JP3379014B2 - Push-up method and its device - Google Patents
Push-up method and its deviceInfo
- Publication number
- JP3379014B2 JP3379014B2 JP23051499A JP23051499A JP3379014B2 JP 3379014 B2 JP3379014 B2 JP 3379014B2 JP 23051499 A JP23051499 A JP 23051499A JP 23051499 A JP23051499 A JP 23051499A JP 3379014 B2 JP3379014 B2 JP 3379014B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- push
- tower
- guide
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title description 10
- 238000010276 construction Methods 0.000 claims description 8
- 230000008602 contraction Effects 0.000 claims description 7
- 229910000831 Steel Inorganic materials 0.000 description 10
- 239000010959 steel Substances 0.000 description 10
- 230000003014 reinforcing effect Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 208000019901 Anxiety disease Diseases 0.000 description 1
- 230000036506 anxiety Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、橋梁や建築構造物
等を吊り上げ扛重して建設する際のプッシュアップ工法
およびそのために使用される仮設支柱としての伸縮可能
なプッシュアップ装置に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a push-up construction method for constructing a bridge, a building structure or the like by hoisting and suspending it, and an extendable push-up device as a temporary column used for the push-up construction method.
【0002】[0002]
【従来の技術】橋梁や建築構造物等を建設する際の仮設
支柱としてのプッシュア装置すなわちベントとして、従
来から図8に示すようなものが一般に使用されていた。
図8(A)に示した従来型は最も多用されるもので、一
辺の長さが2m、高さが25m程度のベントを形成する
のに、トラッククレーン等を用いて柱部材や繋ぎ部材等
で各部品を組み立てながら積層するものである。図8
(B)に示したものはユニットブロックを積層していく
ものであるが、ユニットブロックを最下部から挿入して
油圧、スクリュージャッキ、ラック・ピニオンあるいは
ロープ操作にて積み上げていくものである。図8(C)
に示したテレスコープ型は、サイズを異にしたユニット
ブロックを油圧やロープ操作によって積層していくもの
である。図8(D)に示したパンタグラフ型は、四辺形
に設置されたリンクの形状を油圧操作によって変形さ
せ、パンタグラフ機能によって所定高さのベントを得る
ものである。図8(E)に示す脚立型は文字通り大型の
脚立を作業現場にて起立させるものである。2. Description of the Related Art As a push-up device, that is, a vent as a temporary support for constructing a bridge or a building structure, the one shown in FIG. 8 has been generally used.
The conventional type shown in FIG. 8 (A) is most often used, and a pillar member, a connecting member, etc. are formed by using a truck crane or the like to form a vent having a side length of 2 m and a height of about 25 m. The parts are stacked while being assembled. Figure 8
Although the unit block shown in (B) is formed by stacking unit blocks, the unit blocks are inserted from the lowermost part and stacked by hydraulic pressure, a screw jack, a rack and pinion, or a rope operation. FIG. 8 (C)
In the telescope type shown in, unit blocks of different sizes are stacked by hydraulic pressure or rope operation. In the pantograph type shown in FIG. 8D, the shape of the links installed in a quadrangle is deformed by hydraulic operation, and a vent having a predetermined height is obtained by the pantograph function. The stepladder shown in FIG. 8 (E) stands up a literally large stepladder at the work site.
【0003】ところが、このようなベントにあって、図
8(A)の従来型では柱部材や繋ぎ部材等の多数の部品
を現場にて組み付けていくために、建方や解体作業に時
間を要する(t当たり1.0〜1.5人工)他、数組の
部品を用意する必要から煩雑で部品の運搬性にも劣るも
のであった。また、図8(A)〜(E)のものではベン
トの装置自体あるいは使用状態への建方のためのジャッ
キ、クレーン等の揚重装置も大容量のものが必要であっ
た。特に、図8(B)、(C)のものについてはベント
をユニットブロック毎に分割してはいるものの、ユニッ
トブロック自体も比較的重量がありその積み上げには大
型の揚重装置を必要としていた。However, in such a vent, in the conventional type shown in FIG. 8 (A), many parts such as a pillar member and a connecting member are assembled on site, so that it takes time to construct and dismantle. In addition to the above (1.0 to 1.5 artificial per t), it is complicated and inferior in the transportability of the parts because it is necessary to prepare several sets of parts. In addition, in FIGS. 8 (A) to 8 (E), a lifting device such as a vent device itself or a jack, a crane or the like for constructing the device in a used state requires a large capacity. 8B and 8C, although the vent is divided for each unit block, the unit block itself is relatively heavy, and a large lifting device was required for stacking it. .
【0004】このため、本件出願人は、前記従来のベン
トにおける諸課題を解決して、作業現場での揚重装置に
よる組立作業が少なく、かつ小型の揚重装置にても高さ
を容易に調整しつつ組立が可能で、しかも軽量で作業性
に優れ、工期の短縮とコスト低減も図られるテレスコー
プ型ベントを提案した(特開平10−252285号公
報)。図9によってこのテレスコープ型ベントを簡単に
説明すると、建築構造物等の仮設支柱として使用される
テレスコープ型ベント21において側面に多数のピン孔
28・・・が所定間隔にて穿設された複数組の角形鋼管
21A、21B、21Cをサイズの大きな外側鋼管の中
に順次スライド可能に挿入すると共に、外側鋼管に設け
られた高さ調整ピンを内外鋼管のピン孔28に選択的に
挿入することによって内側鋼管の出し入れ長さを選定す
るように構成したことを特徴とするものである。Therefore, the applicant of the present invention has solved the above-mentioned problems in the conventional vent, and has less assembly work by the lifting device at the work site, and can easily increase the height even with a small lifting device. We proposed a telescope type vent that can be assembled while adjusting, is lightweight, has excellent workability, and can shorten the construction period and cost (Japanese Patent Laid-Open No. 10-252285). This telescope type vent will be briefly described with reference to FIG. 9. In the telescope type vent 21 used as a temporary support for a building structure or the like, a large number of pin holes 28 ... A plurality of sets of rectangular steel pipes 21A, 21B, 21C are sequentially slidably inserted into a large-sized outer steel pipe, and height adjusting pins provided on the outer steel pipe are selectively inserted into pin holes 28 of the inner and outer steel pipes. This is characterized in that the inner steel pipe is configured so as to select the length for taking in and out.
【0005】[0005]
【発明が解決しようとする課題】かくして、前記テレス
コープ型ベントは現場にて単に複数組の角形鋼管を順次
スライドするだけでよいので、揚重装置による組立作業
も格段に少なく、部品を紛失することも殆どなくなっ
た。しかしながら、このテレスコープ型ベントは構造物
である屋根等を載置したまま仮設支柱を押し上げるもの
ではなく、クレーン等を用いてテレスコープ式に組み込
まれた複数の鋼管を内側から順次抜き出して、予め所定
の高さに引き上げておくものであるため、屋根等の構造
物は仮設支柱であるテレスコープ型ベントと別途に組み
付ける必要があって、テレスコープ型ベント共々その扛
重組立には依然として比較的大型の揚重装置が必要であ
った。Thus, since the telescope type vent is required to simply slide a plurality of sets of rectangular steel pipes in sequence on site, the assembly work by the lifting device is remarkably small and parts are lost. Things are almost gone. However, this telescope type vent does not push up the temporary support pillar while the roof, which is a structure, is placed on it, and a plurality of steel pipes incorporated in the telescope type are sequentially extracted from the inside using a crane or the like, and Since it is to be raised to a predetermined height, it is necessary to assemble the structure such as the roof separately from the telescopic type vent which is a temporary support, and both the telescopic type vent and the telescopic type vent are still relatively difficult to assemble. A large lifting device was needed.
【0006】そこで、本発明では、前記本件出願人によ
るテレスコープ型ベントをさらに改良して、より小型の
簡便な吊上げ部材にても容易かつ確実に構造物共々伸縮
サポートを構築することができるプッシュアップ工法お
よびその装置を提供することを目的とする。Therefore, in the present invention, the telescope type vent by the applicant of the present invention is further improved so that a telescopic support for a structure can be easily and surely constructed even with a smaller and simple lifting member. An object is to provide an up-construction method and an apparatus therefor.
【0007】[0007]
【課題を解決するための手段】このため本発明は、地上
に構築された櫓状のガイドタワー内に配設された複数の
径の異なる管部材を嵌合してなる伸縮サポートの前記各
管部材を、ガイドタワー上に設置した吊上げ部材により
最外周の管部材から順次繰り出して吊り上げ、伸長位置
にて各管部材間をピン部材によって固定することによ
り、前記伸縮サポートの上部に固定した構造物を扛重す
るようにしたことを特徴とするものである。また本発明
は、地上に櫓状に構築されたガイドタワーと、該ガイド
タワー内に配設された複数の径の異なる管部材を嵌合し
てなり扛重すべき構造物を上部に固定する伸縮サポート
と、前記管部材を最外周のものから順次繰り出して吊り
上げるガイドタワー上に設置された吊上げ部材と、前記
各管部材の伸長位置での位置を固定すべくこれらの管部
材を連結するピン部材とから構成されたことを特徴とす
るものである。 また本発明は、前記吊上げ部材が、管
部材に固縛されガイドタワーにガイドされるガイドリン
グを介して管部材を吊り上げるように構成されたことを
特徴とするものである。また本発明は、前記吊上げ部材
が、ジャッキとワイヤあるいはロッドから構成されたこ
とを特徴とするものである。また本発明は、前記吊上げ
部材が、ウインチとワイヤおよび複数の滑車から構成さ
れたことを特徴とするもので、これらを課題解決のため
の手段とするものである。Therefore, according to the present invention, the above-mentioned respective tubes of the expansion support, which are formed by fitting a plurality of tube members having different diameters, which are arranged in a tower tower constructed on the ground. With the lifting member installed on the guide tower,
It is characterized in that the structure fixed on the upper part of the expansion support is weighed by sequentially feeding out from the outermost pipe member and lifting it, and fixing each pipe member at the extension position with a pin member. It is a thing. Further, according to the present invention, a guide tower constructed in a turret shape on the ground and a plurality of pipe members arranged in the guide tower and having different diameters are fitted to each other to fix a structure to be stacked on top. A telescopic support, a hoisting member installed on a guide tower for sequentially hoisting and hoisting the pipe members from the outermost one, and a pin connecting these pipe members so as to fix the positions of the pipe members at the extended position. And a member. Further, the present invention is characterized in that the hoisting member is configured to hoist the pipe member via a guide ring that is fixed to the pipe member and guided by the guide tower. Further, the present invention is characterized in that the lifting member comprises a jack and a wire or a rod. Further, the present invention is characterized in that the lifting member comprises a winch, a wire and a plurality of pulleys, and these are means for solving the problems.
