JP3408938B2 - Elevator for construction - Google Patents
[go: Go Back, main page]

JP3408938B2 - Elevator for construction - Google Patents

Elevator for construction

Info

Publication number
JP3408938B2
JP3408938B2 JP34827696A JP34827696A JP3408938B2 JP 3408938 B2 JP3408938 B2 JP 3408938B2 JP 34827696 A JP34827696 A JP 34827696A JP 34827696 A JP34827696 A JP 34827696A JP 3408938 B2 JP3408938 B2 JP 3408938B2
Authority
JP
Japan
Prior art keywords
rope
machine room
car
governor rope
governor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP34827696A
Other languages
Japanese (ja)
Other versions
JPH10182030A (en
Inventor
和夫 国藤
博 大川
浩嗣 渡辺
英吾 新井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP34827696A priority Critical patent/JP3408938B2/en
Publication of JPH10182030A publication Critical patent/JPH10182030A/en
Application granted granted Critical
Publication of JP3408938B2 publication Critical patent/JP3408938B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Types And Forms Of Lifts (AREA)
  • Maintenance And Inspection Apparatuses For Elevators (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Description

【発明の詳細な説明】 【0001】 【発明の属する技術分野】本発明は、高層ビル等の建築
工事現場において、その工事進行過程に合わせて昇降路
内の機械室を上方へ移設することにより乗かごの昇降行
程を順次延長していく工事用エレベータに関する。 【0002】 【従来の技術】一般に、高層ビルの建築工事現場では、
エレベータが未完成の間は、上層階へ建設資材を運搬し
たり建設作業者を昇降させたりするために多大な時間と
労力を要し、これが建築工事の効率化を阻害するという
問題点があった。そこで従来、特開平8−133635
号公報に開示されているように、ビルの建築工事の進行
過程に合わせて、昇降路内に仮設した機械室を吊り上げ
て上方へ移設していき、もって乗かごの昇降行程を順次
延長していくという工事用エレベータが提案されてい
る。 【0003】かかる従来の工事用エレベータにおいて、
昇降路内に仮設される機械室には、乗かごと釣合いおも
りとを連結する巻上ロープ(メインロープ)を駆動する
ための巻上装置や、プーリに巻き掛けたガバナロープを
介して検出される乗かごの昇降速度が許容値を越えたと
きに該乗かごを停止させるためのガバナマシン等が実装
されている。また、この機械室の底部には、両端の間の
長さ寸法が変更可能な支持体が設けられており、機械室
を仮設する際には、相対向する昇降路壁に配設されてい
る一対の建屋梁の間隔よりも長くなるように該支持体を
伸ばし、該支持体の両端部を建屋梁上に載せることで機
械室が安定して支持されるようになっている。 【0004】 【発明が解決しようとする課題】しかしながら、上述し
た従来の工事用エレベータでは、機械室を移設するたび
にガバナロープを交換しなければならないという煩雑さ
があり、この交換作業が機械室を移設する際の作業効率
を悪化させる要因となっていた。すなわち、機械室を上
方へ移設しようとする場合、機械室内のガバナマシンの
プーリ(上部プーリ)と昇降路の底部に設置された下部
プーリとに巻き掛けた状態で両プーリ間に張設されてい
るガバナロープは、それまでの長さでは不足してしまう
ので、従来技術では、まず既設のガバナロープを取り外
してから、それよりも所定寸法長い新たなガバナロープ
を両プーリに巻き掛けて張設するという交換作業を余儀
なくされており、この交換作業に多くの時間と労力を費
やしていた。 【0005】本発明はこのような従来技術の課題を解消
するためになされたもので、その目的は、機械室の移設
時にガバナロープを交換する必要がなくて、移設作業が
効率よく行える工事用エレベータを提供することにあ
る。 【0006】 【課題を解決するための手段】上述した目的を達成すべ
く、本発明は、乗かごと釣合いおもりとを連結する巻上
ロープを駆動するための巻上装置が実装された機械室を
昇降路内に仮設して、この機械室の下方で前記乗かごを
運行可能となすとともに、前記機械室に設置された上部
プーリと昇降路の底部に設置された下部プーリとの間に
張設されて両端部が前記乗かごに係合されるガバナロー
プを介して、該乗かごの昇降速度の異常を検出可能とな
し、且つ、建屋の建築工事の進行過程に合わせて前記機
械室を吊り上げて移設する工事用エレベータにおいて、
エレベータ完成時には必要となるが当面は余分なガバナ
ロープの余裕代を巻回して保持するリール装置を前記乗
かごに搭載し、前記プーリ間に張設されたガバナロープ
の一端部とが連続するように構成すると共に、前記両プ
ーリ間に張設されたガバナロープの一端を係止する第1
の係止部と他端部とを係止する第2の係止部とを有し
て、一方の係止部を他方の係止部に対し回動自在となし
たロープ端連結装置を、前記乗かごに一体的に設けた構
成にしてある。 【0007】かかる構成の工事用エレベータは、機械室
を上方へ移設しようとする際に、機械室の移動に伴って
不足する長さ分だけガバナロープをリール装置から送り
出してやれば、上部プーリと下部プーリとの間に張設さ
れるガバナロープの長さを必要量だけ増加させることが
できるので、煩雑なガバナロープの交換作業が不要とな
る。 【0008】また、かかる構成において、両プーリ間に
張設されたガバナロープの一端部を係止する第1の係止
部と他端部を係止する第2の係止部とを有して、一方の
係止部を他方の係止部に対し回動自在となしたロープ端
連結装置を、乗かごと一体的に設けておけば、リール装
置から送り出したガバナロープが張設時にねじれたとし
ても、第1の係止部もしくは第2の係止部が回動して該
ねじれが速やかに解消されるので、好ましい。 【0009】 【発明の実施の形態】以下、本発明による工事用エレベ
ータの一実施形態を図1ないし図4に基づいて説明す
る。ここで、図1は本実施形態に係るガバナロープの取
付状態を示す説明図、図2は図1に示すロープ端連結具
の詳細な正面図、図3は該ロープ端連結具の詳細な側面
図、図4は本実施形態の全体構成を示す概略図である。 【0010】まず、主に図4を参照しつつ、本発明を適
用した工事用エレベータの概略について説明する。同図
に示すように、昇降路1内に搬入された機械室2の底部
には支持体12が設けられていて、この支持体12の両
端部を、相対向する昇降路壁に配設されている一対の建
屋梁(図示せず)上に載置することにより、機械室2は
昇降路1内の所定の位置に安定して支持されるようにな
っている。この機械室2には、乗かご10と釣合いおも
り11とを連結するメインロープ9を駆動するための巻
上機3や、昇降速度の異常を検出して乗かご10を停止
させるためのガバナマシン4や、エレベータ完成時には
必要となるが当面は余分なメインロープ9の余裕代が巻
回・保持されているメインロープリール14等が実装さ
れている。つまり、余裕代以外のメインロープ9は、メ
インロープリール14から取り出された後、乗かご10
上のプーリ16と巻上機3と釣合いおもり11上のプー
リ17とに順次巻き掛けられて、機械室2に固定されて
いるので、巻上機3を正逆回転させてメインロープ9を
駆動することにより、機械室2の下方で乗かご10を昇
降させることができる。 【0011】前記ガバナマシン4に設けられた上部プー
リ7と昇降路1の底部に設けられた下部プーリ8とに巻
き掛けられているガバナロープ6は、図1に示すよう
に、ロープ端連結具15を介して両端部6a,6bが連
結された状態で、両プーリ7,8間に張設されている。
このロープ端連結具15は、乗かご10の側部に配置さ
れたもので、図2,3に示すように、ガバナロープ6の
一端部6aを係止する第1の係止部15aと、ガバナロ
ープ6の他端部6bを係止して第1の係止部15aに対
し回動自在な第2の係止部15bとを備えた構成になっ
ている。また、乗かご10の上部にはガバナロープリー
ル5が搭載されていて、このガバナロープリール5に
は、エレベータ完成時には必要となるが当面は余分なガ
バナロープ6の余裕代が巻回・保持されている。そし
て、このガバナロープリール5に保持されたガバナロー
プ6の先端部6cと、両プーリ7,8間に張設されたガ
バナロープ6の一端部6aとが連続しており、ロープ端
連結具15の第1の係止部15aのすぐ下方で、両者6
c,6aがロープクリップ18の締結により仮固定状態
で結束されている。なお、ロープ端連結具15の第2の
係止部15bのすぐ上方では、ガバナロープ6の他端部
6bがロープクリップ19の締結により本固定状態で結
束されている。 【0012】このように概略構成される工事用エレベー
タは、建屋(ビル)の建築工事の進行過程に合わせて、
昇降路1内の機械室2を上方へ移設することにより、乗
かご10の昇降行程を順次延長していくことができる。
すなわち、前記建屋梁に支持された仮設状態の機械室2
は、ワイヤ13を介してクレーン等で吊り上げることに
より、上方へ移動させることができるので、上方の階の
工事が開始されるときには、その階まで乗かご10が運
行できるように、機械室2の仮設位置を上方へ移動させ
る。その際、機械室2の移動に伴って必要となるメイン
ロープ9の長さ不足分はメインロープリール14から送
り出し、且つ、ガバナロープ6の長さ不足分はガバナロ
ープリール5から送り出すことにより、機械室2の移設
時にメインロープ9やガバナロープ6を交換する必要が
なくなる。 【0013】すなわち、メインロープ9については従来
技術でも、機械室2の移設時に発生する長さ不足分を該
機械室2内のメインロープリール14から送り出すとい
う対応策が講じられていたが、本実施形態ではガバナロ
ープ6についても交換作業を不要とするため、乗かご1
0上にガバナロープリール5を搭載して、機械室2の移
設時に該ガバナロープリール5から必要量のガバナロー
プ6が送り出せるようになっている。具体的に述べる
と、機械室2を上方へ移設しようとする場合、上部プー
リ7と下部プーリ8との間に張設されるガバナロープ6
の長さをそれまでよりも増大させなければならないの
で、まず、この長さ不足分だけガバナロープリール5か
らガバナロープ6を引き出して、ロープクリップ18を
緩めた後、この引き出した長さ分だけガバナロープ6の
前記一端部6aを下部プーリ8側へ移動させ、しかる
後、ロープクリップ18を再び締め付けてやれば、機械
室2の移設後も両プーリ7,8間に所定の長さのガバナ
ロープ6を張設することができ、煩雑なガバナロープ6
の交換作業が不要となる。その結果、機械室2を移設す
る際に要する作業時間や労力が軽減できて、作業効率が
大幅に向上する。 【0014】また、本実施形態では、両プーリ7,8間
に張設されるガバナロープ6の両端部6a,6bを係止
・連結して乗かご10の側部に一体化されているロープ
端連結具15として、該ガバナロープ6の一端部6aを
係止する第1の係止部15aに対し他端部6bを係止す
る第2の係止部15bが回動自在な構成のものを使用し
ているので、ガバナロープリール5から送り出したガバ
ナロープ6が張設時にねじれたとしても、第2の係止部
15bが回動して該ねじれが速やかに解消されるように
なっている。 【0015】 【発明の効果】本発明による工事用エレベータは以上説
明したような形態で実施され、以下に記載されるような
効果を奏する。 【0016】エレベータ完成時には必要となるが当面は
余分なガバナロープの余裕代を巻回して保持するリール
装置を備えており、機械室を上方へ移設する際には、機
械室の移動に伴って不足する長さ分だけガバナロープを
該リール装置から送り出してやれば、上部プーリと下部
プーリとの間に張設されるガバナロープの長さを必要量
だけ増加させることができるので、煩雑なガバナロープ
の交換作業が不要となり、よって機械室の移設作業を効
率よく行うことができる。 【0017】また、両プーリ間に張設されたガバナロー
プの一端部を係止する第1の係止部と他端部を係止する
第2の係止部とを有して、一方の係止部を他方の係止部
に対し回動自在となしたロープ端連結装置を用いれば、
前記リール装置から送り出したガバナロープが張設時に
ねじれたとしても、第1の係止部もしくは第2の係止部
が回動して該ねじれを速やかに解消することができる。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction site of a high-rise building or the like, in which a machine room in a hoistway is moved upward in accordance with the progress of the construction. The present invention relates to a construction elevator for sequentially extending a car elevator stroke. 2. Description of the Related Art Generally, in a construction site of a high-rise building,
While the elevator is incomplete, it takes a lot of time and effort to transport construction materials to the upper floors and raise and lower construction workers, which hinders the efficiency of construction work. Was. Therefore, conventionally, Japanese Patent Application Laid-Open No. 8-133635
As disclosed in the official gazette, in accordance with the progress of the construction work of the building, the temporary machine room in the hoistway is lifted and moved upward, and the elevator ascent / descent process is sequentially extended. An elevator for construction has been proposed. In such a conventional construction elevator,
The machine room temporarily installed in the hoistway is detected via a hoisting device for driving a hoisting rope (main rope) connecting the car and the counterweight, and a governor rope wound around a pulley. A governor machine or the like for stopping the car when the ascent / descent speed of the car exceeds an allowable value is mounted. Further, at the bottom of the machine room, a support whose length dimension between both ends can be changed is provided, and when the machine room is temporarily installed, it is arranged on the opposed hoistway wall. The support is extended so as to be longer than the interval between the pair of building beams, and the machine room is stably supported by placing both ends of the support on the building beams. [0004] However, in the above-mentioned conventional construction elevator, there is a problem that the governor rope must be replaced every time the machine room is relocated. This was a factor that worsened the work efficiency when relocating. That is, when the machine room is to be moved upward, the pulley (upper pulley) of the governor machine in the machine room and the lower pulley installed at the bottom of the hoistway are stretched between the two pulleys. Since the governor rope is too short in its previous length, in the conventional technology, the existing governor rope is first removed, and then a new governor rope that is longer than the prescribed length is wound around both pulleys and stretched. The work had to be done and a lot of time and effort was spent on this replacement. The present invention has been made to solve such problems of the prior art, and an object of the present invention is to eliminate the necessity of replacing a governor rope when a machine room is relocated, thereby making it possible to efficiently perform a relocation operation. Is to provide. SUMMARY OF THE INVENTION In order to achieve the above-mentioned object, the present invention provides a machine room equipped with a hoisting device for driving a hoisting rope for connecting a car and a counterweight. Is temporarily installed in the hoistway so that the car can be operated below the machine room, and tension is applied between an upper pulley installed in the machine room and a lower pulley installed at the bottom of the hoistway. It is possible to detect abnormalities in the elevation speed of the car through a governor rope that is provided and both ends are engaged with the car, and lifts the machine room in accordance with the progress of building construction of the building Construction elevators to be relocated
Although it is necessary at the time of completion of the elevator, for the time being, a reel device that winds and holds an extra margin of the governor rope is mounted on the car, and one end of the governor rope stretched between the pulleys is configured to be continuous. And both
The first that locks one end of the governor rope stretched between
And a second locking portion for locking the other end and the other end.
To make one of the locking parts pivotable with respect to the other
Rope end connecting device is provided integrally with the car.
I have done it . In the construction elevator having such a configuration, when the machine room is to be relocated upward, the governor rope is sent out from the reel device by an insufficient length due to the movement of the machine room. Since the length of the governor rope stretched between the pulley and the pulley can be increased by a required amount, a complicated governor rope exchange operation is not required. [0008] In this configuration, a first locking portion for locking one end of the governor rope stretched between the pulleys and a second locking portion for locking the other end are provided. If a rope end connecting device that makes one locking portion rotatable with respect to the other locking portion is provided integrally with the ride, the governor rope sent from the reel device is twisted at the time of stretching. This is also preferable because the first locking portion or the second locking portion rotates and the twist is quickly eliminated. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a construction elevator according to the present invention will be described below with reference to FIGS. Here, FIG. 1 is an explanatory view showing an attached state of the governor rope according to the present embodiment, FIG. 2 is a detailed front view of the rope end connector shown in FIG. 1, and FIG. 3 is a detailed side view of the rope end connector. FIG. 4 is a schematic diagram showing the overall configuration of the present embodiment. First, an outline of a construction elevator to which the present invention is applied will be described mainly with reference to FIG. As shown in the figure, a support 12 is provided at the bottom of the machine room 2 carried into the hoistway 1, and both ends of the support 12 are arranged on opposing hoistway walls. The machine room 2 is stably supported at a predetermined position in the hoistway 1 by being placed on a pair of building beams (not shown). The machine room 2 includes a hoisting machine 3 for driving a main rope 9 connecting the car 10 and the counterweight 11 and a governor machine for stopping the car 10 by detecting an abnormality in the elevating speed. 4 and a main rope reel 14 or the like, which is necessary for completion of the elevator but is wound and held with an extra margin of the main rope 9 for the time being. In other words, the main ropes 9 other than the spare room are taken out from the main rope reel 14 and then the car 10
The main rope 9 is driven by rotating the hoisting machine 3 forward and reverse since the upper pulley 16, the hoisting machine 3, and the pulley 17 on the counterweight 11 are sequentially wound around and fixed to the machine room 2. By doing so, the car 10 can be moved up and down below the machine room 2. As shown in FIG. 1, a governor rope 6 wound around an upper pulley 7 provided on the governor machine 4 and a lower pulley 8 provided on the bottom of the hoistway 1 has a rope end connector 15 as shown in FIG. Are stretched between the pulleys 7 and 8 in a state where the both end portions 6a and 6b are connected via the pulley.
This rope end connector 15 is disposed on the side of the car 10 and, as shown in FIGS. 2 and 3, a first locking portion 15a for locking one end 6a of the governor rope 6, and a governor rope. 6 is provided with a second locking portion 15b which locks the other end 6b and is rotatable with respect to the first locking portion 15a. A governor rope reel 5 is mounted on the upper part of the car 10. The governor rope reel 5, which is necessary when the elevator is completed, has an extra margin for the governor rope 6 wound and held for the time being. I have. The leading end 6c of the governor rope 6 held by the governor rope reel 5 and the one end 6a of the governor rope 6 stretched between the pulleys 7 and 8 are continuous with each other. Immediately below the locking portion 15a,
c and 6a are bound in a temporarily fixed state by fastening the rope clip 18. Immediately above the second locking portion 15b of the rope end connector 15, the other end 6b of the governor rope 6 is bound in a fully fixed state by fastening a rope clip 19. The construction elevator generally constructed in this manner is used in accordance with the progress of the construction work of the building (building).
By moving the machine room 2 in the hoistway 1 upward, the hoisting stroke of the car 10 can be sequentially extended.
That is, the machine room 2 in a temporary state supported by the building beams
Can be moved upward by lifting it with a crane or the like via the wire 13 so that when the construction of the upper floor is started, the car 10 is moved to the floor so that the car 10 can operate to that floor. The temporary position is moved upward. At this time, the shortage of the length of the main rope 9 necessary for the movement of the machine room 2 is sent out from the main rope reel 14, and the shortage of the governor rope 6 is sent out from the governor rope reel 5. There is no need to replace the main rope 9 and governor rope 6 when the chamber 2 is relocated. That is, in the prior art, a countermeasure has been taken for the main rope 9 in which the shortage generated when the machine room 2 is relocated is sent out from the main rope reel 14 in the machine room 2. In the embodiment, the exchange work is not required for the governor rope 6, so that the car 1
A governor rope reel 5 is mounted on the top of the machine room 2 so that a required amount of governor rope 6 can be sent from the governor rope reel 5 when the machine room 2 is relocated. Specifically, when the machine room 2 is to be moved upward, the governor rope 6 stretched between the upper pulley 7 and the lower pulley 8 is used.
First, the governor rope 6 is pulled out of the governor rope reel 5 by this shortage, the rope clip 18 is loosened, and then the governor rope is extended by this length. 6 is moved to the lower pulley 8 side, and then the rope clip 18 is tightened again, so that the governor rope 6 having a predetermined length is maintained between the two pulleys 7 and 8 even after the transfer of the machine room 2. Governor rope 6 that can be stretched
Replacement work becomes unnecessary. As a result, the work time and labor required for relocating the machine room 2 can be reduced, and the work efficiency is greatly improved. Further, in this embodiment, both ends 6a and 6b of the governor rope 6 stretched between the pulleys 7 and 8 are locked and connected to each other to be integrated with the side of the car 10 as a rope end. A connector 15 is used in which a second locking portion 15b for locking the other end 6b is rotatable with respect to a first locking portion 15a for locking the one end 6a of the governor rope 6. Therefore, even if the governor rope 6 sent out from the governor rope reel 5 is twisted at the time of stretching, the second locking portion 15b is rotated and the twist is quickly eliminated. [0015] The construction elevator according to the present invention is embodied in the form described above, and has the following effects. A reel device which is necessary for the completion of the elevator but is wound around an extra margin of the governor rope for the time being is provided. When the machine room is moved upward, the reel device is insufficient due to the movement of the machine room. If the governor rope is sent out from the reel device by a length corresponding to the length of the governor rope, the length of the governor rope stretched between the upper pulley and the lower pulley can be increased by a required amount, so that complicated governor rope replacement work is performed. Is unnecessary, and the transfer operation of the machine room can be performed efficiently. [0017] Further, a first locking portion for locking one end of the governor rope stretched between the pulleys and a second locking portion for locking the other end are provided. If a rope end connecting device is used in which the stopping portion is rotatable with respect to the other locking portion,
Even if the governor rope sent from the reel device is twisted at the time of stretching, the first locking portion or the second locking portion is rotated, and the twist can be quickly eliminated.

【図面の簡単な説明】 【図1】本実施形態に係るガバナロープの取付状態を示
す説明図である。 【図2】図1に示すロープ端連結具の詳細な正面図であ
る。 【図3】該ロープ端連結具の詳細な側面図である。 【図4】本実施形態の全体構成を示す概略図である。 【符号の説明】 1 昇降路 2 機械室 3 巻上機 4 ガバナマシン 5 ガバナロープリール 6 ガバナロープ 7 上部プーリ 8 下部プーリ 9 メインロープ(巻上ロープ) 10 乗かご 11 釣合いおもり 13 ワイヤ 14 メインロープリール 15 ロープ端連結具 15a 第1の係止部 15b 第2の係止部 18,19 ロープクリップ
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an explanatory diagram showing an attached state of a governor rope according to the present embodiment. FIG. 2 is a detailed front view of the rope end connector shown in FIG. 1; FIG. 3 is a detailed side view of the rope end connector. FIG. 4 is a schematic diagram showing the overall configuration of the present embodiment. [Description of Signs] 1 hoistway 2 machine room 3 hoisting machine 4 governor machine 5 governor rope reel 6 governor rope 7 upper pulley 8 lower pulley 9 main rope (hoisting rope) 10 car 11 counterweight 13 wire 14 main rope reel 15 Rope end connector 15a First locking portion 15b Second locking portion 18, 19 Rope clip

───────────────────────────────────────────────────── フロントページの続き (72)発明者 新井 英吾 茨城県ひたちなか市堀口832番地の2 日立システムプラザ勝田 日立水戸エン ジニアリング株式会社内 (56)参考文献 特開 昭49−42039(JP,A) 実開 昭51−91476(JP,U) (58)調査した分野(Int.Cl.7,DB名) B66B 7/00 B66B 9/187 ──────────────────────────────────────────────────続 き Continuing from the front page (72) Eigo Arai, Inventor 832-2 Horiguchi, Hitachinaka-city, Ibaraki Pref. Hitachi Systems Plaza Katsuta Hitachi Mito Engineering Co., Ltd. (56) References JP-A-49-42039 (JP, A (58) Field surveyed (Int. Cl. 7 , DB name) B66B 7/00 B66B 9/187

Claims (1)

(57)【特許請求の範囲】 【請求項1】 乗かごと釣合いおもりとを連結する巻上
ロープを駆動するための巻上装置が実装された機械室を
昇降路内に仮設して、この機械室の下方で前記乗かごを
運行可能となすとともに、前記機械室に設置された上部
プーリと昇降路の底部に設置された下部プーリとの間に
張設されて両端部が前記乗かごに係合されるガバナロー
プを介して、該乗かごの昇降速度の異常を検出可能とな
し、且つ、建屋の建築工事の進行過程に合わせて前記機
械室を吊り上げて移設する工事用エレベータにおいて、 エレベータ完成時には必要となるが当面は余分なガバナ
ロープの余裕代を巻回して保持するリール装置を前記乗
かごに搭載し、このリール装置に保持されたガバナロー
プの先端部と、前記プーリ間に張設されたガバナロープ
の一端部とが連続するように構成すると共に、前記両プ
ーリ間に張設されたガバナロープの一端を係止する第1
の係止部と他端部とを係止する第2の係止部とを有し
て、一方の係止部を他方の係止部に対し回動自在となし
たロープ端連結装置を、前記乗かごに一体的に設けたこ
とを特徴とする工事用エレベータ。
(57) [Claims 1] A machine room in which a hoisting device for driving a hoisting rope for connecting a rider and a counterweight is mounted is temporarily installed in a hoistway. The car is operable below the machine room, and is stretched between an upper pulley installed in the machine room and a lower pulley installed at the bottom of the hoistway so that both ends are connected to the car. An elevator for construction, in which an abnormality in the elevation speed of the car can be detected via the engaged governor rope, and the machine room is lifted and relocated in accordance with the progress of building construction of the building. Although sometimes necessary, for the time being, a reel device for winding and holding an extra margin of the governor rope is mounted on the car, and the reel device is stretched between the tip of the governor rope held by the reel device and the pulley. Governor And one end of the loop
The first that locks one end of the governor rope stretched between
And a second locking portion for locking the other end and the other end.
To make one of the locking parts pivotable with respect to the other
A construction elevator , wherein a rope end connecting device is provided integrally with the car .
JP34827696A 1996-12-26 1996-12-26 Elevator for construction Expired - Fee Related JP3408938B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34827696A JP3408938B2 (en) 1996-12-26 1996-12-26 Elevator for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34827696A JP3408938B2 (en) 1996-12-26 1996-12-26 Elevator for construction

Publications (2)

Publication Number Publication Date
JPH10182030A JPH10182030A (en) 1998-07-07
JP3408938B2 true JP3408938B2 (en) 2003-05-19

Family

ID=18395955

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34827696A Expired - Fee Related JP3408938B2 (en) 1996-12-26 1996-12-26 Elevator for construction

Country Status (1)

Country Link
JP (1) JP3408938B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4673574B2 (en) * 2003-05-07 2011-04-20 インベンテイオ・アクテイエンゲゼルシヤフト ELEVATOR EQUIPMENT USING APPARATUS FOR PROVIDING TEMPORARY PROTECTION SPACE, METHOD FOR MOUNTING THE APPARATUS, AND METHOD FOR PROVIDING TEMPORARY PROTECTION SPACE
FI118995B (en) 2006-12-27 2008-06-13 Kone Corp Arrangement for feeding the elevator speed limiter rope
JP5132336B2 (en) * 2008-01-29 2013-01-30 日本ケーブル株式会社 Wire rope connection structure of elevator parking equipment
DE102012111622A1 (en) * 2012-11-29 2014-06-05 Thyssenkrupp Elevator Ag Elevator installation for a building under construction
CN113474276B (en) * 2019-03-05 2023-02-10 株式会社日立制作所 Construction elevator device and speed governor rope extending method for construction elevator device
CN112110363A (en) * 2020-09-15 2020-12-22 国网湖北省电力有限公司武汉市新洲区供电公司 Installation equipment for power converter and use method thereof

Also Published As

Publication number Publication date
JPH10182030A (en) 1998-07-07

Similar Documents

Publication Publication Date Title
CN101466630B (en) Method for installing hoisting ropes of an elevator
JP2812598B2 (en) Equipment lifting device in hoistway
JP3408938B2 (en) Elevator for construction
JP4491110B2 (en) Elevator rope hanging method
JPH09240957A (en) Main rope guide device of elevator
JPS5935822B2 (en) Construction elevator installation method
JP7717274B2 (en) Elevator equipment and its repair method
JPH0791012B2 (en) Driving method of elevator main rope
JP2815251B2 (en) Elevator main cable replacement method
JPH09278325A (en) Ascending and moving method of construction elevator and construction elevator device
JP4157750B2 (en) Elevator main rope changer
JP2912989B2 (en) Main rope hanging method of elevator
JP3299905B2 (en) Elevator for construction
JPH05262475A (en) Installation method of elevator
JPH0313477A (en) Main rope replacing method
JP2621587B2 (en) High head construction crane
JP3297345B2 (en) Governor rope extension method for construction elevators
JPH05201648A (en) Installation of elevator
JP2004091208A (en) Main rope replacement method and device for elevator
JPS5934633B2 (en) Construction elevator installation method
JPH0859132A (en) Lifting of load
JPH10218529A (en) Replacement method of elevator main rope
JP2003146556A (en) Elevator main rope changing device
JP2003073052A (en) Rope installing method of elevator and rope guide device
JPH1045348A (en) Hydraulic elevator installation method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees