JP3389006B2 - Earthwork volume control device - Google Patents
[go: Go Back, main page]

JP3389006B2 - Earthwork volume control device - Google Patents

Earthwork volume control device

Info

Publication number
JP3389006B2
JP3389006B2 JP16420696A JP16420696A JP3389006B2 JP 3389006 B2 JP3389006 B2 JP 3389006B2 JP 16420696 A JP16420696 A JP 16420696A JP 16420696 A JP16420696 A JP 16420696A JP 3389006 B2 JP3389006 B2 JP 3389006B2
Authority
JP
Japan
Prior art keywords
line
triangle
designated
tin
processing means
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP16420696A
Other languages
Japanese (ja)
Other versions
JPH109857A (en
Inventor
裕喜 木村
規仁 川合
則宏 酒井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP16420696A priority Critical patent/JP3389006B2/en
Publication of JPH109857A publication Critical patent/JPH109857A/en
Application granted granted Critical
Publication of JP3389006B2 publication Critical patent/JP3389006B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)
  • Processing Or Creating Images (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、TIN(Triangul
ated Irregular Network)処理を、より現状の地形にマ
ッチするように制御するようにした土工量管理装置に関
するものである。
TECHNICAL FIELD The present invention relates to TIN (Triangul).
ed Irregular Network) processing, which is related to the earthwork management device that is controlled so as to better match the current topography.

【0002】[0002]

【従来の技術】従来、地形データをデータ処理してディ
スプレーに表示する方法として、TIN処理を行うよう
にした装置が提案されている。
2. Description of the Related Art Hitherto, as a method of processing terrain data and displaying it on a display, an apparatus for performing TIN processing has been proposed.

【0003】これは、測地装置で実際の地形を測地する
ことにより得た測地点の標高及び座標位置を地形データ
として取込み、この地形データ中の上記測地点を、平面
上にプロットし、このプロットした各点を、三角形の頂
点として、三角メッシュを描いて表現するようにしたも
のである。
This is to take in the altitude and coordinate position of a survey point obtained by geodetic actual terrain with a geodetic device as terrain data, plot the survey point in the terrain data on a plane, and plot this Each point is represented as a triangular mesh by drawing a triangular mesh.

【0004】上記三角形の各頂点は、Z値情報を持った
3次元データであるため、ランダムな地形を表現でき
る。このようにして、TIN処理により得られる三角メ
ッシュデータは、断面法にもとづく画像処理又はメッシ
ュ法(点高法)にもとづく画像処理の基本となるので、
この三角メッシュデータを用いて断面法にもとづき地形
を表示したり、メッシュ法にもとづき地形を表示したり
できる。
Since each vertex of the above triangle is three-dimensional data having Z value information, it is possible to represent a random topography. In this way, the triangular mesh data obtained by the TIN processing becomes the basis of the image processing based on the cross-sectional method or the mesh method (point height method).
By using this triangular mesh data, it is possible to display the terrain based on the cross-section method or display the terrain based on the mesh method.

【0005】メッシュ法の概要は、図2に示すように2
次元座標上で、所定間隔の位置座標に設けられた多数の
格子点mを有するメッシュAを設け、上記格子点m毎の
作業対象物又は作業対象地の標高の測地結果をもとに作
業対象物又は作業対象地を図3に示すようにグラフィッ
ク表示するものである。
The outline of the mesh method is as shown in FIG.
A mesh A having a large number of grid points m provided at position coordinates at predetermined intervals on a dimensional coordinate is provided, and a work object is obtained based on the geodetic result of the work object or the work target site for each grid point m. The object or the work site is displayed graphically as shown in FIG.

【0006】断面法については、メッシュ法と同様に線
形補完法的な考え方で,土量の切り,盛り,工事進捗,
工事前後の数量の割出しが行え、メッシュ法と同様に
2.5次元的な考え方で、2次元の形状を得ることがで
きる。
As for the cross-section method, similar to the mesh method, the concept of linear complementation method is used to cut and pile up the soil volume, construction progress,
The quantity before and after construction can be indexed, and a two-dimensional shape can be obtained with the 2.5-dimensional concept as in the mesh method.

【0007】断面法の概略は、被測定地の、前,後の断
面積を足して、2で割って前,後の断面の距離を剰算し
てボリウム(体積)を算出するものである。
The outline of the cross-section method is to calculate the volume (volume) by adding the front and rear cross-sectional areas of the measured site and dividing by 2 to add up the distances of the front and rear cross-sections. .

【0008】このように、TIN処理にもとづく三角メ
ッシュデータは、断面法の計算にもとづく地形表示、あ
るいはメッシュ法にもとづく地形表示にとって基本デー
タとなるものであり、これ等の表示が、実際ないしは設
計の地形と正確に整合するためには、TIN処理が正確
に実行されることが肝要である。
As described above, the triangular mesh data based on the TIN processing is the basic data for the terrain display based on the calculation of the sectional method or the terrain display based on the mesh method, and these displays are actually or designed. It is essential that the TIN process is executed accurately in order to accurately match the terrain.

【0009】[0009]

【発明が解決しようとする課題】しかし、従来は図4に
示すように外形線Mで囲まれる領域内を測地した場合
に、その測地した結果として得られた測地点としての各
点aが図4に示すように分布している場合(通常はこの
ように間隔がランダムに分布)において、TIN処理を
施すと、最外周側に位置する外周点a1は、図5に示す
ように測地領域の外形線Mに沿う辺(線)E1で結ばれ
るべきであるにも拘わらず、図6に示すように、外周点
a1が、内周点a2と結ばれて、外形線Mに沿わない辺
(線)E2が形成されて、実際とはかけ離れたTIN処
理が実行されることがあった。
However, conventionally, when the area surrounded by the outline M is geodesiced as shown in FIG. 4, each point a as a geodetic point obtained as a result of the geodesic is shown in FIG. 4 (normally, the intervals are randomly distributed in this way), when TIN processing is performed, the outer peripheral points a1 located on the outermost peripheral side are located in the geodetic area as shown in FIG. Although it should be connected by the side (line) E1 along the outer shape line M, as shown in FIG. 6, the outer peripheral point a1 is connected to the inner peripheral point a2 and the side (line) which does not follow the outer shape line M ( (Line) E2 was formed, and a TIN process far from the actual case was executed.

【0010】すなわち、外周点a1は測地領域の外形線
Mの決定要因であるにも拘わらず、TIN処理では、優
先的に最短にある点を頂点とする三角形を描くように辺
を決定するという条件があるために、この条件に従って
処理がなされた場合、実際の外形線Mとはかけ離れた辺
E2が設定されてしまう不都合があった。
That is, although the outer peripheral point a1 is a determining factor of the outline M of the geodesic area, the TIN processing preferentially determines the sides so as to draw a triangle with the shortest point as the vertex. Since there is a condition, when processing is performed according to this condition, there is an inconvenience that a side E2 that is far from the actual contour line M is set.

【0011】また、図7に示すように実際の測地領域中
に、測地のために立入ることができないような残存緑地
G、すなわちTIN処理排除領域が存在するにも拘わら
ず、そのままTIN処理を施すと、この残存緑地Gをま
たぐような辺E3が設定されて、実情にそぐわないTI
N処理が実施されてしまうこともあった。このようなT
IN処理は、前述の場合と同様に、TIN処理が、最短
位置にある点a,a間を結ぶように条件設定されている
からである。
Further, as shown in FIG. 7, the TIN process is performed as it is even though there is a residual green area G, that is, a TIN processing exclusion area, which cannot be entered due to the geodetic area in the actual geodetic area. When applied, a side E3 that straddles this residual green space G is set, and TI that does not match the actual situation
In some cases, N treatment was carried out. Such T
This is because in the IN process, as in the case described above, the TIN process is conditionally set so as to connect the points a and a at the shortest position.

【0012】また、従来のものにおいては、図8に示す
ように測地領域の尾根線Sや谷線Tが存在する場合に、
図9に示すようにTIN処理したとき尾根線Sや谷線T
に沿うように三角形の各辺E5,E6が描かれるべきで
あるが、そのままTIN処理を施すと、図10に示すよ
うに尾根線Sや谷線Tをまたぐような辺E5,E6が設
定され、尾根線S,谷線Tが三角形の面で埋められてし
まうので、実情にそぐわないTIN処理が実施されてし
まう。
Further, in the conventional case, as shown in FIG. 8, when the ridge line S and the valley line T of the geodetic region are present,
As shown in FIG. 9, when the TIN process is performed, the ridge line S and the valley line T
The respective sides E5, E6 of the triangle should be drawn along the line, but if the TIN process is performed as it is, the sides E5, E6 that cross the ridge line S and the valley line T are set as shown in FIG. Since the ridge line S and the valley line T are filled with the triangular surface, the TIN processing that does not fit the actual situation is performed.

【0013】この発明は、上記課題を解決するためにな
されたもので、残存緑地G内ではTIN処理を行わない
ようにし、また、外形線,尾根線,谷線をまたぐような
三角形が設定されないようするとともに、傾斜地に対し
て平坦地を意味する三角形が設定されないようにして、
実際の地形により近いTIN処理が実行されるようにす
るものである。
The present invention has been made in order to solve the above-mentioned problems. TIN processing is not performed in the remaining green space G, and a triangle that straddles the outline, ridge line, and valley line is not set. At the same time, make sure that a triangle that means a flat ground is not set for the sloping ground,
The TIN processing closer to the actual topography is executed.

【0014】[0014]

【課題を解決するための手段】この請求項1に係る発明
では、指定された残存緑地G内では辺を描かないように
TIN処理手段5を制御する残存緑地処理手段6を備え
た。
The invention according to claim 1 is provided with the remaining green area processing means 6 for controlling the TIN processing means 5 so that no side is drawn in the designated remaining green area G.

【0015】第2の発明では、測量領域の外形線に対応
する指定線にもとづき、この指定線に三角形の辺が沿う
ように制御する辺定義手段7を設けた。
In the second aspect of the invention, the side defining means 7 is provided for controlling the specified side corresponding to the outline of the survey area so that the side of the triangle is along the specified line.

【0016】第3の発明では、指定された尾根線,谷線
等の指定線にもとづき、この指定線に三角形の辺が沿う
とともに、この指定線を境として背中合せの三角形が形
成されるようにTIN処理手段5を制御する辺定義手段
7を設けた。
According to the third aspect of the invention, based on a designated line such as a designated ridge line or valley line, a side of a triangle follows the designated line, and a back-to-back triangle is formed with the designated line as a boundary. The edge defining means 7 for controlling the TIN processing means 5 is provided.

【0017】[0017]

【発明の実施の形態】DETAILED DESCRIPTION OF THE INVENTION

実施の形態1.図1は本発明による土工量管理装置の一
実施の形態を示すブロック図であり、同図において、1
はキーボード,マウス等の入力手段であり、工事地形デ
ータ,工事図面データ,工事仕様データ等が入力され
る。また、この入力手段1には地形の測地点の標高,国
家座標等の座標位置も地形データとして入力される。
Embodiment 1. FIG. 1 is a block diagram showing an embodiment of the earthwork amount management apparatus according to the present invention. In FIG.
Is an input means such as a keyboard and a mouse, and is used for inputting construction landform data, construction drawing data, construction specification data, and the like. In addition, the altitude of the topographical measurement point, the coordinate position such as the national coordinates, etc. are also input to the input means 1 as topographical data.

【0018】入力手段1からの地形データ等の出力2は
データ処理手段3に入力され、これで処理されてディス
プレー4には出力2にもとづく処理結果が表示される。
The output 2 such as topographical data from the input means 1 is input to the data processing means 3 and processed by the data processing means 3 to display the processing result based on the output 2 on the display 4.

【0019】上記データ処理手段3にはTIN処理手段
5が設けられており、このTIN処理手段5は、測地点
間を頂点とする三角形を描くことにより、地形を三角メ
ッシュで表現する。上記三角メッシュは平面的にランダ
ムな測地データを元に構築した三次元地形モデルである
といえ、断面法はこの三角メッシュから任意断面を切り
出す機能を用いて、その断面線上のセンターからの距離
と標高値を求めるもので、またメッシュ法(点高法)も
同様に三角メッシュから任意点の標高値を求める機能を
用いて、その格子点の標高値を求めるものである。
The data processing means 3 is provided with a TIN processing means 5, and the TIN processing means 5 draws a triangle having vertices between the measurement points to express the terrain with a triangular mesh. It can be said that the triangular mesh is a three-dimensional terrain model constructed based on two-dimensional random geodetic data, and the cross-section method uses the function of cutting out an arbitrary cross-section from this triangular mesh, and the distance from the center on the cross-section line The elevation value is obtained, and the mesh method (point elevation method) similarly obtains the elevation value of the grid point by using the function of obtaining the elevation value of an arbitrary point from the triangular mesh.

【0020】従って、上記TIN処理手段5で求めた三
角メッシュにもとづいて、断面法,メッシュ法の処理を
施すことにより、ディスプレー4に断面法又はメッシュ
法の処理に従う表示を行わせることができる。
Therefore, the display 4 can be displayed according to the processing of the cross section method or the mesh method by performing the processing of the cross section method and the mesh method based on the triangular mesh obtained by the TIN processing means 5.

【0021】6は残存緑地処理手段であり、図7に示す
如く、残存緑地G内ではTIN処理を実行しないように
するもので、三角メッシュの三角形の辺を、上記残存緑
地Gの区画線Pに沿って設定するようにし、他の2辺は
残存緑地G内には踏み込まないようにする。上記区画線
Pはキーボード,マウス等の操作にもとづくカーソルの
移動軌跡でディスプレー4上に表現される。
Reference numeral 6 denotes a residual green area processing means, which does not execute the TIN processing in the residual green area G, as shown in FIG. 7. The triangle side of the triangular mesh is a division line P of the residual green area G. And the other two sides are prevented from stepping into the remaining green space G. The partition line P is represented on the display 4 by a moving path of a cursor based on an operation of a keyboard, a mouse or the like.

【0022】7は辺定義手段であり、第1辺定義手段7
aと第2辺定義手段7bとから成り、キーボード,マウ
ス等の操作にもとづくカーソルの移動軌跡でディスプレ
ー4上に表現される指定線に沿う如く、三角メッシュの
辺を設定するとともに、上記指定線を背中合せとする三
角形を形成するようにTIN処理手段5を制御する。
Reference numeral 7 is an edge defining means, which is a first edge defining means 7.
a and the second side defining means 7b, the side of the triangular mesh is set along the designated line represented on the display 4 by the movement path of the cursor based on the operation of the keyboard, mouse, etc., and the designated line is also set. The TIN processing means 5 is controlled so as to form a triangle with back to back.

【0023】以上の構成において、動作を説明すると次
のとおりである。まず、図7において、残存緑地Gの外
形を区画する区画線Pを図面等から読取って、この区画
線Pにほぼ沿うように、カーソルを移動して行き、適当
なポイントbでクリックしてディスプレー4上に、ポイ
ントbを結ぶような区画線Pを描くように操作する。こ
れで、区画線Pに近い線又は合致する線が指定される
と、残存緑地処理手段6では、このようにして指定され
た指定線内の残存緑地領域G中ではTIN処理を行わな
いように、すなわち三角形の辺E3が設定されないよう
にする。この場合、辺E3がこの指定線に沿うようにT
IN処理手段6を制御する。
The operation of the above configuration will be described below. First, in FIG. 7, the division line P that divides the outer shape of the remaining green space G is read from the drawing or the like, the cursor is moved so as to be substantially along the division line P, and the display is clicked at an appropriate point b. An operation is performed so that a division line P that connects the points b is drawn on 4. Thus, when a line close to the comparting line P or a matching line is designated, the residual green area processing means 6 does not perform the TIN processing in the residual green area G within the designated line thus specified. , That is, the side E3 of the triangle is not set. In this case, the edge E3 is T so that it follows this designated line.
The IN processing means 6 is controlled.

【0024】これにより、残存緑地G中には三角メッシ
ュが形成されることはなく、三角メッシュの空白領域が
残されることになり、測地の実情に沿うTIN処理がな
される。
As a result, the triangular mesh is not formed in the remaining green area G, and the blank area of the triangular mesh is left, so that the TIN processing is performed according to the actual situation of the geodetic survey.

