JP3286095B2 - How to create an underground structure - Google Patents
How to create an underground structureInfo
- Publication number
- JP3286095B2 JP3286095B2 JP30051594A JP30051594A JP3286095B2 JP 3286095 B2 JP3286095 B2 JP 3286095B2 JP 30051594 A JP30051594 A JP 30051594A JP 30051594 A JP30051594 A JP 30051594A JP 3286095 B2 JP3286095 B2 JP 3286095B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- frame
- floor frame
- excavation
- supported
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009412 basement excavation Methods 0.000 claims description 58
- 238000000034 method Methods 0.000 claims description 26
- 238000005520 cutting process Methods 0.000 description 16
- 238000010276 construction Methods 0.000 description 11
- 238000009415 formwork Methods 0.000 description 9
- 238000009432 framing Methods 0.000 description 6
- 239000011150 reinforced concrete Substances 0.000 description 6
- 230000015572 biosynthetic process Effects 0.000 description 4
- 238000002360 preparation method Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 238000010009 beating Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 239000004567 concrete Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 102200124760 rs587777729 Human genes 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、山留め壁と構真柱とを
作成したのち、掘削作業と床躯体を構真柱に支持させる
状態で作成する躯体作成作業とを繰り返すことにより、
各階の床躯体を上方のものから順に作成する、つまり、
逆打ち工法で地下構造体を作成する方法に関する。BACKGROUND OF THE INVENTION The present invention relates to a method of forming a retaining wall and a straight pillar, and then repeating an excavating operation and a frame forming operation of forming a floor frame supported by the straight pillar.
Create the floor frame of each floor in order from the top, that is,
The present invention relates to a method for creating an underground structure by a reverse strike method.
【0002】[0002]
【従来の技術】逆打ち工法では、地下躯体のうち作成し
た躯体部分を切梁として、その後の掘削において必要と
なる山留め壁の支保を行うのであるが、作成した地下躯
体部分のみで山留め壁を支保する場合には、地下の階高
により、各掘削のレベル(深さ)が決定されたり、或い
は、山留め壁の仕様が決定されたりする制約がある。そ
こで、前記の地下階高に起因した制約をなくして、山留
め壁の仕様の最適化を図るために、作成した地下躯体部
分のみで山留め壁を支保するのではなく、仮設の切梁を
も用いて山留め壁を支保する手段が提案されている。そ
の仮設切梁を用いて山留め壁を支保する手段としては、 (イ)各掘削毎に仮設切梁を構築する手段と (ロ)一つの切梁を作成し、その切梁を掘削に応じてス
ライドダウンさせて、一つの切梁を各掘削での支保に転
用する手段と が知られている。2. Description of the Related Art In a reverse striking method, a skeleton portion formed in an underground skeleton is used as a cutting beam to support a retaining wall required for subsequent excavation. In the case of supporting, there is a restriction that the level (depth) of each excavation is determined or the specification of the retaining wall is determined by the height of the basement. Therefore, in order to eliminate the constraint caused by the height of the basement floor and to optimize the specification of the retaining wall, instead of supporting the retaining wall only with the created underground frame portion, a temporary cutting beam is also used. Means for supporting the retaining wall have been proposed. Means for supporting the retaining wall using the temporary cutting beam include (a) means for constructing a temporary cutting beam for each excavation, and (b) one cutting beam, and the cutting beam is formed in accordance with the excavation. There is known a means for sliding down one diversion beam to be used as a support for each excavation.
【0003】[0003]
【発明が解決しようとする課題】しかし、上記従来の
(イ)及び(ロ)の技術のいずれによるときも、仮設切
梁を使用するから、地下構造体の作成に、資材及び手数
の掛かる切梁の仮設工事が必要であった。特に(イ)に
よるときは、掘削毎に仮設切梁を組み立てる必要がある
から、非常に作業性が悪いものであった。However, in both of the above-mentioned conventional techniques (a) and (b), temporary cutting beams are used, so that the production of underground structures requires time-consuming materials and cutting. Temporary construction of beams was required. In particular, in the case of (a), the workability was extremely poor because the temporary cutting beam had to be assembled for each excavation.
【0004】本発明の目的は、山留め壁の仕様の最適化
を図りながらも、そのための切梁の仮設工事を不要化、
簡略化して、工期の短縮化及びコストダウンを図る点に
ある。SUMMARY OF THE INVENTION It is an object of the present invention to optimize the specifications of a retaining wall while eliminating the necessity of temporary construction of a cutting beam for the purpose.
The simplification is to reduce the construction period and cost.
【0005】[0005]
【課題を解決するための手段】請求項1に記載した本発
明の第1発明による地下構造体の作成方法の特徴は、地
盤内に山留め壁及び構真柱を作成し、地盤上に基礎躯体
を山留め壁に対する切梁となる状態で作成し、次いで、
基礎躯体を構真柱に支持させた状態で基礎躯体の下側を
掘削する掘削作業と、基礎躯体を掘削跡に下降位置させ
る下降作業と、構真柱のうち基礎躯体よりも上方の部分
に支持させる状態で床躯体を作成する床躯体作成作業と
からなる逆打ち工程を所定回数繰り返し行って、各階の
床躯体を上方のものから順に作成するとともに、基礎躯
体を所定のレベルに設置する点にある。The feature of the method for preparing an underground structure according to the first invention of the present invention is that a retaining wall and a straight pillar are formed in the ground, and a foundation frame is formed on the ground. Is created as a beam to the retaining wall, and then
Excavation work to excavate the lower side of the foundation frame with the foundation frame supported by the straight pillars, lowering work to lower the foundation frame to the excavation mark, and the lower part of the straight pillars above the foundation frame Repeating the reverse striking process consisting of the floor skeleton creation work of creating the floor skeleton in a state where it is supported is repeated a predetermined number of times, creating the floor skeleton on each floor in order from the top, and installing the foundation skeleton at a predetermined level It is in.
【0006】請求項2に記載した本発明の第2発明によ
る地下構造体の作成方法の特徴は、地盤内に山留め壁及
び構真柱を作成し、地盤上に最下段床躯体を山留め壁に
対する切梁となる状態で作成し、次いで、最下段床躯体
を構真柱に支持させた状態で最下段床躯体の下側を掘削
する掘削作業と、最下段床躯体を掘削跡に下降位置させ
る下降作業と、構真柱のうち最下段床躯体よりも上方の
部分に支持させる状態で床躯体を作成する床躯体作成作
業とからなる逆打ち工程を所定回数繰り返し行って、各
階の床躯体を上方のものから順に作成するとともに、最
下段床躯体の下側を掘削して基礎躯体の作成と最下段床
躯体の所定のレベルへの設置とを行う点にある。According to a second aspect of the present invention, there is provided a method of manufacturing an underground structure according to the second aspect of the present invention, in which a retaining wall and a straight pillar are formed in the ground, and a lowermost floor frame is formed on the ground. Excavation work to excavate the lower side of the lowermost floor frame with the lowermost floor frame supported by a straight pillar, and then move the lowermost floor frame down to the excavation site A predetermined number of times of the reverse striking process consisting of the lowering work and the floor frame creation work of creating a floor frame in a state where the floor frame is supported by a portion above the lowermost floor frame of the straight pillars, is repeated for the floor frame of each floor. The point is that, in addition to the steps from the upper one, the lower side of the lowermost floor frame is excavated to create the foundation frame and to install the lowermost floor frame at a predetermined level.
【0007】請求項3に記載した本発明の第3発明によ
る地下構造体の作成方法の特徴は、地盤内に山留め壁及
び構真柱を作成し、地盤上に、基礎躯体と最下段床躯体
とを備えた構造体を山留め壁に対する切梁となる状態で
作成し、次いで、構造体を構真柱に支持させた状態で構
造体の下側を掘削する掘削作業と、構造体を掘削跡に下
降位置させる下降作業と、構真柱のうち構造体よりも上
方の部分に支持させる状態で床躯体を作成する床躯体作
成作業とからなる逆打ち工程を所定回数繰り返し行っ
て、各階の床躯体を上方のものから順に作成するととも
に、構造体を所定のレベルに設置する点にある。A feature of the method for preparing an underground structure according to the third aspect of the present invention is that a retaining wall and a straight pillar are formed in the ground, and a foundation frame and a lowermost floor frame are formed on the ground. Excavation work for excavating the lower side of the structure with the structure being supported by a straight pillar, and excavating the structure with excavation marks A predetermined number of times, a back-up process consisting of a lowering operation for lowering the floor and a floor frame forming operation for forming a floor frame in a state in which the floor frame is supported by a portion above the structure in the timber pillars, and The point is that the skeleton is created in order from the top and the structure is set at a predetermined level.
【0008】[0008]
【作用】第1発明によれば、地下構造体を構成するにあ
たっては基礎躯体が必要不可欠であることと、その必要
不可欠な基礎躯体が切梁としての強度・剛性を備えてい
ることとに着目して、基礎躯体を床躯体に先行して作成
し、その基礎躯体を構真柱に支持させ、各掘削毎に下降
させて、その基礎躯体を各掘削時に必要となる山留め壁
の支保に転用するようにしてあるから、基礎躯体作成作
業自体が切梁の作成作業となる。According to the first aspect of the present invention, attention is paid to the fact that a foundation frame is indispensable in constructing an underground structure, and that the essential foundation frame has the strength and rigidity as cut beams. Then, the foundation frame is created prior to the floor frame, and the foundation frame is supported by the timber pillars, lowered for each excavation, and the foundation frame is used as a support for the retaining wall required for each excavation Therefore, the work of creating the foundation frame itself is the work of creating the cutting beams.
【0009】しかも、基礎躯体を下降させることを利用
して基礎躯体を任意の高さ位置に位置させることができ
るから、山留め壁の仕様の最適化を図ることができる切
梁作用位置に基礎躯体を位置させることができる。Moreover, since the base frame can be positioned at an arbitrary height by utilizing the lowering of the base frame, the base frame can be positioned at the cutting beam working position where the specifications of the retaining wall can be optimized. Can be located.
【0010】第2発明によれば、地下構造体では最下段
床躯体が形成されることと、その最下段床躯体が切梁と
しての強度・剛性を備えていることとに着目して、最下
段床躯体を他の床躯体に先行して作成し、その最下段床
躯体を構真柱に支持させ、各掘削毎に下降させて、その
最下段床躯体を各掘削時に必要となる山留め壁の支保に
転用するようにしてあるから、最下段床躯体作成作業自
体が切梁の作成作業となる。[0010] According to the second aspect of the invention, focusing on the fact that the lowermost floor frame is formed in the underground structure and that the lowermost floor frame has the strength and rigidity as the cut beam, The lower floor frame is created prior to the other floor frames, the lowest floor frame is supported by a straight pillar, and lowered for each excavation, and the lower floor frame required for each excavation The work for creating the lowermost floor frame itself is the work for creating the cutting beams.
【0011】しかも、最下段床躯体を下降させることを
利用して最下段床躯体を任意の高さ位置に位置させるこ
とができるから、山留め壁の仕様の最適化を図ることが
できる切梁作用位置に最下段床躯体を位置させることが
できる。Moreover, since the lowermost floor frame can be positioned at an arbitrary height by utilizing the lowering of the lowermost floor frame, it is possible to optimize the specification of the retaining wall. The lowermost floor frame can be located at the position.
【0012】その上、各掘削時に切梁として作用する最
下段床躯体が他の各階の床躯体作成箇所の下方に位置す
るから、各階の床躯体を作成する際、その下に配置する
最下段床躯体を作業用及び床躯体作成型枠の支保用のス
テージに利用して、作業性良く、かつ、安全に各階の床
躯体作成を行うことができる。[0012] In addition, since the lowermost floor skeleton acting as a cutting beam at each excavation is located below the floor framing portion on each of the other floors, the lowermost tier disposed below the floor framing for each floor is formed. By using the floor frame as a work stage and a stage for supporting the floor frame forming formwork, the floor frame of each floor can be created with good workability and safely.
【0013】第3発明によれば、基礎躯体及び最下段床
躯体が切梁としての強度・剛性を備えていることとに着
目して、基礎躯体と最下段床躯体とを備えた構造体を他
の床躯体に先行して作成し、その構造体を構真柱に支持
させ、各掘削毎に下降させて、その構造体を各掘削時に
必要となる山留め壁の支保に転用するようにしてあるか
ら、構造体作成作業自体が切梁の作成作業となる。According to the third aspect of the present invention, focusing on the fact that the foundation frame and the lowermost floor frame have the strength and rigidity as cut beams, a structure provided with the foundation frame and the lowermost floor frame is provided. Created prior to the other floor structures, make the structure supported by straight pillars, lower each excavation, and divert the structure to support the retaining wall necessary for each excavation Because of this, the work of creating the structure itself is the work of creating the girder.
【0014】しかも、構造体を下降させることを利用し
て構造体を任意の高さ位置に位置させることができるか
ら、山留め壁の仕様の最適化を図ることができる切梁作
用位置に構造体を位置させることができる。In addition, since the structure can be positioned at an arbitrary height by utilizing the lowering of the structure, the structure can be located at the cutting beam action position where the specifications of the retaining wall can be optimized. Can be located.
【0015】その上、各掘削時に切梁として作用する構
造体が他の各階の床躯体作成箇所の下方に位置し、か
つ、構造体が最下段床躯体を備えたものであるから、各
階の床躯体を作成する際、その下に配置する構造体、詳
しくは、最下段床躯体を作業用及び床躯体作成型枠の支
保用のステージに利用して、作業性良く、かつ、安全に
各階の床躯体作成を行うことができる。[0015] In addition, since the structure acting as a girder at each excavation is located below the floor frame forming location on each of the other floors, and since the structure has the lowermost floor frame, the structure on each floor is provided. When creating a floor skeleton, the structure to be placed under it, specifically, the bottom floor skeleton is used as a work stage and a stage for supporting the floor frame creation formwork, and it is easy to work and safely on each floor. Floor skeleton can be created.
【0016】[0016]
【発明の効果】従って、本発明によれば、適切な高さ位
置で山留め壁を支保できて山留め壁の仕様の最適化を図
ることができながらも、切梁の仮設工事を不要化、簡略
化できて、その分、工期の短縮化及びコストダウンを図
ることができる。Thus, according to the present invention, the retaining wall can be supported at an appropriate height and the specifications of the retaining wall can be optimized, but temporary construction of the cutting beam is unnecessary and simplified. Therefore, the construction period can be shortened and the cost can be reduced accordingly.
【0017】特に請求項2や3に記載の本発明第2、第
3発明によれば、最下段床躯体を利用して、各階の床躯
体の作成を作業性良く安全に行えることにより、より一
層、工期の短縮化を図ることができる。In particular, according to the second and third aspects of the present invention, the floor frame of each floor can be created with good workability and safety by utilizing the lowermost floor frame. Further, the construction period can be shortened.
【0018】[0018]
〈実施例1〉図1に示すような地下2階の地下構造体1
への適用例を示す。地下構造体1の1階及び地下1階の
床躯体FS、最下段床躯体である地下2階床躯体FL、
基礎躯体Fは、鉄筋コンクリート(RC)造りや鉄骨鉄
筋コンクリート(SRC)造りのものである。なお、1
階及び地下1階の床躯体FSの区別を容易にするため、
1階の床躯体FSを1階床躯体F1とする一方、地下1
階の床躯体FSを地下1階床躯体B1とする。<Example 1> Underground structure 1 on the second floor underground as shown in FIG.
Here is an example of application to A floor structure FS on the first floor and the first basement floor of the underground structure 1, a second basement floor structure FL which is the lowest floor structure,
The base frame F is made of reinforced concrete (RC) or steel reinforced concrete (SRC). In addition, 1
In order to make it easy to distinguish the floor FS of the floor and the first basement floor,
While the floor structure FS on the first floor is referred to as a floor structure F1 on the first floor,
The floor frame FS of the floor is a basement floor floor frame B1.
【0019】作成方法を工程順に示せば次の通りであ
る。 〈1〉図2に示すように、地下構造体1の作成予定箇所
の地盤の周りに山留め壁2を作成するとともに、構真台
柱3及びそれに支持される構真柱4を作成する。構真台
柱3は、鉄筋コンクリート造りや無筋コンクリート造り
のものであり、構真柱4は、鉄筋コンクリート造りや鉄
骨(S)造り、鉄骨鉄筋コンクリート造りのものであ
る。なお、山留め壁2、構真台柱3、構真柱4は、周知
の方法により作成するのであって、作成方法の具体的な
実施例の説明は省略する。 〈2〉図3に示すように、山留め壁2で囲まれた地盤
を、地下構造体1のうち基礎躯体Fと地下2階床躯体F
Lとを備えた構造体Aの高さAhに相当する深さまで掘
削する予備掘削を行う。 〈3〉図4に示すように、山留め壁2で囲まれた地盤の
上に構造体Aを、山留め壁2に周囲で接してその山留め
壁2に対する切梁となる状態で作成する。なお、この構
造体Aの作成は、基礎躯体F及び地下2階床躯体FLと
を一体化する状態で行う。 〈4〉図5に示すように、構真柱4に構造体Aを吊り材
5を介して吊り支持させた状態でその構造体Aの下側を
掘削する一次掘削作業を行う。 〈5〉図6に示すように、構真柱4をガイドとして構造
体Aを掘削跡に下降位置させる下降作業を行う。 〈6〉図7に示すように、1階床躯体F1を構真柱4に
支持させる状態で作成する床躯体作成作業を行う一方、
構造体Aを構真柱4に吊り材5を介して吊り支持させた
状態でその構造体Aの下側を掘削する二次掘削作業を行
う。 〈7〉図8に示すように、構真柱4をガイドとして構造
体Aを掘削跡に下降位置させる下降作業を行う。 〈8〉図9に示すように、地下1階床躯体B1を構真柱
4に支持させる状態で作成する床躯体作成作業を行う一
方、構造体Aを構真柱4に吊り材5を介して吊り支持さ
せた状態でその構造体Aの下側を、構造体Aを所定のレ
ベルに位置させ得る深さまで掘削する三次掘削を行う。 〈9〉図10に示すように、構真柱4をガイドとして構
造体Aを掘削跡に下降位置させ、所定のレベルに設置す
る。 〈10〉各階の柱、壁を作成する。柱のうち構真柱4の
位置に作成するものはその構真柱4を利用して作成する
が、そうしなくても良い。The preparation method is as follows in the order of steps. <1> As shown in FIG. 2, a mountain retaining wall 2 is created around the ground at a location where the underground structure 1 is to be created, and a truss pillar 3 and a truss pillar 4 supported by it are created. The truss pillar 3 is made of reinforced concrete or unreinforced concrete, and the truss pillar 4 is made of reinforced concrete, steel frame (S), or steel reinforced concrete. In addition, the retaining wall 2, the trussed pillar 3, and the trussed pillar 4 are created by a known method, and a description of a specific example of the creating method is omitted. <2> As shown in FIG. 3, the ground surrounded by the retaining wall 2 is divided into the foundation frame F and the second floor basement frame F of the underground structure 1.
Preliminary excavation is performed to excavate to a depth corresponding to the height Ah of the structure A having L. <3> As shown in FIG. 4, a structure A is formed on the ground surrounded by the retaining wall 2 so as to be in contact with the retaining wall 2 around the periphery and to be a cut beam for the retaining wall 2. The formation of the structure A is performed in a state where the base frame F and the second floor basement frame FL are integrated. <4> As shown in FIG. 5, a primary excavation operation for excavating the lower side of the structure A is performed in a state where the structure A is suspended and supported on the straight pillar 4 via the suspending member 5. <5> As shown in FIG. 6, a lowering operation for lowering the structure A to the excavation mark is performed using the straight pillar 4 as a guide. <6> As shown in FIG. 7, while performing the floor frame creation work of creating the first-floor floor frame F1 in a state of being supported by the timber pillars 4,
A secondary excavation operation for excavating the lower side of the structure A is performed in a state where the structure A is suspended and supported on the straight pillar 4 via the hanging member 5. <7> As shown in FIG. 8, a lowering operation for lowering the structure A to the excavation mark is performed using the straight pillar 4 as a guide. <8> As shown in FIG. 9, while performing the floor frame creation work of creating a state in which the first basement floor frame B1 is supported by the timber columns 4, the structure A is attached to the timber columns 4 via the hanging members 5. In the state where the structure A is suspended and supported, tertiary excavation is performed to excavate the lower side of the structure A to a depth at which the structure A can be positioned at a predetermined level. <9> As shown in FIG. 10, the structure A is lowered to the excavation site using the straight pillar 4 as a guide, and installed at a predetermined level. <10> Create pillars and walls for each floor. Of the pillars, those created at the position of the timber pillar 4 are created using the timber pillar 4, but this need not be the case.
【0020】この作成方法では、逆打ち工程が二回繰り
返されている。つまり、一回目の逆打ち工程は、前記
〈4〉の工程の一次掘削作業と、〈5〉の工程の下降作
業と、〈6〉の工程の床躯体作成作業とからなり、二回
目の逆打ち工程は、〈6〉の工程の二次掘削作業と、
〈7〉の工程の下降作業と、〈8〉の工程の床躯体作成
作業とからなり、〈6〉の工程において、一回目の逆打
ち工程での床躯体作成作業と二回目の逆打ち工程での二
次掘削作業とが同時的に行われ、作業工期の短縮化が図
られている。In this manufacturing method, the reverse striking step is repeated twice. That is, the first reverse striking step includes the primary excavation operation of the step <4>, the lowering operation of the step <5>, and the floor frame forming operation of the step <6>. The beating process is the secondary excavation work of the process <6>,
It consists of the lowering work of the step <7> and the floor skeletal construction work of the step <8>. In the step <6>, the floor skeletal formation work in the first reverse smashing step and the second reverse smashing step The secondary excavation work is performed at the same time, and the work period is shortened.
【0021】前記〈6〉及び〈8〉の工程での床躯体作
成作業は、構造体A、詳しくは、地下2階床躯体FLを
作業用のステージとして行う。つまり、型枠工事などを
構造体Aを足場として行い、型枠を構造体Aに支保させ
る。この型枠支保は、地下2階床躯体FLの上面が平滑
であることにより、確実安全に行える。The floor framing work in the steps <6> and <8> is performed using the structure A, more specifically, the second floor underground floor framing FL as a work stage. That is, the formwork is performed using the structure A as a scaffold, and the formwork is supported by the structure A. The form support can be reliably and safely performed because the upper surface of the second basement floor frame FL is smooth.
【0022】〈実施例2〉上述した地下2階の地下構造
体1への適用例を示す。<Embodiment 2> An example of application to the above-described underground structure 1 on the second basement floor will be described.
【0023】作成方法を工程順に示せば次の通りであ
る。 〈1〉上記実施例1で示した〈1〉の作業を行う。 〈2〉図11に示すように、山留め壁2で囲まれた地盤
を、地下構造体1における地下2階床躯体FLの高さF
Lhに相当する深さまで掘削する予備掘削を行う。 〈3〉図12に示すように、山留め壁2で囲まれた地盤
の上に地下2階床躯体FLを、山留め壁2に周囲で接し
てその山留め壁2に対する切梁となる状態で作成する。 〈4〉図13に示すように、構真柱4に地下2階床躯体
FLを吊り材5を介して吊り支持させた状態でその地下
2階床躯体FLの下側を掘削する一次掘削作業を行う。 〈5〉図14に示すように、構真柱4をガイドとして地
下2階床躯体FLを掘削跡に下降位置させる下降作業を
行う。 〈6〉図15に示すように、1階床躯体F1を構真柱4
に支持させる状態で作成する床躯体作成作業を行う一
方、地下2階床躯体FLを構真柱4に吊り材5を介して
吊り支持させた状態でその地下2階床躯体FLの下側を
掘削する二次掘削作業を行う。 〈7〉図16に示すように、構真柱4をガイドとして地
下2階床躯体FLを掘削跡に下降位置させる下降作業を
行う。 〈8〉図17に示すように、地下1階床躯体B1を構真
柱4に支持させる状態で作成する床躯体作成作業を行う
一方、地下2階床躯体FLを構真柱4に吊り材5を介し
て吊り支持させた状態でその地下2階床躯体FLの下側
を、基礎躯体Fの設置を可能とさせる深さまで掘削する
三次掘削を行う。 〈9〉図18に示すように、構真柱4をガイドとして地
下2階床躯体FLを掘削跡の所定のレベルにまで下降さ
せる。 〈10〉図19に示すように、地下2階床躯体FLを支
持する状態で基礎躯体Fを作成する。 〈11〉上記実施例1で示した〈10〉の作業を行う。The preparation method is as follows in the order of steps. <1> The operation <1> described in the first embodiment is performed. <2> As shown in FIG. 11, the ground surrounded by the retaining wall 2 is moved to the height F of the second basement floor frame FL in the underground structure 1.
Preliminary excavation is performed to excavate to a depth corresponding to Lh. <3> As shown in FIG. 12, on the ground surrounded by the retaining wall 2, a second-floor basement floor frame FL is formed so as to be in contact with the retaining wall 2 around the periphery and to be a cut beam for the retaining wall 2. . <4> As shown in FIG. 13, a primary excavation operation of excavating below the second basement floor frame FL in a state where the second basement floor frame FL is suspended and supported on the straight columns 4 via the hanging members 5. I do. <5> As shown in FIG. 14, a lowering operation of lowering the second basement floor frame FL to the excavation site is performed using the straight pillar 4 as a guide. <6> As shown in FIG. 15, the first-floor floor frame F1 is
While the work of creating the floor frame is performed in a state where the floor frame FL is supported by the basement, the lower side of the floor structure FL of the second basement floor is supported while the floor structure FL of the second basement is suspended and supported by the vertical columns 4 via the hanging members 5. Perform secondary excavation work to excavate. <7> As shown in FIG. 16, a lowering operation of lowering the floor structure FL on the second basement floor to the excavation site is performed using the straight pillar 4 as a guide. <8> As shown in FIG. 17, while performing a floor frame creation operation for creating a state in which the first basement floor frame B1 is supported by the timber pillars 4, the second basement floor frame FL is suspended on the timber pillars 4. The third excavation is performed to excavate the lower side of the second floor underground floor frame FL to a depth at which the foundation frame F can be installed in a state where the base frame F is suspended and supported through the base 5. <9> As shown in FIG. 18, the basement floor 4 is used as a guide to lower the second basement floor frame FL to a predetermined level of the excavation site. <10> As shown in FIG. 19, the base frame F is created in a state where the basement floor FL is supported. <11> The operation of <10> shown in the first embodiment is performed.
【0024】この作成方法でも、逆打ち工程が二回繰り
返されている。つまり、一回目の逆打ち工程は、前記
〈4〉の工程の一次掘削作業と、〈5〉の工程の下降作
業と、〈6〉の工程の床躯体作成作業とからなり、二回
目の逆打ち工程は、〈6〉の工程の二次掘削作業と、
〈7〉の工程の下降作業と、〈8〉の工程の床躯体作成
作業とからなり、〈6〉の工程において、一回目の逆打
ち工程での床躯体作成作業と二回目の逆打ち工程での二
次掘削作業とが同時的に行われ、作業工期の短縮化が図
られている。In this method, the reverse striking step is repeated twice. That is, the first reverse striking step includes the primary excavation operation of the step <4>, the lowering operation of the step <5>, and the floor frame forming operation of the step <6>. The beating process is the secondary excavation work of the process <6>,
It consists of the lowering work of the step <7> and the floor skeletal construction work of the step <8>. In the step <6>, the floor skeletal formation work in the first reverse smashing step and the second reverse smashing step The secondary excavation work is performed at the same time, and the work period is shortened.
【0025】前記〈6〉及び〈8〉の工程での床躯体作
成作業は、地下2階床躯体FLを作業用のステージとし
て行う。つまり、型枠工事などを地下2階床躯体FLを
足場として行い、型枠を地下2階床躯体FLに支保させ
る。この型枠支保は、地下2階床躯体FLの上面が平滑
であることにより、確実安全に行える。The floor framing work in the steps <6> and <8> is performed using the second basement floor framing FL as a work stage. That is, formwork or the like is performed using the second basement floor frame FL as a scaffold, and the formwork is supported by the second basement floor frame FL. The form support can be reliably and safely performed because the upper surface of the second basement floor frame FL is smooth.
【0026】〈実施例3〉上述した地下2階の地下構造
体1への適用例を示す。<Embodiment 3> An example of application to the above-described underground structure 1 on the second basement floor will be described.
【0027】作成方法を工程順に示せば次の通りであ
る。 〈1〉上記実施例1で示した〈1〉の作業を行う。 〈2〉図20に示すように、山留め壁2で囲まれた地盤
を、地下構造体1における基礎躯体Fの高さFhに相当
する深さまで掘削する予備掘削を行う。 〈3〉図21に示すように、山留め壁2で囲まれた地盤
の上に基礎躯体Fを、山留め壁2に周囲で接してその山
留め壁2に対する切梁となる状態で作成する。 〈4〉図22に示すように、構真柱4に基礎躯体Fを吊
り材5を介して吊り支持させた状態でその基礎躯体Fの
下側を掘削する一次掘削作業を行う。 〈5〉図23に示すように、構真柱4をガイドとして基
礎躯体Fを掘削跡に下降位置させる下降作業を行う。 〈6〉図24に示すように、1階床躯体F1を構真柱4
に支持させる状態で作成する床躯体作成作業を行う一
方、基礎躯体Fを構真柱4に吊り材5を介して吊り支持
させた状態でその基礎躯体Fの下側を掘削する二次掘削
作業を行う。 〈7〉図25に示すように、構真柱4をガイドとして基
礎躯体Fを掘削跡に下降位置させる下降作業を行う。 〈8〉図26に示すように、地下1階床躯体B1を構真
柱4に支持させる状態で作成する床躯体作成作業を行う
一方、基礎躯体Fを構真柱4に吊り材5を介して吊り支
持させた状態でその基礎躯体Fの下側を、基礎躯体Fの
設置を可能とさせる深さまで掘削する三次掘削を行う。 〈9〉図27に示すように、構真柱4をガイドとして基
礎躯体Fを掘削跡に下降させ、所定のレベルに設置す
る。 〈10〉図28に示すように、地下2階床躯体FLを基
礎躯体Fの上に作成する。 〈11〉上記実施例1で示した〈10〉の作業を行う。The preparation method is as follows in the order of steps. <1> The operation <1> described in the first embodiment is performed. <2> As shown in FIG. 20, preliminary excavation is performed to excavate the ground surrounded by the retaining wall 2 to a depth corresponding to the height Fh of the foundation frame F in the underground structure 1. <3> As shown in FIG. 21, a foundation frame F is formed on the ground surrounded by the retaining wall 2 so as to be in contact with the retaining wall 2 around the periphery and to be a cut beam for the retaining wall 2. <4> As shown in FIG. 22, a primary excavation operation for excavating the lower side of the base frame F is performed in a state where the base frame F is suspended and supported on the straight pillar 4 via the hanging members 5. <5> As shown in FIG. 23, a lowering operation of lowering the foundation frame F to the excavation mark is performed using the straight pillar 4 as a guide. <6> As shown in FIG. 24, the first-floor floor frame F1 is
Excavation work to excavate the lower side of the base frame F while the base frame F is supported and supported by the vertical pillars 4 via the hanging members 5 while the floor frame preparation work is performed in a state where the floor frame is supported. I do. <7> As shown in FIG. 25, a lowering operation for lowering the foundation frame F to the excavation mark is performed using the straight pillar 4 as a guide. <8> As shown in FIG. 26, while performing a floor frame creation operation of creating a state in which the first basement floor frame B1 is supported by the timber columns 4, the base frame F is attached to the timber columns 4 via the hanging members 5. The third excavation is performed to excavate the lower side of the foundation frame F to a depth at which the foundation frame F can be installed in a state where the foundation frame F is suspended and supported. <9> As shown in FIG. 27, the foundation frame F is lowered to the excavation mark using the straight pillar 4 as a guide, and is installed at a predetermined level. <10> As shown in FIG. 28, the basement floor F is formed on the second basement floor frame FL. <11> The operation of <10> shown in the first embodiment is performed.
【0028】この作成方法でも、逆打ち工程が二回繰り
返されている。つまり、一回目の逆打ち工程は、前記
〈4〉の工程の一次掘削作業と、〈5〉の工程の下降作
業と、〈6〉の工程の床躯体作成作業とからなり、二回
目の逆打ち工程は、〈6〉の工程の二次掘削作業と、
〈7〉の工程の下降作業と、〈8〉の工程の床躯体作成
作業とからなり、〈6〉の工程において、一回目の逆打
ち工程での床躯体作成作業と二回目の逆打ち工程での二
次掘削作業とが同時的に行われ、作業工期の短縮化が図
られている。In this method, the reverse striking step is repeated twice. That is, the first reverse striking step includes the primary excavation operation of the step <4>, the lowering operation of the step <5>, and the floor frame forming operation of the step <6>. The beating process is the secondary excavation work of the process <6>,
It consists of the lowering work of the step <7> and the floor skeletal construction work of the step <8>. In the step <6>, the floor skeletal formation work in the first reverse smashing step and the second reverse smashing step The secondary excavation work is performed at the same time, and the work period is shortened.
【0029】前記〈6〉及び〈8〉の工程での床躯体作
成作業は、基礎躯体Fを作業用のステージとして行う。
つまり、型枠工事などを基礎躯体Fを足場として行い、
型枠を基礎躯体Fに支保させる。この型枠の支保などの
床躯体作成作業は、直接に基礎躯体F上を利用して行っ
ても良いが、図中二点鎖線で示すように、基礎躯体Fの
上に仮設床6を構築して行うことが好ましい。つまり、
仮設床6を構築することにより、上面が平滑な作業ステ
ージを構成でき、これによって作業の確実安全化を促進
できる。The floor frame making operation in the steps <6> and <8> is performed using the basic frame F as a work stage.
In other words, formwork etc. are performed using the foundation frame F as a scaffold,
The formwork is supported on the base frame F. The work of preparing the floor frame such as the support of the formwork may be performed directly on the base frame F, but the temporary floor 6 is constructed on the base frame F as shown by a two-dot chain line in the figure. It is preferable to perform it. That is,
By constructing the temporary floor 6, a work stage having a smooth upper surface can be formed, thereby promoting safe operation.
【0030】〔別実施例〕上記実施例では、地下構造体
1が地下2階の場合の適用例を示したが、本発明は各種
階数の地下構造体1に適用することができる。つまり、
所定の回数逆打ち工程を繰り返すことにより所定階数の
床躯体FSを上方のものから順に作成できるのであり、
複数の逆打ち工程を繰り返すにあたっては、上記実施例
のように、先の逆打ち工程での床躯体作成作業とその後
の逆打ち工程での掘削作業とを同時的に行うことが工期
の短縮化を図る上で好ましい。[Alternative Embodiment] In the above-described embodiment, an example in which the underground structure 1 has the second basement floor is shown. However, the present invention can be applied to the underground structure 1 having various floors. That is,
By repeating the reverse strike process a predetermined number of times, the floor frame FS of the predetermined number of floors can be created in order from the upper one,
When repeating a plurality of reverse striking steps, as in the above-described embodiment, it is necessary to simultaneously perform the floor frame creation work in the preceding reverse striking step and the excavation work in the subsequent reverse striking step, thereby shortening the construction period. It is preferable in aiming at.
【0031】上記実施例では、予備掘削を行って構造体
Aや最下段床躯体FL、基礎躯体Fの作成を行ったが、
予備掘削を行わずにそれらを作成しても良い。In the above embodiment, the preliminary excavation was performed to create the structure A, the lowermost floor frame FL, and the foundation frame F.
They may be created without preliminary drilling.
【0032】上記実施例では、地下2階の階高が地下1
階の階高よりも高い地下構造体への適用を示したが、各
階の階高が同じ地下構造体にも本発明は適用できる。In the above embodiment, the height of the second basement is 1 basement.
Although the application to the underground structure higher than the floor height of the floor has been described, the present invention is also applicable to the underground structure where the floor height of each floor is the same.
【0033】尚、特許請求の範囲の項に図面との対照を
便利にするために符号を記すが、該記入により本発明は
添付図面の構成に限定されるものではない。Incidentally, reference numerals are written in the claims for convenience of comparison with the drawings, but the present invention is not limited to the configuration of the attached drawings by the entry.
【図1】実施例1における地下構造体を示す断面図FIG. 1 is a cross-sectional view illustrating an underground structure according to a first embodiment.
【図2】実施例1における作業工程を示す断面図FIG. 2 is a sectional view showing a working process in the first embodiment.
【図3】実施例1における作業工程を示す断面図FIG. 3 is a sectional view showing a working process in the first embodiment.
【図4】実施例1における作業工程を示す断面図FIG. 4 is a sectional view showing a working process in the first embodiment.
【図5】実施例1における作業工程を示す断面図FIG. 5 is a sectional view showing a working process in the first embodiment.
【図6】実施例1における地下構造体の断面図FIG. 6 is a cross-sectional view of the underground structure according to the first embodiment.
【図7】実施例1における地下構造体の断面図FIG. 7 is a cross-sectional view of the underground structure according to the first embodiment.
【図8】実施例1における地下構造体の断面図FIG. 8 is a cross-sectional view of the underground structure according to the first embodiment.
【図9】実施例1における地下構造体の断面図FIG. 9 is a cross-sectional view of the underground structure according to the first embodiment.
【図10】実施例1における地下構造体の断面図FIG. 10 is a sectional view of an underground structure according to the first embodiment.
【図11】実施例2における地下構造体の断面図FIG. 11 is a sectional view of an underground structure according to the second embodiment.
【図12】実施例2における地下構造体の断面図FIG. 12 is a sectional view of an underground structure according to the second embodiment.
【図13】実施例2における地下構造体の断面図FIG. 13 is a sectional view of an underground structure according to the second embodiment.
【図14】実施例2における地下構造体の断面図FIG. 14 is a sectional view of an underground structure according to the second embodiment.
【図15】実施例2における地下構造体の断面図FIG. 15 is a sectional view of an underground structure according to the second embodiment.
【図16】実施例2における地下構造体の断面図FIG. 16 is a sectional view of an underground structure according to the second embodiment.
【図17】実施例2における地下構造体の断面図FIG. 17 is a sectional view of an underground structure according to the second embodiment.
【図18】実施例2における地下構造体の断面図FIG. 18 is a sectional view of an underground structure according to the second embodiment.
【図19】実施例2における地下構造体の断面図FIG. 19 is a sectional view of an underground structure according to the second embodiment.
【図20】実施例3における地下構造体の断面図FIG. 20 is a sectional view of an underground structure according to the third embodiment.
【図21】実施例3における地下構造体の断面図FIG. 21 is a sectional view of an underground structure according to the third embodiment.
【図22】実施例3における地下構造体の断面図FIG. 22 is a sectional view of an underground structure according to the third embodiment.
【図23】実施例3における地下構造体の断面図FIG. 23 is a sectional view of an underground structure according to the third embodiment.
【図24】実施例3における地下構造体の断面図FIG. 24 is a sectional view of an underground structure according to the third embodiment.
【図25】実施例3における地下構造体の断面図FIG. 25 is a sectional view of an underground structure according to the third embodiment.
【図26】実施例3における地下構造体の断面図FIG. 26 is a sectional view of an underground structure according to the third embodiment.
【図27】実施例3における地下構造体の断面図FIG. 27 is a sectional view of an underground structure according to the third embodiment.
【図28】実施例3における地下構造体の断面図FIG. 28 is a sectional view of an underground structure according to the third embodiment.
2 山留め壁 4 構真柱 F 基礎躯体 FS 床躯体 FL 最下段床躯体 A 構造体 2 Mountain retaining wall 4 Construction pillar F Foundation frame FS Floor frame FL Lowermost floor frame A Structure
───────────────────────────────────────────────────── フロントページの続き (72)発明者 長田 省作 大阪府大阪市中央区本町四丁目1番13号 株式会社竹中工務店 大阪本店内 (56)参考文献 特開 昭49−33415(JP,A) 特開 平3−100225(JP,A) 特開 平6−158672(JP,A) (58)調査した分野(Int.Cl.7,DB名) E02D 29/045 E02D 17/04 E21D 13/00 ──────────────────────────────────────────────────続 き Continuation of front page (72) Inventor Shosaku Osada 4-1-1-13 Honcho, Chuo-ku, Osaka-shi, Osaka Takenaka Corporation Osaka Main Store (56) References JP-A-49-33415 (JP, A) JP-A-3-100225 (JP, A) JP-A-6-158672 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E02D 29/045 E02D 17/04 E21D 13 / 00
Claims (3)
(4)を作成し、地盤上に基礎躯体(F)を山留め壁
(2)に対する切梁となる状態で作成し、次いで、基礎
躯体(F)を構真柱(4)に支持させた状態で基礎躯体
(F)の下側を掘削する掘削作業と、基礎躯体(F)を
掘削跡に下降位置させる下降作業と、構真柱(4)のう
ち基礎躯体(F)よりも上方の部分に支持させる状態で
床躯体(FS)を作成する床躯体作成作業とからなる逆
打ち工程を所定回数繰り返し行って、各階の床躯体(F
S)を上方のものから順に作成するとともに、基礎躯体
(F)を所定のレベルに設置する地下構造体の作成方
法。1. A retaining wall (2) and a timber pillar (4) are formed in the ground, and a foundation frame (F) is formed on the ground so as to be a cut beam for the retaining wall (2). Excavation work for excavating the lower side of the foundation skeleton (F) while the foundation skeleton (F) is supported by the timber pillar (4); and descent work for lowering the foundation skeleton (F) to the excavation mark. The floor striking step of forming the floor frame (FS) in a state where the floor frame (FS) is supported by the pillars (4) above the base frame (F) is repeated a predetermined number of times, and the floor of each floor is repeated. Frame (F
A method for creating an underground structure in which S) is created in order from the top and the foundation frame (F) is installed at a predetermined level.
(4)を作成し、地盤上に最下段床躯体(FL)を山留
め壁(2)に対する切梁となる状態で作成し、次いで、
最下段床躯体(FL)を構真柱(4)に支持させた状態
で最下段床躯体(FL)の下側を掘削する掘削作業と、
最下段床躯体(FL)を掘削跡に下降位置させる下降作
業と、構真柱(4)のうち最下段床躯体(FL)よりも
上方の部分に支持させる状態で床躯体(FS)を作成す
る床躯体作成作業とからなる逆打ち工程を所定回数繰り
返し行って、各階の床躯体(FS)を上方のものから順
に作成するとともに、最下段床躯体(FL)の下側を掘
削して基礎躯体(F)の作成と最下段床躯体(FL)の
所定のレベルへの設置とを行う地下構造体の作成方法。2. A retaining wall (2) and a straight pillar (4) are formed in the ground, and a lowermost floor frame (FL) is formed on the ground so as to be a cut beam for the retaining wall (2). Then
Excavation work for excavating the lower side of the lowermost floor frame (FL) in a state where the lowermost floor frame (FL) is supported by the straight pillar (4);
Lowering work to lower the lowermost floor frame (FL) to the excavation site, and creation of the floor frame (FS) in a state where the lower right floor frame (FL) is supported by the part above the lowermost floor frame (FL) in the straight pillar (4) Is repeated a predetermined number of times to create the floor frame (FS) of each floor in order from the top, and excavate the lower side of the lowermost floor frame (FL) to form a foundation. A method of creating an underground structure for creating a frame (F) and installing a lowermost floor frame (FL) at a predetermined level.
(4)を作成し、地盤上に、基礎躯体(F)と最下段床
躯体(FL)とを備えた構造体(A)を山留め壁(2)
に対する切梁となる状態で作成し、次いで、構造体
(A)を構真柱(4)に支持させた状態で構造体(A)
の下側を掘削する掘削作業と、構造体(A)を掘削跡に
下降位置させる下降作業と、構真柱(4)のうち構造体
(A)よりも上方の部分に支持させる状態で床躯体(F
S)を作成する床躯体作成作業とからなる逆打ち工程を
所定回数繰り返し行って、各階の床躯体(FS)を上方
のものから順に作成するとともに、構造体(A)を所定
のレベルに設置する地下構造体の作成方法。3. A structure (A) in which a mountain retaining wall (2) and a timber frame (4) are formed in the ground, and a foundation frame (F) and a lowermost floor frame (FL) are formed on the ground. To the retaining wall (2)
Then, the structure (A) is formed in a state where the structure (A) is supported by the straight pillar (4).
Excavation work to excavate the lower side of the building, a lowering operation to lower the structure (A) to the excavation site, and a floor in a state in which it is supported by a portion of the straight pillar (4) above the structure (A). Frame (F
S) is repeated a predetermined number of times, including a floor frame forming operation for forming a floor frame, and a floor frame (FS) of each floor is sequentially formed from an upper one, and the structure (A) is installed at a predetermined level. How to create underground structures.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP30051594A JP3286095B2 (en) | 1994-12-05 | 1994-12-05 | How to create an underground structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP30051594A JP3286095B2 (en) | 1994-12-05 | 1994-12-05 | How to create an underground structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH08158385A JPH08158385A (en) | 1996-06-18 |
| JP3286095B2 true JP3286095B2 (en) | 2002-05-27 |
Family
ID=17885754
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP30051594A Expired - Fee Related JP3286095B2 (en) | 1994-12-05 | 1994-12-05 | How to create an underground structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3286095B2 (en) |
-
1994
- 1994-12-05 JP JP30051594A patent/JP3286095B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH08158385A (en) | 1996-06-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5528877A (en) | Concrete building frame construction method | |
| JP3728654B2 (en) | Building dismantling and construction methods | |
| JP3644605B2 (en) | Reverse driving method of underground structure under road surface. | |
| RU2220258C1 (en) | Process of erection of multilevel underground structure ( variants ) | |
| KR102396786B1 (en) | Underground expansion and top-down method of new building using reinforcement of existing underground outer wall | |
| JP3724320B2 (en) | Construction method for underground structures | |
| KR20200122037A (en) | The construction method using a exterio wall of undergound structure | |
| JP3286095B2 (en) | How to create an underground structure | |
| KR20000058238A (en) | Underground construction method using permanent reinforced concrete girders as temporary struts | |
| KR0179708B1 (en) | Working method for underground structure of a building | |
| JPH0684690B2 (en) | Building basement extension method | |
| JP3308407B2 (en) | How to create an underground structure | |
| KR102150388B1 (en) | A method of construction complexes for building demolition and building construction of the same time | |
| JPH03253613A (en) | Underground excavation mountain stop construction method | |
| JP2736542B2 (en) | Construction method of underground structure omitting temporary materials | |
| JPH04189922A (en) | Consturction method for underground structure using core section | |
| JPH1130053A (en) | Construction method of seismic isolation building | |
| KR100593203B1 (en) | Construction method of underground structure using deck support frame for side pressure support formation and deck support frame for side pressure support formation | |
| JPH05255943A (en) | Construction method for underground skeleton by slide down system | |
| JPS63312437A (en) | Construction of underground structure | |
| JP6682173B1 (en) | How to build a building | |
| JPH07173847A (en) | Large scale and large depth conformable independent open-cut method | |
| JPH0657769A (en) | Underground structure and its construction method | |
| JPH0657958B2 (en) | Reverse floor construction method | |
| JPH08177068A (en) | Construction of underground structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090308 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100308 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110308 Year of fee payment: 9 |
|
| LAPS | Cancellation because of no payment of annual fees |