【0008】[0008]
【実施の形態】以下、本発明の実施の形態を図面に基づ
いて説明する。図1〜図6は本発明のプッシュアップ工
法およびその装置の第1実施の形態を示すもので、図1
(A)は伸縮サポータの伸縮前後を示す要部の正面図、
図1(B)は伸縮サポータの伸長前の要部の正面図、図
2はガイドタワーの斜視図、図3(A)は管部材のピン
部材による固定状態を示す断面図、図3(B)はその正
面図、図4は構造物のプッシュアップ前後の正面図、図
5は構造物の平面図、図6は構造物のプッシュアップ工
程の正面図である。本発明のプッシュアップ工法および
その装置は橋梁や屋根等の建築構造物等を建設する際の
仮設のガイドタワーとして使用されるもので、図1に示
すように、地上Gに構築された櫓状のガイドタワー1内
に配設された複数の径の異なる管部材2A、2B、2C
を嵌合してなる伸縮サポート2の前記各管部材2A、2
B、2Cを、ガイドタワー1上に設置した吊上げ部材4
および7により順次繰り出して吊り上げ、伸長位置にて
各管部材2A、2B、2C間をピン部材19(図3)に
よって固定することにより、前記伸縮サポート2の上部
に固定した構造物3を扛重するようにしたことを特徴と
する。図1に例示したものでは、管部材として大きなサ
イズの外管サポート2A、中位のサイズの中管サポート
2Bおよび小さいサイズの内管サポート2Cの3種類の
角形鋼管が順次スライド可能に挿入されて伸縮サポート
2を構成しているが、伸縮サポート2を構成する管部材
の数および断面形状は適宜選定される。Embodiments of the present invention will be described below with reference to the drawings. 1 to 6 show a push-up method and a device therefor according to a first embodiment of the present invention.
(A) is a front view of a main part of the elastic supporter before and after expansion and contraction,
FIG. 1 (B) is a front view of a main part of the telescopic supporter before extension, FIG. 2 is a perspective view of a guide tower, FIG. 3 (A) is a cross-sectional view showing a state where a pipe member is fixed by a pin member, and FIG. ) Is its front view, FIG. 4 is a front view before and after push-up of the structure, FIG. 5 is a plan view of the structure, and FIG. 6 is a front view of the push-up process of the structure. INDUSTRIAL APPLICABILITY The push-up method and its apparatus of the present invention are used as a temporary guide tower when constructing building structures such as bridges and roofs, and as shown in FIG. Pipe members 2A, 2B, 2C having different diameters arranged in the guide tower 1
The tube members 2A, 2 of the expansion support 2 formed by fitting
Lifting member 4 in which B and 2C are installed on the guide tower 1.
And 7 in order to lift the structure, and fix the pipe members 2A, 2B and 2C between the pipe members 2A, 2B and 2C at the extended position by the pin member 19 (FIG. 3), so that the structure 3 fixed to the upper portion of the expansion support 2 is suspended. It is characterized by doing so. In the example illustrated in FIG. 1, three types of rectangular steel pipes, that is, a large-sized outer pipe support 2A, a medium-sized middle pipe support 2B, and a small-sized inner pipe support 2C are sequentially slidably inserted as pipe members. Although the expansion support 2 is configured, the number and sectional shape of the pipe members forming the expansion support 2 are appropriately selected.
【0009】図2はガイドタワーの斜視図であり、地上
に構築された4本脚の櫓状を呈して構成され、該ガイド
タワー1内にはほぼ中央部に鉛直方向に複数の径の異な
る管部材2A、2B、2Cを嵌合してなる伸縮サポート
2が配設されており、伸縮サポート2とガイドタワー1
の脚部との間には、伸縮サポート2を構成する各管部材
2A、2B、2Cに選択的に固縛されガイドタワー1の
脚部にガイドローラ12によってガイドされる上部ガイ
ドリング6および下部ガイドリング8が上下動自在に配
設される。ガイドタワー1の天板であるガイドフレーム
5上には一対のジャッキ4が対照的に設置され、該ジャ
ッキ4と前記ガイドリング6あるいは下部ガイドリング
8との間をワイヤあるいはロッド7によって連結して吊
上げ部材が構成される。図示の例では、図1(A)に示
すように、大きなサイズの外管サポート2Aを最初にプ
ッシュアップし、次に中位のサイズの中管サポート2
B、小さいサイズの内管サポート2Cと順次繰り出して
行く。 FIG. 2 is a perspective view of the guide tower, which is constructed in the shape of a four-legged turret constructed on the ground. Inside the guide tower 1, there are a plurality of vertically different diameters in a substantially central portion. An expansion support 2 formed by fitting the pipe members 2A, 2B, 2C is provided, and the expansion support 2 and the guide tower 1 are arranged.
The upper guide ring 6 and the lower part, which are selectively secured to the tube members 2A, 2B, 2C constituting the expansion support 2 and are guided by the guide rollers 12 to the leg portions of the guide tower 1, between the leg portions of The guide ring 8 is arranged so as to be vertically movable. A pair of jacks 4 are symmetrically installed on a guide frame 5 which is a top plate of the guide tower 1, and the jack 4 and the guide ring 6 or the lower guide ring 8 are connected by a wire or a rod 7. A lifting member is configured. In the illustrated example, as shown in FIG. 1 (A), a large-sized outer tube support 2A is first pushed up, and then a medium-sized middle tube support 2A.
B, sequentially feeding in <br/> row rather the inner tube support 2C of the small size.
【0010】図3に示すように、伸縮サポート2を構成
する各管部材2A、2B、2Cである角形鋼管の4つの
側面にはそれぞれ多数のピン孔15が穿設され、各ピン
孔15の周囲には補強板である補強部材18が添設され
る。また強度上許容されるなら、これらのピン孔15は
必ずしも各角形鋼管の4つの側面全てに設けられなくて
もよい。前記複数組の管部材2A、2B、2C間にはス
ライド金物兼用の隙間調整金物17が配置され、外側管
部材に対する内側管部材のスライドさせての出し入れが
円滑になされるとともに、自立する伸縮サポート2の横
揺れ等に伴う安全性や信頼性に不安を残さないように管
部材間の隙間を充填するように構成される。なお、スラ
イド金物兼用の隙間調整金物17は内側管部材の下部2
段に設けてあるが、段数は適宜必要に応じて選定され
る。かくして、図1(A)に示すように、ガイドタワー
1におけるガイドフレーム5上に設置した吊上げ部材
4、7およびガイドリング6、8により伸縮サポート2
を構成する各管部材2A、2B、2Cを順次繰り出して
吊り上げ(2A’、2B’の状態)、伸長位置にて各管
部材間をピン部材19を整合するピン孔15、15に挿
入することよって固定し、前記伸縮サポート2の上部に
固定した構造物3を扛重することができる。As shown in FIG. 3, a large number of pin holes 15 are formed on each of the four side surfaces of the rectangular steel pipe which is each of the pipe members 2A, 2B and 2C constituting the expansion support 2. A reinforcing member 18, which is a reinforcing plate, is attached to the periphery. If the strength allows, the pin holes 15 do not necessarily have to be provided on all four side surfaces of each rectangular steel pipe. A gap adjusting metal fitting 17 also serving as a slide metal fitting is arranged between the plurality of sets of pipe members 2A, 2B, 2C, so that the inner pipe member can be slid in and out of the outer pipe member, and the self-supporting expansion and contraction support is provided. It is configured to fill the gap between the pipe members so as not to leave anxiety about the safety and reliability associated with the rolling of the pipe 2. In addition, the gap adjusting hardware 17 that also serves as the slide hardware is the lower portion 2 of the inner pipe member.
Although the number of stages is provided, the number of stages is appropriately selected as necessary. Thus, as shown in FIG. 1 (A), the expansion support 2 is provided by the lifting members 4 and 7 and the guide rings 6 and 8 installed on the guide frame 5 in the guide tower 1.
The respective pipe members 2A, 2B, 2C constituting the above are sequentially drawn out and lifted up (state of 2A ', 2B'), and inserted into the pin holes 15, 15 for aligning the pin members 19 between the pipe members at the extended position. Therefore, the structure 3 fixed and fixed to the upper part of the expansion support 2 can be weighed.
【0011】図4は構造物のプッシュアップ前後の正面
図、図5は構造物の平面図であり、図6(A)に示すよ
うに、地上Gの構築すべき建築物の周囲位置には外側屋
根構造物9A、9Bが構築され、中央位置には仮設支柱
11によって仮設床板10が設置される。図6(B)に
示すように、該仮設床板10上にて例えば内側屋根構造
物3を構築した後、仮設床板10の両側位置に本発明に
なる伸縮サポート2を配設したガイドタワー1、1を構
築して、これら伸縮サポート2の上部に前記内側屋根構
造物3を固定する。次いで、伸縮サポート2における各
管部材を、ガイドタワー上に設置した吊上げ部材により
順次繰り出して吊り上げ、伸長位置にて各管部材間をピ
ン部材によって固定(手動でも電動による自動制御でも
よい)することにより、前記伸縮サポート2の上部に固
定した構造物である内側屋根構造物3を扛重して、外側
屋根構造物9A、9Bに整合させた状態にてこれらを連
結して屋根構造物が構築される。なお、前記内側屋根構
造物3と外側屋根構造物9A、9Bとは同時進行で構築
しても構わない。FIG. 4 is a front view of the structure before and after it is pushed up, and FIG. 5 is a plan view of the structure. As shown in FIG. The outer roof structures 9A and 9B are constructed, and a temporary floor board 10 is installed at a central position by a temporary pillar 11. As shown in FIG. 6 (B), after constructing, for example, the inner roof structure 3 on the temporary floor plate 10, the guide tower 1 in which the expansion support 2 according to the present invention is arranged on both sides of the temporary floor plate 10, 1 is built, and the inner roof structure 3 is fixed to the upper part of the expansion support 2. Next, each pipe member in the expansion support 2 is sequentially drawn out and lifted by a lifting member installed on the guide tower, and each pipe member is fixed by a pin member at the extension position (manually or automatically controlled automatically). Thus, the roof structure is constructed by stacking the inner roof structure 3 which is a structure fixed to the upper portion of the expansion support 2 and connecting the inner roof structure 3 with the outer roof structures 9A and 9B in a aligned state. To be done. The inner roof structure 3 and the outer roof structures 9A and 9B may be constructed simultaneously.
【0012】図7は本発明のプッシュアップ工法および
その装置の第2実施の形態を示すもので、本実施の形態
では、ガイドタワー1におけるガイドフレーム5上に設
置した吊上げ部材が、ウインチ13とワイヤ16および
複数の滑車14A、14B群、14C群から構成された
ことを特徴とするものである。吊上げ部材における滑車
14B群を下部ガイドリング8に固定し、ワイヤ16を
滑車14B群、14C群間に数度張設して、ウインチ1
3を小さな牽引力にて回動するだけで、ガイドリングを
介して伸縮サポート2における各管部材2A、2B、2
Cを順次繰り出して吊り上げることができる。FIG. 7 shows a second embodiment of the push-up method and the apparatus therefor according to the present invention. In this embodiment, the hoisting member installed on the guide frame 5 in the guide tower 1 is a winch 13 and a winch 13. The wire 16 and the plurality of pulleys 14A, 14B, and 14C are featured. The pulley 14B group of the hoisting member is fixed to the lower guide ring 8, and the wire 16 is stretched several times between the pulley 14B group and the 14C group, and the winch 1
3 is rotated by a small pulling force, and each pipe member 2A, 2B, 2 in the expansion support 2 is guided through the guide ring.
C can be sequentially paid out and lifted.
【0013】以上、本発明の各実施の形態について説明
してきたが、本発明の趣旨の範囲内で、管部材の形状、
組込段数、断面形状、ピン孔の形状、数、間隔、ピン部
材の形状およびその管部材への設置形態、ガイドタワー
の形式、ガイドタワーと伸縮サポートとの関連構成、ガ
イドリングの形状およびその管部材ないし吊上げ部材で
あるワイヤやロッドへの固縛ないし固定形態、伸縮サポ
ートと構造物との固定形態、ジャッキあるいはウインチ
等の形式、滑車の配設形態等については適宜採用が可能
である。While the respective embodiments of the present invention have been described above, the shape of the pipe member,
Number of built-in steps, cross-sectional shape, pin hole shape, number, spacing, pin member shape and its installation form on pipe member, guide tower type, related configuration of guide tower and expansion support, guide ring shape and its Appropriate adoption can be made for the form of securing or fixing to a wire or rod which is a pipe member or a lifting member, the form of fixing the expansion support and the structure, the form of jacks or winches, the form of arrangement of pulleys, and the like.
【0014】[0014]
【発明の効果】以上、詳細に説明してきたように本発明
によれば、地上に構築された櫓状のガイドタワー内に配
設された複数の径の異なる管部材を嵌合してなる伸縮サ
ポートの前記各管部材を、ガイドタワー上に設置した吊
上げ部材により最外周の管部材から順次繰り出して吊り
上げ、伸長位置にて各管部材間をピン部材によって固定
することにより、前記伸縮サポートの上部に固定した構
造物を扛重するようにしたので、外側の管部の内部に順
次径の小さな管部材が収納されていることにより、作業
現場への輸送の際には多くの容積を占めることがなく効
率的な搬送が可能であり、単純で軽量な複数の径の異な
る管部材のスライド作業のみがその作業工程の大部分を
占め、作業現場での揚重装置による組立作業が少なく、
かつガイドタワー上に設置したジャッキ等の吊上げ部材
である小型の揚重装置にても高さを容易に調整しつつ組
立が可能なため、作業性に優れて、大幅な工期の短縮と
コスト低減が可能となったプッシュアップ工法が実現で
きた。As described above in detail, according to the present invention, the expansion and contraction of a plurality of pipe members having different diameters arranged in a tower tower constructed on the ground are fitted. The respective pipe members of the support are sequentially extended from the outermost pipe member by a lifting member installed on the guide tower and lifted up, and fixed between the pipe members at the extended position by pin members, whereby the upper portion of the expansion support is expanded. Since the structure fixed to the upper part is weighed, the pipe parts with smaller diameters are housed inside the outer pipe part in sequence, so that it occupies a large volume when transported to the work site. There is no need for efficient transportation, only a simple and lightweight slide work of multiple pipe members with different diameters occupies most of the work process, less assembly work by the lifting device at the work site,
Moreover, even small lifting devices such as jacks and other lifting members installed on the guide tower can be assembled while adjusting the height easily, resulting in excellent workability and a drastic reduction in construction period and cost reduction. The push-up construction method that made it possible was realized.
【0015】また、地上に櫓状に構築されたガイドタワ
ーと、該ガイドタワー内に配設された複数の径の異なる
管部材を嵌合してなり扛重すべき構造物を上部に固定す
る伸縮サポートと、前記管部材を最外周のものから順次
繰り出して吊り上げるガイドタワー上に設置された吊上
げ部材と、前記各管部材の伸長位置での位置を固定すべ
くこれらの管部材を連結するピン部材とから構成された
ことにより、台車等を使用して継ぎ足しブロック等の機
材を持ち込む必要がなく、ガイドタワー内に配設された
伸縮サポートにおける各管部材を単に吊上げ部材により
順次繰り出して吊り上げるだけで構造物を扛重して構築
することができるので、作業効率が格段に向上して、構
造が簡単で設備コストが低廉で、仮設材として準備する
場合でも品数を増やす必要のない優れたプッシュアップ
装置が実現できた。さらに、前記吊上げ部材が、管部材
に固縛されガイドタワーにガイドされるガイドリングを
介して管部材を吊り上げるように構成されたことによ
り、伸縮サポートにおける各管部材をがたつくことなく
円滑に移動させることができることとなった。Further, a guide tower constructed in a turret shape on the ground and a plurality of pipe members arranged in the guide tower and having different diameters are fitted to each other to fix a structure to be stacked on top. A telescopic support, a hoisting member installed on a guide tower for sequentially hoisting and hoisting the pipe members from the outermost one, and a pin connecting these pipe members so as to fix the positions of the pipe members at the extended position. Since it is made up of members, it is not necessary to add equipment such as blocks by using a trolley, etc., and each pipe member in the expansion support arranged in the guide tower is simply extended by the lifting member and lifted in order. Since the structure can be constructed by stacking with, the work efficiency is significantly improved, the structure is simple and the equipment cost is low, and the number of items is increased even when preparing as temporary material. You do not need good push-up device can be realized. Further, since the lifting member is configured to lift the pipe member through the guide ring that is fixed to the pipe member and guided by the guide tower, the pipe members in the expansion support can be smoothly moved without rattling. It has become possible.
【0016】さらにまた、前記吊上げ部材が、ジャッキ
とワイヤあるいはロッドから構成された場合は、従来の
もののように大型クレーン等を使用せずとも、ありふれ
た通常の小型で安価なジャッキとワイヤあるいはロッド
にて吊上げ部材を構成することができるので、装置がよ
り低廉となる。また、前記吊上げ部材が、ウインチとワ
イヤおよび複数の滑車から構成された場合は、ウインチ
を小さな牽引力にて回動するだけで、伸縮サポートにお
ける各管部材を順次繰り出して吊り上げることができ
る。かくして、より小型の簡便な吊上げ部材にても容易
かつ確実に構造物共々伸縮サポートを構築することがで
きるプッシュアップ工法およびその装置が提供される。Furthermore, when the hoisting member is composed of a jack and a wire or a rod, it is common to use a small and inexpensive jack and wire or rod without using a large crane as in the conventional one. Since the hoisting member can be configured by, the device becomes less expensive. Further, when the hoisting member is composed of a winch, a wire and a plurality of pulleys, each tube member in the expansion support can be sequentially paid out and hoisted only by rotating the winch with a small pulling force. Thus, there is provided a push-up construction method and a device therefor capable of easily and reliably constructing a stretchable support together with a structure even with a smaller and simpler lifting member.
【図1】本発明のプッシュアップ工法およびその装置の
第1実施の形態を示すもので、図1(A)は伸縮サポー
タの伸縮前後を示す要部の正面図、図1(B)は伸縮サ
ポータの伸長前の要部の正面図である。1A and 1B show a first embodiment of a push-up method and a device therefor according to the present invention. FIG. 1A is a front view of a main part before and after expansion / contraction of an expansion / contraction supporter, and FIG. 1B is expansion / contraction. It is a front view of the principal part before extension of a supporter.
【図2】同、ガイドタワーの斜視図である。FIG. 2 is a perspective view of the guide tower of the same.
【図3】同、図3(A)は管部材のピン部材による固定
状態を示す断面図、図3(B)はその正面図である。FIG. 3 (A) is a sectional view showing a fixed state of a pipe member by a pin member, and FIG. 3 (B) is a front view thereof.
【図4】同、構造物のプッシュアップ前後の正面図であ
る。FIG. 4 is a front view of the structure before and after push-up.
【図5】同、構造物の平面図である。FIG. 5 is a plan view of the structure.
【図6】同、構造物のプッシュアップ工法による工程の
正面図である。FIG. 6 is a front view of a process of the structure according to the push-up method.
【図7】本発明のプッシュアップ工法およびその装置の
第2実施の形態を示すもので、ガイドタワーの斜視図で
ある。FIG. 7 is a perspective view of a guide tower showing a second embodiment of the push-up method and the apparatus therefor according to the present invention.
【図8】従来の各種ベントを例示した図である。FIG. 8 is a diagram illustrating various conventional vents.
【図9】本件出願人によるテレスコープ型ベントの提案
例を示す図である。FIG. 9 is a diagram showing a proposal example of a telescope type vent by the applicant of the present application.
1・・・ガイドタワー 2・・・伸縮サポート 2A・・・外管サポート(管部材) 2B・・・中管サポート(管部材) 2C・・・内管サポート(管部材) 3・・・内側屋根構造物(構造物) 4・・・ジャッキ(吊上げ部材) 5・・・ガイドフレーム 6・・・上部ガイドリング 7・・・ワイヤ、ロッド(吊上げ部材) 8・・・下部ガイドリング 9・・・外側屋根構造物 10・・・仮設床板 11・・・仮設支柱 12・・・ガイドローラ 13・・・ウインチ 14・・・滑車 15・・・ピン孔 16・・・ワイヤ 17・・・隙間調整金物 18・・・補強部材 19・・・ピン部材 1 ... Guide tower 2 ... Telescopic support 2A: Outer pipe support (pipe member) 2B: Middle pipe support (pipe member) 2C: Inner pipe support (pipe member) 3 ... Inner roof structure (structure) 4 jack (lifting member) 5: Guide frame 6 ... Upper guide ring 7: Wire, rod (lifting member) 8 ... Lower guide ring 9 ... Outer roof structure 10 ... Temporary floorboard 11 ... Temporary columns 12 ... Guide roller 13 ... winch 14 ... Pulley 15-pin hole 16 ... Wire 17 ... Gap adjustment hardware 18 ... Reinforcing member 19: Pin member
───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E04G 21/16 E04B 1/35 ─────────────────────────────────────────────────── ─── Continued Front Page (58) Fields surveyed (Int.Cl. 7 , DB name) E04G 21/16 E04B 1/35
Claims (5)
に配設された複数の径の異なる管部材を嵌合してなる伸
縮サポートの前記各管部材を、ガイドタワー上に設置し
た吊上げ部材により最外周の管部材から順次繰り出して
吊り上げ、伸長位置にて各管部材間をピン部材によって
固定することにより、前記伸縮サポートの上部に固定し
た構造物を扛重するようにしたことを特徴とするプッシ
ュアップ工法。1. A hoisting system in which each pipe member of an expansion and contraction support, which is formed by fitting a plurality of pipe members having different diameters and arranged in a tower tower constructed on the ground, is installed on the guide tower. It is characterized in that the structure fixed to the upper part of the expansion support is weighed by sequentially feeding out from the outermost pipe member by means of a member and lifting it, and fixing each pipe member at the extended position with a pin member. And push-up construction method.
と、該ガイドタワー内に配設された複数の径の異なる管
部材を嵌合してなり扛重すべき構造物を上部に固定する
伸縮サポートと、前記管部材を最外周のものから順次繰
り出して吊り上げるガイドタワー上に設置された吊上げ
部材と、前記各管部材の伸長位置での位置を固定すべく
これらの管部材を連結するピン部材とから構成されたこ
とを特徴とするプッシュアップ装置。2. A structure, which is formed by fitting a guide tower constructed in the shape of a turret on the ground and a plurality of pipe members arranged in the guide tower and having different diameters, is fixed to the upper part. A telescopic support, a hoisting member installed on a guide tower for sequentially hoisting and hoisting the pipe members from the outermost one, and a pin connecting these pipe members so as to fix the positions of the pipe members at the extended position. A push-up device comprising: a member.
イドタワーにガイドされるガイドリングを介して管部材
を吊り上げるように構成されたことを特徴とする請求項
2に記載のプッシュアップ装置。3. The push-up device according to claim 2, wherein the lifting member is configured to lift the pipe member via a guide ring that is fixed to the pipe member and guided by the guide tower. .
るいはロッドから構成されたことを特徴とする請求項2
または3に記載のプッシュアップ装置。4. The lifting member comprises a jack and a wire or a rod.
Or the push-up device described in 3.
よび複数の滑車から構成されたことを特徴とする請求項
2または3に記載のプッシュアップ装置。5. The push-up device according to claim 2, wherein the lifting member includes a winch, a wire, and a plurality of pulleys.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP23051499A JP3379014B2 (en) | 1999-08-17 | 1999-08-17 | Push-up method and its device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP23051499A JP3379014B2 (en) | 1999-08-17 | 1999-08-17 | Push-up method and its device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2001055834A JP2001055834A (en) | 2001-02-27 |
| JP3379014B2 true JP3379014B2 (en) | 2003-02-17 |
Family
ID=16908955
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP23051499A Expired - Fee Related JP3379014B2 (en) | 1999-08-17 | 1999-08-17 | Push-up method and its device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3379014B2 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105220769A (en) * | 2014-06-24 | 2016-01-06 | 中国二十冶集团有限公司 | Large area bolt-ball net frame integral top lifting construction method |
| CN111677296A (en) * | 2020-05-29 | 2020-09-18 | 中冶(上海)钢结构科技有限公司 | High-altitude sliding and self-unloading method of large-span crane beam |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5528498B2 (en) * | 2012-05-10 | 2014-06-25 | 太平電業株式会社 | Heavy lifting device |
| CN105507168A (en) * | 2015-12-30 | 2016-04-20 | 中交第三航务工程局有限公司 | Multi-span box girder integral ultrahigh alternate jacking construction system and method |
| CN107345452B (en) * | 2017-06-30 | 2020-01-21 | 中国核工业第五建设有限公司 | Nuclear power station steel containment vessel top head assembling support |
| CN109098091A (en) * | 2018-09-03 | 2018-12-28 | 武汉冶钢结构有限责任公司 | The method that steel structure bridge general assembly moulding bed elevation data can be corrected |
| CN114250689B (en) * | 2021-12-21 | 2023-06-27 | 中交三公局第三工程有限公司 | Construction method for steel arch bridge inclined steel box arch-superposed arch rib |
-
1999
- 1999-08-17 JP JP23051499A patent/JP3379014B2/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105220769A (en) * | 2014-06-24 | 2016-01-06 | 中国二十冶集团有限公司 | Large area bolt-ball net frame integral top lifting construction method |
| CN105220769B (en) * | 2014-06-24 | 2017-06-30 | 中国二十冶集团有限公司 | Large area bolt-ball net frame integral top lifting construction method |
| CN111677296A (en) * | 2020-05-29 | 2020-09-18 | 中冶(上海)钢结构科技有限公司 | High-altitude sliding and self-unloading method of large-span crane beam |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2001055834A (en) | 2001-02-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US10012005B2 (en) | Crane system incorporated into a tower | |
| KR102059105B1 (en) | Tower crane with multistage stacked mast | |
| US3761551A (en) | Method of constructing concrete chimneys | |
| JP2009073599A (en) | Tower crane support structure and climbing method | |
| JP3379014B2 (en) | Push-up method and its device | |
| JP7475345B2 (en) | Crane, crane assembly method, and crane disassembly method | |
| US6430892B1 (en) | Apparatus and method for building a domed structure | |
| EP3375747A1 (en) | Tower crane | |
| JP3220397B2 (en) | Elevating scaffold | |
| JP3532161B2 (en) | Tower construction machine and tower construction method | |
| JP6228774B2 (en) | Wind generator construction method | |
| KR100586843B1 (en) | Lift-up construction method of roof membrane structure and roof membrane structure | |
| JP2704446B2 (en) | Lift-up method using temporary columns | |
| JP3073371B2 (en) | Tower-like structure erection method and equipment | |
| JP5902513B2 (en) | Construction device | |
| JP7127113B2 (en) | A crane, a method for assembling a crane, and a method for disassembling a crane | |
| JP3021199B2 (en) | Construction method of chimney inner cylinder and pull jack up device for the construction | |
| KR102071625B1 (en) | Climbing crane apparatus for transmission tower construction | |
| JP3070438B2 (en) | Temporary frame equipment for construction | |
| JPH10252285A (en) | Telescopic vent | |
| JPH1095594A (en) | Saya pipe jack for building construction and multi-story building construction method using the same | |
| JPS6035512B2 (en) | Erection equipment for tower-like structures | |
| JPS5986593A (en) | Crane for building | |
| JP2767365B2 (en) | Construction method of roof structure | |
| JPH06280395A (en) | Jack-up building constructing apparatus |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |