- Publication number
- JP3453261B2 JP3453261B2 JP29614896A JP29614896A JP3453261B2 JP 3453261 B2 JP3453261 B2 JP 3453261B2 JP 29614896 A JP29614896 A JP 29614896A JP 29614896 A JP29614896 A JP 29614896A JP 3453261 B2 JP3453261 B2 JP 3453261B2
- Authority
- JP
- Japan
- Prior art keywords
- bucket
- turning
- drive device
- boom
- speed command
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Ship Loading And Unloading (AREA)
Description
【発明の詳細な説明】
【0001】
【発明の属する技術分野】本発明は、連続式アンローダ
の荷揚げ量制御方法に係り、特に荷揚げ量の急変にも追
従できる制御方法に関する。
【0002】
【従来の技術】連続式アンローダは、船倉に積まれた鉱
石や石炭等の荷を連続して陸揚げする大型運搬機械であ
り、図5に示すような概略構成を有する。すなわち、図
5において、走行駆動装置11が備えられた脚上にブー
ム旋回駆動装置10にて旋回可能にブームが載り、この
ブーム上に制御機器類12及びオペレータによる入力装
置類13が置かれ、ブーム上をコンベア8が走り、ブー
ム先端のDE旋回駆動装置9にて旋回可能に支柱15が
取付けられ、この、支柱15先端に掘削部2が取付けら
れ、掘削部2とバケット駆動油圧モータ7との間にバケ
ット3が取付けられたチェーン4がかけ回されるもので
ある。なお、持上部14の支柱15に対して掘削部2は
傾転シリンダ6にて傾斜可変に支えられる。
【0003】かかる構造にあって、バケット駆動油圧モ
ータ7の駆動によりチェーン4が矢印5方向に駆動さ
れ、船倉1内の荷がバケット3にて掻き取られ、コンベ
ア8の高さ(持上部14)程持ち上げられ、コンベア8
に移されて陸上に吐き出されるようになっている。この
場合、掘削部2は、図6に示すように順に船倉1内を動
かされ、横行モード、DE旋回モード、走行モードがオ
ペレータにより指令され、各モードに対してブーム旋回
駆動装置10、DE旋回駆動装置9、走行駆動装置11
に指令値が分配され駆動される。
【0004】掘削部2による荷揚げ量の制御にあって
は、図7に示す制御方法により所定量の荷揚げ量制御を
行なっている。つまり、荷揚げ量目標値Qs がオペレー
タにより入力されると、ブロックAでバケット油圧目標
値Pbsに換算する。バケット油圧はバケット駆動油圧モ
ータ7に加わる掘削力に比例する負荷であり、荷揚げ量
が多い程大きくなり少ない程小さくなる。このため。荷
揚げ量とバケット油圧とは比例関係にあり、これら目標
値どおしの換算がブロックAにて可能となる。次に、加
え合せ点Bにてバケット駆動油圧モータ7によるバケッ
ト油圧の実績値Pbfと前述の目標値Pbsとの比較が行な
われ、この比較値をPI制御ブロックCにて横送り速度
指令Vとし、目標値Pbsに対し実績値Pbsの方が大きけ
ればその大きさに応じて横送り速度を遅くし、逆に実績
値Pbfの方が小さければその差分に応じて横送り速度を
速くしている。横送り速度指令Vが入力される速度指令
分配ブロックDでは、横送り動作モードが入力されて、
DE旋回速度指令Vd 、ブーム旋回速度指令Vb 、走行
速度指令Vs が出力される。こうして、荷揚げ量目標値
Qs となるように、実績値Pbfに基づき掘削部2の横送
り速度を増減させ一定の掘削量(力)を得る制御をして
いる。
【0005】
【発明が解決しようとする課題】上述の荷揚げ量制御に
あって、制御にて換算等されるバケット油圧は、実際上
掘削部2にて荷を掻き取る掘削力と持上部14にて荷を
持ち上げる持上力との和であり、構造寸法上掘削部2よ
り持上部14の方が長く、掘削力より持上力の方が大き
くて、バケット油圧は持上力の大きさに支配されて仕舞
いがちという問題がある、つまり、持上力が大きいので
掘削部2の掘削力変化は大きな変化とはならない。その
うえ、掘削力と持上力との関係は、掘削力をある係数倍
して一定時間積分した値を持上力としているため、例え
ば荷崩れ等により掘削力が急変したとしても持上力は徐
々にしか変化しない。この結果、荷崩れ等による掘削力
の急上昇、荷の急激な不足による掘削力の急低下が生じ
た場合でも、掘削力の急変は検知できずしかも持上力に
支配されるバケット油圧にあっては尚更変化が検知しに
くくなる。こうして、掘削力の変化による荷揚げ量の変
動に速応することができず、結局荷揚げ量の変動が大き
いままである。
【0006】本発明は、上述の問題に鑑み、掘削力の急
変を検知して荷揚げ量の変動を抑えるようにした連続式
アンローダの荷揚げ量制御方法の提供を目的とする。
【0007】
【課題を解決するための手段】上述の目的達成のため次
の発明特定事項を有する。脚に設けられた走行駆動装置
と、前記脚上に載せられたブームと、前記ブームを旋回
するブーム旋回駆動装置と、前記ブーム先端に取り付け
られたDE旋回駆動装置と、前記DE旋回駆動装置によ
り旋回する支柱と、前記支柱先端に取り付けられた掘削
部と、前記掘削部とバケット駆動油圧モータとの間にか
け回されバケットが取り付けられたチェーンと、持上部
の前記支柱に対して前記掘削部を傾斜可変に支える傾転
シリンダと、前記バケット駆動油圧モータに取り付けた
圧力センサとを備え、荷揚げ量目標値から換算されたバ
ケット油圧目標値と前記圧力センサによるバケット油圧
実績値とを比較してその差分から横送り速度指令値を求
め、この横送り速度指令値を、横行モード、DE旋回モ
ード、走行モードのうち指令された横送り動作モードに
応じて、ブーム旋回速度指令値と走行速度指令値とDE
旋回速度指令値の3つの速度指令値に分配し、この速度
指令に基づき前記ブーム旋回駆動装置、前記走行駆動装
置、前記DE旋回駆動装置を駆動する連続式アンローダ
の荷揚げ量制御方法において、前記傾転シリンダに取り
付けた圧力センサによる傾転シリンダ圧力に基づく掘削
力から掘削力変動分を求め、この掘削力変動分を比例制
御して前記横送り速度指令値を補正することを特徴とす
る。
【0008】掘削区を積分すると持上力となり、持上力
とバケット油圧はほぼ等しいことから、掘削力はバケッ
ト油圧の微分とみなすことができる。従って、掘削力の
比例制御を付加することは、バケット油圧の微分制御を
付加することと等価である。つまり、(1) 荷崩れ等
で掘削が増えた時、バケット油圧が上がりきる前に、上
がりつつあるという微分情報で、前もって横送り速度を
下げ、(2) 荷が浅くなった等で掘削が減った時、バ
ケット油圧が下がりきる前に、下がりつつあるという微
分情報で、前もって横送り速度を上げる、ということ
で、前もって横送り速度指令を上げ下げすることから、
荷揚げ量の変動を速やかに元の所定値に戻すという、即
応性の向上になる。
【0009】
【発明の実施の形態】ここで、図1〜図4を参照して発
明の実施の形態を説明する。図1は一例の全体構成図で
あり、図5と略同一の構成を有するが、制御機器類12
の入出力装置としては傾転シリンダ6、DE旋回駆動装
置9、バケット駆動油圧モータ7、ブーム旋回駆動装置
10、走行駆動装置11、及びオペレータによる入力装
置類13が存在する。かかる図1の構成にあって、入力
装置類13及び制御機器類12の構成は図2に示すよう
になる。つまり、入力装置類13ではオペレータ入力端
末13aにて荷揚げ量目標値Qs が出力され、またオペ
レータ運転操作盤13bから横行、DE旋回、走行から
なる横送り動作モードが出力される。制御機器類12で
は、図3及び図4に示す処理を行なうための制御装置1
2a及びこの制御装置12aの出力からDE旋回指令、
ブーム旋回指令、走行指令の各信号を出力するモータド
ライブ盤12bを有する。
【0010】制御装置12aの入力としては、オペレー
タ入力端末13aからの荷揚げ量目標値Qs 、オペレー
タ運転操作盤13bからの横送り動作モード、バケット
油圧駆動モータ7に取付けられた圧力センサによるバケ
ット油圧実績値の信号Pbf、傾転シリンダ6に取付けら
れた圧力センサによる傾転シリンダ圧力の信号Pkfがあ
る。そして、この制御装置12aによって図3のブロッ
クにて示される処理が行なわれる。ここでは、図7に示
す処理と同様、荷揚げ量目標値Qs をバケット油圧に比
例計算にて換算し、このバケット油圧目標値Pbsとバケ
ット油圧実績値Pbfとを比較してPI制御によりこの両
者を一致させる速度指令を出力する。
【0011】本例では更に傾転シリンダ6による圧力P
kfを制御装置12aに入力する。今掘削力Fdfが変化し
て増大した場合、掘削部2がその前方に反力を受けて傾
転シリンダ6のヘッド側圧力が大きくなりロッド側圧力
が小さくなる。また、掘削力Fdfが減少した場合には逆
の現象が生ずる。このヘッド側圧力とロッド側圧力との
値により力のバランス式から掘削力Fdfが換算でき、掘
削力Fdfの急変も傾転シリンダ6のこの圧力により検出
されることになる。他方、掘削力を積分すると持上力と
なり、持上力とバケット油圧とが略等しいことから、掘
削力はバケット油圧の微分とみなすことができ、バケッ
ト油圧の変化分とみなすことができる。したがって、掘
削力の比例制御を加えることはバケット油圧の微分制御
を加えることになる。したがって、例えば荷崩れ等で掘
削力が増大したとき、バケット油圧が上がりきる前に上
がりつつある微分情報を加え、また荷が浅くなったとき
掘削力の減少により、バケット油圧が下がりきる前に、
下がりつつある微分情報を加えることになる。この結
果、傾転シリンダ圧力Pkfにて掘削力Fdfを得て、これ
をP制御を介して得た信号は、バケット油圧に基づく横
送り速度指令Vの主回路に対しては掘削力変化に速応す
る微分情報となる。
【0012】図3にて加えられたブロックは、上述の処
理を行なう掘削力制御部Xが加えられており、傾転シリ
ンダ圧力PkfよりブロックEにて掘削力Fdfを求め、掘
削力のオフセット誤差を除去し急速な掘削力変化成分の
み通過させ低周波成分を除去するためハイパスフィルタ
Fを通し、この掘削力変動成分Fdfh を目標変に抑える
ためP制御Gによって主回路のPI制御出力である横送
り指令Vに加え合わせる。この結果、掘削力が上がれば
マイナス(遅くする)横送り速度指令となり、掘削力が
下がればプラス(速くする)横送り速度指令となって、
従来のバケット油圧制御による横送り速度指令値を補正
する。そして、この横送り速度指令値を、オペレータに
より設定された横送り動作モードに応じて、DE旋回と
ブーム旋回と走行の3つの速度指令値に分配し、モータ
ドライブ盤17に指令する。モータドライブ盤17はD
E旋回駆動装置9、ブーム旋回駆動装置10、走行駆動
装置11を駆動する。
【0013】図4は図3のブロックに基づく制御フロー
チャートである。すなわち、荷揚げ量目標値Qs は、ブ
ロックAにてバケット油圧に換算されPbs=kbs×Qs
を得て、加え合せ点Bにてこの目標値Pbsに実績値Pbf
を加え、e=Pbs−Pbfとする。この後、ブロックCに
てPI演算を行ないV1 を得る。他方、傾転シリンダ圧
力PkfをブロックEにて掘削力換算を行ないFdf=f
(Pkf)を得た後、ハイパスフィルタFを通しFdfl =
(a1 +a2 )Fdf、Fdf h =Fdf−Fdfl を求め、P
制御GにてV2 を得る。加え合せ点HではV1 +V2 =
Vを求めてV2 による補正後の横送り速度指令Vを得た
後、ブロックDでは速度指令の分配が行なわれ、各指令
Vd ,Vb ,V s を得る。
【0014】
【発明の効果】本発明の定量荷揚げ制御では、従来の油
圧制御に掘削力制御を付加し、荷揚げ量変動に対する速
応性を向上させた。こうして、荷揚げ量を所定の値に保
ちつつ。従来、荷崩れ等で発生していた荷揚げ量の大き
な変動を低減させることができるようになった。これに
より、荷揚げ量負荷による運転停止や荷揚げ量不足が改
善され、荷揚げ能力向上という有益な効果を得る。DETAILED DESCRIPTION OF THE INVENTION
[0001]
The present invention relates to a continuous unloader.
Related to the method of controlling the amount of unloading
It relates to a control method that can be followed.
[0002]
2. Description of the Related Art A continuous unloader is a type of ore loaded in a hold.
It is a large-sized transport machine that continuously unloads loads such as stone and coal.
And has a schematic configuration as shown in FIG. That is, the figure
5, the boot is mounted on the leg provided with the traveling drive device 11.
The boom is mounted so that it can be turned by the
Control devices 12 and input devices by the operator
Table 13 is placed, conveyor 8 runs on the boom,
Column that can be turned by the DE turning drive 9 at the tip of theFifteenBut
Mounted, this, strutFifteenExcavation part 2 is attached to the tip
Between the excavating section 2 and the bucket driving hydraulic motor 7.
The chain 4 to which the unit 3 is attached
is there. In addition, lifting part 14Pillar 15The excavation part 2
The tilting cylinder 6 is variably supported by the tilting cylinder.
In such a structure, a bucket driving hydraulic motor
The chain 4 is driven in the direction of arrow 5 by driving the
The cargo in the hold 1 is scraped off by the bucket 3 and
The conveyor 8 is lifted up to the height of the
It has been moved to and exhaled on land. this
In this case, the excavating part 2 moves in the hold 1 in order as shown in FIG.
Traverse mode, DE turning mode, and drive mode
Commanded by the pererator, boom swing for each mode
Drive device 10, DE turning drive device 9, traveling drive device 11
Command values are distributed and driven.
In controlling the unloading amount by the excavation section 2,
Controls a predetermined amount of unloading amount by the control method shown in FIG.
I do. That is, the unloading amount target value QsIs an operation
Block A, the bucket hydraulic pressure target
Value PbsConvert to Bucket hydraulic pressure
The load is proportional to the excavating force applied to the
The larger the value, the smaller the value. For this reason. load
There is a proportional relationship between the frying amount and the bucket oil pressure.
Conversion of values can be performed in block A. Next,
Bucket by bucket driving hydraulic motor 7 at matching point B
Actual hydraulic pressure value PbfAnd the aforementioned target value PbsComparison with
The comparison value is calculated by the PI control block C in the traverse speed.
Command V and target value PbsActual value PbsIs larger
If so, reduce the traverse speed according to the size, and conversely
Value PbfIs smaller, the traverse speed is set according to the difference.
You're fast. Speed command at which traverse speed command V is input
In the distribution block D, the traverse operation mode is input,
DE turning speed command Vd, Boom swing speed command Vb, Running
Speed command VsIs output. Thus, the unloading target value
QsSo that the actual value PbfOf excavation part 2 based on
Control to obtain a constant amount of excavation (force)
I have.
[0005]
SUMMARY OF THE INVENTION In the above-mentioned unloading amount control,
Therefore, the bucket oil pressure converted by the control is actually
The digging force to scrape the load at the digging section 2 and the load at the lift 14
It is the sum of the lifting force to lift and
The lifting part 14 is longer, and the lifting force is larger than the excavation force
The bucket oil pressure is controlled by the lifting force
There is a problem of life, that is, because the lifting power is large
The change in the digging force of the digging section 2 does not become a large change. That
In addition, the relationship between the excavating force and the lifting force is obtained by multiplying the excavating force by a certain factor.
Because the lifting force is the value integrated over a certain period of time,
Even if the excavation force suddenly changes due to collapse of the load, the lifting force is gradually reduced
Only changes individually. As a result, the excavation force due to collapse
And the excavation power suddenly drops due to a sudden shortage of cargo.
A sudden change in excavation force cannot be detected, and
In the controlled bucket oil pressure, even further changes are detected.
It becomes hard. Thus, the change in unloading amount due to the change in excavation force
Can not respond quickly, and the fluctuation of the unloading amount is large after all.
There is ever.
The present invention has been made in view of the above-described problems, and has been made in consideration of the above circumstances.
Continuous type that detects fluctuations and suppresses fluctuations in unloading amount
An object of the present invention is to provide a method for controlling the unloading amount of an unloader.
[0007]
In order to achieve the above-mentioned object, the following is provided.
Of the invention.Traveling drive device provided on the leg
And a boom mounted on the leg, and swiveling the boom
Boom swing drive device and attached to the boom tip
DE turning drive device and the DE turning drive device
A turning column and an excavation attached to the tip of the column
Part, between the excavation part and the bucket drive hydraulic motor
Chain with buckled bucket and lift
Tilting that variably supports the excavation part with respect to the support column
Cylinder and attached to the bucket drive hydraulic motor
With a pressure sensor,Unloading target valueConverted fromBa
Ket oil pressure target valueBy the pressure sensorBucket hydraulic
Compare with the actual value and determine the traverse speed command from the difference.valueSeeking
,This traverse speed command value is stored in the traverse mode and the DE turning mode.
Traverse command specified in the modeIn operation mode
DependingAnd the boom swing speed command value, travel speed command value and DE
Three of the turning speed command valuesSpeed commandTo the valueDistributionAnd this speed
The boom swing drive device and the travel drive device are
Drive the DE turning driveContinuous unloader
In the method of controlling the unloading amount ofTake the tilt cylinder
Depending on the attached pressure sensorDrilling based on tilt cylinder pressure
Excavation force fluctuation is calculated from the force, and this excavation force fluctuation is proportionally calculated.
Traverse speed commandvalueIs characterized by correcting
You.
[0008] When the excavation zone is integrated, the lifting force is obtained.
And bucket hydraulic pressure are almost equal,
G can be regarded as a derivative of the hydraulic pressure. Therefore, the drilling power
Adding proportional control makes differential control of bucket oil pressure
It is equivalent to adding. In other words, (1) collapse of cargo
When the excavation increases in
With the differential information that it is going up,
(2) When excavation is reduced due to shallower load, etc.
Before the ket oil pressure drops,
Using the minute information to increase the traversing speed in advance
In order to raise or lower the traverse speed command in advance,
Immediately return fluctuations in unloading amount to the original specified value.
Responsiveness is improved.
[0009]
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Referring now to FIGS.
A description will be given of an embodiment according to the present invention. FIG. 1 is an overall configuration diagram of an example.
And has substantially the same configuration as that of FIG.
The tilting cylinder 6 and the DE turning drive
Installation 9, bucket drive hydraulic motor 7, boom swing drive
10, a traveling drive device 11, and an input device by an operator.
There is a class 13. In the configuration of FIG.
The configuration of the devices 13 and the control devices 12 is as shown in FIG.
become. That is, in the input devices 13, the operator input terminal
The unloading target value Q at the end 13asIs output, and
From traversing, DE turning and running from the operator operation panel 13b
Is output. Control equipment 12
Is a control device 1 for performing the processing shown in FIGS. 3 and 4.
2a and a DE turning command from the output of the control device 12a,
Motorized motor that outputs each signal of boom turning command and running command
It has a live board 12b.
The input of the control unit 12a is an operation
Unloading amount target value Q from the data input terminal 13as, Operating
Traverse operation mode from bucket operation panel 13b, bucket
Bucket by pressure sensor attached to hydraulic drive motor 7
Oil pressure actual value signal PbfAttached to the tilt cylinder 6
Tilt sensor pressure signal PkfThere
You. The control device 12a controls the block shown in FIG.
The processing indicated by the arrow is performed. Here, shown in FIG.
As with the processing, the unloading target value QsTo the bucket hydraulic pressure
Converted by example calculation, this bucket oil pressure target value PbsAnd bake
Oil pressure actual value PbfAnd both of them are controlled by PI control.
Output a speed command that matches the driver.
In this embodiment, the pressure P by the tilt cylinder 6 is further increased.
kfIs input to the control device 12a. Now excavation force FdfChanges
When the excavation part 2 is increased by the
The pressure on the head side of the rotary cylinder 6 increases and the pressure on the rod side
Becomes smaller. Also, the excavating force FdfReverse if decreases
Phenomenon occurs. This head side pressure and rod side pressure
Excavation force FdfCan be converted
Cutting force FdfSudden change is detected by this pressure of the tilt cylinder 6.
Will be done. On the other hand, when excavating force is integrated, lifting force and
Since the lifting force and the bucket hydraulic pressure are almost equal,
The cutting force can be regarded as the differential of the bucket oil pressure,
G can be regarded as a change in hydraulic pressure. Therefore, dig
Adding proportional control of cutting force is differential control of bucket hydraulic pressure.
Will be added. Therefore, for example,
When the cutting force increases, the bucket
When the differential information is being added and the load becomes shallow again
Before the bucket oil pressure drops due to the decrease in excavation power,
We will add falling differential information. This result
As a result, tilt cylinder pressure PkfExcavation force F atdfGet this
Is obtained through the P control,
The main circuit of the feed speed command V responds quickly to changes in excavation force.
Differential information.
The blocks added in FIG.
The excavation force control unit X for controlling
Pressure PkfExcavation force F at block EdfSeeking and digging
Eliminates cutting force offset errors and allows rapid
High-pass filter to pass low-frequency components
F, this excavating force fluctuation component FdfhTo a strange goal
Therefore, the horizontal feed, which is the PI control output of the main circuit by the P control G,
To the command V. As a result, if the drilling power increases
A minus (slow) traverse speed command is issued, and the excavation force
If it goes down, it becomes a plus (faster) traverse speed command,
Corrects traverse speed command value by conventional bucket hydraulic control
I do. The traverse speed command value is sent to the operator.
Depending on the traversing operation mode set by
The motor is distributed to three speed command values, boom turning and running.
Command the drive panel 17. Motor drive board 17 is D
E-turn drive 9, boom-turn drive 10, traveling drive
The device 11 is driven.
FIG. 4 is a control flow based on the block of FIG.
It is a chart. That is, the unloading amount target value QsIs
Converted to bucket hydraulic pressure by lock A and Pbs= Kbs× Qs
At the point of addition BbsTo the actual value Pbf
And e = Pbs-PbfAnd After this, in block C
Perform PI calculation and V1Get. On the other hand, tilt cylinder pressure
Force PkfIs converted to excavating force at block E and Fdf= F
(Pkf), And then pass through a high-pass filter F to obtain Fdfl=
(A1+ ATwo) Fdf, Fdf h= Fdf-Fdfl, And P
V in control GTwoGet. At the addition point H, V1+ VTwo=
V for VTwoTraverse speed command V after correction
Thereafter, in block D, distribution of speed commands is performed, and each command is distributed.
Vd, Vb, V sGet.
[0014]
According to the quantitative unloading control of the present invention, the conventional oil
Excavation force control is added to pressure control, and
Improved responsiveness. In this way, the unloading amount is maintained at a predetermined value.
Chitzu. Large unloading amount, which has conventionally occurred due to collapse of cargo
Significant fluctuations can be reduced. to this
Operation due to unloading load and shortage of unloading
It has the beneficial effect of improving unloading capacity.
【図面の簡単な説明】
【図1】本発明の実施の形態の一例の全体構成図。
【図2】制御機器類、及び入力装置類のブロック構成
図。
【図3】制御ブロック図。
【図4】制御フローチャート。
【図5】連続式アンローダの全体構成図。
【図6】掘削部の軌道の説明図。
【図7】従来の制御ブロック図。
【符号の説明】
1 船倉
2 掘削部
3 バケット
4 チェーン
5 チェーン駆動方向
6 傾転シリンダ
7 バケット駆動油圧モータ
8 コンベア
9 DE旋回駆動装置
10 ブーム旋回駆動装置
11 走行駆動装置
12 制御機器類
12a 制御装置
12b モータドライブ盤
13 入力装置類
13a オペレータ入力端末
13b オペレータ運転操作盤
14 持上部15 支柱
A〜H ブロックBRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an overall configuration diagram of an example of an embodiment of the present invention. FIG. 2 is a block diagram of control devices and input devices. FIG. 3 is a control block diagram. FIG. 4 is a control flowchart. FIG. 5 is an overall configuration diagram of a continuous unloader. FIG. 6 is an explanatory diagram of a trajectory of a digging section. FIG. 7 is a conventional control block diagram. [Description of Signs] 1 Hold 2 Excavation part 3 Bucket 4 Chain 5 Chain drive direction 6 Tilt cylinder 7 Bucket drive hydraulic motor 8 Conveyor 9 DE turning drive 10 Boom turning drive 11 Traveling drive 12 Control equipment 12a Control device 12b Motor drive panel 13 Input devices 13a Operator input terminal 13b Operator operation panel 14 Upper support 15 Prop A to H blocks
───────────────────────────────────────────────────── フロントページの続き (72)発明者 仁保 博 広島県広島市西区観音新町四丁目6番22 号 三菱重工業株式会社 広島製作所内 (72)発明者 横山 智広 広島県広島市西区観音新町四丁目6番22 号 三菱重工業株式会社 広島製作所内 (72)発明者 清田 茂式 千葉県富津市新富20−1 新日本製鐵株 式会社 技術開発本部内 (72)発明者 宮崎 義彦 千葉県富津市新富20−1 新日本製鐵株 式会社 技術開発本部内 (56)参考文献 特開 平9−315586(JP,A) 特開 平8−119461(JP,A) (58)調査した分野(Int.Cl.7,DB名) B65G 67/60 B65G 65/06 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Hiroshi Nibo, Inventor Hiroshima Prefecture, Hiroshima 4-6-22 Kannon Shinmachi, Hiroshima Works, Mitsubishi Heavy Industries, Ltd. No. 6-22 Mitsubishi Heavy Industries, Ltd.Hiroshima Plant (72) Inventor Shigeru Kiyota 20-1 Shintomi, Futtsu City, Chiba Prefecture Nippon Steel Corporation Technology Development Division (72) Inventor Yoshihiko Miyazaki Shintomi, Futtsu City, Chiba Prefecture 20-1 Inside the Technology Development Division of Nippon Steel Corporation (56) References JP-A-9-315586 (JP, A) JP-A 8-119461 (JP, A) (58) Fields surveyed (Int. Cl. 7 , DB name) B65G 67/60 B65G 65/06
Claims (1)
れバケットが取り付けられたチェーンと、 持上部の前記支柱に対して前記掘削部を傾斜可変に支え
る傾転シリンダと、 前記バケット駆動油圧モータに取り付けた圧力センサと
を備え、 荷揚げ量目標値から換算されたバケット油圧目標値と前
記圧力センサによるバケット油圧実績値とを比較してそ
の差分から横送り速度指令値を求め、この横送り速度指
令値を、横行モード、DE旋回モード、走行モードのう
ち指令された横送り動作モードに応じて、ブーム旋回速
度指令値と走行速度指令値とDE旋回速度指令値の3つ
の速度指令値に分配し、この速度指令に基づき前記ブー
ム旋回駆動装置、前記走行駆動装置、前記DE旋回駆動
装置を駆動する連続式アンローダの荷揚げ量制御方法に
おいて、前記傾転シリンダに取り付けた圧力センサによる 傾転シ
リンダ圧力に基づく掘削力から掘削力変動分を求め、こ
の掘削力変動分を比例制御して前記横送り速度指令値を
補正することを特徴とする連続式アンローダの荷揚げ量
制御方法。(57) [Claims 1] A traveling drive device provided on a leg, a boom mounted on the leg, a boom turning drive device for turning the boom, and a boom turning drive device mounted on a tip of the boom. DE turning drive device, a strut turned by the DE turning drive device, a digging portion attached to the tip of the post, and a swinging motor between the digging portion and the bucket driving hydraulic motor.
The digging part is variably supported with respect to the chain to which the bucket is attached, and
A tilting cylinder, and a pressure sensor attached to the bucket drive hydraulic motor.
The provided, bucket hydraulic target value converted from unloading amount target value and the previous
Calculated lateral feed speed command value from the difference is compared with the bucket hydraulic actual value by serial pressure sensor, the traversing speed finger
Set the quotation value in the traversing mode, DE turning mode, and driving mode.
Boom rotation speed according to the commanded traverse operation mode
Command value, travel speed command value and DE turning speed command value
The speed command value, and based on the speed command,
System turning drive device, the traveling drive device, the DE turning drive
In the method for controlling the unloading amount of a continuous unloader that drives the apparatus, a digging force variation is obtained from a digging force based on a tilting cylinder pressure by a pressure sensor attached to the tilting cylinder, and the digging force variation is proportionally controlled. A method for controlling the unloading amount of a continuous unloader, wherein the lateral feed speed command value is corrected.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP29614896A JP3453261B2 (en) | 1996-11-08 | 1996-11-08 | Control method of unloading amount of continuous unloader |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP29614896A JP3453261B2 (en) | 1996-11-08 | 1996-11-08 | Control method of unloading amount of continuous unloader |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH10139173A JPH10139173A (en) | 1998-05-26 |
| JP3453261B2 true JP3453261B2 (en) | 2003-10-06 |
Family
ID=17829780
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP29614896A Expired - Fee Related JP3453261B2 (en) | 1996-11-08 | 1996-11-08 | Control method of unloading amount of continuous unloader |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3453261B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5936964B2 (en) * | 2012-09-10 | 2016-06-22 | 住友重機械搬送システム株式会社 | Continuous unloader |
| KR101766774B1 (en) * | 2012-08-10 | 2017-08-09 | 스미도모쥬기가이 한소시스템 가부시키가이샤 | Unloader |
-
1996
- 1996-11-08 JP JP29614896A patent/JP3453261B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH10139173A (en) | 1998-05-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US6609315B1 (en) | Automatic backhoe tool orientation control | |
| KR100231757B1 (en) | Method and device for controlling attachment of construction machine | |
| US6763619B2 (en) | Automatic loader bucket orientation control | |
| US7222444B2 (en) | Coordinated linkage system for a work vehicle | |
| JP3453261B2 (en) | Control method of unloading amount of continuous unloader | |
| JPH05163746A (en) | Oscillation suppressing device for working machine | |
| US3160284A (en) | Weight stabilizing load handling machine | |
| JP2922726B2 (en) | Excavator bucket guidance system | |
| JPH07137614A (en) | Horizontal installation system for work vehicle with outrigger | |
| KR200154544Y1 (en) | Heavy Equipment Loading Device of Trailer | |
| JP3091319B2 (en) | Lifting equipment | |
| JP3495477B2 (en) | Handling control method for continuous unloader | |
| JP3443747B2 (en) | Quantitative scraping method of continuous unloader | |
| JPH0565723A (en) | Operation controller | |
| JPH11199060A (en) | Control method of unloading amount of continuous unloader | |
| JPH04203032A (en) | Inclination angle control for construction machine | |
| JPS5847834A (en) | Keeper for uniform crawler landing pressure | |
| JPH0781898A (en) | High-place working vehicle | |
| JP2785795B2 (en) | Tilt control device for traveling vehicle | |
| JPH08119461A (en) | Cargo Handling Control Method for Continuous Unloader | |
| JPS6181395A (en) | Safety control device for aerial work vehicles | |
| JP2735068B2 (en) | Tilt control device for traveling vehicle | |
| JPH10250538A (en) | Jack cylinder control device for work vehicle with outrigger | |
| JP2785796B2 (en) | Tilt control device for traveling vehicle | |
| JPS6181398A (en) | Safety control device for self-propelled aerial work vehicles |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20030617 |
|
| LAPS | Cancellation because of no payment of annual fees |