JP3090625B2 - Tunnel excavator and excavation method - Google Patents
Tunnel excavator and excavation methodInfo
- Publication number
- JP3090625B2 JP3090625B2 JP09035939A JP3593997A JP3090625B2 JP 3090625 B2 JP3090625 B2 JP 3090625B2 JP 09035939 A JP09035939 A JP 09035939A JP 3593997 A JP3593997 A JP 3593997A JP 3090625 B2 JP3090625 B2 JP 3090625B2
- Authority
- JP
- Japan
- Prior art keywords
- liner
- gripper
- ground
- excavator
- ring shape
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、地盤を掘削してト
ンネルを構築するトンネル掘削機及びトンネル掘削方法
に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel excavator and a tunnel excavation method for constructing a tunnel by excavating the ground.
【0002】[0002]
【従来の技術】トンネル掘削機により地盤を掘削してト
ンネルを構築するには、掘削機で地盤を掘削し、掘削し
た地山を鋼製支保工、吹付ライナ等で被覆して地山の崩
壊防止等を図るようにしている。2. Description of the Related Art To construct a tunnel by excavating the ground with a tunnel excavator, excavating the ground with an excavator and covering the excavated ground with a steel support, a spray liner, etc. Prevention and other measures are taken.
【0003】軟弱地盤で鋼製支保工及びライナを使用す
る場合(以下ライナ等)、従来の装置及び方法によると
きは、通常、ライナ等の建込みを掘進と併行して行うこ
とができなかつた。また、グリッパ反力が不足し、ライ
ナから推進反力を得ようとする場合、事前に数基のライ
ナを建込み、ライナと地山間にモルタル等を注入し、地
山との摩擦力を得た後、始めて充分な推進反力が得られ
た。なお、この場合、推進装置として、別の推進装置が
必要になる。In the case of using a steel support and a liner on soft ground (hereinafter referred to as a liner), it is usually impossible to build the liner or the like in parallel with the excavation when using the conventional apparatus and method. . Also, if the gripper reaction force is insufficient and you want to obtain propulsion reaction force from the liner, build several liners in advance and inject mortar etc. between the liner and the ground to obtain frictional force with the ground. After that, sufficient propulsion reaction was obtained for the first time. In this case, another propulsion device is required as the propulsion device.
【0004】[0004]
【発明が解決しようとする課題】本発明は、従来技術の
前記の問題点を解決すべきなされたもので、掘進と併行
してライナ等の仮組みを行うことができ、何時でもライ
ナに切換えることができ、別の推進装置が不要なトンネ
ル掘削機及びトンネル掘削方法を提供することを目的と
するものである。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems of the prior art, and a temporary assembling of a liner or the like can be performed in parallel with excavation, and the liner can be switched to the liner at any time. It is an object of the present invention to provide a tunnel excavator and a tunnel excavation method that do not require another propulsion device.
【0005】[0005]
【課題を解決するための手段】本発明によれば、掘削機
本体外の後方に複数のグリッパを設け、該グリッパは、
各々独立して油圧ジャッキにより作動してリング状に仮
組みされたライナを地山に押圧するものであり、前記グ
リッパの後方に、分割されて搬送されて來るライナをリ
ング状に仮組みするエレクタ装置を設け、該エレクタ装
置でリング状に仮組みされたライナを前記グリッパに搬
送する搬送手段を備え、更に前記エレクタ装置に、分割
されたライナを搬送する搬送手段を設けて成るものとす
る。According to the present invention, a plurality of grippers are provided outside a body of an excavator, and the grippers include:
Each of them is independently operated by a hydraulic jack to press the liner temporarily assembled in a ring shape against the ground, and the liner that is divided and conveyed is temporarily assembled in a ring shape behind the gripper. It is provided that an erector device is provided, and that the erector device is provided with transport means for transporting the liner temporarily assembled in a ring shape to the gripper, and that the erector device is further provided with transport means for transporting the divided liners. .
【0006】本発明によれば、 分割されたライナを搬
送手段により掘削機本体外の後方に設けたエレクタ装置
に搬送し、該ライナをエレクタ装置によりリング状に仮
組みし、リング状に仮組みされたライナを搬送手段によ
り掘削機本体外の後方に設けた複数のグリッパの内の何
れかのグリッパに搬送し、該グリッパの油圧ジャッキを
作動してリング状に仮組みされたライナを地山に押圧
し、掘削機の推進反力を、地山にグリッパにより押圧さ
れたライナを介して地山で受けるようにして成るものと
する。According to the present invention, the divided liner is conveyed by the conveying means to the erector device provided behind the excavator body, and the liner is temporarily assembled in a ring shape by the erector device, and is temporarily assembled in a ring shape. The liner is transported to any one of a plurality of grippers provided rearward outside the excavator body by a transporting means, and the hydraulic liner of the gripper is operated to remove the liner temporarily assembled in a ring shape from the ground. And the propulsion reaction force of the excavator is received at the ground through the liner pressed by the gripper against the ground.
【0007】掘削機本体外の後方に設けたエレクタ装置
により、掘進と併行して、分割されて搬送されて來るラ
イナ等の仮組みを行い、また掘削機本体外の後方に設け
たグリッパにより、掘進完了後、仮組したライナ等の拡
張・建込みを行うことができる。[0007] A temporary assembly of a liner or the like that is divided and conveyed is carried out in parallel with the excavation by an erector device provided outside the body of the excavator, and by a gripper provided rearward outside the body of the excavator. After the excavation is completed, the temporarily assembled liner and the like can be expanded and built.
【0008】また、複数のグリッパを作動し複数のライ
ナを同時に地山に押圧しライナを介して地山で受けるこ
とにより、低い接地面圧で大きな推進反力が得られる。
したがって、推進反力はライナ使用時もグリッパからと
るため、別の推進装置は必要がない。Further, by operating a plurality of grippers to simultaneously press a plurality of liners against the ground and receiving the ground through the liner, a large propulsion reaction force can be obtained with a low contact pressure.
Therefore, since the propulsion reaction force is obtained from the gripper even when the liner is used, another propulsion device is not required.
【0009】[0009]
【発明の実施の形態】図1に本発明の実施例に係るトン
ネル掘削機を、ライナで被覆したトンネルT内に設置し
た概要を示し、上流側(図において左側)より、図示さ
れていない掘削機本体外の後方に、同様に図示されてい
ないプレスリングを介して全体を1で示すグリッパが設
けらている。グリッパ1はメインビーム2で支持され、
図示の例では、グリッパは1a、1b、1c、1dの4
機が設けられていて、各々独立に作動する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows an outline of a tunnel excavator according to an embodiment of the present invention installed in a tunnel T covered with a liner. A gripper, generally designated by 1, is provided on the rear outside the machine body via a press ring (not shown). The gripper 1 is supported by the main beam 2,
In the illustrated example, the grippers are 1a, 1b, 1c, and 1d.
Machines are provided and operate independently of each other.
【0010】グリッパ1の後方には、分割されて搬送さ
れて來るライナをリング状に仮組みするエレクタ装置3
が設けられている。エレクタ装置3は、従来公知のエレ
クタ装置を使用することができ、エレクタ装置3により
リング状に仮組みされたライナ等を前記グリッパ1に搬
送する搬送手段、例えば、搬送台車4が設けられてい
る。[0010] Behind the gripper 1, an erector device 3 for temporarily assembling a liner divided and conveyed into a ring shape.
Is provided. As the erector device 3, a conventionally known erector device can be used, and a transport means for transporting a liner or the like temporarily assembled in a ring shape by the erector device 3 to the gripper 1, for example, a transport trolley 4 is provided. .
【0011】エレクタ装置3に、分割されたライナ等R
を搬送する搬送手段が設けられており、図示の例では、
搬送手段はレール5上を走行する台車6と分割されたラ
イナ等を吊下げて搬送する吊下コンベア7とから成って
いる。[0011] A split liner or the like R
Is provided, and in the illustrated example,
The conveying means includes a carriage 6 traveling on the rail 5 and a suspended conveyor 7 for suspending and conveying the divided liners and the like.
【0012】メインビーム2の後方端に、油圧ジャッキ
で作動するリセットシュー8が設けれており、グリッパ
1の盛替え時にメインビーム2を支持する。更に、掘削
ズリを搬出するベルトコンベア9が設けられている。し
たがって、メインビーム2はその前方が掘削機本体で支
持され、後方がリセットシュー8で支持されている。図
2及び図3に主として、エレクタ装置3を示し、エレク
タ装置3は、旋回リング10、肥持ジャッキ11、シュ
ージャッキ12等からなり、それ自体公知のものであっ
て、搬送手段6、7で搬送されて來る分割されたライナ
等(図示の例では5分割)をリング状に仮組みする。図
3において、13は仮止め材である。図4及び図5に主
として、グリッパ1を示し、グリッパは前記のように、
各々独立して作動する4機のグリッパ1a、1b、1
c、1dからなり、何れも同一構造のものであり、油圧
作動する押上げジャッキ14とグリッパジャッキ15と
を備えている。図4において、16はローラである。At the rear end of the main beam 2, a reset shoe 8 operated by a hydraulic jack is provided, and supports the main beam 2 when the gripper 1 is changed. Further, a belt conveyor 9 for carrying out the excavation waste is provided. Therefore, the front of the main beam 2 is supported by the excavator body, and the rear is supported by the reset shoe 8. 2 and 3 mainly show the erector device 3, which is composed of a swivel ring 10, a fertilizing jack 11, a shoe jack 12 and the like, and is a well-known device. The conveyed divided liners and the like (five divisions in the illustrated example) are temporarily assembled in a ring shape. In FIG. 3, reference numeral 13 denotes a temporary fixing member. FIGS. 4 and 5 mainly show the gripper 1, and the gripper is, as described above,
Four independently operated grippers 1a, 1b, 1
c and 1d, each having the same structure and having a hydraulically operated push-up jack 14 and a gripper jack 15. In FIG. 4, reference numeral 16 denotes a roller.
【0013】押上げジャッキ14を作動することによ
り、図5に示すように、仮組みされたライナ等Rは、略
円形に拡張される。更に、グリッパジャッキ15を作動
することにより、図8に示すように、グリッパシュー1
s,1sが外方に移動し、ライナRを地山に押圧する。By operating the push-up jack 14, the temporarily assembled liner or the like R is expanded into a substantially circular shape as shown in FIG. Further, by operating the gripper jack 15, as shown in FIG.
s, 1s move outward and press the liner R against the ground.
【0014】図6、図7及び図8に、グリッパの他の例
を示し、先の例のグリッパ1は、押上げジャッキ14は
1基であって、メンビーム2に反力を取っているが、こ
の例のグリッパ1Aは、押上げギャッキ14は2基であ
って、グリッパジャッキ15に反力を取っている。FIGS. 6, 7 and 8 show other examples of the gripper. The gripper 1 of the previous example has one push-up jack 14 and takes a reaction force on the member beam 2. The gripper 1A of this example has two push-up jacks 14, and takes a reaction force on the gripper jack 15.
【0015】図示していない掘削機により、地盤掘削を
行うが、その際、推進反力を、グリッパ1により地山に
押圧されたライナRを介して地山で受け、接地面圧を低
く抑えて必要とする推進反力を得る。また、複数のグリ
ッパを作動させることにより、低い接地面圧で大きな推
進反力が得られる。Ground excavation is performed by an excavator (not shown). At this time, a propulsion reaction force is received by the ground via the liner R pressed against the ground by the gripper 1, and the contact pressure on the ground is kept low. To obtain the required propulsion reaction force. By operating the plurality of grippers, a large propulsion reaction force can be obtained with a low contact pressure.
【0016】[0016]
【発明の効果】本発明によれば、掘削機本体外の後方に
エレクタ装置及びグリッパが設けられているので、エレ
クタ装置により、掘進と併行して、分割されて搬送され
て來るライナの仮組みを行うことができ、またグリッパ
により、掘進と併行して、ライナの建込みを行うことが
できる。According to the present invention, since the erector device and the gripper are provided at the rear outside the excavator main body, the erector device is used to temporarily move the liner divided and conveyed in parallel with the excavation. The assembling can be performed, and the gripper allows the liner to be built in parallel with the excavation.
【0017】また、掘削機の推進反力を、グリッパによ
り地山に押圧されたライナを介して地山で受けるように
しているので、接地面圧を低く抑えて必要とする推進反
力が得られ、また複数のグリッパを作動し複数のライナ
を同時に地山に押圧することにより、低い接地面圧で大
きな推進反力が得られる。Further, since the propulsion reaction force of the excavator is received at the ground through the liner pressed against the ground by the gripper, the required ground reaction pressure can be suppressed by keeping the contact pressure at a low level. By operating a plurality of grippers and simultaneously pressing a plurality of liners against the ground, a large propulsion reaction force can be obtained with a low contact pressure.
【図1】本発明の実施例に係るトンネル掘削機を、ライ
ナで被覆したトンネル内に設置した側面図。FIG. 1 is a side view in which a tunnel excavator according to an embodiment of the present invention is installed in a tunnel covered with a liner.
【図2】3つのライナ部品を仮組みしたエレクタ装置の
正面図。FIG. 2 is a front view of an erector device in which three liner components are temporarily assembled.
【図3】5つのライナ部品を仮組みしたエレクタ装置の
正面図。FIG. 3 is a front view of an erector device in which five liner components are temporarily assembled.
【図4】押上げジャッキでライナを押上げる前のグリッ
パの正面図。FIG. 4 is a front view of the gripper before the liner is pushed up by a push-up jack.
【図5】押上げジャッキでライナを押上げる後のグリッ
パの正面図。FIG. 5 is a front view of the gripper after the liner is pushed up by a push-up jack.
【図6】押上げジャッキでライナを押上げる前の他の例
のグリッパの正面図。FIG. 6 is a front view of another example of a gripper before a liner is pushed up by a push-up jack.
【図7】押上げジャッキでライナを押上げる後の同グリ
ッパの正面図。FIG. 7 is a front view of the gripper after the liner is pushed up by a push-up jack.
【図8】グリッパジャッキでライナを地山に押圧した同
グリッパの正面図。FIG. 8 is a front view of the gripper in which the liner is pressed against the ground with a gripper jack.
1・・・グリッパ 2・・・メインビーム 3・・・エレクタ装置 4・・・運搬台車 5・・・レール 6・・・運搬台車 7・・・吊下コンベア 8・・・リセットシュー 9・・・ベルトコンベア 10・・・旋回リング 11・・・肥持ジャッキ 12・・・シュージャッキ 13・・・仮止め材 14・・・押上げジャッキ 15・・・グリッパジャッキ 16・・・ローラ R・・・ライナ T・・・トンネル DESCRIPTION OF SYMBOLS 1 ... Gripper 2 ... Main beam 3 ... Electa apparatus 4 ... Carrier 5 ... Rail 6 ... Carrier 7 ... Suspension conveyor 8 ... Reset shoe 9 ...・ Belt conveyor 10 ・ ・ ・ Swirl ring 11 ・ ・ ・ Holding jack 12 ・ ・ ・ Shoe jack 13 ・ ・ ・ Temporary fixing material 14 ・ ・ ・ Push-up jack 15 ・ ・ ・ Gripper jack 16 ・ ・ ・ Roller R ・ ・・ Liner T ・ ・ ・ Tunnel
フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E21D 9/10 E21D 11/40 Continuation of the front page (58) Field surveyed (Int.Cl. 7 , DB name) E21D 9/10 E21D 11/40
Claims (2)
設け、該グリッパは、各々独立して油圧ジャッキにより
作動してリング状に仮組みされたライナを地山に押圧す
るものであり、前記グリッパの後方に、分割されて搬送
されて來るライナをリング状に仮組みするエレクタ装置
を設け、該エレクタ装置でリング状に仮組みされたライ
ナを前記グリッパに搬送する搬送手段を備え、更に前記
エレクタ装置に、分割されたライナを搬送する搬送手段
を設けて成ることを特徴とするトンネル掘削機。1. A plurality of grippers are provided at the rear outside the excavator main body, and the grippers are independently operated by hydraulic jacks to press a liner temporarily assembled in a ring shape against the ground. Behind the gripper, an erector device for temporarily assembling a liner that is divided and conveyed is provided in a ring shape, and a conveying unit for conveying the liner tentatively assembled in a ring shape by the erector device to the gripper, A tunnel excavator, further comprising a transporting means for transporting the divided liners in the erector device.
機本体外の後方に設けたエレクタ装置に搬送し、該ライ
ナをエレクタ装置によりリング状に仮組みし、リング状
に仮組みされたライナを搬送手段により掘削機本体外の
後方に設けた複数のグリッパの内の何れかのグリッパに
搬送し、該グリッパの油圧ジャッキを作動してリング状
に仮組みされたライナを地山に押圧し、掘削機の推進反
力を、地山にグリッパにより押圧されたライナを介して
地山で受けるようにして成ることを特徴とするトンネル
掘削方法。2. The divided liner is transported by a transporting means to an erector device provided rearward outside the body of the excavator, and the liner is temporarily assembled in a ring shape by the erector device. It is conveyed to any one of a plurality of grippers provided rearward outside the excavator main body by the conveyance means, and the hydraulic jack of the gripper is operated to press the liner temporarily assembled in a ring shape against the ground, A tunnel excavation method, wherein a propulsion reaction force of an excavator is received at a ground through a liner pressed by a gripper against the ground.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP09035939A JP3090625B2 (en) | 1997-02-20 | 1997-02-20 | Tunnel excavator and excavation method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP09035939A JP3090625B2 (en) | 1997-02-20 | 1997-02-20 | Tunnel excavator and excavation method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH10231690A JPH10231690A (en) | 1998-09-02 |
| JP3090625B2 true JP3090625B2 (en) | 2000-09-25 |
Family
ID=12455995
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP09035939A Expired - Fee Related JP3090625B2 (en) | 1997-02-20 | 1997-02-20 | Tunnel excavator and excavation method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3090625B2 (en) |
-
1997
- 1997-02-20 JP JP09035939A patent/JP3090625B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH10231690A (en) | 1998-09-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3090625B2 (en) | Tunnel excavator and excavation method | |
| JP3106004B2 (en) | Simultaneous simultaneous tunnel construction method and equipment | |
| JPH04333800A (en) | Lining material carrying device | |
| JP3611288B2 (en) | Electa device, support assembling method and tunnel excavator | |
| JP2003155889A (en) | Parent-child shield excavator and its excavation method | |
| JP2011080298A (en) | Tunnel excavating equipment | |
| JPH09184393A (en) | Construction method for underground structures with different cross-sectional areas | |
| JP4374535B2 (en) | Tunnel construction method | |
| JPH06108800A (en) | Segment feeder | |
| JP3838843B2 (en) | Conveying method by stretching belt conveyor and stretching belt conveyor equipment | |
| JP2002004796A (en) | Underground transport system and loading / unloading method | |
| JPH11173079A (en) | Gap removal system in tunnel excavation by mobile conveyor and blasting method | |
| JP2000265779A (en) | Shield excavation method and triple branch widening shield excavator | |
| JPH0266300A (en) | Segment supply equipment | |
| JP5279676B2 (en) | Box assembly equipment | |
| JP2002276298A (en) | Steel plate shell segment, shield excavation method | |
| JPH04179800A (en) | Self-traveling type segment carrying device | |
| JP2012241419A (en) | Disassembling method of shield machine | |
| JPS61207793A (en) | Contruction of tunnel by advance timbering | |
| JPH07139299A (en) | Mobile carrier for tunnel building materials | |
| JP2000008405A (en) | Ground excavating and back-filling device | |
| JP2004183419A (en) | Shield tunnel construction equipment | |
| JP2577633Y2 (en) | Excavation shear discharge device of widening tunnel excavator | |
| JP2943921B1 (en) | Tunnel excavation and tunnel construction method | |
| JPH04327699A (en) | Erector for shielding machine |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |