Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP3446151B2 - Bucket discharging instruction device for earth drill excavator - Google Patents
[go: Go Back, main page]

JP3446151B2 - Bucket discharging instruction device for earth drill excavator - Google Patents

Bucket discharging instruction device for earth drill excavator

Info

Publication number
JP3446151B2
JP3446151B2 JP00189895A JP189895A JP3446151B2 JP 3446151 B2 JP3446151 B2 JP 3446151B2 JP 00189895 A JP00189895 A JP 00189895A JP 189895 A JP189895 A JP 189895A JP 3446151 B2 JP3446151 B2 JP 3446151B2
Authority
JP
Japan
Prior art keywords
bucket
depth
excavation
earth
length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP00189895A
Other languages
Japanese (ja)
Other versions
JPH08189283A (en
Inventor
寿保 美濃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Heavy Industries Construction Crane Co Ltd
Original Assignee
Sumitomo Heavy Industries Construction Crane Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Heavy Industries Construction Crane Co Ltd filed Critical Sumitomo Heavy Industries Construction Crane Co Ltd
Priority to JP00189895A priority Critical patent/JP3446151B2/en
Publication of JPH08189283A publication Critical patent/JPH08189283A/en
Application granted granted Critical
Publication of JP3446151B2 publication Critical patent/JP3446151B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、ア−スドリル掘削機に
よる掘削作業時にバケツが土砂等により一杯になり、作
業効率が下がることを防止する為にバケツからの土砂の
排土指示を出すようにしたア−スドリル掘削機のバケツ
排土指示装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention provides an instruction to discharge earth and sand from a bucket in order to prevent the bucket from being filled with earth and sand during excavation work by an earth drill excavator and lowering work efficiency. The present invention relates to a bucket earth removal instruction device for an earth drill excavator.

【0002】[0002]

【従来の技術】従来のア−スドリル掘削機では、土砂等
によりバケツの掘削効率が下がらないように、オペレ−
タが深度計等から掘削した深さを知り、バケツが一杯に
なっているかどうかを判断していた為、経験が必要であ
り、又、たえず深度計表示部を見ていなければならず、
オペレ−タの負担が大きかった。
2. Description of the Related Art In a conventional earth drill excavator, an operator operates an excavator to prevent the excavation efficiency of a bucket from being lowered by soil or the like.
Since he knew the depth of excavation from the depth gauge etc. and judged whether the bucket was full, experience was necessary, and he had to constantly look at the depth gauge display section,
The burden on the operator was heavy.

【0003】[0003]

【発明が解決しようとする課題】本発明は、上述した従
来のア−スドリル掘削機の問題点を解決すべく、オペレ
−タが深度計表示部を見ないでも掘削作業を行うことが
でき、オペレ−タの負担を軽減することを目的とする。
SUMMARY OF THE INVENTION In order to solve the above-mentioned problems of the conventional ground drill excavator, the present invention enables excavation work without the operator looking at the depth gauge display. The purpose is to reduce the burden on the operator.

【0004】[0004]

【課題を解決するための手段】バケツ深さ設定手段と、
土砂係数設定手段と、掘進長を検出する手段と、演算部
と、排土指示を表示する表示部とを有し、前記演算部
に、前記バケツ深さ設定手段により設定されたバケツ深
さと前記土砂係数設定手段により設定された土砂係数と
を乗じた値を前記掘進長を検出する手段により検出され
た掘進長とを比較する手段と、この比較する手段により
掘進長がバケツ深さと土砂係数とを乗じた値より大きく
なった場合に排土指示信号を出力し、前記表示部に排土
指示を表示する手段とを設けた。
[Means for Solving the Problems] Bucket depth setting means,
It has a sediment factor setting means, a means for detecting the length of excavation, a calculation section, and a display section for displaying a discharge instruction, and the calculation section has the bucket depth and the bucket depth set by the bucket depth setting means. A means for comparing the value obtained by multiplying the sediment coefficient set by the sediment coefficient setting means with the excavation length detected by the means for detecting the excavation length, and the excavation depth by this comparison means is the bucket depth and the sediment coefficient. And a means for outputting an earth unloading instruction signal and displaying the earth unloading instruction on the display unit when the value becomes larger than the value multiplied by.

【0005】[0005]

【作用】演算部にバケツ深さと掘削する地盤による補正
係数である土砂係数を入力する。又、それとは別に掘進
長を検出する手段よりたえず送られてくる掘進長が入力
されている。それらの入力を比較することによりバケツ
が土砂が一杯であることを判断して、表示部に排土指示
を表示する。なお図4に示すように、1回目の掘削深度
(前回排土時の掘削深度)を掘削深度1とし、2回目の
掘削深度(現在の掘削深度)を掘削深度2とすると、掘
進長は、掘進長=掘削深度2−掘削深度1と定義される
ものである。
[Operation] The bucket depth and the sediment coefficient, which is a correction coefficient depending on the ground to be excavated, are input to the calculation unit. In addition to this, the excavation length which is constantly sent from the means for detecting the excavation length is input. By comparing these inputs, it is determined that the bucket is full of earth and sand, and the earth discharging instruction is displayed on the display unit. As shown in FIG. 4, assuming that the first excavation depth (excavation depth at the previous earth removal) is excavation depth 1 and the second excavation depth (current excavation depth) is excavation depth 2, the advancing length is The excavation length = excavation depth 2−excavation depth 1 is defined.

【0006】[0006]

【実施例】本発明の実施例を図面に基いて説明する。図
1は、ア−スドリル掘削機の概略側面図であり、1はア
−スドリル本体、2はバケツであり、3は土中でのバケ
ツの位置を掘進長として表示する深度計である。バケツ
排土指示装置4は、ア−スドリル本体1の運転室内に装
備されている。
Embodiments of the present invention will be described with reference to the drawings. FIG. 1 is a schematic side view of an ass drill excavator, 1 is an ass drill main body, 2 is a bucket, and 3 is a depth gauge for displaying the position of the bucket in the soil as the excavation length. The bucket earth removal instruction device 4 is installed in the cab of the earth drill body 1.

【0007】図2は、バケツ排土指示装置4の構成を示
すブロック図である。図2のブロック図の構成をマイク
ロコンピュ−タを用いて実現した場合の、処理の流れを
示すフロ−チャ−トを図3に示す。以下、図2と図3を
参照して、バケツ排土指示装置の処理の流れを説明す
る。
FIG. 2 is a block diagram showing the construction of the bucket earth discharging instruction device 4. FIG. 3 shows a flow chart showing the flow of processing when the configuration of the block diagram of FIG. 2 is realized by using a microcomputer. The process flow of the bucket earth unloading instruction device will be described below with reference to FIGS. 2 and 3.

【0008】まず、バケツ深さ設定手段7により設定さ
れたバケツ深さhを読み込む(ステップ1)。このバケ
ツ深さhは、ア−スドリルに取り付けられているバケツ
2の深さである。次に、土砂係数設定手段8により設定
された土砂係数kを読み込む(ステップ2)。
First, the bucket depth h set by the bucket depth setting means 7 is read (step 1). This bucket depth h is the depth of the bucket 2 attached to the ground drill. Next, the sediment coefficient k set by the sediment coefficient setting means 8 is read (step 2).

【0009】バケツ深さhと土砂係数kとを演算部5に
読み込んだ後に、掘削作業に入る。掘進長を検出する手
段6により検出された掘進長と、前記バケツ深さhと土
砂係数kとを乗じた値とを演算部5の比較手段により比
較する(ステップ3)。
After the bucket depth h and the sediment coefficient k are read into the arithmetic unit 5, excavation work is started. The excavation length detected by the excavation length detecting means 6 is compared with the value obtained by multiplying the bucket depth h by the sediment factor k by the comparing means of the arithmetic unit 5 (step 3).

【0010】ここで、掘進長が、kとhとを乗じた値
(k×h)より大きくなった場合には、バケツ2が土砂
で一杯になったと判断し、排土指示信号を出力し(ステ
ップ4)、表示部に排土指示を表示する。バケツが排土
されるまで信号を出力し(ステップ5)、排土されれば
掘進長をゼロクリアし(ステップ6)、上記フロ−を再
度行う。バケツ深さhや土砂係数kの変更があれば、バ
ケツ深さ設定手段6又は土砂係数設定手段8により設定
を再度行う。
If the excavation length becomes larger than a value (k × h) obtained by multiplying k by h, it is judged that the bucket 2 is full of earth and sand, and an earth discharging instruction signal is output. (Step 4), an earth removal instruction is displayed on the display unit. A signal is output until the bucket is discharged (step 5). When the bucket is discharged, the excavation length is cleared to zero (step 6), and the above-mentioned flow is performed again. When the bucket depth h or the sediment coefficient k is changed, the bucket depth setting means 6 or the sediment coefficient setting means 8 sets again.

【0011】[0011]

【発明の効果】以上のように本発明によれば、自動的に
バケツの排土指示がなされるため、従来とは違ってオペ
レ−タの技量,経験に依らずに排土作業が行なうことが
でき、オペレ−タの負担も軽減できる。
As described above, according to the present invention, since the instruction for soil removal of the bucket is automatically given, unlike the conventional case, the soil removal work can be performed regardless of the skill and experience of the operator. It is possible to reduce the burden on the operator.

【図面の簡単な説明】[Brief description of drawings]

【図1】ア−スドリル掘削機の概略側面図。FIG. 1 is a schematic side view of an earth drill excavator.

【図2】バケツ排土指示装置の構成を示すブロック図。FIG. 2 is a block diagram showing a configuration of a bucket earth removal instruction device.

【図3】バケツ排土指示装置の処理の流れを示すフロ−
チャ−ト。
FIG. 3 is a flow chart showing a processing flow of the bucket earth discharging instruction device.
Chart.

【図4】掘進長の定義を説明する図。FIG. 4 is a diagram for explaining the definition of a digging length.

【符号の説明】[Explanation of symbols]

1 ア−スドリル本体 2 バケツ 3 深度計 4 バケツ排土指示
装置 5 演算部 6 掘進長検出手段 7 バケツ深さ設定手段 8 土砂係数設定手
段 9 表示部
1 Aace Drill Main Body 2 Bucket 3 Depth Meter 4 Bucket Discharge Indication Device 5 Calculation Section 6 Excavation Length Detection Means 7 Bucket Depth Setting Means 8 Sediment Coefficient Setting Means 9 Display Section

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 バケツ深さ設定手段と、土砂係数設定手
段と、掘進長を検出する手段と、演算部と、排土指示を
表示する表示部とを有し、前記演算部に、前記バケツ深
さ設定手段により設定されたバケツ深さと前記土砂係数
設定手段により設定された土砂係数とを乗じた値を前記
掘進長を検出する手段により検出された掘進長とを比較
する手段と、この比較する手段により掘進長がバケツ深
さと土砂係数とを乗じた値より大きくなった場合に排土
指示信号を出力し、前記表示部に排土指示を表示する手
段とを設けたことを特徴とするア−スドリル掘削機のバ
ケツ排土指示装置。
1. A bucket depth setting means, a sediment coefficient setting means, a means for detecting the length of excavation, a calculation section, and a display section for displaying a discharge instruction, the calculation section including the bucket. A means for comparing the excavation length detected by the means for detecting the excavation length with a value obtained by multiplying the bucket depth set by the depth setting means and the sediment coefficient set by the sediment coefficient setting means, and this comparison When the excavation length becomes larger than the value obtained by multiplying the bucket depth and the sediment coefficient by the means for outputting, an earth discharging instruction signal is output, and means for displaying the earth discharging instruction on the display unit is provided. Earth drill excavator bucket dumping instruction device.
【請求項2】 深度計を掘進長を検出する手段としたこ
とを特徴とするア−スドリル掘削機のバケツ排土指示装
置。
2. A bucket earth removal instructing device for an earth drill excavator, characterized in that a depth gauge is used as means for detecting the length of excavation.
JP00189895A 1995-01-10 1995-01-10 Bucket discharging instruction device for earth drill excavator Expired - Fee Related JP3446151B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP00189895A JP3446151B2 (en) 1995-01-10 1995-01-10 Bucket discharging instruction device for earth drill excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP00189895A JP3446151B2 (en) 1995-01-10 1995-01-10 Bucket discharging instruction device for earth drill excavator

Publications (2)

Publication Number Publication Date
JPH08189283A JPH08189283A (en) 1996-07-23
JP3446151B2 true JP3446151B2 (en) 2003-09-16

Family

ID=11514409

Family Applications (1)

Application Number Title Priority Date Filing Date
JP00189895A Expired - Fee Related JP3446151B2 (en) 1995-01-10 1995-01-10 Bucket discharging instruction device for earth drill excavator

Country Status (1)

Country Link
JP (1) JP3446151B2 (en)

Also Published As

Publication number Publication date
JPH08189283A (en) 1996-07-23

Similar Documents

Publication Publication Date Title
JP5908500B2 (en) Excavator image display device
CN110382790B (en) Construction machine
AU2012201039B2 (en) Method and system for monitoring the operation of a cable shovel machine
JP3286143B2 (en) Mobile automatic crushing plant and automatic excavator
JP3446151B2 (en) Bucket discharging instruction device for earth drill excavator
JP3432802B2 (en) Trencher type ground improvement machine, its construction management device and ground improvement method
JPH10246091A (en) Shield construction method and shield excavator
JP2000064360A (en) Load measuring device for hydraulic backhoe
JP3254643B2 (en) Tunnel excavator and tunnel excavation method
JP2005264651A (en) Construction control device for rotating pile
JPH1060954A (en) Excavation load measurement and display device for blasting ground
JPS62202131A (en) Bucket device for construction machinery
JP3835341B2 (en) Ditch excavator and ditch excavation support method
JPH0762980A (en) Excavation control method for tunnel excavator
JP2876263B2 (en) Drilling rig for underground continuous wall method
JP3652062B2 (en) Automatic excavation load measuring device for blasting ground
JPH11210020A (en) Automatically operated construction equipment
JP3129853B2 (en) Automatic control system of face water pressure in mud pressurized shield construction
CN114555890B (en) Engineering machinery
JP2882760B2 (en) Rock drilling device for earth drilling machine
JP3463226B2 (en) Operating device for continuous unloader
JPH0688478A (en) Automatic control device for digging speed of shield machine
JPH0518188A (en) Small-diameter pipe propulsion device
JPH0688479A (en) Automatic control device for drilling speed of shield machine
JP2000248892A (en) Slurry treatment equipment for slurry pressurizing and driving

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090704

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120704

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees