JP3232501B2 - Double pipe buried method - Google Patents
Double pipe buried methodInfo
- Publication number
- JP3232501B2 JP3232501B2 JP05867596A JP5867596A JP3232501B2 JP 3232501 B2 JP3232501 B2 JP 3232501B2 JP 05867596 A JP05867596 A JP 05867596A JP 5867596 A JP5867596 A JP 5867596A JP 3232501 B2 JP3232501 B2 JP 3232501B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- main pipe
- sheath
- main
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は例えば道路の地下に
ガス管の本管を埋設するための二重管先行埋設工法、特
に幹線道路において常設作業帯が確保できない区間に覆
工を必要とせず、管埋設の費用の低減化と工期の短縮化
を図るようにしたものに関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a double pipe precedent burial method for burying a main pipe of a gas pipe, for example, under a road, and in particular, does not require lining in a section where a permanent work zone cannot be secured on a main road. To reduce the cost of burying pipes and shorten the construction period.
【0002】[0002]
【従来の技術】従来の例えば幹線道路の地下にガス管の
本管を埋設する管埋設工法は、まず本管を埋設すべき地
域である道路に、予め本管の管径より大きい溝幅で、所
定深さで例えば170mの長さの本管投入溝を掘削し、
その本管投入溝の両側に鋼矢板を打ち込んで土留めを
し、さらに鋼矢板の間に所定間隔毎に支保工で山止めを
し、また本管投入溝の互いに隣接する本管の接続すべき
端部が位置する部分ではその溝幅を拡げて作業領域の会
所としておき、その会所にも鋼矢板を打ち込んで土留め
をし、支保工で山止めをする。しかる後に、例えば長さ
が12mの本管をクレーンにより本管投入溝の区間始点
部より区間終点部に向けて次々と吊り降ろし、区間始点
部より隣接する本管同士を芯出しした後に突き合せた端
部を会所で溶接により接合し、溶接後は溶接検査を受
け、区間終点部まで次々と溶接と検査を繰り返してい
く。このようにして本管投入溝に本管が溶接により一体
になるよう敷設したら、本管投入溝に土を埋め戻して本
管の埋設が完了するというものである。2. Description of the Related Art Conventionally, for example, a pipe burial method of burying a main pipe of a gas pipe underground of a main road, firstly, on a road in which a main pipe is to be buried, with a groove width larger than a pipe diameter of the main pipe in advance. Excavating a main injection groove having a predetermined depth, for example, a length of 170 m,
Steel sheet piles are driven into both sides of the main pipe insertion groove for earth retaining, and a steel sheet pile is secured between the steel sheet piles at predetermined intervals by shoring, and the main pipes adjacent to each other in the main pipe insertion groove are connected. At the part where the edge to be located is located, the width of the groove is widened and set as a meeting place in the working area, and steel sheet piles are also driven into the meeting place, and earth retaining is carried out, and a shoring is carried out. Thereafter, for example, the main pipe having a length of 12 m is suspended by a crane from the section start point of the main pipe introduction groove to the section end point one after another, and the main pipes adjacent from the section start point are centered and then joined. The welded ends are joined at the meeting place by welding, and after welding, they are subjected to welding inspection, and welding and inspection are repeated one after another until the section end point. When the main pipe is laid in the main pipe insertion groove in such a manner as to be integrated by welding, soil is buried back in the main pipe insertion groove, and the embedding of the main pipe is completed.
【0003】[0003]
【発明が解決しようとする課題】上記のような従来の管
埋設工法では、本管を埋設すべき地域である道路に、所
定長さの本管投入溝を掘削し、その本管投入溝に区間始
点部より区間終点部に向けて複数の本管を設置し、区間
始点部より区間終点部まで次々と隣接する本管同士を溶
接し、その溶接の検査をし、本管投入溝に本管を溶接に
より一体になるよう敷設したら、本管投入溝に土を埋め
戻して本管の埋設が完了するようにしているから、本管
を埋設すべき地域である道路に本管を埋設する工期とし
て例えば1週間かかるとすると、その道路の交差点、道
路にに面した工場並びに商店、駐車場の出入口等の常設
作業帯が確保できない場所の区間があるとすると、その
区間については人の出入りを確保したり、自動車が走行
できるようにするために、その区間における本管投入溝
をを鉄板で覆う覆工を行わなければならず、その覆工は
安全性の面からも本管投入溝に用いた鋼矢板に比べて強
度が充分なものが必要なため、覆工を行うと費用が嵩
み、また覆工作業の時間が余分にかかり、管埋設の工期
がより長期化するという問題点があった。In the conventional pipe burying method as described above, a main pipe charging groove of a predetermined length is excavated on a road which is an area where the main pipe is to be buried, and the main pipe charging groove is excavated. A plurality of main pipes are installed from the section start point to the section end point, adjacent main pipes are welded one after another from the section start point to the section end point, the welding inspection is performed, and the main pipe is inserted into the main pipe insertion groove. After the pipes are laid together by welding, the soil is buried back in the mains entrance groove to complete the embedding of the mains, so bury the mains on the road where the mains should be buried. For example, if it takes one week as a construction period, if there is a section of a place where a permanent work zone cannot be secured, such as an intersection of the road, a factory facing the road, a store, an entrance of a parking lot, and the like, a person enters and exits the section. Or allow the car to run Therefore, lining must be performed to cover the main slot in the section with a steel plate, and the lining has sufficient strength compared to the steel sheet pile used for the main slot in terms of safety. Since lining is required, lining is costly and requires extra time for lining, which leads to a longer construction period for burying pipes.
【0004】本発明は、このような問題点を解決するた
めになされたものであり、本管を埋設すべき地域が道路
であって、その道路に常設作業帯が確保できない場所の
区間があっても、覆工を必要とせず、管埋設の費用の低
減化と工期の短縮化が図れる二重管先行埋設工法を得る
ことを目的とする。The present invention has been made to solve such a problem, and the area where the main pipe is to be buried is a road, and there is a section where the permanent work zone cannot be secured on the road. However, it is an object of the present invention to obtain a double pipe advance burial method that does not require lining, reduces the cost of burying pipes, and shortens the construction period.
【0005】[0005]
【課題を解決するための手段】本発明に係る二重管先行
埋設工法は、本管を埋設すべき地域で、常設作業帯が確
保できない区間に、本管より管径の大きい鞘管を埋設す
るための所定長さの鞘管埋設溝を掘削し、その鞘管埋設
溝内に複数の鞘管を設置し、これら鞘管同士を鞘管継手
バンドで接続した後に該鞘管埋設溝に土砂を埋め戻して
鞘管を埋設する鞘管埋設工程と、前記鞘管の一端側に設
けられた本管投入溝に設置された複数のローラ上に先端
に係留具を有する第1番目の本管を投入し、その後前記
鞘管の一端側で本管投入溝に並設された会所に設置され
た管吊込み装置に第1番目の本管を懸架させ、懸架され
た本管の外周に、帯体とその外側面に設けられた多数の
突起とからなる硬質合成樹脂で形成されたパイピングス
ムーサを取り付ける本管投入・懸架工程と、前記管吊込
み装置に懸架され、パイピングスムーサが取り付けられ
た第1番目の本管の係留具に前記鞘管の他端側に設けら
れた配管引込み溝に設置された管引込み装置の引込みロ
ープを係留するロープ係留工程と、前記本管投入溝に第
2番目の本管を投入し、その第2番目の本管を前記管吊
込み装置に懸架されている第1番目の本管に溶接する本
管溶接工程と、前記管引込み装置を動作させて引込みロ
ープを牽引して前記第1番目の本管を第2番目の本管と
第1番目の本管との溶接部分を前記会所の端部に位置さ
せるよう前記鞘管内に引込む本管引込み工程と、そし
て、第3番目の本管からn番目の本管までは前記本管投
入・懸架工程と前記溶接工程と前記引込み込み工程とを
第1番目の本管が鞘管の配管引込み溝側端部に達し、n
番目の本管が鞘管の会所側端部に位置するまで順次繰り
返して行い、鞘管内に溶接接続された複数の本管を挿通
させるようにしたものである。According to the double pipe precedent burial method of the present invention, a sheath pipe having a larger diameter than the main pipe is buried in a section where a permanent work zone cannot be secured in an area where the main pipe is to be buried. A plurality of sheath pipes are installed in the sheath pipe embedding groove, and these sheath pipes are connected to each other by a sheath pipe joint band. And a first main pipe having a mooring tool at a tip thereof on a plurality of rollers installed in a main pipe insertion groove provided at one end of the sheath pipe. Then, the first main pipe is suspended on a pipe suspending device installed at a meeting place arranged in parallel with the main pipe introduction groove at one end side of the sheath pipe, and on the outer periphery of the suspended main pipe, Attach a piping smoother made of hard synthetic resin consisting of a band and a number of protrusions provided on its outer surface A main pipe charging / suspending step, and installing in a pipe drawing groove provided on the other end side of the sheath pipe in a mooring tool of a first main pipe suspended by the pipe hanging device and having a piping smoother attached thereto; A rope mooring step of mooring the drawn-in rope of the drawn pipe pulling-in device, charging a second main pipe into the main pipe charging groove, and suspending the second main pipe by the pipe hanging device. A main pipe welding step of welding to the first main pipe, and operating the pipe retraction device to pull a pull-in rope to connect the first main pipe to the second main pipe and the first main pipe. A main pipe drawing-in step of pulling the welded part of the main pipe into the sheath pipe so as to be located at an end of the meeting place; and a main pipe charging / suspending step from a third main pipe to an n-th main pipe. The first main pipe is formed in a pipe-ingoing groove of a sheath pipe by the welding step and the drawing-in step. It reaches the end portion, n
The procedure is repeated in order until the second main pipe is located at the end of the sheath pipe at the meeting place side, so that a plurality of main pipes connected by welding are inserted into the sheath pipe.
【0006】本発明においては、本管を埋設すべき地域
で、常設作業帯が確保できない区間に対しては、本管よ
り管径の大きい鞘管を埋設するための所定長さの鞘管埋
設溝を掘削し、その鞘管埋設溝内に複数の鞘管を設置
し、これら鞘管同士を鞘管継手バンドで接続した後に該
鞘管埋設溝に土砂を埋め戻して鞘管を埋設するようにし
ているから、鞘管同士の接続は極めて短時間で行うこと
ができ、その鞘管の埋設作業時間は従来の溝を掘削し、
その溝には複数の本管を設置し、これら本管同士を溶接
した後に検査し、塗覆装を行ってから土砂を埋め戻して
本管を埋設する方法の場合に比べて大幅に短縮されるた
め、覆工すべき場合が少なくなり、また常設作業帯が確
保できない区間が短い場合には即日復旧化も可能となっ
て覆工を設ける必要はなくなり、それに伴う覆工作業と
時間が不要となる。In the present invention, in a region where the main pipe is to be buried, in a section where a permanent working zone cannot be secured, a sheath pipe having a predetermined length for burying a sheath pipe having a pipe diameter larger than the main pipe is buried. A trench is excavated, a plurality of sheath tubes are installed in the sheath tube embedding groove, and these sheath tubes are connected to each other by a sheath joint band, and then the sheath tube is buried by burying earth and sand in the sheath tube embedding groove. Therefore, the connection between the sheath pipes can be performed in a very short time, and the embedding work time of the sheath pipes is excavated in the conventional groove,
In this groove, multiple main pipes are installed.These main pipes are welded together, inspected, coated, covered with earth and sand, and the main pipe is buried. Therefore, the number of cases where lining is required is reduced, and when the section where the permanent work zone cannot be secured is short, it is possible to restore the same day, so there is no need to provide lining. Becomes
【0007】また、鞘管の埋設が終了した後に、本管投
入溝に第1番目の本管が投入され、その本管はその後に
本管投入溝に並設された会所に設置された管吊込み装置
に懸架させられ、会所内ではつぎに第2番目の本管が本
管投入溝に投入されて本管投入溝に大部分がある第2番
目の本管の端部と会所の管吊込み装置に懸架されている
第1番目の本管の端部との溶接が行われ、しかる後に溶
接された管吊込み装置に懸架されている第1番目の本管
はその溶接部分が会所の端部に位置させられるよう管引
込み装置によって鞘管内に引き込まれ、そして、第3番
目の本管からn番目の本管までは前記本管投入・懸架工
程と前記溶接工程と前記引込み込み工程とを第1番目の
本管が鞘管の配管引込み溝側端部に達し、n番目の本管
が鞘管の会所側端部に位置するまで順次繰り返して行
い、鞘管内に溶接接続された複数の本管を挿通させるよ
うにしているから、土木工事と分離して配管工事を集中
的に行うことができ、その配管工事においてそれまで本
管投入溝にあった本管が管吊込み装置に懸架され、その
本管と新たに本管投入溝に投入された本管との溶接を行
う場合にはそれと並行して会所の端部に位置させられて
いる溶接部分の溶接検査を行うことが可能となり、しか
も溶接と溶接検査を常に同じ場所で行うことができるた
め、溶接装置と検査装置を持ち運ぶ必要がなくなり、溶
接作業能率が著しく向上することとなった。[0007] After the embedding of the sheath tube is completed, the first main tube is charged into the main tube charging groove, and the main tube is then placed in a meeting place located next to the main line charging groove. In the hall, the second main pipe is then inserted into the main slot, and the end of the second main pipe having most of the main slot and the pipes of the hall are suspended in the hall. Welding is performed with the end of the first main pipe suspended on the suspension device, and then the first main pipe suspended on the welded pipe suspension device is welded at the joint. Is drawn into the sheath tube by the pipe drawing device so as to be positioned at the end of the main pipe, and the main pipe charging / suspending step, the welding step, and the drawing step are performed from the third main pipe to the n-th main pipe. The first main pipe reaches the end of the sheath pipe on the side of the pipe drawing groove, and the n-th main pipe is the end of the sheath pipe on the meeting place side. It is repeated repeatedly until it is located at the position, and multiple main pipes connected by welding are inserted into the sheath pipe, so that pipe work can be intensively performed separately from civil engineering work. If the mains in the mains slot were suspended by the pipe lifting device and the mains were to be welded to the mains newly inserted in the mains slot, the main Welding inspection of the welded part located at the end can be performed, and welding and welding inspection can always be performed in the same place. Therefore, there is no need to carry the welding equipment and the inspection equipment, and the welding work efficiency is reduced. Significantly improved.
【0008】また、本管投入・懸架工程において、会所
に設置された管吊込み装置に懸架された本管の外周に、
帯体とその外側面に設けられた多数の突起とからなる硬
質合成樹脂で形成されたパイピングスムーサを取り付け
ることにより、管引込み装置によって本管を引っ張る場
合、鞘管に本管が直接接触している場合に比べて鞘管に
対する接触面積が減って摺動抵抗が少なくなり、管引込
み装置による本管の引き込み力は少なくて済むことにな
る。Further, in the main pipe charging / suspending step, the outer circumference of the main pipe suspended by the pipe suspension device installed at the meeting place is
By attaching a piping smoother made of a hard synthetic resin consisting of a band and a number of protrusions provided on its outer surface, when the main pipe is pulled by a pipe retraction device, the main pipe directly contacts the sheath pipe. The contact area with the sheath tube is reduced and the sliding resistance is reduced as compared with the case where the tube is retracted, and the pulling force of the main tube by the tube drawing device is reduced.
【0009】さらに、前記第1番目の本管の先端に設け
られた係留具に動滑車を取り付けるようにしてもよい。
動滑車を1基使用する構成とすることにより、管引込み
装置による本管の引き込み力は本管を直接引っ張る場合
に比べて二分の一で済むことになり、特に接続された複
数の本管を引き込むときには有効である。Further, a moving pulley may be attached to a mooring tool provided at the tip of the first main pipe.
By using one moving pulley, the pulling force of the main pipe by the pipe retraction device can be reduced to one half of that in the case of directly pulling the main pipe. It is effective when pulling in.
【0010】また、前記鞘管内に複数の溶接接続された
本管を挿通させた後、鞘管と本管との間に充填材を充填
するようにしてもよい。かかる構成とすることにより、
本管が地中に埋設されているのと同じ状態になり、しか
もその周囲に鞘管があることにより、従来のような防護
鉄板を設ける必要がなくなる。又、ガス管の占用位置が
官民境界より3m未満の場所に於いては、防護側鉄板の
設置も必要となるが、鞘管を使用することにより、この
防護側鉄板の設置も必要なくなる。[0010] Further, after a plurality of main pipes connected by welding are inserted into the sheath pipe, a filler may be filled between the sheath pipe and the main pipe. With such a configuration,
Since the main pipe is buried under the ground, and the sheath pipe is provided around the main pipe, it is not necessary to provide a conventional protective iron plate. Further, when the occupation position of the gas pipe is less than 3 m from the public-private boundary, it is necessary to install a protection-side iron plate. However, by using the sheath tube, the protection-side iron plate is not required.
【0011】[0011]
【発明の実施の形態】図1は本発明の一実施形態に係る
二重管先行埋設工法の工程を示す工程図、図2は同二重
管先行埋設工法に用いられる鞘管が鞘管継手バンドによ
って接続された状態を示す正面図、図3は鞘管継手バン
ドの断面図、図4は本管投入溝の縦断面図、図5は会所
の縦断面図、図6は鞘管内にパイピングスムーサを取り
付けた本管が挿入された状態を示す断面図である。次
に、本発明の一実施形態に係る二重管先行埋設工法につ
いて図面を参照して説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is a process diagram showing the steps of a double pipe preceding embedding method according to an embodiment of the present invention, and FIG. 2 is a sheath pipe joint used in the double pipe preceding embedding method. FIG. 3 is a sectional view of a sheath pipe joint band, FIG. 4 is a longitudinal sectional view of a main pipe insertion groove, FIG. 5 is a longitudinal sectional view of a meeting place, and FIG. 6 is piping in a sheath pipe. It is sectional drawing which shows the state in which the main pipe | tube which attached the smoother was inserted. Next, a double pipe preceding burying method according to an embodiment of the present invention will be described with reference to the drawings.
【0012】まず、鞘管の埋設工程について説明する。
ガス管である本管を埋設すべき地域で常設作業帯が確保
できない区間2に対し、予め本管より管径の大きい鋼管
である鞘管1を埋設するために、例えば長さが83m
で、幅が1400mm、深さが2600mmの鞘管埋設
溝を掘削する。次に、例えば径が800mmで、長さが
6mの鞘管1を14本、クレーン付トラックで鞘管埋設
溝内に始点側より終点側に向けて投入し、その後に管台
を使用して鞘管1の高さの設定を行ってから図3に示す
判割り状の鞘管継手バンド3を一対使用してその連結部
3aをボルト4にて隣接する鞘管1同士をそれぞれ連結
し、図2に示すように一体となった鞘管1が鞘管埋設溝
2内に設置される。こうして、鞘管埋設溝2内に鞘管1
が設置されたら、一体となった鞘管1の両端側を残して
鞘管1の上部に土砂を埋め戻し、図1の(イ)に示すよ
うに鞘管1が常設作業帯が確保できない区間2に埋設さ
れる。First, the step of embedding the sheath tube will be described.
In order to bury the sheath pipe 1 which is a steel pipe having a diameter larger than the main pipe in advance in the section 2 where the permanent work zone cannot be secured in the area where the main pipe as the gas pipe is to be buried, for example, the length is 83 m.
Then, a sheath pipe embedding groove having a width of 1400 mm and a depth of 2600 mm is excavated. Next, for example, 14 sheath pipes 1 each having a diameter of 800 mm and a length of 6 m are inserted into the sheath pipe embedding groove from the starting point side to the end point side by a truck equipped with a crane. After setting the height of the sheath tube 1, the connecting portions 3a are connected to each other with the bolts 4 to connect the adjacent sheath tubes 1 to each other using a pair of split sheath joint bands 3 shown in FIG. As shown in FIG. 2, an integrated sheath tube 1 is installed in a sheath tube embedding groove 2. Thus, the sheath tube 1 is inserted into the sheath tube burying groove 2.
Is installed, earth and sand are buried in the upper portion of the sheath tube 1 except for both ends of the integrated sheath tube 1, and as shown in FIG. 1A, a section where the sheath tube 1 cannot secure a permanent working zone. 2 buried.
【0013】このように常設作業帯が確保できない区間
2は、鞘管1同士を鞘管継手バンド3で接続した後に鞘
管埋設溝に土砂を埋め戻して鞘管1を埋設するようにし
ているから、鞘管1同士の接続は極めて短時間で行うこ
とができ、その鞘管1の埋設作業時間は従来の溝を掘削
し、その溝には複数の本管を設置し、これら本管同士を
溶接した後に検査し、塗覆装を行ってから土砂を埋め戻
して本管を埋設する方法の場合に比べて大幅に短縮され
る。そのため、覆工すべき場合が少なくなり、また常設
作業帯が確保できない区間2が短い場合には即日復旧化
も可能となって覆工を設ける必要はなくなり、それに伴
う覆工作業と時間が不要となる。In the section 2 where the permanent work zone cannot be secured, the sheath pipes 1 are buried by connecting the sheath pipes 1 to each other with the sheath pipe joint band 3 and then backfilling the soil into the sheath pipe embedding groove. Therefore, the connection between the sheath pipes 1 can be performed in a very short time, and the embedding work of the sheath pipes 1 requires excavating a conventional groove, installing a plurality of main pipes in the groove, and connecting these main pipes. Inspection after welding, coating and coating, and then backfilling the earth and sand, greatly shortening the method compared to the method of burying the main pipe. Therefore, the number of cases where lining should be performed is reduced, and when the section 2 in which the permanent work zone cannot be secured is short, it is possible to recover the same day, and it is not necessary to provide lining. Becomes
【0014】次に、鞘管に本管を挿通させる工程につい
て説明する。まず、一体となった鞘管1の両側に作業溝
を設ける。即ち、一体となった鞘管1の図1において左
側に本管5の1本分の長さより少し長い会所6とその会
所6に隣りあって本管5の1本分の長さより少し長い本
管投入溝7を設ける。そして、その会所6には管吊込み
装置8を設ける。その管吊込み装置8は図5に示すよう
に会所6の両側に設けられた軽量鋼矢板9に沿って設け
られた支柱10に支持されたH型鋼の複数の支保工11
に固定されたI型鋼のレール12と、レール12を走行
する複数のプレントローリ13と、各プレントローリ1
3に取り付けられチェーンブロ14と、チェーンブロ1
4から吊下げられた管支持バンド15とから構成されて
いる。また、本管投入溝7の両側にも軽量鋼矢板9が設
けられ、図4に示すように軽量鋼矢板9、9の間に上下
配置に二本の複数の伸縮及び旋回可能な支保工16が設
けられ、本管投入溝7の底部には配管受台ローラ17が
設けられている。Next, the step of inserting the main tube through the sheath tube will be described. First, working grooves are provided on both sides of the integrated sheath tube 1. That is, a meeting place 6 slightly longer than the length of one main pipe 5 and a book adjacent to the meeting place 6 and slightly longer than the length of one main pipe 5 are shown on the left side in FIG. A pipe introduction groove 7 is provided. The meeting place 6 is provided with a pipe hanging device 8. As shown in FIG. 5, the pipe suspension device 8 includes a plurality of H-shaped steel supports 11 supported on columns 10 provided along lightweight steel sheet piles 9 provided on both sides of the meeting place 6.
I-shaped steel rails 12 fixed to the rails, a plurality of Plenty trucks 13 running on the rails 12, and each Plenty truck 1
3 and a chain blow 14 and a chain blow 1
4 and a tube support band 15 suspended from the tube support band 4. In addition, light steel sheet piles 9 are provided on both sides of the main pipe introduction groove 7, and as shown in FIG. And a pipe receiving roller 17 is provided at the bottom of the main pipe introduction groove 7.
【0015】また、一体となった鞘管1の図1に示すよ
うに右側に配管引込み溝20を設ける。その配管引込み
溝20の両側にも軽量鋼矢板が設けられ、軽量鋼矢板の
間に支保工が設けられ、配管引込み溝20の底部に管引
込み装置21が設けられている。その管引込み装置21
は引込みロープ22と、引込みロープ22の一端を係留
する係留具23と、引込みロープ22の他端を引き寄せ
る機構、例えばチルホールとロープ巻取装置24とで構
成されている。Further, as shown in FIG. 1, a pipe lead-in groove 20 is provided on the right side of the integrated sheath tube 1. Light steel sheet piles are also provided on both sides of the pipe drawing groove 20, supports are provided between the light steel sheet piles, and a pipe drawing device 21 is provided at the bottom of the pipe drawing groove 20. The pipe retraction device 21
The pull-in rope 22 includes a pull-in rope 22, a mooring device 23 for mooring one end of the pull-in rope 22, and a mechanism for pulling the other end of the pull-in rope 22, for example, a chill hole and a rope winding device 24.
【0016】次に、本管を本管投入溝に投入してから、
鞘管に本管を挿通させるまでの工程について説明する。
まず、図1の(イ)に示すように第1番目の本管5を芯
出し一体型吊り降ろし装置(図示省略)を使用して本管
投入溝7の配管受台ローラ17上に仮置きする。この第
1番目の本管5の先端には吊り金具26を有するキャッ
プ25が取り付けられており、その吊り金具26にはシ
ャックル27を介して引き込み用の動滑車28が接続さ
れている。次に、図1の(イ)に示すように配管受台ロ
ーラ17上に仮置きされた第1番目の本管5を会所6に
向けて転がし、会所6内に設置した管吊込み装置8の複
数の管支持バンド15に懸架させ、プレントロリー13
を走行させて溶接位置まで引き込む。しかる後に、配管
引込み溝20に設けられている管引込み装置21の引込
みロープ22を第1番目の本管5の動滑車28に掛け回
す。動滑車28を使用することにより、管引込み装置2
1の引込み力は引込みロープ22を本管5の吊り金具2
5に直接係留して引っ張る場合に比べて二分の一の力で
済む。なお、引込みロープ22を本管5の吊り金具26
に直接係留してもよい。Next, after inserting the main pipe into the main pipe insertion groove,
A process until the main tube is inserted through the sheath tube will be described.
First, as shown in FIG. 1 (a), the first main pipe 5 is temporarily placed on a pipe receiving roller 17 in a main pipe insertion groove 7 by using an integrated hanging apparatus (not shown). I do. A cap 25 having a hanging metal fitting 26 is attached to the tip of the first main pipe 5, and a pulling movable pulley 28 is connected to the hanging metal fitting 26 via a shackle 27. Next, as shown in FIG. 1A, the first main pipe 5 temporarily placed on the pipe receiving roller 17 is rolled toward the meeting place 6, and the pipe hanging device 8 installed in the meeting place 6. Suspended on a plurality of tube support bands 15
And run to the welding position. Thereafter, the pull-in rope 22 of the pipe pull-in device 21 provided in the pipe pull-in groove 20 is wrapped around the moving pulley 28 of the first main pipe 5. By using the moving pulley 28, the pipe retraction device 2
The pull-in force 1 is used to connect the pull-in rope 22 to the hanging fitting 2 of the main pipe 5.
It takes only half the force of pulling by mooring directly to 5. In addition, the pull-in rope 22 is connected to the hanging bracket 26
May be moored directly.
【0017】しかる後に、本管投入溝7に第2番目の本
管5を設置し、その第2番目の本管5と管吊込み装置8
の管支持バンド15に懸架されている第1番目の本管5
とをインンターナルクランプ(図示省略)で芯出しを行
った後に、図1の(ロ)に示すように溶接機(図示省
略)で外面溶接する。なお、n+(n+1)本目の溶接
と同時に(n−1)+n本目の継手の検査と塗覆装を行
い、また図6に示す本管5の外周に、帯体31とその外
側面に設けられた多数の突起32とからなる硬質合成樹
脂で形成されたパイピングスムーサ30を規定の間隔、
例えば2mピッチで取り付ける。このように本管5の外
周にパイピングスムーサ30を取り付けるのは、管引込
み装置21によって本管5を引っ張る場合、本管5の塗
覆装の防護になると共に鞘管1に本管5が直接接触して
いる場合に比べて鞘管1に対する接触面積が減って摺動
抵抗が少なくなり、又パイピングスムーサ30の摩擦係
数が低いため、管引込み装置21による本管5の引き込
み力は少なくて済むからである。そして、溶接が終了し
たら、図1の(ハ)に示すように管引込み装置21のロ
ープ巻取装置24を動作させて第2番目の本管5と第1
番目の本管5との溶接部分を会所6に位置させるよう第
1番目の本管5を鞘管1内に引込む。Thereafter, the second main pipe 5 is set in the main pipe introduction groove 7, and the second main pipe 5 and the pipe suspending device 8 are installed.
First main pipe 5 suspended on the pipe support band 15
Are centered by an internal clamp (not shown), and then externally welded by a welding machine (not shown) as shown in FIG. The (n-1) + n-th joint is inspected and coated simultaneously with the (n +) (n + 1) -th welding, and is provided on the outer periphery of the main body 5 shown in FIG. A piping smoother 30 formed of a hard synthetic resin having a large number of projections 32 formed at specified intervals,
For example, they are mounted at a pitch of 2 m. Attaching the piping smoother 30 to the outer periphery of the main pipe 5 in this way protects the coating of the main pipe 5 when the main pipe 5 is pulled by the pipe retraction device 21 and at the same time, the main pipe 5 is attached to the sheath pipe 1. As compared with the case of direct contact, the contact area with the sheath tube 1 is reduced and the sliding resistance is reduced, and the friction coefficient of the piping smoother 30 is low. Because it's easy. When the welding is completed, the rope winding device 24 of the pipe drawing-in device 21 is operated as shown in FIG.
The first main pipe 5 is drawn into the sheath pipe 1 so that the welded portion with the second main pipe 5 is located at the meeting place 6.
【0018】そして、第3番目の本管5から14番目の
本管5までは、前述した本管5の本管投入溝7への投
入、管吊下装置8による懸架、本管5同士の溶接、本管
5の鞘管1への引き込みを、図1の(ニ)に示すように
第1番目の本管5が鞘管1の装置収容溝20側端部に達
し、14番目の本管5が鞘管1の会所側端部に位置する
まで順次繰り返し行い、鞘管1内に14本の溶接接続さ
れた本管5を挿通させるようにしている。なお、第3番
目の本管5から14番目の本管5がそれぞれ次の本管5
と会所6の左側端部で溶接される時には、その前に行わ
れた溶接部分は会所6の右側端部で溶接検査が行われ、
また同時に会所6に位置する本管5に対して塗覆層とパ
イピングスムーサ30の取り付けが行われる。このよう
に会所6では一方の端部で本管5同士の溶接が行われ、
他方の端部では本管5の溶接部分の溶接検査が行われ、
溶接と検査を常に同じ場所で行うことができるため、溶
接装置と検査装置を持ち運ぶ必要がなくなり、これらの
作業能率が著しく向上した。From the third main pipe 5 to the fourteenth main pipe 5, the main pipe 5 is inserted into the main pipe insertion groove 7, suspended by the pipe suspension device 8, and the main pipes 5 are connected to each other. As shown in FIG. 1D, the first main pipe 5 reaches the end of the sheath pipe 1 on the device housing groove 20 side, and the fourteenth main pipe 5 is pulled into the sheath pipe 1 by welding. The procedure is sequentially repeated until the pipe 5 is located at the end of the sheath pipe 1 at the meeting place side, so that 14 welded main pipes 5 are inserted into the sheath pipe 1. The third main pipe 5 to the fourteenth main pipe 5 are respectively connected to the next main pipe 5.
When welding is performed at the left end of the meeting place 6, the welded part performed before that is subjected to welding inspection at the right end of the meeting place 6,
At the same time, the coating layer and the piping smoother 30 are attached to the main pipe 5 located at the meeting place 6. As described above, at the meeting place 6, the main pipes 5 are welded to each other at one end,
At the other end, a weld inspection of the welded portion of the main pipe 5 is performed,
Since welding and inspection can always be performed in the same place, there is no need to carry a welding device and an inspection device, and the work efficiency of these devices has been significantly improved.
【0019】かかる溶接作業について具体的に従来例と
比較すると、従来法では本管の配管、溶接、検査、塗覆
装の工程が終われば、その溶接された本管に対して次の
本管の配管、溶接、検査、塗覆装の工程が行われ、こう
して次々とかかる工程が繰り返されるため、例えば本管
一本当たり、本管の配管に0.5時間、溶接に1時間、
検査に1時間、塗覆装に0.5時間の計3時間がかかる
とすると、通常埋設での溶接作業は、1日の作業時間を
7時間とすると1日当たり1〜2回しか行えなかった
が、本発明の実施形態の二重管先行埋設工法では土木工
事と配管工事とが分離され、土木工事による埋設された
鞘管1に本管5の配管工事を行うもので、その配管工事
の作業時間はステーション溶接を行うことで、本管の配
管に0.5時間、溶接、検査及び塗覆装に1.0時間、
引き込みに0.5時間の計2時間程度で済み、溶接は1
日当たり3〜4回行えることとなり、高能率溶接が可能
となったものである。In comparison with the conventional example, such a welding operation will be described in detail. In the conventional method, when the steps of piping, welding, inspection and coating of the main pipe are completed, the next main pipe is connected to the welded main pipe. Since the steps of piping, welding, inspection, and coating are performed, and such steps are repeated one after another, for example, for one main pipe, 0.5 hour for main pipe, one hour for welding,
Assuming that it takes 1 hour for inspection and 0.5 hour for coating and covering, a total of 3 hours, welding work in normal burial can be performed only once or twice a day, if the working time per day is 7 hours. However, in the double pipe precedent burial method according to the embodiment of the present invention, the civil engineering work and the plumbing work are separated, and the piping work of the main pipe 5 is performed on the sheath pipe 1 buried by the civil engineering work. Work time is 0.5 hours for main pipes by performing station welding, 1.0 hours for welding, inspection and coating,
A total of about 2 hours, 0.5 hours for retraction, 1 weld
The welding can be performed three to four times a day, and high-efficiency welding can be performed.
【0020】このようにして鞘管1内に本管5が引込ま
れた後に、図6に示すように鞘管1と本管5との離隔部
分に充填材であるセメントベントナイト33による中詰
め工を行う。この中詰め工は、鞘管1及び本管5の管口
を型枠、例えばシュリンクチューブで閉塞し、鞘管1の
一端部の頂部に確認口を設け、鞘管1の他端に設けた充
填口からセメントベントナイト33を充填し、セメント
ベントナイト33が確認口に上がってきたら充填を終了
する。鞘管1内に本管5が引き込まれ、セメントベント
ナイト33の中詰め工が行える段階になったら、会所6
から管吊込み装置8を取り出し、配管引込み溝20から
管引込み装置21を取り出し、会所6と本管投入溝7と
配管引込み溝20とに土砂を埋め戻して二重管先行埋設
工法が終了する。このように、鞘管1内に複数の溶接接
続された本管5を挿通させた後、鞘管1と本管5との間
に充填材を充填するようにしたのは、鞘管1と本管5と
の間に充填材が存在することにより、本管5が地中に埋
設されているのと同じ状態とするためであり、しかも本
管5の周囲に鞘管1があることにより、従来のような防
護鉄板、場合によって防護側鉄板を設ける必要がなくな
った。また、充填材としてセメントベントナイト33を
用いたのは、充填性、例えば流動性に優れているからで
ある。After the main pipe 5 is drawn into the sheath pipe 1 in this way, as shown in FIG. 6, the space between the sheath pipe 1 and the main pipe 5 is filled with cement bentonite 33 as a filler. I do. In this filling, the mouths of the sheath tube 1 and the main tube 5 are closed with a mold, for example, a shrink tube, a confirmation port is provided at the top of one end of the sheath tube 1, and the other end of the sheath tube 1 is provided. The cement bentonite 33 is filled from the filling port, and the filling is completed when the cement bentonite 33 comes up to the confirmation port. When the main pipe 5 is drawn into the sheath pipe 1 and the cement can be filled with cement bentonite 33, the meeting place 6
The pipe pull-in device 8 is taken out from the pipe, the pipe pull-in device 21 is pulled out from the pipe pull-in groove 20, and the earth and sand are back-filled in the meeting place 6, the main pipe charging groove 7, and the pipe pull-in groove 20, and the double pipe leading embedding method is completed. . As described above, after the plurality of main pipes 5 connected by welding are inserted into the sheath pipe 1, the filler is filled between the sheath pipe 1 and the main pipe 5 because the sheath pipe 1 and the main pipe 5 are filled with the filler. This is because the presence of the filler between the main pipe 5 makes the same state as the main pipe 5 is buried in the ground, and the presence of the sheath pipe 1 around the main pipe 5 It is no longer necessary to provide a conventional protective iron plate, and in some cases, a protective iron plate. The reason why cement bentonite 33 was used as the filler is that it has excellent filling properties, for example, fluidity.
【0021】[0021]
【発明の効果】以上のように本発明によれば、本管を埋
設すべき地域で、常設作業帯が確保できない区間に対し
ては、本管より管径の大きい鞘管を埋設するための所定
長さの鞘埋設管溝を掘削し、その鞘埋設管溝内に複数の
鞘管を設置し、これら鞘管同士を鞘管継手バンドで接続
した後に該鞘埋設管溝に土砂を埋め戻して鞘管を埋設す
るようにしているから、鞘管同士の接続は極めて短時間
で行うことができ、その鞘管の埋設作業時間は従来の溝
を掘削し、その溝には複数の本管を設置し、これら本管
同士を溶接した後に検査し、塗覆装を行ってから土砂を
埋め戻して本管を埋設する方法の場合に比べて大幅に短
縮されるため、覆工すべき場合が少なくなり、また常設
作業帯が確保できない区間が短い場合には即日復旧化も
可能となって覆工を設ける必要はなくなり、それに伴う
覆工作業と時間が不要となるため、管埋設の費用の低減
化と工期の短縮化が図れるという効果を有する。As described above, according to the present invention, in a region where the main pipe is to be buried, in a section where a permanent working zone cannot be secured, a sheath pipe having a pipe diameter larger than the main pipe is buried. Excavating a sheath buried pipe groove of a predetermined length, installing a plurality of sheath pipes in the sheath buried pipe groove, connecting these sheath pipes with a sheath pipe joint band, and then backfilling the sheath buried pipe groove with earth and sand. Since the sheath pipes are buried, the connection between the sheath pipes can be performed in a very short time, and the embedding work of the sheath pipes requires excavating a conventional groove, and a plurality of main pipes are provided in the groove. Inspection after welding these main pipes to each other, applying coating and coating, and then backfilling the earth and sand to bury the main pipe. If the section where the permanent work zone cannot be secured is short, it can be restored on the same day. Provided need no longer, since the lining work and time associated therewith becomes unnecessary, an effect that can be reduced reduction and shortening of the construction period of the cost of pipe burying.
【0022】また、鞘管の埋設が終了した後に、本管投
入溝に第1番目の本管が投入され、その本管はその後に
本管投入溝に並設された会所に設置された管吊込み装置
に懸架させられ、会所内ではつぎに第2番目の本管が本
管投入溝に投入されて本管投入溝に大部分がある第2番
目の本管の端部と会所の管吊込み装置に懸架されている
第1番目の本管の端部との溶接が行われ、しかる後に溶
接された管吊込み装置に懸架されている第1番目の本管
はその溶接部分が会所の端部に位置させられるよう管引
込み装置によって鞘管内に引き込まれ、そして、第3番
目の本管からn番目の本管までは前記本管投入・懸架工
程と前記溶接工程と前記引込み込み工程とを第1番目の
本管が鞘管の配管引込み溝側端部に達し、n番目の本管
が鞘管の会所側端部に位置するまで順次繰り返して行
い、鞘管内に溶接接続された複数の本管を挿通させるよ
うにしているから、土木工事と分離して配管工事を集中
的に行うことができ、その配管工事においてそれまで本
管投入溝にあった本管が管吊込み装置に懸架され、その
本管と新たに本管投入溝に投入された本管との溶接を行
う場合にはそれと並行して会所の端部に位置させられて
いる溶接部分の溶接検査並びに塗覆装工を行うことが可
能となり、しかも溶接と溶接部の検査を常に同じ場所で
行うことができるため、溶接装置と検査装置を持ち運ぶ
必要がなくなり、溶接作業能率が著しく向上するという
効果を有する。Further, after the embedding of the sheath pipe is completed, the first main pipe is charged into the main pipe charging groove, and the main pipe is thereafter placed in a meeting place arranged in parallel with the main pipe charging groove. In the hall, the second main pipe is then inserted into the main slot, and the end of the second main pipe having most of the main slot and the pipes of the hall are suspended in the hall. Welding is performed with the end of the first main pipe suspended on the suspension device, and then the first main pipe suspended on the welded pipe suspension device is welded at the joint. Is drawn into the sheath tube by the pipe drawing device so as to be positioned at the end of the main pipe, and the main pipe charging / suspending step, the welding step, and the drawing step are performed from the third main pipe to the n-th main pipe. The first main pipe reaches the end of the sheath pipe on the side of the pipe drawing groove, and the n-th main pipe is the end of the sheath pipe on the meeting place side. It is repeated repeatedly until it is located at the position, and multiple main pipes connected by welding are inserted into the sheath pipe, so that pipe work can be intensively performed separately from civil engineering work. If the mains in the mains slot were suspended by the pipe lifting device and the mains were to be welded to the mains newly inserted in the mains slot, the main Welding and inspection equipment can be carried out because welding inspection and coating of the welded part located at the end can be performed, and welding and inspection of the welded part can always be performed in the same place. This eliminates the need and has the effect of significantly improving the welding work efficiency.
【0023】また、本管投入・懸架工程において、会所
に設置された管吊込み装置に懸架された本管の外周に、
帯体とその外側面に設けられた多数の突起とからなる硬
質合成樹脂で形成されたパイピングスムーサを取り付け
るようにしたので、管引込み装置によって本管を引っ張
る場合、鞘管に本管が直接接触している場合に比べて本
管の塗覆装の防護になると共に鞘管に対する接触面積が
減って摺動抵抗が少なくなり、又パイピングスムーサの
摩擦係数が低いため、管引込み装置による本管の引き込
み力は少なくて済むという効果を有する。Further, in the main pipe charging / suspending step, the outer circumference of the main pipe suspended by the pipe suspending device installed at the meeting place,
A piping smoother made of a hard synthetic resin consisting of a band and a number of protrusions provided on the outer surface is attached.When pulling the main pipe with a pipe retraction device, the main pipe is directly attached to the sheath pipe. Compared to the case of contact, it protects the coating and coating of the main pipe, reduces the contact area with the sheath pipe and reduces sliding resistance, and the pipe smoother has a low coefficient of friction. This has the effect of reducing the pulling force of the tube.
【0024】さらに、第1番目の本管の先端に設けられ
た係留具に動滑車を取り付けるようにしたので、管引込
み装置による本管の引き込み力は本管を直接引っ張る場
合に比べて二分の一で済むことになり、特に接続された
複数の本管を引き込むときには有効であり、管引込み装
置を小型化できるという効果も有する。Further, since the movable pulley is attached to the mooring tool provided at the tip of the first main pipe, the pulling force of the main pipe by the pipe retraction device is one-half that of the case where the main pipe is directly pulled. This is effective only when a plurality of connected main pipes are drawn in, and also has an effect that the pipe drawing-in device can be reduced in size.
【0025】さらにまた、前記鞘管内に複数の溶接接続
された本管を挿通させた後、鞘管と本管との間に充填材
を充填するようにしたので、本管が地中に埋設されてい
るのと同じ状態になり、しかもその周囲に鞘管があるこ
とにより、従来のような防護鉄板を設ける必要がなくな
るという効果を有する。Further, after a plurality of welded main pipes are inserted into the sheath pipe, a filler is filled between the sheath pipe and the main pipe, so that the main pipe is buried in the ground. By providing a sheath tube around the surroundings, it is possible to eliminate the need to provide a conventional protective iron plate.
【図1】本発明の一実施形態に係る二重管先行埋設工法
の工程を示す工程図である。FIG. 1 is a process diagram showing a process of a double-pipe pre-burial method according to an embodiment of the present invention.
【図2】同二重管先行埋設工法に用いられる鞘管が鞘管
継手バンドによって接続された状態を示す正面図であ
る。FIG. 2 is a front view showing a state in which a sheath pipe used in the double pipe preceding embedding method is connected by a sheath pipe joint band.
【図3】鞘管継手バンドの断面図である。FIG. 3 is a sectional view of a sheath pipe joint band.
【図4】本管投入溝の縦断面図である。FIG. 4 is a longitudinal sectional view of a main pipe charging groove.
【図5】会所の縦断面図である。FIG. 5 is a vertical sectional view of a meeting place.
【図6】鞘管内にパイピングスムーサを取り付けた本管
が挿入された状態を示す断面図である。FIG. 6 is a cross-sectional view showing a state where a main pipe with a piping smoother attached is inserted into a sheath pipe.
1 鞘管 2 鞘管埋設溝 3 鞘管継手バンド 5 本管 6 会所 7 本管投入溝 8 管吊込み装置 17 配管受台ローラ 20 配管引込み溝 21 管引込み装置 22 引込みロープ 26 吊り金具(係留具) DESCRIPTION OF SYMBOLS 1 Sheath pipe 2 Sheath pipe embedding groove 3 Sheath pipe joint band 5 Main pipe 6 Meeting place 7 Main pipe insertion groove 8 Pipe hanging device 17 Pipe cradle roller 20 Pipe drawing groove 21 Pipe drawing device 22 Pull rope 26 Hanging fitting )
フロントページの続き (72)発明者 石森 清隆 神奈川県横浜市港北区綱島東5−6−23 −403 (72)発明者 高田 直将 東京都大田区大森中1−14−8 ベアー ズサンケイ302 (72)発明者 太田 和之 神奈川県横須賀市三春町5−24 (72)発明者 相沢 好輝 神奈川県横浜市港北区日吉1−25−13 (72)発明者 篠崎 孝行 千葉県東金市求名2−29 (72)発明者 岸野 洋也 東京都荒川区南千住3−28−70−410 (72)発明者 高田 貴文 東京都三鷹市上連雀2−15−6 (72)発明者 鈴木 一生 東京都葛飾区高砂3−2−7−116 (56)参考文献 特開 昭63−189531(JP,A) 特開 平6−129187(JP,A) 特開 平7−268853(JP,A) 特開 平8−158426(JP,A) (58)調査した分野(Int.Cl.7,DB名) E02D 29/10 E02B 9/06 E02F 5/10 F16L 1/038 F16L 1/024 Continuation of the front page (72) Inventor Kiyotaka Ishimori 5-6-23-403, Tsunashimahigashi, Kohoku-ku, Yokohama-shi, Kanagawa Prefecture (72) Inventor Naomasa Takada 1-14-8 Omorinaka, Ota-ku, Tokyo Bears Sankei 302 (72) ) Inventor Kazuyuki Ota 5-24 Miharucho, Yokosuka City, Kanagawa Prefecture (72) Yoshiki Aizawa 1-25-13 Hiyoshi, Kohoku-ku, Yokohama, Kanagawa Prefecture (72) Inventor Takayuki Shinozaki 2- Togane, Togane-shi, Chiba Prefecture 29 (72) Inventor Hiroya Kishino 3-28-70-410, Minamisenju, Arakawa-ku, Tokyo (72) Inventor Takafumi Takada 2-15-6, Kamedarijaku, Mitaka-shi, Tokyo (72) Inventor Issey Suzuki, Katsushika-ku, Tokyo Takasago 3-2-7-116 (56) Reference JP-A-63-189531 (JP, A) JP-A-6-129187 (JP, A) JP-A-7-268853 (JP, A) JP-A-8 −158426 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E02D 29/10 E02B 9/06 E02F 5/10 F16L 1/038 F16L 1/024
Claims (3)
確保できない区間に、本管より管径の大きい鞘管を埋設
するための所定長さの鞘管埋設溝を掘削し、 その鞘管埋設溝内に複数の鞘管を設置し、これら鞘管同
士を鞘管継手バンドで接続した後に該鞘管埋設溝に土砂
を埋め戻して鞘管を埋設する鞘管埋設工程と、 前記鞘管の一端側に設けられた本管投入溝に設置された
複数のローラ上に先端に係留具を有する第1番目の本管
を投入し、その後前記鞘管の一端側で本管投入溝に並設
された会所に設置された管吊込み装置に第1番目の本管
を懸架させ、懸架された本管の外周に、帯体とその外側
面に設けられた多数の突起とからなる硬質合成樹脂で形
成されたパイピングスムーサを取り付ける本管投入・懸
架工程と、 前記管吊込み装置に懸架され、パイピングスムーサが取
り付けられた第1番目の本管の係留具に前記鞘管の他端
側に設けられた配管引込み溝に設置された管引込み装置
の引込みロープを係留するロープ係留工程と、 前記本管投入溝に第2番目の本管を投入し、その第2番
目の本管を前記管吊込み装置に懸架されている第1番目
の本管に溶接する本管溶接工程と、 前記管引込み装置を動作させて引込みロープを牽引して
前記第1番目の本管を第2番目の本管と第1番目の本管
との溶接部分を前記会所の端部に位置させるよう前記鞘
管内に引込む本管引込み工程と、 そして、第3番目の本管からn番目の本管までは前記本
管投入・懸架工程と前記溶接工程と前記引込み込み工程
とを第1番目の本管が鞘管の配管引込み溝側端部に達
し、n番目の本管が鞘管の会所側端部に位置するまで順
次繰り返して行い、鞘管内に溶接接続された複数の本管
を挿通させることを特徴とする二重管先行埋設工法。1. In a region where a main pipe is to be buried, in a section where a permanent working zone cannot be secured, a sheath pipe burying groove of a predetermined length for burying a sheath pipe having a pipe diameter larger than the main pipe is excavated. A plurality of sheath pipes are installed in the sheath pipe embedding groove, and after connecting these sheath pipes to each other with a sheath pipe joint band, the sheath pipe is embedded in the sheath pipe embedding groove to embed the sheath pipe, and the sheath pipe embedding step, A first main pipe having a mooring tool at its tip is loaded onto a plurality of rollers provided in a main pipe loading groove provided at one end of the sheath pipe, and then a main pipe feeding groove is placed at one end of the sheath pipe. The first main pipe is suspended on a pipe suspension device installed at a meeting place located side by side, and a belt and the outside thereof are provided around the suspended main pipe.
Formed with hard synthetic resin consisting of a number of protrusions provided on the surface
A main pipe loading / suspending step of attaching the formed piping smoother; and a first main pipe mooring tool suspended by the pipe hanging device and having the piping smoother attached thereto, at the other end side of the sheath pipe. A rope mooring step for mooring a pull-in rope of a pipe pull-in device installed in a provided pipe pull-in groove, and charging a second main pipe into the main pipe charging groove, and connecting the second main pipe to the pipe A main pipe welding step of welding to a first main pipe suspended on a suspension device; and operating the pipe retraction device to pull a drop rope and connect the first main pipe to a second main pipe. A main pipe drawing-in step of pulling the welded portion between the main pipe and the first main pipe into the sheath pipe so as to be located at an end of the meeting place; and the third main pipe to the n-th main pipe, Main pipe loading / suspending process, the welding process, and the retracting process Were repeated until the first main pipe reached the end of the sheath pipe on the side of the pipe drawing groove, and the n-th main pipe was located at the meeting place end of the sheath pipe, and was welded and connected to the inside of the sheath pipe. A double pipe pre-burial method characterized by inserting a plurality of main pipes.
係留具に動滑車を取り付けたことを特徴とする請求項1
記載の二重管先行埋設工法。2. A moving pulley is attached to a mooring tool provided at a tip of the first main pipe.
Double pipe prior burial method as described.
を挿通させた後、鞘管と本管との間に充填材を充填した
ことを特徴とする請求項1又は2のいずれか記載の二重
管先行埋設工法。3. After inserting the plurality of weld connected mains to the sheath tube, claim 1 or 2, characterized in that the filler is filled between the sleeve pipe and the main pipe Double pipe prior burial method as described.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP05867596A JP3232501B2 (en) | 1996-03-15 | 1996-03-15 | Double pipe buried method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP05867596A JP3232501B2 (en) | 1996-03-15 | 1996-03-15 | Double pipe buried method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH09250125A JPH09250125A (en) | 1997-09-22 |
| JP3232501B2 true JP3232501B2 (en) | 2001-11-26 |
Family
ID=13091163
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP05867596A Expired - Lifetime JP3232501B2 (en) | 1996-03-15 | 1996-03-15 | Double pipe buried method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3232501B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6145197B1 (en) * | 2016-06-06 | 2017-06-07 | 新菱冷熱工業株式会社 | Piping method |
| CN106015733B (en) * | 2016-08-03 | 2018-05-04 | 北京政平建设投资集团有限公司 | A kind of straight top steel pipeline jacking construction method |
-
1996
- 1996-03-15 JP JP05867596A patent/JP3232501B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH09250125A (en) | 1997-09-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108843857B (en) | A municipal pipeline construction device and construction method | |
| US5605419A (en) | Underground duct banks | |
| JP2879021B2 (en) | How to lay a sewer | |
| JP3232501B2 (en) | Double pipe buried method | |
| CN109441457B (en) | Construction method for synchronously transferring shield split starting pipeline | |
| US4594025A (en) | Tunnelling and tunnel relining equipment | |
| CN107542086A (en) | A kind of New Anchor Cable and its construction method for embankment side slope | |
| JP7357517B2 (en) | Pipe construction method using propulsion method | |
| KR101925828B1 (en) | Underground structure pressing system for reducing friction and construction method using the same | |
| EP0592567A1 (en) | A method of installing a soil anchor and a soil anchor. | |
| CN119196400A (en) | A pipeline down-pipeline assembly line and construction method for plain areas | |
| CN103382842B (en) | A kind of construction method preventing push-bench and tube coupling from rotating | |
| US3768267A (en) | Telescoping lining and support structure and method for lining tunnels and shafts | |
| CN107747494B (en) | Box culvert relay pushing system with moving mechanism | |
| JP3528889B2 (en) | Ground anchor, construction method, and ground excavation method using the anchor | |
| CN223257683U (en) | A pipeline unloading line in plain areas | |
| KR20180096239A (en) | The Construction Method of Non-excavation tunnel what used easy excavation method of Steel pipe and Deckplate | |
| US4148193A (en) | Method and apparatus for producing underground installations of concrete pipe | |
| JPH06129188A (en) | Buried pipe construction method | |
| JPH05280664A (en) | Piping method and piping materials used in this piping method | |
| JP2538314B2 (en) | Shield tunnel construction method without vertical shaft | |
| KR102781654B1 (en) | Construction method of steel pipe for laying non-re | |
| JPS621074B2 (en) | ||
| JPH08338567A (en) | Burying process for gas pipe line | |
| JP2765475B2 (en) | Pipeline laying method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20070921 Year of fee payment: 6 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20070921 Year of fee payment: 6 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080921 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090921 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
| R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100921 Year of fee payment: 9 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110921 Year of fee payment: 10 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120921 Year of fee payment: 11 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130921 Year of fee payment: 12 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| EXPY | Cancellation because of completion of term |