JP3399778B2 - Power system evaluation device, power system power flow optimization method and device, and power system planning support method and device - Google Patents
Power system evaluation device, power system power flow optimization method and device, and power system planning support method and deviceInfo
- Publication number
- JP3399778B2 JP3399778B2 JP10947797A JP10947797A JP3399778B2 JP 3399778 B2 JP3399778 B2 JP 3399778B2 JP 10947797 A JP10947797 A JP 10947797A JP 10947797 A JP10947797 A JP 10947797A JP 3399778 B2 JP3399778 B2 JP 3399778B2
- Authority
- JP
- Japan
- Prior art keywords
- data
- failure
- cost
- amount
- power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、連系構成された電
力系統の評価技法に係り、特に、その評価した結果に基
づいて、電力系統の評価を行ない、潮流の最適化を図
り、電力系統の計画立案を支援する方法と装置に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an evaluation technique for a power system configured to be interconnected, and in particular, the power system is evaluated based on the evaluation result to optimize the power flow, And apparatus for supporting the planning of the.
【0002】[0002]
【従来の技術】電力系統の運用に際しては、需要と供給
を均衡させ、電力系統の円滑、且つ経済的な運用が得ら
れるようにするのが望ましい。そして、このためには、
電力系統の特性、例えば経済性を評価し、その評価結果
に基づいて電力系統を制御する必要がある。2. Description of the Related Art When operating a power system, it is desirable to balance supply and demand so that the power system can be operated smoothly and economically. And for this,
It is necessary to evaluate the characteristics of the power system, such as economic efficiency, and control the power system based on the evaluation results.
【0003】ところで、このような連系構成された電力
系統の評価に関する従来技術としては、例えば、平成5
年10月発行、電気学会論文誌B113巻10号「需要
端予備率に基づく発電・送電系統の信頼度評価」を挙げ
ることができる。By the way, as a conventional technique relating to the evaluation of such an interconnected power system, for example,
The Institute of Electrical Engineers of Japan, Volume B113, Volume 10, Issue 10, "Evaluation of Reliability of Power Generation / Transmission System Based on Demand End Reserve" can be mentioned.
【0004】そして、この論文には、各送電線のルート
断時での供給支障量の総量を最小化するのに必要な各発
電機の出力を、線形計画法により求める技術が開示され
ており、そこでは、需要と、送電線潮流制約と、発電機
出力制約を制約条件とし、各送電線のルート断時の供給
支障量の総計を目的関数とする定式化が行なわれてい
る。Then, this paper discloses a technique for obtaining the output of each generator required to minimize the total amount of supply hindrance when the route of each transmission line is broken by a linear programming method. , There, the demand, the transmission line power flow constraint, and the generator output constraint are used as constraint conditions, and a formulation is performed in which the total amount of supply hindrance when the route of each transmission line is disconnected is an objective function.
【0005】また、電力系統における送電線増設計画の
立案に際しては、送電線増設によりもたらされる効果の
評価が重要なポイントになるが、この増設効果として
は、その結果として電力系統にもたらされる信頼度及び
経済性の両面を評価する必要がある。In addition, when planning a transmission line extension plan for an electric power system, the evaluation of the effect brought by the transmission line extension is an important point. As a result of this addition effect, the reliability brought to the electric power system. And it is necessary to evaluate both aspects of economy.
【0006】上記の論文では、発電機の出力上下限制約
や送電線の送電容量制約から生じる需要端の供給支障
量、或いは供給支障となるまでの裕度(需要端予備率)を
評価指標とし、供給支障量や需要端予備率のレベルによ
って系統内の信頼度分布を表現することによって、系統
計画立案を支援するアイデアについても開示している。In the above-mentioned paper, the amount of supply hindrance at the demand end caused by the upper and lower limit constraints of the generator and the transmission capacity constraint of the transmission line, or the margin until the supply hindrance (demand end reserve ratio) is used as an evaluation index. It also discloses the idea of supporting system planning by expressing the reliability distribution in the system by the level of supply hindrance and the level of demand margin.
【0007】[0007]
【発明が解決しようとする課題】上記従来技術は、電力
系統の評価に際して考慮すべき要素の多様性について配
慮しない。例えば、上記従来技術では、供給支障量を最
小化するように各発電機出力を調整しているが、通常の
運用状態での電力系統における総発電コストは考慮され
ていない。この結果、系統内に複数の発電所が存在して
いた場合、各発電所の発電コストに違いがあるため、単
に供給支障量を最小化するように、各発電機の出力を調
整したのでは、平常時での総発電コストが増加してしま
う可能性がある。The above-mentioned prior art does not consider the variety of factors to be considered when evaluating the power system. For example, in the above-described conventional technique, the output of each generator is adjusted so as to minimize the amount of supply hindrance, but the total power generation cost in the power system in the normal operating state is not considered. As a result, if there are multiple power plants in the grid, there is a difference in the power generation cost of each power plant, so the output of each power generator may not be adjusted to simply minimize the amount of supply disruption. , There is a possibility that the total power generation cost in normal times will increase.
【0008】また、系統でのルート断時の供給支障量
は、実際にルート断が発生しなければ現実のものとはな
らず、且つ、その発生確率はかなり低いので、このよう
な条件をもつルート断時供給支障量については、単に最
小化だけを図るのではなく、場合によっては増加させた
方が、平常時の総発電コストは削減でき、経済的には有
利になる可能性がある。さらに、故障時損失としては、
ルート断以外の故障時に、系統全体の安定化のために一
部の発電機を強制遮断することによる総発電コストの増
加もある。[0008] Further, the supply hindrance amount at the time of the route cut in the system does not become actual unless the route cut actually occurs, and the occurrence probability thereof is considerably low, so that there is such a condition. It may be economically advantageous to increase the amount of power supply disruption during a route break, rather than simply to minimize it, in some cases because it can reduce the total power generation cost during normal times. Furthermore, as the loss at the time of failure,
There is also an increase in the total power generation cost by forcibly shutting off some of the generators to stabilize the entire system in the event of a failure other than a route disconnection.
【0009】従って、以上をまとめると、ルート断によ
る故障時損失によるコストと、ルート断以外の故障時損
失によるコストと、平常時の総発電コストを定量的に勘
案して、各発電機の出力を最適化することが課題とな
る。しかし、この場合、目的関数が線形とはならないた
め、従来技術のように線形計画法を適用することは困難
である。Therefore, to summarize the above, the output of each generator is quantitatively considered by taking into account the cost due to failure loss due to route disconnection, the cost due to failure loss other than route disconnection, and the total power generation cost during normal times. Optimization is a challenge. However, in this case, since the objective function is not linear, it is difficult to apply the linear programming as in the prior art.
【0010】次に、電力系統での総発電コストは、与え
られた各発電機の発電コスト特性データを用いて各発電
機の出力値に対する発電コストを求め、これを全ての発
電機について合計することによって計算する。このと
き、系統の信頼度は、故障発生時の損失の大きさと考え
ることができるが、上記従来技術は、これを送電線ルー
ト断時の供給支障量によって評価している。Next, for the total power generation cost in the power system, the power generation cost with respect to the output value of each generator is obtained using the given power generation cost characteristic data of each generator, and this is summed for all the generators. Calculate by At this time, the reliability of the system can be considered as the amount of loss at the time of failure occurrence, but the above conventional technology evaluates this by the amount of supply hindrance when the transmission line route is interrupted.
【0011】しかし、上記したように、故障時損失とし
ては、ルート断時以外の故障時に、系統全体の安定化の
ために行なわれる一部の発電機の強制遮断による総発電
コストの増加もある。また、送電線増設により、信頼度
の観点も含めて各送電線に予め設定されている潮流限度
(潮流制約)が緩和され、各発電機出力配分が改善される
ことにより実現される総発電コストが削減される可能性
がある。そこで、この総発電コストの削減も送電線増設
の効果として評価する必要がある。これを計算するため
には、送電線増設により各送電線の潮流制約を再計算す
る必要がある。However, as described above, as the loss at the time of failure, there is also an increase in the total power generation cost due to the forced shutoff of a part of the generators for stabilizing the entire system at the time of a failure other than the time when the route is cut. . Also, due to the extension of transmission lines, the power flow limit set in advance for each transmission line including the viewpoint of reliability
There is a possibility that the total power generation cost will be reduced by relaxing the (tidal flow constraint) and improving the output distribution of each generator. Therefore, it is necessary to evaluate this reduction in total power generation cost as an effect of the extension of transmission lines. In order to calculate this, it is necessary to recalculate the power flow constraint of each transmission line by adding transmission lines.
【0012】本発明の目的は、より的確な評価が得られ
るようにした電力系統評価装置を提供することにあり、
さらに、この結果を用いた電力系統潮流最適化方法と装
置並びに電力系統計画支援方法と装置を提供することに
ある。It is an object of the present invention to provide an electric power system evaluation device capable of obtaining a more accurate evaluation,
It is another object of the present invention to provide a power system power flow optimization method and device and a power system planning support method and device that use the results.
【0013】[0013]
【課題を解決するための手段】まず、上記目的は、信頼
性に富んだ確率的な量であるルート断時とルート断以外
時の故障時損失によるコストと、平常時の総発電コスト
を定量的に勘案して得た評価指標を用い、これにより電
力系統を評価することにより達成され、さらにこの評価
指標を用いて発電機の出力を制御することにより達成さ
れる。[Means for Solving the Problems] First, the above-mentioned purpose is to quantify the cost due to failure loss at the time of route disconnection and at times other than route disconnection, which is a highly reliable and stochastic amount, and the total power generation cost in normal times. This is achieved by using an evaluation index obtained by taking into consideration the above, and by evaluating the power system by this, and further by controlling the output of the generator using this evaluation index.
【0014】具体的には、上記目的は、以下の手段を用
いることにより達成される。まず、ルート断故障時の負
荷強制遮断量及びルート断以外の故障時での発電機強制
遮断による負荷遮断量の合計をコスト換算して求めた負
荷遮断量コストに、前記発電機強制遮断による総発電コ
ストの変化量を合算した値を故障時損失コストとした上
で、この故障時損失コストを故障ケース毎に付与される
重み係数により合算し、これを平常時の総発電コストと
合算して電力系統の評価指標とし、この評価指標により
電力系統の評価を行うようにして達成される。Specifically, the above object is achieved by using the following means. First, the total load cutoff amount at the time of route disconnection failure and the load cutoff amount due to generator forced cutoff at the time of failure other than route disconnection is converted into cost, and The value obtained by summing the amount of change in the power generation cost is taken as the loss cost at the time of failure, and this loss cost at the time of failure is added up by the weighting coefficient given to each failure case, and this is added to the total power generation cost in normal times. This is achieved by using the evaluation index of the power system as the evaluation index of the power system.
【0015】次に、ルート断故障時の負荷遮断量を計算
する手段と、ルート断以外故障時の発電機強制遮断によ
る負荷遮断量を計算する手段と、前記負荷遮断量をコス
ト換算する手段と、前記故障時の発電機強制遮断による
総発電コストの変化量を計算する手段と、故障時の負荷
遮断コストと総発電コスト変化量を合算して、これを故
障ケース毎の重み係数により合算して故障時損失コスト
とする手段と、この故障時損失コストと平常時総発電コ
ストを合算し、評価指標として出力する手段とを設ける
ことにより達成される。Next, there are provided means for calculating a load shedding amount at the time of a route disconnection failure, means for calculating a load shedding amount due to forced compulsion of the generator at the time of a failure other than the route disconnection, and means for converting the load shedding amount into a cost. , Means for calculating the amount of change in the total power generation cost due to forced shutdown of the generator at the time of failure, and summing the load cut-off cost at the time of failure and the amount of change in total power generation cost, and summing this with a weighting factor for each failure case It is achieved by providing means for setting the loss cost at the time of failure and means for adding the loss cost at the time of failure and the total power generation cost during normal operation and outputting as the evaluation index.
【0016】また、ルート断故障時の負荷強制遮断量及
びルート断以外の故障時での発電機強制遮断による負荷
遮断量の合計をコスト換算して求めた負荷遮断量コスト
に、前記発電機強制遮断による総発電コストの変化量を
合算した値を故障時損失コストとした上で、この故障時
損失コストを故障ケース毎に付与される重み係数により
合算し、これを平常時の総発電コストと合算して電力系
統の評価指標とし、この評価指標が最小化されるよう
に、発電機の出力を制御するようにして達成される。In addition, the load compulsory cutoff amount at the time of a route disconnection failure and the total load cutoff amount due to the generator forced cutoff at the time of a failure other than the route disconnection are converted into costs, and the load compulsion amount cost is added to the generator forced compulsion amount cost. The value obtained by summing the changes in the total power generation cost due to interruption is taken as the loss cost at the time of failure, and this loss cost at the time of failure is added up by the weighting coefficient assigned to each failure case, and this is taken as the total power generation cost in normal times. This is achieved by summing them up as an evaluation index of the power system and controlling the output of the generator so that this evaluation index is minimized.
【0017】さらに、ルート断故障時の負荷遮断量を計
算する手段と、ルート断以外故障時の発電機強制遮断に
よる負荷遮断量を計算する手段と、前記負荷遮断量をコ
スト換算する手段と、前記故障時の発電機強制遮断によ
る総発電コストの変化量を計算する手段と、故障時の負
荷遮断コストと総発電コスト変化量を合算して、これを
故障ケース毎の重み係数により合算して故障時損失コス
トとする手段と、この故障時損失コストと平常時総発電
コストを合算し、評価指標として出力する手段と、この
評価指標を最小化するのに必要な各発電機の出力を計算
する手段とを設けることにより達成される。Further, means for calculating a load shedding amount at the time of a route disconnection failure, means for calculating a load shedding amount due to forced compulsion of a generator at the time of a failure other than the route interruption, and means for converting the load shedding amount into a cost. The means for calculating the amount of change in the total power generation cost due to forced shutdown of the generator at the time of failure, the load cutoff cost at the time of failure, and the total amount of power generation cost change are added together, and this is added by the weighting factor for each failure case. Calculates the loss cost at the time of failure, the means for adding the loss cost at the time of failure and the total power generation cost in normal times, and outputting it as an evaluation index, and the output of each generator required to minimize this evaluation index. And a means for doing so.
【0018】上記の手段により、与えられた系統状態及
び各種制約条件のもとで、ルート断時及びルート断以外
時の負荷遮断量及び総発電コスト増加量を計算してコス
ト換算し、これに各故障ケース毎の重み係数(例えば故
障発生確率)を乗じて平常時の総発電コストとの合計か
らなる電力系統の評価指標が得られ、さらに、この評価
指数を最小化するのに必要な各発電機の出力が計算でき
る。By the above means, the load cutoff amount and the total power generation cost increase amount at the time of the route disconnection and at the time other than the route disconnection are calculated and converted into the cost under the given system condition and various constraint conditions. The weighting factor for each failure case (for example, failure probability) is multiplied to obtain the evaluation index of the power system consisting of the total of the total power generation cost in normal times, and further, each evaluation index required to minimize this evaluation index. The output of the generator can be calculated.
【0019】また、本発明の目的は、確率的な量である
故障時損失と平常時の総発電コストを統一的かつ定量的
な指標により計算する手段と、送電線増設後系統の各送
電線の送電容量制約値を計算する手段、それに送電線増
設前後における前記指標の差を計算する手段とを設け、
送電線増設が信頼度及び経済性に及ぼす効果を定量的に
かつ統一的な指標で評価することにより達成される。Another object of the present invention is a means for calculating the loss at the time of failure and the total power generation cost in normal times, which are probabilistic quantities, by means of a unified and quantitative index, and each transmission line in the system after the transmission line is added. And a means for calculating the difference between the indexes before and after transmission line addition,
This is achieved by quantitatively and uniformly evaluating the effect of additional transmission lines on reliability and economic efficiency.
【0020】具体的には、上記目的は、以下の手段を用
いることにより達成される。すなわち、まず、電力系統
の送電線増設による信頼度及び経済性の向上効果を評価
する電力系統計画支援方法において、ルート断故障時の
負荷強制遮断量及びルート断以外の故障時での発電機強
制遮断による負荷遮断量の合計をコスト換算して求めた
負荷遮断量コストに、前記発電機強制遮断による総発電
コストの変化量を合算した値を故障時損失コストとした
上で、この故障時損失コストを故障ケース毎に付与され
る重み係数により合算し、これを平常時の総発電コスト
と合算して電力系統の評価指標とし、この評価指標を送
電線増設前後の系統に対して求めて、その差によって送
電線増設による信頼度及び経済性の向上を評価すること
により達成される。Specifically, the above object is achieved by using the following means. That is, first, in the power system planning support method that evaluates the improvement effect of reliability and economic efficiency by adding the transmission line of the power system, in the power system planning support method, the load forced cutoff amount at the time of the route disconnection failure and the generator forced at the time of the failure other than the route disconnection The load loss amount cost obtained by converting the total load cutoff amount due to the cutoff into a cost, and the sum of the change amount of the total power generation cost due to the forced generator cutoff as the failure loss cost. The cost is summed with the weighting coefficient given to each failure case, and this is summed with the total power generation cost in normal times as an evaluation index of the power system, and this evaluation index is obtained for the system before and after the transmission line addition, This difference is achieved by evaluating the improvement in reliability and economic efficiency due to the addition of transmission lines.
【0021】次に、電力系統の送電線増設による信頼度
及び経済性の向上効果を評価する電力系統計画支援装置
において、ルート断故障時の負荷遮断量を計算する手段
と、ルート断以外故障時の発電機強制遮断による負荷遮
断量を計算する手段と、前記負荷遮断量をコスト換算す
る手段と、前記故障時の発電機強制遮断による総発電コ
ストの変化量を計算する手段と、故障時の負荷遮断コス
トと総発電コスト変化量を合算して、これを故障ケース
毎の重み係数により合算して故障時損失コストとする手
段と、この故障時損失コストと平常時総発電コストを合
算し、評価指標として出力する手段と、送電線増設後系
統の各送電線の潮流制約値を計算する手段と、送電線増
設前後系統の電力系統評価指標の差を前記の各手段を用
いて計算する手段とを設けることにより達成される。Next, in the electric power system planning support device for evaluating the improvement effect of reliability and economy by the addition of transmission lines of the electric power system, a means for calculating the load shedding amount at the time of the route disconnection failure, and a means for calculating the load disconnection amount at the time of failure other than the route disconnection. Means for calculating the amount of load shedding due to forced shutoff of the generator, means for converting the amount of load shedding into costs, means for calculating the amount of change in total power generation cost due to forced shutoff of the generator at the time of failure, and A means for summing the load shedding cost and the total power generation cost change amount and summing this with the weighting coefficient for each failure case to be the failure loss cost, and this failure loss cost and the normal total power generation cost, A means for outputting as an evaluation index, a means for calculating the power flow constraint value of each transmission line in the system after the transmission line is added, and a means for calculating the difference between the power system evaluation indices before and after the transmission line is added by using each of the above means. It is achieved by providing a.
【0022】上記の手段により、送電線増設後の系統に
対して、まず各送電線の潮流制約を計算し、その次にル
ート断時とルート断以外時の負荷遮断量及び総発電コス
ト増加量を計算してコスト換算し、これに各故障ケース
毎の重み係数(例えば故障発生確率)を乗じて平常時の総
発電コストとの合計をとることができる。With the above means, first, the power flow constraint of each transmission line is calculated for the system after the transmission line is added, and then the load cutoff amount at the time of the route disconnection and at the time other than the route disconnection and the total power generation cost increase amount. Can be calculated and converted into a cost, which can be multiplied by a weighting factor for each failure case (for example, failure probability) to obtain the total power generation cost in normal times.
【0023】そして、送電線増設後系統に対する値から
送電線増設前系統に対する値を差し引き、その結果を送
電線増設による信頼度及び経済性向上効果として出力す
ることができる。Then, the value for the system before the transmission line expansion is subtracted from the value for the system after the transmission line expansion, and the result can be output as the reliability and economic improvement effect by the transmission line expansion.
【0024】[0024]
【発明の実施の形態】以下、本発明について、図示の実
施形態により詳細に説明する。まず、本発明の一実施形
態では、与えられた電力系統の状態のもとで、RG指標
を求めるようにした電力系統評価方法と装置として具現
され、更にこの指標を最小にするのに必要な発電機の出
力値を求めるようにした電力系統潮流最適化方法及び装
置として具現されている。ここで、RG指標とは、平常
時総発電コストと、コストで換算した故障時損失期待値
を合計したものであり、従って、このRG指標が小さい
程、その電力系統の運用コストが低いことになり、コス
トが考慮されているので、電力系統の運用の適否を的確
に表す評価指標として用いることができるのである。BEST MODE FOR CARRYING OUT THE INVENTION The present invention will be described in detail below with reference to the embodiments shown in the drawings. First, an embodiment of the present invention is embodied as a power system evaluation method and device for obtaining an RG index under a given state of the power system, and is further required to minimize this index. The present invention is embodied as a power system power flow optimization method and device for obtaining an output value of a generator. Here, the RG index is a sum of the normal total power generation cost and the expected loss loss at cost. Therefore, the smaller the RG index, the lower the operating cost of the power system. Since the cost is taken into consideration, it can be used as an evaluation index that accurately represents the suitability of operation of the power system.
【0025】そして、故障時損失期待値とは、予めリス
トアップしておいた故障ケースに対する障時損失を、予
め故障ケース毎に付与されている重み係数(例えば故障
発生確率)を乗じて合計したものであり、また、故障時
損失とは、故障時に保護装置が動作して負荷遮断が起動
されたときと、ルート断以外故障時の発電機強制遮断が
起動されることにより生じる需要家及び系統側が被る損
失の合計である。The expected loss value at the time of failure is obtained by multiplying the failure loss for the failure cases listed in advance by multiplying the weighting coefficient (for example, the failure occurrence probability) assigned to each failure case in advance. In addition, the loss at the time of failure is the customer and the system that are generated when the protective device operates at the time of failure and the load cutoff is activated, and when the generator forced cutoff is activated at the time of failure other than the route interruption. It is the total loss incurred by the side.
【0026】このときの需要家側の損失としては、例え
ば負荷遮断により発生する需要家の停電によるものが考
えられ、系統側の損失としては、例えばルート断以外故
障時の発電機強制遮断(以下、電制という)により供給停
止させられた発電量を補うために残りの各発電機の出力
が変化することによって生じる総発電コストの増加によ
るものが考えられる。The loss on the customer side at this time may be due to a power failure of the customer caused by load shedding, for example, and the loss on the system side may be, for example, forced shutoff of the generator (hereinafter It is conceivable that the total power generation cost increases as the output of each of the remaining generators changes in order to compensate for the amount of power generation that has been stopped due to electric control.
【0027】図1は、本発明の一実施形態における機能
ブロック図で、図示のように、入出力部1と発電機出力
調整部2、RG指標計算部3、潮流制約付発電コスト最
小化潮流データ生部4、系統分断時負荷遮断量計算部
5、電制機決定部6、電制量計算部7、電制時負荷遮断
量計算部8、負荷遮断量コスト換算部9、それに総発電
コスト計算部10とで構成されている。FIG. 1 is a functional block diagram according to an embodiment of the present invention. As shown in the figure, an input / output unit 1, a generator output adjusting unit 2, an RG index calculating unit 3, a power flow cost-constrained power generation cost minimizing power flow. Data generation section 4, load cut-off amount calculation section 5 during system disconnection, electronic control unit determination section 6, electric control amount calculation section 7, load cut-off amount calculation section 8 during electric control, load cutoff amount cost conversion section 9, and total power generation It is composed of a cost calculator 10.
【0028】そして、さらに、各種のデータの保持用と
して、系統状態データベース部11と故障データベース
部12、パラメータデータベース部13、RG指標計算
用潮流データ部14が設けられている。入出力部1は、
運用者からの入力を電力系統潮流最適化装置に取込み、
逆に発電機出力調整部2から受け取った各発電機出力値
を運用者、もしくは電力系統の発電機出力制御装置へ送
る働きをする。Further, a system status database section 11, a failure database section 12, a parameter database section 13, and an RG index calculation power flow data section 14 are provided for holding various data. The input / output unit 1 is
Capture the input from the operator to the power system power flow optimization device,
Conversely, it functions to send each generator output value received from the generator output adjusting unit 2 to the operator or the generator output control device of the power system.
【0029】発電機出力調整部2は、系統状態データベ
ース部11から与えられる各種の条件データ(系統構成
データ、潮流データ、総需要データ、発電機出力上下限
データ、固定供給力出力データ、発電コスト特性デー
タ、送電線潮流制約データ、分断点許容電源脱落量デー
タ、許容電制量データ)のもとで、RG指標を最小にす
るのに必要な各発電機出力を計算し、結果を出力する働
きをするもので、このとき、潮流制約付発電コスト最小
化潮流データ生成部4及びRG指標計算部3と連携しな
がら処理を行うようになっており、処理の詳細について
は後述する。The generator output adjustment unit 2 is provided with various condition data (system configuration data, tidal current data, total demand data, generator output upper and lower limit data, fixed supply power output data, power generation cost) given from the system state database unit 11. Characteristic data, transmission line power flow constraint data, break point allowable power supply loss amount data, allowable power control amount data), calculate each generator output required to minimize the RG index, and output the result. At this time, the process is performed in cooperation with the power flow cost minimizing power generation cost with power flow constraint generation unit 4 and the RG index calculation unit 3, and the details of the process will be described later.
【0030】RG指標計算部3は、系統状態データベー
ス部11から与えられる条件データ(系統構成データ、
総需要データ、発電機出力上下限データ、固定供給力出
力データ、発電コスト特性データ、送電線潮流制約デー
タ、分断点許容電源脱落量データ、許容電制量デー
タ)、及びRG指標計算用潮流データ部14、さらに故
障データベース部12から与えられる故障ケースに関す
る条件のもとで、RG指標を計算し、結果を出力する働
きをするもので、処理の詳細については後述する。The RG index calculation unit 3 uses the condition data (system configuration data, system configuration data,
Total demand data, generator output upper and lower limit data, fixed supply capacity output data, power generation cost characteristic data, transmission line power flow constraint data, break point allowable power loss data, allowable power control data), and RG index calculation power flow data Under the conditions related to the failure case given from the unit 14 and the failure database unit 12, the RG index is calculated and the result is output. The details of the processing will be described later.
【0031】潮流制約付発電コスト最小化潮流データ生
成部4は、与えられた発電機出力上下限制約、固定供給
力出力制約、送電線潮流制約、それに総需要制約のそれ
ぞれを満たす範囲内で、総発電コストが最小となるよう
な潮流データを生成し、そのデータを出力する働きをす
るもので、処理の詳細については後述する。The power flow cost generating minimization of power generation cost with power flow constraint: The power flow data generating unit 4 is within a range satisfying each of the given generator output upper / lower limit constraint, fixed supply power output constraint, transmission line power flow constraint, and total demand constraint. It functions to generate tidal current data that minimizes the total power generation cost and output the data, and the details of the processing will be described later.
【0032】系統分断時負荷遮断量計算部5は、系統分
断を生じる故障ケースに対して、安定化に必要な負荷遮
断量を計算し、その結果を出力する働きをするもので、
処理の詳細については後述する。電制機決定部6は、系
統分断を生じない故障ケースに対して、安定化に必要な
電制対象発電機を選択し、結果を出力する働きをするも
ので、処理の詳細については後述する。The load cutoff amount calculation unit 5 during system disconnection functions to calculate the load cutoff amount necessary for stabilization in the case of a failure that causes system disconnection, and output the result.
Details of the processing will be described later. The electric control device determination unit 6 has a function of selecting an electric control target generator necessary for stabilization and outputting a result for a failure case that does not cause system division, and details of the processing will be described later. .
【0033】電制量計算部7は、与えられた電制対象発
電機の出力値の合計を計算し、結果を出力する働きをす
るもので、処理の詳細については後述する。電制時負荷
遮断量計算部8は、与えられた電制量に対して、安定化
のために必要な負荷遮断量を計算し、結果を出力する働
きをするもので、処理の詳細については後述する。The electric quantity control unit 7 has a function of calculating the total output value of the given electric power generators subject to electric control and outputting the result. The details of the processing will be described later. The electronically controlled load cutoff amount calculation unit 8 has a function of calculating a load cutoff amount required for stabilization with respect to a given electric control amount and outputting the result. It will be described later.
【0034】負荷遮断量コスト換算部9は、与えられた
負荷遮断量をコスト換算し、結果を出力する働きをする
もので、処理の詳細については後述する。総発電コスト
計算部10は、与えられた各発電機の発電コスト特性デ
ータと出力データから総発電コストを計算し、結果を出
力する働きをするもので、処理の詳細については後述す
る。The load cutoff amount cost conversion unit 9 has a function of cost-converting the given load cutoff amount and outputting the result. The details of the processing will be described later. The total power generation cost calculation unit 10 calculates the total power generation cost from the given power generation cost characteristic data and output data of each generator, and outputs the result. The details of the processing will be described later.
【0035】系統状態データベース部11は、潮流最適
化の対象とする系統の状態や各種制約条件に関するデー
タを管理するものである。故障データベース部12は、
故障時損失を計算すべき対象となる故障ケースに関する
データを管理する働きをする。The system status database unit 11 manages data concerning the status of the system targeted for power flow optimization and various constraints. The failure database unit 12 is
It serves to manage the data about the failure case for which the loss at failure should be calculated.
【0036】パラメータデータベース部13は、RG指
標計算部3や発電機出力調整部2で必要とする各種パラ
メータ値を管理するものである。一方、RG指標計算用
潮流データ部14は、RG指標を計算すべき対象となる
系統の潮流条件を与えるのに必要なデータを管理するも
のである。The parameter database unit 13 manages various parameter values required by the RG index calculation unit 3 and the generator output adjustment unit 2. On the other hand, the RG index calculation power flow data unit 14 manages the data necessary to give the power flow conditions of the system for which the RG index is to be calculated.
【0037】次に、各データベース部で管理されるデー
タについて、図2により説明する。まず、系統状態デー
タベース部11では、図示のように、系統構成データと
潮流データ、総需要データ、発電機出力上下限データ、
固定供給力出力データ、発電コスト特性データ、送電線
潮流制約データ、分断点許容電源脱落量データ、それに
許容電制量データを与えるようになっている。Next, the data managed by each database unit will be described with reference to FIG. First, in the system state database unit 11, as shown in the figure, system configuration data and power flow data, total demand data, generator output upper and lower limit data,
It provides fixed power output data, power generation cost characteristic data, transmission line power flow constraint data, break point allowable power drop amount data, and allowable power control amount data.
【0038】そして、これらデータの詳細は以下の通り
である。系統構成データとは、送電線のインピーダンス
や発電機の定格容量などの系統設備の各定数、及び各系
統設備間の接続情報のことである。潮流データとは、発
電機や負荷や送電線など各系統設備上の電気データ(有
効電力、無効電力、電圧など)のことである。総需要デ
ータとは、全ての負荷の有効電力の合計である。The details of these data are as follows. The system configuration data is each constant of system equipment such as impedance of a transmission line and rated capacity of a generator, and connection information between each system equipment. The power flow data is electrical data (active power, reactive power, voltage, etc.) on each system equipment such as a generator, a load, and a transmission line. The total demand data is the total active power of all loads.
【0039】発電機出力上下限データとは、各発電機毎
に与えられる有効電力出力の上下限値のことである。固
定供給力出力データとは、幾つかの発電機に対して有効
電力出力値を指定するデータのことである。発電コスト
特性データとは、各発電機の発電コストを出力に応じて
与えるデータのことである。送電線潮流制約データと
は、各送電線の有効電力潮流量の上限を与えるデータこ
とである。The generator output upper and lower limit data are upper and lower limit values of active power output given to each generator. Fixed power output data is data that specifies active power output values for some generators. The power generation cost characteristic data is data that gives the power generation cost of each generator according to the output. The transmission line power flow constraint data is data that gives an upper limit of the active power flow rate of each transmission line.
【0040】分断点許容電源脱落量データとは、系統を
分断する個所について、そこを分断したときに生じる双
方の分断系統それぞれについて許容し得る発電量不足量
上限値を与えるデータのことである。許容電制量データ
とは、系統全体で許容できる発電量不足量上限値を与え
るデータのことである。The break point allowable power supply dropout amount data is data that gives the allowable upper limit of the amount of power generation for each of the divided grids that occurs when the grid is divided. The allowable electricity control amount data is data that gives the upper limit value of the amount of power generation insufficiency that is allowable in the entire system.
【0041】次に、故障データベース部12では、図示
のように、各故障ケース毎に、故障点データと故障シー
クエンスデータ、それに重み係数データを与えるように
なっている。そして、これらデータの詳細は以下の通り
である。Next, in the failure database unit 12, as shown in the figure, failure point data, failure sequence data, and weighting coefficient data are given for each failure case. The details of these data are as follows.
【0042】故障点データとは、系統中における故障設
備を指定するデータのことである。故障シークエンスデ
ータとは、故障内容や系統操作内容をその発生時刻と共
に与えるデータのことである。重み係数データとは、そ
の故障ケースの影響をどの程度まで重くみるかを決める
データのことで、例えば故障発生確率を与えるデータの
ことである。The fault point data is data designating a faulty facility in the system. The failure sequence data is data that gives details of the failure and details of the system operation together with the time of occurrence. The weighting factor data is data that determines to what degree the influence of the failure case is to be weighted, for example, data that gives a failure occurrence probability.
【0043】また、パラメータデータベース部13で
は、発電機出力調整幅初期値データと発電機出力調整幅
しきい値データ、それに負荷遮断量コスト換算定数デー
タを与えるようになっている。なお、これらのデータの
内容と、使用目的については、後述する。Further, the parameter database unit 13 is adapted to provide initial value data of generator output adjustment width, threshold value data of generator output adjustment width, and load cutoff amount cost conversion constant data. The contents of these data and the purpose of use will be described later.
【0044】次に、各部の処理について説明する。ま
ず、発電機出力調整部2での処理について説明すると、
ここでの大まかな処理は以下の通りである。
(1) 各発電機について、出力を一定量(発電機出力調整
幅ΔP)変化させたときのRG指標の変化量(ΔRGi)
を計算する。
(2) ΔRGi<0で、|ΔRG|が最大の発電機(Gi)を
選択する。
(3) 発電機Giの出力を調整幅ΔPだけ変化させる。Next, the processing of each unit will be described. First, the processing in the generator output adjusting unit 2 will be described.
The rough processing here is as follows. (1) For each generator, the amount of change in the RG index (ΔRGi) when the output is changed by a fixed amount (generator output adjustment range ΔP)
To calculate. (2) When ΔRGi <0, select the generator (Gi) with the largest | ΔRG |. (3) The output of the generator Gi is changed by the adjustment width ΔP.
【0045】(4) ΔRGi<0になる発電機が存在しな
くなるまで、上記(1)〜(3)の処理を繰り返す。
(5) 全ての発電機についてΔRGi≧0となったら、調
整幅ΔPを小さくする。
(6) ΔPがしきい値(発電機出力調整幅しきい値δ)より
小さくなるまで、上記(1) 〜(5)の処理を繰り返す。
(7) 調整幅ΔPがしきい値δより小さくなったら処理を
終了する。(4) The above processes (1) to (3) are repeated until there is no generator with ΔRGi <0. (5) When ΔRGi ≧ 0 for all generators, decrease the adjustment width ΔP. (6) The above processes (1) to (5) are repeated until ΔP becomes smaller than the threshold value (generator output adjustment width threshold value δ). (7) When the adjustment width ΔP becomes smaller than the threshold value δ, the process ends.
【0046】次に、以上の発電機出力調整部2での詳細
な処理の流れを、図3のPAD図に従って説明する。
(1) 初期処理
・調整幅パラメータΔPの初期値をパラメータデータベ
ース部13から読み出す。
・しきい値パラメータδの初期値をパラメータデータベ
ース部13から読み出す。
・系統状態データベース部11の潮流データをRG指標
計算用潮流データにコピーする。Next, the detailed processing flow in the generator output adjusting section 2 will be described with reference to the PAD diagram of FIG. (1) The initial value of the initial processing / adjustment width parameter ΔP is read from the parameter database unit 13. Read the initial value of the threshold parameter δ from the parameter database unit 13. -Copies the tidal current data of the grid state database unit 11 to the tidal current data for RG index calculation.
【0047】(2) 調整幅ΔP≧δである間、以下の(3)
〜(17)の処理を繰り返す。
(3) RG指標計算部3にRG指標計算起動信号を出力
し、RG指標値RG0データを受け取る。
・発電機出力調整前RG指標RG0の計算。
(4) 全ての調整対象発電機に対して、以下の(5)〜(12)
の処理を繰り返す。
・選択された発電機をGiとおく。(2) While the adjustment width ΔP ≧ δ, the following (3)
The processing from (17) is repeated. (3) The RG index calculation start signal is output to the RG index calculation unit 3, and the RG index value RG0 data is received. -Calculation of RG index RG0 before generator output adjustment. (4) For all generators subject to adjustment,
The process of is repeated. -Set the selected generator as Gi.
【0048】(5) 系統状態データベース部11から、発
電機出力上下限データと固定供給力出力データ、送電線
潮流制約データ、それに総需要データをそれぞれ読み出
し、発電機Giの出力値を調整幅ΔP増加させ、その値
を固定供給力出力データに加えて、潮流制約付発電コス
ト最小化潮流データ生成部4へ送り、潮流データを受け
取る。(5) The generator output upper and lower limit data, the fixed supply capacity output data, the transmission line power flow constraint data, and the total demand data are read out from the system state database unit 11, and the output value of the generator Gi is adjusted by ΔP. The value is increased, and the value is added to the fixed supply power output data, and is sent to the tidal current data generation unit 4 with the tidal current constraint to minimize power generation cost, and the tidal current data is received.
【0049】・受け取った潮流データは、発電機Giの
出力値を調整幅ΔPだけ増加させたときの潮流データと
なる。
(6) RG指標計算用潮流データを更新する。
(7) RG指標計算部3にRG指標計算起動信号を出力
し、RG指標値RGi+ データを受け取る。
・発電機Gi出力調整後のRG指標RGi+ を計算す
る。The received tidal current data becomes tidal current data when the output value of the generator Gi is increased by the adjustment width ΔP. (6) Update the power flow data for RG index calculation. (7) The RG index calculation start signal is output to the RG index calculation unit 3 and the RG index value RGi + data is received. -Calculate the RG index RGi + after adjusting the generator Gi output.
【0050】(8) ΔRGi+ =RGi+−RG0とお
く。
(9) 系統状態データベース部11から、発電機出力上下
限データ、固定供給力出力データ、送電線潮流制約デー
タ、総需要データを読み出し、発電機Giの出力値をΔ
P減少させた値を固定供給力出力データに加えて、潮流
制約付発電コスト最小化潮流データ生成部4へ送り、潮
流データを受け取る。
・受け取った潮流データは、発電機Giの出力値を調整
幅ΔPだで減少させたときの潮流データとなる。(8) Let ΔRGi + = RGi + -RG0. (9) The generator output upper / lower limit data, fixed supply capacity output data, transmission line power flow constraint data, and total demand data are read from the system state database unit 11 and the output value of the generator Gi is Δ.
The value reduced by P is added to the fixed supply power output data, and is sent to the tidal current data generation unit 4 with the tidal current constraint to minimize power generation cost, and the tidal current data is received. The received power flow data becomes the power flow data when the output value of the generator Gi is reduced by the adjustment width ΔP.
【0051】(10) RG指標計算用潮流データを更新す
る。
(11) RG指標計算部3にRG指標計算起動信号を出力
し、RG指標値RGi-データを受け取る。
・発電機Gi出力調整後のRG指標RGi- を計算す
る。(10) Update the tide flow data for RG index calculation. (11) The RG index calculation start signal is output to the RG index calculation unit 3, and the RG index value RGi - data is received. And generator Gi output adjusted for RG indicators RGi - calculated.
【0052】(12) ΔRGi- =RGi-−RG0とお
く。(12) Set ΔRGi − = RGi − −RG0.
【0053】(13) ΔRGi+、ΔRGi- の最小値を選
択し、ΔRGix とおく。
(14)ΔRGix≧0ならばΔPを更新し、(2)の処理に
戻る。
・例えば、ΔP=ΔP/2とすることが考えられる。(13) The minimum value of ΔRGi + and ΔRGi − is selected and set as ΔRGi x . (14) If ΔRGix ≧ 0, ΔP is updated, and the process returns to (2). -For example, it can be considered that ΔP = ΔP / 2.
【0054】(15) ΔRGix <0ならば発電機Giの
出力を更新し、(2)の処理に戻る。
・x=+なら、系統状態データベース部11から、発電
機出力上下限データと固定供給力出力データ、送電線潮
流制約データ、それに総需要データをそれぞれ読み出
し、発電機Giの出力値をΔPだけ増加させ、その値を
固定供給力出力データに加えて潮流制約付発電コスト最
小化潮流データ生成部4に送り、潮流データを受け取っ
て、系統状態データベース中の潮流データとして格納す
る。(15) If ΔRGi x <0, the output of the generator Gi is updated, and the process returns to (2).・ If x = +, the generator output upper / lower limit data, fixed supply capacity output data, transmission line power flow constraint data, and total demand data are read from the system state database unit 11, and the output value of the generator Gi is increased by ΔP. Then, the value is added to the fixed supply power output data and is sent to the power flow cost minimizing power generation cost minimizing power flow data generation unit 4, and the power flow data is received and stored as the power flow data in the system state database.
【0055】・x=−なら、系統状態データベース部1
1から、発電機出力上下限データと固定供給力出力デー
タ、送電線潮流制約データ、それに総需要データをそれ
ぞれ読み出し、発電機Giの出力値をΔPだけ減少させ
た値を固定供給力出力データに加えて潮流制約付発電コ
スト最小化潮流データ生成部4に送り、潮流データを受
け取って、系統状態データベース中の潮流データとして
格納する。If x =-, system state database unit 1
From 1, the generator output upper and lower limit data, the fixed supply power output data, the transmission line power flow constraint data, and the total demand data are read, and the value obtained by reducing the output value of the generator Gi by ΔP is set as the fixed supply power output data. In addition, the power generation cost with power flow restriction is sent to the power flow data generation unit 4 to minimize the power flow data, and the power flow data is received and stored as the power flow data in the system state database.
【0056】(16) 発電機出力調整終了
・系統状態データベース中の潮流データに示された各発
電機出力値が、調整結果となる。(16) Completion of Generator Output Adjustment / Each generator output value shown in the tidal current data in the system state database is the adjustment result.
【0057】次に、RG指標計算部3での処理の流れ
を、図4に示すPAD図に従って説明する。
(1) 故障データベース部12で与えられる全ての故障ケ
ースについて、以下の(2)〜(12)の処理を行う。
・選択された故障ケースをFiとおく。
(2) 故障ケースFiが系統分断を発生させる場合は(3)
の処理を行い、系統分断を発生させない場合は(4)〜(9)
の処理を行う。Next, the flow of processing in the RG index calculator 3 will be described with reference to the PAD diagram shown in FIG. (1) The following processes (2) to (12) are performed for all the failure cases given by the failure database unit 12. -Set the selected failure case as Fi. (2) If the failure case Fi causes system disruption (3)
(4) to (9) when processing is performed and system division does not occur
Process.
【0058】(3) 系統状態データベース部11中の各分
断点許容電源脱落量データから故障ケースFiの故障点
の周波数低下側系統の許容電源脱落量を読み出し、ま
た、RG指標計算用潮流データから故障点の故障前潮流
量を読み出して、これらを系統分断時負荷遮断量計算へ
送り、系統分断時負荷遮断量データを受け取る。(3) The allowable power loss amount of the frequency lowering side system at the failure point of the failure case Fi is read from the data of the allowable power loss amount of each break point in the system status database unit 11, and from the RG index calculation power flow data. The pre-fault tidal flow rate at the failure point is read out, sent to the load cutoff amount calculation at the time of system disconnection, and the load cutoff amount data at the time of system disconnection is received.
【0059】(4) 系統状態データベース部11から読み
出した系統構成データとRG指標計算用潮流データを電
制機決定部6に送り、電制機データを受け取る。
(5) 電制機の出力値をRG指標計算用潮流データから読
み取って電制量計算へ送り、電制量データを受け取る。
(6) 系統状態データベース部11から読み出す許容電制
量データと電制量データを電制時負荷遮断量計算へ送
り、電制時負荷遮断量データを受け取る。(4) The system configuration data and the RG index calculation power flow data read from the system state database unit 11 are sent to the electronic control unit determination unit 6, and the electronic control unit data is received. (5) Read the output value of the electric control device from the power flow data for RG index calculation, send it to the electric control amount calculation, and receive the electric control amount data. (6) The allowable electric power control amount data and the electric power control amount data read from the system state database unit 11 are sent to the electric load control load shedding amount calculation, and the electric power control load shedding amount data is received.
【0060】(7) 系統状態データベース部11から、発
電機出力上下限データと固定供給力出力データ、送電線
潮流制約データ、それに総需要データをそれぞれ読み出
し、電制機の出力を0とした固定供給力出力データを加
えて、潮流制約付発電コスト最小化潮流データ生成部4
へ送り、潮流データを受け取る。
(8) RG指標計算用潮流データを更新する。(7) The generator output upper and lower limit data, fixed supply capacity output data, transmission line power flow constraint data, and total demand data are read from the system state database unit 11 and fixed to 0 for the output of the electric control unit. The power flow data generation unit 4 that adds power output data and minimizes power generation cost with power flow constraint
To receive the current data. (8) Update the tide flow data for RG index calculation.
【0061】(9) RG指標計算用潮流データから各発電
機出力値を読み出し、系統状態データベース部11から
各発電機の発電コスト特性データを読み出して、総発電
コスト計算部10へ送り、総発電コストを受け取る。
(10) 系統分断時負荷遮断量と電制時負荷遮断量を合計
し、負荷遮断量とする。
(11) 負荷遮断量を負荷遮断量コスト換算部9へ送り、
負荷遮断量コストデータを受け取る。
(12) 負荷遮断量コストと総発電コストを合計し、これ
に故障ケースFiに付与されている重み係数を乗じる。
・結果をRGiとおく。
(13) 全てのRGiを合計し、これをRG指標とする。(9) Each generator output value is read from the RG index calculation power flow data, and the power generation cost characteristic data of each generator is read from the system state database unit 11 and sent to the total power generation cost calculation unit 10 for total power generation. Receive the cost. (10) Add the load shedding amount when the system is divided and the electric system load shedding amount to obtain the load shedding amount. (11) Send the load shedding amount to the load shedding amount cost conversion unit 9,
Receive load shed cost data. (12) The load cutoff cost and the total power generation cost are summed up, and this is multiplied by the weighting factor given to the failure case Fi.・ Set the result as RGi. (13) Add all RGi and use this as the RG index.
【0062】次に、潮流制約付発電コスト最小化潮流デ
ータ生成部4の処理について説明する。まず、このとき
の送電線潮流制約がない場合の処理としては、一般にラ
グランジェの未定係数法を用いた方法が知られており、
これについては、例えば、関根泰次 他4名 著、「電力
系統工学」コロナ社、昭和54年3月発行に詳細に開示
されている。Next, the processing of the power flow data generator 4 with the power flow cost with power flow constraint minimized will be described. First, as a process when there is no power flow line constraint at this time, a method using Lagrange's undetermined coefficient method is generally known,
This is disclosed in detail in, for example, Yasuji Sekine and 4 others, "Electrical Power System Engineering", published by Corona Publishing Co., March, 1979.
【0063】そして、この方法では、総発電量が総需要
と一致し、かつ出力調整対象の各発電機の増分運転費
(ある出力で運転中に、出力を単位量だけ増加させるの
に必要な運転費)が等しくなるように各発電機の出力を
決めるようになっている。ここで、増分運転費の関数が
有界でなければ、必ずそのような出力値が存在する。In this method, the total amount of power generation matches the total demand, and the incremental operating cost of each generator whose output is to be adjusted.
The output of each generator is determined so that (the operating cost required to increase the output by a unit amount while operating at a certain output) becomes equal. Here, if the function of the incremental operating cost is not bounded, such an output value always exists.
【0064】しかし、この場合でも、求まった出力値が
各発電機出力の上下限値から外れる可能性がある。しか
して、この場合でも、上限を越えた発電機については、
その出力を上限値と設定して出力調整対象発電機から除
外し、総需要からその発電量を差し引いた需要量と、残
りの出力調整対象発電機について再度ラグランジェの未
定係数法を適用し、これを繰り返し行うことで、各発電
機の出力上下限を考慮した出力値が決定できる。However, even in this case, the obtained output value may deviate from the upper and lower limit values of each generator output. And, even in this case, for generators that exceed the upper limit,
The output is set as the upper limit value and excluded from the generators subject to output adjustment, the demand amount obtained by subtracting the generated amount from the total demand and the remaining generators subject to output adjustment are again applied with Lagrange's undetermined coefficient method, By repeating this, the output value considering the upper and lower limits of the output of each generator can be determined.
【0065】本発明でも、系統状態データベースで与え
られる発電コスト特性データは、各発電機の出力に対す
る運転費を与えるものであり、従って、これを用いるこ
とにより各発電機の増分運転費を求め、ラグランジェの
未定係数法を適用することができる。Also in the present invention, the power generation cost characteristic data given in the system state database gives the operating cost for the output of each generator. Therefore, by using this, the incremental operating cost of each generator is obtained, Lagrange's undetermined coefficient method can be applied.
【0066】そこで、この実施形態における潮流制約付
発電コスト最小化潮流データ生成部4では、与えられた
発電機出力上下限制約、固定供給力出力制約、送電線潮
流制約、総需要制約を満たす範囲内で、総発電コストが
最小となるような潮流データを生成するようになってい
る。すなわち、ある1系統の送電線Lに潮流制約がある
場合の処理は次の通りである。Therefore, the power flow cost-minimized power flow data generation unit 4 in this embodiment satisfies the given generator output upper / lower limit constraint, fixed supply power output constraint, transmission line power flow constraint, and total demand constraint. The power flow data is generated so that the total power generation cost is minimized. That is, the processing when there is a power flow restriction on the transmission line L of a certain system is as follows.
【0067】(1) 総発電コストを最小化する発電機出力
を等増分燃料費法により求める。
(2) 求められた各発電機出力での各送電線の潮流量を計
算する。
(3) 送電線Lの潮流量が潮流制約以下の場合は、ここで
処理を終了し、そうでない場合は(4)以下の処理を行
う。
(4) 送電線Lの受電側系統内で、総需要=受電側系統内
総発電量+送電線Lの潮流制約超過量として、等増分燃
料費法を適用し、各発電機出力を求める。(1) The generator output that minimizes the total power generation cost is calculated by the equal incremental fuel cost method. (2) Calculate the tidal flow of each transmission line at the obtained output of each generator. (3) If the tidal flow rate of the power transmission line L is less than or equal to the tidal flow constraint, the process ends here, and if not, the process of (4) or less is performed. (4) In the power receiving side system of the power transmission line L, the equal incremental fuel cost method is applied to obtain each generator output, with the total demand = total power generation in the power receiving side system + the power flow constraint excess amount of the power transmission line L.
【0068】(5) 送電線Lの送電側系統内で、総需要=
送電側系統内総発電量−送電線Lの潮流制約超過量とし
て、等増分燃料費法を適用し、各発電機出力を求める。
一方、潮流制約のある送電線が複数系統ある場合は、予
め付与されている優先順位に従って、順次上記の処理を
実行することにより、全ての潮流制約を考慮するのであ
る。(5) Total demand in the transmission side system of the transmission line L =
The equal incremental fuel cost method is applied as the total power generation amount in the power transmission side system-the power flow constraint excess amount of the power transmission line L to obtain each generator output.
On the other hand, when there are a plurality of transmission lines with power flow restrictions, all the power flow restrictions are considered by sequentially executing the above processing in accordance with the priority order given in advance.
【0069】次に、系統分断時負荷遮断量計算部5の処
理について説明すると、ここでの系統分断時負荷遮断量
は、与えられた周波数低下側系統許容電源脱落量と故障
点故障前潮流量から次の式によって計算するようになっ
ている。
系統分断時負荷遮断量=故障点故障前潮流量−周波数低
下側系統許容電源脱落量Next, the processing of the load interruption amount calculation part 5 at the time of system disconnection will be explained. Here, the load interruption amount at the time of system disconnection is the given frequency drop side system allowable power supply dropout amount and the failure point tidal flow before failure. Is calculated by the following formula. Load cutoff amount during system disconnection = Failure point Tide flow rate before failure-Frequency reduction side system allowable power supply dropout amount
【0070】次に、電制機決定部6での処理について説
明する。なお、電制機とは、電制される発電機のことで
ある。Next, the processing in the electronic control device determining section 6 will be described. The electronically controlled machine is a power generator that is electrically controlled.
【0071】ここで、故障ケースFiに対する電制機の
決定方式としては、例えばその一方式が、電気学会論文
誌B115巻、1号、平成7年1月「オンライン安定度
計算による脱調未然防止システム(TSC)の開発」で詳
細に述べられているが、本発明の実施形態による電制機
決定部6の処理も、この方式を採用しており、その内容
は、以下の通りである。Here, as a method of determining the electric control device for the failure case Fi, for example, one of the methods is the Institute of Electrical Engineers of Japan, Volume B115, No. 1, January 1995. As described in detail in "Development of system (TSC)", the processing of the electric machine controller 6 according to the embodiment of the present invention also employs this method, and the contents thereof are as follows.
【0072】まず、電制機を求める対象となる故障ケー
スを想定し、それをFiとする。そして、故障ケースF
iの電制機無しの場合の過渡安定度計算を行い、安定か
否かを判定する。そして、もし安定であれば、この想定
故障に対する電制機は無しと決定する。しかして、不安
定であれば、過渡安定度計算の結果から電制効果が最大
と思われる発電機を1台選択する。これが1台目の電制
機である。First, assume a failure case for which an electric control machine is to be obtained, and let it be Fi. And the failure case F
The transient stability calculation is performed in the case where there is no electric control device of i, and it is determined whether or not it is stable. If it is stable, it is determined that there is no electric control device for this contingency. Then, if it is unstable, one generator that has the maximum electric control effect is selected from the results of the transient stability calculation. This is the first electric control machine.
【0073】次に、今度は所定のタイミングで、先に選
択された発電機の遮断シークエンスを挿入し、再び過渡
安定度計算を行って、安定度判定を行う。そして、もし
安定であれば、現在得られている電制機がこの想定故障
に対する電制機の全てであることになる。Next, at a predetermined timing, the interruption sequence of the previously selected generator is inserted, the transient stability is calculated again, and the stability is judged. And, if stable, the electric control machines currently obtained are all the electric control machines for this contingency.
【0074】しかして、今度も不安定であれば、過渡安
定度計算の結果から電制効果が最大と思われる発電機を
さらに1台選択する。これが2台目の電制機である。以
下、この処理を過渡安定度計算の結果が安定となるまで
繰り返すことにより故障ケースFiに対する電制機を決
定することができる。こうして電制機が決定されたら、
電制量計算部7では、上記したように、これらの電制機
の出力値を合計し、電制量が計算される。If it is unstable again, one more generator is considered to have the maximum electric control effect from the result of the transient stability calculation. This is the second electric control machine. Thereafter, this process is repeated until the result of the transient stability calculation becomes stable, so that the electric control device for the failure case Fi can be determined. Once the electric control machine is decided in this way,
As described above, the electric control amount calculation unit 7 sums the output values of these electric control devices to calculate the electric control amount.
【0075】次に、電制時負荷遮断量計算部8での処理
について説明する。ここでの電制時負荷遮断量は、与え
られた電制量と許容電制量を用いて、次の式によって計
算する。
電制時負荷遮断量=電制量−許容電制量Next, the processing in the load shedding amount calculation section 8 during electric control will be described. The load shedding amount under electric control here is calculated by the following formula using the given electric control amount and the allowable electric control amount. Electric load shedding amount = Electric control amount-Allowable electric control amount
【0076】次に、負荷遮断量コスト換算部9での処理
について説明する。ここでの負荷遮断量のコスト換算
は、予めパラメータデータベース部13に設定してある
単位電力量kWh当りのコスト(負荷遮断量コスト換算
定数データ)を負荷遮断量に乗じて負荷遮断量コストと
するのである。Next, the processing in the load cutoff amount cost conversion unit 9 will be described. In the cost conversion of the load shedding amount here, the cost per unit electric energy kWh (load shedding amount cost conversion constant data) preset in the parameter database unit 13 is multiplied by the load shedding amount to obtain the load shedding amount cost. Of.
【0077】次に、総発電コスト計算部10での処理に
ついて説明する。ここでの処理は、与えられた各発電機
の発電コスト特性データを用いることにより、各発電機
の出力値に対する発電コストを求め、これを全ての発電
機について合計することにより、総発電コストを計算す
る処理である。Next, the processing in the total power generation cost calculation unit 10 will be described. The process here is to obtain the power generation cost for each generator output value by using the given power generation cost characteristic data of each generator, and sum this for all generators to obtain the total power generation cost. This is a calculation process.
【0078】従って、以上の実施形態によれば、与えら
れた系統状態及び各種制約条件のもとで、ルート断時及
びルート断以外時の負荷遮断量及び総発電コスト増加量
を計算してコスト換算し、これに各故障ケース毎の重み
係数を乗じて平常時の総発電コストとの合計からなるR
G指標が得られることになる。Therefore, according to the above-described embodiment, the load cutoff amount and the total power generation cost increase amount at the time of the route disconnection and at the time other than the route disconnection are calculated under the given system state and various constraint conditions to reduce the cost. R, which is calculated by multiplying it by the weighting factor for each failure case and the total power generation cost in normal times
The G index will be obtained.
【0079】そして、このRG指標とは、上記したよう
に、平常時総発電コストと、コストで換算した故障時損
失期待値を合計したものなので、このRG指標が小さい
程、その電力系統の運用コストが低いことになり、且
つ、それはコストを考慮したもとなっているので、電力
系統の運用の適否を的確に表す適切な評価指標となって
おり、従って、上記実施形態によれば、極めて的確に電
力系統の評価を得ることができる。As described above, this RG index is the sum of the normal total power generation cost and the expected loss loss at the time of cost conversion. Therefore, the smaller this RG index, the more the operation of the power system. Since the cost is low and the cost is taken into consideration, it is an appropriate evaluation index that accurately represents the adequacy of the operation of the power system. Therefore, according to the above embodiment, An accurate evaluation of the power system can be obtained.
【0080】また、この結果、上記実施形態によれば、
このRG指標を最小化するのに必要な各発電機の出力が
計算できるので、電力系統を常に最良な状態で運用する
ことができる。As a result, according to the above embodiment,
Since the output of each generator required to minimize this RG index can be calculated, the power system can always be operated in the best condition.
【0081】次に、本発明の他の実施形態について説明
する。以下に説明する実施形態は、本発明を電力系統計
画支援装置として具体化したもので、送電線増設によっ
て得られる電力系統信頼度の向上及び総発電コストの削
減の程度を、上記した実施形態と同じく、本発明の特徴
であるRG指標を用いることにより、統一的に、且つ定
量的に計算し、評価することができるようにしたもので
ある。Next, another embodiment of the present invention will be described. The embodiment described below is one in which the present invention is embodied as a power system planning support device, and the degree of improvement of the power system reliability and reduction of the total power generation cost obtained by adding a transmission line are compared with those of the above-described embodiment. Similarly, by using the RG index, which is a feature of the present invention, it is possible to calculate and evaluate in a unified and quantitative manner.
【0082】まず、図5は、この実施形態の機能ブロッ
ク図で、この実施形態は、図1の実施形態に、制御部1
5と送電線増設効果計算部16、系統データ設定部1
7、送電線潮流制約計算部18を設けた上で、系統状態
データベース部11に代えて、増設前系統データベース
部19と増設後系統データベース部20、それにRG指
標計算用系統データ部21を設け、更に入出力部1の機
能とパラメータデータベース部13のデータ内容の一部
を変更したものであり、従って、他の構成は、図1の実
施形態と同じである。First, FIG. 5 is a functional block diagram of this embodiment. This embodiment is the same as the embodiment of FIG.
5, transmission line extension effect calculation unit 16, system data setting unit 1
7. In addition to the transmission line power flow constraint calculation unit 18, in place of the system state database unit 11, a system database unit before expansion 19, a system database unit after expansion 20, and a system data unit 21 for RG index calculation are provided, Further, the function of the input / output unit 1 and a part of the data content of the parameter database unit 13 are changed, and therefore the other configuration is the same as that of the embodiment of FIG.
【0083】入出力部1は、外部(運用者や他システム
など)から、この電力系統計画支援装置にのデータを取
り込み、また、この電力系統計画支援装置から外部にデ
ータを出力する働きをするもので、基本的には、図1の
実施形態と同じであるが、具体的には異なっていて、ま
ず外部からのシステム起動入力を制御部2に送るだけで
はなく、系統データ設定部17からの指示信号に従っ
て、送電線増設前後系統に関するデータを外部から取り
込み、系統データ設定部17に渡す働きをすると共に、
制御部15を介して受け取った送電線増設効果値ΔRG
を外部へ出力する働きをするものである。The input / output unit 1 has a function of fetching data from the outside (operator or other system) into the power system planning support apparatus and outputting data from the power system planning support apparatus to the outside. Basically, it is the same as the embodiment of FIG. 1, but is specifically different, not only by sending a system start input from the outside to the control unit 2 but also by the system data setting unit 17 In accordance with the instruction signal of, the data about the system before and after the transmission line extension is taken in from the outside and is passed to the system data setting unit 17, and
Transmission line extension effect value ΔRG received via control unit 15
Is output to the outside.
【0084】制御部15は、入出力部1を介して運用者
から与えられる送電線増設効果計算の起動信号によっ
て、まず送電線増設前後の系統に関するデータの増設前
系統データベース部19と増設後系統データベース部2
0への格納を系統データ設定部17に指示し、次に送電
線増設効果計算部16へ送電線増設効果計算起動信号を
送り、送電線増設効果値として、送電線増設前後のRG
指標の差ΔRGを受け取り、この送電線増設効果値ΔR
Gを入出力部1を介して外部に出力する働きをする。The control unit 15 first receives the transmission line extension effect calculation start signal given by the operator via the input / output unit 1, and firstly, the before-addition system database unit 19 and the after-addition system data unit 19 for the data regarding the system before and after the transmission line extension. Database part 2
0 is instructed to the system data setting unit 17, then a transmission line expansion effect calculation start signal is sent to the transmission line expansion effect calculation unit 16, and the RG before and after the transmission line expansion is set as the transmission line expansion effect value.
The difference ΔRG in the index is received, and this transmission line extension effect value ΔR
It functions to output G to the outside through the input / output unit 1.
【0085】送電線増設効果計算部16は、増設前系統
データベース部19から与えられる各種の条件データに
基づくRG指標と、増設後系統データベース部20から
与えられる各種の条件データに基づくRG指標の2種の
RG指標を、それぞれRG指標計算部3を用いて計算
し、更に、それらの差を計算して、送電線増設効果量と
して出力する働きをするもので、処理の詳細については
後述する。The transmission line extension effect calculation unit 16 has two types of RG indicators based on various condition data given from the pre-addition system database unit 19 and various condition data given from the post-addition system database unit 20. The RG index of each kind is calculated by using the RG index calculator 3, and the difference between them is calculated and output as the transmission line extension effect amount. The details of the process will be described later.
【0086】なお、ここで、増設前系統データベース部
19から与えられる各種の条件データとは、上述の通
り、系統構成データと初期潮流データ、総需要データ、
発電機出力上下限データ、固定供給力出力データ、発電
コスト特性データ、送電線潮流制約関連データ、分断点
許容電源脱落量データ、許容電制量データ、それに電制
テーブルデータのことである。Here, the various condition data provided from the pre-expansion system database unit 19 are, as described above, the system configuration data, the initial power flow data, the total demand data,
These are the generator output upper / lower limit data, fixed supply power output data, power generation cost characteristic data, transmission line power flow constraint related data, break point allowable power drop amount data, allowable power control amount data, and power control table data.
【0087】また、増設後系統データベース部20から
与えられる各種の条件データとは、これも上述の通り、
系統構成データと初期潮流データ、総需要データ、発電
機出力上下限データ、固定供給力出力データ、発電コス
ト特性データ、送電線潮流制約関連データ、分断点許容
電源脱落量データ、許容電制量データ、それに電制テー
ブルデータのことである。The various condition data given from the post-expansion system database section 20 are as described above.
System configuration data and initial power flow data, total demand data, generator output upper / lower limit data, fixed supply capacity output data, power generation cost characteristic data, transmission line power flow constraint related data, break point allowable power loss data, allowable power control data , And electronically controlled table data.
【0088】系統データ設定部17は、制御部15から
の起動信号を受け、以下に(a)〜(c)で示す3種の処理を
実行する。
(a) 入出力部1から送電線増設前系統に関する各種のデ
ータ(系統構成データ、初期潮流データ、総需要デー
タ、発電機出力上下限データ、固定供給力出力データ、
発電コスト特性データ、送電線潮流制約関連データ、分
断点許容電源脱落量データ、許容電制量データ、電制テ
ーブルデータ)を取り込み、増設前系統データベース部
19に格納する処理。The system data setting unit 17 receives the activation signal from the control unit 15 and executes the following three types of processing (a) to (c). (a) Various data (system configuration data, initial power flow data, total demand data, generator output upper and lower limit data, fixed supply capacity output data,
Power generation cost characteristic data, transmission line power flow restriction related data, break point allowable power supply drop amount data, allowable power control amount data, power control table data) are fetched and stored in the pre-expansion system database unit 19.
【0089】(b) 同じく入出力部1から、送電線増設後
系統に関する各種のデータ(系統構成データ、初期潮流
データ、総需要データ、発電機出力上下限データ、固定
供給力出力データ、発電コスト特性データ、送電線潮流
制約関連データ、分断点許容電源脱落量データ、許容電
制量データ、電制テーブルデータ)を取り込み、増設後
系統データベース部20に格納する処理。(B) Similarly, from the input / output unit 1, various data (system configuration data, initial power flow data, total demand data, generator output upper / lower limit data, fixed supply power output data, power generation cost) related to the system after the transmission line is added. Processing for loading characteristic data, transmission line power flow constraint related data, break point allowable power supply drop amount data, allowable power control amount data, power control table data) and storing it in the system database unit 20 after the expansion.
【0090】(c) 増設後系統データベース部20から、
系統構成データ、初期潮流データ、送電線潮流制約関連
データ、電制テーブルデータ、各分断点許容電源脱落量
データを送電線潮流制約計算部18に送り、各送電線潮
流制約関連データを再計算させ、その出力である各送電
線の潮流制約関連データを受け取り、増設後系統データ
ベース部19へ格納する処理。(C) From the system database section 20 after expansion,
The system configuration data, the initial power flow data, the transmission line power flow constraint related data, the electrical control table data, and each allowable break point allowable power loss amount data are sent to the transmission line power flow constraint calculation unit 18 to recalculate each transmission line power flow constraint related data. A process of receiving the output, the power flow constraint related data of each transmission line, and storing it in the system database unit 19 after the addition.
【0091】次に、送電線潮流制約計算部18は、与え
られた系統構成データ、初期潮流データ、送電線潮流制
約関連データ、電制テーブルデータ、各分断点許容電源
脱落量データに基づいて、各送電線の潮流制約関連デー
タを再計算し、それを出力する働きをするもので、その
際、電制機決定部6と協調して処理を行うようになって
いる。なお、処理の詳細については後述する。Next, the transmission line power flow constraint calculation unit 18 determines, based on the given system configuration data, initial power flow data, transmission line power flow constraint-related data, power control table data, and each break point allowable power loss amount data. It recalculates the power flow constraint related data of each power transmission line and outputs it, and at that time, the power flow constraint related data is processed in cooperation with the electronic control device determination unit 6. The details of the processing will be described later.
【0092】増設前系統データベース部19は、送電線
増設前の系統に関して、系統状態に関するデータや各種
制約条件に関するデータなど、RG指標の計算に必要な
データを管理するものである。そして、この増設前系統
データベース部19では、図6に示すように、送電線増
設前の系統構成データと初期潮流データ、総需要デー
タ、発電機出力上下限データ、固定供給力出力データ、
発電コスト特性データ、送電線潮流制約データ、分断点
許容電源脱落量データ、許容電制量データ、それに電制
テーブルデータを管理する。The pre-addition system database unit 19 manages data necessary for calculating the RG index, such as system state data and various constraint conditions regarding the system before transmission line expansion. Then, in the pre-expansion system database unit 19, as shown in FIG. 6, the system configuration data before the transmission line expansion, initial power flow data, total demand data, generator output upper and lower limit data, fixed supply power output data,
It manages power generation cost characteristic data, transmission line power flow constraint data, break point allowable power supply drop amount data, allowable power control amount data, and power control table data.
【0093】増設後系統データベース部20は、送電線
増設後の系統に関して、系統状態に関するデータや各種
制約条件に関するデータなど、RG指標の計算に必要な
データを管理するもので、増設前系統データベース部1
9と同じく、図6に示すように、送電線増設後の系統構
成データ、初期潮流データ、総需要データ、発電機出力
上下限データ、固定供給力出力データ、発電コスト特性
データ、送電線潮流制約関連データ、分断点許容電源脱
落量データ、許容電制量データ、電制テーブルデータを
管理するものである。The post-expansion system database unit 20 manages the data necessary for calculating the RG index, such as the data regarding the system state and the data regarding various constraints regarding the system after the extension of the transmission line. 1
As in Fig. 9, as shown in Fig. 6, system configuration data after transmission line expansion, initial power flow data, total demand data, generator output upper / lower limit data, fixed supply capacity output data, power generation cost characteristic data, transmission line power flow constraint It manages related data, break point allowable power supply drop amount data, allowable power control amount data, and power control table data.
【0094】ここで、これらデータベース部19、20
が管理するデータについて詳細に説明すると、以下の通
りである。系統構成データとは、送電線のインピーダン
スや発電機の定格容量などの系統設備の各定数、及び各
系統設備間の接続情報のことである。初期潮流データと
は、発電機や負荷や送電線など、各系統設備上の電気デ
ータ(有効電力、無効電力、電圧など)の初期値のことで
ある。総需要データとは、全ての負荷の有効電力を合計
した値のことである。Here, these database units 19 and 20
The details of the data managed by are as follows. The system configuration data is each constant of system equipment such as impedance of a transmission line and rated capacity of a generator, and connection information between each system equipment. The initial power flow data is an initial value of electrical data (active power, reactive power, voltage, etc.) on each system equipment such as a generator, a load, and a transmission line. The total demand data is a value obtained by summing active powers of all loads.
【0095】発電機出力上下限データとは、各発電機毎
に与えられる有効電力出力の上下限値のことである。固
定供給力出力データとは、幾つかの発電機に対して有効
電力出力値を指定するデータのことである。発電コスト
特性データとは各発電機の発電コストを出力に応じて与
えるデータのことである。The generator output upper and lower limit data is the upper and lower limit values of the active power output given to each generator. Fixed power output data is data that specifies active power output values for some generators. The power generation cost characteristic data is data that gives the power generation cost of each generator according to the output.
【0096】送電線潮流制約関連データとは、各送電線
の有効電力潮流量の上限を与えるデータのことであり、
熱容量面潮流制約データと周波数面潮流制約データ、及
び安定度面潮流制約データの3種のデータと、その最小
値で定義される送電線潮流制約データとで構成されてい
るものである。The transmission line power flow constraint related data is data which gives the upper limit of the active power flow rate of each transmission line,
The heat capacity surface power flow constraint data, the frequency surface power flow constraint data, and the stability surface power flow constraint data are three types of data, and the transmission line power flow constraint data defined by the minimum value thereof.
【0097】分断点許容電源脱落量データとは、系統を
分断する個所について、そこを分断したときに生じる2
系統の分断系統それぞれについて許容できる発電量不足
量上限値を与えるデータのことである。許容電制量デー
タとは、系統全体で許容できる発電量不足量上限値を与
えるデータのことである。Separation point Allowable power supply dropout amount data refers to a point where a system is divided, and occurs when the point is divided.
It is the data that gives the allowable upper limit of the amount of power generation insufficiency for each divided system. The allowable electricity control amount data is data that gives the upper limit value of the amount of power generation insufficiency that is allowable in the entire system.
【0098】電制テーブルデータとは、故障点・故障内
容と故障点潮流量しきい値を電制起動条件データとし、
これに対して電制機データを対応させるものであり、故
障内容とは1回線事故や3相4線地絡などを表すデータ
で、故障点潮流量しきい値とは実際の故障点潮流量がそ
の値を越えた場合に電制を実施するという基準値のこと
である。The electronically controlled table data is the electrically controlled starting condition data including the failure point / failure content and the failure point tide flow rate threshold value,
On the other hand, the electric machine data is made to correspond, and the failure content is data representing a one-line accident, a three-phase four-wire ground fault, etc., and the failure point tide flow rate threshold is the actual failure point tide flow rate. Is the standard value that the electronic control is implemented when the value exceeds that value.
【0099】RG指標計算用系統データ部21は、RG
指標を計算する対象系統に関して、系統構成データ、初
期潮流データ、総需要データ、発電機出力上下限デー
タ、固定供給力出力データ、発電コスト特性データ、送
電線潮流制約データ、分断点許容電源脱落量データ、許
容電制量データ、電制テーブルデータを管理するもので
ある。The RG index calculation system data section 21 is
Regarding the target system for which the index is calculated, system configuration data, initial power flow data, total demand data, generator output upper and lower limit data, fixed supply capacity output data, power generation cost characteristic data, transmission line power flow constraint data, break point allowable power loss It manages data, allowable power control data, and power control table data.
【0100】ここで、パラメータデータベース部13で
管理されるデータの内、負荷遮断量コスト換算定数デー
タについては、図1の実施形態と同じであるが、その他
のデータは送電線潮流量調整幅データになっている点
で、異なっている。なお、その他のブロックについて
は、図1の実施形態と同じでなので、説明は割愛する。Among the data managed by the parameter database unit 13, the load cutoff amount cost conversion constant data is the same as that in the embodiment of FIG. 1, but the other data is the transmission line tide flow rate adjustment width data. It is different in that it has become. The other blocks are the same as those in the embodiment shown in FIG. 1 and therefore will not be described.
【0101】次に、送電線増設効果計算部16による処
理について、図7示すPAD図に従って説明する。
(1) 増設前系統データベース部14のデータを、RG指
標計算用系統データ部21にコピーする。
(2) RG指標計算用系統データ部21から、発電機出力
上下限データ、固定供給力出力データ、送電線潮流制約
データ、総需要データをそれぞれ読み出し、潮流制約付
発電コスト最小化潮流データ生成部4に送り、それから
潮流データを受け取る。Next, the processing by the transmission line extension effect calculation unit 16 will be described with reference to the PAD diagram shown in FIG. (1) Copy the data of the pre-expansion system database section 14 to the RG index calculation system data section 21. (2) The generator output upper / lower limit data, fixed supply capacity output data, transmission line power flow constraint data, and total demand data are read from the RG index calculation system data unit 21, respectively, and the power flow cost with power flow constraint minimizes the power flow data generation unit. 4 and then receive the tidal current data.
【0102】(3) 受け取った潮流データにより、RG指
標計算用潮流データ部14のデータを更新する。
(4) RG指標計算部3にRG指標計算起動信号を出力
し、それからRG指標値RG0データを受け取る。
(5) 増設後系統データベース部20のデータを、RG指
標計算用系統データ部21にコピーする。
(6) RG指標計算用系統データ部21から、発電機出力
上下限データ、固定供給力出力データ、送電線潮流制約
データ、総需要データをそれぞれ読み出し、潮流制約付
発電コスト最小化潮流データ生成部4に送り、それから
潮流データを受け取る。(3) Update the data of the RG index calculation power flow data section 14 with the received power flow data. (4) The RG index calculation start signal is output to the RG index calculation unit 3, and the RG index value RG0 data is received therefrom. (5) Copy the data of the system database section 20 after the expansion to the system data section 21 for RG index calculation. (6) The generator output upper and lower limit data, the fixed supply capacity output data, the transmission line power flow constraint data, and the total demand data are read from the RG index calculation system data unit 21, respectively, and the power generation cost minimized power flow data generator with the power flow constraint is read. 4 and then receive the tidal current data.
【0103】(7) 受け取った潮流データによって、RG
指標計算用潮流データ部14を更新する。
(8) RG指標計算部4にRG指標計算起動信号を出力
し、それからRG指標値RG1データを受け取る。
(9) ΔRG=RG1−RG0とおく。
(10) このΔRGを、送電線増設効果量として出力す
る。
ここで、RG指標計算部3によるRG指標処理は、既に
図1の実施形態において、図4に示すPAD図を用いて
説明した通りである。(7) According to the received power flow data, RG
The index calculation power flow data unit 14 is updated. (8) The RG index calculation start signal is output to the RG index calculation unit 4, and the RG index value RG1 data is received therefrom. (9) Set ΔRG = RG1-RG0. (10) This ΔRG is output as the transmission line extension effect amount. Here, the RG index processing by the RG index calculation unit 3 is as already described with reference to the PAD diagram shown in FIG. 4 in the embodiment of FIG.
【0104】次に、送電線潮流制約計算部18による処
理について、図8に示すPAD図に従って説明する。図
1の実施形態では、送電線潮流制約データが、予め定数
として系統状態データベース部11に格納されている
が、この図5の実施形態では、送電線の増設を前提とし
ているので、定数として与えることができない。そこ
で、この図5の実施形態では、送電線潮流制約計算部1
8を設け、これにより、以下のようにして、送電線潮流
制約データが与えられるようにしているのである。Next, the processing by the transmission line power flow constraint calculation unit 18 will be described with reference to the PAD diagram shown in FIG. In the embodiment of FIG. 1, the transmission line power flow restriction data is stored in advance in the system state database unit 11 as a constant, but in the embodiment of FIG. 5, since it is premised on the addition of transmission lines, it is given as a constant. I can't. Therefore, in the embodiment of FIG. 5, the transmission line power flow constraint calculation unit 1
8, the transmission line power flow constraint data is given in the following manner.
【0105】(1) 初期処理
・系統構成データ、潮流データ、送電線潮流制約関連デ
ータ、電制テーブルデータ、各分断点許容電源脱落量デ
ータを受け取る。
・送電線潮流量調整幅データを、パラメータデータベー
ス部13から読み出し、これをΔPとする。
・P=−ΔPとする。(1) Initial processing / system configuration data, power flow data, transmission line power flow constraint-related data, power control table data, and each break point allowable power supply drop amount data are received. The power flow adjustment width data of the power transmission line is read from the parameter database unit 13 and is set as ΔP.・ P = −ΔP.
【0106】(2) 全ての送電線Liについて、以下の
(3)〜(9)の処理を行う。
(3) 送電線Liを故障点とする安定化不可能な故障ケー
スが存在するまで、(4)〜(7)の処理を行う。
(4) P=P+ΔPとする。
(5) 与えられた潮流データ中の送電線Liの受電側ノー
ドに+P、送電側ノードに−Pの負荷を追加設置する。
・送電線Liの潮流量PLiをP増加させる。(2) For all transmission lines Li,
Perform steps (3) to (9). (3) The processes (4) to (7) are performed until there is an unstabilizable failure case where the transmission line Li is the failure point. (4) P = P + ΔP. (5) A load of + P is additionally installed at the power receiving side node of the power transmission line Li in the given power flow data, and a load of −P is additionally installed at the power transmitting side node. -Increase the tidal flow rate PLi of the power transmission line Li by P.
【0107】(6) 故障データベース部12で与えられる
送電線Liを故障点とする全ての故障ケースについて、
(7)の処理を行う。
・選択された故障ケースをFjとおく。(6) For all the failure cases where the transmission line Li given by the failure database unit 12 is the failure point,
Perform the processing of (7). -Set the selected failure case as Fj.
【0108】(7) 故障ケースFjのデータと、与えられ
た系統構成データ、与えられた電制テーブルデータ、そ
れに(5)の処理で修正した後の潮流データとを電制機決
定部6に送り、決定した電制機の電制により安定化が可
能か否かの結果を得る。(7) The data of the failure case Fj, the given system configuration data, the given electric control table data, and the tidal current data corrected by the processing of (5) are sent to the electric control device deciding unit 6. Send and obtain the result of whether stabilization is possible by the electric control of the decided electric control machine.
【0109】(8) P−ΔPを、送電線Liの安定度面潮
流制約値PLi3 とする。
(9) 送電線Liの熱容量面潮流制約データPLi1 を、
与えられた各送電線潮流制約関連データから読み出す。
(10) 送電線Liがループ系統の一部を構成している場
合は(11)の処理を行い、そうでない場合は(12)の処理を
行う。(8) Let P-ΔP be the stability surface power flow constraint value PLi 3 of the transmission line Li. (9) The heat capacity surface flow constraint data PLi 1 of the transmission line Li is
The data is read from the given power line constraint data. (10) If the power transmission line Li forms a part of the loop system, the process of (11) is performed, and if not, the process of (12) is performed.
【0110】(11) 送電線Liの周波数面潮流制約値P
Li2 を、max{PLi1、PLi3}として設定する。
(12) 与えられた各分断点許容電源脱落量データから、
送電線Liの周波数低下側系統の許容電源脱落量を読み
出し、これを送電線Liの周波数面潮流制約値PLi3
とする。
(13) 各送電線Liの潮流制約値PLiを、min{PLi
1、PLi2、PLi3}として設定する。(11) Frequency plane power flow constraint value P of transmission line Li
Li 2 is set as max {PLi 1 , PLi 3 }. (12) From the given data on the allowable amount of power loss for each break point,
The permissible power dropout amount of the frequency lowering system of the power transmission line Li is read out, and this is read as the frequency plane power flow constraint value PLi 3 of the power transmission line Li.
And (13) Set the power flow constraint value PLi of each transmission line Li to min {PLi
1 , PLi 2 , PLi 3 }.
【0111】(14) PLi1 を各送電線Liの熱容量面
潮流制約データ、PLi2 を周波数面潮流制約データ、
PLi3 を安定度面潮流制約データ、そして、PLiを
送電線潮流制約データとして設定し、それぞれを系統デ
ータ設定部17から各データ部19、20に出力する。(14) PLi 1 is heat capacity surface flow restriction data of each transmission line Li, PLi 2 is frequency surface flow restriction data,
PLi 3 is set as the stability surface power flow constraint data, and PLi is set as the transmission line power flow constraint data, and each is output from the system data setting unit 17 to the data units 19 and 20.
【0112】従って、この実施形態によれば、運用者の
指示により、入出力部1から随時、容易に送電線増設前
後のRG指標の差からなる送電線増設効果値ΔRGを得
ることができることになり、この結果、運用者は、この
送電線増設効果値ΔRGを評価することにより、定量
的、且つ統一的な指標のもとで、送電線増設が信頼度及
び経済性に及ぼす効果を的確に判定することができる。Therefore, according to this embodiment, the transmission line extension effect value ΔRG, which is the difference between the RG indices before and after the transmission line extension, can be easily obtained from the input / output unit 1 at any time by the operator's instruction. As a result, the operator evaluates the transmission line extension effect value ΔRG to accurately determine the effect of the transmission line extension on reliability and economic efficiency under a quantitative and uniform index. Can be determined.
【0113】[0113]
【発明の効果】本発明によれば、ルート断時とルート断
以外時の故障時損失をコスト換算し、故障ケース毎に重
み付きで合計して、これと平常時の総発電コストを合計
して得られるRG指標の大小によって、確率的な概念で
ある信頼性と経済性をコストという統一された指標で定
量的に評価することができる。According to the present invention, the loss at the time of failure at the time of the route disconnection and the time at the time of other than the route disconnection are cost-converted, weighted for each failure case and summed, and this and the total power generation cost at normal times are summed. The reliability and economic efficiency, which are probabilistic concepts, can be quantitatively evaluated with a unified index of costs, depending on the magnitude of the RG index obtained.
【0114】また、このRG指標を、送電線の増設前後
の電力系統のそれぞれについて計算し、その差を計算す
ることにより、送電線増設が信頼度及び経済性に及ぼす
効果を定量的に統一的な指標で評価することができる。
また、このとき、送電線増設後系統の各送電線の潮流制
約を再計算することにより、送電線増設による発電機出
力再配分による総発電コスト改善量の評価を、より正確
に得ることができる。Further, the RG index is calculated for each of the power systems before and after the transmission line is added, and the difference is calculated to quantitatively unify the effect of the transmission line addition on reliability and economy. It can be evaluated with various indicators.
Further, at this time, by recalculating the power flow constraint of each transmission line in the system after the transmission line is added, it is possible to more accurately obtain an evaluation of the total amount of power generation cost improvement by the generator output redistribution due to the addition of the transmission line. .
【図1】本発明の第1の実施形態を示す機能ブロック図
である。FIG. 1 is a functional block diagram showing a first embodiment of the present invention.
【図2】第1の実施形態においてデータベースとして用
いられている各種のデータの説明図である。FIG. 2 is an explanatory diagram of various data used as a database in the first embodiment.
【図3】本発明の実施形態における発電機出力調整部で
の処理フローの説明図である。FIG. 3 is an explanatory diagram of a processing flow in a generator output adjustment unit according to the embodiment of the present invention.
【図4】本発明の実施形態におけるRG指標計算部での
処理フローの説明図である。FIG. 4 is an explanatory diagram of a processing flow in an RG index calculation unit in the embodiment of the present invention.
【図5】本発明の第2の実施形態を示す機能ブロック図
である。FIG. 5 is a functional block diagram showing a second embodiment of the present invention.
【図6】本発明の第2の実施形態においてデータベース
として用いられている各種のデータの説明図である。FIG. 6 is an explanatory diagram of various data used as a database in the second embodiment of the present invention.
【図7】本発明の第2の実施形態における送電線増設効
果計算部での処理フローの説明図である。FIG. 7 is an explanatory diagram of a processing flow in a transmission line extension effect calculation unit according to the second embodiment of the present invention.
【図8】本発明の第2の実施形態における送電線潮流制
約計算部での処理フローの説明図である。FIG. 8 is an explanatory diagram of a processing flow in a transmission line power flow constraint calculation unit in the second embodiment of the present invention.
【符号の説明】 1 入出力部 2 制御部 3 RG指標計算部 4 潮流制約付発電コスト最小化潮流データ生成部 5 系統分断時負荷遮断量計算部 6 電制機決定部 7 電制量計算部 8 電制時負荷遮断量計算部 9 負荷遮断量コスト換算部 10 総発電コスト計算部 11 系統状態データベース部 12 故障データベース部 13 パラメータデータベース部 14 RC指標計算用潮流データ部 15 制御部 16 送電線増設効果計算部 17 系統データ設定部 18 送電線潮流制約計算部 19 増設前系統データベース部 20 増設後系統データベース部 21 RG指標計算用系統データ部[Explanation of symbols] 1 I / O section 2 control unit 3 RG index calculator 4 Power flow cost generation with power flow constraint to minimize power generation cost 5 Load cut-off amount calculation section for system disconnect 6 Electric control machine decision part 7 Electricity calculation section 8 Load shedding calculation section under electric control 9 Load cutoff cost conversion unit 10 Total power generation cost calculator 11 System status database section 12 Failure database section 13 Parameter database section 14 Power flow data section for RC index calculation 15 Control unit 16 Transmission line expansion effect calculation unit 17 System data setting section 18 Transmission line power flow constraint calculation unit 19 System database before expansion 20 System database after expansion 21 RG index calculation system data section
───────────────────────────────────────────────────── フロントページの続き (72)発明者 田村 滋 茨城県日立市大みか町五丁目2番1号 株式会社 日立製作所 大みか工場内 (72)発明者 田中 愁佳夫 大阪府大阪市北区中之島3丁目3番22号 関西電力株式会社内 (72)発明者 井上 忍 大阪府大阪市北区中之島3丁目3番22号 関西電力株式会社内 (56)参考文献 特開 平4−54828(JP,A) 特開 平8−196041(JP,A) 特開 昭62−155728(JP,A) 特開 昭61−210830(JP,A) (58)調査した分野(Int.Cl.7,DB名) H02J 3/00 - 5/00 H02J 13/00 - 13/00 311 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Shigeru Tamura 5-2-1 Omika-cho, Hitachi-shi, Ibaraki Hitachi Omika factory (72) Inventor Shikao Tanaka 3-chome Nakanoshima, Kita-ku, Osaka-shi, Osaka 3-22 Kansai Electric Power Co., Inc. (72) Inventor Shinobu Inoue 3-3-22 Nakanoshima, Kita-ku, Osaka-shi, Osaka Kansai Electric Power Co., Inc. (56) Reference JP-A-4-54828 (JP, A) JP-A-8-196041 (JP, A) JP-A-62-155728 (JP, A) JP-A-61-210830 (JP, A) (58) Fields investigated (Int.Cl. 7 , DB name) H02J 3/00-5/00 H02J 13/00-13/00 311
Claims (6)
手段と、ルート断以外故障時の発電機強制遮断による負
荷遮断量を計算する手段と、前記負荷遮断量をコスト換
算する手段と、前記故障時の発電機強制遮断による総発
電コストの変化量を計算する手段と、故障時の負荷遮断
コストと総発電コスト変化量を合算して、これを故障ケ
ース毎の重み係数により合算して故障時損失コストとす
る手段と、この故障時損失コストと平常時総発電コスト
を合算し、評価指標として出力する手段とで構成されて
いることを特徴とする電力系統評価装置。1. A means for calculating a load shedding amount at the time of a route disconnection failure, a means for calculating a load shedding amount due to a forced generator shutdown at the time of a failure other than a route disconnection, and a means for converting the load shedding amount into a cost. The means for calculating the amount of change in the total power generation cost due to forced shutdown of the generator at the time of failure, the load cutoff cost at the time of failure, and the total amount of power generation cost change are added together, and this is added by the weighting factor for each failure case. An electric power system evaluation device comprising: a failure loss cost means; and a means for adding the failure loss cost and the normal total power generation cost and outputting the cost as an evaluation index.
ート断以外の故障時での発電機強制遮断による負荷遮断
量の合計をコスト換算して求めた負荷遮断量コストに、
前記発電機強制遮断による総発電コストの変化量を合算
した値を故障時損失コストとした上で、この故障時損失
コストを故障ケース毎に付与される重み係数により合算
し、これを平常時の総発電コストと合算して電力系統の
評価指標とし、この評価指標が最小化されるように発電
機の出力を制御することを特徴とする電力系統潮流最適
化方法。2. The load cutoff amount cost obtained by converting the total load cutoff amount at the time of a route cutoff fault and the load cutoff amount at the time of a fault other than the route cutoff by the generator forced cutoff to a cost,
The value obtained by summing the change amount of the total power generation cost due to the forced shutoff of the generator is set as the loss cost at the time of failure, and this loss cost at the time of failure is added up by the weighting factor given to each failure case, which is A method for optimizing a power system power flow, comprising summing the total power generation cost to obtain a power system evaluation index, and controlling the generator output so that the evaluation index is minimized.
手段と、ルート断以外故障時の発電機強制遮断による負
荷遮断量を計算する手段と、前記負荷遮断量をコスト換
算する手段と、前記故障時の発電機強制遮断による総発
電コストの変化量を計算する手段と、故障時の負荷遮断
コストと総発電コスト変化量を合算して、これを故障ケ
ース毎の重み係数により合算して故障時損失コストとす
る手段と、この故障時損失コストと平常時総発電コスト
を合算し、評価指標として出力する手段と、この評価指
標を最小化するのに必要な各発電機の出力を計算する手
段とで構成されていることを特徴とする電力系統潮流最
適化装置。3. A means for calculating a load shedding amount at the time of a route disconnection failure, a means for calculating a load shedding amount due to a forced generator shutdown at the time of a failure other than a route disconnection, and a means for converting the load shedding amount into a cost. The means for calculating the amount of change in the total power generation cost due to forced shutdown of the generator at the time of failure, the load cutoff cost at the time of failure, and the total amount of power generation cost change are added together, and this is added by the weighting factor for each failure case. Calculates the loss cost at the time of failure, the means for adding the loss cost at the time of failure and the total power generation cost in normal times, and outputting it as an evaluation index, and the output of each generator required to minimize this evaluation index. A power system power flow optimizing device comprising:
オンラインで与える手段と、 現在の系統状態をオンラインで取り込む手段とを設けた
ことを特徴とする電力系統評価装置。4. The electric power supply system according to claim 1 , further comprising: a means for providing a current failure occurrence probability as a weighting factor for the failure case online, and a means for fetching a current system state online. System evaluation device.
オンラインで与える手段と、 現在の系統状態をオンラインで取り込む手段とを設けた
ことを特徴とする電力系統潮流最適化装置。5. The electric power supply system according to claim 3 , further comprising: a means for providing a current failure occurrence probability online as a weighting factor for the failure case and a means for capturing a current system state online. System power flow optimization device.
経済性の向上効果を評価する電力系統計画支援装置にお
いて、 ルート断故障時の負荷遮断量を計算する手段と、ルート
断以外故障時の発電機強制遮断による負荷遮断量を計算
する手段と、前記負荷遮断量をコスト換算する手段と、
前記故障時の発電機強制遮断による総発電コストの変化
量を計算する手段と、故障時の負荷遮断コストと総発電
コスト変化量を合算して、これを故障ケース毎の重み係
数により合算して故障時損失コストとする手段と、この
故障時損失コストと平常時総発電コストを合算し、評価
指標として出力する手段と、送電線増設後系統の各送電
線の潮流制約値を計算する手段と、送電線増設前後系統
の電力系統評価指標の差を前記の各手段を用いて計算す
る手段とで構成されていることを特徴とする電力系統計
画支援装置。6. A power system planning support apparatus for evaluating the improvement effect of reliability and economy by adding a transmission line of a power system, a means for calculating a load shedding amount at the time of a route disconnection failure, and a means for calculating a load disconnection amount at the time of a route disconnection failure. A means for calculating a load shedding amount due to the forced shutoff of the generator; a means for converting the load shedding amount into a cost;
The means for calculating the amount of change in the total power generation cost due to forced shutdown of the generator at the time of failure, the load cut-off cost at the time of failure, and the total amount of power generation cost change are added together, and this is added by the weighting factor for each failure case. There are means for calculating the loss cost at the time of failure, means for adding the loss cost at the time of failure and the total power generation cost for normal operation, and outputting as an evaluation index, and means for calculating the power flow constraint value of each transmission line in the system after the transmission line is added. And a means for calculating the difference between the power system evaluation indexes of the system before and after the transmission line extension by using each of the above means.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10947797A JP3399778B2 (en) | 1997-04-25 | 1997-04-25 | Power system evaluation device, power system power flow optimization method and device, and power system planning support method and device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10947797A JP3399778B2 (en) | 1997-04-25 | 1997-04-25 | Power system evaluation device, power system power flow optimization method and device, and power system planning support method and device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH10304565A JPH10304565A (en) | 1998-11-13 |
| JP3399778B2 true JP3399778B2 (en) | 2003-04-21 |
Family
ID=14511241
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP10947797A Expired - Fee Related JP3399778B2 (en) | 1997-04-25 | 1997-04-25 | Power system evaluation device, power system power flow optimization method and device, and power system planning support method and device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3399778B2 (en) |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4044512B2 (en) * | 2003-11-12 | 2008-02-06 | 三菱電機株式会社 | Power system stabilization control device and power system stabilization control method |
| JP5557525B2 (en) * | 2009-12-28 | 2014-07-23 | 株式会社日立製作所 | Wind power generation system and control method for wind power generation system |
| CN103532136A (en) * | 2013-10-16 | 2014-01-22 | 国网安徽省电力公司 | On-line computation and aid decision making system and on-line computation and aid decision making method for province-prefecture-country integrated network loss |
| US20160071013A1 (en) * | 2014-09-10 | 2016-03-10 | Mitsubishi Electric Research Laboratories, Inc. | Method for Estimating Optimal Power Flows in Power Grids using Consensus-Based Distributed Processing |
| JP6886414B2 (en) * | 2018-02-09 | 2021-06-16 | 株式会社日立製作所 | Market-ready reliability management device and its method and market management system |
| CN113191634A (en) * | 2021-04-29 | 2021-07-30 | 中国电力科学研究院有限公司 | Method and system for evaluating health state of electricity consumption behavior of industrial user |
| CN113986970B (en) * | 2021-10-25 | 2024-08-13 | 国网江苏省电力有限公司营销服务中心 | A method for detecting quantity and fee calculation results based on baseline library data |
| JP2025177248A (en) * | 2024-05-23 | 2025-12-05 | 株式会社日立製作所 | Power system stabilization device and power system stabilization method |
-
1997
- 1997-04-25 JP JP10947797A patent/JP3399778B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH10304565A (en) | 1998-11-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3932735A (en) | Method of controlling supply of power | |
| US6492801B1 (en) | Method, apparatus, and system for real time reactive power output monitoring and predicting | |
| US6625520B1 (en) | System and method for operating electric power systems utilizing optimal power flow | |
| US8290634B2 (en) | Optimizing system loss for a system of multiple windfarms | |
| EP2161444B1 (en) | Intra-area master reactive controller for tightly coupled windfarms | |
| EP2227847B1 (en) | Method for controlling a grid voltage | |
| JP4094206B2 (en) | Power system stabilizer | |
| JP2007288877A (en) | Power quality maintenance support method and power quality maintenance support system for a distribution system in which a plurality of distributed power sources are connected | |
| JP2013013178A (en) | Operation control system, operation control device, and operation control method for electric power system | |
| Vournas et al. | Postmortem analysis and data validation in the wake of the 2004 Athens blackout | |
| JP7662243B2 (en) | Energy management system and method of operation thereof | |
| JP3399778B2 (en) | Power system evaluation device, power system power flow optimization method and device, and power system planning support method and device | |
| Kundur et al. | Practical considerations in voltage stability assessment | |
| KR102753438B1 (en) | Electric power system control system and method | |
| KR102055620B1 (en) | Method of receving system control for conservation voltage reduction with volt var optimization based on load model, apparatus for performing the method and conservation voltage reduction system of receving system including the same | |
| KR20220028756A (en) | Wind Farm System for Reducing Power Deviation of Wind Turbine Generator | |
| CN110994639A (en) | Simulation constant volume method, device and equipment for power plant energy storage auxiliary frequency modulation | |
| JP2011019361A (en) | Power system stabilization system with load correction control function | |
| CN110417064B (en) | Dynamic regulation and control method and system for regulation rate based on active capacity monitoring of AGC unit | |
| JP4031412B2 (en) | Power generation control device and program for power consignment | |
| JP3436677B2 (en) | Power system stabilizer | |
| JP4664930B2 (en) | Power factor control device for power generator and power factor control method thereof | |
| KR102538077B1 (en) | System and method for forecasting maximum generation limit of renewable energy | |
| Nghia et al. | A voltage sensitivity index application for power system load shedding considering the generator controls | |
| CN117955178B (en) | Thermal power startup and output configuration method for large-scale wind power DC transmission system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080221 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090221 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090221 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100221 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100221 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110221 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120221 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120221 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130221 Year of fee payment: 10 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130221 Year of fee payment: 10 |
|
| LAPS | Cancellation because of no payment of annual fees |