【0025】また、図6において、測地領域の外形線M
を図面等から読取って、この外形線Mにほぼ沿うよう
に、カーソルを移動して行き、適当なポイントbでクリ
ックしてディスプレー4上にポイントbを結ぶ外形線M
を描くように操作する。
Further, in FIG. 6, the contour line M of the geodetic area
Is read from the drawing or the like, the cursor is moved so as to substantially follow the outline M, and the outline M connecting the point b on the display 4 by clicking at an appropriate point b is clicked.
To draw.

【0026】これで、外形線Mに近い線又は合致する線
が指定されると、第1辺定義手段7aでは、このように
して指定された線に沿うように、三角形の辺E2,E2
を設定する。
Thus, when a line close to the contour line M or a matching line is designated, the first side defining means 7a causes the sides E2, E2 of the triangle to follow the line designated in this way.
To set.

【0027】これにより、図5に示すように外形線Mに
沿うように設定された辺E1を有する三角形が形成され
ることになり、地形の実情に沿う三角メッシュが形成さ
れる。
As a result, as shown in FIG. 5, a triangle having the side E1 set along the outline M is formed, and a triangular mesh is formed in accordance with the actual condition of the terrain.

【0028】さらに、図10において、尾根線S,谷線
Tを図面等から読取って、この尾根線S,谷線Tにほぼ
沿うように、カーソルを移動して行き、適当なポイント
bでクリックしてディスプレー4上に、ポイントbを結
ぶ尾根線S,谷線Tを描くように操作する。
Further, in FIG. 10, the ridge line S and the valley line T are read from the drawing or the like, the cursor is moved so as to be substantially along the ridge line S and the valley line T, and clicked at an appropriate point b. Then, the ridge line S and the valley line T connecting the points b are drawn on the display 4.

【0029】これで、尾根線S,谷線Tに近い線又は合
致する線が指定されると、第2辺定義手段7bでは、こ
のようにして指定された線に沿うように、三角形の辺E
5,E6を設定する。この場合、第2辺定義手段7bに
は尾根線S,谷線Tであることが入力されるので、この
入力にもとづき、尾根線S,谷線Tを境として背中合せ
となるような三角形が設定されるように制御するので、
三角メッシュは図9に示すようになり、尾根線S,谷線
Tをまたぐような三角形が設定されてしまうことはなく
なる。すなわち、尾根線,谷線が平坦な面に設定されて
しまうことはなくなる。
When a line close to the ridge line S or the valley line T or a matching line is designated, the second side defining means 7b causes the sides of the triangle to follow the designated lines. E
Set 5 and E6. In this case, since the ridge line S and the valley line T are input to the second side defining means 7b, based on this input, the triangles that are back to back with the ridge line S and the valley line T as boundaries are set. Control so that
The triangular mesh is as shown in FIG. 9, and a triangle that straddles the ridge line S and the valley line T will not be set. That is, the ridge line and the valley line are not set on a flat surface.

【0030】以上は、三角形の一辺を外形線M,尾根線
S,谷線Tに沿うように設定するとして説明したが、こ
のような各線に限らず他の指示線、例えば、三角形の一
辺を地形の等高線に沿うように設定することも、本発明
に含まれる。
In the above description, one side of the triangle is set so as to be along the contour line M, the ridge line S, and the valley line T. However, the present invention is not limited to such lines, and other indicator lines, for example, one side of the triangle. Setting along the contour lines of the terrain is also included in the present invention.

【0031】本発明では、外形線M等の指定線は、カー
ソルで入力することに限定されず、タッチペンで入力可
能としてもよい。また、測地点を結ぶ辺(線)で形成さ
れる三角形は、できるだけ正三角形に近くなるように設
定される。つまり、正角形を描くような頂点に近い測地
点が選択して、辺で結ばれる。
In the present invention, the designated line such as the outline M is not limited to being input by the cursor, and may be input by the touch pen. The triangle formed by the sides (lines) connecting the measurement points is set as close to an equilateral triangle as possible. In other words, the measurement points near the vertices that draw a regular polygon are selected and connected by edges.

【0032】[0032]

【発明の効果】以上説明したように、この請求項1に係
る発明では、指定された残存緑地G内では辺を描かない
ようにTIN処理手段5を制御する残存緑地処理手段6
を備えた。このために、残存緑地内に三角メッシュの空
白領域を残すことができるので、測地の実情にマッチし
た三角メッシュを形成できる。
As described above, in the invention according to claim 1, the remaining green area processing means 6 for controlling the TIN processing means 5 so that no side is drawn in the designated remaining green area G.
Equipped with. For this reason, since a blank area of the triangular mesh can be left in the remaining green space, it is possible to form the triangular mesh that matches the actual situation of the geodetic.

【0033】第2の発明では、指定線にもとづき、この
指定線に三角形の辺が沿うように制御する辺定義手段7
を設けた。このために、外形線に合うように三角メッシ
ュの外形を設定できる。
In the second invention, the side defining means 7 is controlled based on the designated line so that the side of the triangle is along the designated line.
Was set up. For this reason, the outer shape of the triangular mesh can be set so as to match the outer shape line.

【0034】第3の発明では、指定された尾根線,谷線
等の指定線にもとづき、この指定線に三角形の辺が沿う
とともに、この指定線を境として背中合せの三角形が形
成されるようにTIN処理手段5を制御する辺定義手段
7を設けた。このために、尾根線,谷線の所が平坦な面
として設定されることがなくなる。
According to the third aspect of the invention, based on a designated line such as a designated ridge line or valley line, a triangle side is formed along the designated line, and a back-to-back triangle is formed with the designated line as a boundary. The edge defining means 7 for controlling the TIN processing means 5 is provided. Therefore, the ridge line and the valley line are not set as flat surfaces.

【図面の簡単な説明】[Brief description of drawings]

【図1】 この発明の土工量管理装置の一実施の形態を
示すブロック図。
FIG. 1 is a block diagram showing an embodiment of an earthwork amount management apparatus of the present invention.

【図2】 メッシュ法の一例を示す平面図。FIG. 2 is a plan view showing an example of a mesh method.

【図3】 メッシュ法の一例を示す斜視図。FIG. 3 is a perspective view showing an example of a mesh method.

【図4】 この発明及び従来の説明をするための平面
図。
FIG. 4 is a plan view for explaining the present invention and the related art.

【図5】 この発明及び従来の説明をするための平面
図。
FIG. 5 is a plan view for explaining the present invention and the related art.

【図6】 この発明及び従来の説明をするための平面
図。
FIG. 6 is a plan view for explaining the present invention and the related art.

【図7】 この発明及び従来の説明をするための平面
図。
FIG. 7 is a plan view for explaining the present invention and the related art.

【図8】 この発明及び従来の説明をするための斜視
図。
FIG. 8 is a perspective view for explaining the present invention and the related art.

【図9】 この発明及び従来の説明をするための平面
図。
FIG. 9 is a plan view for explaining the present invention and the related art.

【図10】 この発明及び従来の説明をするための平面
図。
FIG. 10 is a plan view for explaining the present invention and the related art.

【符号の説明】[Explanation of symbols]

1 入力手段 3 データ処理手段 4 ディスプレー 5 TIN処理手段 6 残存緑地処理手段 7 辺定義手段 1 Input means 3 Data processing means 4 displays 5 TIN processing means 6 Residual green space treatment means 7 side definition means

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平6−36013(JP,A) (58)調査した分野(Int.Cl.7,DB名) G01C 7/00 - 7/06 G01D 21/00 - 21/02 G06T 1/00 G06T 17/40 - 17/50 ─────────────────────────────────────────────────── ─── Continuation of front page (56) References JP-A-6-36013 (JP, A) (58) Fields investigated (Int.Cl. 7 , DB name) G01C 7 /00-7/06 G01D 21 / 00-21/02 G06T 1/00 G06T 17/40-17/50

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 被測地領域の標高等の複数の測地点を、
三角形を描く辺で結び、三角メッシュを形成するTIN
処理手段5を備えた土工量管理装置において、指定され
た残存緑地G内では上記辺を描かないように制御する残
存緑地処理手段6を備えたことを特徴とする土工量管理
装置。
1. A plurality of measurement points such as the altitude of the measured area
TIN that connects the sides that draw a triangle to form a triangular mesh
An earthwork amount management apparatus comprising a processing means 5, characterized by further comprising a remaining green area processing means 6 for controlling such that the above side is not drawn in a designated remaining green area G.
【請求項2】 被測地領域の標高等の複数の測地点を、
三角形を描く辺で結び、三角メッシュを形成するTIN
処理手段5を備えた土工量管理装置において、測地領域
の外形線に対応する指定線にもとづき、この指定線に三
角形の辺が沿うように制御する辺定義手段7を設けたこ
とを特徴とする土工量管理装置。
2. A plurality of measurement points such as the altitude of the measured area are
TIN that connects the sides that draw a triangle to form a triangular mesh
The earthwork management apparatus provided with the processing means 5 is characterized in that a side defining means 7 is provided for controlling a specified side corresponding to an outline of the geodetic area so that a side of a triangle follows the specified line. Earthwork amount management device.
【請求項3】 被測地領域の標高等の複数の測地点を、
三角形を描く辺で結び、三角メッシュを形成するTIN
処理手段5を備えた土工量管理装置において、指定され
た尾根線,谷線等の指定線にもとづき、この指定線に三
角形の辺が沿うとともに、この指定線を境として背中合
せの三角形が形成されるように制御する辺定義手段7を
設けたことを特徴とする土工量管理装置。
3. A plurality of measurement points such as the altitude of the measured area
TIN that connects the sides that draw a triangle to form a triangular mesh
In the earthwork amount management device provided with the processing means 5, based on a designated line such as a designated ridge line or valley line, a side of the triangle is along the designated line, and a back-to-back triangle is formed with the designated line as a boundary. An earthwork amount management device characterized in that a side defining means 7 for controlling so as to be provided is provided.
JP16420696A 1996-06-25 1996-06-25 Earthwork volume control device Expired - Fee Related JP3389006B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16420696A JP3389006B2 (en) 1996-06-25 1996-06-25 Earthwork volume control device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16420696A JP3389006B2 (en) 1996-06-25 1996-06-25 Earthwork volume control device

Publications (2)

Publication Number Publication Date
JPH109857A JPH109857A (en) 1998-01-16
JP3389006B2 true JP3389006B2 (en) 2003-03-24

Family

ID=15788690

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16420696A Expired - Fee Related JP3389006B2 (en) 1996-06-25 1996-06-25 Earthwork volume control device

Country Status (1)

Country Link
JP (1) JP3389006B2 (en)

Also Published As

Publication number Publication date
JPH109857A (en) 1998-01-16

Similar Documents

Publication Publication Date Title
US9430871B2 (en) Method of generating three-dimensional (3D) models using ground based oblique imagery
CN109523630B (en) Contour line generation method and device based on tension spline interpolation
CN101930623A (en) A three-dimensional road modeling method and device
CN108919295A (en) Airborne LiDAR point cloud road information extracting method and device
CN115063557B (en) Building intelligent extraction method and device based on tilt model
CN115797288B (en) Method for calculating filling and excavating amount based on ground point cloud data
CN112002012B (en) Visibility Analysis Methods for Urban Areas
CN113932779A (en) Earth and stone calculation method and system based on unmanned aerial vehicle oblique photography and storage medium
US6674431B1 (en) Method for processing data expressing three-dimensional shape
JP3389006B2 (en) Earthwork volume control device
CN116030116A (en) Landfill volume analysis method and device, electronic equipment and storage medium
CN116934986A (en) Three-dimensional road map optimization method and device and electronic equipment
CN117036452B (en) A method for segmenting complex irregular buildings based on voxel models
JPH09147086A (en) Automatic slope estimation method for elevation data
JPH09305643A (en) Method and device for designing plant layout
JP3572253B2 (en) Three-dimensional model generation method and apparatus, and recording medium recording execution program of this method
JP6746851B2 (en) Terrain classification system and terrain classification method
CN107767458A (en) TIN surface geometry topological coherence analysis method and system
JP3270319B2 (en) Geological information processing system
JPH109860A (en) Earth-volume managing apparatus
JP3063134B2 (en) Terrain data creation device
JP7760273B2 (en) Topographical plan view display system and topographical plan view display method
JP2571079B2 (en) 3D topographic map display device
JP3440278B2 (en) Civil engineering surveying and construction support system
JP3376884B2 (en) 3D terrain display device

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20021224

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090117

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees