JP3308488B2 - Construction equipment on the slope - Google Patents
Construction equipment on the slopeInfo
- Publication number
- JP3308488B2 JP3308488B2 JP07570998A JP7570998A JP3308488B2 JP 3308488 B2 JP3308488 B2 JP 3308488B2 JP 07570998 A JP07570998 A JP 07570998A JP 7570998 A JP7570998 A JP 7570998A JP 3308488 B2 JP3308488 B2 JP 3308488B2
- Authority
- JP
- Japan
- Prior art keywords
- slope
- construction
- height direction
- construction device
- facility
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims description 111
- 238000004804 winding Methods 0.000 claims description 22
- 238000005553 drilling Methods 0.000 claims description 17
- 238000005507 spraying Methods 0.000 claims description 13
- 238000004080 punching Methods 0.000 claims 2
- 210000003128 head Anatomy 0.000 description 11
- 210000001061 forehead Anatomy 0.000 description 8
- 230000001174 ascending effect Effects 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 239000000725 suspension Substances 0.000 description 3
- 230000009193 crawling Effects 0.000 description 2
- 210000005069 ears Anatomy 0.000 description 1
- 230000003028 elevating effect Effects 0.000 description 1
- 210000004744 fore-foot Anatomy 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Landscapes
- Earth Drilling (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、法面におけるたと
えば法枠構築工事などにおいて、アンカー孔やロックボ
ルト孔などを削孔する装置、あるいは吹付装置などの施
工装置を用いて法面を施工する設備に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a slope by using an apparatus for drilling an anchor hole, a lock bolt hole, or the like, or a spraying apparatus in a slope construction work, for example. Equipment related.
【0002】[0002]
【従来の技術】法面のたとえば法枠構築工事において
は、アンカー孔の削孔などの作業を必要とする。この場
合、通常は、法面に足場を組み上げ、順次所定個所に削
孔機を設置しながら削孔を行うようにしている。2. Description of the Related Art For example, in the construction of a slope on a slope, work such as drilling of an anchor hole is required. In this case, usually, a scaffold is assembled on a slope, and drilling is performed while a drilling machine is sequentially installed at a predetermined location.
【0003】しかし、足場の構築に多大な手間を要する
とともに、急な斜面においては、足場の確保すら困難な
ことがある。[0003] However, construction of a scaffold requires a great deal of trouble, and it is sometimes difficult to secure the scaffold even on a steep slope.
【0004】そこで、特公平7−33682号などにお
いては、法面の加工機械をウインチを用いて昇降させる
ことが提案されている。[0004] In view of this, Japanese Patent Publication No. 7-33682 proposes raising and lowering a slope processing machine using a winch.
【0005】[0005]
【発明が解決しようとする課題】かかる先行技術は、足
場が不要となる点などにおいて優れるものの、単に法頭
と加工機械との一方にウインチを、他方にアンカーを設
けるのみであるために、次記の問題が残されている。Although the prior art is excellent in that a scaffold is not required, the prior art merely provides a winch on one of the forehead and the processing machine and an anchor on the other. The problem described above remains.
【0006】(1)ウインチを加工機械に設けるとする
と、そのウインチが大型化し、装置全体の重量が嵩み、
機動性に劣るものとなる。(1) If a winch is provided on a processing machine, the winch becomes large and the weight of the entire apparatus increases,
It becomes inferior in mobility.
【0007】(2)さりとて、ウインチを法頭に設ける
とすると、そのウインチおよびその駆動源を法頭まで運
び上げる必要があり、その作業に多大な手間がかかると
ともに、場合によって、その設置スペースの確保が困難
なこともある。(2) If the winch is provided on the prong, the winch and its driving source must be carried to the promon, which requires a great deal of work and, in some cases, the installation space. It can be difficult to secure.
【0008】したがって、本発明の主たる課題は、かか
る問題を解消して、施工装置の軽量化を図るとともに、
施工能率を高めることにある。Accordingly, a main object of the present invention is to solve such a problem, reduce the weight of the construction apparatus, and
The purpose is to increase construction efficiency.
【0009】[0009]
【課題を解決するための手段】上記課題を解決した本発
明の請求項1記載の発明は、法面においてその高さ方向
および水平方向のうち少なくとも高さ方向に沿って、施
工装置を移動させながら法面に対して施工を行う設備に
おいて、前記施工装置は、アンカー孔またはロックボル
ト孔を削孔する装置、あるいは吹付装置を搭載した基台
を有し、前記施工装置を通り法面の高さ方向に沿う昇降
線を挟んで;法頭側に1対の支持体を固定して設け、法
尻側に1対の巻き上げ機を固定して設け、前記施工装置
と、支持体と、巻き上げ機とを牽引ワイヤー類により繋
ぎ、かつ前記支持体に設けた案内部に前記牽引ワイヤー
類を案内させて繋ぎ、この繋ぎ経路に動滑車を介在さ
せ、 前記各巻き上げ機の作動により前記牽引ワイヤー類
の巻取または巻戻しにより前記施工装置を法面の高さ方
向に昇降させるように構成したことを特徴とする法面に
おける施工設備である。According to the first aspect of the present invention, which solves the above-mentioned problems, according to the present invention, a construction apparatus is moved along at least a height direction among a height direction and a horizontal direction on a slope. In a facility that performs construction on a slope, the construction device includes an anchor hole or a rock bolt.
A base equipped with a device for drilling holes or a spraying device
Having a pair of supports fixedly provided on the forehead side and a pair of hoisting machines fixed on the bottom side, with the ascending and descending line extending along the slope direction passing through the construction device. The construction device, the support, and the hoist are connected by a pulling wire, and the guide portion provided on the support is connected by guiding the pulling wire, and a moving pulley is interposed in the connecting path. Sa
So, the puller wire such by the operation of the respective hoisting machines
The construction equipment on a slope, wherein the construction apparatus is configured to be moved up and down in the height direction of the slope by winding or unwinding .
【0010】請求項2記載の発明は、法面においてその
高さ方向および水平方向のうち少なくとも高さ方向に沿
って、施工装置を移動させながら法面に対して施工を行
う設備において、前記施工装置は、アンカー孔またはロ
ックボルト孔を削孔する装置、あるいは吹付装置を搭載
した基台を有し、前記施工装置を通り法面の高さ方向に
沿う昇降線を挟んで;法頭側に1対の支持体を固定して
設け、法尻側に1対の巻き上げ機を固定して設け、前記
施工装置、支持体に設けた案内部、巻き上げ機を、これ
らの順で牽引ワイヤー類により繋ぎ、この繋ぎ経路に動
滑車を介在させ、 前記各巻き上げ機の作動により前記牽
引ワイヤー類の巻取または巻戻しにより前記施工装置を
法面の高さ方向に昇降させるように構成したことを特徴
とする法面における施工設備である。According to a second aspect of the present invention, there is provided a facility for performing a construction on a slope by moving a construction apparatus along at least a height direction and a horizontal direction on the slope. The device can be installed in the anchor hole or
Equipped with a device for drilling bolt holes or spraying device
Having a base that is formed and sandwiching an ascending and descending line extending in the height direction of the slope passing through the construction device; a pair of supports are fixedly provided on the side of the forehead; Is fixed, and the construction device, the guide portion provided on the support, and the hoist are connected in this order by traction wires, and moving along this connection path.
The pulley is interposed, and the above-mentioned traction machine is
A construction facility on a slope, wherein the construction apparatus is configured to be moved up and down in a height direction of the slope by winding or unwinding a pull wire .
【0011】請求項3記載の発明は、法面においてその
高さ方向および水平方向のうち少なくとも高さ方向に沿
って、施工装置を移動させながら法面に対して施工を行
う設備において、前記施工装置は、アンカー孔またはロ
ックボルト孔を削孔する装置、あるいは吹付装置を搭載
した基台を有し、前記施工装置を通り法面の高さ方向に
沿う昇降線を挟んで;法頭側に1対の支持体を固定して
設け、法尻側に1対の巻き上げ機を固定して設け、前記
支持体を一端部の固定点とし、施工装置に設けた案内
部、および支持体に設けた案内部を順に案内させて巻き
上げ機に牽引ワイヤー類を繋ぎ、この繋ぎ経路に動滑車
を介在させ、 前記各巻き上げ機の作動により前記牽引ワ
イヤー類の巻取または巻戻しにより前記施工装置を法面
の高さ方向に昇降させるように構成したことを特徴とす
る法面における施工設備である。According to a third aspect of the present invention, there is provided a facility for performing construction on a slope while moving a construction apparatus along at least a height direction and a horizontal direction on the slope. The device can be installed in the anchor hole or
Equipped with a device for drilling bolt holes or spraying device
Having a base that is formed and sandwiching an ascending and descending line extending in the height direction of the slope passing through the construction device; a pair of supports are fixedly provided on the side of the forehead; Is fixed, the support is used as a fixing point at one end, and the guide provided on the construction device and the guide provided on the support are sequentially guided to connect the pulling wires to the hoist , and this connection path Moving pulley
, And the operation of each of the hoisting machines causes the
A construction facility on a slope, wherein the construction device is configured to be moved up and down in a height direction of the slope by winding or rewinding ears .
【0012】請求項4記載の発明は、法面においてその
高さ方向および水平方向のうち少なくとも高さ方向に沿
って、施工装置を移動させながら法面に対して施工を行
う設備において、前記施工装置は、アンカー孔またはロ
ックボルト孔を削孔する装置、あるいは吹付装置を搭載
した基台を有し、前記施工装置を通り法面の高さ方向に
沿う昇降線を挟んで;法頭側に1対の支持体を固定して
設け、法尻側に1対の巻き上げ機を固定して設け、前記
施工装置を一端部の固定点とし、支持体に設けた第1案
内部、施工装置に設けた案内部、および支持体に設けた
第2案内部を順に案内させて巻き上げ機に牽引ワイヤー
類を繋ぎ、この繋ぎ経路に動滑車を介在させ、 前記各巻
き上げ機の作動により前記牽引ワイヤー類の巻取または
巻戻しにより前記施工装置を法面の高さ方向に昇降させ
るように構成したことを特徴とする法面における施工設
備である。[0012] The invention of claim 4, wherein along at least the height direction of the height direction and the horizontal direction in the slope, the equipment performing construction against slope while moving the construction unit, said construction The device can be installed in the anchor hole or
Equipped with a device for drilling bolt holes or spraying device
Having a base that is formed and sandwiching an ascending and descending line extending in the height direction of the slope passing through the construction device; a pair of supports are fixedly provided on the side of the forehead; Is fixed, the construction device is set as a fixing point at one end, and the first guide portion provided on the support, the guide portion provided on the construction device, and the second guide portion provided on the support are sequentially guided. a hoist connecting the traction wire such, the movable pulley is interposed the connecting path, the each volume
Winding of the pulling wires or the like by the operation of the hoisting machine
A construction facility on a slope, wherein the construction apparatus is configured to be moved up and down in the height direction of the slope by unwinding .
【0013】請求項5記載の発明は、法面においてその
高さ方向および水平方向のうち少なくとも高さ方向に沿
って、施工装置を移動させながら法面に対して施工を行
う設備において、前記施工装置は、アンカー孔またはロ
ックボルト孔を削孔する装置、あるいは吹付装置を搭載
した基台を有し、前記施工装置を通り法面の高さ方向に
沿う昇降線を挟んで;法頭側に少なくとも1対の支持体
を固定して設け、法尻側に1対の巻き上げ機を固定して
設け、前記施工装置を一端部の固定点とし、前記巻き上
げ機を他端部の固定点とし、これらを中間に動滑車を介
在させて牽引ワイヤー類により連結し、各動滑車の軸は
前記支持体または施工装置に連結し、前記各巻き上げ機
の作動により前記牽引ワイヤー類の巻取または巻戻しに
より前記施工装置を法面の高さ方向に昇降させるように
構成したことを特徴とする法面における施工設備であ
る。According to a fifth aspect of the present invention, there is provided a facility for performing construction on a slope by moving a construction apparatus along at least a height direction and a horizontal direction of the slope on the slope. The device can be installed in the anchor hole or
Equipped with a device for drilling bolt holes or spraying device
To have a base and, across the lift line along the construction apparatus in the height direction of the street slopes; provided by fixing at least one pair support law cranial, winding pair law trailing Machine is fixedly provided, the construction device is a fixed point at one end, the hoisting machine is a fixed point at the other end, and these are connected by a pulling wire with a moving pulley interposed therebetween. The shaft is connected to the support or the construction device, and each of the hoists
Operation to take up or rewind the pulling wires
The construction equipment on a slope , wherein the construction apparatus is configured to be moved up and down in a height direction of the slope.
【0014】請求項6記載の発明は、法面においてその
高さ方向および水平方向のうち少なくとも高さ方向に沿
って、施工装置を移動させながら法面に対して施工を行
う設備において、前記施工装置は、アンカー孔またはロ
ックボルト孔を削孔する装置、あるいは吹付装置を搭載
した基台を有し、前記施工装置を通り法面の高さ方向に
沿う昇降線を挟んで;法頭側に少なくとも1対の支持体
を固定して設け、法尻側に1対の巻き上げ機を固定して
設け、前記支持体を一端部の固定点とし、前記巻き上げ
機を他端部の固定点とし、これらを中間に動滑車を介在
させて牽引ワイヤー類により連結し、各動滑車の軸は前
記支持体または施工装置に連結し、前記各巻き上げ機の
作動により前記牽引ワイヤー類の巻取または巻戻しによ
り前記施工装置を法面の高さ方向に昇降させるように構
成したことを特徴とする法面における施工設備である。According to a sixth aspect of the present invention, there is provided a facility for performing a construction on a slope while moving a construction device along at least a height direction and a horizontal direction on the slope. The device can be installed in the anchor hole or
Equipped with a device for drilling bolt holes or spraying device
To have a base and, across the lift line along the construction apparatus in the height direction of the street slopes; provided by fixing at least one pair support law cranial, winding pair law trailing The support is used as a fixing point at one end, the hoist is used as a fixing point at the other end, and these are connected by pulling wires with a moving pulley interposed therebetween. The shaft is connected to the support or construction device, and the
By operation, winding or rewinding of the pulling wires
The construction equipment on a slope has a configuration in which the construction device is moved up and down in a height direction of the slope.
【0015】[0015]
【発明の実施の形態】以下本発明を図面に示す実施の形
態によってさらに詳説する。請求項1は以下に述べる全
ての実施の形態に関係する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below in more detail with reference to the embodiments shown in the drawings. Claim 1 relates to all the embodiments described below.
【0016】<第1の実施の形態> 図1および図2は、第1の実施の形態を示したもので、
10は施工装置で、たとえば基台10Aとこれに搭載さ
れた削孔機10Bとを備える。基台10Aの前部には支
持軸10Cを介して吊持部10Dが設けられている。吊
持部10Dに対して支持軸10C回りに基台10Aが軸
支されている結果、基台10Aは、施工装置10を通り
法面の高さ方向に沿う昇降線Lに沿う姿勢を維持するよ
うにしてある。< First Embodiment > FIGS. 1 and 2 show a first embodiment.
Reference numeral 10 denotes a construction apparatus, which includes, for example, a base 10A and a drilling machine 10B mounted on the base. At the front of the base 10A, a suspension 10D is provided via a support shaft 10C. As a result of the base 10A being pivotally supported around the support shaft 10C with respect to the suspension unit 10D, the base 10A maintains the posture along the hoisting line L passing through the construction apparatus 10 and along the height direction of the slope. It is like that.
【0017】施工装置10は、法面3においてその高さ
方向および水平方向のうち少なくとも高さ方向に沿って
移動自在とされている。The construction apparatus 10 is movable along at least the height direction among the height direction and the horizontal direction on the slope 3.
【0018】このために、昇降線Lを挟んで、法頭1側
に1対の支持体11A,11Bが固定され、法尻2側に
1対の巻き上げ機(ウインチ)12A,12Bが固定し
て設けられている。図示例においては、支持体11A,
11Bは、法頭1の固定したアンカー11aに支持され
たガイドヘッド11bに滑車(案内部を構成する)11
cを備える。巻き上げ機(ウインチ)12A,12B
は、法尻2のほか、図示のように、法面3の適宜の位置
に、少なくとも施工装置10の昇降作動中は固定され
る。To this end, a pair of supports 11A and 11B are fixed on the side of the forehead 1 and a pair of hoists 12A and 12B are fixed on the side of the forefoot 2 with the lifting line L interposed therebetween. It is provided. In the illustrated example, the support 11A,
11B is a pulley (constituting a guide portion) 11 on a guide head 11b supported by an anchor 11a to which the femoral head 1 is fixed.
c. Winding machines (winches) 12A, 12B
Is fixed to an appropriate position of the slope 3 as shown in the drawing, in addition to the bottom 2, at least during the elevating operation of the construction apparatus 10.
【0019】施工装置10、支持体11A,11Bに設
けた滑車11c,11c、巻き上げ機12A,12B
は、これらの順で牽引用ワイヤー13A,13Bにより
繋がれている。The construction apparatus 10, pulleys 11c and 11c provided on supports 11A and 11B, and hoists 12A and 12B.
Are connected by the towing wires 13A and 13B in this order.
【0020】かくして、施工装置10は、各巻き上げ機
12A,12Bを作動させてワイヤー13A,13Bを
巻取または巻戻しすることにより、法面3に沿って昇降
させることができる。Thus, the construction apparatus 10 can be moved up and down along the slope 3 by operating each of the hoists 12A and 12B to wind or unwind the wires 13A and 13B.
【0021】この昇降を順次行いながら、所定の各位置
において、削孔機10Bによりアンカー孔やロックボル
ト孔などを削孔できる。また、各巻き上げ機12A,1
2Bによるワイヤー13A,13Bの巻取または巻戻し
量を調整することにより、昇降線Lまたは這い上がり線
を左または右に所定距離移動させることができる。この
移動させた後の次の這い上がり線に沿って、同様に削孔
を順次行うことができる。While sequentially moving up and down, an anchor hole, a lock bolt hole and the like can be drilled at a predetermined position by the drilling machine 10B. Also, each of the hoists 12A, 1
By adjusting the amount of winding or rewinding of the wires 13A, 13B by the 2B, the hoisting line L or the crawling line can be moved left or right by a predetermined distance. Drilling can be similarly performed sequentially along the next crawling line after the movement.
【0022】<第2の実施の形態:請求項3の発明に関
係する> 図3に第2の実施の形態を示した。この第2の実施の形
態においては、施工装置10の吊持部10Dに動滑車と
して機能する滑車10E,10E(案内部を構成する)
を設け、支持体11A,11Bのガイドヘッド11b,
11bを一端部の固定点とし、施工装置10の滑車10
E,10E、および支持体11A,11Bの滑車11
c,11cを順に案内させて巻き上げ機12A,12B
に牽引用ワイヤー13A,13Bを繋ぎ、各巻き上げ機
12A,12Bを作動させてワイヤー13A,13Bを
巻取または巻戻しすることにより、法面3に沿って施工
装置10を昇降させるようにしたものである。<Second Embodiment: Related to the Invention of Claim 3> FIG. 3 shows a second embodiment. In the second embodiment, pulleys 10E, 10E functioning as moving pulleys on the suspension 10D of the construction apparatus 10 (constituting the guide).
And guide heads 11b of supports 11A and 11B,
11b is a fixed point at one end, and the pulley 10
E, 10E and pulley 11 of supports 11A, 11B
winding machines 12A and 12B by sequentially guiding c and 11c.
The towing wires 13A, 13B are connected to the winding machine 12A, 12B, and the wires 13A, 13B are wound or unwound, so that the construction apparatus 10 is moved up and down along the slope 3. It is.
【0023】この場合、滑車10E,10Eが動滑車を
構成するので、巻き上げ機12A,12Bによる巻き上
げ力は小さいもので足り、巻き上げ機12A,12Bを
小型化できる。In this case, since the pulleys 10E and 10E constitute a moving pulley, the hoisting force of the hoisting machines 12A and 12B is small, and the hoisting machines 12A and 12B can be downsized.
【0024】<第3の実施の形態:請求項4の発明に関
係する> 図4に第3の実施の形態を示した。この第3の実施の形
態は第2の実施の形態の思想をさらに発展させたもの
で、施工装置10の吊持部10Dに動滑車として機能す
る滑車10E,10E(案内部を構成する)を設け、支
持体11A,11Bのガイドヘッド11b,11bに第
1滑車11c1,11c1および第2滑車11c2,1
1c2を設け、施工装置10の吊持部10Dを一端部の
固定点とし、ガイドヘッド11b,11bの第1滑車1
1c1,11c1、施工装置10の滑車10E,10
E、およびガイドヘッド11b,11bの第2滑車11
c2,11c2を順に案内させて巻き上げ機12A,1
2Bに牽引用ワイヤー13A,13Bを繋ぎ、各巻き上
げ機12A,12Bを作動させてワイヤー13A,13
Bを巻取または巻戻しすることにより、法面3に沿って
施工装置10を昇降させるようにしたものである。<Third Embodiment: Related to the Invention of Claim 4> FIG. 4 shows a third embodiment. The third embodiment is a further development of the concept of the second embodiment. Pulleys 10E and 10E (constituting a guide portion) functioning as moving pulleys are provided on a hanging portion 10D of the construction apparatus 10. The first pulleys 11c1, 11c1 and the second pulleys 11c2, 1 are provided on the guide heads 11b, 11b of the supports 11A, 11B.
1c2, and the first pulley 1 of the guide heads 11b, 11b is provided with the hanging portion 10D of the construction device 10 as a fixed point at one end.
1c1, 11c1, pulleys 10E, 10 of the construction device 10
E and the second pulley 11 of the guide heads 11b, 11b
c2, 11c2 are sequentially guided, and the winders 12A, 1
2B, the towing wires 13A, 13B are connected, and each of the hoists 12A, 12B is operated, so that the wires 13A, 13B are connected.
By winding or rewinding B, the construction apparatus 10 is moved up and down along the slope 3.
【0025】この場合、巻き上げ機12A,12Bによ
る巻き上げ力は第2の実施の形態よりさらに小さいもの
で足り、巻き上げ機12A,12Bを小型化できる。In this case, the hoisting force of the hoisting machines 12A and 12B is smaller than that of the second embodiment, and the hoisting machines 12A and 12B can be downsized.
【0026】<第4の実施の形態:請求項5の発明に関
係する> 図5に第4の実施の形態を示した。この第4の実施の形
態においては、支持体11A,11Bのアンカー11
a,11aに(またはガイドヘッド11b,11b(図
4参照)に)第1動滑車14A,14Aを繋ぎ、施工装
置10の吊持部10Dに第2動滑車14B,14Bを繋
ぎ、施工装置10の吊持部10Dを一端部の固定点と
し、第1動滑車14A,14A、および第2動滑車14
B,14Bを順に案内させて巻き上げ機12A,12B
に牽引用ワイヤー13A,13Bを繋いだものである。<Fourth Embodiment: Related to the Invention of Claim 5> FIG. 5 shows a fourth embodiment. In the fourth embodiment, the anchors 11 of the supports 11A and 11B
a, 11a (or to the guide heads 11b, 11b (see FIG. 4)), the first moving pulleys 14A, 14A are connected, and the second moving pulleys 14B, 14B are connected to the hanging portions 10D of the working device 10, and the working device 10 is connected. Of the first moving pulleys 14A, 14A and the second moving pulley 14
B and 14B are sequentially guided to wind-up machines 12A and 12B
And tow wires 13A and 13B.
【0027】かかる設備では、各巻き上げ機12A,1
2Bを作動させてワイヤー13A,13Bを巻取または
巻戻しすることにより、法面3に沿って施工装置10を
昇降させるようにしたものである。In such equipment, each of the hoists 12A, 1
The construction apparatus 10 is moved up and down along the slope 3 by operating or retracting the wires 13A and 13B by operating 2B.
【0028】この場合、第1動滑車14A,14A、お
よび第2動滑車14B,14Bを用いることにより、巻
き上げ機12A,12Bによる巻き上げ力は小さいもの
で足り、巻き上げ機12A,12Bを小型化できる。In this case, by using the first moving pulleys 14A, 14A and the second moving pulleys 14B, 14B, the hoisting force of the hoisting machines 12A, 12B is small, and the hoisting machines 12A, 12B can be downsized. .
【0029】<第5の実施の形態:請求項5の発明に関
係する> 図6に第5の実施の形態を示した。この第5の実施の形
態においては、支持体11A,11Bの第1アンカー1
1a1,11a1に(またはガイドヘッド11b,11
b(図4参照)に)第1動滑車14A,14Aを繋ぎ、
施工装置10の吊持部10Dに第2動滑車14B,14
Bを繋ぎ、さらに、支持体11A,11Bの第2アンカ
ー11a2,11a2に(またはガイドヘッド11b,
11b(図4参照)に)第3動滑車14C,14Cを繋
いだものである。<Fifth Embodiment: Related to the Invention of Claim 5> FIG. 6 shows a fifth embodiment. In the fifth embodiment, the first anchor 1 of the supports 11A and 11B
1a1 and 11a1 (or guide heads 11b and 11a).
b (see FIG. 4), connect the first moving pulleys 14A, 14A,
The second moving pulleys 14B, 14
B and further connected to the second anchors 11a2 and 11a2 of the supports 11A and 11B (or the guide heads 11b and 11b).
11b (see FIG. 4) to which the third moving pulleys 14C, 14C are connected.
【0030】これに対して、施工装置10の吊持部10
Dを一端部の固定点とし、第1動滑車14A,14A、
第2動滑車14B,14B、および第3動滑車14C,
14Cを順に案内させて巻き上げ機12A,12Bに牽
引用ワイヤー13A,13Bを繋いだものである。On the other hand, the hanging part 10 of the construction apparatus 10
D is a fixed point at one end, and the first moving pulleys 14A, 14A,
The second moving pulleys 14B, 14B, and the third moving pulley 14C,
The towing wires 13A and 13B are connected to the hoisting machines 12A and 12B while guiding the 14C sequentially.
【0031】かかる設備では、各巻き上げ機12A,1
2Bを作動させてワイヤー13A,13Bを巻取または
巻戻しすることにより、法面3に沿って施工装置10を
昇降させることができる。In such equipment, each hoist 12A, 1
By operating the 2B and winding or rewinding the wires 13A and 13B, the construction apparatus 10 can be moved up and down along the slope 3.
【0032】この場合、第1動滑車14A,14A、第
2動滑車14B,14B、および第3動滑車14C,1
4Cを用いることにより、巻き上げ機12A,12Bに
よる巻き上げ力は小さいもので足り、巻き上げ機12
A,12Bを小型化できる。In this case, the first moving pulleys 14A, 14A, the second moving pulleys 14B, 14B, and the third moving pulleys 14C, 1
By using 4C, the hoisting force of the hoisting machines 12A and 12B is small, and
A and 12B can be miniaturized.
【0033】<第6の実施の形態:請求項6の発明に関
係する> 図7に第6の実施の形態を示した。この第6の実施の形
態においては、施工装置10の吊持部10Dに第1動滑
車14A,14Aを繋ぎ、支持体11A,11Bの第2
アンカー11a2,11a2に(またはガイドヘッド1
1b,11b(図4参照)に)第2動滑車14B,14
Bを繋いだものである。<Sixth Embodiment: Related to the Claim 6> FIG. 7 shows a sixth embodiment. In the sixth embodiment, the first moving pulleys 14A, 14A are connected to the hanging portions 10D of the construction device 10, and the second
Anchor 11a2, 11a2 (or guide head 1
1b, 11b (see FIG. 4)) the second moving pulleys 14B, 14
B is connected.
【0034】これに対して、支持体11A,11Bの第
1アンカー11a1,11a1を一端部の固定点とし、
第1動滑車14A,14A、および第2動滑車14B,
14Bを順に案内させて巻き上げ機12A,12Bに牽
引用ワイヤー13A,13Bを繋いだものである。On the other hand, the first anchors 11a1 and 11a1 of the supports 11A and 11B are fixed at one end,
A first moving pulley 14A, 14A, and a second moving pulley 14B,
The tow wires 13A and 13B are connected to the hoisting machines 12A and 12B while sequentially guiding the 14B.
【0035】かかる設備では、各巻き上げ機12A,1
2Bを作動させてワイヤー13A,13Bを巻取または
巻戻しすることにより、法面3に沿って施工装置10を
昇降させることができる。In such a facility, each hoist 12A, 1
By operating the 2B and winding or rewinding the wires 13A and 13B, the construction apparatus 10 can be moved up and down along the slope 3.
【0036】この場合、第1動滑車14A,14A、お
よび第2動滑車14B,14Bを用いることにより、巻
き上げ機12A,12Bによる巻き上げ力は小さいもの
で足り、巻き上げ機12A,12Bを小型化できる。In this case, by using the first moving pulleys 14A and 14A and the second moving pulleys 14B and 14B, the hoisting force of the hoisting machines 12A and 12B is small, and the hoisting machines 12A and 12B can be downsized. .
【0037】(その他) 本発明において、ワイヤー13A,13Bに代えて、ロ
ープやチェーンなどの牽引用長尺部材を用いることがで
きるので、これらを総称して牽引ワイヤー類という。ま
た、巻き上げ機としては、ウインチのほか、チェーンブ
ロックなども用いることができる。(Others) In the present invention, a long tow member such as a rope or a chain can be used in place of the wires 13A and 13B, and these are collectively referred to as tow wires. As the hoist, a chain block or the like can be used in addition to the winch.
【0038】上記の牽引ワイヤー類は、右または左にお
いて、複数本を用いてもよいことは当然である。したが
って、巻き上げ機を片側あたり複数台とすることもでき
る。It goes without saying that a plurality of the above pulling wires may be used on the right or left. Therefore, a plurality of hoists can be provided on one side.
【0039】上記の支持体11A,11Bおよび巻き上
げ機12A,12Bは、それぞれ法頭側または法尻側に
あればよく、法面に設置されていてもよい。The supports 11A and 11B and the hoists 12A and 12B need only be located on the side of the forehead or the bottom of the law, respectively, and may be installed on the slope.
【0040】また、上記の支持体11A,11Bおよび
巻き上げ機12A,12Bは、法面の幅方向について、
あるスパン内に施工が終了した時点で、そられの設置位
置を隣接するスパンに移動させて、設置した後に、同様
な施工を行うことができる。The supports 11A and 11B and the hoists 12A and 12B are provided in the width direction of the slope.
When the construction is completed in a certain span, the installation position is moved to an adjacent span and the same construction can be performed after the installation.
【0041】[0041]
【発明の効果】以上のとおり、本発明によれば、巻き上
げ機を加工機械に設けることなく、法尻側に固定して設
けたので、巻き上げ機の小型化を図ることができ、施工
装置の重量の軽量化を図ることができるとともに、結果
として、施工装置の機動性が高まる。As described above, according to the present invention, since the hoist is fixedly provided on the side of the bottom without providing the hoist in the processing machine, the hoist can be reduced in size and the construction apparatus can be reduced. The weight can be reduced, and as a result, the mobility of the construction apparatus is improved.
【0042】しかも、巻き上げ機を法尻側に設けたもの
で、その巻き上げ機およびその駆動源を法頭まで運び上
げる必要はなく、その作業が不要となる。法尻側であれ
ば、通常はその設置スペースの確保が容易であるため
に、作業を支承なく行うことができる。Further, since the hoist is provided on the side of the leg, it is not necessary to carry the hoist and its drive source to the forehead, and the work is unnecessary. On the side of the butt, usually, it is easy to secure the installation space, so that the work can be performed without support.
【図1】第1の実施の形態を示す側面図である。FIG. 1 is a side view showing a first embodiment.
【図2】第1の実施の形態を示す正面図である。FIG. 2 is a front view showing the first embodiment.
【図3】第2の実施の形態を示す正面図である。FIG. 3 is a front view showing a second embodiment.
【図4】第3の実施の形態を示す正面図である。FIG. 4 is a front view showing a third embodiment.
【図5】第4の実施の形態を示す正面図である。FIG. 5 is a front view showing a fourth embodiment.
【図6】第5の実施の形態を示す正面図である。FIG. 6 is a front view showing a fifth embodiment.
【図7】第6の実施の形態を示す正面図である。FIG. 7 is a front view showing a sixth embodiment.
1…法頭、2…法尻、3…法面、10…施工装置、11
A,11B…支持体、12A,12B…巻き上げ機、1
3A,13B…牽引用ワイヤー類。DESCRIPTION OF SYMBOLS 1 ... Hope head 2 ... Hoshiri 3 ... Slope 10 ... Construction equipment 11
A, 11B: Support, 12A, 12B: Winding machine, 1
3A, 13B ... towing wires.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 一色 弘 東京都千代田区九段北4丁目2番35号 ライト工業株式会社内 (72)発明者 青木 登 東京都千代田区九段北4丁目2番35号 ライト工業株式会社内 (56)参考文献 特開 平10−265179(JP,A) (58)調査した分野(Int.Cl.7,DB名) B66D 3/00 - 3/26 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Hiroshi Isshiki, Inventor 4-2-2, Kudankita, Chiyoda-ku, Tokyo Inside Light Industry Co., Ltd. (72) Noboru Aoki Inventor 4-35, 2-35, Kudankita, Chiyoda-ku, Tokyo (56) References JP-A-10-265179 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) B66D 3/00-3/26
Claims (6)
のうち少なくとも高さ方向に沿って、施工装置を移動さ
せながら法面に対して施工を行う設備において、前記施工装置は、アンカー孔またはロックボルト孔を削
孔する装置、あるいは吹付装置を搭載した基台を有し、 前記施工装置を通り法面の高さ方向に沿う昇降線を挟ん
で;法頭側に1対の支持体を固定して設け、法尻側に1
対の巻き上げ機を固定して設け、 前記施工装置と、支持体と、巻き上げ機とを牽引ワイヤ
ー類により繋ぎ、かつ前記支持体に設けた案内部に前記
牽引ワイヤー類を案内させて繋ぎ、この繋ぎ経路に動滑
車を介在させ、 前記各巻き上げ機の作動により前記牽引ワイヤー類の巻
取または巻戻しにより 前記施工装置を法面の高さ方向に
昇降させるように構成したことを特徴とする法面におけ
る施工設備。1. A facility for performing construction on a slope while moving the construction device along at least a height direction of a height direction and a horizontal direction on the slope, wherein the construction device includes an anchor hole or Cut the lock bolt hole
It has a base equipped with a device for drilling or a spraying device, with a lifting line along the height direction of the slope passing through the construction device; a pair of supports are fixedly provided on the slope head side, 1 at the bottom
Provided by fixing the pair of hoist, and the working device, a support and a hoist connecting the puller wire such, and connecting by guiding the traction wires such a guide portion provided on the support, the Glide along the connecting path
A vehicle is interposed, and the winding of the traction wires is performed by the operation of each of the hoists.
A construction facility on a slope, wherein the construction apparatus is configured to move up and down in the height direction of the slope by taking or unwinding .
のうち少なくとも高さ方向に沿って、施工装置を移動さ
せながら法面に対して施工を行う設備において、前記施工装置は、アンカー孔またはロックボルト孔を削
孔する装置、あるいは吹付装置を搭載した基台を有し、 前記施工装置を通り法面の高さ方向に沿う昇降線を挟ん
で;法頭側に1対の支持体を固定して設け、法尻側に1
対の巻き上げ機を固定して設け、 前記施工装置、支持体に設けた案内部、巻き上げ機を、
これらの順で牽引ワイヤー類により繋ぎ、この繋ぎ経路
に動滑車を介在させ、 前記各巻き上げ機の作動により前記牽引ワイヤー類の巻
取または巻戻しにより 前記施工装置を法面の高さ方向に
昇降させるように構成したことを特徴とする法面におけ
る施工設備。2. A facility for performing construction on a slope by moving the construction device along at least a height direction of a height direction and a horizontal direction on the slope, wherein the construction device includes an anchor hole or an anchor hole. Cut the lock bolt hole
It has a base equipped with a device for drilling or a spraying device, with a lifting line along the height direction of the slope passing through the construction device; a pair of supports are fixedly provided on the slope head side, 1 at the bottom
The pair of hoisting machines are fixedly provided, the construction device, the guide provided on the support, the hoisting machine,
In this order, connect with the traction wire, and this connection path
The pulley is interposed between the pulleys and the winding of the pulling wires is performed by the operation of each of the hoists.
A construction facility on a slope, wherein the construction apparatus is configured to move up and down in the height direction of the slope by taking or unwinding .
のうち少なくとも高さ方向に沿って、施工装置を移動さ
せながら法面に対して施工を行う設備において、前記施工装置は、アンカー孔またはロックボルト孔を削
孔する装置、あるいは吹付装置を搭載した基台を有し、 前記施工装置を通り法面の高さ方向に沿う昇降線を挟ん
で;法頭側に1対の支持体を固定して設け、法尻側に1
対の巻き上げ機を固定して設け、 前記支持体を一端部の固定点とし、施工装置に設けた案
内部、および支持体に設けた案内部を順に案内させて巻
き上げ機に牽引ワイヤー類を繋ぎ、前記各巻き上げ機の作動により前記牽引ワイヤー類の巻
取または巻戻しにより 前記施工装置を法面の高さ方向に
昇降させるように構成したことを特徴とする法面におけ
る施工設備。3. A facility for performing construction on a slope while moving the construction device along at least a height direction of a height direction and a horizontal direction on the slope, wherein the construction device includes an anchor hole or Cut the lock bolt hole
It has a base equipped with a device for drilling or a spraying device, with a lifting line along the height direction of the slope passing through the construction device; a pair of supports are fixedly provided on the slope head side, 1 at the bottom
A pair of winders are fixedly provided, and the support is used as a fixing point at one end, and the guides provided on the construction device and the guides provided on the support are sequentially guided to connect the pulling wires to the winders. , The winding of the pulling wires by the operation of each of the hoists.
A construction facility on a slope, wherein the construction apparatus is configured to move up and down in the height direction of the slope by taking or unwinding .
のうち少なくとも高さ方向に沿って、施工装置を移動さ
せながら法面に対して施工を行う設備において、前記施工装置は、アンカー孔またはロックボルト孔を削
孔する装置、あるいは吹付装置を搭載した基台を有し、 前記施工装置を通り法面の高さ方向に沿う昇降線を挟ん
で;法頭側に1対の支持体を固定して設け、法尻側に1
対の巻き上げ機を固定して設け、 前記施工装置を一端部の固定点とし、支持体に設けた第
1案内部、施工装置に設けた案内部、および支持体に設
けた第2案内部を順に案内させて巻き上げ機に牽引ワイ
ヤー類を繋ぎ、この繋ぎ経路に動滑車を介在させ、 前記各巻き上げ機の作動により前記牽引ワイヤー類の巻
取または巻戻しにより 前記施工装置を法面の高さ方向に
昇降させるように構成したことを特徴とする法面におけ
る施工設備。 4. A facility for performing construction on a slope while moving the construction device along at least a height direction of a height direction and a horizontal direction on the slope, wherein the construction device includes an anchor hole or Cut the lock bolt hole
It has a base equipped with a device for drilling or a spraying device, with a lifting line along the height direction of the slope passing through the construction device; a pair of supports are fixedly provided on the slope head side, 1 at the bottom
A pair of winding machines are fixedly provided, and the construction device is a fixing point at one end, and a first guide portion provided on the support, a guide portion provided on the construction device, and a second guide portion provided on the support are provided. The traction wires are connected to the hoist by being guided in order, and a moving pulley is interposed in this connection path, and the winding of the traction wires is performed by the operation of each of the hoists.
A construction facility on a slope, wherein the construction apparatus is configured to move up and down in the height direction of the slope by taking or unwinding .
のうち少なくとも高さ方向に沿って、施工装置を移動さ
せながら法面に対して施工を行う設備において、前記施工装置は、アンカー孔またはロックボルト孔を削
孔する装置、あるいは吹付装置を搭載した基台を有し、 前記施工装置を通り法面の高さ方向に沿う昇降線を挟ん
で;法頭側に少なくとも1対の支持体を固定して設け、
法尻側に1対の巻き上げ機を固定して設け、 前記施工装置を一端部の固定点とし、前記巻き上げ機を
他端部の固定点とし、これらを中間に動滑車を介在させ
て牽引ワイヤー類により連結し、各動滑車の軸は前記支
持体または施工装置に連結し、前記各巻き上げ機の作動により前記牽引ワイヤー類の巻
取または巻戻しにより 前記施工装置を法面の高さ方向に
昇降させるように構成したことを特徴とする法面におけ
る施工設備。 5. A facility for performing construction on a slope while moving the construction device along at least a height direction of a height direction and a horizontal direction on the slope, wherein the construction device includes an anchor hole or Cut the lock bolt hole
It has a base on which a device for punching or a spraying device is mounted, with a lifting line extending along the height direction of the slope passing through the construction device; at least one pair of supports is fixedly provided on the side of the slope ,
A pair of hoisting machines are fixedly provided on the side of the butt, the construction device is used as a fixing point at one end, the hoisting machine is used as a fixing point at the other end, and a pulley wire is interposed therebetween with a moving pulley interposed therebetween. And the shaft of each moving pulley is connected to the support or the construction device, and the operation of each of the hoists causes the winding of the pulling wires.
A construction facility on a slope, wherein the construction apparatus is configured to move up and down in the height direction of the slope by taking or unwinding .
のうち少なくとも高さ方向に沿って、施工装置を移動さ
せながら法面に対して施工を行う設備において、前記施工装置は、アンカー孔またはロックボルト孔を削
孔する装置、あるいは吹付装置を搭載した基台を有し、 前記施工装置を通り法面の高さ方向に沿う昇降線を挟ん
で;法頭側に少なくとも1対の支持体を固定して設け、
法尻側に1対の巻き上げ機を固定して設け、 前記支持体を一端部の固定点とし、前記巻き上げ機を他
端部の固定点とし、これらを中間に動滑車を介在させて
牽引ワイヤー類により連結し、各動滑車の軸は前記支持
体または施工装置に連結し、前記各巻き上げ機の作動により前記牽引ワイヤー類の巻
取または巻戻しにより 前記施工装置を法面の高さ方向に
昇降させるように構成したことを特徴とする法面におけ
る施工設備。 6. A facility for performing construction on a slope while moving the construction device along at least a height direction of the slope in a height direction and a horizontal direction, wherein the construction device includes an anchor hole or an anchor hole. Cut the lock bolt hole
It has a base on which a device for punching or a spraying device is mounted, with a lifting line extending along the height direction of the slope passing through the construction device; at least one pair of supports is fixedly provided on the side of the slope ,
A pair of hoisting machines are fixedly provided on the side of the butt, and the support is used as a fixing point at one end, and the hoisting machine is used as a fixing point at the other end. And the shaft of each moving pulley is connected to the support or the construction device, and the operation of each of the hoists causes the winding of the pulling wires.
A construction facility on a slope, wherein the construction apparatus is configured to move up and down in the height direction of the slope by taking or unwinding .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP07570998A JP3308488B2 (en) | 1998-03-24 | 1998-03-24 | Construction equipment on the slope |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP07570998A JP3308488B2 (en) | 1998-03-24 | 1998-03-24 | Construction equipment on the slope |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH11268888A JPH11268888A (en) | 1999-10-05 |
| JP3308488B2 true JP3308488B2 (en) | 2002-07-29 |
Family
ID=13584040
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP07570998A Expired - Fee Related JP3308488B2 (en) | 1998-03-24 | 1998-03-24 | Construction equipment on the slope |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3308488B2 (en) |
Families Citing this family (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4553884B2 (en) * | 2006-10-25 | 2010-09-29 | 俊仁 岡本 | Civil engineering work methods such as slopes |
| JP4121038B1 (en) * | 2007-04-10 | 2008-07-16 | 有限会社洋翔建設 | How to suspend an inclined work vehicle |
| JP4834870B2 (en) * | 2007-09-30 | 2011-12-14 | ノーベル技研工業株式会社 | Work vehicle for steep slopes |
| JP5901873B2 (en) * | 2010-06-21 | 2016-04-13 | 日工株式会社 | How to install a temporary scaffold for slopes |
| CN106423625A (en) * | 2016-12-01 | 2017-02-22 | 江苏杰成凯新材料科技有限公司 | Automatic control system for chemical spraying of high and steep slope |
| CN111851979A (en) * | 2020-08-20 | 2020-10-30 | 中国水利水电第四工程局有限公司 | A mobile operating system for road side slope bolt support |
| CN116142985A (en) * | 2022-12-07 | 2023-05-23 | 中铁二局集团有限公司 | A canyon lifting device and its installation and use method |
-
1998
- 1998-03-24 JP JP07570998A patent/JP3308488B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH11268888A (en) | 1999-10-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP2058265B1 (en) | Traveling crane and assembling/disassembling method thereof | |
| CN102471042B (en) | mobile crane | |
| US8640895B2 (en) | Drum tensioning method and apparatus for load hoist wire rope | |
| JP2004010354A (en) | Device for changing rigging of pulley block of crane | |
| KR101405010B1 (en) | Lifting Gantry for Girder Erection Works of Suspension Bridges | |
| JP3308488B2 (en) | Construction equipment on the slope | |
| EP1591406B1 (en) | Method and apparatus for changing the rope of a traction sheave elevator | |
| CN112566864B (en) | Application method of lift extension technology of elevator | |
| CN104340907A (en) | Hoisting and winching control device capable of preventing rope from messing and control method | |
| CN215756056U (en) | Wall connecting machine based on double-traction hoisting mechanism and double-traction hoisting mechanism | |
| JP3841616B2 (en) | Elevator main rope replacement method and apparatus | |
| JP3264889B2 (en) | Construction equipment and method on slope | |
| JP2018172189A (en) | Quay crane and method for controlling quay crane | |
| JP6825774B2 (en) | How to replace the unloader and its grab bucket | |
| JP3264888B2 (en) | Construction equipment and method on slope | |
| JP3238976B2 (en) | Jib removal device for jib boom | |
| JP3382720B2 (en) | Wire drawing method and wire drawing wheel device for wire drawing | |
| CN218540216U (en) | Structure for moving out felt tensioning roller under pressing part of paper machine | |
| KR20150023157A (en) | Block loader | |
| KR101464494B1 (en) | moving apparatus for machine room of elevator | |
| JP3320554B2 (en) | Incline hoisting device | |
| JPH07315740A (en) | How to carry out escalator truss | |
| CN210619910U (en) | A roof beam for towing formula construction elevator | |
| JPH06199492A (en) | Tension device of winding drum type winch | |
| JP2007070979A (en) | Drill head elevator |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080517 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090517 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100517 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110517 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110517 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120517 Year of fee payment: 10 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120517 Year of fee payment: 10 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130517 Year of fee payment: 11 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140517 Year of fee payment: 12 |
|
| LAPS | Cancellation because of no payment of annual fees |