Preflex beam manufacturing method

Info

Publication number
JP3443617B2
JP3443617B2 JP2000266052A JP2000266052A JP3443617B2 JP 3443617 B2 JP3443617 B2 JP 3443617B2 JP 2000266052 A JP2000266052 A JP 2000266052A JP 2000266052 A JP2000266052 A JP 2000266052A JP 3443617 B2 JP3443617 B2 JP 3443617B2
Authority
JP
Japan
Prior art keywords
rolled
steel
plate girder
manufacturing
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000266052A
Other languages
Japanese (ja)
Other versions
JP2001123578A (en
Inventor
民世 丘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from KR1019990037506A external-priority patent/KR19990083979A/en
Priority claimed from KR1020000022033A external-priority patent/KR20000049711A/en
Priority claimed from KR2020000011805U external-priority patent/KR200211591Y1/en
Priority claimed from KR1020000022034A external-priority patent/KR20000058343A/en
Priority claimed from KR1020000022032A external-priority patent/KR20000049710A/en
Priority claimed from KR1020000039748A external-priority patent/KR20000063437A/en
Application filed by Individual filed Critical Individual
Publication of JP2001123578A publication Critical patent/JP2001123578A/en
Priority claimed from US09/955,283 external-priority patent/US20030051437A1/en
Publication of JP3443617B2 publication Critical patent/JP3443617B2/en
Application granted granted Critical
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C3/10Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal prestressed
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/29Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
    • E04C3/293Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0404Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects
    • E04C2003/0408Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by assembly or the cross-section
    • E04C2003/0413Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by assembly or the cross-section being built up from several parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0404Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects
    • E04C2003/0408Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by assembly or the cross-section
    • E04C2003/0421Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by assembly or the cross-section comprising one single unitary part
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0404Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects
    • E04C2003/0426Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by material distribution in cross section
    • E04C2003/0434Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by material distribution in cross section the open cross-section free of enclosed cavities
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0404Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects
    • E04C2003/0443Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by substantial shape of the cross-section
    • E04C2003/0452H- or I-shaped

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Rod-Shaped Construction Members (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明はプレフレックスビー
ム(preflex beam)を製作する方法に係り、より詳しく
はそり(camber)を付けたプレートガーダ(plate gird
er)、またはそりを付けない圧延形鋼を利用して単純ビ
ーム用や連続ビーム用に使用される多数個のプレフレッ
クスビームを同時に製作する方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for manufacturing a preflex beam, and more particularly, to a plate girder having a camber.
er), or a method of simultaneously producing a large number of pre-flex beams used for simple beams or continuous beams by utilizing rolled steel without warping.

【0002】[0002]

【従来の技術】単純ビーム(simple beam)用として用
いられるプレフレックスビーム(preflexbeam)を一例
として従来の技術を説明すれば次の通りである。図1は
約40年間あまり施工されてきた直線形の単純ビーム用
プレフレックスビームの製作方法を示した図であって、
図1aは正面図、そして図1bは平面図である。プレー
トガーダ10を現場に運搬して2ケを1組にしてプレフ
レクション(preflexion)荷重載荷台2に据え置きした
後、設計時プレフレクション荷重の載荷点になるプレー
トガーダの両端から約L/5の位置二カ所に支持部材
(propping member)9を固設する。次で、プレフレク
ション荷重作用時、プレートガーダの設計上の支点部に
なるプレートガーダの両端に油圧ジャッキ4を設けてプ
レフレクション荷重を加える。その後、PS棒鋼5を利
用してプレフレクション荷重を加えた状態を保ちながら
プレートガーダの下部フランジにコンクリートを被覆す
ることで単純ビーム用プレフレックスビームが製作され
る。
2. Description of the Related Art A conventional technique will be described by taking a preflex beam used for a simple beam as an example. FIG. 1 is a diagram showing a manufacturing method of a straight type preflex beam for a simple beam which has been constructed for about 40 years,
1a is a front view and FIG. 1b is a plan view. After transporting the plate girders 10 to the site and making two sets as a set and placing them on the pre-flexion loading platform 2, approximately L / L from both ends of the plate girders that become the loading points of the pre-flexion load at the time of design. A supporting member (propping member) 9 is fixed at two positions of 5. Next, when the pre-reflection load is applied, the pre-reflection load is applied by providing the hydraulic jacks 4 at both ends of the plate girder, which are fulcrums in the design of the plate girder. Then, the pre-flex beam for a simple beam is manufactured by coating the lower flange of the plate girder with concrete by using the PS steel bar 5 while keeping the pre-reflection load applied.

【0003】しかし、前述したような従来のプレフレッ
クスビームの製作方法は、プレートガーダにプレフレク
ション荷重を加える時、プレートガーダが横座屈される
ことを防止するためにプレートガーダの交軸方向に一定
間隔に配置されプレートガーダを固定する横支持装置1
2を設けるべきである。このため、現場では1組のプレ
フレックスのプレートガーダ毎に別途に載荷台と横支持
装置などを設けなければならず、プレフレクション荷重
の作用時発生しうる横力に抵抗するために厚さ250m
m以上のコンクリート基礎を作るべきなど追加作業が必
要である。したがって、このための充分な作業空間を確
保する必要があるだけでなく、1回のプレフレクション
荷重の載荷作業によって只二つのプレフレックスビーム
だけ製作されるので、比較的工事に長期間が所要され、
特に直線形のプレフレックスビームの製作にだけ限って
使われている。
However, in the conventional method of manufacturing a pre-flex beam as described above, when a pre-reflection load is applied to the plate girder, the plate girder is prevented from being laterally buckled. Lateral support device 1 arranged at regular intervals and fixing plate girders
2 should be provided. For this reason, it is necessary to separately provide a loading platform and a lateral support device for each set of pre-flex plate girders in the field, and to prevent lateral forces that may occur during the action of pre-reflection load 250m
Additional work is required, such as making concrete foundations of m or more. Therefore, not only is it necessary to secure a sufficient working space for this purpose, but since only two preflex beams are manufactured by one loading operation of the pre-reflection load, it takes a relatively long time for construction. Is
In particular, it is used only for the production of linear preflex beams.

【0004】[0004]

【発明が解決しようとする課題】従って、本発明は先行
技術の問題点を解決するために案出されたものであっ
て、その目的は、2本以上の直線形及び曲線形プレフレ
ックスビームを1回の荷重載荷作業により製作するプレ
フレックスビームの製作方法を提供することである。
Accordingly, the present invention was devised to solve the problems of the prior art, and its purpose was to provide two or more linear and curved preflex beams. It is an object of the present invention to provide a method for manufacturing a pre-flex beam which is manufactured by one load loading operation.

【0005】本発明の他の目的は、そりをつけない圧延
形鋼に塑性変形を起こし設計上のそりを付けるようにす
るプレフレックスビームの製作方法を提供することであ
る。本発明のさらなる他の目的は、圧延形鋼の両側フラ
ンジに被覆されるコンクリートの全てに圧縮応力が導入
されたパイル(pile)及び柱(column)用プレフレック
スビームの製作方法を提供することである。
Another object of the present invention is to provide a method of manufacturing a pre-flex beam which causes plastic deformation of a rolled steel without a warp so as to provide a designed warp. Still another object of the present invention is to provide a method for manufacturing a pre-flex beam for pile and column in which compressive stress is introduced into all of the concrete coated on both side flanges of rolled steel. is there.

【0006】[0006]

【課題を解決するための手段】前述した目的を達成する
ために、本発明の第1実施形態としてそりを付けたプレ
ートガーダを使用するプレフレックスビームの製作方法
は、お互い上下側に配置された第1組のそり(camber)
を付けた上下側プレートガーダ(plate girder)を設
け、前記第1組の上下側プレートガーダを一定支点でP
S棒鋼(PS steelbar)を利用して連結する段階と、お
互い上下側に配置された第2組のそりを付けた上下側プ
レートガーダを設け、前記第2組の上下側プレートガー
ダを一定支点で前記PS棒鋼を利用して連結する段階
と、前記第1組の上下側プレートガーダと第2組の上下
側プレートガーダを一定間隔を開けて並んで配置する段
階と、前記第1組及び第2組の上側プレートガーダと前
記第1組及び第2組の下側プレートガーダを各々一定間
隔を開けて配置された複数の上側ダイアフラム(diaphr
agm)と下側ダイアフラムを利用してお互い連結する段
階と、前記各下側ダイアフラムに下側支持台を設ける段
階と、プレフレクション荷重の載荷位置に該当する各組
の上側プレートガーダと下側プレートガーダとの間に油
圧ジャッキを設け、前記油圧ジャッキを利用して前記上
下側プレートガーダにプレフレクション荷重を加える段
階と、前記各上側プレートガーダの上部フランジと下側
プレートガーダの下部フランジにコンクリートを被覆す
る段階とを含めてなされる。
In order to achieve the above-mentioned object, a method of manufacturing a pre-flex beam using a plate girder with a sled as a first embodiment of the present invention is arranged above and below each other. First set of sled (camber)
The upper and lower plate girders are attached to the upper and lower plate girders of the first set at a fixed fulcrum.
The step of connecting using S steel bar (PS steelbar) and the upper and lower plate girders with the second set of sledges arranged on the upper and lower sides are provided, and the upper and lower plate girders of the second set are fixed at a fulcrum. Connecting using the PS steel bar, arranging the upper and lower plate girders of the first set and the upper and lower plate girders of the second set side by side at regular intervals, and the first and second sets A set of upper plate girders and a plurality of upper diaphragms of the first and second sets arranged at regular intervals.
agm) and lower diaphragms are used to connect to each other, a lower support is provided on each of the lower diaphragms, and an upper plate girder and a lower side of each set corresponding to the preload loading position. A hydraulic jack is provided between the plate girder and a step of applying a pre-reflection load to the upper and lower plate girders using the hydraulic jack, and an upper flange of each upper plate girder and a lower flange of the lower plate girder. And the step of coating the concrete.

【0007】プレフレックスビームを単純ビームの用途
に作るためには、前記一定支点の位置を各々前記プレー
トガーダの両端にし、前記プレフレクション荷重の載荷
位置を各々前記プレートガーダの両端から約L/5にな
るようにする。プレフレックスビームを連続ビーム(co
ntinuous beam)の内側ビーム(internal beam)の用途
に作るためには、前記一定支点の位置を各々前記プレー
トガーダの両端から約L/5にし、前記プレフレクショ
ン荷重の載荷位置を各々前記プレートガーダの両端から
約L/3になるようにする。
In order to make a pre-flex beam for a simple beam application, the fixed fulcrum positions are located at both ends of the plate girder, and the pre-reflection load loading position is about L / L from both ends of the plate girder. Make it 5 Preflex beam to continuous beam (co
In order to make a use of an internal beam of the ntinuous beam, the positions of the fixed fulcrums are set to about L / 5 from both ends of the plate girder, and the loading position of the pre-reflection load is set to the plate girder. It should be about L / 3 from both ends.

【0008】プレフレックスビームを連続ビームの外側
ビーム(external beam)の用途に作るためには、前記
一定支点の位置を各々前記プレートガーダの一方終端と
反対側終端から約L/5にし、前記プレフレクション荷
重の載荷位置を各々前記プレートガーダの両端から約L
/4とL/2なるようにする。一方、プレフレックスビ
ームを単純ビームの用途、または連続ビームの内側ビー
ムの外側ビームの用途に作るにあたって、プレートガー
ダの長さが20m以下の場合、前記下側支持台は各々前
記プレフレクション荷重の載荷位置に設けられるよう
に、前記下側支持台の設置段階後、前記上側プレートガ
ーダを支持する複数の上側支持台を前記下側支持台の設
置位置と同一に前記上側プレートガーダに設ける段階を
さらに含む。
In order to make a pre-flex beam for use as an external beam of a continuous beam, the positions of the fixed fulcrums are set to about L / 5 from one end and the other end of the plate girder, respectively. The loading position of the reflection load is approximately L from both ends of the plate girder.
/ 4 and L / 2. On the other hand, when the pre-flex beam is used for a simple beam application or a continuous beam inner beam outer beam application, when the length of the plate girder is 20 m or less, the lower support bases respectively have the pre-reflection load of 20 m or less. After the step of installing the lower support base so as to be provided at the loading position, a step of providing a plurality of upper support bases supporting the upper plate girder on the upper plate girder at the same position as the installation position of the lower support base. Including further.

【0009】プレートガーダの長さが20m〜30mの
範囲の場合、前記下側支持台は各々前記下側プレートガ
ーダの両端から0.1Lと0.5になる三カ所に設けら
れるようにし、前記下側支持台の設置段階後、前記上側
プレートガーダを支持する複数の上側支持台を前記下側
支持台の設置位置と同一に前記上側プレートガーダに設
ける段階をさらに含む。プレートガーダの長さが30m
以上の場合、前記下側支持台は各々前記下側プレートガ
ーダの両端から0.1Lと0.3Lになる四カ所に設け
られるようにし、前記下側支持台の設置段階後、前記上
側プレートガーダを支持する複数の上側支持台を前記下
側支持台の設置位置と同一に前記上側プレートガーダに
設ける段階をさらに含む。
When the length of the plate girder is in the range of 20 m to 30 m, the lower supports are arranged at three positions of 0.1 L and 0.5 from both ends of the lower plate girder. After the step of installing the lower support base, the method further includes providing a plurality of upper support bases supporting the upper plate girder on the upper plate girder at the same positions as the lower support bases. Plate girder length is 30m
In the above case, the lower supports may be installed at four places of 0.1L and 0.3L from both ends of the lower plate girder, and after the installation of the lower support, the upper plate girder may be installed. The method further includes the step of providing a plurality of upper supports for supporting the upper plate girder at the same positions as the lower supports.

【0010】そりを付けたプレートガーダを使用する本
発明のプレフレックスビームの他の製作方法は、お互い
上下側に配置された第1組のそりを付けた上下側プレー
トガーダを設ける段階と、お互い上下側に配置された第
2組のそりを付けた上下側プレートガーダを設ける段階
と、前記第1組及び第2組の上側プレートガーダと前記
第1組及び第2組の下側プレートガーダを各々一定間隔
を開けて配置された複数の上側ダイアフラムと下側ダイ
アフラムを利用してお互い連結する段階と、前記各下側
ダイアフラムに横に複数の下側支持台を設ける段階と、
前記各下側プレートガーダの上部の一定支点に支持部材
を設ける段階と、プレフレクション荷重の載荷位置に該
当する各組の上側プレートガーダの上部または各組の下
側プレートガーダの下部に油圧ジャッキを設ける段階
と、四角フレームを利用して前記各組の上側プレートガ
ーダと下側プレートガーダ、そして油圧ジャッキを堅固
に取り囲む段階と、前記油圧ジャッキを利用して前記各
組のプレートガーダにプレフレクション荷重を加える段
階と、隣接した前記各上側プレートガーダの下部フラン
ジと下側プレートガーダの上部フランジにコンクリート
を被覆する段階とを含んでなされる。
Another method of making the pre-flex beam of the present invention using a sled plate girder is to provide a first set of sled upper and lower plate girders that are positioned one above the other, and one another. Providing the upper and lower plate girders with the second set of sleds arranged on the upper and lower sides, and the upper plate girders of the first and second sets and the lower plate girders of the first and second sets. Connecting each other using a plurality of upper diaphragms and lower diaphragms arranged at regular intervals, and providing a plurality of lower support bases laterally on each of the lower diaphragms,
A step of providing a supporting member at a fixed fulcrum above each of the lower plate girders, and a hydraulic jack on the upper part of the upper plate girder of each set or the lower part of the lower plate girder of each set corresponding to the loading position of the pre-reflection load. And firmly surrounding the upper plate girder and the lower plate girder of each set, and the hydraulic jacks using a square frame, and using the hydraulic jacks to pre-flex the plate girders of each set. Applying a suction load, and coating the lower flange of each of the adjacent upper plate girders and the upper flange of the lower plate girder with concrete.

【0011】本方式にともなうプレフレックスビームの
製作方法も四角フレームを設けなく製作される前述した
製作方法と同じく、単純ビームや連続ビームの用途とプ
レートガーダの長さに基づき選定されたPS棒鋼の支点
の位置とプレフレクション荷重の載荷位置が適用され、
そして複数の上側支持台を設ける段階が追加されること
ができる。ここで、第1組の上下側プレートガーダと並
んで配置された第2組の上下側プレートガーダを複数で
構成すれば、1回のプレフレクション荷重の作用により
多くのプレフレックスビームを製作することができる。
The manufacturing method of the pre-flex beam according to this method is the same as the manufacturing method described above in which the square frame is not provided, and the PS steel bar selected based on the use of the simple beam or the continuous beam and the length of the plate girder. The position of the fulcrum and the loading position of the pre-reflection load are applied,
And the step of providing a plurality of upper supports can be added. Here, if a plurality of second set upper and lower plate girders arranged side by side with the first set upper and lower plate girders are formed, many pre-flex beams are manufactured by the action of one pre-reflection load. be able to.

【0012】本発明の第2実施形態としてそりを付けな
い圧延形鋼を使用するプレフレックスビームの製作方法
は、お互い上下側に配置された第1組のそりを付けない
直線形の圧延形鋼を設け、前記第1組の上下側圧延形鋼
を一定支点でPS棒鋼を利用して連結する段階と、お互
い上下側に配置された第2組のそりを付けない直線形の
圧延形鋼を設け、前記第2組の上下側圧延形鋼を一定支
点でPS棒鋼を利用して連結する段階と、前記第1組の
上下側圧延形鋼と第2組の上下側圧延形鋼を一定間隔を
開けて並んで配置する段階と、前記第1組及び第2組の
上側圧延形鋼と前記第1組及び第2組の下側圧延形鋼を
各々一定間隔を開けて配置された複数の上側ダイアフラ
ムと下側ダイアフラムを利用してお互い連結する段階
と、前記各下側ダイアフラムの下側支持台を設ける段階
と、プレフレクション荷重の載荷位置に該当する各組の
上側圧延形鋼と下側圧延形鋼間に油圧ジャッキを設け、
前記油圧ジャッキを利用して前記上下側圧延形鋼にプレ
フレクション荷重を加えて塑性変形を起こしてそりを付
ける段階と、前記各下側圧延形鋼の上部の一定支点に支
持部材を設ける段階と、前記一定支点に設けられたPS
棒鋼とプレフレクション荷重の載荷位置に設けられた油
圧ジャッキを除去する段階と、プレフレクション荷重の
載荷位置に該当する各組の上側圧延形鋼の上部または各
組の下側圧延形鋼の下部に油圧ジャッキを設ける段階
と、四角フレームを利用して前記各組の上側圧延形鋼と
下側圧延形鋼、そして油圧ジャッキを堅固に取り囲む段
階と、前記油圧ジャッキを利用して前記各組の圧延形鋼
にプレフレクション荷重を加える段階と、隣接した前記
各上側圧延形鋼の下部フランジと下側圧延形鋼の上部フ
ランジにコンクリートを被覆する段階とを含めてなされ
る。
As a second embodiment of the present invention, a method of manufacturing a pre-flex beam using a rolled shape steel without a warp is as follows. And a step of connecting the first set of upper and lower rolled shape steels using PS bars at a fixed fulcrum, and a second set of straight type rolled shape steels which are arranged on the upper and lower sides without warping. And connecting the second set of upper and lower rolled shaped steels with PS bars at a fixed fulcrum, and the first set of upper and lower rolled shaped steels and the second set of upper and lower rolled shaped steels at fixed intervals. And arranging them side by side, and a plurality of upper and lower rolled steel shapes of the first set and the second set and a plurality of lower rolled shape steels of the first and second sets are arranged at regular intervals. Connecting the upper and lower diaphragms to each other, The steps of providing the lower support base of the Fram, the hydraulic jack between each pair of upper rolled shape steel corresponding to loading position of the pre Deflection load and lower rolling shape steel provided,
Using the hydraulic jack to apply a pre-load to the upper and lower rolled steel bars to cause plastic deformation and warp, and to provide a supporting member at a fixed fulcrum above each of the lower rolled steel bars. And the PS provided at the fixed fulcrum
The step of removing the hydraulic jacks provided at the loading position of the steel bar and the pre-reflection load, and the upper rolling section of each set or the lower rolling section of each set corresponding to the loading position of the pre-reflection load. A step of providing a hydraulic jack on the lower part, a step of firmly surrounding the upper rolled section steel and the lower rolled section steel of each set by using a square frame, and a hydraulic jack, and each of the sets using the hydraulic jack. And a step of applying a pre-reflection load to the rolled shape steels, and a step of coating the lower flange of each of the adjacent upper rolled shape steels and the upper flange of the lower rolled shape steels with concrete.

【0013】この第2実施形態にともなうプレフレック
スビームの製作方法も前記第1実施形態にともなうプレ
フレックスビームの製作方法と同じく、単純ビームや連
続ビームの用途と圧延形鋼の長さによって選定されたP
S棒鋼の支点の位置とプレフレクション荷重の載荷位置
が適用され、そして複数の上側支持台を設ける段階がさ
らに追加されることができる。ここで、第1組の上下側
圧延形鋼と並んで配置された第2組の上下側圧延形鋼を
複数で構成するようになれば、1回のプレフレクション
荷重の作用により多くのプレフレックスビームを製作す
ることが可能になる。
The manufacturing method of the preflex beam according to the second embodiment is also selected according to the application of the simple beam or the continuous beam and the length of the rolled steel, like the manufacturing method of the preflex beam according to the first embodiment. P
The position of the fulcrum of the S steel bar and the loading position of the pre-reflection load are applied, and the step of providing a plurality of upper supports can be further added. Here, if a plurality of the second set of upper and lower rolled shape steels arranged side by side with the first set of upper and lower rolled shape steels are configured, a large number of pre-reflection loads are applied to increase the number of plates. It becomes possible to manufacture a flex beam.

【0014】本発明の第3実施形態としてそりを付けな
い圧延形鋼の両端にダミー圧延形鋼を連結する方式を使
用するプレフレックスビームの製作方法は、そりを付け
ない直線形圧延形鋼の両端にボルトを利用してダミー圧
延形鋼を連結させる段階と、一対よりなる第1組の前記
圧延形鋼を上下側に配置し、その支点になる両端をPS
棒鋼を利用して連結する段階と、他の一対よりなる第2
組の前記圧延形鋼を上下側に配置し、その支点になる両
端をPS棒鋼を利用して連結する段階と、前記第1組の
上下側圧延形鋼と第2組の上下側圧延形鋼を一定間隔を
開けて並んで配置する段階と、前記第1組及び第2組の
上側圧延形鋼と前記第1組及び第2組の下側圧延形鋼を
各々一定間隔を開けて配置された複数の上側ダイアフラ
ムと下側ダイアフラムを利用してお互い連結する段階
と、前記各下側ダイアフラムの下側支持台を設ける段階
と、プレフレクション荷重の載荷位置になる、各組の上
側圧延形鋼のボルト連結部と下側圧延形鋼のボルト連結
部との間に油圧ジャッキを設け、前記油圧ジャッキを利
用して前記上下側圧延形鋼にプレフレクション荷重を加
える段階と、前記各上側圧延形鋼からダミー圧延形鋼を
除外した残り圧延形鋼の上部フランジと前記各下側圧延
形鋼からダミー圧延形鋼を除外した残り圧延形鋼の下部
フランジにコンクリートを被覆する段階と、前記各下側
圧延形鋼の上部の一定支点に支持部材を設ける段階と、
前記PS棒鋼と油圧ジャッキを除去する段階と、各組の
上側圧延形鋼の上部または各組の下側圧延形鋼の下部の
ボルト連結部に油圧ジャッキを設ける段階と、四角フレ
ームを利用して前記各組の上側圧延形鋼と下側圧延形
鋼、そして油圧ジャッキを堅固に取り囲む段階と、前記
油圧ジャッキを利用して前記各組の圧延形鋼にプレフレ
クション荷重を加える段階と、前記各上側圧延形鋼から
ダミー圧延形鋼を除外した残り圧延形鋼の下部フランジ
と前記各下側圧延形鋼からダミー圧延形鋼を除外した残
り圧延形鋼の上部フランジにコンクリートを被覆する段
階と、コンクリートが被覆された前記各圧延形鋼の両端
に連結されたダミー圧延形鋼を解体する段階とを含めて
なされる。
As a third embodiment of the present invention, a method of manufacturing a preflex beam using a method of connecting dummy rolled shape steels to both ends of a rolled shape steel without a warp is a straight rolling shape steel without a warp. The step of connecting the dummy rolled shaped steels using bolts at both ends, and the first set of the rolled shaped steels consisting of a pair are arranged on the upper and lower sides, and both ends serving as fulcrums are PS
Connecting using steel bars and second pair consisting of other pairs
A step of arranging the rolled shaped steels in a set on the upper and lower sides and connecting both ends serving as fulcrums by using PS steel bars; and a pair of the upper and lower rolled shaped steels of the first set and a second set of upper and lower rolled shaped steels And arranging them side by side at regular intervals, and the upper rolled shaped steels of the first set and the second set and the lower rolled shaped steels of the first set and the second set are placed at regular intervals. A plurality of upper diaphragms and lower diaphragms are connected to each other; a lower support base for each lower diaphragm is provided; A hydraulic jack is provided between the steel bolt connection portion and the lower rolled shape steel bolt connection portion, and a step of applying a pre-reflection load to the upper and lower rolled shape steels by using the hydraulic jack, and the upper side Remaining rolled shape excluding dummy rolled shape steel from rolled shape steel The upper flange and the step of coating the lower flange of the remaining rolled shape steel excluding the dummy rolled shape steel from each of the lower rolled shape steel with concrete, and a supporting member at a fixed fulcrum at the upper part of each of the lower rolled shape steel. The stage of providing
Removing the PS steel bar and the hydraulic jack, providing a hydraulic jack on the bolt connection portion of the upper rolling section steel of each set or the lower rolling section steel of each set, and using a square frame Firmly surrounding the upper and lower rolled steel bars of each set, and the hydraulic jack, and applying a reflection load to the rolled steel bars of each group using the hydraulic jack; Coating the lower flange of the remaining rolled shape steel excluding the dummy rolled shape steel from each upper rolled shape steel and the upper flange of the remaining rolled shape steel excluding the dummy rolled shape steel from each of the lower rolled shape steel described above, and , Dismantling the dummy rolled steel bars connected to both ends of each of the rolled steel bars covered with concrete.

【0015】前記実施形態において腹部コンクリートに
も圧縮応力を導入するべきな場合、前記圧延形鋼の腹部
にコンクリートを被覆とPC鋼線(PC steel wires)を
挿入した後、プレテンション(pretension)方法による
圧縮応力を導入する段階をさらに含めてパイル及び柱用
プレフレックスビームが製作できる。
In the above embodiment, when compressive stress should be introduced into the abdominal concrete as well, the abdomen of the rolled shaped steel is covered with concrete and PC steel wires are inserted, and then a pretension method is applied. The pre-flex beam for piles and columns can be manufactured by further including the step of introducing compressive stress due to.

【0016】また製作されるプレフレックスビームが一
定長さ以上になる場合、前記各圧延形鋼の連結部断面を
拡大して剛性を増加させる段階と、相手圧延形鋼が挿入
されるためのグラウティング溝(grouting groove)を
作って前記圧延形鋼をお互い結合する段階と、前記グラ
ウティング溝を介してグラウティング剤を注入する段階
とをさらに含めてパイル及び柱用プレフレックスビーム
が製作できる。
In addition, when the pre-flex beam to be manufactured has a certain length or more, the step of expanding the cross section of the connecting portion of each rolled shape steel to increase the rigidity and the grout for inserting the mating rolled shape steel. The pre-flex beam for piles and columns may further be manufactured by forming a grouting groove to bond the rolled steel bars to each other and injecting a grouting agent through the grouting groove.

【0017】この第2実施形態において、前記圧延形鋼
の長さが20m以下の場合、前記下側支持台は各々前記
プレフレクション荷重の載荷位置に設けられ、前記下側
支持台の設置段階後、前記上側圧延形鋼を支持する複数
のの上側支持台を前記下側支持台の設置位置と同一に前
記上側圧延形鋼に設ける段階をさらに含めてパイル及び
柱用プレフレックスビームが製作される。
In the second embodiment, when the length of the rolled shaped steel is 20 m or less, the lower support bases are respectively provided at the loading positions of the pre-reflection load, and the lower support bases are installed. After that, the pre-flex beam for piles and columns is manufactured further including a step of providing a plurality of upper support bases for supporting the upper rolled steel bars on the upper rolled steel bars at the same installation positions of the lower support steels. It

【0018】また、前記圧延形鋼の長さが20m〜30
mの範囲の場合、前記下側支持台は各々前記下側圧延形
鋼の両端から0.1Lと0.5Lになる三カ所に設けら
れ、前記下側支持台の設置段階後、前記上側圧延形鋼を
支持する複数の上側支持台を前記下側支持台の設置位置
と同一に前記上側圧延形鋼に設ける段階をさらに含めて
パイル及び柱用プレフレックスビームが製作される。
Further, the rolled shaped steel has a length of 20 m to 30.
In the case of the range of m, the lower supporting bases are respectively provided at three places of 0.1L and 0.5L from both ends of the lower rolling section steel, and after the installing stage of the lower supporting base, the upper rolling is performed. The pre-flex beam for piles and columns further includes a step of providing a plurality of upper support bases for supporting the shaped steels on the upper rolled shape steels at the same positions as the installation positions of the lower support bases.

【0019】また、前記圧延形鋼の長さが30m以上の
場合、前記下側支持台は、各々前記下側圧延形鋼の両端
から0.1Lと0.3Lになる四カ所に設け、前記下側
支持台の設置段階後、前記上側圧延形鋼を支持する複数
の上側支持台を前記下側支持台の設置位置と同一に前記
上側圧延形鋼に設ける段階をさらに含めてパイル及び柱
用プレフレックスビームが製作される。
Further, when the length of the rolled steel strip is 30 m or more, the lower support bases are provided at four positions of 0.1 L and 0.3 L from both ends of the lower rolled steel strip, respectively. After the step of installing the lower support, further including the step of providing a plurality of upper support for supporting the upper rolled section steel on the upper rolled section at the same position as the installation position of the lower support for piles and columns. Pre-flex beam is manufactured.

【0020】この第2実施形態においてもまた第1組の
上下側圧延形鋼と並んで配置された第2組の上下側圧延
形鋼を複数で構成すれば、1回のプレフレクション荷重
の作用により多くのプレフレックスビームを製作するこ
とができる。
Also in this second embodiment, if a plurality of second sets of upper and lower rolled shape steels arranged side by side with the first set of upper and lower rolled shape steels are used, a single reflection load Many preflex beams can be produced by the action.

【0021】[0021]

【発明の実施の形態】以下、添付した図面に基づき本発
明の実施形態を詳細に説明する。図2は本発明の第1実
施形態に伴ってそりを付けた上下側プレートガーダのう
ち下側のプレートガーダのための支持台だけを設けた単
純ビーム用プレフレックスビームの製作方法を説明する
ために示した図であって、図2aは正面図、図2bは直
線形のプレフレックスビームの製作時の平面図、図2c
は曲線形のプレフレックスビーム製作時の平面図、そし
て図2dは側断面図である。支点になる両端部はPS棒
鋼5で連結して固定させ、フレフレクション荷重(P)
の載荷点になる第1組のプレートガーダ10a、10b
の両端から約L/5の位置二カ所に各々油圧ジャッキ4
を設けて二つのプレートガーダ10a、10bをお互い
広まる形でプレフレクション荷重(P)を載荷する。こ
の時、他の第2組のプレートガーダ10a’、10b’
と第3組のプレートガーダ10a”、10b”を同じ方
法で設け、ダイアフラム7を利用して各組のプレートガ
ーダを一定間隔に連結してプレフレクション荷重(P)
の載荷時発生できる横座屈を防止する。このように作ら
れた3組またはそれ以上のプレートガーダを支点になる
両端部に設けられた三脚形の支持台6上にダイアフラム
7を通じて載置し、上記のような荷重載荷作業を施して
上側プレートガーダ10a、10a’、10a”等の上
部フランジと下側プレートガーダ10b、10b’、1
0b”の下部フランジにコンクリートを被覆すること
で、単純ビーム用プレフレックスビームが製作される。
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. FIG. 2 is a view for explaining a method of manufacturing a pre-flex beam for a simple beam, in which only a supporting base for a lower plate girder of the upper and lower plate girders provided with a sled according to the first embodiment of the present invention is provided. 2a is a front view, FIG. 2b is a plan view of a linear preflex beam when it is manufactured, and FIG.
Is a plan view of a curved preflex beam, and FIG. 2d is a side sectional view. Both ends, which are fulcrums, are connected and fixed with PS steel bar 5, and the deflection load (P)
First set of plate girders 10a, 10b that become loading points for
4 hydraulic jacks at two locations approximately L / 5 from both ends of
Is provided and the two plate girders 10a and 10b are loaded with a pre-reflection load (P) in such a manner that they spread each other. At this time, the other second set of plate girders 10a ', 10b'
And the third set of plate girders 10a "and 10b" are provided in the same manner, and the plate girders of each set are connected at regular intervals by using the diaphragm 7 to provide a pre-reflection load (P).
Prevents lateral buckling that can occur during loading. The three or more sets of plate girders thus made are placed on the tripod-shaped support bases 6 provided at both ends serving as fulcrums through the diaphragm 7 and subjected to the above-described load-loading work and then the upper side. Upper flanges such as plate girders 10a, 10a ', 10a "and lower plate girders 10b, 10b', 1
The 0b ″ lower flange is coated with concrete to produce a preflex beam for simple beams.

【0022】図3は本発明の第1実施形態によって下側
プレートガーダの支持台だけを用いた連続ビーム構造の
内側ビーム用プレフレックスビームの製作方法であっ
て、図3aは正面図、図3bは直線形プレフレックスビ
ーム製作時の平面図、図3cは曲線形プレフレックスビ
ーム製作時の平面図、そして図3dは側断面図である。
支点になる両端部から約L/5になる位置で第1組のプ
レートガーダ10a、10bをPS棒鋼5で連結するよ
うに固定させた後プレフレクション荷重(P)の載荷点
になる、スチルガーダの両端から約L/3になる二カ所
の位置には各々油圧ジャッキ4を設けてフレフレクショ
ン荷重(P)を載荷する。この時他の第2組のプレート
ガーダ10a’、10b’と第3組のプレートガーダ1
0a”、10b”を同じ方法で設け、ダイアフラム7を
利用して各組のプレートガーダを一定間隔に連結してプ
レフレクション荷重(P)の載荷時発生しうる横座屈を
防止する。このように作られた3組またはそれ以上のプ
レートガーダを支点になる両端部から約L/5位置に設
けられた三脚形の支持台6上にダイアフラム7を通じて
載置し、前述したような荷重載荷作業を施して上側プレ
ートガーダ10a、10a’、10a”の上部フランジ
と下側プレートガーダ10b、10b’、10b”の下
部フランジにコンクリートを被覆することで、連続ビー
ムの内側ビーム用プレフレックスビームが製作される。
FIG. 3 shows a method of manufacturing a pre-flex beam for an inner beam having a continuous beam structure using only the support of the lower plate girder according to the first embodiment of the present invention. Is a plan view of a straight preflex beam, FIG. 3c is a plan view of a curved preflex beam, and FIG. 3d is a side sectional view.
A still girder that becomes the loading point of the pre-reflection load (P) after the first set of plate girders 10a and 10b are fixed so as to be connected by the PS steel bar 5 at a position that is approximately L / 5 from both ends that are fulcrums A hydraulic jack 4 is provided at each of two positions which are approximately L / 3 from both ends to load the deflection load (P). At this time, the other second set of plate girders 10a ', 10b' and the third set of plate girders 1
0a ″ and 10b ″ are provided in the same manner, and the diaphragm 7 is used to connect the plate girders of each set at regular intervals to prevent lateral buckling that may occur when the pre-reflection load (P) is loaded. The three or more sets of plate girders thus formed are placed through the diaphragm 7 on the tripod-shaped support base 6 provided at about L / 5 positions from both ends serving as fulcrums, and the load as described above is set. A pre-flex beam for an inner beam of a continuous beam by performing a loading operation and coating the upper flanges of the upper plate girders 10a, 10a ', 10a "and the lower flanges of the lower plate girders 10b, 10b', 10b" with concrete. Is produced.

【0023】図4は本発明の第1実施形態によって下側
プレートガーダの支持台だけを用いた連続ビーム構造の
外側ビーム用プレフレックスビームの製作方法であっ
て、図4aは正面図、図4bは直線形プレフレックスビ
ームの製作時の平面図、図4cは曲線形プレフレックス
ビーム製作時の平面図、そして図4dは側断面図であ
る。支点になる、端部と反対側端部から約L/5位置で
第1組のプレートガーダ10a、10bをPS棒鋼で連
結して固定させた後プレフレクション荷重(P)の載荷
点になる、プレートガーダの端部から各々約L/4位置
と約L/2位置になる二カ所には各々油圧ジャッキ4を
設けてプレフレクション荷重(P)を載荷する。この
時、他の第2組のプレートガーダ10a’、10b’と
第3組のプレートガーダ10a”、10b”を同じ方法
で設け、ダイアフラム7を利用して各組のプレートガー
ダを一定間隔に連結してプレフレクション荷重(P)の
載荷時発生しうる横座屈を防止する。このように作られ
た3組またはそれ以上のプレートガーダを支点になる位
置に設けられた三脚形の支持台6上にダイアフラム7を
通じて載置し、前述したような荷重載荷作業を施して上
側プレートガーダ10a、10a’、10a”の上部フ
ランジと下側プレートガーダ10b、10b’、10
b”の下部フランジにコンクリートを被覆することで、
連続ビームの外側ビーム用プレフレックスビームが製作
される。
FIG. 4 shows a method of manufacturing a preflex beam for an outer beam having a continuous beam structure using only the support of the lower plate girder according to the first embodiment of the present invention. Is a plan view of a straight preflex beam during fabrication, FIG. 4c is a plan view of a curved preflex beam during fabrication, and FIG. 4d is a side sectional view. After the first set of plate girders 10a, 10b are connected and fixed with PS steel bar at a position of about L / 5 from the end opposite to the end serving as a fulcrum, it becomes a loading point of the pre-reflection load (P). A hydraulic jack 4 is provided at each of two positions, ie, the L / 4 position and the L / 2 position from the end of the plate girder, and a pre-reflection load (P) is applied thereto. At this time, the other second set of plate girders 10a ′ and 10b ′ and the third set of plate girders 10a ″ and 10b ″ are provided in the same manner, and the diaphragm 7 is used to connect the plate girders of each set at regular intervals. This prevents lateral buckling that may occur when the pre-reflection load (P) is loaded. The three or more sets of plate girders thus made are placed on the tripod-shaped support base 6 provided at the fulcrum through the diaphragm 7, and the upper plate is subjected to the load loading work as described above. Upper flange of girders 10a, 10a ', 10a "and lower plate girders 10b, 10b', 10
By coating the bottom flange of b "with concrete,
A preflex beam for the outer beam of the continuous beam is produced.

【0024】図5は本発明の第1実施形態によって上下
側プレートガーダの両方に設けられる支持台を用いた単
純ビーム用プレフレックスビームの製作方法であって、
図5aは正面図、図5bは直線形プレフレックスビーム
製作時の平面図、図5cは曲線形プレフレックスビーム
製作時の平面図、そして図5dは側断面図である。プレ
ートガーダの自重による影響を最小限に減らし、安全事
故の危険を排除するために上側プレートガーダ10a、
10a’を支持するためのラーメン(Rigid Frame)形
の支持台3と下側プレートガーダ10b、10b’を支
持するための三脚形の支持台6を全体プレートガーダの
両端部から0.1L位置と0.5L位置の三カ所に設け
る。
FIG. 5 shows a method of manufacturing a pre-flex beam for a simple beam using a support provided on both upper and lower plate girders according to the first embodiment of the present invention.
5a is a front view, FIG. 5b is a plan view when manufacturing a linear preflex beam, FIG. 5c is a plan view when manufacturing a curved preflex beam, and FIG. 5d is a side sectional view. In order to minimize the influence of the plate girder's own weight and eliminate the risk of safety accident, the upper plate girder 10a,
A rigid frame (Rigid Frame) -shaped support base 3 for supporting 10a 'and a tripod-shaped support base 6 for supporting the lower plate girders 10b, 10b' are set at 0.1L positions from both ends of the whole plate girder. It is installed at three places of 0.5L position.

【0025】この時、製作しようとするプレフレックス
ビームの長さが短い場合は二カ所に、長い場合は四カ所
にこれら支持台を設けることもできる。このように設け
られたラーメン形の支持台3上には横座屈を防止するた
めのダイアフラム7を利用して横に連結した上側プレー
トガーダ10a、10a’を、三脚形の支持台6上には
同じくダイアフラム7を利用して横に連結した下側プレ
ートガーダ10b、10b’を載置する(図5d参
照)。その後、設計上の支点になるプレートガーダの両
端部にPS棒鋼5を利用して上下側プレートガーダを連
結させ、フレフレクション荷重(P)の載荷点になるプ
レートガーダの両端部から約L/5位置の二カ所の上下
側プレートガーダの間に油圧ジャッキ4を設けて2組の
プレートガーダを広げる形にプレフレクション荷重
(P)を載荷し、上側プレートガーダ10a、10a’
の上部フランジと下側プレートガーダ10b、10b’
の下部フランジにコンクリートを被覆することで、単純
ビーム用プレフレックスビームが製作される。
At this time, when the length of the pre-flex beam to be manufactured is short, these support bases can be provided at two places, and when it is long, these support bases can be provided. The upper plate girders 10a and 10a ', which are laterally connected using the diaphragm 7 for preventing lateral buckling, are mounted on the ramen-shaped support base 3 thus provided, and on the tripod-shaped support base 6. Similarly, the lower plate girders 10b and 10b ', which are horizontally connected using the diaphragm 7, are placed (see FIG. 5d). After that, the upper and lower plate girders are connected to both ends of the plate girder, which is a fulcrum in design, by using PS steel bar 5, and about L / 5 from both ends of the plate girder, which is a loading point of the reflection load (P). The hydraulic jacks 4 are provided between the upper and lower plate girders at the two positions, and the pre-reflection load (P) is loaded so as to spread the two sets of plate girders.
Upper flange and lower plate girders 10b, 10b '
A preflex beam for simple beams is manufactured by coating the lower flange of the with concrete.

【0026】図6は本発明の第1実施形態によって連続
ビーム構造物において上下側スチルガーダの両方に設け
られた支持台を用いた内側ビーム用プレフレックスビー
ムの製作方法であって、図6aは正面図、図6bは直線
形プレフレックスビーム製作時の平面図、図6cは曲線
形プレフレックスビーム製作時の平面図、そして図6d
は側断面図である。プレートガーダの自重による影響を
最小限に減らし安全事故の危険を排除するために上側プ
レートガーダ10a、10a’を支持するためのラーメ
ン形の支持台3と下側プレートガーダ10b、10b’
を支持するための三脚形の支持台6を全てプレートガー
ダの両端部から0.1L位置と0.5L位置になる三カ
所に設ける。
FIG. 6 shows a method of manufacturing a preflex beam for an inner beam using a support table provided on both upper and lower still girders in a continuous beam structure according to the first embodiment of the present invention, and FIG. Fig. 6b is a plan view of a linear preflex beam, Fig. 6c is a plan view of a curved preflex beam, and Fig. 6d.
FIG. A ramen-shaped support base 3 and lower plate girders 10b, 10b 'for supporting the upper plate girders 10a, 10a' in order to minimize the influence of the weight of the plate girders and eliminate the risk of safety accidents.
All of the tripod-shaped support bases 6 for supporting the plate girders are provided at three positions of 0.1 L position and 0.5 L position from both ends of the plate girder.

【0027】この時、製作しようとするプレフレックス
ビームの長さが短い場合は二カ所に、長い場合は四カ所
にこれら支持台を設けることもできる。このように設け
られたラーメン形の支持台3上には横座屈を防止のため
のダイアフラム7を利用して横に連結した上側プレート
ガーダ10a、10a’を、三脚形の支持台6上には同
じくダイアフラム7を利用して横に連結した下側プレー
トガーダ10b、10b’を載置する(図6d参照)。
その後、設計上の支点になる、プレートガーダの両端部
から約L/5になる位置にPS棒鋼5を利用して上下側
プレートガーダを連結させ、プレフレクション荷重
(P)の載荷点になる、プレートガーダの両端部から約
L/3位置になる二カ所の上下側プレートガーダの間に
油圧ジャッキ4を設けて2組のプレートガーダを広げる
形でプレフレクション荷重(P)を載荷し、上側プレー
トガーダ10a、10a’の上部フランジと下側プレー
トガーダ10b、10b’の下部フランジにコンクリー
トを被覆することで連続ビームの内側ビーム用プレフレ
ックスビームが製作される。
At this time, when the length of the pre-flex beam to be manufactured is short, these support bases can be provided at two places, and when it is long, these support bases can be provided at four places. The upper plate girders 10a and 10a ', which are laterally connected using the diaphragm 7 for preventing lateral buckling, are mounted on the ramen-shaped support base 3 thus provided, and on the tripod-shaped support base 6. Similarly, the diaphragm 7 is used to place the lower plate girders 10b and 10b 'which are horizontally connected (see FIG. 6d).
After that, the PS plate steel 5 is used to connect the upper and lower plate girders to a position that is about L / 5 from both ends of the plate girder, which is a fulcrum in design, and becomes a loading point of the pre-reflection load (P). , A pre-reflection load (P) is applied by expanding the two sets of plate girders by providing hydraulic jacks 4 between the two upper and lower plate girders located at approximately L / 3 positions from both ends of the plate girder, A preflex beam for a continuous beam is produced by coating the upper flanges of the upper plate girders 10a and 10a 'and the lower flanges of the lower plate girders 10b and 10b' with concrete.

【0028】図7は本発明の第1実施形態によって連続
ビーム構造物において上下側プレートガーダの両方に設
けられた支持台を用いた外側ビーム用プレフレックスビ
ームの製作方法であって、図7aは正面図、図7bは直
線形プレフレックスビーム製作時の平面図、図7cは曲
線形プレフレックスビーム製作時の平面図、そして図7
dは側断面図である。ここでも同じく、プレートガーダ
の自重による影響を最小限に減らし安全事故の危険を排
除するために上側プレートガーダ10a、10a’を支
持するためのラーメン形の支持台3と下側プレートガー
ダ10b、10b’を支持するための三脚形の支持台6
を全体プレートガーダの両端部から0.1L位置と0.
5Lになる三カ所の位置に設ける。
FIG. 7 shows a method of manufacturing a pre-flex beam for an outer beam using a support provided on both upper and lower plate girders in a continuous beam structure according to the first embodiment of the present invention. Front view, FIG. 7b is a plan view when manufacturing a linear preflex beam, FIG. 7c is a plan view when manufacturing a curved preflex beam, and FIG.
d is a side sectional view. Again, in order to minimize the influence of the plate girder's own weight and eliminate the risk of a safety accident, a rigid frame type support stand 3 for supporting the upper plate girders 10a, 10a 'and the lower plate girders 10b, 10b. 'Supporting tripod for supporting 6
From the both ends of the whole plate girder at 0.1 L position and 0.
It will be installed at three locations that will be 5L.

【0029】この時、製作しようとするプレフレックス
ビームの長さが短い場合は2ケ所に、長い場合は四カ所
にこれら支持台を設けることもできる。このように設け
られたラーメン形の支持台3上には横座屈を防止するた
めのダイアフラム7を利用して横に連結した上側プレー
トガーダ10a、10a’を、三脚形の支持台6上には
同じくダイアフラム7を利用して横に連結した下側プレ
ートガーダ10b、10b’を載置する(図7d参
照)。その後、設計上の支点になるプレートガーダの端
部とプレートガーダ端部から約L/5になる位置にPS
棒鋼5を利用して上下側プレートガーダを連結させ、プ
レフレクション荷重(P)の載荷点になる、プレートガ
ーダの端部から各々約L/4位置と約L/2になる二カ
所の上下側プレートガーダの間に油圧ジャッキ4を設け
て2組のプレートガーダを広げる形でプレフレクション
荷重(P)を載荷し、上側プレートガーダ10a、10
a’の上部フランジと下側プレートガーダ10b、10
b’の下部フランジにコンクリートを被覆することで、
連続ビームの外側ビーム用プレフレックスビームが製作
される。
At this time, when the length of the pre-flex beam to be manufactured is short, these support bases can be provided at two places, and when it is long, these support bases can be provided. The upper plate girders 10a and 10a ', which are laterally connected using the diaphragm 7 for preventing lateral buckling, are mounted on the ramen-shaped support base 3 thus provided, and on the tripod-shaped support base 6. Similarly, the diaphragm 7 is used to place the lower plate girders 10b and 10b 'connected laterally (see FIG. 7d). After that, PS at the end of the plate girder, which is the fulcrum in design, and at a position about L / 5 from the end of the plate girder.
The upper and lower plate girders are connected using the steel bar 5 to become the loading point for the pre-reflection load (P), and the upper and lower parts are located at about L / 4 position and about L / 2 from the end of the plate girder, respectively. A hydraulic jack 4 is provided between the side plate girders to spread the two sets of plate girders, and the pre-reflection load (P) is applied to the upper plate girders 10a, 10a.
a'upper flange and lower plate girders 10b, 10
By coating the bottom flange of b'with concrete,
A preflex beam for the outer beam of the continuous beam is produced.

【0030】前述した図2から図7までの製作方法は、
ダイアフラムを使用せず先行技術と同じく横座屈を防止
するための横支持装置を別設する場合、1組のプレート
ガーダ、即ち2本のプレフレックスビームを製作でき2
組以上の直線形及び曲線形の形鋼をダイアフラムを利用
して横に連結させ、同時に4本以上の直線形及び曲線形
プレフレックスビームの製作も可能である。引き続き、
そりを付けない圧延形鋼を用いたプレフレックスビーム
と両側フランジコンクリートの両方に圧縮応力が導入さ
れたパイル及び柱用プレフレックスビームの製作方法を
説明しようとする。
The manufacturing method shown in FIGS. 2 to 7 is as follows.
If a lateral support device for preventing lateral buckling is provided separately without using a diaphragm, one set of plate girders, that is, two preflex beams can be manufactured.
It is also possible to connect more than one set of straight and curved shape steels laterally using a diaphragm and simultaneously manufacture four or more straight and curved preflex beams. Continuing,
A method for manufacturing a preflex beam for piles and columns in which a compressive stress is introduced into both a preflex beam using a rolled steel without warping and a double-sided flange concrete will be described.

【0031】前述した先行技術の製作方法はそりを付け
ない圧延形鋼を塑性変形させそりを付けたり、または両
側フランジコンクリートの両方に圧縮応力を導入させる
ために載荷台上に圧延形鋼を据え置きさせ1回の荷重載
荷作業を施した後、再び載荷台から圧延形鋼を分離させ
てひっくり返して据え置きさせた後再び荷重載荷作業を
施さなければならないため、作業上相当な面倒さが伴わ
れる。従って、後述する載荷方法はそのような面倒さを
解消しようとしたものである。
The above-mentioned prior art manufacturing method is such that the rolled section steel without a warp is plastically deformed to have a warp, or the rolled section steel is placed on a loading table in order to introduce compressive stress to both side flange concretes. After carrying out the load loading work once, the rolled shaped steel must be separated from the loading platform again, turned upside down, and set again, and then the load loading work must be performed again, which causes considerable trouble in the work. . Therefore, the loading method described below is intended to eliminate such trouble.

【0032】そうした製作方法を単純ビームを一例とし
て、図面を利用して説明すれば次の通りである。図8a
は正面図、図8bは直線形プレフレックスビーム製作時
の平面図、図8cは曲線形プレフレックスビーム製作時
の平面図、そして図8dは側断面図である。圧延形鋼の
自重による影響を最小限に減らし安全事故の危険を排除
するために上側圧延形鋼10a、10a’を支持するた
めのラーメン形の支持台3と下側圧延形鋼10b、10
b’を支持するための三脚形の支持台6を全体圧延形鋼
の両端部から0.1L位置と0.5L位置になる三カ所
に設ける。
The manufacturing method will be described below with reference to the drawings using a simple beam as an example. Figure 8a
Is a front view, FIG. 8b is a plan view when manufacturing a linear preflex beam, FIG. 8c is a plan view when manufacturing a curved preflex beam, and FIG. 8d is a side sectional view. In order to minimize the influence of the rolled shape steel due to its own weight and to eliminate the risk of safety accidents, a ramen-shaped support base 3 for supporting the upper rolled shape steels 10a and 10a 'and lower rolled shape steels 10b and 10b.
Tripod-shaped support bases 6 for supporting b ′ are provided at three positions, 0.1 L position and 0.5 L position, from both ends of the overall rolled shape steel.

【0033】この時、製作しようとするプレフレックス
ビームの長さが短い場合は2ケ所に、長い場合は四カ所
にこれら支持台を設けることもできる。荷重載荷時の横
座屈を防止するために設けたダイアフラム7を利用して
1組または多組の圧延形鋼を横に連結し、上側圧延形鋼
10a、10a’はラーメン形の支持台3上に、下側圧
延形鋼10b、10b’は三脚形の支持台6上にダイア
フラム7を通じて載置する(図8d参照)。その後、設
計上支点になる圧延形鋼の両端部にはそれぞれの上下側
圧延形鋼の間に支持部材9を設け、プレフレクション荷
重(P)の載荷点になる、圧延形鋼の両端から約L/5
位置になる二カ所に各々油圧ジャッキ4を上側圧延形1
0a、10a’の上部に設けて四角フレーム8でこれら
全てを取り囲んで圧延形鋼を縮める形でプレフレクショ
ン荷重(P)を載荷する。ここで、油圧ジャッキ4の設
置位置は現場条件に基づき下側圧延形鋼の下部に設ける
こともできる。
At this time, when the length of the pre-flex beam to be manufactured is short, these support bases can be provided at two places, and when it is long, these support bases can be provided. Using the diaphragm 7 provided to prevent lateral buckling at the time of load loading, one set or multiple sets of rolled shaped steels are laterally connected, and the upper rolled shaped steels 10a and 10a 'are mounted on the ramen-shaped support base 3. Then, the lower rolled steel shapes 10b and 10b 'are mounted on the tripod-shaped support base 6 through the diaphragm 7 (see FIG. 8d). After that, support members 9 are provided between the upper and lower rolled steel bars at both ends of the rolled steel bars which are design fulcrums, and the both ends of the rolled steel bars become the loading points of the pre-reflection load (P). About L / 5
Position the hydraulic jacks 4 at each of the two positions,
The pre-reflection load (P) is applied in a form of being provided on the upper part of 0a and 10a 'and surrounding all of them with a square frame 8 to shrink the rolled shaped steel. Here, the installation position of the hydraulic jack 4 can also be provided in the lower part of the lower rolled section steel based on site conditions.

【0034】本発明に係るそりを付けない圧延形鋼を用
いたプレフレックスビームの製作時、鋼材の材料的な特
徴の塑性変形に対する理論を図9のグラフを利用して説
明すれば次の通りである。図9aのグラフは引張を受け
る典型的な構造用鋼の応力−変形率線図である。変形率
を水平軸に、応力は垂直軸に表した。グラフに示した通
り、O点からA点までは直線であるが、この領域では応
力と変形率が比例し、材料の挙動は線形だと呼ばれる。
またA点をすぎては応力と変形率との線形関係がこれ以
上維持されないが、この時A点を比例限度(proportion
al limit)と呼ぶ。
The theory for plastic deformation of the material characteristics of the steel material when manufacturing the pre-flex beam using the rolled shape steel without warping according to the present invention will be described with reference to the graph of FIG. 9 as follows. Is. The graph of Figure 9a is a stress-deformation diagram for a typical structural steel under tension. The deformation rate is shown on the horizontal axis and the stress is shown on the vertical axis. As shown in the graph, from point O to point A is a straight line, but in this region, the stress and the deformation rate are proportional, and the behavior of the material is called linear.
Moreover, the linear relationship between the stress and the deformation rate is no longer maintained beyond point A, but at this time point A is a proportional limit (proportion limit).
al limit).

【0035】比例限度を越えて荷重を次第に増加してい
けば、応力に比べて変形率が遥かに急速に増加し、応力
−変形率曲線は、傾斜が次第に小さくなっていてから水
平になる点Bに到達するようになる。このB点からC点
までは、引張力がほとんど増加しなくても相当な変形が
起る。こういう現象を材料の降伏(yielding)とし、B
点の応力を降伏応力(yielding stress)または降伏点
(yielding point)と称する。そして、B点からC点ま
での領域では材料が完全塑性(perfectly plastic)状
態になって作用荷重が増えなくても変形が起る。BC領
域の降伏過程で大きい変形率が生じた後、ひずみ硬化
(strain hardening)が始まるが、この際材料は原子及
び結晶構造の変化を起こしてこれ以上の変形に対する材
料の抵抗力を高める。
If the load is gradually increased beyond the proportional limit, the deformation rate increases much more rapidly than the stress, and the stress-deformation curve becomes a point where the slope becomes gradually smaller and then becomes horizontal. You will reach B. From point B to point C, considerable deformation occurs even if the tensile force hardly increases. This phenomenon is called yielding of material, and
The stress at a point is called the yield stress or the yield point. Then, in the region from the point B to the point C, the material is in a perfectly plastic state and deformation occurs even if the applied load does not increase. After a large deformation rate occurs in the yielding process in the BC region, strain hardening begins, in which the material undergoes changes in its atomic and crystalline structure, increasing the material's resistance to further deformation.

【0036】従って、引張力が増加してこそ追加的な伸
張が起こり応力−変形率線図はC点からD点まで正の傾
斜を持つようになる。即ち、荷重は結局最大値まで到達
するようになり、この際の応力を極限応力(ultimate s
tress)という。またこの点を越えれば荷重が減少する
にもかかわらず、材料は増え続けてE点で破壊(fractu
re)が起こる。
Therefore, only when the tensile force increases, additional extension occurs, and the stress-deformation rate diagram has a positive inclination from the point C to the point D. That is, the load eventually reaches the maximum value, and the stress at this time is the ultimate stress (ultimate s
tress). In addition, if the load is reduced beyond this point, the material will continue to increase and fracture at point E (fractu
re) occurs.

【0037】図9bは図9aの応力−変形率線図を簡略
化して表したグラフである。もし与えられた荷重の作用
によって、材料に生じた変形が荷重が除去される時なく
なれば、その材料は弾性を持って線形的に挙動すると言
う。しかし、もし降伏点に到達すれば、前述した通り降
伏が起こり荷重が除去される時応力と変形率は荷重曲線
の直線部ABに平行した線CDに沿って線形的に減少す
る。荷重が除去された後変形率が0に戻らないことは材
料に永久変形または塑性変形が起きたことを示したこと
である。図9bにおいて、AD区間は塑性変形による残
留変形値を表したことである。
FIG. 9b is a simplified graph showing the stress-deformation rate diagram of FIG. 9a. A material is said to be elastic and behave linearly if the deformation caused by the applied load disappears when the load is removed. However, if the yield point is reached, the stress and deformation rate will linearly decrease along the line CD parallel to the straight line portion AB of the load curve when yield occurs and the load is removed as described above. The fact that the deformation rate does not return to 0 after the load is removed indicates that the material has undergone permanent or plastic deformation. In FIG. 9b, the AD section represents the residual deformation value due to plastic deformation.

【0038】従って、本発明に係るプレフレックスビー
ムの製作方法は現在使われている殆んどの製作方法が材
料の弾性だけを考慮してスチルガーダ(steel girder)
に予め死荷重による垂れに対応するそりを付けて製作上
の難しさと面倒なさを耐えるしかなかったこととは違
い、そりを付けない圧延形鋼に所定の工程を経て塑性変
形による設計上のそりを付けようとしたものである。
Therefore, in the method of manufacturing the pre-flex beam according to the present invention, most of the manufacturing methods used at present have a steel girder considering only the elasticity of the material.
Unlike the conventional method in which a warp corresponding to sagging due to dead load was attached in advance to withstand the difficulty and troublesomeness in manufacturing, the warped rolled steel without a warp was subjected to a predetermined process and a plastic warpage caused by plastic deformation. I tried to attach.

【0039】本発明のそりを付けない圧延形鋼を用いた
プレフレックスビームの製作工程を図面に基づき説明す
れば次の通りである。図10は単純ビーム圧延形鋼を用
いたプレフレックスビームを製作するための1段階工程
であって、そりを付けない圧延形鋼に死荷重による垂れ
に対応するそりを付ける過程を示す。この時、そりを付
けるための荷重の載荷方法は図2または図5の方法に従
う。
The manufacturing process of the pre-flex beam using the rolled shape steel without warping according to the present invention will be described below with reference to the drawings. FIG. 10 is a one-step process for producing a pre-flex beam using a simple beam rolled shape steel, and shows a process in which a rolled shape steel without a warp is provided with a warp corresponding to sagging due to dead load. At this time, the method of loading the load for attaching the sled follows the method of FIG. 2 or FIG.

【0040】図10bは単純ビーム構造物のような支点
条件を持つ支点上に置かれたそりを付けない圧延形鋼
(図10a)の両端から約1/5L位置に二つの荷重
(P)を弾性範囲を越えて加えることによって死荷重載
荷時、最大撓みモーメントが発生する位置即ち、圧延形
鋼の中央に頂点を有する3次放物線形態の塑性変形を発
生させる工程を示す。この時、放物線の形態は死荷重及
び活荷重の大きさと構造物の用途に応じて3次放物線式
に容易に誘導されうる。図10cは前記過程から3次放
物線形態に塑性変形された圧延形鋼の斜視図である。
FIG. 10b shows two loads (P) at the positions of about ⅕ L from both ends of the non-sled rolled shaped steel (FIG. 10a) placed on a fulcrum having a fulcrum condition such as a simple beam structure. A step of causing a plastic deformation in the form of a third parabola having an apex at the position where the maximum bending moment occurs, that is, in the center of the rolled steel, when a dead load is applied by applying the material beyond the elastic range is shown. At this time, the shape of the parabola can be easily induced to a tertiary parabolic type according to the size of dead load and live load and the use of the structure. FIG. 10c is a perspective view of rolled steel that has been plastically deformed into a third parabolic form from the above process.

【0041】図11は図10の過程において製作された
下部に塑性変形された圧延形鋼を図8のような四角フレ
ームを用いた載荷方法によりコンクリートに圧縮応力を
導入させる過程を示す。図11bは圧延形鋼の上部フラ
ンジにコンクリートを被覆させ圧縮応力を導入させるた
めに湾曲した圧延形鋼の両端から約1/5L位置に2個
の荷重(P)を加えた状態を表している。
FIG. 11 shows a process of introducing a compressive stress into concrete by the loading method using the square frame as shown in FIG. 8 for the plastically deformed rolled steel manufactured in the process of FIG. FIG. 11b shows a state in which two loads (P) are applied to the upper flange of the rolled section steel at a position of about ⅕ L from both ends of the rolled section steel which is covered with concrete to introduce compressive stress. .

【0042】図11cは圧延形鋼に2個の荷重を加えた
状態で圧延形鋼の上部フランジにコンクリートを被覆さ
せた状態図である。図11dは上部コンクリートが養生
された後加わった荷重を除去させることによって死荷重
及び活荷重により発生する応力に相反する圧縮応力が導
入されたプレフレックスビームに変換された状態であ
る。
FIG. 11c shows a state in which the upper flange of the rolled shape steel is covered with concrete in the state where two loads are applied to the rolled shape steel. FIG. 11d shows a state in which the load applied after the upper concrete is cured is converted into a pre-flex beam in which a compressive stress that is opposite to the stress generated by the dead load and the live load is introduced.

【0043】図12は連続ビーム構造物において左右縁
部に位置するビームであって、左側端は終端に、右側端
は終端から約1/5L位置に支点を配置した圧延形鋼を
利用してプレフレックスビームを製作するための1段階
工程でそりを付けない圧延形鋼に連続ビーム構造物の外
側ビームの死荷重による垂れに対応するそりを付ける過
程を示している。この時、そりを付けるための荷重載荷
方法は図4または図7の方法に従う。
FIG. 12 is a beam positioned at the left and right edges of a continuous beam structure, which uses rolled steel having a fulcrum at the left end and the right end at about 1/5 L from the end. Fig. 2 shows a process for forming a pre-flex beam in a one-step process in which a non-warped rolled steel section is provided with a warp corresponding to sagging due to dead load of an outer beam of a continuous beam structure. At this time, the load loading method for attaching the sled follows the method of FIG. 4 or 7.

【0044】図12aは左側端は終端に、右側端は終端
から約1/5L位置に支点を配置したそりを付けない圧
延形鋼を示している。図12bは圧延形鋼の左側端から
約1/4L間隔に二つの荷重(P)を弾性範囲を超えて
加えることによって、死荷重の載荷時、最大撓みモーメ
ントが発生する位置、すなわち左側端から約3/8L位
置に頂点を有する3次放物線形態の塑性変形を発生させ
る工程を示す。この時、放物線の形態は死荷重及び活荷
重の大きさと構造物の用途に応じて3次放物線式に容易
に導かれる。図12cは前述した過程から3次放物線形
態に塑性変形された圧延形鋼の斜視図である。
FIG. 12a shows a rolled steel without a warp, in which a left end is located at the end and a right end is provided with a fulcrum at a position of about 1/5 L from the end. FIG. 12b shows a position at which the maximum bending moment is generated when a dead load is applied, that is, from the left end by applying two loads (P) beyond the elastic range at intervals of about 1/4 L from the left end of the rolled steel. The process which produces | generates the plastic deformation of the 3rd parabolic form which has an apex in a 3 / 8L position is shown. At this time, the shape of the parabola can be easily guided to the third parabolic type depending on the size of dead load and live load and the use of the structure. FIG. 12c is a perspective view of rolled steel that has been plastically deformed into a third parabolic form from the above-described process.

【0045】図13は図12の過程において製作された
下部に塑性変形された圧延形鋼を四角フレームを用いた
載荷方法に基づきコンクリートに圧縮応力を導入させる
過程を示す。図13bは圧延形鋼の上部フランジにコン
クリートを被覆させ圧縮応力を導入させるために湾曲し
た圧延形鋼の左側端から約1/4L間隔に二つの荷重
(P)を加えた状態を示す。
FIG. 13 shows a process of introducing a compressive stress into concrete based on a loading method using a square frame for the plastically deformed rolled steel manufactured in the process of FIG. FIG. 13b shows a state in which two loads (P) are applied at intervals of about 1/4 L from the left end of the rolled rolled steel to cover the upper flange of the rolled steel with concrete and to introduce compressive stress.

【0046】図13cは圧延形鋼に二つの荷重(P)を
加えた状態で圧延形鋼の上部フランジにコンクリートを
被覆させた状態図である。図13dは上部コンクリート
が養生された後加わった荷重(P)を除去させることに
よって、死荷重及び活荷重により発生する応力に相反す
る圧縮応力が導入されたプレフレックスビームに変換さ
れた状態である。この時、右側支点の外側の上部コンク
リートは無応力状態であることが分かる。
FIG. 13c is a state diagram in which the upper flange of the rolled steel is covered with concrete in the state where two loads (P) are applied to the rolled steel. FIG. 13d is a state in which the load (P) applied after the upper concrete has been cured is removed to convert it into a preflex beam in which a compressive stress that is opposite to the stress generated by the dead load and the live load is introduced. . At this time, it can be seen that the upper concrete outside the right fulcrum is in a stress-free state.

【0047】図14は連続ビーム構造物において内側に
位置するビームまたは建築構造物において柱と柱とを連
結するビームであって、両端から約1/5L位置に支点
を配置した圧延形鋼を用いたプレフレックスビームを製
作するための1段階工程で、そりを付けない圧延形鋼に
連続ビーム構造物の内側ビームの死荷重による垂れに対
応するそりを付ける過程を示している。この時、そりを
付けるための荷重載荷方法は図3または図6の方法に従
う。
FIG. 14 shows a beam located inside in a continuous beam structure or a beam connecting columns in a building structure, which uses rolled steel having fulcrums at about 1/5 L positions from both ends. FIG. 2 shows a process of manufacturing a pre-flex beam, which is a one-step process, in which a rolled shape steel without a warp is provided with a warp corresponding to the sag of the inner beam of the continuous beam structure due to the dead load. At this time, the load loading method for attaching the sled follows the method of FIG. 3 or FIG.

【0048】図14aは連続ビーム構造物において内側
ビームまたは建築構造物において柱と柱を連結するのに
使用するビームを示した図であって、両端から約1/5
L位置で支点を配置したそりを付けない圧延形鋼を示し
ている。この時、連続ビーム構造物の場合、内側ビーム
は外側ビームより約25%ほど長くして経済性を高める
ことができる。
FIG. 14a shows an inner beam in a continuous beam structure or a beam used to connect columns in a building structure, about 1/5 from both ends.
It shows a rolled steel without a warp with a fulcrum at the L position. At this time, in the case of a continuous beam structure, the inner beam may be made longer than the outer beam by about 25% to improve economic efficiency.

【0049】図14bは圧延形鋼の中央から左右に約1
/6Lになる支点に二つの荷重(P)を弾性限界以上に
加えることによって得られる3次放物線形態の塑性変形
を発生させる工程を示している。この時、放物線の形態
は死荷重及び活荷重の大きさと構造物の用途に応じて3
次放物線式に容易に誘導されうる。図14cは前述した
過程から3次放物線形態に塑性変形された圧延形鋼の斜
視図である。
FIG. 14b shows about 1 point left and right from the center of the rolled steel.
It shows a process of generating plastic deformation in the form of a third parabola obtained by applying two loads (P) to the fulcrum that becomes / 6L above the elastic limit. At this time, the shape of the parabola depends on the size of dead load and live load and the use of the structure.
It can be easily guided to the next parabolic type. FIG. 14c is a perspective view of the rolled steel that has been plastically deformed into the third parabolic form from the above process.

【0050】図15は連続ビームにおける内側ビームま
たは建築構造物において柱と柱とを連結させる圧延形鋼
を用いたプレフレックスビームの製作工程を示した図で
ある。図15aは図14cで示した下向に塑性変形させ
た圧延形鋼の上部フランジに被覆されたコンクリートに
圧縮応力の導入のために圧延形鋼の中央から左右に約1
/6Lになる二支点に荷重(P)を加えた状態を示して
いる(図15b参照)。この時の荷重載荷方法は同じく
四角フレームを利用する。
FIG. 15 is a view showing a manufacturing process of an inner beam in a continuous beam or a pre-flex beam using rolled steel for connecting columns in a building structure. FIG. 15a shows about 1 to the left and right of the center of the rolled shape steel for introducing compressive stress into the concrete covered by the upper flange of the downwardly plastically deformed rolled shape steel shown in FIG. 14c.
It shows a state in which a load (P) is applied to two fulcrums of / 6L (see FIG. 15b). A square frame is also used for the load loading method at this time.

【0051】図15cは二つの荷重(P)を加えた状態
で圧延形鋼の上部フランジにコンクリートを被覆させた
状態図である。図15dは上部コンクリートが養生され
た後加わった荷重(P)を除去させることで、死荷重及
び活荷重により発生する応力に相反する圧縮応力が導入
されたプレフレックスビームに変換された状態である。
この時、両端支点の外側の上部コンクリートは無応力状
態であることが分かる。
FIG. 15c shows a state in which the upper flange of the rolled steel is covered with concrete under the condition that two loads (P) are applied. FIG. 15d shows a state in which the load (P) applied after the upper concrete has been cured is removed to convert it into a pre-flex beam in which a compressive stress that is contrary to the stress generated by the dead load and the live load is introduced. .
At this time, it can be seen that the upper concrete outside the fulcrums at both ends is in a stress-free state.

【0052】次に、プレフレックスビームを用いた適用
工法により両側フランジに被覆されたコンクリートの全
てに圧縮応力が導入されたパイル及び柱用プレフレック
スビームを製作する過程について説明する。パイルは上
部構造及び下部構造に作用する荷重を確実に地盤に伝達
させるためのことであり、力学的に安定的でかつ有害な
変位が生じてはいけない。しかし、従来のパイルはその
構造上横方向荷重や地震等により横変位が誘発され支持
力が弱まる場合もあった。また、充分な支持力の確保の
ために多数のパイルを必要とするので、相当な工事費が
所要されるだけでなく、パイルが長くなる場合、連結部
の剛性弱化による施工上の制約があった。また、鋼材パ
イルの場合、腐食による強度低下は大きな短所であっ
た。
Next, a process of manufacturing a preflex beam for piles and columns in which a compressive stress is introduced into all of the concrete coated on both side flanges by an applied method using a preflex beam will be described. The pile is for reliably transmitting the load acting on the upper structure and the lower structure to the ground, and is mechanically stable and should not cause harmful displacement. However, due to the structure of conventional piles, lateral displacement may be induced by lateral loads, earthquakes, etc., which weakens the bearing capacity. Also, since a large number of piles are required to secure sufficient bearing capacity, not only is the construction cost considerable, but when the piles are long, there are restrictions on construction due to weakening of the rigidity of the connecting part. It was Further, in the case of steel piles, the strength reduction due to corrosion was a big disadvantage.

【0053】従って、本適用工法は既存パイルの問題点
を改善するために圧延形鋼にコンクリートを被覆し、こ
こに全断面にかけてプレストレス(pre-stressed)圧縮
応力を導入させて撓み剛性向上を図って、横荷重及び地
震力に抵抗させかつ腐食を防止し、また圧延形鋼の断面
状に起因した周面摩擦力(skin friction force)の増
加により支持力の増加を期することができ、大きな剛性
により既存のパイルに比して遥かに少数のパイルでも所
要の支持力が得られる。また柱の場合は撓み剛性増加に
よりモーメントの大きな柱において断面節減効果が得ら
れる。本適用工法は図16乃至図19で提示した。
Therefore, in this applied method, in order to improve the problems of the existing pile, the rolled shaped steel is coated with concrete, and the pre-stressed compressive stress is introduced over the entire cross section to improve the flexural rigidity. As a result, it is possible to resist lateral load and seismic force and prevent corrosion, and to increase the bearing force by increasing the skin friction force due to the sectional shape of the rolled steel. Due to the high rigidity, the required bearing capacity can be obtained with a far smaller number of piles than existing piles. Further, in the case of a column, the effect of increasing the bending rigidity can be obtained by reducing the sectional area of the column having a large moment. This applied construction method is presented in FIGS. 16 to 19.

【0054】図16aは全断面のコンクリートに均一な
圧縮応力が導入されたパイル及び柱用プレフレックスビ
ームを製作するためにダミー圧延形鋼11をボルトを用
いた連結部材20により連結させた状態図である。この
ように連結させた圧延形鋼を、図2または図5の製作方
法のように、載荷台上に据え置きした後端部から約L/
5の支点に荷重(P)を載荷した後(図16b参照)、
上側圧延形鋼の上部フランジと下側圧延形鋼の下部フラ
ンジにコンクリートを被覆する(図16c参照)。
FIG. 16a is a state diagram in which the dummy rolled shaped steel 11 is connected by a connecting member 20 using bolts in order to manufacture a preflex beam for piles and columns in which uniform compressive stress is introduced into concrete of all sections. Is. The rolled shaped steels thus connected are placed on a loading table and placed at about L / L from the rear end as in the manufacturing method shown in FIG. 2 or 5.
After applying the load (P) to the fulcrum of 5 (see FIG. 16b),
The upper flange of the upper rolled section steel and the lower flange of the lower rolled section steel are coated with concrete (see Fig. 16c).

【0055】図16dは載荷した荷重(P)を除去して
被覆されたコンクリートに圧縮応力を導入させる過程を
示す。図16eは図8に示した荷重載荷方法のように、
四角フレームを利用して逆方向に荷重(P)を載荷した
状態を示す。この時は上下側圧延形鋼の全てのフランジ
にコンクリートが被覆されていて、横方向の剛性が確保
されることにより所定個数のダイアフラムだけ設けても
構わない。
FIG. 16d shows the process of removing the applied load (P) and introducing compressive stress into the coated concrete. 16e is similar to the load loading method shown in FIG.
A state where a load (P) is applied in the opposite direction using a square frame is shown. At this time, all flanges of the upper and lower rolled section steels are covered with concrete, and a predetermined number of diaphragms may be provided by ensuring rigidity in the lateral direction.

【0056】図16fは荷重(P)が載荷された状態で
上側に圧延形鋼の下部フランジと下側圧延形鋼の上部フ
ランジにコンクリートを被覆した状態を示した図であ
る。図16gはコンクリートが養生された後荷重(P)
を除去させダミー圧延形鋼11と連結部材20を解体し
て二番目に被覆されたコンクリートに圧縮応力を導入さ
せる過程を示す。また腹部コンクリートにも圧縮応力を
導入させるべき場合は腹部コンクリートにPC鋼線(PC
steel wires)を挿入してプレテンション(pre-tensio
n)方法による圧縮応力を与えることによって(図17
参照)、全断面にわたって応力が導入されたパイル及び
柱用プレフレックスビームを製作できる。
FIG. 16f is a view showing a state in which concrete is coated on the lower flange of the rolled shape steel and the upper flange of the lower rolled shape steel under the load (P). Figure 16g shows the load (P) after the concrete is cured.
A process of removing the dummy rolled steel 11 and the connecting member 20 and introducing compressive stress into the second coated concrete will be described. When compressive stress should be introduced into the abdominal concrete, PC steel wire (PC
Insert steel wires) and pre-tension (pre-tensio
n) by applying compressive stress by the method (Fig. 17).
It is possible to manufacture pre-flex beams for piles and columns in which stress is introduced over the entire cross section.

【0057】以上のような過程を通じて全断面にわたっ
て一定の圧縮応力を有する性能面において優れたパイル
及び柱用プレフレックスビームを大量生産することがで
きる。また必要な長さは連結及び切断を通じて任意に調
節可能である。図18a及び図18bは各々全断面コン
クリートに圧縮力が導入されたパイル用プレフレックス
ビームと柱用プレフレックスビームを示した斜視図であ
る。パイル用プレフレックスビームの場合、杭打時先端
の損傷と摩擦を減少させるために楔状のコンクリートキ
ャップをさらに打設養生させる(図18a参照)。
Through the above-described process, it is possible to mass-produce the pre-flex beam for piles and columns, which is excellent in performance having a constant compressive stress over the entire cross section. Also, the required length can be arbitrarily adjusted through connecting and cutting. 18a and 18b are perspective views showing a pre-flex beam for piles and a pre-flex beam for columns, in which a compressive force is introduced into concrete having a full cross section. In the case of a pre-flex beam for piles, a wedge-shaped concrete cap is additionally cured to reduce damage and friction at the tip when driving a pile (see FIG. 18a).

【0058】また、パイル用プレフレックスビームの根
入深さが長くなって連結部が必要な場合、強度の低下を
もたらさず連結が可能な方法を図19に示した。連結部
は断面を拡大して剛性低下に構えたし、圧延形鋼が差し
込まれるソケット式溝を作ってパイル及び柱用プレフレ
ックスビームを結合し、グラウティング材を注入する溝
を作って完全接合を図る。
FIG. 19 shows a method in which the preflex beam for piles can be connected without lowering the strength when the depth of penetration is long and a connecting portion is required. The connecting part has an enlarged cross-section to reduce rigidity, and a socket type groove into which rolled steel is inserted is made to join the pre-flex beam for piles and columns, and a groove for injecting grouting material is made to make a complete joint. Plan.

【0059】[0059]

【発明の効果】以上述べた通り、本発明は下側プレート
ガーダまたは圧延形鋼だけを支持する三脚形の支持台を
設計上支点になる位置に設け、ダイアフラムを通じて載
置したり、あるいは上下側プレートガーダまたは圧延形
鋼を全て支持する場合にはラーメン形の支持台と三脚形
の支持台を、プレフレックスビームの長さが短い場合は
二カ所に、長い場合は三カ所または四カ所に設け、上側
プレートガーダまたは圧延形鋼はラーメン形の支持台
に、下側プレートガーダまたは圧延形鋼は三脚形の支持
台にダイアフラムを通じて載置し、プレフレクション荷
重載荷作業を施すプレフレックスビームの製作方法を提
示したことである。このような本発明の製作方法により
1回のプレフレクション作業により2本以上またはそれ
以上、即ち大量の直線形及び曲線形のプレフレックスビ
ームを製作できるようになる。従って、工期を大幅に短
縮させられる。
As described above, according to the present invention, the lower plate girder or the tripod-shaped support base for supporting only the rolled steel is provided at a position serving as a fulcrum by design, and it is placed through the diaphragm or the upper and lower sides. If all plate girders or rolled steel are to be supported, a ramen-shaped support and a tripod-shaped support are provided at two locations if the preflex beam is short, and at three or four locations if it is long. , The upper plate girder or rolled section steel is mounted on the rigid frame type support, and the lower plate girder or rolled section steel is mounted on the tripod type support through the diaphragm, and the pre-flex beam for pre-reflection load loading is manufactured. That is the method. According to the manufacturing method of the present invention, it is possible to manufacture two or more, that is, a large amount of linear and curved preflex beams by one pre-reflection operation. Therefore, the construction period can be significantly shortened.

【0060】また、四角フレームをさらに設けて上下側
プレートガーダまたは圧延形鋼を縮める形で荷重を載荷
する方法を利用してそりを付けない圧延形鋼を用いたプ
レフレックスビームを製作することによって、プレフレ
ックスビームの製作時予め死荷重による垂れに対応する
そりを付ける困難さと面倒さを解消することができる。
By using a method of applying a load in the form of contracting the upper and lower plate girders or the rolled steel bars by further providing a square frame, a preflex beam using rolled steel bars without warping is manufactured. , It is possible to eliminate the difficulty and troublesomeness of attaching a sled corresponding to sagging due to a dead load when manufacturing the pre-flex beam.

【0061】また、全断面コンクリートに圧縮応力が導
入されたパイル及び柱用プレフレックスビームを製作す
ることによって、パイル用プレフレックスビームの場合
は撓み剛性向上を図って横荷重及び地震力に抵抗させか
つ腐食を防止し、圧延形鋼の断面状による周面摩擦力の
増加により支持力の増加を期することができる。さら
に、大きい剛性により既存のパイルに比して遥かに少数
のパイルでも所要の支持力が得られる。また、柱用プレ
フレックスビームの場合は撓み剛性増加によって大きな
モーメントが作用する柱において断面節減効果を奏す
る。
Further, by manufacturing pre-flex beams for piles and columns in which compressive stress is introduced into all cross-section concrete, in the case of pre-flex beams for piles, flexural rigidity is improved to resist lateral load and seismic force. In addition, corrosion can be prevented, and the supporting force can be increased by increasing the frictional force on the peripheral surface due to the sectional shape of the rolled steel. In addition, the high stiffness provides the required bearing capacity with far fewer piles than existing piles. Further, in the case of the column pre-flex beam, a cross-section saving effect is obtained in the column to which a large moment acts due to an increase in flexural rigidity.

【図面の簡単な説明】[Brief description of drawings]

【図1】 先行技術にともなう単純ビーム用プレフレッ
クスビームの製作方法を説明するために示した図であっ
て、aは正面図であり、bは平面図である。
FIG. 1 is a diagram shown for explaining a method of manufacturing a preflex beam for a simple beam according to the prior art, in which a is a front view and b is a plan view.

【図2】 本発明によって下側プレートガーダに支持台
を設けた単純ビーム用プレフレックスビームの製作方法
を説明するために示した図であって、aはプレートガー
ダに対する正面図、bは直線形プレートガーダに対する
平面図、cは曲線形プレートガーダに対する平面図、そ
してdはプレートガーダに対する側断面図である。
2A and 2B are views for explaining a method of manufacturing a pre-flex beam for a simple beam in which a lower plate girder is provided with a support according to the present invention, where a is a front view of the plate girder and b is a linear shape. FIG. 5 is a plan view of the plate girder, c is a plan view of the curved plate girder, and d is a side sectional view of the plate girder.

【図3】 本発明によって下側プレートガーダに支持台
を設けた連続ビームの内側ビーム用プレフレックスビー
ムの製作方法を説明するために示した図であって、aは
プレートガーダに対する正面図、bは直線形プレートガ
ーダに対する平面図、cは曲線形プレートガーダに対す
る平面図、そしてdはプレートガーダに対する側断面図
である。
FIG. 3 is a view for explaining a method of manufacturing a pre-flex beam for an inner beam of a continuous beam in which a lower plate girder is provided with a support according to the present invention, a is a front view of the plate girder, and b is a front view. Is a plan view for a linear plate girder, c is a plan view for a curved plate girder, and d is a side sectional view for a plate girder.

【図4】 本発明によって下側プレートガーダに支持台
を設けた連続ビームの外側ビーム用プレフレックスビー
ムの製作方法を説明するために示した図であって、aは
プレートガーダに対する正面図、bは直線形プレートガ
ーダに対する平面図、cは曲線形プレートガーダに対す
る平面図、そしてdはプレートガーダに対する側断面図
である。
FIG. 4 is a view for explaining a method of manufacturing a pre-flex beam for an outer beam of a continuous beam in which a support is provided on a lower plate girder according to the present invention, a is a front view of the plate girder, and b is a front view. Is a plan view for a linear plate girder, c is a plan view for a curved plate girder, and d is a side sectional view for a plate girder.

【図5】 本発明によって上側と下側のプレートガーダ
に支持台を設けた単純ビーム用プレフレックスビームの
製作方法を説明するために示した図であって、aはプレ
ートガーダに対する正面図、bは直線形プレートガーダ
に対する平面図、cは曲線形プレートガーダに対する平
面図、そしてdはプレートガーダに対する側断面図であ
る。
FIG. 5 is a view for explaining a method of manufacturing a preflex beam for a simple beam in which upper and lower plate girders are provided with a support according to the present invention, a is a front view of the plate girder, and b Is a plan view for a linear plate girder, c is a plan view for a curved plate girder, and d is a side sectional view for a plate girder.

【図6】 本発明によって上側と下側のプレートガーダ
に支持台を設けた連続ビームの内側ビーム用プレフレッ
クスビームの製作方法を説明するために示した図であっ
て、aはプレートガーダに対する正面図、bは直線形プ
レートガーダに対する平面図、cは曲線形プレートガー
ダに対する平面図、そしてdはプレートガーダに対する
側断面図である。
FIG. 6 is a view for explaining a method for manufacturing a preflex beam for an inner beam of a continuous beam in which upper and lower plate girders are provided with a support according to the present invention, and a is a front surface of the plate girder. Figure, b is a plan view for a linear plate girder, c is a plan view for a curved plate girder, and d is a side sectional view for a plate girder.

【図7】 本発明によって上側と下側のプレートガーダ
に支持台を設けた連続ビームの外側ビーム用プレフレッ
クスビームの製作方法を説明するために示した図であっ
て、aはプレートガーダに対する正面図、bは直線形プ
レートガーダに対する平面図、cは曲線形プレートガー
ダに対する平面図、そしてdはプレートガーダに対する
側断面図である。
FIG. 7 is a view for explaining a method of manufacturing a pre-flex beam for an outer beam of a continuous beam in which upper and lower plate girders are provided with supports according to the present invention, and a is a front surface of the plate girder. Figure, b is a plan view for a linear plate girder, c is a plan view for a curved plate girder, and d is a side sectional view for a plate girder.

【図8】 本発明によって四角フレームを設けた単純ビ
ーム用プレフレックスビームの製作方法を説明するため
に示した図であって、aはプレートガーダに対する正面
図、bは直線形プレートガーダに対する平面図、cは曲
線形プレートガーダに対する平面図、そしてdはプレー
トガーダに対する側断面図である。
8A and 8B are views for explaining a method for manufacturing a preflex beam for a simple beam having a square frame according to the present invention, in which a is a front view of a plate girder and b is a plan view of a linear plate girder. , C is a plan view for a curved plate girder, and d is a side sectional view for the plate girder.

【図9】 aは引張応力の作用にともなう典型的な構造
用鋼の変形率をグラフで表した応力−変形率線図であ
り、bは図9aを簡略に表した線図である。
9A is a stress-deformation rate diagram showing a deformation rate of a typical structural steel due to the action of tensile stress in a graph, and FIG. 9B is a diagram simply showing FIG. 9A.

【図10】 本発明によってプレフレックスビームの製
作のために用いられるそりを付けない単純ビーム用の圧
延形鋼(rolled steel)に塑性変形を発生させる工程
を示した図面であって、aはそりを付けない圧延形鋼
を、bはその圧延形鋼に荷重を加える段階を、そしてc
は3次放物線形態に塑性変形された圧延形鋼を示した図
である。
FIG. 10 is a view showing a process of causing plastic deformation of rolled steel for a simple beam without a warp used for manufacturing a preflex beam according to the present invention, where a is a warp; A rolled section without a bar, b the step of loading the rolled section, and c
FIG. 4 is a diagram showing a rolled steel that is plastically deformed into a tertiary parabolic form.

【図11】 図10cの圧延形鋼を利用してプレフレッ
クスビームを製作する工程を示した図であって、aは塑
性変形された単純ビーム用圧延形鋼を、bはその圧延形
鋼に荷重を加える段階を、cは圧延形鋼の上部フランジ
にコンクリートを被覆する段階を、そしてdは圧延形鋼
がプレフレックスビームに変換された状態を示した図で
ある。
FIG. 11 is a diagram showing a process of manufacturing a pre-flex beam using the rolled shaped steel of FIG. 10c, in which a is a plastically deformed rolled shaped steel for simple beam and b is a rolled shaped steel. FIG. 3 is a view showing a step of applying a load, c is a step of coating the upper flange of the rolled steel with concrete, and d is a state in which the rolled steel has been converted into a preflex beam.

【図12】 本発明によってプレフレックスビームの製
作のために用いられるそりを付けない連続ビームの外側
ビーム用圧延形鋼に塑性変形を発生させる工程を示した
図面であって、aはそりを付けない圧延形鋼を、bはそ
の圧延形鋼に荷重を加える段階を、そしてcは3次放物
線形態に塑性変形された圧延形鋼を示した図である。
FIG. 12 is a view showing a process of causing plastic deformation in a rolled beam for outer beam of a continuous beam without a warp used for manufacturing a preflex beam according to the present invention, where a is a warp; [Fig. 3] Fig. 3 is a view showing an unrolled shape steel, b showing a step of applying a load to the rolled shape steel, and c showing a rolled shape steel plastically deformed into a third parabolic form.

【図13】 図12cの圧延形鋼を利用してプレフレッ
クスビームを製作する工程を示した図であって、aは塑
性変形された連続ビームの外側ビーム用圧延形鋼を、b
はその圧延形鋼に荷重を加える段階を、cは圧延形鋼の
上部フランジにコンクリートを被覆する段階を、そして
dは圧延形鋼がプレフレックスビームに変換された状態
を示した図である。
FIG. 13 is a diagram showing a process of manufacturing a pre-flex beam using the rolled shape steel of FIG. 12c, wherein a is a plastically deformed continuous beam outer shape rolled shape steel, and b is
FIG. 4 is a diagram showing a step of applying a load to the rolled shape steel, a step of coating the upper flange of the rolled shape steel with concrete, and a state of converting the rolled shape steel into a pre-flex beam.

【図14】 本発明によってプレフレックスビームの製
作のために用いられるそりを付けない連続ビームの内側
ビーム用または建築構造物用の圧延形鋼に塑性変形を発
生させる工程を示した図であって、aはそりを付けない
圧延形鋼を、bはその圧延形鋼に荷重を加える段階を、
そしてcは3次放物線形態に塑性変形された圧延形鋼を
示した図である。
FIG. 14 is a view showing a process of causing plastic deformation in a rolled steel for a continuous beam without a warp or for an inner beam of a continuous beam used for manufacturing a preflex beam according to the present invention. , A is a rolled shape steel without warping, b is a step of applying a load to the rolled shape steel,
And c is the figure which showed the rolled shape steel plastically deformed to the tertiary parabolic form.

【図15】 図14cの圧延形鋼を利用してプレフレッ
クスビームを製作する工程を示した図であって、aは塑
性変形された連続ビームの内側ビーム用または建築構造
物用の圧延形鋼を、bはその圧延形鋼に荷重を加える段
階を、cは圧延形鋼の上部フランジにコンクリートを被
覆する段階を、そしてdは圧延形鋼がプレフレックスビ
ームに変換された状態を示した図である。
FIG. 15 is a view showing a process of manufacturing a pre-flex beam using the rolled shape steel of FIG. 14c, wherein a is a rolled shape steel for an inner beam of a plastically deformed continuous beam or for a building structure. FIG. 3b is a view showing a step of applying a load to the rolled steel, c is a step of coating the upper flange of the rolled steel with concrete, and d is a state in which the rolled steel is converted into a preflex beam. Is.

【図16】 本発明によってパイル及び柱用プレフレッ
クスビームを製作する工程を示した図であって、aは圧
延形鋼の両端にダミー圧延形鋼を連結させる段階を、b
はその圧延形鋼の一側面に荷重を加える段階を、cは圧
延形鋼の下部フランジにコンクリートを被覆する段階
を、dは圧延形鋼に作用する荷重を除去した段階を、e
は圧延形鋼の反対側面に荷重を加える段階を、fは圧延
形鋼の上部フランジにコンクリートを被覆する段階を、
そしてgは圧延形鋼に作用する荷重を除去しダミー圧延
形鋼の連結を解体する段階を示した図である。
FIG. 16 is a diagram showing a process of manufacturing a pre-flex beam for piles and columns according to the present invention, wherein a is a step of connecting dummy rolled shaped steels to both ends of the rolled shaped steels;
Is a step of applying a load to one side of the rolled steel, c is a step of coating the lower flange of the rolled steel with concrete, d is a step of removing the load acting on the rolled steel, e
Is the step of applying a load to the opposite side of the rolled steel, f is the step of coating the upper flange of the rolled steel with concrete,
Further, g is a diagram showing a step of removing the load acting on the rolled steel shapes and dismantling the connection of the dummy rolled steel shapes.

【図17】 本発明によって圧延形鋼の腹部コンクリー
トに圧縮応力を導入する方法を示した図面である。
FIG. 17 is a view showing a method of introducing compressive stress to abdominal concrete of rolled steel according to the present invention.

【図18】 aは本発明によって製作されたパイル用プ
レフレックスビームを、bは柱用プレフレックスビーム
を示した斜視図である。
18A is a perspective view showing a preflex beam for piles manufactured by the present invention, and FIG. 18B is a perspective view showing a preflex beam for columns.

【図19】 本発明に係るパイル及び柱用プレフレック
スビーム連結部の詳細図である。
FIG. 19 is a detailed view of a preflex beam connecting portion for piles and columns according to the present invention.

【符号の説明】[Explanation of symbols]

2 載荷台 3 上側支持台 4 油圧ジャッキ 5 PS棒鋼 6 下側支持台 7 ダイアフラム 8 四角フレーム 9 支持部材 10 プレートガーダ(圧延形鋼) 11 ダミー圧延形鋼 20 連結部材 2 loading platform 3 Upper support 4 hydraulic jack 5 PS steel bar 6 Lower support 7 diaphragm 8 square frame 9 Support members 10 Plate girder (rolled steel) 11 Dummy rolled steel 20 Connection member

───────────────────────────────────────────────────── フロントページの続き (31)優先権主張番号 200022034 (32)優先日 平成12年4月25日(2000.4.25) (33)優先権主張国 韓国(KR) (31)優先権主張番号 200039748 (32)優先日 平成12年7月11日(2000.7.11) (33)優先権主張国 韓国(KR) (31)優先権主張番号 200011805 (32)優先日 平成12年4月25日(2000.4.25) (33)優先権主張国 韓国(KR) (58)調査した分野(Int.Cl.7,DB名) E04C 3/293 E04B 1/30 ─────────────────────────────────────────────────── --Continued from the front page (31) Priority claim number 200022034 (32) Priority date April 25, 2000 (April 25, 2000) (33) Priority claiming country Korea (KR) (31) Priority Claim number 200039748 (32) Priority date July 11, 2000 (July 11, 2000) (33) Priority claiming country Korea (KR) (31) Priority claim number 200011805 (32) Priority date 2000 25th (April 25, 2000) (33) Priority claim countries South Korea (KR) (58) Fields investigated (Int.Cl. 7 , DB name) E04C 3/293 E04B 1/30

Claims (29)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 お互い上下側に配置された第1組のそり
を付けた上下側プレートガーダを設け、前記第1組の上
下側プレートガーダを一定支点でPS棒鋼を利用して連
結する段階と、 お互い上下側に配置された第2組のそりを付けた上下側
プレートガーダを設け、前記第2組の上下側プレートガ
ーダを一定支点で前記PS棒鋼を利用して連結する段階
と、 前記第1組の上下側プレートガーダと第2組の上下側プ
レートガーダを一定間隔を開けて並列に配置する段階
と、 前記第1組及び第2組の上側プレートガーダと前記第1
組及び第2組の下側プレートガーダを各々一定間隔を開
けて配置された複数の上側ダイアフラムと下側ダイアフ
ラムを利用してお互い連結する段階と、 前記各下側ダイアフラムに下側支持台を設ける段階と、 プレフレクション荷重の載荷位置に該当する各組の上側
プレートガーダと下側プレートガーダとの間に油圧ジャ
ッキを設け、前記油圧ジャッキを利用して前記上下側プ
レートガーダにプレフレクション荷重を加える段階と、 前記各上側プレートガーダの上部プランジと下側プレー
トガーダの下部フランジにコンクリートを被覆する段階
とを含めてなることを特徴とするプレフレックスビーム
の製作方法。
1. A step of providing upper and lower plate girders having a first set of sleds arranged on the upper and lower sides of each other, and connecting the upper and lower plate girders of the first set at a fixed fulcrum using PS steel bars, Providing upper and lower plate girders with a second set of sledges arranged on the upper and lower sides, and connecting the upper and lower plate girders of the second set at a fixed fulcrum using the PS steel bar; Arranging one set of upper and lower plate girders and a second set of upper and lower plate girders in parallel at regular intervals; and the first and second upper plate girders and the first set
Connecting the lower plate girders of the first set and the second set to each other using a plurality of upper diaphragms and lower diaphragms arranged at regular intervals, and providing a lower support base on each of the lower diaphragms Step, and install a hydraulic jack between the upper plate girder and the lower plate girder of each set corresponding to the loading position of the pre-reflection load, and use the hydraulic jack to apply the pre-reflection load to the upper and lower plate girders. And a step of coating the upper plunge of each upper plate girder and the lower flange of the lower plate girder with concrete.
【請求項2】 単純ビームの用途にするため、前記一定
支点の位置を各々前記プレートガーダの両端にし、前記
プレフレクション荷重の載荷位置を各々前記プレートガ
ーダの両端から約L/5になるようにすることを特徴と
する請求項1に記載のプレフレックスビームの製作方
法。
2. In order to use as a simple beam, the fixed fulcrum is positioned at both ends of the plate girder, and the loading position of the pre-reflection load is about L / 5 from both ends of the plate girder. The method for manufacturing a preflex beam according to claim 1, wherein
【請求項3】 連続ビームの内側ビームの用途にするた
め、前記一定支点の位置を各々前記プレートガーダの両
端から約L/5にし、前記プレフレクション荷重の載荷
位置を各々前記プレートガーダの両端から約L/3にな
るようにすることを特徴とする請求項1に記載のプレフ
レックスビームの製作方法。
3. In order to use as an inner beam of a continuous beam, the position of the fixed fulcrum is set to about L / 5 from both ends of the plate girder, and the loading position of the pre-reflection load is set to both ends of the plate girder. To about L / 3, the manufacturing method of the pre-flex beam according to claim 1.
【請求項4】 連続ビームの外側ビームの用途にするた
め、前記一定支点の位置を各々前記プレートガーダの一
側端部と反対側の終端から約L/5にし、前記プレフレ
クション荷重の載荷位置を各々前記プレートガーダの両
端から約L/4及びL/2になるようにすることを特徴
とする請求項1に記載のプレフレックスビームの製作方
法。
4. In order to use as an outer beam of a continuous beam, the positions of the fixed fulcrums are set to about L / 5 from one end of the plate girder opposite to one end thereof, and the pre-reflection load is applied. The method of manufacturing a pre-flex beam according to claim 1, wherein the positions are about L / 4 and L / 2 from both ends of the plate girder.
【請求項5】 前記プレートガーダの長さが20m以下
の場合、前記下側支持台は各々前記プレフレクション荷
重の載荷位置に設けられ、 前記下側支持台の設置段階後、前記上側プレートガーダ
を支持する複数の上側支持台を前記下側支持台の設置位
置と同一に前記上側プレートガーダに設ける段階をさら
に含むことを特徴とする請求項2から請求項4のいずれ
かに記載のプレフレックスビームの製作方法。
5. When the length of the plate girder is 20 m or less, the lower supports are respectively provided at the loading positions of the pre-reflection load, and the upper plate girder is installed after the installation of the lower supports. The preflex according to any one of claims 2 to 4, further comprising the step of providing a plurality of upper support bases supporting the same on the upper plate girder at the same installation position as the lower support bases. Beam manufacturing method.
【請求項6】 前記プレートガーダの長さが20m〜3
0mの範囲の場合、前記下側支持台は各々前記下側プレ
ートガーダの両端から0.1Lと0.5Lになる三カ所
に設けられ、 前記下側支持台の設置段階後、前記上側プレートガーダ
を支持する複数の上側支持台を前記下側支持台の設置位
置と同一に前記上側プレートガーダに設ける段階をさら
に含むことを特徴とする請求項2から請求項4のいずれ
かに記載のプレフレックスビームの製作方法。
6. The plate girder has a length of 20 m to 3
In the case of the range of 0 m, the lower supports are provided at three places, 0.1L and 0.5L respectively from both ends of the lower plate girder, and after the installation of the lower support, the upper plate girder is installed. The preflex according to any one of claims 2 to 4, further comprising the step of providing a plurality of upper support bases supporting the same on the upper plate girder at the same installation position as the lower support bases. Beam manufacturing method.
【請求項7】 前記プレートガーダの長さが30m以上
の場合、前記下側支持台は各々前記下側プレートガーダ
の両端から0.1Lと0.3Lになる四カ所に設けら
れ、 前記下側支持台の設置段階後、前記上側プレートガーダ
を支持する複数の上側支持台を前記下側支持台の設置位
置と同一に前記上側プレートガーダに設ける段階をさら
に含むことを特徴とする請求項2から請求項4のいずれ
かに記載のプレフレックスビームの製作方法。
7. When the length of the plate girder is 30 m or more, the lower support bases are provided at four positions of 0.1 L and 0.3 L from both ends of the lower plate girder, respectively. 3. The method according to claim 2, further comprising a step of providing a plurality of upper supporters supporting the upper plate girder on the upper plate girder at the same position as the lower supporter, after the supporting step is installed. The method for manufacturing a preflex beam according to claim 4.
【請求項8】 お互い上下側に配置された第1組のそり
を付けた上下側プレートガーダを設ける段階と、 お互い上下側に配置された第2組のそりを付けた上下側
プレートガーダを設ける段階と、 前記第1組及び第2組の上側プレートガーダと前記第1
組及び第2組の下側プレートガーダを各々一定間隔を開
けて配置された複数の上側ダイアフラムと下側ダイアフ
ラムを利用してお互い連結する段階と、 前記各下側ダイアフラムに横に複数の下側支持台を設け
る段階と、 前記各下側プレートガーダの上部の一定支点に支持部材
を設ける段階と、 プレフレクション荷重の載荷位置に該当する各組の上側
プレートガーダの上部または各組の下側プレートガーダ
の下部に油圧ジャッキを設ける段階と、 四角フレームを利用して前記各組の上側プレートガーダ
と下側プレートガーダ、そして油圧ジャッキを堅固に取
り囲む段階と、 前記油圧ジャッキを利用して前記各組のプレートガーダ
にプレフレクション荷重を加える段階と、 隣接した前記各上側プレートガーダの下部フランジと下
側プレートガーダの上部フランジにコンクリートを被覆
する段階とを含めてなることを特徴とするプレフレック
スビームの製作方法。
8. A step of providing a first pair of upper and lower plate girders with sleds arranged on the upper and lower sides, and a second set of upper and lower plate girders with sleds arranged on the upper and lower sides of each other. The first and second sets of upper plate girders and the first set
Connecting the lower plate girders of the first set and the second set to each other using a plurality of upper diaphragms and lower diaphragms arranged at regular intervals, and a plurality of lower sides laterally to each of the lower diaphragms. The step of providing a support base, the step of providing a support member at a fixed fulcrum above each of the lower plate girders, and the upper part of the upper plate girders of each set corresponding to the loading position of the pre-reflection load or the lower side of each set Providing a hydraulic jack at the bottom of the plate girder, firmly surrounding the upper plate girder and the lower plate girder of each set, and the hydraulic jack using a square frame, and using the hydraulic jack Applying a pre-reflection load to the pair of plate girders, and the lower flange and lower plate girder of each of the adjacent upper plate girders. Production method of pre flexbeam characterized by comprising, including the steps of coating the concrete Da upper flange.
【請求項9】 単純ビームの用途にするため、前記一定
支点の位置を各々前記プレートガーダの両端にし、前記
プレフレクション荷重の載荷位置を各々前記プレートガ
ーダの両端から約L/5になるようにすることを特徴と
する請求項8に記載のプレフレックスビームの製作方
法。
9. In order to use as a simple beam, the fixed fulcrum is located at both ends of the plate girder, and the loading position of the pre-reflection load is about L / 5 from both ends of the plate girder. 9. The method for manufacturing a preflex beam according to claim 8, wherein:
【請求項10】 連続ビームの内側ビームの用途にする
ため、前記一定支点の位置を各々前記プレートガーダの
両端から約L/5にし、前記プレフレクション荷重の載
荷位置を各々前記プレートガーダの両端から約L/3に
なるようにすることを特徴とする請求項8に記載のプレ
フレックスビームの製作方法。
10. In order to use as an inner beam of a continuous beam, the position of the fixed fulcrum is set to about L / 5 from both ends of the plate girder, and the loading position of the pre-reflection load is set to both ends of the plate girder. To about L / 3, the manufacturing method of the preflex beam according to claim 8, wherein.
【請求項11】 連続ビームの外側ビームの用途にする
ため、前記一定支点の位置を各々前記プレートガーダの
両端から約L/5にし、前記プレフレクション荷重の載
荷位置を各々前記プレートガーダの両端から約L/4と
L/2になるようにすることを特徴とする請求項8に記
載のプレフレックスビームの製作方法。
11. For use as an outer beam of a continuous beam, the position of the fixed fulcrum is set to about L / 5 from both ends of the plate girder, and the loading position of the pre-reflection load is set to both ends of the plate girder. To about L / 4 and L / 2. 9. The method for manufacturing a preflex beam according to claim 8, wherein
【請求項12】 前記プレートガーダの長さが20m以
下の場合、前記下側支持台は各々前記プレフレクション
荷重の載荷位置に設けられ、前記下側支持台の設置段階
後、前記上側プレートガーダを支持する複数の上側支持
台を前記下側支持台の設置位置と同一に前記上側プレー
トガーダに設ける段階をさらに含むことを特徴とする請
求項9から請求項11のいずれかに記載のプレフレック
スビームの製作方法。
12. When the length of the plate girder is 20 m or less, the lower supports are respectively provided at the loading positions of the pre-reflection load, and the upper plate girder is installed after the installation of the lower supports. The pre-flex according to any one of claims 9 to 11, further comprising the step of providing a plurality of upper support bases for supporting the upper support plate on the upper plate girder at the same position as that of the lower support support. Beam manufacturing method.
【請求項13】 前記プレートガーダの長さが20m〜
30mの範囲の場合、前記下側支持台は各々前記下側プ
レートガーダの両端から0.1Lと0.5Lになる三カ
所に設けられ、 前記下側支持台の設置段階後、前記上側プレートガーダ
を支持する複数の上側支持台を前記下側支持台の設置位
置と同一に前記上側プレートガーダに設ける段階をさら
に含むことを特徴とする請求項9から請求項11のいず
れかに記載のプレフレックスビームの製作方法。
13. The plate girder has a length of 20 m to
In the case of the range of 30 m, the lower support bases are provided at three places, 0.1L and 0.5L from both ends of the lower plate girder, respectively. The pre-flex according to any one of claims 9 to 11, further comprising the step of providing a plurality of upper support bases for supporting the upper support plate on the upper plate girder at the same position as that of the lower support support. Beam manufacturing method.
【請求項14】 前記プレートガーダの長さが30m以
上の場合、前記下側支持台は各々前記下側プレートガー
ダの両端から0.1Lと0.3Lになる四カ所に設けら
れ、 前記下側支持台の設置段階後、前記上側プレートガーダ
を支持する複数の上側支持台を前記下側支持台の設置位
置と同一に前記上側プレートガーダに設ける段階をさら
に含むことを特徴とする請求項9から請求項11のいず
れかに記載のプレフレックスビームの製作方法。
14. When the length of the plate girder is 30 m or more, the lower support bases are provided at four positions of 0.1 L and 0.3 L from both ends of the lower plate girder, respectively. 10. The method according to claim 9, further comprising a step of providing a plurality of upper supporters for supporting the upper plate girder on the upper plate girder at the same position as the lower supporter, after the supporting step is installed. The method for manufacturing a preflex beam according to claim 11.
【請求項15】 前記第1組の上下側プレートガーダと
並んで配置された前記第2組の上下側プレートガーダは
少なくとも一つ以上で構成されることを特徴とする請求
項1または請求項8に記載のプレフレックスビームの製
作方法。
15. The upper and lower plate girders of the second set, which are arranged side by side with the upper and lower plate girders of the first set, are configured by at least one or more. Manufacturing method of pre-flex beam described in.
【請求項16】 お互い上下側に配置された第1組のそ
りを付けない直線形の圧延形鋼を設け、前記第1組の上
下側圧延形鋼を一定支点でPS棒鋼を利用して連結する
段階と、 お互い上下側に配置された第2組のそりを付けない直線
形の圧延形鋼を設け、前記第2組の上下側圧延形鋼を一
定支点でPS棒鋼を利用して連結する段階と、 前記第1組の上下側圧延形鋼と第2組の上下側圧延形鋼
を一定間隔を開けて並んで配置する段階と、 前記第1組及び第2組の上側圧延形鋼と前記第1組及び
第2組の下側圧延形鋼を各々一定間隔を開けて配置され
た複数の上側ダイアフラムと下側ダイアフラムを利用し
てお互い連結する段階と、 前記各下側ダイアフラムに下側支持台を設ける段階と、 プレフレクション荷重の載荷位置に該当する各組の上側
圧延形鋼と下側圧延形鋼との間に油圧ジャッキを設け、
前記油圧ジャッキを利用して前記上下側圧延形鋼にプレ
フレクション荷重を加えて塑性変形を起こしてそりを付
ける段階と、 前記各下側圧延形鋼の上部の一定支点に支持部材を設け
る段階と、 前記一定支点に設けられたPS棒鋼とプレフレクション
荷重の載荷位置に設けられた油圧ジャッキを除去する段
階と、 プレフレクション荷重の載荷位置に該当する各組の上側
圧延形鋼の上部または各組の下側圧延形鋼の下部に油圧
ジャッキを設ける段階と、 四角フレームを利用して前記各組の上側圧延形鋼と下側
圧延形鋼、そして油圧ジャッキを堅固に取り囲む段階
と、 前記油圧ジャッキを利用して前記各組の圧延形鋼にプレ
フレクション荷重を加える段階と、 隣接した前記各上側圧延形鋼の下部フランジと下側圧延
形鋼の上部フランジにコンクリートを被覆する段階とを
含めてなされることを特徴とするそりを付けない直線形
の圧延形鋼を用いたプレフレックスビームの製作方法。
16. A pair of first and second straight rolled steel bars without a warp, which are arranged on the upper and lower sides of each other, are provided, and the first and upper rolled steel bars are connected at a fixed fulcrum using PS steel bars. And a second set of straight rolled steel bars without a warp, which are arranged on the upper and lower sides of each other, are provided, and the second set of upper and lower rolled steel bars are connected using PS steel bars at a fixed fulcrum. A step of arranging the first set of upper and lower rolled shape steels and a second set of upper and lower rolled shape steels side by side at regular intervals, and the first and second set of upper rolled shape steels Connecting the lower rolled shaped steels of the first set and the second set to each other using a plurality of upper diaphragms and lower diaphragms arranged at regular intervals, and connecting each of the lower diaphragms to the lower side. The stage of installing the support and the upper side of each set corresponding to the loading position of the pre-reflection load The hydraulic jack is provided between the rolled shape steel and the lower rolling shape steel,
Applying a pre-load to the upper and lower rolled steel bars by using the hydraulic jack to cause plastic deformation and warp, and a step of providing a supporting member at a fixed fulcrum above each of the lower rolled steel bars. And a step of removing the PS steel bar provided at the fixed fulcrum and the hydraulic jack provided at the loading position of the pre-reflection load, and an upper part of each set of the upper rolled shaped steels corresponding to the loading position of the pre-reflection load Or, a step of providing a hydraulic jack on the lower part of the lower rolled section steel of each set, and a step of firmly surrounding the upper rolled section steel and the lower rolled section steel of each set and the hydraulic jack using a square frame, Applying a pre-reflection load to each set of rolled steel bars using the hydraulic jack, and connecting the lower flange of each upper rolled steel bar and the upper flange of each lower rolled steel bar adjacent to each other. Pre flexbeam fabrication method using the linear rolling shaped steel without the sled, characterized in that it is made, including the steps of coating the over bets.
【請求項17】 単純ビームの用途にするため、前記一
定支点の位置を各々前記圧延形鋼の両端にし、前記プレ
フレクション荷重の載荷位置を各々前記プレートガーダ
の両端から約L/5になるようにすることを特徴とする
請求項16に記載のそりを付けない直線形の圧延形鋼を
用いたプレフレックスビームの製作方法。
17. For use as a simple beam, the fixed fulcrums are located at both ends of the rolled section steel, and the loading position of the pre-reflection load is about L / 5 from both ends of the plate girder. The method of manufacturing a pre-flex beam using a straight rolled shape steel without a warp according to claim 16, characterized in that.
【請求項18】 連続ビームの内側ビームの用途にする
ため、前記一定支点の位置を各々前記圧延形鋼の両端か
ら約L/5にし、前記プレフレクション荷重の載荷位置
を各々前記圧延形鋼の両端から約L/3になるようにす
ることを特徴とする請求項16に記載のそりを付けない
直線形の圧延形鋼を用いたプレフレックスビームの製作
方法。
18. For use as an inner beam of a continuous beam, the positions of the fixed fulcrums are set to about L / 5 from both ends of the rolled shape steel, and the loading position of the pre-reflection load is set to the rolled shape steel. 17. The method for producing a pre-flex beam using a straight rolled shape steel without a warp according to claim 16, wherein the length is set to about L / 3 from both ends.
【請求項19】 連続ビームの外側ビームの用途にする
ため、前記一定支点の位置を各々前記圧延形鋼の一側終
端と反対側終端から約L/5にし、前記プレフレクショ
ン荷重の載荷位置を各々前記圧延形鋼の両端から約L/
4とL/2になるようにすることを特徴とする請求項1
6に記載のそりを付けない直線形の圧延形鋼を用いたプ
レフレックスビームの製作方法。
19. In order to use as an outer beam of a continuous beam, the positions of the fixed fulcrums are set to about L / 5 from one end and the other end of the rolled steel, respectively, and the loading position of the pre-reflection load is set. From each end of the rolled steel to approximately L /
4. It becomes 4 and L / 2, It is characterized by the above-mentioned.
7. A method for manufacturing a preflex beam using the straight rolled steel having no warp according to 6.
【請求項20】 前記圧延形鋼の長さが20m以下の場
合、前記下側支持台は各々前記プレフレクション荷重の
載荷位置に設けられ、 前記下側支持台の設置段階後、前記上側圧延形鋼を支持
する複数の上側支持台を前記下側支持台の設置位置と同
一に前記上側圧延形鋼に設ける段階をさらに含むことを
特徴とする請求項17から請求項19のいずれかに記載
のそりを付けない直線形の圧延形鋼を用いたプレフレッ
クスビームの製作方法。
20. When the length of the rolled steel is 20 m or less, each of the lower supports is provided at the loading position of the pre-reflection load, and after the installation of the lower support, the upper rolling is performed. 20. The method according to claim 17, further comprising the step of providing a plurality of upper supporting bases for supporting the shaped steel in the upper rolled shaped steel at the same position as the installation position of the lower supporting base. Manufacturing method of pre-flex beam using straight rolled steel without warping.
【請求項21】 前記圧延形鋼の長さが20m〜30m
の範囲の場合、前記下側支持台は各々前記下側圧延形鋼
の両端から0.1Lと0.5Lになる三カ所に設けら
れ、 前記下側支持台の設置段階後、前記上側圧延形鋼を支持
する複数の上側支持台を前記下側支持台の設置位置と同
一に前記上側圧延形鋼に設ける段階をさらに含むことを
特徴とする請求項17から請求項19のいずれかに記載
のそりを付けない直線形の圧延形鋼を用いたプレフレッ
クスビームの製作方法。
21. The rolled shaped steel has a length of 20 m to 30 m.
In the case of the above range, the lower support bases are respectively provided at three places of 0.1L and 0.5L from both ends of the lower rolled shape steel. 20. The method according to claim 17, further comprising the step of providing a plurality of upper supporting bases for supporting the steel on the upper rolled shaped steel at the same position as the installation position of the lower supporting base. Manufacturing method of pre-flex beam using straight rolled steel without warping.
【請求項22】 前記圧延形鋼の長さが30m以上の場
合、前記下側支持台は各々前記下側圧延形鋼の両端から
0.1Lと0.3Lになる四カ所に設けられ、 前記下側支持台の設置段階後、前記上側圧延形鋼を支持
する複数の上側支持台を前記下側支持台の設置位置と同
一に前記上側圧延形鋼に設ける段階をさらに含むことを
特徴とする請求項17から請求項19のいずれかに記載
のそりを付けない直線形の圧延形鋼を用いたプレフレッ
クスビームの製作方法。
22. When the length of the rolled steel strip is 30 m or more, the lower support bases are provided at four positions of 0.1 L and 0.3 L from both ends of the lower rolled steel strip, respectively. After the step of installing the lower support base, the method further comprises the step of providing a plurality of upper support bases supporting the upper rolled shape steel on the upper rolled shape steel at the same positions as the installation positions of the lower support base. A method of manufacturing a pre-flex beam using the straight rolled steel having no warpage according to any one of claims 17 to 19.
【請求項23】 そりを付けない直線形圧延形鋼の両端
にボルトを利用してダミー圧延形鋼を連結させる段階
と、 一対よりなる第1組の前記圧延形鋼を上下側に配置し、
その支点になる両端をPS棒鋼を利用して連結する段階
と、 他の一対よりなる第2組の前記圧延形鋼を上下側に配置
し、その支点になる両端をPS棒鋼を利用して連結する
段階と、 前記第1組の上下側圧延形鋼と第2組の上下側圧延形鋼
を一定間隔を開けて並んで配置する段階と、 前記第1組及び第2組の上側圧延形鋼と前記第1組及び
第2組の下側圧延形鋼を各々一定間隔を開けて配置され
た複数の上側ダイアフラムと下側ダイアフラムを利用し
てお互い連結する段階と、 前記各下側ダイアフラムに下側支持台を設ける段階と、 プレフレクション荷重の載荷位置になる、各組の上側圧
延形鋼のボルト連結部と下側圧延形鋼のボルト連結部と
の間に油圧ジャッキを設け、前記油圧ジャッキを利用し
て前記上下側圧延形鋼にプレフレクション荷重を加える
段階と、 前記各上側圧延形鋼からダミー圧延形鋼を除外した残り
圧延形鋼の上部フランジと前記各下側圧延形鋼からダミ
ー圧延形鋼を除外した残り圧延形鋼の下部フランジにコ
ンクリートを被覆する段階と、 前記各下側圧延形鋼の上部の一定支点に支持部材を設け
る段階と、 前記PS棒鋼と油圧ジャッキを除去する段階と、 各組の上側圧延形鋼の上部または各組の下側圧延形鋼の
下部のボルト連結部に油圧ジャッキを設ける段階と、 四角フレームを利用して前記各組の上側圧延形鋼と下側
圧延形鋼、そして油圧ジャッキを堅固に取り囲む段階
と、 前記油圧ジャッキを利用して前記各組の圧延形鋼にプレ
フレクション荷重を加えるる段階と、 前記各上側圧延形鋼からダミー圧延形鋼を除外した残り
圧延形鋼の下部フランジと前記各下側圧延形鋼からダミ
ー圧延形鋼を除外した残り圧延形鋼の上部フランジにコ
ンクリートを被覆する段階と、 コンクリートが被覆された前記各圧延形鋼の両端に連結
されたダミー圧延形鋼を解体する段階とを含めてなるこ
とを特徴とするパイル及び柱用プレフレックスビームの
製作方法。
23. A step of connecting dummy rolled steel bars using bolts to both ends of a straight rolled steel sheet without warping, and arranging a pair of the first rolled steel sheets above and below,
A step of connecting both ends to be the fulcrum by using PS steel bar, and a second pair of the above-mentioned rolled shaped steels arranged in another pair are arranged on the upper and lower sides, and both ends to be the fulcrum are connected using PS steel bar. And a step of arranging the first set of upper and lower rolled shape steels and the second set of upper and lower rolled shape steels side by side at regular intervals, and the first and second sets of upper rolled shape steels. And connecting the lower rolled shaped steels of the first set and the second set to each other by using a plurality of upper diaphragms and lower diaphragms arranged at regular intervals, and connecting the lower rolled steel bars to the lower diaphragms. A hydraulic jack is provided between the bolt connection part of the upper rolling section steel and the bolt connection section of the lower rolling section steel of each set at the stage where the side support base is installed and at the loading position of the pre-reflection load. Use a jack to pre-flex the upper and lower rolled steel The step of applying a load, the upper flange of the remaining rolled shape steel excluding the dummy rolled shape steel from each of the upper rolled shape steel and the lower flange of the remaining rolled shape steel excluding the dummy rolled shape steel from each of the lower rolled shape steel With concrete, a step of providing a supporting member at a fixed fulcrum above each of the lower rolled steel bars, a step of removing the PS steel bar and the hydraulic jack, an upper portion of each upper rolled steel bar of each set or Providing a hydraulic jack in the lower bolt connection part of the lower rolled section steel of each set, and firmly surrounding the upper rolled section steel and lower rolled section steel of each set and the hydraulic jack using a square frame. A step of applying a pre-reflection load to each of the rolled shaped steels of the set using the hydraulic jack, and a lower flange of the remaining rolled shaped steel excluding the dummy rolled shaped steel from each of the upper rolled shaped steels. Note: The step of coating the upper flange of the remaining rolled shape steel excluding the dummy rolled shape steel from each lower rolled shape steel with concrete, and the dummy rolled shape steel connected to both ends of each rolled shape steel covered with concrete. A method of manufacturing a preflex beam for a pile and a pillar, which comprises a step of dismantling.
【請求項24】 腹部コンクリートにも圧縮応力を導入
すべきな場合、前記圧延形鋼の腹部にコンクリートを被
覆しPC鋼線を挿入した後、プレテンション方法による
圧縮応力を導入する段階がさらに含まれることを特徴と
する請求項23に記載のパイル及び柱用プレフレックス
ビームの製作方法。
24. When compressive stress should be introduced into abdominal concrete, the method further includes the step of coating the abdomen of the rolled shaped steel with concrete and inserting a PC steel wire, and then introducing compressive stress by a pretensioning method. 24. The method for manufacturing a preflex beam for piles and columns according to claim 23, wherein:
【請求項25】 製作されるプレフレックスビームが一
定長さ以上になる場合、前記各圧延形鋼の連結部断面を
拡大して剛性を増やす段階と、 相手圧延形鋼が挿入されるためのグラウティング溝を作
って前記圧延形鋼をお互い結合する段階と、 前記グラウティング溝を介してグラウティング剤を注入
する段階とをさらに含めてなることを特徴とする請求項
23に記載のパイル及び柱用プレフレックスビームの製
作方法。
25. When the pre-flex beam to be manufactured has a predetermined length or more, a step of expanding the cross section of the connecting portion of each rolled shape steel to increase the rigidity, and a grou for inserting the mating rolled shape steel. The pile and the pillar according to claim 23, further comprising: forming a grooving groove to bond the rolled shaped steels to each other; and injecting a grouting agent through the grouting groove. For manufacturing pre-flex beam for car.
【請求項26】 前記圧延形鋼の長さが20m以下の場
合、前記下側支持台は各々前記プレフレクション荷重の
載荷位置に設けられ、 前記下側支持台の設置段階後、前記上側圧延形鋼を支持
する複数の上側支持台を前記下側支持台の設置位置と同
一に前記上側圧延形鋼に設ける段階をさらに含むことを
特徴とする請求項23に記載のパイル及び柱用フリーフ
レックス型の製作方法。
26. When the length of the rolled steel is 20 m or less, the lower supports are respectively provided at the loading positions of the pre-reflection load, and after the installation of the lower supports, the upper rolling is performed. The free flex for pile and column according to claim 23, further comprising the step of providing a plurality of upper supporting bases for supporting the shaped steel in the upper rolled shaped steel at the same position as the installation position of the lower supporting base. How to make a mold.
【請求項27】 前記圧延形鋼の長さが20m〜30m
の範囲の場合、前記下側支持台は各々前記下側圧延形鋼
の両端から0.1Lと0.5Lになる三カ所に設けら
れ、 前記下側支持台の設置段階後、前記上側圧延形鋼を支持
する複数の上側支持台を前記下側支持台の設置位置と同
一に前記上側圧延形鋼に設ける段階をさらに含むことを
特徴とする請求項23に記載のパイル及び柱用フリーフ
レックス型の製作方法。
27. The rolled shaped steel has a length of 20 m to 30 m.
In the case of the above range, the lower support bases are respectively provided at three places of 0.1L and 0.5L from both ends of the lower rolled shape steel. 24. The pile and pillar free flex type of claim 23, further comprising the step of providing a plurality of upper supporting bases for supporting the steel on the upper rolled shaped steel at the same position as that of the lower supporting base. How to make.
【請求項28】 前記圧延形鋼の長さが30m以上の場
合、前記下側支持台は各々前記下側圧延形鋼の両端から
0.1Lと0.3Lになる四カ所に設けられ、 前記下側支持台の設置段階後、前記上側圧延形鋼を支持
する複数の上側支持台を前記下側支持台の設置位置と同
一に前記上側圧延形鋼に設ける段階をさらに含むことを
特徴とする請求項23に記載のパイル及び柱用フリーフ
レックス型の製作方法。
28. When the length of the rolled section steel is 30 m or more, the lower support bases are provided at four positions of 0.1 L and 0.3 L from both ends of the lower rolled section steel, respectively. After the step of installing the lower support base, the method further comprises the step of providing a plurality of upper support bases supporting the upper rolled shape steel on the upper rolled shape steel at the same positions as the installation positions of the lower support base. A method for manufacturing a pile and a post-free flex type according to claim 23.
【請求項29】 前記第1組の上下側圧延形鋼と並んで
配置された前記第2組の上下側圧延形鋼は少なくとも一
つ以上で構成されることを特徴とする請求項23に記載
のパイル及び柱用プレフレックスビームの製作方法。
29. The upper and lower rolled shape steels of the second set arranged side by side with the upper and lower rolled shape steels of the first set are configured by at least one or more. For manufacturing pre-flex beams for piles and columns.
JP2000266052A 1999-09-03 2000-09-01 Preflex beam manufacturing method Expired - Fee Related JP3443617B2 (en)

Applications Claiming Priority (13)

Application Number Priority Date Filing Date Title
KR1019990037506A KR19990083979A (en) 1999-09-03 1999-09-03 A Great Quantity Production Method for Curved Simple & Continuous Preflex Beam
KR199937506 1999-09-03
KR200022033 2000-04-25
KR200022034 2000-04-25
KR1020000022033A KR20000049711A (en) 2000-04-25 2000-04-25 Manufacturing method of preplex pile and column
KR200022032 2000-04-25
KR1020000022032A KR20000049710A (en) 2000-04-25 2000-04-25 Fabrication method of prestressed composite beam using H-beam
KR1020000022034A KR20000058343A (en) 2000-04-25 2000-04-25 A Method for Prestressing Adjacent Upper & Lower Flange in More Than Two Band of Preflex Beam
KR200011805 2000-04-25
KR2020000011805U KR200211591Y1 (en) 2000-04-25 2000-04-25 Sectional Structure of Piles and Columns Using Preflex Beams
KR1020000039748A KR20000063437A (en) 2000-07-11 2000-07-11 Fabrication method of preflex type for simple beam and continuous beam structure
KR200039748 2000-07-11
US09/955,283 US20030051437A1 (en) 1999-09-03 2001-09-18 Polymer powder blending apparatus

Publications (2)

Publication Number Publication Date
JP2001123578A JP2001123578A (en) 2001-05-08
JP3443617B2 true JP3443617B2 (en) 2003-09-08

Family

ID=27567139

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000266052A Expired - Fee Related JP3443617B2 (en) 1999-09-03 2000-09-01 Preflex beam manufacturing method

Country Status (4)

Country Link
EP (1) EP1179105A4 (en)
JP (1) JP3443617B2 (en)
AU (1) AU7039000A (en)
WO (1) WO2001018319A1 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10259584A1 (en) * 2002-04-04 2004-07-15 Gerhards, Karl, Dipl.-Ing. Manufacturing method for steel flexure beam e.g. for high-speed train track carrier or bridge structure, has pre-stressed base profile combined with plate for completing beam cross-sectional profile
CZ297559B6 (en) * 2004-03-16 2007-02-07 Rojík@Václav Floor concrete beam and process for producing thereof
KR101339362B1 (en) 2013-08-02 2013-12-09 민대홍 Method for loading pre-flex load
CN109024276B (en) * 2018-07-25 2020-06-12 重庆交通大学 Cable-stayed bridge cable tower steel frame penetration system
KR102485849B1 (en) * 2021-12-23 2023-01-09 구민세 Manufacturing method of pre-flex composite beam that causes bulging due to plastic deformation of steel beam

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1048852A (en) * 1951-09-21 1953-12-24 Anciens Etablissements Metallu Prestressed metal parts and method for prestressing such parts
US4493177A (en) * 1981-11-25 1985-01-15 Grossman Stanley J Composite, pre-stressed structural member and method of forming same
JPS6011171B2 (en) * 1982-07-30 1985-03-23 川田工業株式会社 Prestress introduction method and device for prestressed steel girders
US4709456A (en) * 1984-03-02 1987-12-01 Stress Steel Co., Inc. Method for making a prestressed composite structure and structure made thereby
LU86442A1 (en) * 1986-05-23 1987-12-16 Arbed PROCESS FOR THE MANUFACTURE OF PRE-STRESSED STEEL BEAMS
JPH1136224A (en) * 1997-07-15 1999-02-09 Ohbayashi Corp Prestress introducing method and introducing device for prestress concrete
KR100341165B1 (en) * 1998-07-03 2002-11-29 (주)한국해외기술공사 Construction method of preflex molding by factory production
KR100282773B1 (en) * 1998-07-03 2001-03-02 구민세 Preflex type manufacturing method

Also Published As

Publication number Publication date
AU7039000A (en) 2001-04-10
EP1179105A4 (en) 2003-08-27
JP2001123578A (en) 2001-05-08
WO2001018319A1 (en) 2001-03-15
EP1179105A1 (en) 2002-02-13

Similar Documents

Publication Publication Date Title
WO2001027406A1 (en) Method for designing and fabricating multi-step tension prestressed girder
CN100529264C (en) Method of applying prestress and connecting means used therein and prestressed concrete beam therefrom
JP3443617B2 (en) Preflex beam manufacturing method
KR101209063B1 (en) Pre-stressed girder by plate and method thereof
KR200333102Y1 (en) H-Beam Combined with Reinforcement Panel
KR20230041309A (en) Earthquake resistance design structure
KR100889857B1 (en) Rigidity steel beam manufacturing method
KR100402235B1 (en) Construction method of pile pile for earth wall using preflex composite beam
JPH11152929A (en) Seismic strengthening method for steel building.
JPH11350778A (en) Damping damper and damping structure
US20030051433A1 (en) Method of manufacturing preflex beams
KR102491179B1 (en) Preflex steel girder and the manufacturing method
JP3411884B2 (en) Supporting member and earth retaining support using the same
JP4490853B2 (en) Brace structure using shape memory alloy
JP2008050788A (en) Seismic reinforcement structure for existing buildings
KR100657745B1 (en) Cactus Compressors
KR20090112983A (en) Joining structure of wood members
KR100416217B1 (en) Composite structural material
JP2686372B2 (en) Unit house
KR101912422B1 (en) Composite beam fabricating method with pre-load process and composite beam using the same
TWI837047B (en) Part-span side sealing plate anti-frustration buckling method
KR200321141Y1 (en) H-Beam Combined with Reinforcement Panel
JP7852425B2 (en) Beam design method
JP7397752B2 (en) concrete member structure
JP7491606B2 (en) Structural base materials, structural members and structures

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20030325

R150 Certificate of patent or registration of utility model

Ref document number: 3443617

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080627

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090627

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100627

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100627

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110627

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120627

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130627

Year of fee payment: 10

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees