JP3569691B2 - Under-track structure construction method - Google Patents
[go: Go Back, main page]

JP3569691B2 - Under-track structure construction method - Google Patents

Under-track structure construction method Download PDF

Info

Publication number
JP3569691B2
JP3569691B2 JP2001219181A JP2001219181A JP3569691B2 JP 3569691 B2 JP3569691 B2 JP 3569691B2 JP 2001219181 A JP2001219181 A JP 2001219181A JP 2001219181 A JP2001219181 A JP 2001219181A JP 3569691 B2 JP3569691 B2 JP 3569691B2
Authority
JP
Japan
Prior art keywords
girder
temporary
track
under
permanent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001219181A
Other languages
Japanese (ja)
Other versions
JP2003027423A (en
Inventor
忠良 石橋
昭夫 伊藤
清一 佐藤
正人 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East Japan Railway Co
Original Assignee
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East Japan Railway Co filed Critical East Japan Railway Co
Priority to JP2001219181A priority Critical patent/JP3569691B2/en
Publication of JP2003027423A publication Critical patent/JP2003027423A/en
Application granted granted Critical
Publication of JP3569691B2 publication Critical patent/JP3569691B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、鉄道の線路下に構造物を構築する工法に関するものであり、特に、線路下の地盤掘削等に用いる仮設桁を補強して本設桁を形成し線路下構造物の一部として利用する線路下構造物構築工法に関する。
【0002】
【従来の技術】
従来、鉄道営業を行い列車が走行している線路(以下、「活線」という。)の下方を横断するトンネルや函渠等の構造物(以下、「線路下構造物」という。)を構築する場合には、図7に示すような工法が採用されていた。
【0003】
この場合には、まず、図7(A)に示すように、線路の近傍、例えば線路側方等に複数の立坑、例えばH1、H2、H3、及びH4を所定の深さまで掘削し、この立坑H1〜H4の内部に、仮設橋脚、例えば11、12、13、及び14を設置する。仮設橋脚11〜14は、鋼材等からなり、柱状に構成され、立坑の底部の地盤G1により支持される。その後、線路近傍に複数の仮設桁、例えば221、222、223、224、及び225を設置し、これらの仮設桁221〜225が、仮設橋脚11〜14により支持(例えば、各仮設桁の両端の単純支持)されるようにする。仮設桁221等は、工事桁とも呼ばれる。
【0004】
次に、図7(B)に示すように、上記した仮設橋脚11〜14と仮設桁221〜225などにより、軌道を仮受けし、列車荷重や軌きょう(レールとまくらぎ等から構成される梯子状の構造体)の自重等を仮設橋脚11〜14と仮設桁221〜225などにより支持する。
【0005】
図8は、仮設桁の詳細な構成を示す図であり、図8(A)は、仮設桁221と軌きょうとの関係を示す横断面図である。図8(A)に示すように、仮設桁221は、鋼材等からなるI形断面等の主桁411及び412を有し、主桁411、412は、軌道の両側に沿って設置され、桁の中心軸方向が軌道の長手方向と略平行となるように配置される。各主桁411、412の軌道側には、鋼材等からなる横桁固定用部材414、415が取り付けられており、これらにより、鋼材等からなる横桁413が支持されている。横桁413の横断面は、図8(B)に示すような略「U」字状又は樋状となっており、この横桁413の内部の溝状の空間に、まくらぎTが抱き込まれるようにして収容されるようになっている。まくらぎTは、レールR1及びR2を支持している。
【0006】
次に、上記のように仮設橋脚11〜14と仮設桁221〜225などにより軌きょうが仮受けされている状態で、線路下の地盤G2を掘削し、本設橋脚、例えば31、32を設置する。本設橋脚31等は、例えばコンクリート構造物等によって構成される。本設橋脚31等が設置されると、次に、本設桁、例えば271、272、273等を設置し、これらの本設桁271〜273が、本設橋脚31、32により支持(例えば、各仮設桁の両端の単純支持)されるようにする。
【0007】
次に、図7(C)に示すように、軌道(軌きょう)を、仮設桁221等から本設桁271等に受け替える。これにより、列車荷重や軌きょう自重等は、本設桁271等と本設橋脚31等と本設橋脚下の地盤G3により支持されるようになる。この受け替え工程の後、仮設桁221等はてっ去され、軌道の形状(平面形状、水準高低等)は所定の精度範囲内となるように整正され復旧される。なお、図7(C)において、符号RLは、図8(A)に示すレールR1等の頂面の位置を示している。図7(C)において、本設桁271等と本設橋脚31等は、線路下構造物を構成している。
【0008】
【発明が解決しようとする課題】
しかしながら、上記した従来の線路下構造物構築工法では、いったん仮設桁を軌道近傍に設置して線路下構造物を構築した後、設置された仮設桁を今度はてっ去し、軌道を復旧する必要がある。活線における仮設桁の設置及びてっ去は、列車運行の安全を確保するために夜間作業となったり、保安対策に万全を尽くす必要があるなど、多大な労力を要し、それに伴って建設コストも高価なものとなっていた。また、仮設桁自体は、本設構造物ではなく、何回かは転用が可能ではあるが、その製作費用の分は、余分な建設コストとなっていた。また、仮設桁のてっ去工事の分だけ全体の工事期間が伸びることになる、という問題もあった。
【0009】
本発明は上記の問題を解決するためになされたものであり、本発明の解決しようとする課題は、仮設桁を活用して本設桁を形成し線路下構造物を構築し得る工法を提供することにある。
【0010】
【課題を解決するための手段】
上記課題を解決するため、本発明に係る線路下構造物構築工法は、複数の仮設橋脚を線路近傍に設置した後、前記仮設橋脚により支持される複数の仮設桁を設置し、前記仮設橋脚と仮設桁により軌道を仮受けし、次いで本設橋脚を設置するとともに前記複数の仮設桁どうしを添接部材によって連結しかつ補強桁により補強することにより本設桁を形成し、前記本設桁を前記仮設橋脚から前記本設橋脚に受け替え、次いで前記本設橋脚上の仮設桁の添接部材を取り外し、次いで前記仮設橋脚をてっ去することにより、前記仮設桁のうち主桁だけでなく前記横桁も本設桁の一部として利用し、前記本設桁を線路下構造物の一部として利用することを特徴とする。
【0011】
上記した線路下構造物構築工法において、好ましくは、前記補強桁はトラス桁である。
【0012】
また、上記した線路下構造物構築工法において、好ましくは、前記仮設橋脚と前記仮設桁との間に仮支承又は仮支承受桁が設置され、前記仮支承受桁は前記トラス桁の下弦材の一部を構成する。
【0013】
また、上記した線路下構造物構築工法において、好ましくは、前記仮設桁は前記トラス桁の上弦材の一部を構成する。
【0014】
また、上記した線路下構造物構築工法において、好ましくは、前記補強桁は、H形鋼により形成される桁である。
【0015】
また、上記した線路下構造物構築工法において、好ましくは、前記補強桁は、鋼管により形成される桁である。
【0016】
また、上記した線路下構造物構築工法において、好ましくは、前記鋼管の内部には、コンクリートが充填されて補強される。
【0017】
【発明の実施の形態】
以下、本発明の実施形態について、図面を参照しながら詳細に説明する。
【0018】
(1)第1実施形態
図1は、本発明の第1実施形態である線路下構造物構築工法の手順を示す概念図である。また、図2は、図1に示す線路下構造物構築工法における各部の詳細な構成を示す図である。
【0019】
第1実施形態の線路下構造物構築工法の場合は、まず、図7(A)に示すように、線路の近傍、例えば線路側方等に複数の立坑、例えばH1、H2、及びH3を所定の深さまで掘削し、この立坑H1〜H3の内部に、仮設橋脚、例えば11、12、及び13を設置する。仮設橋脚11〜13は、棒状鋼材、H形鋼、鋼管等からなり、柱状に構成され、立坑の底部の地盤G1により支持される。
【0020】
次に、図1(A)に示すように、各仮設橋脚11、12、13の頂部に、それぞれ仮支承受桁51、52、53を設置し、さらに仮支承受桁51、52、53の上にそれぞれ仮支承61及び62、63及び64、65及び66を載置する。そして、仮支承61等の上に複数の仮設桁、例えば21、22、23、24、25、及び26を設置し、これらの仮設桁21〜26が、仮設橋脚11〜13によって支持されるようにする。仮支承受桁51等は、例えばH形鋼によって構成される。また、仮支承61等は、例えばH形鋼、ブロック状鋼などによって構成される。
【0021】
上記した仮設桁21等の構成は、図7、8に示す従来の仮設桁221等とほぼ同様であるが、仮設桁どうしを連結する添接部材(後述。符号83等を参照。)が取り付け可能なボルト穴等が桁端付近にあらかじめ開設されている点が、従来の仮設桁221等と異なっている。また、仮設桁22と23は添接部材81と添接ボルト(図示を省略)によってあらかじめ連結されており、同様に仮設桁25と26は添接部材82と添接ボルト(図示を省略)によってあらかじめ連結されている。添接部材81、82は、鋼板に所定のボルト挿通孔が開設されたもの等が用いられる。
【0022】
仮設橋脚12における上記の状態を拡大して示した図が図2(A)である。図2(A)に示すように、仮設桁23の図における左端付近は仮支承63によって単純支持されている。また、仮設桁24の図における右端付近は仮支承64によって単純支持されている。他の仮設橋脚11、13も同様の構成となっている。
【0023】
次に、図1(A)に示す状態で、上記した仮設橋脚11〜13と仮設桁21〜26などにより、軌道を仮受けし、列車荷重や軌きょう自重等を仮設橋脚11〜13と仮設桁21〜26などにより支持する。
【0024】
次に、上記のように仮設橋脚11〜13と仮設桁21〜26などにより軌きょうが仮受けされている状態で、線路下の地盤G2を掘削し、本設橋脚、例えば31、32を設置する。本設橋脚31等は、例えばコンクリート構造物等によって構成される。
【0025】
次に、図1(B)に示すように、複数の仮設桁どうし、例えば仮設桁23と24、仮設桁24と25は、それぞれ添接部材83、84と添接ボルト(図示を省略)によって互いに連結される。添接部材83、84の構成は、添接部材81、82の場合と同様である。また、この連結作業と並行して、仮設桁23、24、25の下方に補強トラス桁42が取り付けられる。同様にして、仮設桁21などの下方に補強トラス桁41が取り付けられ、仮設桁26などの下方に補強トラス桁43が取り付けられる。
【0026】
仮設橋脚12付近における補強トラス桁42の構成を拡大して示した図が図2(B)である。図2(B)に示すように、仮設橋脚12上の仮支承受桁52は、補強トラス桁42の下弦材の一部を構成している。仮支承受桁52の右方には、補強トラス桁42の下弦材の他の部分を構成するトラス部材42aが添接部材85と添接ボルト(図示を省略)によって接合されている。また、仮支承受桁52の左方には、補強トラス桁42の下弦材のさらに他の部分を構成するトラス部材42bが添接部材86と添接ボルト(図示を省略)によって接合されている。添接部材85、86の構成は、添接部材81、82の場合と同様である。
【0027】
また、仮支承受桁52と仮設桁23の間には、補強トラス桁42の斜材の一部を構成するトラス部材42cが添接部材(図示を省略)と添接ボルトB1、B2によって接合されている。また、仮支承受桁52と仮設桁24の間には、補強トラス桁42の斜材の他の部分を構成するトラス部材42dが添接部材(図示を省略)と添接ボルトB3、B4によって接合されている。また、トラス部材42aと仮設桁23の間には、補強トラス桁42の斜材のさらに他の部分を構成するトラス部材42eが添接部材(図示を省略)と添接ボルトB5、B6によって接合されている。また、トラス部材42bと仮設桁24の間には、補強トラス桁42の斜材のさらに他の部分を構成するトラス部材42fが添接部材(図示を省略)と添接ボルトB7、B8によって接合されている。補強トラス桁42における仮設橋脚13の付近も同様の構成となっている。これらの図示しない添接部材の構成は、添接部材81、82の場合と同様である。
【0028】
上記のような構成により、添接部材83及び84によって連結された仮設桁23及び24及び25は、補強トラス桁42によって下方が補強され、全体としての桁長(桁スパン)が延長されている。また、連結された仮設桁23及び24及び25が、補強トラス桁42を含む大きなトラスの上弦材を構成している。これにより、連結された仮設桁23及び24及び25と、補強トラス桁42が、全体として大きなトラス状の桁(以下、「本設桁」という。)72を形成している。図1(B)における本設橋脚31の右側、図1(B)における本設橋脚32の左側についても同様に、連結された仮設桁22等と下方の補強トラス桁41、連結された仮設桁26等と下方の補強トラス桁43が、それぞれ、大きなトラス状の本設桁71、73を形成している。
【0029】
次に、上記の状態で、本設桁71〜73どうしの連結部、例えば添接部材81の位置、あるいは添接部材82の位置が、本設橋脚31、32により支持されるようにする。また、図2(C)に示すように、仮設橋脚12の最上部の垂直部材12a及び12bを取り外し、仮設橋脚12が仮支承受桁52を支持しないようにする。同様にして、仮設橋脚13が仮支承受桁53を支持しないようにする。これにより、仮設橋脚12等から、本設橋脚31等への受け替えが行われる。この受け替えにより、列車荷重や軌きょう自重等は、本設桁72等と本設橋脚31、32等と本設橋脚下の地盤G3により支持されるようになる。
【0030】
次に、本設橋脚31、32の上の本設桁71〜73どうしの連結部における添接部材、例えば添接部材81、あるいは添接部材82の添接ボルトを緩めてはずし、添接部材81及び82を取り外す。この作業と並行して、仮設橋脚12及び13をてっ去する。これにより、図1(C)に図示する状態となる。その後、軌道の形状(平面形状、水準高低等)は所定の精度範囲内となるように整正され復旧される。図1(C)において、本設桁72等と本設橋脚31等は、線路下構造物を構成している。
【0031】
第1実施形態の線路下構造物構築工法は、上記したような手順によって行われるため、以下のような利点を有している。
【0032】
a)仮設桁を補強して本設桁を形成し、この本設桁を線路下構造物の一部として利用することになるため、従来のような仮設専用の桁は不要となり、仮設と本設の両機能を発揮させることができる。このため、従来のような工事桁は不要となり、工事桁製作費用と工事桁てっ去費用が不要となるため、工事費用を低減することできる。
【0033】
b)従来のような工事桁てっ去作業が不要となるため、その分の工事期間を短縮することができる。
【0034】
(2)第2実施形態
本発明は、上記した第1実施形態以外の構成によっても実現可能である。図3は、本発明の第2実施形態である線路下構造物構築工法の内容を説明する図である。また、図4は、本発明の第2実施形態である線路下構造物構築工法に用いるH形鋼補強桁の構成を示す図である。
【0035】
第2実施形態の線路下構造物構築工法の場合は、まず、線路の近傍に複数の仮設橋脚を設置する。この仮設橋脚の設置方法は、上記した第1実施形態の場合とまったく同様である。次に、図3(A)に示すように、仮設橋脚(例えば符号12)の頂部に、仮支承受桁(例えば符号52A)を設置し、さらに仮支承受桁52A等の上に仮支承(例えば符号63A及び64A)を載置する。そして、仮支承63A等の上に複数の仮設桁(例えば符号23及び24)を設置し、仮設桁23等が、仮設橋脚12等によって支持されるようにする。仮支承受桁52A等は、H形鋼によって構成される。また、仮支承63A、64Aは、H形鋼からなる桁であり、添接部材(図示を省略)と添接ボルトB11、B13によって仮支承受桁52Aに接合され、仮設桁23、24に対して直角方向となるように並べて配置されている。
【0036】
次に、図3(A)に示す状態で、上記した仮設橋脚12等と仮設桁23等により、軌道を仮受けし、列車荷重や軌きょう自重等を仮設橋脚12等と仮設桁23等により支持する。
【0037】
次に、上記のように仮設橋脚12等と仮設桁23等により軌きょうが仮受けされている状態で、線路下の地盤を掘削し、本設橋脚(図4における符号31、32を参照。)を設置する。本設橋脚31等は、例えばコンクリート構造物等によって構成される。
【0038】
次に、図3(B)に示すように、複数の仮設桁どうし、例えば仮設桁23と24を、それぞれ添接部材(例えば符号83A)と添接ボルト(図示を省略)によって互いに連結される。添接部材83Aの構成は、上記した添接部材81等の場合と同様である。また、図4に示すように、仮設桁どうしの連結作業と並行して、仮設桁23、24、25などの下方にH形鋼補強桁92が取り付けられる。
【0039】
図3(B)に示すように、仮設橋脚12上の仮支承受桁52Aは、H形鋼補強桁92の下部(下フランジ又は下弦材に相当する部材)の一部を構成している。仮支承受桁52Aの右方には、H形鋼補強桁92の下部の他の部分を構成するH形鋼桁部材92aが添接部材85Aと添接ボルト(図示を省略)によって接合されている。また、仮支承受桁52Aの左方には、H形鋼補強桁92の下部のさらに他の部分を構成するH形鋼桁部材92bが添接部材86Aと添接ボルト(図示を省略)によって接合されている。添接部材85A、86Aの構成は、添接部材81等の場合と同様である。
【0040】
また、仮支承受桁52Aと仮設桁23の間には、H形鋼補強桁92の腹部の一部を構成するH形鋼桁部材67Aが添接部材(図示を省略)と添接ボルトB15、B16によって接合されている。また、仮支承受桁52Aと仮設桁24の間には、H形鋼補強桁92の腹部の他の一部を構成するH形鋼桁部材68Aが添接部材(図示を省略)と添接ボルトB17、B18によって接合されている。また、仮支承63Aは、H形鋼補強桁92の腹部の他の一部を構成し、その上部は、添接部材(図示を省略)と添接ボルトB12によって接合されている。また、仮支承64Aは、H形鋼補強桁92の腹部の他の一部を構成し、その上部は、添接部材(図示を省略)と添接ボルトB14によって接合されている。これらの図示しない添接部材の構成は、添接部材81の場合と同様である。
【0041】
上記のような構成により、図4に示すように、添接部材83A等によって連結された仮設桁23及び24及び25は、H形鋼補強桁92によって下方が補強され、全体としての桁長(桁スパン)が延長されている。また、連結された仮設桁23及び24及び25が、H形鋼補強桁92を含む大きな桁の上部(上フランジ又は上弦材に相当する部材)を構成している。これにより、連結された仮設桁23及び24及び25と、H形鋼補強桁92が、全体として大きな桁(以下、「本設桁」という。)74を形成している。図4における本設橋脚31の右側、図4における本設橋脚32の左側についても、図示はしていないが、上記と同様に、連結された仮設桁22等と下方のH形鋼補強桁、連結された仮設桁26等と下方のH形鋼補強桁が、それぞれ、大きな桁状の本設桁を形成している。
【0042】
次に、上記の状態で、本設桁(例えば符号74)どうしの連結部、例えば図4におけるP1の位置、あるいは図4におけるP2の位置が、本設橋脚31、32により支持されるようにする。また、図3(C)に示すように、仮設橋脚12の最上部の垂直部材12a及び12bを取り外し、仮設橋脚12が仮支承受桁52Aを支持しないようにする。同様にして、他の仮設橋脚が他の仮支承受桁を支持しないようにする。これにより、仮設橋脚12等から、本設橋脚31等への受け替えが行われる。この受け替えにより、列車荷重や軌きょう自重等は、本設桁74等と本設橋脚31、32等と本設橋脚下の地盤により支持されるようになる。
【0043】
次に、本設橋脚31、32の上の本設桁どうしの連結部における添接部材(図示せず)の添接ボルトを緩めてはずし、添接部材を取り外す。この作業と並行して、仮設橋脚12等をてっ去する。これにより、図4に図示する状態となる。その後、軌道の形状(平面形状、水準高低等)は所定の精度範囲内となるように整正され復旧される。図4において、本設桁74等と本設橋脚31等は、線路下構造物を構成している。
【0044】
第2実施形態の線路下構造物構築工法は、上記したような手順によって行われるため、第1実施形態の場合とまったく同様の利点を有している。
【0045】
(3)第3実施形態
本発明は、上記した第1、2実施形態以外の構成によっても実現可能である。図5は、本発明の第3実施形態である線路下構造物構築工法における本設桁の構成を示す横断面図である。
【0046】
第3実施形態の線路下構造物構築工法が第1、2実施形態の線路下構造物構築工法と異なる点は、第2実施形態におけるH形鋼桁部材92a等のかわりに、H形鋼からなる主桁部材102aを用い、第2実施形態におけるH形鋼桁部材67A等のかわりに、H形鋼からなる垂直部材102bを用い、軌道の左右両側の主桁部材(例えば符号102a)どうしを横桁部材102cにより連結することにより、補強桁102を構成し、仮設桁23等と合成することにより本設桁75を構成している点である。
【0047】
第3実施形態の線路下構造物構築工法の施工手順は、第2実施形態の場合とほぼ同様である。異なる点は、仮支承63A等のかわりに、垂直部材102bと同様な構成の仮支承を用いる点である。また、埋設型枠102dを用いて軌道の下方を被覆し、埋設型枠102dの内部にコンクリート102eを打設して上床版の機能を発揮させるようにしてもよい。
【0048】
図5に示すように、仮設桁23は、鋼材等からなるI形断面等の主桁311及び312を有し、主桁311、312は、軌道の両側に沿って設置され、桁の中心軸方向が軌道の長手方向と略平行となるように配置される。各主桁311、312の軌道側には、鋼材等からなる横桁固定用部材314、315が取り付けられており、これらにより、鋼材等からなる横桁313が支持されている。横桁313の横断面は、上記した仮設桁221の場合と同様に略「U」字状又は樋状となっており、この横桁313の内部の溝状の空間に、まくらぎTが抱き込まれるようにして収容されるようになっている。まくらぎTは、レールR1及びR2を支持している。
【0049】
この第3実施形態の線路下構造物構築工法においても、第1、2実施形態の場合とまったく同様の利点を有している。
【0050】
(4)第4実施形態
本発明は、上記した第1〜3実施形態以外の構成によっても実現可能である。図6は、本発明の第4実施形態である線路下構造物構築工法に用いる鋼管補強桁の構成を示す図である。
【0051】
第4実施形態の線路下構造物構築工法が第1〜3実施形態の線路下構造物構築工法と異なる点は、補強桁として、鋼管により鋼管補強桁112を構成し、仮設桁23等と合成することにより本設桁76を構成している点である。
【0052】
第4実施形態の線路下構造物構築工法の施工手順は、第3実施形態の場合とほぼ同様である。異なる点は、主桁部材102aのかわりに、鋼管桁112aを用い、仮支承63Aや垂直部材102b等のかわりに、垂直部材112b、112cと同様な構成の部材を用いる点である。また、鋼管桁112aの内部にコンクリートを打設して強度をさらに増大させるように構成してもよい。
【0053】
図6において、符号112dは、コンクリート部材を示しており、上床版の機能を発揮するように構成されている。また、符号112eは鋼管桁112aに対して直角方向となるように並べて配置された並列桁であり、H形鋼等により形成される。
【0054】
この第4実施形態の線路下構造物構築工法においても、第1〜3実施形態の場合とまったく同様の利点を有している。
【0055】
なお、本発明は、上記各実施形態に限定されるものではない。上記各実施形態は、例示であり、本発明の特許請求の範囲に記載された技術的思想と実質的に同一な構成を有し、同様な作用効果を奏するものは、いかなるものであっても本発明の技術的範囲に包含される。
【0056】
例えば、上記各実施形態におけるH形鋼、鋼管などのかわりに、「ロ」字状断面を有する鋼材、「日」字状断面を有する鋼材、「田」字状断面を有する鋼材等を用いてもよい。
【0057】
また、鋼管等の内部にコンクリートを打設するだけでなく、適宜の鉄筋、鉄骨部材、強化用繊維部材、PC鋼線、PC鋼棒等、又はこれらの適宜の組み合わせをコンクリート内に埋設配置し、適宜にプレストレスを導入するように構成してもよい。
【0058】
また、補強桁の構造形式としては、上記した桁形式のほか、アーチ桁、I形断面ビーム桁、方杖構造、各種ラーメン構造等を採用してもよい。
【0059】
【発明の効果】
以上説明したように、本発明によれば、複数の仮設橋脚を線路近傍に設置した後、仮設橋脚により支持される複数の仮設桁を設置し、仮設橋脚と仮設桁により軌道を仮受けし、次いで本設橋脚を設置するとともに複数の仮設桁どうしを添接部材によって連結しかつ補強桁により補強することにより本設桁を形成し、本設桁を仮設橋脚から本設橋脚に受け替え、次いで本設橋脚上の仮設桁の添接部材を取り外し、次いで仮設橋脚をてっ去することにより、本設桁を線路下構造物の一部として利用するように構成したので、従来のような仮設専用の桁は不要となり、仮設と本設の両機能を発揮させることができる。このため、従来のような工事桁は不要となり、工事桁製作費用と工事桁てっ去費用が不要となるため、工事費用を低減することできる、という利点を有している。また、従来のような工事桁てっ去作業が不要となるため、その分の工事期間を短縮することができる、という利点も有している。
【図面の簡単な説明】
【図1】本発明の第1実施形態である線路下構造物構築工法の手順を示す概念図である。
【図2】図1に示す線路下構造物構築工法における各部の詳細な構成を示す図である。
【図3】本発明の第2実施形態である線路下構造物構築工法の内容を説明する図である。
【図4】本発明の第2実施形態である線路下構造物構築工法に用いるH形鋼補強桁の構成を示す図である。
【図5】本発明の第3実施形態である線路下構造物構築工法における本設桁の構成を示す横断面図である。
【図6】本発明の第4実施形態である線路下構造物構築工法に用いる鋼管補強桁の構成を示す図である。
【図7】従来の線路下構造物構築工法の手順を示す概念図である。
【図8】図7に示す線路下構造物構築工法における仮設桁の詳細な構成を示す図である。
【符号の説明】
11、12 仮設橋脚
12a、12b 垂直部材
13、14 仮設橋脚
21〜26 仮設桁
31、32 本設橋脚
41 補強桁
42 補強トラス桁
42a〜42f トラス部材
43 補強桁
51〜53、51A 仮支承受桁
61〜66、61A〜64A 仮支承
67A、68A H形鋼桁部材
71〜76 本設桁
81〜86、83A〜86A 添接部材
92 H形鋼補強桁
92a、92b H形鋼桁部材
102 補強桁
102a 主桁部材
102b 垂直部材
102c 横桁部材
102d 埋設型枠
102e コンクリート
112 鋼管補強桁
112a 鋼管桁
112b、112c 垂直部材
112d コンクリート床版部
112e 並列桁
221〜225 仮設桁
271〜273 本設桁
311、312 主桁
313 横桁
314、315 横桁固定用部材
411、412 主桁
413 横桁
414、415 横桁固定用部材
B1〜B18 添接ボルト
G1〜G3 地盤
H1〜H4 立坑
R1、R2 レール
T まくらぎ
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method of constructing a structure under a railroad track, and in particular, as a part of a structure under the track, forming a temporary girder by reinforcing a temporary girder used for excavation of ground under the railroad or the like. The present invention relates to a method of constructing under-track structures to be used.
[0002]
[Prior art]
Conventionally, structures such as tunnels and culverts that run below railway tracks (hereinafter referred to as “hot lines”) that operate in the railway business (hereinafter referred to as “under-track structures”) are constructed. In such a case, a construction method as shown in FIG. 7 has been adopted.
[0003]
In this case, first, as shown in FIG. 7A, a plurality of shafts, for example, H1, H2, H3, and H4 are excavated to a predetermined depth in the vicinity of the track, for example, on the side of the track. Temporary bridge piers, for example, 11, 12, 13, and 14, are installed inside H1 to H4. The temporary piers 11 to 14 are made of steel or the like, are configured in a columnar shape, and are supported by the ground G1 at the bottom of the shaft. Thereafter, a plurality of temporary girders, for example, 221, 222, 223, 224, and 225, are installed near the track, and these temporary girders 221 to 225 are supported by the temporary piers 11 to 14 (for example, both ends of each temporary girders). Simple support). The temporary girder 221 and the like are also called construction girder.
[0004]
Next, as shown in FIG. 7B, the track is temporarily received by the above-mentioned temporary bridge piers 11 to 14 and the temporary girders 221 to 225, and the train load and the gauge (including rails and sleepers, etc.) are provided. The weight of the ladder-like structure) is supported by the temporary piers 11 to 14 and the temporary girders 221 to 225.
[0005]
FIG. 8 is a diagram showing a detailed configuration of the temporary girder, and FIG. 8A is a cross-sectional view showing a relationship between the temporary girder 221 and the rail. As shown in FIG. 8A, the temporary girder 221 has main girders 411 and 412 having an I-shaped cross section made of steel or the like, and the main girders 411 and 412 are installed along both sides of the track. Are arranged so that the center axis direction of the track is substantially parallel to the longitudinal direction of the track. Cross girder fixing members 414 and 415 made of steel or the like are attached to the track sides of the main girders 411 and 412, and these support the cross girder 413 made of steel or the like. The cross section of the cross beam 413 has a substantially “U” shape or a gutter shape as shown in FIG. 8B, and the sleeper T is embraced in the groove-shaped space inside the cross beam 413. It is housed in such a way that The sleeper T supports the rails R1 and R2.
[0006]
Next, under the condition that the gages are temporarily received by the temporary piers 11 to 14 and the temporary girders 221 to 225 as described above, the ground G2 under the track is excavated, and the permanent piers, for example, 31 and 32 are installed. I do. The main pier 31 and the like are constituted by, for example, a concrete structure or the like. When the permanent pier 31 or the like is installed, next, a permanent girder, for example, 271, 272, 273, or the like is installed, and these permanent girders 271 to 273 are supported by the permanent piers 31 and 32 (for example, Simple support at both ends of each temporary girder).
[0007]
Next, as shown in FIG. 7C, the track (gauge) is changed from the temporary girder 221 or the like to the permanent girder 271 or the like. As a result, the train load, the gauge's own weight, and the like are supported by the permanent girder 271 and the like, the permanent pier 31 and the like, and the ground G3 below the permanent pier. After the replacement step, the temporary girder 221 and the like are removed, and the shape (planar shape, level, etc.) of the track is adjusted and restored to be within a predetermined accuracy range. In FIG. 7C, reference numeral RL indicates the position of the top surface of the rail R1 or the like shown in FIG. 8A. In FIG. 7C, the permanent girder 271 and the permanent pier 31 and the like constitute an under-track structure.
[0008]
[Problems to be solved by the invention]
However, in the above-mentioned conventional under-track structure construction method, once the temporary girder is installed near the track to construct the under-track structure, the installed temporary girder is removed, and the track is restored. There is a need. The installation and removal of temporary girder on livelines requires a great deal of labor, such as night work to ensure the safety of train operation, and the need to make every effort to ensure security measures. The cost was also expensive. Further, the temporary girder itself is not a permanent structure, and can be diverted several times, but the production cost is extra construction cost. In addition, there was a problem that the entire construction period would be extended by the removal of the temporary girder.
[0009]
The present invention has been made in order to solve the above problems, and an object of the present invention is to provide a construction method capable of forming a permanent girder using a temporary girder and constructing an under-track structure. Is to do.
[0010]
[Means for Solving the Problems]
In order to solve the above-mentioned problems, the under-track structure construction method according to the present invention includes installing a plurality of temporary piers near the track, installing a plurality of temporary girders supported by the temporary piers, The track is temporarily received by the temporary girder, and then a permanent pier is installed, and the plurality of temporary girderes are connected to each other by an attachment member and reinforced by a reinforcing girder to form a permanent girder. By replacing the temporary pier with the permanent pier, then removing the attachment member of the temporary girder on the permanent pier, and then removing the temporary pier, not only the main girder of the temporary girder, The horizontal girder is also used as a part of the main girder, and the main girder is used as a part of the under-track structure.
[0011]
In the above-mentioned under-track structure construction method, preferably, the reinforcing girder is a truss girder.
[0012]
Further, in the above-described under-track structure construction method, preferably, a temporary bearing or a temporary bearing girder is installed between the temporary pier and the temporary girder, and the temporary bearing girder is a lower chord material of the truss girder. Make up part.
[0013]
In the above-mentioned under-track structure construction method, preferably, the temporary girder forms a part of the upper chord material of the truss girder.
[0014]
In the above-mentioned under-track structure construction method, preferably, the reinforcing girder is a girder made of H-section steel.
[0015]
In the above-mentioned under-track structure construction method, preferably, the reinforcing girder is a girder formed of a steel pipe.
[0016]
Further, in the above-described under-track structure construction method, preferably, the inside of the steel pipe is filled with concrete and reinforced.
[0017]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
[0018]
(1) First embodiment
FIG. 1 is a conceptual diagram showing the procedure of the under-track structure construction method according to the first embodiment of the present invention. FIG. 2 is a diagram showing a detailed configuration of each part in the under-track structure construction method shown in FIG.
[0019]
In the case of the under-track structure construction method according to the first embodiment, first, as shown in FIG. 7A, a plurality of shafts, for example, H1, H2, and H3 are provided in the vicinity of the track, for example, on the side of the track. And temporary piers, for example, 11, 12, and 13, are installed inside the shafts H1 to H3. The temporary piers 11 to 13 are made of a bar-shaped steel material, an H-shaped steel, a steel pipe, or the like, are configured in a columnar shape, and are supported by the ground G1 at the bottom of the shaft.
[0020]
Next, as shown in FIG. 1 (A), temporary support receiving girders 51, 52, and 53 are installed on the tops of the temporary piers 11, 12, and 13, respectively. The temporary bearings 61 and 62, 63 and 64, 65 and 66 are placed thereon. Then, a plurality of temporary girders, for example, 21, 22, 23, 24, 25, and 26 are installed on the temporary bearing 61 or the like, and these temporary girders 21 to 26 are supported by the temporary piers 11 to 13. To The temporary support receiving girder 51 and the like are made of, for example, H-shaped steel. The temporary bearing 61 and the like are made of, for example, H-shaped steel, block-shaped steel, or the like.
[0021]
The configuration of the temporary girder 21 and the like is substantially the same as that of the conventional temporary girder 221 shown in FIGS. 7 and 8, but an attachment member (refer to a reference numeral 83 and the like described later) for connecting the temporary girder is attached. The difference from the conventional temporary girder 221 and the like is that possible bolt holes and the like are provided in advance near the end of the girder. Further, the temporary girders 22 and 23 are connected in advance by an attaching member 81 and an attaching bolt (not shown), and similarly, the temporary girders 25 and 26 are joined by an attaching member 82 and an attaching bolt (not shown). Pre-connected. As the attachment members 81 and 82, a member having a predetermined bolt insertion hole formed in a steel plate or the like is used.
[0022]
FIG. 2A is an enlarged view of the above state of the temporary pier 12. As shown in FIG. 2A, the vicinity of the left end of the temporary girder 23 in the drawing is simply supported by the temporary bearing 63. Further, the vicinity of the right end of the temporary girder 24 in the drawing is simply supported by a temporary bearing 64. The other temporary bridge piers 11 and 13 have the same configuration.
[0023]
Next, in the state shown in FIG. 1 (A), the track is temporarily received by the above-mentioned temporary piers 11 to 13 and the temporary girders 21 to 26, and the train load, the gauge weight and the like are temporarily connected to the temporary piers 11 to 13. It is supported by girders 21 to 26 and the like.
[0024]
Next, the ground G2 under the track is excavated in a state where the gages are temporarily received by the temporary piers 11 to 13 and the temporary girders 21 to 26 as described above, and permanent piers, for example, 31 and 32 are installed. I do. The main pier 31 and the like are constituted by, for example, a concrete structure or the like.
[0025]
Next, as shown in FIG. 1 (B), a plurality of temporary girders, for example, temporary girders 23 and 24 and temporary girders 24 and 25, are respectively attached by attaching members 83 and 84 and attaching bolts (not shown). Linked to each other. The configuration of the attachment members 83 and 84 is the same as that of the attachment members 81 and 82. In parallel with this connection work, a reinforcing truss girder 42 is attached below the temporary girder 23, 24, 25. Similarly, a reinforcing truss girder 41 is attached below the temporary girder 21 and a reinforcing truss girder 43 is attached below the temporary girder 26 and the like.
[0026]
FIG. 2B is an enlarged view of the configuration of the reinforcing truss girder 42 near the temporary pier 12. As shown in FIG. 2B, the temporary support girder 52 on the temporary pier 12 constitutes a part of the lower chord material of the reinforcing truss girder 42. A truss member 42a constituting another portion of the lower chord member of the reinforcing truss girder 42 is joined to the right side of the temporary bearing girder 52 by an attachment member 85 and an attachment bolt (not shown). Further, a truss member 42b, which constitutes another portion of the lower chord member of the reinforcing truss girder 42, is joined to the left side of the temporary bearing girder 52 by an additional member 86 and an additional bolt (not shown). . The configuration of the attachment members 85 and 86 is the same as that of the attachment members 81 and 82.
[0027]
A truss member 42c, which constitutes a part of the diagonal member of the reinforcing truss girder 42, is connected between the temporary support receiving girder 52 and the temporary girder 23 by an auxiliary member (not shown) and auxiliary bolts B1, B2. Have been. A truss member 42d, which constitutes another part of the diagonal member of the reinforcing truss girder 42, is provided between the temporary support receiving girder 52 and the temporary girder 24 by an attachment member (not shown) and attachment bolts B3, B4. Are joined. In addition, between the truss member 42a and the temporary girder 23, a truss member 42e constituting still another part of the diagonal member of the reinforcing truss girder 42 is joined by an attachment member (not shown) and attachment bolts B5 and B6. Have been. Further, between the truss member 42b and the temporary girder 24, a truss member 42f constituting still another portion of the diagonal member of the reinforcing truss girder 42 is joined by an auxiliary member (not shown) and auxiliary bolts B7, B8. Have been. The vicinity of the temporary pier 13 in the reinforcing truss girder 42 has the same configuration. The configuration of the attachment members (not shown) is the same as that of the attachment members 81 and 82.
[0028]
With the above configuration, the temporary girder 23, 24, and 25 connected by the abutment members 83 and 84 are reinforced at the lower part by the reinforcing truss girder 42, and the overall girder length (girder span) is extended. . The connected temporary girders 23, 24 and 25 constitute the upper chord of the large truss including the reinforcing truss girders 42. As a result, the connected temporary girders 23, 24 and 25 and the reinforcing truss girders 42 form a large truss-like girder (hereinafter referred to as "main girders") 72 as a whole. Similarly, on the right side of the permanent pier 31 in FIG. 1B and on the left side of the permanent pier 32 in FIG. 1B, the connected temporary girder 22 and the like, the lower reinforcing truss girder 41, and the connected temporary girder are connected. 26 and the lower reinforcing truss girders 43 form large truss-like permanent girders 71 and 73, respectively.
[0029]
Next, in the above state, the connecting portions of the permanent girders 71 to 73, for example, the position of the contact member 81 or the position of the contact member 82 are supported by the permanent piers 31 and 32. Further, as shown in FIG. 2C, the uppermost vertical members 12a and 12b of the temporary pier 12 are removed so that the temporary pier 12 does not support the temporary support girder 52. Similarly, the temporary pier 13 does not support the temporary support receiving girder 53. As a result, replacement from the temporary pier 12 or the like to the permanent pier 31 or the like is performed. By this exchange, the train load, the gauge weight and the like are supported by the permanent girder 72 and the like, the permanent piers 31 and 32, and the ground G3 below the permanent pier.
[0030]
Next, at the connecting portion between the permanent girders 71 to 73 on the permanent piers 31 and 32, the attachment bolts of the attachment member 81, for example, the attachment member 81 or the attachment member 82 are loosened and removed. Remove 81 and 82. In parallel with this work, the temporary piers 12 and 13 are removed. Thus, the state shown in FIG. 1C is obtained. Thereafter, the shape of the trajectory (planar shape, level height, etc.) is corrected and restored so as to be within a predetermined accuracy range. In FIG. 1C, the permanent girder 72 and the permanent pier 31 and the like constitute a structure under the track.
[0031]
The under-track structure construction method of the first embodiment has the following advantages because it is performed according to the above-described procedure.
[0032]
a) A temporary girder is reinforced to form a permanent girder, and the permanent girder is used as a part of a structure under the track. Therefore, a special temporary girder as in the related art is unnecessary, and the temporary girder and the main girder are not used. Both functions can be exhibited. For this reason, the conventional construction girder becomes unnecessary, and the construction girder manufacturing cost and the construction girder stripping cost become unnecessary, so that the construction cost can be reduced.
[0033]
b) The necessity for the stripping work of the construction girder as in the prior art is unnecessary, so that the construction period can be shortened accordingly.
[0034]
(2) Second embodiment
The present invention can be realized by a configuration other than the above-described first embodiment. FIG. 3 is a diagram illustrating the contents of the under-track structure construction method according to the second embodiment of the present invention. FIG. 4 is a diagram showing a configuration of an H-shaped steel reinforcing girder used in the under-track structure construction method according to the second embodiment of the present invention.
[0035]
In the case of the under-track structure construction method of the second embodiment, first, a plurality of temporary piers are installed near the track. The method of installing the temporary pier is exactly the same as that of the first embodiment. Next, as shown in FIG. 3 (A), a temporary support girder (for example, reference numeral 52A) is installed on the top of a temporary pier (for example, reference numeral 12), and a temporary support girder (for example, reference numeral 52A) is placed on the temporary support girder 52A or the like. For example, reference numerals 63A and 64A) are placed. Then, a plurality of temporary girders (for example, reference numerals 23 and 24) are installed on the temporary bearing 63A or the like, and the temporary girders 23 or the like are supported by the temporary pier 12 or the like. The temporary bearing support beams 52A and the like are made of H-shaped steel. The temporary bearings 63A and 64A are girders made of H-shaped steel, and are joined to the temporary bearing receiving girder 52A by attaching members (not shown) and attaching bolts B11 and B13. Are arranged side by side so as to be at right angles.
[0036]
Next, in the state shown in FIG. 3A, the track is temporarily received by the above-mentioned temporary bridge piers 12 and the temporary girder 23 and the like, and the train load and the gauge's own weight are reduced by the temporary bridge piers 12 and the temporary girder 23 and the like. To support.
[0037]
Next, the ground under the track is excavated in a state where the gauge is temporarily received by the temporary pier 12 and the temporary girder 23 as described above, and the permanent pier (see reference numerals 31 and 32 in FIG. 4). ). The main pier 31 and the like are constituted by, for example, a concrete structure or the like.
[0038]
Next, as shown in FIG. 3B, a plurality of temporary girders, for example, temporary girders 23 and 24, are connected to each other by an attaching member (for example, reference numeral 83A) and an attaching bolt (not shown). . The configuration of the attachment member 83A is the same as that of the attachment member 81 described above. As shown in FIG. 4, an H-shaped steel reinforcing girder 92 is attached below the temporary girder 23, 24, 25, etc., in parallel with the work of connecting the temporary girder.
[0039]
As shown in FIG. 3B, the temporary bearing girder 52 </ b> A on the temporary pier 12 forms a part of a lower portion (a member corresponding to a lower flange or a lower chord) of the H-shaped steel reinforcing girder 92. An H-shaped steel girder member 92a, which is another part of the lower part of the H-shaped steel reinforcing girder 92, is joined to the right side of the temporary bearing receiving girder 52A by an additional member 85A and an additional bolt (not shown). I have. On the left side of the temporary bearing girder 52A, an H-shaped steel girder member 92b constituting a further lower part of the H-shaped steel reinforcing girder 92 is attached by an attachment member 86A and an attachment bolt (not shown). Are joined. The configuration of the attachment members 85A and 86A is the same as that of the attachment member 81 and the like.
[0040]
Further, between the temporary support receiving girder 52A and the temporary girder 23, an H-shaped steel girder member 67A constituting a part of the abdomen of the H-shaped steel reinforcing girder 92 has an auxiliary member (not shown) and an additional bolt B15. , B16. Further, between the temporary support receiving girder 52A and the temporary girder 24, an H-shaped steel girder member 68A constituting another part of the abdomen of the H-shaped steel reinforcing girder 92 is attached to an auxiliary member (not shown). They are joined by bolts B17 and B18. The temporary bearing 63A forms another part of the abdomen of the H-shaped steel reinforcing girder 92, and the upper part thereof is joined to an attachment member (not shown) by an attachment bolt B12. The temporary bearing 64A forms another part of the abdomen of the H-shaped steel reinforcing girder 92, and the upper part thereof is joined to an attachment member (not shown) by an attachment bolt B14. The configuration of these attachment members (not shown) is the same as that of the attachment member 81.
[0041]
With the above-described configuration, as shown in FIG. 4, the temporary girder 23, 24, and 25 connected by the attachment member 83 </ b> A or the like are reinforced downward by the H-shaped steel reinforcing girder 92, and the overall girder length ( Girder span) has been extended. Further, the connected temporary girders 23, 24 and 25 constitute the upper part (a member corresponding to the upper flange or the upper chord) of the large girder including the H-shaped steel reinforcing girder 92. As a result, the connected temporary girders 23, 24, and 25 and the H-shaped steel reinforcing girder 92 form a large girder (hereinafter, referred to as "main girders") 74 as a whole. The right side of the permanent pier 31 in FIG. 4 and the left side of the permanent pier 32 in FIG. 4 are also not shown, but similarly to the above, the connected temporary girder 22 and the like and the lower H-shaped steel reinforcing girder, The connected temporary girder 26 and the like and the lower H-shaped steel reinforcing girder respectively form a large girder-shaped permanent girder.
[0042]
Next, in the above-mentioned state, the connection part of the permanent girder (for example, reference numeral 74), for example, the position of P1 in FIG. 4 or the position of P2 in FIG. I do. In addition, as shown in FIG. 3C, the uppermost vertical members 12a and 12b of the temporary pier 12 are removed, so that the temporary pier 12 does not support the temporary bearing girder 52A. Similarly, another temporary bridge pier does not support another temporary bearing girder. As a result, replacement from the temporary pier 12 or the like to the permanent pier 31 or the like is performed. As a result of this exchange, the train load, the gauge's own weight, and the like are supported by the permanent girder 74 and the like, the permanent piers 31 and 32, and the ground under the permanent pier.
[0043]
Next, the attachment bolts of the attachment members (not shown) at the connecting portions of the permanent girders on the permanent piers 31 and 32 are loosened and removed, and the attachment members are removed. In parallel with this work, the temporary pier 12 and the like are removed. This results in the state shown in FIG. Thereafter, the shape of the trajectory (planar shape, level height, etc.) is corrected and restored so as to be within a predetermined accuracy range. In FIG. 4, the permanent girder 74 and the permanent bridge pier 31 and the like constitute an under-track structure.
[0044]
Since the under-track structure construction method of the second embodiment is performed according to the above-described procedure, it has exactly the same advantages as those of the first embodiment.
[0045]
(3) Third embodiment
The present invention can be realized by a configuration other than the first and second embodiments. FIG. 5 is a cross-sectional view showing a configuration of a permanent girder in the under-track structure construction method according to the third embodiment of the present invention.
[0046]
The difference between the under-track structure construction method of the third embodiment and the under-track structure construction method of the first and second embodiments is that, instead of the H-shaped beam girder member 92a and the like in the second embodiment, an H-beam is used. The main girder members (for example, reference numeral 102a) on both the left and right sides of the track are used by using a vertical member 102b made of an H-beam instead of the H-shaped steel girder member 67A or the like in the second embodiment. The reinforcement girder 102 is formed by connecting with the horizontal girder member 102c, and the permanent girder 75 is formed by combining with the temporary girder 23 and the like.
[0047]
The construction procedure of the under-track structure construction method of the third embodiment is almost the same as that of the second embodiment. The difference is that a temporary bearing having the same configuration as the vertical member 102b is used instead of the temporary bearing 63A and the like. Alternatively, the lower part of the track may be covered by using the buried formwork 102d, and concrete 102e may be cast inside the buried formwork 102d to exhibit the function of the upper floor slab.
[0048]
As shown in FIG. 5, the temporary girder 23 has main girders 311 and 312 such as an I-shaped cross-section made of steel or the like, and the main girders 311 and 312 are installed along both sides of the track, and the center axis of the girder. It is arranged so that the direction is substantially parallel to the longitudinal direction of the track. Cross girder fixing members 314 and 315 made of steel or the like are attached to the track sides of the main girders 311 and 312, and these support the cross girder 313 made of steel or the like. The cross section of the cross beam 313 is substantially “U” -shaped or gutter-shaped similarly to the case of the temporary girder 221 described above, and the sleeper T is held in the groove-shaped space inside the cross beam 313. It is to be housed as if it were to be inserted. The sleeper T supports the rails R1 and R2.
[0049]
The under-track structure construction method of the third embodiment has exactly the same advantages as those of the first and second embodiments.
[0050]
(4) Fourth embodiment
The present invention can be realized by configurations other than the above-described first to third embodiments. FIG. 6 is a diagram showing a configuration of a steel pipe reinforcing girder used in the under-track structure construction method according to the fourth embodiment of the present invention.
[0051]
The difference between the under-track structure construction method of the fourth embodiment and the under-track structure construction method of the first to third embodiments is that a steel pipe reinforcing girder 112 is composed of a steel pipe as a reinforcing girder and is combined with the temporary girder 23 and the like. Thus, the permanent girder 76 is constituted.
[0052]
The construction procedure of the under-track structure construction method of the fourth embodiment is almost the same as that of the third embodiment. The difference is that a steel pipe girder 112a is used instead of the main girder member 102a, and a member having the same configuration as the vertical members 112b and 112c is used instead of the temporary bearing 63A and the vertical member 102b. Moreover, you may comprise so that concrete may be cast in the inside of the steel pipe girder 112a and a strength may be further increased.
[0053]
In FIG. 6, reference numeral 112d denotes a concrete member, which is configured to exhibit the function of the upper floor slab. Reference numeral 112e denotes a parallel girder arranged side by side so as to be perpendicular to the steel pipe girder 112a, and is formed of an H-beam or the like.
[0054]
The under-track structure construction method of the fourth embodiment also has exactly the same advantages as those of the first to third embodiments.
[0055]
The present invention is not limited to the above embodiments. Each of the above-described embodiments is merely an example, and has substantially the same configuration as the technical idea described in the claims of the present invention, and any device that has the same operation and effect can be obtained. It is included in the technical scope of the present invention.
[0056]
For example, instead of the H-section steel and the steel pipe in each of the above embodiments, a steel material having a “B” -shaped cross section, a steel material having a “Japanese” -shaped cross section, a steel material having a “D” -shaped cross section, or the like is used. Is also good.
[0057]
In addition to casting concrete inside steel pipes, etc., appropriate reinforcing bars, steel members, reinforcing fiber members, PC steel wires, PC steel rods, etc., or appropriate combinations of these are buried and arranged in concrete. Alternatively, the prestress may be appropriately introduced.
[0058]
Further, as the structural form of the reinforcing girder, in addition to the above-mentioned girder form, an arch girder, an I-shaped beam girder, a cross beam structure, various ramen structures and the like may be adopted.
[0059]
【The invention's effect】
As described above, according to the present invention, after installing a plurality of temporary piers near the track, installing a plurality of temporary girders supported by the temporary pier, temporarily receiving the track by the temporary pier and the temporary girder, Next, a permanent pier is installed, and a plurality of temporary girders are connected to each other by an attachment member and reinforced with a reinforcing girder to form a permanent girder. The temporary girder on the permanent pier was removed, and the temporary pier was removed.Then, the temporary girder was removed and used as part of the under-track structure. No special girder is required, and both temporary and permanent functions can be exhibited. For this reason, the conventional construction girder is not required, and the construction girder manufacturing cost and the construction girder stripping cost are not required, so that there is an advantage that the construction cost can be reduced. In addition, since there is no need to remove the work of the conventional construction girder, there is an advantage that the construction period can be shortened accordingly.
[Brief description of the drawings]
FIG. 1 is a conceptual diagram showing a procedure of a method of constructing a structure under a track according to a first embodiment of the present invention.
FIG. 2 is a diagram showing a detailed configuration of each part in the under-track structure construction method shown in FIG.
FIG. 3 is a diagram illustrating the contents of a method of constructing a structure under a track according to a second embodiment of the present invention.
FIG. 4 is a view showing a configuration of an H-shaped steel reinforcing girder used in a method of constructing an under-track structure according to a second embodiment of the present invention.
FIG. 5 is a cross-sectional view illustrating a configuration of a permanent girder in a method of constructing a structure under a track according to a third embodiment of the present invention.
FIG. 6 is a view showing a configuration of a steel pipe reinforcing girder used in a method of constructing an under-track structure according to a fourth embodiment of the present invention.
FIG. 7 is a conceptual diagram showing a procedure of a conventional under-track structure construction method.
8 is a diagram showing a detailed configuration of a temporary girder in the under-track structure construction method shown in FIG.
[Explanation of symbols]
11,12 Temporary pier
12a, 12b vertical member
13, 14 Temporary pier
21-26 Temporary girder
31, 32 bridge pier
41 Reinforced girder
42 Reinforced truss girder
42a-42f Truss member
43 Reinforced girder
51-53, 51A Temporary bearing receiving girder
61-66, 61A-64A Temporary bearing
67A, 68A H-shaped steel girder members
71 to 76 permanent girder
81-86, 83A-86A Attaching member
92 H-beam reinforced girder
92a, 92b H-beam members
102 Reinforced girder
102a Main girder member
102b vertical member
102c Cross beam member
102d buried formwork
102e concrete
112 Steel pipe reinforcement girder
112a Steel girder
112b, 112c Vertical member
112d concrete slab
112e parallel girder
221-225 Temporary girder
271-273 Built-in girder
311, 312 main girder
313 horizontal girder
314,315 Cross beam fixing member
411, 412 Main girder
413 horizontal girder
414, 415 Cross beam fixing member
B1 to B18 Connecting bolt
G1-G3 ground
H1-H4 shaft
R1, R2 rail
T sleepers

Claims (7)

複数の仮設橋脚を線路近傍に設置した後、前記仮設橋脚により支持される複数の仮設桁を設置し、前記仮設橋脚と、主桁と横桁を有する仮設桁により軌道を仮受けし、次いで本設橋脚を設置するとともに前記複数の仮設桁どうしを添接部材によって連結しかつ補強桁により補強することにより本設桁を形成し、前記本設桁を前記仮設橋脚から前記本設橋脚に受け替え、次いで前記本設橋脚上の仮設桁の添接部材を取り外し、次いで前記仮設橋脚をてっ去することにより、前記仮設桁のうち主桁だけでなく前記横桁も本設桁の一部として利用し、前記本設桁を線路下構造物の一部として利用することを特徴とする線路下構造物構築工法。After a plurality of temporary piers are installed near the track, a plurality of temporary girders supported by the temporary piers are installed, and the track is temporarily received by the temporary piers and a temporary girder having a main girder and cross beams, and then A permanent pier is installed, and the plurality of temporary girders are connected to each other by an attachment member and reinforced by a reinforcing girder to form a permanent girder. The permanent girders are replaced from the temporary piers to the permanent piers. Then, by removing the attachment member of the temporary girder on the permanent pier, and then removing the temporary pier, not only the main girder but also the horizontal girder of the temporary girder as a part of the permanent girder. A method for constructing a structure under a track, wherein the permanent girder is used as a part of a structure under the track. 請求項1記載の線路下構造物構築工法において、
前記補強桁はトラス桁であることを特徴とする線路下構造物構築工法。
In the method of constructing an under-track structure according to claim 1,
The construction method under a track, wherein the reinforcing girder is a truss girder.
請求項2記載の線路下構造物構築工法において、
前記仮設橋脚と前記仮設桁との間に仮支承又は仮支承受桁が設置され、前記仮支承受桁は前記トラス桁の下弦材の一部を構成することを特徴とする線路下構造物構築工法。
In the method for constructing a structure under a track according to claim 2,
A temporary bearing or a temporary bearing girder is installed between the temporary pier and the temporary girder, and the temporary bearing girder constitutes a part of a lower chord of the truss girder. Construction method.
請求項2記載の線路下構造物構築工法において、
前記仮設桁は前記トラス桁の上弦材の一部を構成することを特徴とする線路下構造物構築工法。
In the method for constructing a structure under a track according to claim 2,
The under-track structure construction method, wherein the temporary girder constitutes a part of an upper chord material of the truss girder.
請求項1記載の線路下構造物構築工法において、
前記補強桁は、H形鋼により形成される桁であることを特徴とする線路下構造物構築工法。
In the method of constructing an under-track structure according to claim 1,
The under-track structure construction method, wherein the reinforcing girder is a girder formed of H-section steel.
請求項1記載の線路下構造物構築工法において、
前記補強桁は、鋼管により形成される桁であることを特徴とする線路下構造物構築工法。
In the method of constructing an under-track structure according to claim 1,
The under-rail structure construction method, wherein the reinforcing girder is a girder formed of a steel pipe.
請求項6記載の線路下構造物構築工法において、
前記鋼管の内部には、コンクリートが充填されて補強されることを特徴とする線路下構造物構築工法。
In the method of constructing an under-track structure according to claim 6,
A method for constructing a structure under a track, wherein concrete is filled in the inside of the steel pipe and reinforced.
JP2001219181A 2001-07-19 2001-07-19 Under-track structure construction method Expired - Fee Related JP3569691B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001219181A JP3569691B2 (en) 2001-07-19 2001-07-19 Under-track structure construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001219181A JP3569691B2 (en) 2001-07-19 2001-07-19 Under-track structure construction method

Publications (2)

Publication Number Publication Date
JP2003027423A JP2003027423A (en) 2003-01-29
JP3569691B2 true JP3569691B2 (en) 2004-09-22

Family

ID=19053224

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001219181A Expired - Fee Related JP3569691B2 (en) 2001-07-19 2001-07-19 Under-track structure construction method

Country Status (1)

Country Link
JP (1) JP3569691B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5666329B2 (en) * 2011-02-02 2015-02-12 前田建設工業株式会社 Railway viaduct replacement method
CN103437291B (en) * 2013-08-02 2015-10-21 中交二公局第一工程有限公司 Monolithic water tank precompressed construction technology
JP6180376B2 (en) * 2014-06-23 2017-08-16 首都高速道路株式会社 Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method
CN108708285B (en) * 2018-05-28 2019-09-20 北京市市政工程设计研究总院有限公司 By adjusting temporary rest pier improvement combination beam internal force at bridge method
CN112176892A (en) * 2020-08-24 2021-01-05 甘肃恒通路桥工程有限公司 Temporary supporting device for rigid frame bridge dismantling
CN113718784B (en) * 2021-09-29 2022-06-10 西安建筑科技大学 High-water loess stratum multi-track railway composite overhead system and its construction method

Also Published As

Publication number Publication date
JP2003027423A (en) 2003-01-29

Similar Documents

Publication Publication Date Title
KR100839439B1 (en) Steel structure of ramen bridge that combines substructure and superstructure prefabricated and construction method of ramen bridge using the same
KR101318773B1 (en) T-shaped composite girder segment integrated by i-shaped girder filled with concrete and slab and construction method of slab by prefabrication of the t-shaped composite girder segment
KR101833373B1 (en) Precast modular bridge and its construction method
JP3844743B2 (en) Box girder bridge structure and its construction method
US6988337B1 (en) Means and method for constructing a fully precast top arch overfilled system
JP4002771B2 (en) Continuous girder structure of existing simple girder bridges
KR101112195B1 (en) Steel-concrete composite crossbeam having wire mesh and construction method using the same
JP2005256341A (en) Corrugated steel-plate web u component bridge
KR101232329B1 (en) Integral bridge and construction method using arched and concrete-filled tube
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
JP3595528B2 (en) Under-track structure construction method
KR101300296B1 (en) Rapid cnstruction method of semi-integral abutment bridge using prestressed concrete girder having end diaphragm
KR101705002B1 (en) Prefabricated double composite plate girder bridge and its construction method
JP3569691B2 (en) Under-track structure construction method
JP2004270270A (en) Steel concrete composite floor slab bridge
JP4585614B1 (en) Method for constructing synthetic steel slab bridge, ribbed steel slab, and synthetic steel slab bridge
KR20120053869A (en) Bridge construction method using precast end-block with girder connection member
JP5217428B2 (en) Composite hollow structure of bridge column head or girder end
KR100889140B1 (en) Prefabricated hollow slab and method of constructing it
JP3595517B2 (en) Under-track structure construction method
CN113957993B (en) An assembly system and its construction method
KR102270427B1 (en) Composite rahmen bridge and constructing method thereof
JP2004263501A (en) Beam-column joint structure
KR101293646B1 (en) Bridge construction method using arch support connection member

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040601

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040621

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090625

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100625

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100625

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110625

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110625

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120625

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130625

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140625

Year of fee payment: 10

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees