のずれ落ち、
つぶれなどの変形 隙間の皺など施工精度のバラツキ
又、入れ忘れ 湿気及び結露による断熱性能の低下
断熱材の切りくずによる現場の汚れ 断熱工事をき
ちんとすればするほど、人工及び日数が多くなるFor this reason, the construction method of a steel frame building shown in FIGS. 1 and 2 has the disadvantage that the quality varies because it depends on the skill of a field craftsman and that the construction cannot be performed efficiently and in a short period of time. Furthermore, in this construction method, after fixing a structural plywood or the like, a heat insulating material such as glass wool is fixed on the inner surface thereof. Insulation slips,
Deformation such as crushing Variations in construction accuracy such as wrinkles in gaps, or forgetting to insert Reduced insulation performance due to moisture and dew condensation Dirt on site due to chips from insulation material The more properly the insulation work, the more man-made and the number of days
【0008】本発明は、このような欠点を解決すること
を目的に開発されたものである。本発明の重要な目的
は、下地用パネルを、簡単かつ容易に、しかも能率よく
正確な位置に固定できる鉄骨造建物における下地用パネ
ルの建築方法を提供することにある。[0008] The present invention has been developed for the purpose of solving such disadvantages. An important object of the present invention is to provide a method of constructing a base panel in a steel frame building, which can fix the base panel at an accurate position simply, easily, and efficiently.
【0009】[0009]
【課題を解決するための手段】本発明の鉄骨造建物にお
ける下地用パネルの建築方法は、現場で構築された鉄骨
に、連結部材9を介して下地用パネル10を固定する工
法を改良して発明したものである。本発明の建築方法
は、連結部材9に、水平構造材1に、アーム9Aを介し
て平行に連結される下地バー9Bと、この下地バー9B
の定位置に下地用パネル10を連結する位置決材9Cと
を使用する。位置決材9Cとして、下地用パネル10の
上縁を位置決めする上側位置決材9Cと、下地用パネル
10の下縁を位置決めする下側位置決材9Cを使用す
る。According to the present invention, there is provided a method of constructing a base panel in a steel structure building by improving a method of fixing a base panel 10 via a connecting member 9 to a steel frame constructed on site. It was invented. The construction method according to the present invention includes a base bar 9B connected to the connecting member 9 in parallel with the horizontal structural member 1 via an arm 9A, and the base bar 9B.
And the positioning material 9C for connecting the base panel 10 to the predetermined position. As the positioning material 9C, an upper positioning material 9C for positioning the upper edge of the base panel 10 and a lower positioning material 9C for positioning the lower edge of the base panel 10 are used.
【0010】さらに、本発明の建築方法は、下地バー9
Bを、たとえば、鉄骨を加工する工場で、水平構造材1
から屋外側に突出して、アーム9Aを介して水平構造材
1と平行に固定する。鉄骨を構築した後に、水平構造材
1の定位置に固定している下地バー9Bに、上側位置決
材9Cと下側位置決材9Cからなる位置決材9Cを施工
現場で固定する。上側位置決材9Cと下側位置決材9C
は、下地用パネル10をフラットに固定できる位置に固
定する。下側位置決材9Cは下地バー9Bの上面に固定
し、上側位置決材9Cは下地バー9Bの下面に固定す
る。下地用パネル10の上縁を上側位置決材9Cで位置
決めして、下地用パネル10の下縁を下地バー9Bに載
せて、下側位置決材9Cに当接させて、下地バー9Bの
定位置に配設し、この状態で、下地用パネル10の上側
の水平枠10Aと下側の水平枠10Aを下地バー9Cに
固定する。Further, the building method of the present invention provides
B, for example, at a factory that processes steel frames,
From outside and fixed in parallel with the horizontal structural member 1 via the arm 9A. After constructing the steel frame, the positioning material 9C composed of the upper positioning material 9C and the lower positioning material 9C is fixed to the base bar 9B fixed to the fixed position of the horizontal structural member 1 at the construction site. Upper positioning material 9C and lower positioning material 9C
Is fixed to a position where the base panel 10 can be fixed flat. The lower positioning member 9C is fixed to the upper surface of the base bar 9B, and the upper positioning member 9C is fixed to the lower surface of the base bar 9B. The upper edge of the base panel 10 is positioned by the upper positioning member 9C, and the lower edge of the base panel 10 is placed on the base bar 9B and is brought into contact with the lower positioning member 9C to fix the base bar 9B. In this state, the upper horizontal frame 10A and the lower horizontal frame 10A of the base panel 10 are fixed to the base bar 9C.
【0011】さらに、本発明の請求項2の鉄骨造建物に
おける下地用パネルの建築方法は、上側位置決材9Cと
して、内側に下地用パネル10を嵌入できるコ字状の溝
型鋼を使用し、下側位置決材9Cには幅の狭い溝型鋼を
使用する。下地用パネル10は、上縁を上側位置決材9
Cの溝に入れるが、下地用パネル10の下縁は下地バー
9Bに載せて、下側位置決材9Cに当接して、下地バー
9Bの定位置に配設する。Further, in the method of constructing a base panel in a steel frame building according to claim 2 of the present invention, a U-shaped channel steel into which the base panel 10 can be fitted is used as the upper positioning member 9C, A narrow channel steel is used for the lower positioning member 9C. The base panel 10 has an upper edge formed by the upper positioning member 9.
The lower edge of the base panel 10 is placed on the base bar 9B, abuts against the lower positioning member 9C, and is disposed at a fixed position of the base bar 9B.
【0012】さらにまた、本発明の請求項3の鉄骨造建
物における下地用パネルの建築方法は、下地用パネル1
0を製作する工場で、下地用パネル10に断熱材5を固
定する。あらかじめ断熱材5の固定された下地用パネル
10を、施工現場で下地バー9Bに固定することを特徴
とする。Still further, according to a third aspect of the present invention, there is provided a method of constructing a base panel in a steel frame building, comprising:
In a factory for manufacturing the base material 0, the heat insulating material 5 is fixed to the base panel 10. The base panel 10 to which the heat insulating material 5 is fixed in advance is fixed to the base bar 9B at the construction site.
【0013】[0013]
【発明の実施の形態】以下、本発明の実施例を図面に基
づいて説明する。ただし、以下に示す実施例は、本発明
の技術思想を具体化するための鉄骨造建物における下地
用パネルの建築方法を例示するものであって、本発明は
建築方法を下記のものに特定しない。Embodiments of the present invention will be described below with reference to the drawings. However, the following examples illustrate a method of building a base panel in a steel-framed building to embody the technical idea of the present invention, and the present invention does not specify a building method as follows. .
【0014】さらに、この明細書は、特許請求の範囲を
理解し易いように、実施例に示される部材に対応する番
号を、「特許請求の範囲の欄」、および「課題を解決す
るための手段の欄」に示される部材に付記している。た
だ、特許請求の範囲に示される部材を、実施例の部材に
特定するものでは決してない。Further, in this specification, in order to make it easy to understand the claims, the numbers corresponding to the members shown in the embodiments will be referred to as “claims” and “ In the column of “means”. However, the members described in the claims are not limited to the members of the embodiments.
【0015】図3ないし図5に示す鉄骨造建物は、基礎
11に柱12を垂直に固定し、この柱12に、水平構造
材1である梁を連結して鉄骨を構築している。鉄骨に
は、連結部材9を介して下地用パネル10を固定してい
る。連結部材9は、アーム9Aを介して水平構造材1で
ある梁に連結されている下地バー9Bと、この下地バー
9Bの定位置に下地用パネル10を配設する位置決材9
Cとからなる。In the steel-frame building shown in FIGS. 3 to 5, a pillar 12 is vertically fixed to a foundation 11, and a beam, which is a horizontal structural member 1, is connected to the pillar 12, thereby constructing a steel frame. A base panel 10 is fixed to the steel frame via a connecting member 9. The connecting member 9 includes a base bar 9B connected to a beam as the horizontal structural member 1 via an arm 9A, and a positioning member 9 for disposing a base panel 10 at a fixed position of the base bar 9B.
C.
【0016】下地バー9Bは、肉厚が2.3mmである
鉄パイプの鋼製角型パイプである。この下地バー9B
は、タッピングビスで位置決材9Cを簡単に固定できる
特長がある。また、軽くて、強靭な特長もある。ただ、
本発明の建築方法は、下地バー9Bを角型パイプに特定
しない。下地バー9Bには、たとえば、C型鋼である軽
量形鋼やL形鋼も使用できる。下地バー9Bは、アーム
9Aを介して水平構造材1に平行に連結される。アーム
9Aは一定の間隔で、下地バー9Bと水平構造材1とに
溶接して、下地バー9Bを水平構造材1に固定する。さ
らに、下地バー9Bは、水平構造材1よりも屋外側に突
出して固定される。The base bar 9B is a steel square pipe made of an iron pipe having a thickness of 2.3 mm. This base bar 9B
Is characterized in that the positioning material 9C can be easily fixed with a tapping screw. It also has light and tough features. However,
The construction method of the present invention does not specify the base bar 9B as a square pipe. For the base bar 9B, for example, a light section steel or an L-section steel, which is a C-type steel, can also be used. The base bar 9B is connected in parallel to the horizontal structural member 1 via an arm 9A. The arm 9A is welded to the base bar 9B and the horizontal structural member 1 at regular intervals to fix the base bar 9B to the horizontal structural member 1. Further, the base bar 9B protrudes outward from the horizontal structural member 1 and is fixed.
【0017】図3と図4は二階建ての鉄骨造建物を示
す。この建物は、1階と2階の境界に設けられる水平構
造材1である梁と、2階の天井部分に位置する水平構造
材1である梁にアーム9Aを介して下地バー9Bを固定
している。1階の床に位置する下地バー9Bは、水平構
造材1でなくて、L金具13を介して基礎11に固定し
ている。図3と図4に示される全ての下地バー9Bは、
同一垂直面に位置するように固定される。FIGS. 3 and 4 show a two-story steel frame building. In this building, a base bar 9B is fixed via an arm 9A to a beam, which is a horizontal structural member 1 provided at the boundary between the first floor and the second floor, and a beam, which is a horizontal structural member 1 located at the ceiling portion of the second floor. ing. The ground bar 9B located on the floor of the first floor is not fixed to the horizontal structural member 1, but is fixed to the foundation 11 via an L bracket 13. All the underlying bars 9B shown in FIG. 3 and FIG.
It is fixed so that it is located on the same vertical plane.
【0018】位置決材9Cは、下地バー9Bの定位置に
下地用パネル10を固定するために下地バー9Bに固定
される。位置決材9Cは、下地用パネル10の上縁を入
れて定位置に配設する上側位置決材9Cと、下地用パネ
ル10の下縁を当接させて位置決めする下側位置決材9
Cとからなる。上側位置決材9Cは、内側に下地用パネ
ル10を嵌入できるコ字状の溝型鋼である。下側位置決
材9Cは、幅の狭い溝型鋼である。The positioning member 9C is fixed to the base bar 9B in order to fix the base panel 10 at a fixed position of the base bar 9B. The positioning member 9C includes an upper positioning member 9C that is disposed at a fixed position with the upper edge of the base panel 10 inserted therein and a lower positioning member 9 that positions the lower panel 10 by abutting the lower edge thereof.
C. The upper positioning member 9C is a U-shaped channel steel into which the base panel 10 can be fitted. The lower positioning member 9C is a narrow channel steel.
【0019】上側位置決材9Cは、図5に示すように、
下地バー9Bの下面に固定される。下側位置決材9C
は、基礎11に固定される1階の下地バー9Bの上面
と、1階と2階の境界に位置する下地バー9Bの上面と
に固定される。上側位置決材9Cと下側位置決材9C
は、位置決材9Cと下地バー9Bとを貫通するタッピン
グビスで、下地バー9Bにネジ止して固定される。The upper positioning member 9C is, as shown in FIG.
It is fixed to the lower surface of base bar 9B. Lower positioning material 9C
Are fixed to the upper surface of the ground bar 9B on the first floor fixed to the foundation 11 and the upper surface of the ground bar 9B located at the boundary between the first floor and the second floor. Upper positioning material 9C and lower positioning material 9C
Is a tapping screw that penetrates the positioning member 9C and the base bar 9B, and is fixed to the base bar 9B by screws.
【0020】上下に配設される下地バー9Bの間に下地
用パネル10が固定される。下地用パネル10は、図6
の背面図に示すように、構造用合板の周囲に、水平枠1
0Aと垂直枠10Bとからなる木製の外周枠を固定した
木下地のパネル、あるいは、構造用合板に鉄骨の外周枠
を固定している鉄骨下地のパネルである。この図の下地
用パネル10は、中央も垂直枠10Bを固定している。
下地用パネル10は、断熱特性を改善するために、構造
用合板の内面で、水平枠10Aと垂直枠10Bの内側に
グラスウールや合成樹脂発泡体等の断熱材5を固定して
いる。A base panel 10 is fixed between base bars 9B provided above and below. The base panel 10 is shown in FIG.
As shown in the rear view of FIG.
It is a wooden base panel in which a wooden outer frame composed of 0A and a vertical frame 10B is fixed, or a steel base panel in which a steel outer frame is fixed to a structural plywood. In the base panel 10 in this figure, the vertical frame 10B is also fixed at the center.
The base panel 10 has a heat insulating material 5 such as glass wool or a synthetic resin foam fixed inside the horizontal frame 10A and the vertical frame 10B on the inner surface of the structural plywood in order to improve the heat insulating property.
【0021】以上の構造の鉄骨造建物は、下記の建築方
法で構築される。 (1) 工場で下地用パネル10を製作する。下地用パネ
ル10は、構造用合板の片面に、水平枠10Aと垂直枠
10Bを固定し、さらに、構造用合板の内面にグラスウ
ール等の断熱材5を固定する。 (2) 鉄骨を加工する工場で、水平構造材1となる梁
に、アーム9Aを介して下地バー9Bを溶接して固定す
る。下地バー9Bは、図3と図4に示すように、鉄骨を
基礎11に固定した状態で、下地用パネル10を固定す
る位置に配設される。 (3) 下地バー9Bの固定された水平構造材1となる梁
や柱、さらに、下地用パネル10を加工工場から建築現
場に運ぶ。 (4) 基礎11に柱や水平構造材1となる梁を固定し
て、鉄骨を組み立てる。さらに、基礎11の上面にL金
具13を介して下地バー9Bを固定する。 (5) 定位置に固定された下地バー9Bに、墨だしして
位置決材9Cを定位置に固定する。上側位置決材9Cと
下側位置決材9Cからなる位置決材9Cは、下地用パネ
ル10をフラットに固定できる位置に固定される。位置
決材9Cは、タッピングビスで下地バー9Bに固定され
る。 (6) 下地用パネル10の上縁を上側位置決材9Cの溝
に入れ、下縁を下地バー9Bに載せて押し込み、下側位
置決材9Cに当接させて、下地用パネル10を下地バー
9Bの定位置に配設する。この状態で、下地用パネル1
0の上側の水平枠10Aを、上側位置決材9Cを貫通す
るタッピングビスで上側位置決材9Cに固定し、下側の
水平枠10Aは、これを貫通するタッピングビスで下地
バー9Bに固定する。この状態で、下地用パネル10が
下地バー9Bに固定される。The steel frame building having the above structure is constructed by the following construction method. (1) The base panel 10 is manufactured at the factory. In the base panel 10, a horizontal frame 10A and a vertical frame 10B are fixed to one surface of the structural plywood, and a heat insulating material 5 such as glass wool is fixed to the inner surface of the structural plywood. (2) At a steelwork factory, a base bar 9B is welded and fixed to a beam serving as the horizontal structural member 1 via an arm 9A. The base bar 9B is provided at a position where the base panel 10 is fixed in a state where the steel frame is fixed to the foundation 11, as shown in FIGS. (3) The beams and columns serving as the horizontal structural material 1 to which the base bar 9B is fixed, and the base panel 10 are transported from the processing plant to the construction site. (4) The pillars and the beams to be the horizontal structural members 1 are fixed to the foundation 11, and a steel frame is assembled. Further, the base bar 9B is fixed to the upper surface of the base 11 via the L bracket 13. (5) Inking is performed on the base bar 9B fixed at the fixed position, and the positioning material 9C is fixed at the fixed position. The positioning material 9C including the upper positioning material 9C and the lower positioning material 9C is fixed to a position where the base panel 10 can be fixed flat. The positioning material 9C is fixed to the base bar 9B with tapping screws. (6) Put the upper edge of the base panel 10 into the groove of the upper positioning member 9C, put the lower edge on the base bar 9B and push it into contact with the lower positioning member 9C. It is arranged at a fixed position of the bar 9B. In this state, the base panel 1
The upper horizontal frame 10A is fixed to the upper positioning material 9C with tapping screws penetrating the upper positioning material 9C, and the lower horizontal frame 10A is fixed to the ground bar 9B with tapping screws penetrating the upper positioning material 9C. . In this state, the base panel 10 is fixed to the base bar 9B.
【0022】以上の建築方法で下地用パネル10を固定
した後、下地用パネル10の表面に防水シート7を固定
し、さらに、その表面に外壁8が固定される。After fixing the base panel 10 by the above construction method, the waterproof sheet 7 is fixed to the surface of the base panel 10, and the outer wall 8 is fixed to the surface.
【0023】[0023]
【発明の効果】本発明の鉄骨造建物における下地用パネ
ルの建築方法は、下地用パネルを、簡単かつ容易に、し
かも能率よく正確な位置に固定できる特長がある。それ
は、本発明の建築方法が、下地用パネルを固定する下地
バーを、施工現場に搬入する前工程で、水平構造材にア
ームを介して下地バーを固定すると共に、この下地バー
に位置決材を固定して、下地用パネルを定位置に固定す
るからである。とくに、下地バーが、施工現場に搬入す
る前に、鉄骨を加工する工場等で水平構造材に固定され
るので、下地バーを簡単かつ容易に、しかも正確な位置
に固定できる。下地バーは、水平構造材から屋外に突出
するように設けられており、この下地バーに下地用パネ
ルを載せ、しかも、位置決材で正確な位置に配設して固
定するので、下地用パネルを正確に位置ずれなく固定で
きる。According to the present invention, there is provided a method of constructing a base panel in a steel frame building, which has a feature that the base panel can be fixed at a precise position simply, easily and efficiently. That is, the building method of the present invention fixes the base bar for fixing the base panel to the construction site, before fixing the base bar to the construction site, and fixing the base bar to the horizontal structural member via the arm, and positioning the base bar to the base bar. Is fixed, and the base panel is fixed at a fixed position. In particular, since the base bar is fixed to a horizontal structural member at a steel processing factory or the like before being transported to the construction site, the base bar can be fixed easily, easily, and accurately. The base bar is provided so as to protrude outside from the horizontal structural material, and the base panel is placed on the base bar, and furthermore, it is arranged and fixed at an accurate position by the positioning material. Can be accurately fixed without displacement.
【0024】さらに、本発明の請求項3の建築方法は、
あらかじめ断熱材を固定している下地用パネルを下地バ
ーに固定するので、断熱材を簡単かつ容易に、しかも確
実に剥離しないように、理想的な状態に固定できる特長
がある。Further, the construction method according to claim 3 of the present invention,
Since the base panel to which the heat insulating material is fixed in advance is fixed to the base bar, there is a feature that the heat insulating material can be fixed in an ideal state easily and easily and not to be surely peeled off.
【図1】従来の建築方法で施工される鉄骨造建物の断面
図FIG. 1 is a cross-sectional view of a steel-frame building constructed by a conventional building method.
【図2】従来の建築方法で施工される他の鉄骨造建物の
断面図FIG. 2 is a cross-sectional view of another steel-framed building constructed by a conventional building method.
【図3】本発明の実施例の建築方法で構築される鉄骨造
建物の断面図FIG. 3 is a sectional view of a steel-frame building constructed by the construction method according to the embodiment of the present invention.
【図4】図3に示す鉄骨造建物の一部断面斜視図FIG. 4 is a partial cross-sectional perspective view of the steel frame building shown in FIG. 3;
【図5】図3に示す鉄骨造建物の1階と2階の壁を示す
断面図FIG. 5 is a sectional view showing the first and second floor walls of the steel frame building shown in FIG. 3;
【図6】図5に示す鉄骨造建物に使用される下地用パネ
ルの背面図FIG. 6 is a rear view of a base panel used in the steel frame building shown in FIG. 5;
1…水平構造材 2…フラットバー 3…胴ぶち 4…パネル 5…断熱材 6…ボルト7…防水シート 8…外壁 9…連結部材 9A…アーム 9B…下地
バー 9C…位置決材 10…下地用パネル 10A…水平枠 10B…
垂直枠 11…基礎 12…柱 13…L金具DESCRIPTION OF SYMBOLS 1 ... Horizontal structure material 2 ... Flat bar 3 ... Body edge 4 ... Panel 5 ... Insulation material 6 ... Bolt 7 ... Waterproof sheet 8 ... Outer wall 9 ... Connecting member 9A ... Arm 9B ... Ground bar 9C ... Positioning material 10 ... Ground Panel 10A ... Horizontal frame 10B ...
Vertical frame 11 ... foundation 12 ... pillar 13 ... L bracket
───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.7 識別記号 FI E04B 2/56 605 E04B 2/56 605E 611 611B 611C 632 632D 632H 645 645A 651 651J 2/90 2/90 ──────────────────────────────────────────────────の Continued on the front page (51) Int.Cl. 7 Identification code FI E04B 2/56 605 E04B 2/56 605E 611 611B 611C 632 632D 632H 645 645A 651 651J 2/90 2/90
Claims (3)
て下地用パネル(10)を固定する建築方法において、 連結部材(9)として、アーム(9A)を介して水平構造材(1)
に平行に連結される下地バー(9B)と、この下地バー(9B)
の定位置に下地用パネル(10)を連結するための位置決材
(9C)を使用すると共に、この位置決材(9C)として、下地
用パネル(10)の上縁を位置決めする上側位置決材(9C)
と、下地用パネル(10)の下縁を位置決めする下側位置決
材(9C)とを使用し、 建物を構築する前工程において、水平構造材(1)から屋
外側に突出して、アーム(9A)を介して水平構造材(1)と
平行に下地バー(9B)を固定し、 鉄骨を構築した後に、水平構造材(1)の定位置に固定し
ている下地バー(9B)に、上側位置決材(9C)と下側位置決
材(9C)からなる位置決材(9C)を施工現場で固定し、上側
位置決材(9C)と下側位置決材(9C)は、下地用パネル(10)
をフラットに固定できる位置に固定すると共に、下側位
置決材(9C)は下地バー(9B)の上面に固定して、上側位置
決材(9C)は下地バー(9B)の下面に固定し、 下地用パネル(10)の上縁を上側位置決材(9C)で位置決め
して、下地用パネル(10)の下縁を下地バー(9B)に載せ
て、下側位置決材(9C)に当接させて、下地バー(9B)の定
位置に配設し、この状態で、下地用パネル(10)の上側の
水平枠(10A)と下側の水平枠(10A)を下地バー(9C)に固定
することを特徴とする鉄骨造建物における下地用パネル
の建築方法。1. A building method for fixing a base panel (10) to a constructed steel frame via a connecting member (9), wherein the connecting member (9) includes a horizontal structural member (9) via an arm (9A). 1)
The base bar (9B) connected in parallel with the base bar (9B)
Positioning material for connecting the base panel (10) to the specified position
(9C) and, as the positioning material (9C), an upper positioning material (9C) for positioning the upper edge of the base panel (10).
And a lower positioning member (9C) for positioning the lower edge of the base panel (10), and protruding from the horizontal structural member (1) to the outdoor side in a pre-process of building a building, the arm ( After fixing the ground bar (9B) in parallel with the horizontal structural material (1) via 9A) and constructing the steel frame, the ground bar (9B) fixed in place on the horizontal structural material (1) The positioning material (9C) consisting of the upper positioning material (9C) and the lower positioning material (9C) is fixed at the construction site, and the upper positioning material (9C) and the lower positioning material (9C) are Panel (10)
The lower locating material (9C) is fixed to the upper surface of the base bar (9B), and the upper locating material (9C) is fixed to the lower surface of the base bar (9B). Position the upper edge of the base panel (10) with the upper positioning member (9C), place the lower edge of the base panel (10) on the base bar (9B), and place the lower positioning member (9C). To the base bar (9B), and in this state, the upper horizontal frame (10A) and the lower horizontal frame (10A) of the base panel (10) are connected to the base bar (9B). 9C) A method of constructing a base panel in a steel framed building, wherein the panel is fixed to 9C).
パネル(10)を嵌入できるコ字状の溝型鋼を使用し、下側
位置決材(9C)には幅の狭い溝型鋼を使用し、下地用パネ
ル(10)の上縁を上側位置決材(9C)の溝に入れるが、下地
用パネル(10)の下縁は下地バー(9B)に載せて、下側位置
決材(9C)に当接して、下地用パネル(10)を下地バー(9B)
の定位置に配設する請求項1の鉄骨造建物における下地
用パネルの建築方法。2. A U-shaped channel steel into which a base panel (10) can be fitted is used as the upper positioning member (9C), and a narrow channel steel is used as the lower positioning member (9C). Use the to place the upper edge of the base panel (10) in the groove of the upper positioning material (9C), but place the lower edge of the base panel (10) on the ground bar (9B) and Material (9C) and the base panel (10) into the base bar (9B)
2. The method of building a base panel in a steel frame building according to claim 1, wherein said panel is disposed at a predetermined position.
固定し、断熱材(5)の固定された下地用パネル(10)を、
施工現場で下地バー(9B)に固定する請求項1の鉄骨造建
物における下地用パネルの建築方法。3. A heat insulating material (5) is fixed to a base panel (10) at a factory, and the base panel (10) to which the heat insulating material (5) is fixed is provided.
The method of building a base panel in a steel frame building according to claim 1, wherein the base panel is fixed to a base bar (9B) at a construction site.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP09120331A JP3084253B2 (en) | 1997-04-22 | 1997-04-22 | Construction method of base panel for steel frame building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP09120331A JP3084253B2 (en) | 1997-04-22 | 1997-04-22 | Construction method of base panel for steel frame building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH10299136A JPH10299136A (en) | 1998-11-10 |
| JP3084253B2 true JP3084253B2 (en) | 2000-09-04 |
Family
ID=14783623
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP09120331A Expired - Fee Related JP3084253B2 (en) | 1997-04-22 | 1997-04-22 | Construction method of base panel for steel frame building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3084253B2 (en) |
-
1997
- 1997-04-22 JP JP09120331A patent/JP3084253B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH10299136A (en) | 1998-11-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH11241448A (en) | Fitting method and structure of eave soffit | |
| JP3084253B2 (en) | Construction method of base panel for steel frame building | |
| JP3029789B2 (en) | Wall panels | |
| JP2649323B2 (en) | External wall surface by rationalized wooden thermal insulation system combining two types of panels and glued timber frames | |
| JP3314282B2 (en) | Method of Window Frame Construction and Opening Wall Panel in Wooden House Using Panel | |
| CN219910465U (en) | Prefabricated window frame of steel construction building | |
| JPS5851292Y2 (en) | architectural reinforcement boards | |
| JP7398757B2 (en) | building construction methods | |
| JPH0681410A (en) | Through panel of framework in wooden building | |
| JP2829824B2 (en) | Makabe-like architectural structure frame and its construction method | |
| JP2000356024A (en) | Mounting bracket for exterior trim material, furring strips for vertical sticking, and mounting construction method | |
| JP3018685U (en) | Load bearing wall panel | |
| JP3930356B2 (en) | Outer corner panel | |
| JPH1077706A (en) | Bearing wall construction method for house using heat insulating board and heat insulating board structure | |
| JPS6123123Y2 (en) | ||
| JP3030004U (en) | Connection and reinforcement hardware | |
| JP3030500U (en) | Wall panel with ventilation layer | |
| JP2026014033A (en) | Buildings constructed using the frame wall construction method, and the construction method of such buildings | |
| JP2000336818A (en) | Fixing structure of floor base material | |
| JP2507196Y2 (en) | Wall panels for windows | |
| JPH10311159A (en) | Panel having earthquake resistant construction for building structure | |
| JP2002322786A (en) | Vertical paneling fixing structure of wall plate | |
| JP2003247275A (en) | Framework structure for wooden building | |
| JP2000096709A (en) | Wooden building | |
| JPS6183733A (en) | Porch |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |