JP3567277B2 - Operation planning method and operation planning system for self-propelled cargo transportation means - Google Patents
[go: Go Back, main page]

JP3567277B2 - Operation planning method and operation planning system for self-propelled cargo transportation means - Google Patents

Operation planning method and operation planning system for self-propelled cargo transportation means Download PDF

Info

Publication number
JP3567277B2
JP3567277B2 JP2000180108A JP2000180108A JP3567277B2 JP 3567277 B2 JP3567277 B2 JP 3567277B2 JP 2000180108 A JP2000180108 A JP 2000180108A JP 2000180108 A JP2000180108 A JP 2000180108A JP 3567277 B2 JP3567277 B2 JP 3567277B2
Authority
JP
Japan
Prior art keywords
self
propelled
cargo
combination
job
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2000180108A
Other languages
Japanese (ja)
Other versions
JP2001356819A (en
Inventor
滋 庵原
啓史 石井
信一 江渡
裕一 宮本
正人 林
克敏 日隈
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawasaki Motors Ltd
Original Assignee
Kawasaki Jukogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Jukogyo KK filed Critical Kawasaki Jukogyo KK
Priority to JP2000180108A priority Critical patent/JP3567277B2/en
Publication of JP2001356819A publication Critical patent/JP2001356819A/en
Application granted granted Critical
Publication of JP3567277B2 publication Critical patent/JP3567277B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Control Of Position, Course, Altitude, Or Attitude Of Moving Bodies (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

【0001】
【発明の属する技術分野】
本発明はトランスファクレーンなどの自走式貨物運搬手段の運用計画方法および運用計画システムに関する。さらに詳しくは、コンテナヤードなどの貨物集積場所における各作業指示に対する最適なトランスファクレーンなどの自走式貨物運搬手段の効率的な運用を図る自走式貨物運搬手段の運用計画方法および運用計画システムに関する。
【0002】
【従来の技術】
従来、港湾施設に設けられる大規模なコンテナターミナルにおいては、図12および図13に示すように、コンテナW´の保管場所であるヤードCY´に複数のレーンL1´〜L4´を設定し、各コンテナW´を例えば高さ5段、幅方向6個程度で各レーンL1´〜L4´に積分けて保管する方法が一般的である。
【0003】
各レーンL1´〜L4´は、コンテナの積込み・積出しを行うためにヤードCY´に配される各トランスファクレーン(以下、単にクレーンという)TC´がレーン替え可能なように、複数のブロックBL´に区切られる。このように、各レーンL1´〜L4´の間でクレーンを移動可能に構成することによって、クレーン台数の削減が可能となる。
【0004】
ところが、少数のクレーンTC´で作業を適正に処理するためには、各作業の実行位置やその処理の優先順位、または各クレーン相互の位置関係などの様々な条件を考慮して迅速に各クレーンへの作業割当ておよび移動経路を計画・指示する必要があるが、つまり迅速に最適な各クレーンの運用計画を図る必要があるが、従来、このような計画・指示は現場オペレータの経験的判断に依り行われている。
【0005】
この点に関連して、例えば特開平3−279124号公報、特開平8−272763号公報、特開平8−295408号公報、特開平9−12116号公報および特開平9−267918号公報にあるように、コンテナヤードにおける作業計画方法が種々提案されているが、クレーンを複数のレーンの間で移動経路を指定して移動させつつ作業を効率的に遂行させることが可能なクレーンの運用計画方法および運用計画システムは未だ実現されていない。
【0006】
【発明が解決しようとする課題】
本発明はかかる従来技術の課題に鑑みなされたものであって、複数のレーンからなるコンテナヤードなどの貨物集積場所における各トランスファクレーンなどの自走式貨物運搬手段の効率的な運用が図られる自走式貨物運搬手段の運用計画方法および運用計画システムを提供することを目的としている。
【0007】
【課題を解決するための手段】
本発明の自走式貨物運搬手段の運用計画方法は、複数ベイを有する複数の貨物ブロックからなるレーンを数備える貨物集積場所における複数の自走式貨物運搬手段の運用計画方法であって、
作業指示をその優先順位とともに取得する手順と、
自走式貨物運搬手段の現在位置情報およびその利用可能性に関する情報を取得する手順と、
前記作業指示に関する情報に基づいて、各貨物ブロックにおける必要自走式貨物運搬手段数を算出するジョブ数算出手順と、
前記ジョブ数算出手順により算出されたジョブ数のジョブの処理における自走式貨物運搬手段の貨物ブロックへの割当て、およびその割当てがなされた貨物ブロックへの同自走式貨物運搬手段の移動経路の算出を探索的推論処理によりなす手順
とを含み、
前記探索的推論処理においては、
(1)自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せリストが作成され、その組合せリストにおける自走式貨物運搬手段およびジョブの組合せは、自走式貨物運搬手段の数がジョブ数より少ない場合は、自走式貨物運搬手段の組合せは1通りとされる一方、ジョブの組合せはジョブ数より自走式貨物運搬手段の数だけのジョブを選んでなる組合せとされ、その逆にジョブ数が自走式貨物運搬手段の数より少ない場合は、ジョブの組合せは1通りとされる一方、自走式貨物運搬手段の組合せは全自走式貨物運搬手段からジョブ数だけの自走式貨物運搬手段を選んでなる組合せとされ、
(2)前記組合せリスト中の自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せの全てについて、個々のジョブへの自走式貨物運搬手段の割当が順次なされ、その順次割当てにおいて、(i)ジョブが存在する貨物ブロックに利用可能な自走式貨物運搬手段がある場合、その自走式貨物運搬手段にジョブが優先的に割当され、(ii)ジョブが存在するレーンに利用可能な自走式貨物運搬手段がある場合、その自走式貨物運搬手段にジョブが優先的に割当てされ、(iii)貨物集積場所が所定の基準にしたがって複数の領域に分割され、各領域毎に最初に処理されるべき作業指示が存在するベイにジョブ位置を設定する、ジョブ位置設定処理により設定されたジョブへ自走式貨物運搬手段が割当てされ、(iv)割当がなされた各自走式貨物運搬手段に対して移動経路が決定され、(v)自走式貨物運搬手段に割当てられたジョブおよび決定された移動経路が所定の制約条件に抵触していないか判定され、
(3)前記判定において制約条件に抵触するとされた自走式貨物運搬手段とジョブとの個別組合せを含む、自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せが前記組合せリストから棄却され、
(4)前記制約条件を満足する自走式貨物運搬手段とジョブとの個別組合せを含む、自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せのそれぞれについて、その組合せにおいて処理される各ジョブの優先順位に基づく優先度を、同組合せにおける全ジョブについて加算してなる優先度の総和を比較し、 (5)前記優先度の総和が最大となる自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せが前記組合せリストから選出され
前記選出された自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せをそれに対する推論結果とともに出力する
ことを特徴とする。
【0008】
本発明の自走式貨物運搬手段の運用計画方法においては、前記優先度の総和が等しい場合、自走式貨物運搬手段の移動時間の総和が比較され、移動時間の総和が最小のものが選出されるのが好ましい。この場合、前記移動時間の総和が等しい場合、自走式貨物運搬手段の移動距離の総和が比較され、移動距離の総和が最小のものが選出されるのが好ましい
【0009】
また、本発明の自走式貨物運搬手段の運用計画方法においては、4隅に位置する領域にある貨物ブロックに自走式貨物運搬手段を優先的に割り当てをなすのも好ましい。
【0010】
さらにまた、本発明の自走式貨物運搬手段の運用計画方法においては、前記制約条件が、自走式貨物運搬手段同士によるデッドロックが発生しないとするものであるのも好ましい。
【0011】
さらにまた、本発明の自走式貨物運搬手段の運用計画方法においては、前記制約条件が、自走式貨物運搬手段のレーン替え回数を制限するものであるのも好ましい。
【0013】
さらにまた、本発明の自走式貨物運搬手段の運用計画方法においては、第1優先順位の優先度が最大とされているのも好ましい。
【0014】
さらにまた、本発明の自走式貨物運搬手段の運用計画方法においては、積出しに関する作業指示の優先順位が第1順位とされているのも好ましい。
【0015】
さらにまた、本発明の自走式貨物運搬手段の運用計画方法においては、ランダム作業指示については、作業要求発生からの待ち時間に応じて優先順位が設定されるのも好ましい。
【0016】
一方、本発明の自走式貨物運搬手段の運用計画システムは、複数ベイを有する複数の貨物ブロックからなるレーンを数備える貨物集積場所における複数の自走式貨物運搬手段の運用計画システムであって、
作業指示をその優先順位とともに取得し、自走式貨物運搬手段の現在位置情報およびその利用可能性に関する情報を取得し、前記作業指示に関する情報に基づいて各貨物ブロックにおける必要自走式貨物運搬手段数を算出するジョブ数算出処理をし、自走式貨物運搬手段を必要とされる貨物ブロックへの割当ておよびその割当てがなされた貨物ブロックへの移動経路の算出を探索的推論処理するよう構成され、
前記探索的推論処理において、
(1)自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せリストが作成され、その組合せリストにおける自走式貨物運搬手段およびジョブの組合せは、自走式貨物運搬手段の数がジョブ数より少ない場合は、自走式貨物運搬手段の組合せは1通りとされる一方、ジョブの組合せはジョブ数より自走式貨物運搬手段の数だけのジョブを選んでなる組合せとされ、その逆にジョブ数が自走式貨物運搬手段の数より少ない場合は、ジョブの組合せは1通りとされる一方、自走式貨物運搬手段の組合せは全自走式貨物運搬手段からジョブ数だけの自走式貨物運搬手段を選んでなる組合せとされ、
(2)前記組合せリスト中の自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せの全てについて、個々のジョブへの自走式貨物運搬手段の割当が順次なされ、その順次割当てにおいて、(i)ジョブが存在する貨物ブロックに利用可能な自走式貨物運搬手段がある場合、その自走式貨物運搬手段にジョブが優先的に割当され、(ii)ジョブが存在するレーンに利用可能な自走式貨物運搬手段がある場合、その自走式貨物運搬手段にジョブが優先的に割当てされ、(iii)貨物集積場所が所定の基準にしたがって複数の領域に分割され、各領域毎に最初に処理されるべき作業指示が存在するベイにジョブ位置を設定する、ジョブ位置設定処理により設定されたジョブへ自走式貨物運搬手段が割当てされ、(iv)割当がなされた各自走式貨物運搬手段に対して移動経路が決定され、(v)自走式貨物運搬手段に割当てられたジョブおよび決定された移動経路が所定の制約条件に抵触していないか判定され、
(3)前記判定において制約条件に抵触するとされた自走式貨物運搬手段とジョブとの個別組合せを含む、自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せが前記組合せリストから棄却され、
(4)前記制約条件を満足する自走式貨物運搬手段とジョブとの個別組合せを含む、自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せのそれぞれについて、その組合せにおいて処理される各ジョブの優先順位に基づく優先度を、同組合せにおける全ジョブについて加算してなる優先度の総和を比較し、 (5)前記優先度の総和が最大となる自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せが前記組合せリストから選出され
前記選出された自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せをそれに対する推論結果とともに出力する
ことを特徴とする。
【0017】
本発明の自走式貨物運搬手段の運用計画システムは、具体的には、上位システムから作業指示および自走式貨物運搬手段に関する情報を読込む作業指示・自走式貨物運搬手段情報読込手段と、前記作業指示・自走式貨物運搬手段情報読込手段により読込まれた作業指示および自走式貨物運搬手段に関する情報に基づいて各貨物ブロックにおける必要自走式貨物運搬手段の数を算出してジョブ数を算出する各貨物ブロック必要自走式貨物運搬手段数算出手段と、前記各貨物ブロック必要自走式貨物運搬手段数算出手段により算出された各自走式貨物運搬手段の移動先および移動経路を探索的推論により算出する移動先・移動経路算出手段と、前記移動先・移動経路算出手段により算出された移動先および移動経路を評価して最適な移動先および移動経路を選択する移動先・移動経路評価手段と、前記移動先・移動経路評価手段により選択された移動先および移動経路を出力する移動先・移動経路指示手段とを備えてなることを特徴とする。
【0018】
本発明の自走式貨物運搬手段の運用計画システムにおいては、前記優先度の総和が等しい場合、自走式貨物運搬手段の移動時間の総和が比較され、移動時間の総和が最小のものが選出されるのが好ましく、前記移動時間の総和が等しい場合、自走式貨物運搬手段の移動距離の総和が比較され、移動距離の総和が最小のものが選出されるのが好ましい
【0019】
また、本発明の自走式貨物運搬手段の運用計画システムにおいては、4隅に位置する領域にある貨物ブロックに自走式貨物運搬手段を優先的に割り当てをなすのも好ましい。
【0020】
さらにまた、本発明の自走式貨物運搬手段の運用計画システムにおいては、前記制約条件が、自走式貨物運搬手段同士によるデッドロックが発生しないとするものであるのも好ましい。
【0021】
さらにまた、本発明の自走式貨物運搬手段の運用計画システムにおいては、前記制約条件が、自走式貨物運搬手段のレーン替え回数を制限するものであるのも好ましい。
【0023】
さらにまた、本発明の自走式貨物運搬手段の運用計画システムにおいては、第1優先順位の優先度が最大とされているのも好ましい。
【0024】
さらにまた、本発明の自走式貨物運搬手段の運用計画システムにおいては、積出しに関する作業指示の優先順位が第1順位とされているのも好ましい。
【0025】
さらにまた、本発明の自走式貨物運搬手段の運用計画システムにおいては、ランダム作業指示については、作業要求発生からの待ち時間に応じて優先順位が設定されるのも好ましい。
【0026】
ここで、自走式貨物運搬手段は、例えばトランファクレーンとされ、貨物集積場所は、例えばコンテナヤードとされる。
【0027】
【作用】
本発明は前記のごとく構成されているので、貨物集積場所における自走式貨物運搬手段の効率的な運用計画が迅速になし得る。
【0028】
【発明の実施形態】
以下、添付図面を参照しながら本発明を実施形態に基づいて説明するが、本発明はかかる実施形態のみに限定されるものではない。
【0029】
図1に本発明の一実施形態に係るトランスファクレーン配置計画システムの概略構成を示し、本システムTは、上位システムSTからの作業指示に対応して、複数のレーンL1,L2,…から構成されるコンテナヤードCYに配される各トランスファクレーン(以下、単にクレーンという)TCの効率的な配置および移動経路を指示するものとされる。つまり、クレーンTCの効率的な運用計画を図るものとされる。
【0030】
すなわち、コンテナ船の着岸や外来シャーシとの間のコンテナWの受け渡し、またはヤードCY内におけるコンテナシフト作業実行の際に発生するコンテナWの移動・積付けの作業要求は上位システムSTにより管理されており、この上位システムSTから本システムTに対して、各作業要求に応じるための具体的な作業内容および各クレーンTCの現在位置および稼働状況に関する情報が通知される。
【0031】
本システムTは、図2に示すように、上位システムSTからの作業指示およびクレーン情報を読込む作業指示・クレーン情報読込手段1と、前記作業指示・クレーン情報読込手段1により読込まれた作業指示およびクレーン情報に基づいて各ブロックBLにおける必要クレーン数を算出する各ブロック必要クレーン数算出手段2と、前記各ブロック必要クレーン数算出手段2により算出された必要数の各クレーンTCの移動先および移動経路Yを推論により算出する移動先・移動経路算出手段3と、前記移動先・移動経路算出手段3により算出された移動先および移動経路Yを評価して最適な移動先および移動経路Yを選択する移動先・移動経路評価手段4と、前記移動先・経路評価手段4により選択された移動先および移動経路Yを各クレーンTCに指示する移動先・移動経路指示手段5とを備えてなるものとされ、上位システムSTから通知される作業内容およびクレーン情報に応じて、効率的に各作業指示(以下、1つのコンテナに対応する作業を作業指示と称する)を実行できるように、各クレーンTCの配置および移動経路Yを推論により計画し、無線基地局NSを介して、移動先のベイBYの位置および移動経路Yの指示を送信する。この指示にしたがって、各クレーンTCは自動操縦により、または図示しない車載モニタの表示にしたがうオペレータの操縦により、移動先ベイBYまで移動する。
【0032】
なお、かかる各手段1,2,3,4を有するシステムTは、例えばコンピュータに前記機能に対応させたプログラムを格納することにより実現される。
【0033】
以下、本システムTが各クレーンTCの移動先および移動経路を計画する処理を具体的に説明する。
【0034】
図3に本システムが実行する処理全体の流れを示す。
【0035】
先ず、ステップS1では、上位システムSTから通知される各種情報の読込み(サイクリック)が行われる。
【0036】
すなわち、各作業指示の位置を表すブロック番号およびベイ番号が読込まれるとともに、各ベイBYに含まれる作業指示の数および各作業指示の優先順位Pが読込まれる。
【0037】
表1に各作業指示に付される優先順位Pの一例を示す。
【0038】
【表1】

Figure 0003567277
【0039】
この表1の例では本船作業に最優先作業として第1優先順位が付され、本船作業以外の作業はランダム作業と称して、作業要求発生からの待ち時間に応じた優先順位、すなわち待ち時間1時間以上のものに対して第2優先順位が、30分以上1時間未満のものに対して第3優先順位が、30分未満のものに対して第4優先順位がそれぞれ付されている。
【0040】
また、各作業指示にはそれぞれの優先順位に応じた優先度PDが設定される。すなわち、第1優先順位の作業指示の優先度PDは値α1とされ、第2優先順位の作業の優先度PDは値α2とされ、第3優先順位の作業の優先度PDは値α3とされ、第4優先順位の作業の優先度PDは値α4とされる。この優先度にはα1>α2>α3>α4の関係がある。この優先度PDは、後で説明する移動先・移動経路推論処理を実行する際に用いられる。
【0041】
ステップS2では、各ブロックBL毎の作業指示数に基づいて各ブロックBLに配置されるべきクレーンTCの台数が算出される。この各ブロック必要クレーン数算出の処理については後で詳細に説明する。
【0042】
ステップS3では、各クレーンTCの移動先および移動経路を探索的推論する移動先・移動経路推論処理を実行する。この移動先・移動経路推論処理については後で詳細に説明する。
【0043】
ステップS4では、移動先・移動経路推論処理により推論された各クレーンTCの移動先ベイBYの位置および移動経路の指示を送信する処理が行われる。
【0044】
次に、図4を参照して、前記ステップS2の各ブロック必要クレーン数算出処理を説明する。
【0045】
先ず、ステップS11では、ヤードCY内の全作業指示数を考慮して各ブロックBLに配すべきクレーンTCの台数(以下、ジョブ数という)を算出する各ブロックジョブ数算出処理を実行する。ここで、ジョブJ(図5参照)とは、1台のクレーンTCが取扱うべき作業指示の集合をいう。この各ブロックジョブ数算出処理については後で詳細に説明する。なお、図5中、黒塗りされたマスが1つの作業指示を示す。
【0046】
ステップS12では、各ジョブJに含まれる作業指示数および各ジョブJの具体的配置を考慮して各ジョブJを統合する処理が行われる。
【0047】
すなわち、原則として、あるブロックBL内の各ジョブJに含まれる作業指示数が1台のクレーンTCにより単位時間中に処理可能な数以内であれば、それらのジョブJは1つのジョブに統合される。しかしながら、図5(a)に示すように、統合可能な作業指示数の各ジョブJ1,J2に含まれる作業指示が分散している場合は、それらのジョブJ1,J2は各々独立したジョブJとして維持される。ここで、単位時間とは、本システムをサイクリックに起動する時間間隔をいい、本実施形態では5分とされている。
【0048】
また、図5(b)に示すように、2つのジョブJ3,J4に含まれる作業指示が一箇所に集中している場合は、ジョブJ3,J4に含まれる作業指示数が1台のクレーンTCにより単位時間中に処理可能な数を超えるときにもそれらのジョブJ3,J4は1つのジョブJ5とされる。なお、1台のクレーンTCの単位時間中における処理限界を超える作業指示の処理は、次の単位時間(次の計算タイミング)に持ち越されて処理される。そのため、1台のクレーンTCの単位時間における処理限界を超えてジョブを統合しても問題は生じない。
【0049】
ステップS13では、各ジョブJの位置が設定される。ここで、各ジョブJの位置は各ジョブJ内で最初に処理されるべき作業指示(以下、先頭作業指示という)が存在するベイBYの位置とされる。
【0050】
ステップS14では、各ジョブJの優先度PDが設定される。ここで、各ジョブJの優先度PDは当該ジョブJ内の最高の優先度PDを有する作業指示と同等とされる。
【0051】
ステップS15では、各ジョブJに含まれる作業指示の数が算出される。
【0052】
ステップS16では、ヤードCY内の全ジョブJについて、位置、優先度PDおよび作業指示数が出力される。
【0053】
次に、図6を参照して、前記ステップS11の各ブロックジョブ数算出処理を説明する。
【0054】
先ず、ステップS21では、下記式(1)により、ヤードCY内の各優先順位P毎の作業指示総数JYTtL(P)が算出される。
【0055】
【数1】
Figure 0003567277
【0056】
ここで、BL:ブロック番号、BY:当該ブロックBL内のベイ番号、P:優先順位、M:ヤードCY内のブロック数、N:当該ブロックBL内のベイ数、J(BL,BY,P):あるブロックBL内のあるベイBYに含まれる優先順位Pの作業指示数である。
【0057】
ステップS22では、下記式(2)により、各レーンLに割当てるクレーン台数TCNL(L)が算出される。
【0058】
【数2】
Figure 0003567277
【0059】
ここで、β1:第1優先順位の作業指示に設定される重み付係数、β2:第2優先順位の作業指示に設定される重み付係数、β3:第3優先順位の作業指示に設定される重み付係数、β4:第4優先順位の作業指示に設定される重み付係数であり、これらの係数にはβ1>β2>β3>β4の関係がある。
【0060】
【数3】
Figure 0003567277
【0061】
ステップS23では、下記式(3)により、当該レーンL内の各ブロックBL毎にクレーンTCの必要性の度合いを示す必要度NTC(BL)が算出される。
【0062】
【数4】
Figure 0003567277
【0063】
ステップS24では、下記式(4)により、作業指示が存在する各ブロックBLに対してまず1台のクレーンTCが割当てられる。
【0064】
【数5】
Figure 0003567277
【0065】
ここで、TCNB(BL):各ブロックBLに割当てられるクレーン数である。
【0066】
ステップS25では、下記式(5)により、ステップS24で各ブロックBLに割当てられたクレーンTCの総数dTCNL(LN)が求められる。
【0067】
【数6】
Figure 0003567277
【0068】
ここで、dTCNL(L):レーンL内の各ブロックBLに割当てられたクレーンTC台数の総和である。
【0069】
ステップS26では、dTCNL(L)値がTCNL(L)値以上であるか否かが判定される。dTCNL(L)値がTCNL(L)値以上であれば、ステップS27に進み、その時点で各ブロックBLに割当てられているクレーン台数を前記ジョブ数として出力し、本処理を終了する。
【0070】
dTCNL(L)値がTCNL(L)値未満であればステップS28に進む。ステップS28では、下記式(6)により、レーンL内の各ブロックBLについてクレーンTC1台あたりの必要度R(BL)を算出し、R(BL)値が高いブロックBLにクレーンを1台追加的に割当てた後、ステップS26に戻る。
【0071】
【数7】
Figure 0003567277
【0072】
次に、図7を参照して、前記ステップS3の移動先・移動経路推論処理を説明する。
【0073】
先ず、ステップS31では、クレーンTCの組合わせのリストとジョブJの組合わせのリストとが作成される。
【0074】
例えば、現在3個のジョブJ1,J2,J3があり、これに対して2台のクレーンTC1,TC2が利用可能であれば、2個のジョブだけが現在処理可能である。この場合は、クレーンTCの組合わせは(TC1,TC2)の1通りだけであり、ジョブJの組合わせは3個の中から2個を選び出す各組合わせ、すなわち(J1,J2)、(J2,J3)および(J3,J1)の3通りとされる。
【0075】
このように、現在実行すべきジョブ数(例えばq個とする)が利用可能なクレーン数(例えばr個とする)よりも多い場合(q>r)は、クレーン組合わせは1通りとされ、ジョブ組合わせはq個の中からr個を選び出す組合わせの数(qr)とされる。
【0076】
逆に、実行すべきジョブ数qよりも利用可能なクレーン数rが多い場合(q<r)は、ジョブ組合わせの数は1通り(J1,J2,…,Jq)とされ、これに対して、クレーン組合わせの数はr個の中からq個を選び出す組合わせの数とされる。
【0077】
以下に説明する処理(ステップS32〜ステップS37の処理)は、このジョブ組合わせまたはクレーン組合わせの全てについて順次行われるものである。
【0078】
すなわち、ステップS32では、ジョブJが存在するブロックBLに利用可能なクレーンTCがある場合、先ずそのクレーンTCが当該ジョブJに割当てられる。これは、効率の良いジョブJとクレーンTCとの対応付を先に確定することによって、推論に要する時間を短縮する趣旨である。
【0079】
ステップS33では、ジョブJが存在するレーンLに利用可能なクレーンTCがある場合、そのクレーンTCが当該ジョブJに割当てられる。これも前記ステップS32と同様の趣旨である。
【0080】
ステップS34では、ヤードCYの対称性を利用して、通行妨害などの可能性によりヤードCYが各処理領域ARに分割される。
【0081】
すなわち、図8に示すように、ヤードCYがレーン(A)、レーン(B)、…、レーン(I)の9レーンから構成され、各レーンLが3個のブロックBLから構成されている場合、ヤードCYの四隅にある(A1),(A3),(I1),(I3)の各ブロックBLを第1処理領域AR1とする。第1処理領域AR1の各ブロックに隣接する各ブロック(A2),(B1),(B3),(H1),(H3),(I2)を第2処理領域AR2とし、これに隣接する各ブロック(B2),(C1),(C3),(G1),(G3),(H2)を第3処理領域AR3とする。第3処理領域AR3よりもヤードCY中央側にある各ブロック(C2),(D1),(D2),(D3),(E1),(E2),(E3),(F1),(F2),(F3),(G2)は第4処理領域とされる。
【0082】
ステップS35では、第1処理領域AR1から第4処理領域AR4まで順次各領域内のジョブJにクレーンTCを所定の方法で割当てる領域別クレーン割当・移動経路決定処理が実行される。この方法については後で説明する。
【0083】
このように、ヤードCYを複数の処理領域ARに分割し、各領域AR毎にジョブJへのクレーンTCの割当を行うようにすることによって、推論に要する時間を大幅に短縮することができる。
【0084】
また、ヤードCYの周辺にある領域から先に所定の方法で各クレーンTCを割当てるようにすることによって、各クレーンTCを移動させる際の干渉を起こり難くすることが可能となる。
【0085】
ステップS36では、ステップS32〜ステップS35の処理による割当・移動経路決定の結果が、所定の制約条件に抵触していないかが判定される。
【0086】
この制約条件とは、効率の悪いクレーンTCの移動態様を排除し、各クレーンTCの移動中の干渉を排除し、より優先順位の高いジョブJが処理されずに放置される事態を回避するなどの趣旨のもとに設定される条件である。
【0087】
具体的には、(1)各クレーンTCのレーン替えはk回までと制限され、(2)優先順位の高いジョブJの処理が優先され、(3)デッドロックが発生する各クレーンの配置が禁止され、(4)あるクレーンTCが同じブロックBLに存在するジョブJを処理せずに他のブロックBLに移動し、残されたジョブJを他のクレーンTCが移動して処理する状態を回避するなどのクレーンTCの2台移動は少なくする、などの各条件が設定される。
【0088】
この制約条件に抵触する推論結果は廃棄され、制約条件に抵触しないジョブ組合わせまたはクレーン組合わせについて、ステップS37において、下記の基準で推論結果の評価および保存が行われる。
【0089】
すなわち、先ず第1に、当該組合わせにより処理される各ジョブJの優先度PD(表1参照)の総和が比較され、この総和が最大の組合わせが選出される。
【0090】
優先度PDの総和が等しい場合は、第2に、クレーンTCの移動時間の総和が比較され、最小の組合わせが選出される。移動時間の総和が等しい場合は、第3に、クレーンTCの移動距離の総和が比較され、最短の組合わせが選出される。
【0091】
ステップS38では、全ての組合わせについて推論が行われたか否かが判定され、推論未了の組合わせがあれば、それらの組合わせについてステップS32〜ステップS37の処理が実行される。
【0092】
全ての組合わせについて推論が行われていれば、最良の評価結果を得た組合わせに対する推論結果が、最終的な各クレーンTC移動先・移動経路の推論結果として出力される。
【0093】
次に、図9を参照して、前記ステップS35の領域別クレーン割当・移動経路決定処理を説明する。
【0094】
先ず、ステップS41では、推論対象となる処理領域ARの領域番号iが値1に設定される。
【0095】
ステップS42では、処理領域(i)、すなわち最初は第1処理領域AR1内で当該組合わせに含まれるジョブJが検索される。
【0096】
ステップS43では、検索された各ジョブJに移動時間が最小となるクレーンTCが最短の経路で割当てられる。
【0097】
ステップS44では、この結果により前記制約条件の抵触が発生するか否かが判定される。抵触する場合は、前記ステップS36の処理により廃棄される組合わせとして、処理を打切る。
【0098】
抵触しない場合は、ステップS45において、全ての処理領域AR、すなわち第1処理領域AR1から第4処理領域AR4についてクレーンTCの割当が行われたか否かを判定する。全ての処理領域ARについて割当が行われた場合は処理を終了する一方、割当未了の処理領域ARがあれば、ステップS46において、領域番号iを値1増加させた後、ステップS42の処理に戻る。
【0099】
【実施例】
以下、具体例を用いて各処理を説明する。
【0100】
図10に、ヤードCY全体で18個の処理すべきジョブJ1〜J18があり、これを12台のクレーンTC1〜TC12で処理すべき場合を示す。なお、ヤードCYは図8のものと同一とする。また、各ブロックBL中のジョブJを表している四角中の符号は優先順位を示している。例えば、四角中の符号Sは第1優先順位の本船作業を表し、符号3は第4優先順位のランダム作業(待時間:30分未満)を表す。
【0101】
先ず、前記ステップS31の処理によって、ジョブ組合わせリストおよびクレーン組合わせリストが作成される。本具体例ではジョブ数が18であり、クレーン数が12であるから、クレーン組合わせは1通りとされる一方、ジョブ組合わせは18個の中から12個を選び出す組合わせの数、すなわち18564通りとされる。
【0102】
この全てのジョブ組合わせについて、前記ステップS32〜ステップS37の処理が行われるが、以下の説明では最終的に採用されるジョブ組合わせ(J1,J2,J3,J4,J5,J7,J8,J10,J11,J13,J15,J16)について、図10を参照しながら、各ジョブJへのクレーンTCの割当ておよび移動経路を決定する手順を示す。
【0103】
(手順1)先ず、ステップS32の処理によって、同一ブロックBLに存在するジョブJへのクレーンTCの割当が行われる。
【0104】
すなわち、第5ジョブJ5に第1クレーンTC1が割当てられ、第7ジョブJ7に第10クレーンTC10が割当てられ、第3ジョブJ3に第9クレーンTC9が割当てられ、第7ジョブJ7に第10クレーンTC10が割当てられ、第13ジョブJ13に第12クレーンTC12が割当てられ、第15ジョブJ15に第11クレーンTC11が割当てられる。
【0105】
(手順2)ステップS33の処理によって、手順1で割当てられたクレーン以外のクレーンTCが同一レーンLに存在するジョブJに割当てられる。本具体例では、この手順2で割当て対象となるジョブJは存在しない。
【0106】
(手順3)ステップS35の処理によって、各処理領域AR1〜AR4毎に、順次各ジョブJへのクレーンTCの割当が行われる。以下、各領域毎に説明する。(手順3.1)第1処理領域AR1に属する各ブロック(A1),(A3),(I1),(I3)内の各ジョブJへのクレーンTCの割当が行われる。
【0107】
(手順3.1.1)すなわち、ブロック(A1)にある第1ジョブJ1に未割当のクレーンの中で最も近い第3クレーンTC3が割当てられる。この移動経路は矢印Y1で示される。
【0108】
(手順3.1.2)また、ブロック(A3)にある第3ジョブJ3に未割当のクレーンTCの中で最も近い第2クレーンTC2が割当てられる。この移動経路は矢印Y2で示される。
【0109】
(手順3.2)次に、第2処理領域AR2に属する各ブロック(A2),(B1),(B3),(H1),(H3),(I2)内の各ジョブJへのクレーンTCの割当が行われる。
【0110】
(手順3.2.1)すなわち、ブロック(B1)にある第4ジョブJ4に未割当のクレーンの中で最も近い第5クレーンTC5が割当てられる。この移動経路は矢印Y3で示される。
【0111】
(手順3.2.2)ブロック(A2)にある第2ジョブJ2に未割当のクレーンの中で最も近い第4クレーンTC4が割当てられる。この移動経路は矢印Y4で示される。
【0112】
(手順3.2.3)ブロック(H1)にある第16ジョブJ16に未割当のクレーンTCの中で最も近い第6クレーンTC6が割当てられる。この移動経路は矢印Y5で示される。
【0113】
(手順3.3)次に、第3処理領域AR3に属する各ブロック(B2),(C1),(C3),(G1),(G3),(H2)内の各ジョブJへのクレーンTCの割当が行われる。
【0114】
(手順3.3.1)すなわち、ブロック(G1)にある第11ジョブJ11に対して未割当のクレーンTCの中で最も近い第7クレーンTC7が割当てられる。この移動経路は矢印Y6で示される。
【0115】
(手順3.4)次に、第4処理領域AR4に属する各ブロック(C2),(D1),(D2),(D3),(E1),(E2),(E3),(F1),(F2),(F3),(G2)内の各ジョブJへのクレーンTCの割当が行われる。
【0116】
(手順3.4.1)すなわち、ブロック(F2)にある第8ジョブJ8に対して未割当のクレーンTCの中で最も近い第8クレーンTC8が割当てられる。この移動経路は矢印Y8で示される。
【0117】
このように、本実施形態のシステムTは、上位システムSTからの各作業指示から作業単位である各ジョブJを作成し、経験則を用いて各類型毎に段階的に各ジョブJに対する各クレーンTCの割当および移動経路を探索的推論して算出するようにしているので、比較的短時間の内に各クレーンTCのヤードCYにおける配置および移動計画を作成することができる。つまり、迅速に各クレーンの運用計画を作成できる。
【0118】
以上、本発明を実施形態および実施例に基づいて説明してきたが、本発明はかかる実施形態のみに限定されるものではなく、種々改変が可能である。例えば、実施形態および実施例においては、自走式貨物運搬手段としてトランスファクレーンが用いられているが、自走式貨物運搬手段はトランスファクレーンに限定されるものではなく、各種の自走式貨物運搬手段を用いることができる。また、貨物集積場所はコンテナヤードとされているが、各種の貨物集積場所とすることができる。
【0119】
【発明の効果】
以上詳述したように、本発明においては、所要数の貨物ブロックからなるレーンを有する貨物集積場所における自走式貨物運搬手段の運用計画を所定の制約条件の下で探索的推論によりなし、その探索的推論により得られた自走式貨物運搬手段の運用計画の中から最も効率的な運用計画を選択するようにしているので、貨物集積場所における各自走式貨物運搬手段の効率的な運用がなし得るという優れた効果が得られる。
【図面の簡単な説明】
【図1】本発明の一実施形態に係るトランスファクレーン配置計画システムの概略構成を示す模式図である。
【図2】本システムの機能ブロック図である。
【図3】本システムによる処理の概略の流れを示すフローチャートである。
【図4】各ブロック必要クレーン数算出処理の流れを示すフローチャートである。
【図5】ジョブ作成手順の一例を示す模式図である。
【図6】各ブロックジョブ数算出処理の流れを示すフローチャートである。
【図7】移動先・移動経路推論処理の流れを示すフローチャートである。
【図8】ヤード内における各処理領域の配置を示す模式図である。
【図9】領域別クレーン割当・移動経路決定処理の流れを示すフローチャートである。
【図10】本システムによるクレーン配置の具体例を説明するための模式図であり、配置前の状態を示す。
【図11】本システムによるクレーン配置の具体例を説明するための模式図であり、配置後の状態を示す。
【図12】従来のコンテナヤードにおけるコンテナの保管態様およびトランスファクレーンの配置を示す模式図である。
【図13】従来のコンテナヤードにおけるコンテナの保管態様およびトランスファクレーンの配置を示す模式図である。
【符号の説明】
1 作業指示・クレーン情報読込手段
2 各ブロック必要クレーン数算出手段
3 移動先・移動経路算出手段
4 移動先・移動経路評価手段
5 移動先・移動経路指示手段
BL ブロック
CY ヤード
J ジョブ(作業単位)
L レーン
ST 上位システム
T 本システム
TC トランスファクレーン
W コンテナ
Y 移動経路[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to an operation planning method and an operation planning system for a self-propelled cargo transportation means such as a transfer crane. More specifically, the present invention relates to an operation planning method and an operation planning system for a self-propelled cargo transportation means for efficiently operating a self-propelled cargo transportation means such as a transfer crane that is optimal for each work instruction at a cargo accumulation place such as a container yard. .
[0002]
[Prior art]
Conventionally, in a large-scale container terminal provided in a port facility, as shown in FIGS. 12 and 13, a plurality of lanes L are located in a yard CY ′ where a container W ′ is stored.1'~ LFourIs set, and each container W 'is, for example, 5 rows high and about 6 lanes L in the width direction.1'~ LFourThe method of integrating and storing the values is generally used.
[0003]
Each lane L1'~ LFour′ Are divided into a plurality of blocks BL ′ so that each transfer crane (hereinafter simply referred to as a crane) TC ′ arranged in the yard CY ′ for loading / unloading containers can change lanes. Thus, each lane L1'~ LFourBy configuring the cranes to be movable between ′, the number of cranes can be reduced.
[0004]
However, in order to properly process the work with a small number of cranes TC ', each crane is quickly taken into consideration in consideration of various conditions such as the execution position of each work, the priority of the processing, or the positional relationship between the cranes. It is necessary to plan and instruct the work assignment and the movement route to each crane, that is, to quickly and optimally plan the operation of each crane. It is performed.
[0005]
Regarding this point, for example, Japanese Patent Application Laid-Open Nos. Hei 3-279124, Hei 8-272563, Hei 8-295408, Hei 9-12116 and Hei 9-267918 are disclosed. There have been proposed various work planning methods in a container yard, and a crane operation planning method capable of efficiently performing a work while moving a crane by designating a moving route between a plurality of lanes and The operation planning system has not been realized yet.
[0006]
[Problems to be solved by the invention]
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems of the related art, and has been developed to efficiently operate self-propelled cargo transportation means such as transfer cranes at a cargo accumulation place such as a container yard including a plurality of lanes. It is an object of the present invention to provide an operation planning method and an operation planning system for a traveling freight carrier.
[0007]
[Means for Solving the Problems]
The operation planning method of the self-propelled freight transportation means of the present invention,Multiple with multiple baysA lane of several cargo blocksDuplicateIn the cargo storage areapluralAn operation planning method for a self-propelled cargo transportation means,
A procedure for obtaining work instructions with their priorities;
A procedure for obtaining the current location information of the self-propelled cargo vehicle and information on its availability,
A job number calculation procedure for calculating the required number of self-propelled cargo transport means in each cargo block based on the information on the work instruction;
SaidAssignment of a self-propelled cargo transport means to a cargo block in the processing of a job with the number of jobs calculated by the job number calculation procedure, and calculation of a movement route of the self-propelled cargo transport means to the assigned cargo block ToExploratory reasoningProcedures performed by processing
And
In the exploratory inference process,
(1) A combination list including a combination of the self-propelled cargo conveyance means and a job combination is created, and the combination of the self-propelled cargo conveyance means and the job in the combination list indicates that the number of self-propelled cargo conveyance means If the number is less than the number, the combination of the self-propelled cargo conveyance means is one, and the combination of the jobs is a combination of the number of the self-propelled cargo conveyance means selected from the number of the jobs, and vice versa. If the number of jobs is less than the number of self-propelled freight vehicles, only one job combination is available. It is a combination that chooses a traveling cargo transportation means,
(2) For all combinations of the combination of the self-propelled cargo transport means and the job in the combination list, the assignment of the self-propelled cargo transport means to each job is sequentially performed. (I) If there is a self-propelled cargo carrier available in the cargo block where the job exists, the job is preferentially assigned to the self-propelled carrier, and (ii) it can be used in the lane where the job exists. If there is a suitable self-propelled freight carrier, the job is preferentially assigned to the self-propelled freight carrier, and (iii) the cargo accumulation location is divided into a plurality of areas according to a predetermined standard, and First, a self-propelled freight carrier is assigned to the job set by the job position setting process, in which a job position is set in a bay where a work instruction to be processed is present, and (iv) assignment is performed. Each self-propelled movement path relative expression freight unit is determined, it is determined whether (v) self-propelled jobs assigned to cargo transfer means and the determined moving path does not violate the prescribed constraints,
(3) A combination consisting of a combination of a self-propelled freight carrier and a job, including an individual combination of a self-propelled freight carrier and a job determined to violate the constraint in the determination, is rejected from the combination list. And
(4) Each combination including the combination of the self-propelled cargo conveyance means and the job, including the individual combination of the self-propelled cargo conveyance means and the job that satisfies the constraint, is processed in the combination. Compare the sum of priorities obtained by adding the priorities based on the priorities of each job for all jobs in the same combination,    (5) A combination consisting of a combination of a self-propelled cargo transporting means and a job combination having the maximum sum of the priorities is selected from the combination list.,
A combination consisting of the selected combination of the self-propelled cargo conveyance means and the combination of the job is output together with the inference result for the combination.
It is characterized by the following.
[0008]
In the operation planning method of the self-propelled cargo transportation means of the present invention,SaidpriorityIf the sum of the degrees is equal, the sum of the travel times of theComparisonAnd the one with the shortest total travel time is selected.Preferably. in this case,If the sum of the travel times is equal, the sum of the travel distances of the self-propelledComparisonIt is preferable to select the one with the smallest sum of the moving distance.
[0009]
Further, in the operation planning method of the self-propelled cargo transportation means of the present invention,Priority assignment of self-propelled cargo transportation means to cargo blocks located in the four corner areasIt is also preferred that
[0010]
Furthermore, in the operation planning method of the self-propelled cargo transportation means of the present invention,The constraint condition is that deadlock between self-propelled cargo transportation means does not occur.It is also preferred.
[0011]
Furthermore, in the operation planning method of the self-propelled cargo transportation means of the present invention,The constraint condition is to limit the number of lane changes of the self-propelled cargo transportation means.It is also preferable.
[0013]
Furthermore, in the operation planning method of the self-propelled cargo transportation means of the present invention,The first priority has the highest priorityIs also preferred.
[0014]
Furthermore, in the operation planning method of the self-propelled cargo transportation means of the present invention,The priority of the work instruction regarding shipping is the first priority.It is also preferred.
[0015]
Furthermore, in the operation planning method of the self-propelled cargo transportation means of the present invention,Priorities for random work instructions are set according to the waiting time from the occurrence of work requestsIt is also preferred that
[0016]
On the other hand, the operation planning system of the self-propelled cargo transportation means of the present invention is:Multiple with multiple baysA lane of several cargo blocksDuplicateIn the cargo storage areapluralAn operation planning system for self-propelled cargo transportation means,
Acquire the work instructions together with their priorities, acquire the current position information of the self-propelled cargo transportation means and information on its availability, and based on the information on the work instructions, the necessary self-propelled cargo transportation means in each cargo block The number of jobs for calculating the number is calculated, and the self-propelled cargo transport means is assigned to the required cargo block and the travel route to the assigned cargo block is calculated.Exploratory reasoningConfigured to process,
In the exploratory inference process,
(1) A combination list including a combination of the self-propelled cargo conveyance means and a job combination is created, and the combination of the self-propelled cargo conveyance means and the job in the combination list indicates that the number of self-propelled cargo conveyance means If the number is less than the number, the combination of the self-propelled cargo conveyance means is one, and the combination of the jobs is a combination of the number of the self-propelled cargo conveyance means selected from the number of the jobs, and vice versa. If the number of jobs is less than the number of self-propelled freight vehicles, only one job combination is available. It is a combination that chooses a traveling cargo transportation means,
(2) For all combinations of the combination of the self-propelled cargo transport means and the job in the combination list, the assignment of the self-propelled cargo transport means to each job is sequentially performed. (I) If there is a self-propelled cargo carrier available in the cargo block where the job exists, the job is preferentially assigned to the self-propelled carrier, and (ii) it can be used in the lane where the job exists. If there is a suitable self-propelled freight carrier, the job is preferentially assigned to the self-propelled freight carrier, and (iii) the cargo accumulation location is divided into a plurality of areas according to a predetermined standard, and First, a self-propelled freight carrier is assigned to the job set by the job position setting process, in which a job position is set in a bay where a work instruction to be processed is present, and (iv) assignment is performed. Each self-propelled movement path relative expression freight unit is determined, it is determined whether (v) self-propelled jobs assigned to cargo transfer means and the determined moving path does not violate the prescribed constraints,
(3) A combination consisting of a combination of a self-propelled freight carrier and a job, including an individual combination of a self-propelled freight carrier and a job determined to violate the constraint in the determination, is rejected from the combination list. And
(4) Each combination including the combination of the self-propelled cargo conveyance means and the job, including the individual combination of the self-propelled cargo conveyance means and the job that satisfies the constraint, is processed in the combination. Compare the sum of priorities obtained by adding the priorities based on the priorities of each job for all jobs in the same combination,    (5) A combination consisting of a combination of a self-propelled cargo transporting means and a job combination having the maximum sum of the priorities is selected from the combination list.,
A combination consisting of the selected combination of the self-propelled cargo conveyance means and the combination of the job is output together with the inference result for the combination.
It is characterized by the following.
[0017]
Specifically, the operation planning system for the self-propelled cargo transport means of the present invention includes a work instruction / self-propelled cargo transport means information reading means for reading a work instruction and information about the self-propelled cargo transport means from a higher system. Calculating the number of required self-propelled cargo transport means in each cargo block based on the work instructions read by the work instruction / self-propelled cargo transport means information reading means and information on the self-propelled cargo transport means.And calculate the number of jobsMeans for calculating the number of self-propelled cargo transport means required for each cargo block to be moved and the destination and route of movement of each self-propelled cargo transport means calculated by the means for calculating the number of self-propelled cargo transport means required for each cargo block Destination / movement route calculating means, and destination / moving route evaluation means for evaluating the destination and the moving route calculated by the destination / moving route calculating means and selecting the optimum destination and moving route. And a destination / moving route designating means for outputting the destination and the moving route selected by the destination / moving route evaluating means.
[0018]
In the operation planning system of the self-propelled cargo transportation means of the present invention,SaidpriorityIf the sum of the degrees is equal, the sum of the travel times of theComparisonIt is preferable that the sum of the travel times is the smallest, and if the sum of the travel times is equal, the sum of the travel distances of the self-propelled cargo transport means is selected.ComparisonIt is preferable to select the one with the smallest sum of the moving distance.
[0019]
Further, in the operation planning system of the self-propelled cargo transportation means of the present invention,Priority assignment of self-propelled cargo transportation means to cargo blocks located in the four corner areasIt is also preferred that
[0020]
Furthermore, in the operation planning system of the self-propelled cargo transportation means of the present invention,The constraint condition is that deadlock between self-propelled cargo transportation means does not occur.It is also preferable.
[0021]
Furthermore, in the operation planning system of the self-propelled cargo transportation means of the present invention,The constraint condition is to limit the number of lane changes of the self-propelled cargo transportation means.It is also preferable.
[0023]
Furthermore, in the operation planning system of the self-propelled cargo transportation means of the present invention,The first priority has the highest priorityIs also preferred.
[0024]
Furthermore, in the operation planning system of the self-propelled cargo transportation means of the present invention,The priority of the work instruction regarding shipping is the first priority.It is also preferable.
[0025]
Furthermore, in the operation planning system of the self-propelled cargo transportation means of the present invention,Priorities for random work instructions are set according to the waiting time from the occurrence of work requestsIt is also preferred that
[0026]
Here, the self-propelled cargo transportation means is, for example, a transfer crane, and the cargo accumulation location is, for example, a container yard.
[0027]
[Action]
Since the present invention is configured as described above, an efficient operation plan of the self-propelled cargo transportation means at the cargo accumulation location can be quickly made.
[0028]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described based on embodiments with reference to the accompanying drawings, but the present invention is not limited to only such embodiments.
[0029]
FIG. 1 shows a schematic configuration of a transfer crane arrangement planning system according to an embodiment of the present invention. The system T includes a plurality of lanes L in response to a work instruction from a host system ST.1, LTwo,..., The transfer cranes (hereinafter, simply referred to as cranes) TC arranged in the container yard CY are to be efficiently arranged and moved. That is, an efficient operation plan of the crane TC is intended.
[0030]
In other words, the work request for moving / stacking the container W which occurs when the container W is transferred to / from the shore of the container ship or transferred to the foreign chassis or the container shift operation is performed in the yard CY is managed by the upper system ST. The upper system ST notifies the system T of specific work contents for responding to each work request and information on the current position and the operation status of each crane TC.
[0031]
As shown in FIG. 2, the present system T includes a work instruction / crane information reading means 1 for reading a work instruction and crane information from the host system ST, and a work instruction read by the work instruction / crane information reading means 1. Means for calculating the number of required cranes in each block BL based on the information on the number of cranes in each block BL, based on the crane information, and the destination and movement of the required number of cranes TC calculated by the required number of cranes in each block BL A destination / movement route calculating means 3 for calculating the route Y by inference, and a destination and a moving route Y calculated by the destination / movement route calculating means 3 are evaluated to select an optimum destination and a moving route Y. Destination and travel route evaluation means 4 and the destination and travel route Y selected by the destination and route evaluation means 4 And a moving destination / moving route instructing means 5 for instructing each of the work instructions (hereinafter referred to as one container) according to the work content and the crane information notified from the upper system ST. The work corresponding to is called a work instruction), the arrangement of each crane TC and the movement route Y are planned by inference, and the position of the movement destination bay BY and the movement route Y are set via the radio base station NS. Send instructions. In accordance with this instruction, each crane TC moves to the destination bay BY by automatic operation or by an operator's operation according to the display on the in-vehicle monitor (not shown).
[0032]
The system T having the units 1, 2, 3, and 4 is realized by, for example, storing a program corresponding to the function in a computer.
[0033]
Hereinafter, a process in which the present system T plans a destination and a movement route of each crane TC will be specifically described.
[0034]
FIG. 3 shows a flow of the entire processing executed by the present system.
[0035]
First, in step S1, reading (cyclic) of various information notified from the upper system ST is performed.
[0036]
That is, the block number and the bay number indicating the position of each work instruction are read, and the number of work instructions included in each bay BY and the priority order P of each work instruction are read.
[0037]
Table 1 shows an example of the priority order P assigned to each work instruction.
[0038]
[Table 1]
Figure 0003567277
[0039]
In the example shown in Table 1, the first priority is assigned to the ship work as the highest priority work, and the work other than the ship work is referred to as random work, and the priority according to the waiting time from the generation of the work request, that is, the waiting time 1 Those that are longer than the hour are given a second priority, those that are 30 minutes or more and less than one hour are given a third priority, and those that are less than 30 minutes are given a fourth priority.
[0040]
Also, a priority PD according to each priority is set for each work instruction. That is, the priority PD of the first priority work instruction is the value α.1And the priority PD of the work of the second priority is the value αTwoAnd the priority PD of the third priority work is the value αThreeAnd the priority PD of the work of the fourth priority is the value αFourIt is said. The priority is α1> ΑTwo> ΑThree> ΑFourThere is a relationship. This priority PD is used when executing a destination / movement route inference process described later.
[0041]
In step S2, the number of cranes TC to be arranged in each block BL is calculated based on the number of work instructions for each block BL. The process of calculating the number of cranes required for each block will be described later in detail.
[0042]
In step S3, a destination / moving route inference process for searching and inferring the destination and the moving route of each crane TC is executed. This destination / movement route inference processing will be described later in detail.
[0043]
In step S4, a process of transmitting the position of the destination bay BY of each crane TC and the instruction of the moving route inferred by the destination / moving route inferring process is performed.
[0044]
Next, the process of calculating the number of cranes required for each block in step S2 will be described with reference to FIG.
[0045]
First, in step S11, a block job number calculation process of calculating the number of cranes TC to be allocated to each block BL (hereinafter, referred to as a job number) in consideration of the total number of work instructions in the yard CY is executed. Here, the job J (see FIG. 5) refers to a set of work instructions to be handled by one crane TC. This block job number calculation processing will be described later in detail. In FIG. 5, a black square indicates one work instruction.
[0046]
In step S12, a process of integrating each job J is performed in consideration of the number of work instructions included in each job J and the specific arrangement of each job J.
[0047]
That is, in principle, if the number of work instructions included in each job J in a certain block BL is within the number that can be processed in one unit time by one crane TC, those jobs J are integrated into one job. You. However, as shown in FIG.1, JTwoIf the work instructions included in the1, JTwoAre maintained as independent jobs J. Here, the unit time refers to a time interval at which the present system is cyclically started, and is set to 5 minutes in the present embodiment.
[0048]
Also, as shown in FIG.Three, JFourIf the work instructions included in theThree, JFourWhen the number of work instructions included in the job J exceeds the number that can be processed in one unit time by one crane TC, those jobs JThree, JFourIs one job JFiveIt is said. The processing of the work instruction exceeding the processing limit in one unit time of one crane TC is carried over to the next unit time (the next calculation timing) and processed. Therefore, there is no problem even if jobs are integrated beyond the processing limit per unit time of one crane TC.
[0049]
In step S13, the position of each job J is set. Here, the position of each job J is the position of the bay BY where a work instruction to be processed first in each job J (hereinafter, referred to as a head work instruction) exists.
[0050]
In step S14, the priority PD of each job J is set. Here, the priority PD of each job J is equal to the work instruction having the highest priority PD in the job J.
[0051]
In step S15, the number of work instructions included in each job J is calculated.
[0052]
In step S16, the position, the priority PD, and the number of work instructions are output for all jobs J in the yard CY.
[0053]
Next, the process of calculating the number of block jobs in step S11 will be described with reference to FIG.
[0054]
First, in step S21, the total number of work instructions JYTtL (P) for each priority order P in the yard CY is calculated by the following equation (1).
[0055]
(Equation 1)
Figure 0003567277
[0056]
Here, BL: block number, BY: bay number in the block BL, P: priority, M: number of blocks in the yard CY, N: number of bays in the block BL, J (BL, BY, P) : The number of work instructions of priority P included in a certain bay BY in a certain block BL.
[0057]
In step S22, the number of cranes TCNL (L) to be allocated to each lane L is calculated by the following equation (2).
[0058]
(Equation 2)
Figure 0003567277
[0059]
Where β1: Weighting coefficient set for the first priority work instruction, βTwo: Weighting coefficient set for the second priority work instruction, βThree: Weighting coefficient set for the third priority work instruction, βFour: Weighting coefficients set for the fourth priority work instruction, and these coefficients include β1> ΒTwo> ΒThree> ΒFourThere is a relationship.
[0060]
(Equation 3)
Figure 0003567277
[0061]
In step S23, the necessary degree NTC (BL) indicating the degree of necessity of the crane TC is calculated for each block BL in the lane L by the following equation (3).
[0062]
(Equation 4)
Figure 0003567277
[0063]
In step S24, first, one crane TC is assigned to each block BL in which a work instruction exists, according to the following equation (4).
[0064]
(Equation 5)
Figure 0003567277
[0065]
Here, TCNB (BL): the number of cranes allocated to each block BL.
[0066]
In step S25, the total number dTCNL (LN) of the cranes TC assigned to each block BL in step S24 is calculated by the following equation (5).
[0067]
(Equation 6)
Figure 0003567277
[0068]
Here, dTCNL (L) is the total number of the cranes TC assigned to each block BL in the lane L.
[0069]
In step S26, it is determined whether the dTCNL (L) value is equal to or greater than the TCNL (L) value. If the dTCNL (L) value is equal to or greater than the TCNL (L) value, the process proceeds to step S27, in which the number of cranes assigned to each block BL at that time is output as the number of jobs, and the process ends.
[0070]
If the dTCNL (L) value is less than the TCNL (L) value, the process proceeds to step S28. In step S28, the necessity R (BL) per crane TC is calculated for each block BL in the lane L by the following equation (6), and one crane is added to the block BL having a high R (BL) value. After that, the process returns to step S26.
[0071]
(Equation 7)
Figure 0003567277
[0072]
Next, with reference to FIG. 7, the destination / movement route inference processing in step S3 will be described.
[0073]
First, in step S31, a list of combinations of cranes TC and a list of combinations of jobs J are created.
[0074]
For example, three jobs J1, JTwo, JThreeThere are two cranes TC1, TCTwoIs available, only two jobs can currently be processed. In this case, the combination of the crane TC is (TC1, TCTwo), And the combination of job J is each combination that selects two out of three, that is, (J1, JTwo), (JTwo, JThree) And (JThree, J1)).
[0075]
As described above, when the number of jobs to be executed (for example, q) is larger than the number of available cranes (for example, r) (q> r), the number of crane combinations is one, and The job combination is the number of combinations to select r out of q (qCr).
[0076]
Conversely, when the number of available cranes r is larger than the number of jobs to be executed q (q <r), the number of job combinations is one (J1, JTwo,…, Jq), Whereas the number of crane combinations is the number of combinations that select q from r.
[0077]
The processing described below (the processing of steps S32 to S37) is sequentially performed for all the job combinations or crane combinations.
[0078]
That is, in step S32, when there is a crane TC available in the block BL where the job J exists, the crane TC is first allocated to the job J. This is to reduce the time required for inference by first determining the efficient association between the job J and the crane TC.
[0079]
In step S33, when there is a crane TC available in the lane L where the job J exists, the crane TC is assigned to the job J. This also has the same purpose as in step S32.
[0080]
In step S34, the yard CY is divided into the respective processing areas AR by utilizing the symmetry of the yard CY due to the possibility of traffic obstruction or the like.
[0081]
That is, as shown in FIG. 8, the yard CY is composed of nine lanes of lane (A), lane (B),..., Lane (I), and each lane L is composed of three blocks BL. At the four corners of the yard CY (A1), (AThree), (I1), (IThree) Of each block BL in the first processing area AR1And First processing area AR1Blocks adjacent to each block (ATwo), (B1), (BThree), (H1), (HThree), (ITwo) To the second processing area ARTwoAnd each adjacent block (BTwo), (C1), (CThree), (G1), (GThree), (HTwo) To the third processing area ARThreeAnd Third processing area ARThreeBlocks (CTwo), (D1), (DTwo), (DThree), (E1), (ETwo), (EThree), (F1), (FTwo), (FThree), (GTwo) Is the fourth processing area.
[0082]
In step S35, the first processing area AR1To the fourth processing area ARFourArea-specific crane assignment / moving route determination processing for sequentially allocating the crane TC to the job J in each area by a predetermined method. This method will be described later.
[0083]
In this way, by dividing the yard CY into a plurality of processing areas AR and allocating the crane TC to the job J for each area AR, the time required for inference can be significantly reduced.
[0084]
In addition, by allocating the cranes TC in a predetermined manner from the area around the yard CY, it is possible to make it difficult for interference when moving the cranes TC.
[0085]
In step S36, it is determined whether or not the result of the assignment / movement route determination by the processing in steps S32 to S35 does not conflict with a predetermined constraint condition.
[0086]
The constraints include, for example, eliminating the inefficient movement of the crane TC, eliminating interference during the movement of each crane TC, and avoiding a situation where a job J having a higher priority is left unprocessed without being processed. Is a condition set under the intent of the above.
[0087]
Specifically, (1) the lane change of each crane TC is limited to k times, (2) the processing of the job J having a higher priority is given priority, and (3) the arrangement of each crane in which a deadlock occurs. Prohibited (4) A state in which a certain crane TC moves to another block BL without processing the job J existing in the same block BL, and the remaining crane TC moves and processes the remaining job J is avoided. Each condition is set such that the movement of the two cranes TC is reduced.
[0088]
The inference result that conflicts with the constraint condition is discarded, and the evaluation and storage of the inference result are performed in step S37 for the job combination or the crane combination that does not conflict with the constraint condition according to the following criteria.
[0089]
That is, first, the sum of the priorities PD (see Table 1) of each job J processed by the combination is compared, and the combination having the largest sum is selected.
[0090]
If the sum of the priorities PD is equal, secondly, the sum of the traveling times of the cranes TC is compared, and the smallest combination is selected. Third, if the sum of the travel times is equal, the sum of the travel distances of the cranes TC is compared, and the shortest combination is selected.
[0091]
In step S38, it is determined whether or not inference has been performed for all combinations, and if there are any combinations for which inference has not been completed, the processes of steps S32 to S37 are executed for those combinations.
[0092]
If the inference has been performed for all combinations, the inference result for the combination with the best evaluation result is output as the final inference result for each crane TC destination / movement path.
[0093]
Next, with reference to FIG. 9, the crane assignment / movement route determination process for each area in step S35 will be described.
[0094]
First, in step S41, the area number i of the processing area AR to be inferred is set to the value 1.
[0095]
In step S42, the processing area (i), that is, the first processing area AR1Is searched for a job J included in the combination.
[0096]
In step S43, the crane TC with the shortest moving time is assigned to each searched job J by the shortest route.
[0097]
In step S44, it is determined whether or not a conflict with the constraint condition occurs based on the result. If there is a conflict, the process is terminated as a combination discarded by the process of step S36.
[0098]
If there is no conflict, in step S45, all processing areas AR, that is, the first processing area AR1To the fourth processing area ARFourIt is determined whether or not the crane TC has been assigned to the vehicle. If the allocation has been performed for all the processing areas AR, the processing ends. If there is a processing area AR for which the allocation has not been completed, the area number i is increased by 1 in step S46, and the processing proceeds to step S42. Return.
[0099]
【Example】
Hereinafter, each process will be described using a specific example.
[0100]
FIG. 10 shows 18 jobs J to be processed in the entire yard CY.1~ J18There are 12 crane TCs1~ TC12Shows the case where processing should be performed. The yard CY is the same as that in FIG. Further, the symbols in the squares representing the job J in each block BL indicate the priority. For example, the symbol S in the square represents the ship work of the first priority, and the symbol 3 represents the random work of the fourth priority (waiting time: less than 30 minutes).
[0101]
First, a job combination list and a crane combination list are created by the processing in step S31. In this specific example, the number of jobs is 18, and the number of cranes is 12. Therefore, the number of combinations of cranes is one. On the other hand, the number of combinations of jobs is 12, 564, ie, the number of combinations to select 12 out of 18. It is considered as street.
[0102]
Steps S32 to S37 are performed for all the job combinations. In the following description, the job combination (J1, JTwo, JThree, JFour, JFive, J7, J8, JTen, J11, J13, J15, J1610), the procedure for allocating the crane TC to each job J and determining the movement route will be described with reference to FIG.
[0103]
(Procedure 1) First, the crane TC is assigned to the job J existing in the same block BL by the process of step S32.
[0104]
That is, the fifth job JFiveThe first crane TC1Is assigned, and the seventh job J7To the 10th crane TCTenAre assigned, and the third job JThree9th crane TC9Is assigned, and the seventh job J7To the 10th crane TCTenIs assigned, and the thirteenth job J13The 12th crane TC12Is assigned, and the 15th job J1511th crane TC11Is assigned.
[0105]
(Procedure 2) By the processing in step S33, cranes TC other than the crane allocated in procedure 1 are allocated to the job J existing in the same lane L. In this specific example, there is no job J to be assigned in this procedure 2.
[0106]
(Procedure 3) By processing in step S35, each processing area AR1~ ARFourEach time, the crane TC is assigned to each job J. Hereinafter, each region will be described. (Procedure 3.1) First processing area AR1Each block belonging to (A1), (AThree), (I1), (IThreeThe crane TC is assigned to each job J in the parentheses.
[0107]
(Procedure 3.1.1) That is, block (A)1The first job J in1The third crane TC closest to the unassigned cranesThreeIs assigned. This moving route is indicated by an arrow Y1Indicated by
[0108]
(Procedure 3.1.2) In addition, block (A)ThreeThe third job J)ThreeSecond crane TC closest to crane TC unassigned toTwoIs assigned. This moving route is indicated by an arrow YTwoIndicated by
[0109]
(Procedure 3.2) Next, the second processing area ARTwoEach block belonging to (ATwo), (B1), (BThree), (H1), (HThree), (ITwoThe crane TC is assigned to each job J in the parentheses.
[0110]
(Procedure 3.2.1) That is, block (B)14th job J)FourThe fifth crane TC closest to all unassigned cranesFiveIs assigned. This moving route is indicated by an arrow YThreeIndicated by
[0111]
(Procedure 3.2.2) Block (ATwoThe second job J)Two4th crane TC closest to unassigned cranesFourIs assigned. This moving route is indicated by an arrow YFourIndicated by
[0112]
(Procedure 3.2.3) Block (H116th job J)166th crane TC closest to all unassigned crane TCs6Is assigned. This moving route is indicated by an arrow YFiveIndicated by
[0113]
(Procedure 3.3) Next, the third processing area ARThreeEach block belonging to (BTwo), (C1), (CThree), (G1), (GThree), (HTwoThe crane TC is assigned to each job J in the parentheses.
[0114]
(Procedure 3.3.1) That is, the block (G111th job J)117th crane TC which is the closest among unassigned crane TCs7Is assigned. This moving route is indicated by an arrow Y6Indicated by
[0115]
(Procedure 3.4) Next, the fourth processing area ARFourEach block belonging to (CTwo), (D1), (DTwo), (DThree), (E1), (ETwo), (EThree), (F1), (FTwo), (FThree), (GTwoThe crane TC is assigned to each job J in the parentheses.
[0116]
(Procedure 3.4.1) That is, the block (FTwo8th job J)88th crane TC closest to unassigned crane TC8Is assigned. This moving route is indicated by an arrow Y8Indicated by
[0117]
As described above, the system T of the present embodiment creates each job J, which is a work unit, from each work instruction from the higher system ST, and uses the empirical rules to step by step for each type of crane for each job J for each type. Since the assignment and the movement route of the TC are calculated by exploratory inference, the arrangement and the movement plan of each crane TC in the yard CY can be created within a relatively short time. That is, the operation plan of each crane can be quickly created.
[0118]
As described above, the present invention has been described based on the embodiment and the examples. However, the present invention is not limited to only the embodiment, and various modifications are possible. For example, in the embodiment and the examples, the transfer crane is used as the self-propelled cargo transportation means, but the self-propelled cargo transportation means is not limited to the transfer crane, and various self-propelled cargo transportation Means can be used. Although the cargo accumulation location is a container yard, various cargo accumulation locations can be used.
[0119]
【The invention's effect】
As described in detail above, in the present invention, the operation plan of the self-propelled cargo transportation means at the cargo accumulation place having the lane consisting of the required number of cargo blocks is made by exploratory inference under predetermined constraints, and Since the most efficient operation plan is selected from the operation plans of self-propelled cargo transportation means obtained by exploratory inference, efficient operation of each self-propelled cargo transportation means at the cargo accumulation location An excellent effect that can be achieved is obtained.
[Brief description of the drawings]
FIG. 1 is a schematic diagram showing a schematic configuration of a transfer crane arrangement planning system according to an embodiment of the present invention.
FIG. 2 is a functional block diagram of the present system.
FIG. 3 is a flowchart showing a schematic flow of processing by the present system.
FIG. 4 is a flowchart showing a flow of a crane number calculation process required for each block.
FIG. 5 is a schematic diagram illustrating an example of a job creation procedure.
FIG. 6 is a flowchart illustrating a flow of each block job number calculation process.
FIG. 7 is a flowchart illustrating a flow of a destination / movement route inference process.
FIG. 8 is a schematic diagram showing an arrangement of each processing area in a yard.
FIG. 9 is a flowchart illustrating a flow of a crane assignment / movement route determination process for each area.
FIG. 10 is a schematic diagram for explaining a specific example of crane arrangement by the present system, and shows a state before arrangement.
FIG. 11 is a schematic diagram for explaining a specific example of crane arrangement by the present system, and shows a state after arrangement.
FIG. 12 is a schematic diagram showing a container storage mode and a transfer crane arrangement in a conventional container yard.
FIG. 13 is a schematic diagram showing a container storage mode and a transfer crane arrangement in a conventional container yard.
[Explanation of symbols]
1 Work instruction / crane information reading means
2 Number of cranes required for each block
3 destination / movement route calculation means
4 Destination and travel route evaluation means
5 Moving destination / moving route indicating means
BL block
CY yard
J Job (unit of work)
L lane
ST host system
T This system
TC transfer crane
W container
Y travel route

Claims (25)

複数ベイを有する複数の貨物ブロックからなるレーンを数備える貨物集積場所における複数の自走式貨物運搬手段の運用計画方法であって、
作業指示をその優先順位とともに取得する手順と、
自走式貨物運搬手段の現在位置情報およびその利用可能性に関する情報を取得する手順と、
前記作業指示に関する情報に基づいて、各貨物ブロックにおける必要自走式貨物運搬手段数を算出するジョブ数算出手順と、
前記ジョブ数算出手順により算出されたジョブ数のジョブの処理における自走式貨物運搬手段の貨物ブロックへの割当て、およびその割当てがなされた貨物ブロックへの同自走式貨物運搬手段の移動経路の算出を探索的推論処理によりなす手順
とを含み、
前記探索的推論処理においては、
(1)自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せリストが作成され、その組合せリストにおける自走式貨物運搬手段およびジョブの組合せは、自走式貨物運搬手段の数がジョブ数より少ない場合は、自走式貨物運搬手段の組合せは1通りとされる一方、ジョブの組合せはジョブ数より自走式貨物運搬手段の数だけのジョブを選んでなる組合せとされ、その逆にジョブ数が自走式貨物運搬手段の数より少ない場合は、ジョブの組合せは1通りとされる一方、自走式貨物運搬手段の組合せは全自走式貨物運搬手段からジョブ数だけの自走式貨物運搬手段を選んでなる組合せとされ、
(2)前記組合せリスト中の自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せの全てについて、個々のジョブへの自走式貨物運搬手段の割当が順次なされ、その順次割当てにおいて、(i)ジョブが存在する貨物ブロックに利用可能な自走式貨物運搬手段がある場合、その自走式貨物運搬手段にジョブが優先的に割当され、(ii)ジョブが存在するレーンに利用可能な自走式貨物運搬手段がある場合、その自走式貨物運搬手段にジョブが優先的に割当てされ、(iii)貨物集積場所が所定の基準にしたがって複数の領域に分割され、各領域毎に最初に処理されるべき作業指示が存在するベイにジョブ位置を設定する、ジョブ位置設定処理により設定されたジョブへ自走式貨物運搬手段が割当てされ、(iv)割当がなされた各自走式貨物運搬手段に対して移動経路が決定され、(v)自走式貨物運搬手段に割当てられたジョブおよび決定された移動経路が所定の制約条件に抵触していないか判定され、
(3)前記判定において制約条件に抵触するとされた自走式貨物運搬手段とジョブとの個別組合せを含む、自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せが前記組合せリストから棄却され、
(4)前記制約条件を満足する自走式貨物運搬手段とジョブとの個別組合せを含む、自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せのそれぞれについて、その組合せにおいて処理される各ジョブの優先順位に基づく優先度を、同組合せにおける全ジョブについて加算してなる優先度の総和を比較し、 (5)前記優先度の総和が最大となる自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せが前記組合せリストから選出され
前記選出された自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せをそれに対する推論結果とともに出力する
ことを特徴とする自走式貨物運搬手段の運用計画方法。
Lanes consisting multiple cargo block having a plurality bays a operation plan method of a plurality of self-propelled cargo transfer means in the cargo collection point with multiple,
A procedure for obtaining work instructions with their priorities;
A procedure for obtaining the current location information of the self-propelled cargo vehicle and information on its availability,
A job number calculation procedure for calculating the required number of self-propelled cargo transport means in each cargo block based on the information on the work instruction;
The assignment of the self-propelled cargo transport means to the cargo block in the processing of the job with the number of jobs calculated by the job number calculation procedure, and the movement path of the self-propelled cargo transport means to the assigned cargo block. Procedure for calculating by exploratory inference processing
And
In the exploratory inference process,
(1) A combination list including a combination of the self-propelled cargo conveyance means and a job combination is created, and the combination of the self-propelled cargo conveyance means and the job in the combination list indicates that the number of self-propelled cargo conveyance means If the number is less than the number, the combination of the self-propelled cargo conveyance means is one, and the combination of the jobs is a combination of the number of the self-propelled cargo conveyance means selected from the number of the jobs, and vice versa. If the number of jobs is less than the number of self-propelled freight vehicles, only one job combination is available. It is a combination that chooses a traveling cargo transportation means,
(2) For all combinations of the combination of the self-propelled cargo transport means and the job in the combination list, the assignment of the self-propelled cargo transport means to each job is sequentially performed. (I) If there is a self-propelled cargo carrier available in the cargo block where the job exists, the job is preferentially assigned to the self-propelled carrier, and (ii) it can be used in the lane where the job exists. If there is a suitable self-propelled freight carrier, the job is preferentially assigned to the self-propelled freight carrier, and (iii) the cargo accumulation location is divided into a plurality of areas according to a predetermined standard, and First, a self-propelled freight carrier is assigned to the job set by the job position setting process, in which a job position is set in a bay where a work instruction to be processed is present, and (iv) assignment is performed. Each self-propelled movement path relative expression freight unit is determined, it is determined whether (v) self-propelled jobs assigned to cargo transfer means and the determined moving path does not violate the prescribed constraints,
(3) A combination consisting of a combination of a self-propelled freight carrier and a job, including an individual combination of a self-propelled freight carrier and a job determined to violate the constraint in the determination, is rejected from the combination list. And
(4) Each combination including the combination of the self-propelled cargo conveyance means and the job including the individual combination of the self-propelled cargo conveyance means and the job satisfying the above-described constraint is processed in the combination. The priority based on the priority of each job is compared with the sum of the priorities obtained by adding all the jobs in the same combination. (5) The combination of the self-propelled cargo transportation means having the largest sum of the priorities A combination consisting of a job combination is selected from the combination list ,
A method for planning the operation of a self-propelled freight carrier, comprising: outputting a combination of the selected combination of the self-propelled freight carrier and a combination of jobs together with an inference result for the combination .
前記優先度の総和が等しい場合、自走式貨物運搬手段の移動時間の総和が比較され、移動時間の総和が最小のものが選出されることを特徴とする請求項1記載の自走式貨物運搬手段の運用計画方法。 If the sum of the priority is equal, self-propelled is sum of travel time comparison of cargo transfer means, self-propelled cargo claim 1, wherein the sum of the travel time, characterized in Rukoto elected the smallest How to plan the operation of the vehicle. 前記移動時間の総和が等しい場合、自走式貨物運搬手段の移動距離の総和が比較され、移動距離の総和が最小のものが選出されることを特徴とする請求項2記載の自走式貨物運搬手段の運用計画方法。3. The self-propelled cargo according to claim 2, wherein when the sum of the travel times is equal, the sum of the travel distances of the self-propelled cargo transport means is compared, and the one with the smallest sum of the travel distances is selected. How to plan the operation of the vehicle. 4隅に位置する領域にある貨物ブロックに自走式貨物運搬手段 を優先的に割り当てをなすことを特徴とする請求項1記載の自走式貨物運搬手段の運用計画方法。 2. The operation planning method for a self-propelled freight carrier according to claim 1 , wherein the self-propelled freight carrier is preferentially assigned to the cargo blocks located in the four corners . 前記制約条件が、自走式貨物運搬手段同士によるデッドロックが発生しないとするものであることを特徴とする請求項1記載の自走式貨物運搬手段の運用計画方法。 The constraint, operation planning method of the self-propelled cargo transfer means of claim 1, wherein the der Rukoto those deadlock by self-propelled freight unit with each other is not generated. 前記制約条件が、自走式貨物運搬手段のレーン替え回数を制限するものであることを特徴とする請求項1記載の自走式貨物運搬手段の運用計画方法。 The constraint, operation planning method of the self-propelled cargo transfer means of claim 1, wherein the der Rukoto limiting the lane replacement number of the self-propelled cargo transfer means. 貨物集積場所が対称性を有することを特徴とする請求項1記載の自走式貨物運搬手段の運用計画方法。 2. The operation planning method for a self-propelled cargo transport means according to claim 1, wherein the cargo accumulation location has symmetry . 第1優先順位の優先度が最大とされていることを特徴とする請求項記載の自走式貨物運搬手段の運用計画方法。Operation plan method of self-propelled cargo transfer means of claim 1, wherein the priority of the first priority, characterized in that there is a maximum. 積出しに関する作業指示の優先順位が第1順位とされていることを特徴とする請求項記載の自走式貨物運搬手段の運用計画方法。Operation plan method of self-propelled cargo transfer means of claim 1, wherein the priority of the work instruction relating to the product out, characterized that you have been the first priority. ランダム作業指示については、作業要求発生からの待ち時間に応じて優先順位が設定されることを特徴とする請求項記載の自走式貨物運搬手段の運用計画方法。 For random work order, operation planning method of the self-propelled cargo transfer means of claim 1, wherein the priority in accordance with the waiting time from work request generated is set. 自走式貨物運搬手段がトランファクレーンとされてなることを特徴とする請求項1ないし請求項10のいずれか一項に記載の自走式貨物運搬手段の運用計画方法。Operation plan method of self-propelled cargo transfer means according to any one of claims 1 to 10, characterized in that the self-propelled cargo transport means is formed by the transformer fan crane. 貨物集積場所がコンテナヤードとされてなることを特徴とする請求項1ないし請求項11記載のいずれか一項に記載の自走式貨物運搬手段の運用計画方法。Operation plan method of self-propelled cargo transfer means according to any one of claims 1 to 11, wherein the cargo collection place is characterized by comprising a a container yard. 複数ベイを有する複数の貨物ブロックからなるレーンを数備える貨物集積場所における複数の自走式貨物運搬手段の運用計画システムであって、
作業指示をその優先順位とともに取得し、自走式貨物運搬手段の現在位置情報およびその利用可能性に関する情報を取得し、前記作業指示に関する情報に基づいて各貨物ブロックにおける必要自走式貨物運搬手段数を算出するジョブ数算出処理をし、自走式貨物運搬手段を必要とされる貨物ブロックへの割当ておよびその割当てがなされた貨物ブロックへの移動経路の算出を探索的推論処理するよう構成され、
前記探索的推論処理において、
(1)自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せリストが作成され、その組合せリストにおける自走式貨物運搬手段およびジョブの組合せは、自走式貨物運搬手段の数がジョブ数より少ない場合は、自走式貨物運搬手段の組合せは1通りとされる一方、ジョブの組合せはジョブ数より自走式貨物運搬手段の数だけのジョブを選んでなる組合せとされ、その逆にジョブ数が自走式貨物運搬手段の数より少ない場合は、ジョブの組合せは1通りとされる一方、自走式貨物運搬手段の組合せは全自走式貨物運搬手段からジョブ数だけの自走式貨物運搬手段を選んでなる組合せとされ、
(2)前記組合せリスト中の自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せの全てについて、個々のジョブへの自走式貨物運搬手段の割当が順次なされ、その順次割当てにおいて、(i)ジョブが存在する貨物ブロックに利用可能な自走式貨物運搬手段がある場合、その自走式貨物運搬手段にジョブが優先的に割当され、(ii)ジョブが存在するレーンに利用可能な自走式貨物運搬手段がある場合、その自走式貨物運搬手段にジョブが優先的に割当てされ、(iii)貨物集積場所が所定の基準にしたがって複数の領域に分割され、各領域毎に最初に処理されるべき作業指示が存在するベイにジョブ位置を設定する、ジョブ位置設定処理により設定されたジョブへ自走式貨物運搬手段が割当てされ、(iv)割当がなされた各自走式貨物運搬手段に対して移動経路が決定され、(v)自走式貨物運搬手段に割当てられたジョブおよび決定された移動経路が所定の制約条件に抵触していないか判定され、
(3)前記判定において制約条件に抵触するとされた自走式貨物運搬手段とジョブとの個別組合せを含む、自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せが 前記組合せリストから棄却され、
(4)前記制約条件を満足する自走式貨物運搬手段とジョブとの個別組合せを含む、自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せのそれぞれについて、その組合せにおいて処理される各ジョブの優先順位に基づく優先度を、同組合せにおける全ジョブについて加算してなる優先度の総和を比較し、 (5)前記優先度の総和が最大となる自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せが前記組合せリストから選出され
前記選出された自走式貨物運搬手段の組合せとジョブの組合せとからなる組合せをそれに対する推論結果とともに出力する
ことを特徴とする自走式貨物運搬手段の運用計画システム。
A production planning system of a plurality of self-propelled cargo transfer means in the cargo collection point with multiple lanes consisting multiple cargo block having a plurality bays,
Acquire the work instructions together with their priorities, obtain the current position information of the self-propelled cargo transportation means and information on its availability, and based on the information on the work instructions, the necessary self-propelled cargo transportation means in each cargo block It is configured to perform a job number calculation process for calculating the number, and to perform exploratory inference processing for allocating the self-propelled cargo transportation means to the required cargo blocks and calculating the moving route to the allocated cargo blocks. ,
In the exploratory inference process,
(1) A combination list including a combination of the self-propelled cargo conveyance means and a job combination is created, and the combination of the self-propelled cargo conveyance means and the job in the combination list indicates that the number of self-propelled cargo conveyance means If the number is less than the number, the combination of the self-propelled cargo conveyance means is one, and the combination of the jobs is a combination of the number of the self-propelled cargo conveyance means selected from the number of the jobs, and vice versa. If the number of jobs is less than the number of self-propelled freight vehicles, only one job combination is available. It is a combination that chooses a traveling cargo transportation means,
(2) For all combinations of the combination of the self-propelled cargo transport means and the job in the combination list, the assignment of the self-propelled cargo transport means to each job is sequentially performed. (I) If there is a self-propelled cargo carrier available in the cargo block where the job exists, the job is preferentially assigned to the self-propelled carrier, and (ii) it can be used in the lane where the job exists. If there is a suitable self-propelled freight carrier, the job is preferentially assigned to the self-propelled freight carrier, and (iii) the cargo accumulation location is divided into a plurality of areas according to a predetermined standard, and First, a self-propelled freight carrier is assigned to the job set by the job position setting process, in which a job position is set in a bay where a work instruction to be processed is present, and (iv) assignment is performed. Each self-propelled movement path relative expression freight unit is determined, it is determined whether (v) self-propelled jobs assigned to cargo transfer means and the determined moving path does not violate the prescribed constraints,
(3) A combination consisting of a combination of a self-propelled freight carrier and a job, including an individual combination of a self-propelled freight carrier and a job determined to violate the constraint in the determination, is rejected from the combination list. And
(4) Each combination including the combination of the self-propelled cargo conveyance means and the job including the individual combination of the self-propelled cargo conveyance means and the job satisfying the above-described constraint is processed in the combination. The priority based on the priority of each job is compared with the sum of the priorities obtained by adding all the jobs in the same combination. (5) The combination of the self-propelled cargo transportation means having the largest sum of the priorities A combination consisting of a job combination is selected from the combination list ,
An operation planning system for a self-propelled freight carrier, wherein a combination comprising the selected combination of the self-propelled freight carrier and a job combination is output together with an inference result for the combination .
上位システムから作業指示および自走式貨物運搬手段に関する情報を読込む作業指示・自走式貨物運搬手段情報読込手段と、前記作業指示・自走式貨物運搬手段情報読込手段により読込まれた作業指示および自走式貨物運搬手段に関する情報に基づいて各貨物ブロックにおける必要自走式貨物運搬手段の数を算出してジョブ数を算出する各貨物ブロック必要自走式貨物運搬手段数算出手段と、前記各貨物ブロック必要自走式貨物運搬手段数算出手段により算出された各自走式貨物運搬手段の移動先および移動経路を探索的推論により算出する移動先・移動経路算出手段と、前記移動先・移動経路算出手段により算出された移動先および移動経路を評価して最適な移動先および移動経路を選択する移動先・移動経路評価手段と、前記移動先・移動経路評価手段により選択された移動先および移動経路を出力する移動先・移動経路指示手段とを備えてなることを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。A work instruction and a self-propelled cargo transport means information reading means for reading a work instruction and information about a self-propelled cargo transport means from a host system, and a work instruction read by the work instruction and the self-propelled cargo transport means information reading means. And calculating the number of required self-propelled cargo transport means in each cargo block based on the information on the self-propelled cargo transport means and calculating the number of jobs. Destination / movement route calculation means for calculating the destination and movement route of each self-propelled cargo transportation means calculated by each cargo block required self-propelled cargo transportation means calculation means by search inference; A destination / moving route evaluation means for evaluating the destination and the moving route calculated by the route calculating means and selecting an optimum destination and a moving route; Operation planning system of the self-propelled cargo transfer means according to claim 13, characterized in that it comprises a movement destination and movement routing means for outputting the destination and travel route selected by the route evaluation unit. 前記優先度の総和が等しい場合、自走式貨物運搬手段の移動時間の総和が比較され、移動時間の総和が最小のものが選出されることを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。 If the sum of the priority is equal, self-propelled is sum of travel time comparison of cargo transfer means, self-propelled cargo claim 13 wherein the sum of the travel time, characterized in Rukoto elected the smallest Transportation planning system. 前記移動時間の総和が等しい場合、自走式貨物運搬手段の移動距離の総和が比較され、移動距離の総和が最小のものが選出されることを特徴とする請求項15記載の自走式貨物運搬手段の運用計画システム。 16. The self-propelled cargo according to claim 15, wherein when the sum of the travel times is equal, the sum of the travel distances of the self-propelled cargo transport means is compared , and the one with the smallest total of the travel distance is selected. Transportation planning system. 4隅に位置する領域にある貨物ブロックに自走式貨物運搬手段を優先的に割り当てをなすことを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。 14. The operation planning system for a self-propelled freight carrier according to claim 13 , wherein the self-propelled freight carrier is preferentially assigned to the cargo blocks located in the four corner areas . 前記制約条件が、自走式貨物運搬手段同士によるデッドロックが発生しないとするものであることを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。 The constraint, self-propelled cargo conveyor means between operation planning system of the self-propelled cargo transfer means of claim 13, wherein the der Rukoto those deadlock does not occur due to. 前記制約条件が、自走式貨物運搬手段のレーン替え回数を制限するものであることを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。 The constraint, the operation planning system of the self-propelled cargo transfer means of claim 13, wherein the der Rukoto limiting the lane replacement number of the self-propelled cargo transfer means. 貨物集積場所が対称性を有することを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。14. The operation planning system for a self-propelled cargo transport means according to claim 13, wherein the cargo accumulation location has symmetry . 第1優先順位の優先度が最大とされていることを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。14. The operation planning system for a self-propelled freight carrier according to claim 13, wherein the first priority is the highest priority . 積出しに関する作業指示の優先順位が第1順位とされていることを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。Operation planning system of the self-propelled cargo transfer means of claim 13, wherein the priority of the work instruction relating to the product out, characterized that you have been the first priority. ランダム作業指示については、作業要求発生からの待ち時間に応じて優先順位が設定されることを特徴とする請求項13記載の自走式貨物運搬手段の運用計画システム。 14. The operation planning system for self-propelled freight transport means according to claim 13, wherein priorities are set for the random work instructions according to a waiting time from the generation of the work request . 自走式貨物運搬手段がトランファクレーンとされてなることを特徴とする請求項13ないし請求項23のいずれか一項に記載の自走式貨物運搬手段の運用計画システム。Operation planning system of the self-propelled cargo transfer means according to any one of claims 13 to 23, characterized in that the self-propelled cargo transport means is formed by the transformer fan crane. 貨物集積場所がコンテナヤードとされてなることを特徴とする請求項13ないし請求項24のいずれか一項に記載の自走式貨物運搬手段の運用計画システム。Operation planning system of the self-propelled cargo transfer means according to any one of claims 13 to 24 cargo collection place is characterized by comprising a a container yard.
JP2000180108A 2000-06-15 2000-06-15 Operation planning method and operation planning system for self-propelled cargo transportation means Expired - Lifetime JP3567277B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000180108A JP3567277B2 (en) 2000-06-15 2000-06-15 Operation planning method and operation planning system for self-propelled cargo transportation means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000180108A JP3567277B2 (en) 2000-06-15 2000-06-15 Operation planning method and operation planning system for self-propelled cargo transportation means

Publications (2)

Publication Number Publication Date
JP2001356819A JP2001356819A (en) 2001-12-26
JP3567277B2 true JP3567277B2 (en) 2004-09-22

Family

ID=18681269

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000180108A Expired - Lifetime JP3567277B2 (en) 2000-06-15 2000-06-15 Operation planning method and operation planning system for self-propelled cargo transportation means

Country Status (1)

Country Link
JP (1) JP3567277B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4982531B2 (en) * 2009-07-28 2012-07-25 日立Geニュークリア・エナジー株式会社 Work area arrangement support apparatus, method, program, and recording medium
JP6823335B2 (en) * 2016-09-08 2021-02-03 株式会社三井E&Sマシナリー Transfer crane automatic deployment decision system and shortest movement route calculation method for moving objects
JP6818326B2 (en) * 2017-12-11 2021-01-20 国土交通省港湾局長 Distributed placement system for cargo handling machines utilizing artificial intelligence
KR102775807B1 (en) * 2021-11-09 2025-03-06 울산대학교 산학협력단 Method for Transporter scheduling
JP2024093304A (en) * 2022-12-27 2024-07-09 三菱重工業株式会社 Placement area planning device, placement area planning method, and program
KR102693475B1 (en) * 2023-05-24 2024-08-07 롯데건설 주식회사 A System for Managing Assembling Process of PC Members

Also Published As

Publication number Publication date
JP2001356819A (en) 2001-12-26

Similar Documents

Publication Publication Date Title
CN115097843B (en) Multi-AGV path planning method and device based on dynamic priority express distribution center
CN114023094B (en) Wharf vehicle scheduling system, method, equipment and medium
Meisel et al. Synchronized routing of active and passive means of transport
JP6757490B2 (en) Autonomous replacement of pallets of items in the warehouse
Lee et al. An optimization model for storage yard management in transshipment hubs
CN111091238B (en) An intelligent scheduling method for AGV in automated container terminals
Jiang et al. Flexible space-sharing strategy for storage yard management in a transshipment hub port
TWI397491B (en) Handling systems and handling methods
CN115237137B (en) Multi-AGV scheduling and collaborative path planning method and device
Zhen et al. A review on yard management in container terminals
Dorndorf et al. Scheduling automated triple cross-over stacking cranes in a container yard
JPH064516A (en) Assignment decision support method
JP3567277B2 (en) Operation planning method and operation planning system for self-propelled cargo transportation means
CN118466514A (en) A RMFS multi-AGV path planning and conflict and deadlock avoidance method and system
CN115167457A (en) Multi-AGV scheduling and collaborative path planning method and device considering electric quantity constraint
Rashidi et al. Vehicle scheduling in port automation: advanced algorithms for minimum cost flow problems
Tschöke et al. Container supply with multi-trailer trucks: parking strategies to speed up the gantry crane-based loading of freight trains in rail yards
JP4025652B2 (en) Transportation planning system and method
JP5402943B2 (en) Transport vehicle system and transport vehicle control method
Kim Models and methods for operations in port container terminals
JP4337135B2 (en) Location arrangement method for flat warehouse
Safaeian et al. An integrated quay crane assignment and scheduling problem with several contractors in container terminals
CN117787850A (en) AGV vehicle transportation task allocation method and system based on YTS-SAP model
JP2002370832A (en) Vehicle allocation control method and vehicle allocation control device for manned carrier truck
Vis et al. Container terminal operations: An overview

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040316

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040317

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040527

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080625

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080625

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090625

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090625

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100625

Year of fee payment: 6