JP3579807B2 - Method of reducing lateral pressure on underground structures in aerial landfill method - Google Patents
Method of reducing lateral pressure on underground structures in aerial landfill method Download PDFInfo
- Publication number
- JP3579807B2 JP3579807B2 JP13199796A JP13199796A JP3579807B2 JP 3579807 B2 JP3579807 B2 JP 3579807B2 JP 13199796 A JP13199796 A JP 13199796A JP 13199796 A JP13199796 A JP 13199796A JP 3579807 B2 JP3579807 B2 JP 3579807B2
- Authority
- JP
- Japan
- Prior art keywords
- landfill
- ground
- soil
- underground structure
- aerial
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【0001】
【産業上の利用分野】
この発明は、埋立区域を締切ってから排水を行って、埋立てと埋立地内の施設の建設とを行う気中埋立工法における地下構造物への側圧軽減方法に関するものである。
【0002】
【発明が解決しようとする課題】
海上人工島の構築等に採用されている従来の埋立工法は、水中に土砂投棄を行って、一律な地盤高さまで海面より盛る築島によるものであった。
【0003】
この水中埋立工法では、基礎地盤の沈下時間の延長または地盤改良の増加。水中埋立てに伴う埋立て地盤の強度不足と液状化の危険性及び地盤改良の増加。水中への土砂投棄による水質の汚濁や生態系の破壊。不良土埋立てによる埋立地盤の品質低下と早期利用の困難さ。築島と施設建設の平行作業ができないことによる工期の延長。地下施設の建設における山止め、再掘削などの手戻り作業などの課題を有する。
【0004】
また埋立て完了後に開削を行って地下構造物の建設を行っている関係上、地下構造物の側壁に地表面からの深度に比例した土圧、水圧が掛かり、側壁としては土圧、水圧が掛からない地上の側壁に比べて、きわめて厚いものとなるという課題をも有する。
【0005】
このような水中埋立工法の課題の解決として、埋立区域の締切りを行い、締切り内の排水を行って埋立区域の地盤を出現させ、その現地盤の地盤改良を行ってから締切り内の埋立てと、埋立地内の施設の建設とを行う気中埋立工法が開発された、この気中埋立工法では、
・ 締切り内を排水してから転圧して一層づつ埋立てるため、埋立て地盤の改良が不要で沈下量の少ない高品質な埋立てができる。従って完成後の維持管理が少なくなり、また埋立地盤の早期利用が可能となる。
・ 埋立て土砂量が増加する気中埋立てによる先行荷重のため、現地盤の圧密度が促進され、地盤改良が不要または少なく済む。
・ 締切り内を排水してから埋立てを行うので、水中への土砂投棄による場合に比べて水質汚濁が少なくなり、水質変化による埋立区域周辺の環境や漁業への影響も殆ど無くなる。
・ 建設発生土等の不良土の使用が可能となる。また埋立工と施設建設との同時施工ができるため工事短縮を図ることができる。
・ 施設建設のための山留工、二次掘削工が不要になり、また施設基礎杭が不要または短く済む。
という水中埋立工法では解決し得ない効果を奏するが、地下構造物の建設に関しては、埋立て完了後の開削による施工が採用されていた。
【0006】
この発明は、気中埋立工法における上記地下構造物の建設の課題を解決するために考えられたものであって、その目的は、地下構造物の側壁に掛かる土圧を、地下構造物の周囲土層を不透水土層とすることによって軽減し得る新たな方法を提供することにある。
【0007】
【課題を解決するための手段】
上記目的によるこの発明の特徴は、建設される地下構造物の周囲の地盤に土圧が小さくなる石炭灰またはセメント等による安定処理土の盛土を施工し、その安定処理土と地下構造物の間は軽量盛土とする、ということにある。
【0008】
このような側圧軽減方法では、地下構造物の構造をスリットにでき、石炭灰の有効利用も図れる。また地下構造物の周囲土層が強固なので地震時においても液状化せず、不透水層となるので地下構造物への揚圧力の低減と漏水のない高品質の構造物ができる。
【0009】
上記施設の建築は水底の地盤状況に応じて直接基礎または杭基礎等を基本とする。また上記地下構造物の屋根荷重を軽減する場合にはトラス屋根及び発泡スチロールのブロック、軽量盛土などの利用をもって行うことができ、上載荷重の低減により屋根構造のスリム化が可能となる他、屋根部分の盛土も軽量盛土の利用により可能となる。
【0010】
【発明の実施の形態】
護岸部分地盤の改良工程(図1)
止水性護岸または仮締切りとその補強の構築が可能な地形の水域が埋立区域として設定され、その水域の水底1の地質が軟弱で護岸部分2の地盤沈下が長期にわたる場合や、軟弱過ぎて護岸部分2が構築できない場合には、先ず埋立区域Aの護岸部分2となる水底1の地盤改良を行う。ただし、水域の地盤が良質な場合や長期間の地盤沈下時間を確保可能な場合には、水底1の地盤改良を省略することができる。
【0011】
この地盤改良は、作業船3を使用して所要本数のバーチカルドレーン杭4を支層となる地盤101まで一定間隔ごとに打設する。地盤改良時には汚濁防止幕5を作業船3から施工中の杭の周囲水中に張り設けて、舞い上がった土砂による海水の汚濁を防止する。このバーチカルドレーン杭4の造成により軟弱層の圧密が促進され、支持力が向上して護岸部分2の現地盤6の強度が増加する。
【0012】
締切り矢板打設工程(図2)
護岸部分2となる地盤改良した現地盤6に、止水性の鋼矢板7を地盤101まで一重または二重に打設して、埋立区域Aの外周締切りを行う。鋼矢板7の打設は、沖側に停泊位置させたクレーン付台船8の櫓から鋼矢板7を吊り下ろし、バイブロハンマーまたは油圧ハンマー9により現地盤6に打ち込んで行う。
【0013】
締切り中詰め工程(図3)
二重の鋼矢板で締切り行った場合には、打ち込み完了部分の内外の鋼矢板7をタイロッド10により一定間隔ごとに連結したのち、ガット船11で運んできた中詰め土砂12または捨石を鋼矢板7間に投入し、これにより水密に締切りを行う。
【0014】
締切り補強工程(図4)
さらに消波及び締切り安定のため、締切り矢板の沖側に捨石13を投入し、その上に被覆石,消波ブロックを据え付けて護岸14となす。場合によっては、内側にも捨石または土砂で押さえ盛土を行って安定性を確保する。
【0015】
埋立区域の現地盤不良土改良工程(図5)
締切った埋立区域内の全ての排水を行って水底1を出現させ、軟弱層をスタビライザー15等を使用して地盤改良する。また湧水処理,圧密促進を目的とするディープウイル16を、必要に応じて設置する。
【0016】
現地盤の改良工程(図6)
軟弱層の厚い場所には圧密沈下,支持力向上を目的に、バーチカルドレーンなどの地盤改良杭17を杭打機18により施工する。
【0017】
埋立て工程(図7)
現地盤の改良を完了したのち、土運搬船で運搬してきた埋立土砂19を揚土船20で締切り内に揚土して埋立てを行う。この際の埋立土砂は山土のみに限らず不良土を含む建設発生土でもよく、不良土は良質な砂質土と交互にサンドイッチ状にブルドーザー21により敷均し、充分に転圧する。
【0018】
施設建設工程(図8)
締切り内の埋立てと同時に埋立地内の施設の建設を開始する。この施設が地下構造物22の場合には、先ず施設建設予定地の周辺部まで改良地盤を取り除いて地盤101を出現させ、その地盤101の上にコンクリート躯体の地下構造物22を直接基礎により構築する。
【0019】
側圧軽減工程(図9)
次に地下構造物22の周囲の地盤101の上に、埋立て基盤面まで土圧が小さくなる石炭灰またはセメント等の安定処理土の盛土23を、地下構造物22との間に所要のスペース24を空けて施工する。この施工は盛土位置の地下構造物側の地盤101に薄壁の止水壁25を設けてから行う。
安定処理土の施工が完了したら地下構造物22と盛土23との上記スペース24に軽量盛土26を埋立て基盤面まで施工し、盛土23の外側には通常盛土27を施工する。
【0020】
上記地下構造物22の屋根部分を利用して植栽を行う場合には、、屋根荷重を軽減するために屋根をトラス屋根27とし、その上に発泡スチロールのブロックまたは軽量盛土などの中間層28を設け、その中間層28の上に植栽に必要な厚さ(50cm)に表土29を施す。
【0021】
上記のように、地下構造物22の周囲を石炭灰またはセメント等の安定処理土の盛土23と軽量盛土26とにより構成した場合には、地下構造物22の周囲土層が不透水層となることから、地下構造物22の側壁に掛かる水圧はなくなり、土圧と水圧とによる側圧が軽減されて、地下構造物22の側壁厚が薄く済むようになる。
【図面の簡単な説明】
【図1】気中埋立工法における護岸部分地盤改良工程図である。
【図2】締切り矢板打設工程図である。
【図3】締切り中詰め工程図である。
【図4】締切り補強工程図である。
【図5】埋立区域の現地盤不良土改良工程図である。
【図6】埋立区域の現地盤改良工程図である。
【図7】埋立て工程図である。
【図8】施設構築工程図である。
【図9】この発明の側圧軽減方法により構成した地下構造物周辺の略示縦断面図である。
【符号の説明】
1 埋立区域の地盤
2 護岸部分
4 バーチカルドレーン杭
6 護岸部分の現地盤
14 護岸
17 地盤改良
22 地下構造物
23 安定処理土の盛土
25 止水壁
26 軽量盛土
27 トラス屋根
28 中間層
29 表土
101 地盤[0001]
[Industrial applications]
BACKGROUND OF THE
[0002]
[Problems to be solved by the invention]
The conventional landfill method used for construction of artificial offshore islands, etc., was based on Tsukishima, which dumped sediment into the water and thrived from the sea surface to a uniform ground height.
[0003]
In this underwater landfill method, the subsidence time of the foundation ground is extended or the ground improvement is increased. Insufficient landfill strength due to underwater landfill, risk of liquefaction, and increase in ground improvement. Pollution of water quality and destruction of ecosystems by dumping sediment into water. Deterioration of landfill board quality due to landfill with bad soil and difficulty in early use. Extension of construction period due to the inability to carry out parallel work for Tsukishima and facility construction. There are issues such as rework and re-digging in the construction of underground facilities.
[0004]
In addition, due to the excavation and construction of the underground structure after the completion of landfill, earth pressure and water pressure are applied to the side wall of the underground structure in proportion to the depth from the ground surface. There is also a problem that it becomes extremely thick as compared with a side wall on the ground that does not hang.
[0005]
As a solution to the problem of such underwater reclamation method, the reclamation area is closed, drainage within the deadline is performed, and the ground in the reclamation area appears. The aerial landfill method was developed to construct facilities in the landfill.
・ Since the inside of the deadline is drained and then compacted one by one by rolling, it is not necessary to improve the landfill ground and high quality landfill with little settlement is possible. Therefore, the maintenance after completion is reduced, and the landfill can be used early.
・ Due to the pre-load due to the aerial landfill where the amount of landfill increases, the local density is promoted and the ground improvement is not required or required.
・ Since landfilling is performed after draining the deadline, water pollution is reduced compared to the case of dumping soil into the water, and the impact on the environment and fisheries around the landfill area due to changes in water quality is almost eliminated.
・ It is possible to use poor soil such as soil generated by construction. In addition, since the reclamation work and the facility construction can be performed simultaneously, the construction can be shortened.
・ Eliminating piers and secondary excavation for the construction of facilities is not required, and the foundation piles for facilities are not required or short.
The underwater reclamation method has an effect that cannot be solved, but for the construction of underground structures, construction by open-cutting after completion of reclamation has been adopted.
[0006]
The present invention was conceived in order to solve the problem of the construction of the underground structure in the aerial landfill method, and an object of the invention is to reduce the earth pressure applied to the side wall of the underground structure around the underground structure. It is an object of the present invention to provide a new method that can be reduced by making the soil layer an impermeable soil layer.
[0007]
[Means for Solving the Problems]
The feature of the present invention according to the above object is that embankment of a stabilized soil with coal ash or cement or the like whose earth pressure is reduced is constructed on the ground around the underground structure to be constructed, and between the stabilized soil and the underground structure. Is to use lightweight embankment.
[0008]
In such a side pressure reduction method, the structure of the underground structure can be made into a slit, and the coal ash can be effectively used. In addition, since the soil layer around the underground structure is strong, it does not liquefy even during an earthquake, and becomes an impermeable layer. Therefore, it is possible to reduce the lifting pressure on the underground structure and produce a high-quality structure without water leakage.
[0009]
The construction of the above facilities will be based on direct foundations or pile foundations, etc., depending on the condition of the underwater ground. In addition, the roof load of the underground structure can be reduced by using a truss roof, a block of styrofoam, lightweight embankment, etc., and the roof structure can be reduced by reducing the load on the roof. Embankment can be realized by using lightweight embankment.
[0010]
BEST MODE FOR CARRYING OUT THE INVENTION
Improvement of revetment ground (Fig. 1)
The water area of the terrain where watertight seawalls or temporary cutoffs and the reinforcement can be constructed is set as a landfill area, and the geology of the
[0011]
In this ground improvement, the required number of
[0012]
Cut-off sheet pile driving process (Fig. 2)
A water-resistant
[0013]
Deadline filling process (Fig. 3)
In the case of closing with double steel sheet piles, after the
[0014]
Deadline reinforcement process (Fig. 4)
Further, for the purpose of wave breaking and stabilizing the cut-off, rubble 13 is put offshore of the cut-off sheet pile, and a covering stone and a wave-breaking block are installed thereon to form a
[0015]
Improving the soil in the local area in the landfill area (Fig. 5)
All the drainage in the closed landfill area is drained to make the
[0016]
Improvement process of local panel (Fig. 6)
In a place where the soft layer is thick, a
[0017]
Landfill process (Fig. 7)
After the improvement of the on-site board has been completed, the
[0018]
Facility construction process (Fig. 8)
Construction of the facilities in the landfill will begin at the same time as the reclamation within the deadline. In the case where this facility is an
[0019]
Lateral pressure reduction process (Fig. 9)
Next, on the
When the construction of the stabilized soil is completed, a
[0020]
When planting is performed using the roof portion of the
[0021]
As described above, when the surroundings of the
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a process diagram of a revetment portion ground improvement process in an aerial landfill method.
FIG. 2 is a view showing a process of driving a cut-off sheet pile.
FIG. 3 is a diagram showing a process for closing during closing.
FIG. 4 is a process diagram of a cut-off reinforcement process.
FIG. 5 is a drawing showing a process of improving a soil in a local area in a landfill area.
FIG. 6 is a process chart of a local board improvement process in a landfill area.
FIG. 7 is a landfilling process chart.
FIG. 8 is a facility construction process diagram.
FIG. 9 is a schematic longitudinal sectional view showing the periphery of an underground structure constructed by the lateral pressure reducing method of the present invention.
[Explanation of symbols]
DESCRIPTION OF
Claims (1)
建設される地下構造物の周囲の地盤に土圧が小さくなる石炭灰またはセメント等による安定処理土の盛土を施工し、その安定処理土と地下構造物の間は軽量盛土とすることを特徴とする気中埋立工法における地下構造物への側圧軽減方法。A deadline for the reclamation area, drainage within the deadline to reveal the ground in the reclamation area, improve the ground of the local area, and then reclaim the land within the deadline and construct facilities in the landfill. In the landfill method,
The embankment of the stabilized soil with coal ash or cement that reduces the earth pressure is constructed on the ground around the underground structure to be constructed, and a lightweight embankment is used between the stabilized soil and the underground structure. Method to reduce lateral pressure on underground structures in the aerial landfill method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13199796A JP3579807B2 (en) | 1996-05-27 | 1996-05-27 | Method of reducing lateral pressure on underground structures in aerial landfill method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13199796A JP3579807B2 (en) | 1996-05-27 | 1996-05-27 | Method of reducing lateral pressure on underground structures in aerial landfill method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH09316852A JPH09316852A (en) | 1997-12-09 |
| JP3579807B2 true JP3579807B2 (en) | 2004-10-20 |
Family
ID=15071148
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP13199796A Expired - Fee Related JP3579807B2 (en) | 1996-05-27 | 1996-05-27 | Method of reducing lateral pressure on underground structures in aerial landfill method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3579807B2 (en) |
-
1996
- 1996-05-27 JP JP13199796A patent/JP3579807B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH09316852A (en) | 1997-12-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Porbaha et al. | State of the art in deep mixing technology: part II. Applications | |
| CN105178245A (en) | Large filling bag ecological embankment and revetment building method for river lake channel | |
| CN102995602A (en) | Structure and construction method of muddy coast sheet pile wharf | |
| NO318657B1 (en) | Procedure for the construction of an underground continuous wall | |
| CN104452829A (en) | Piled raft foundation anti-floating structure and construction method | |
| CN101260664A (en) | Soft soil foundation large scale steel float lock head construction method | |
| CN105804007B (en) | A kind of reinforced earth quaywall structure based on the soft base of beach | |
| CN110644427B (en) | A kind of ecological protection structure and dredging method of river bank slope under adverse geological conditions | |
| CN106192880B (en) | The box harbour of L-type and its method of construction | |
| CN202626934U (en) | Gravity wharf built on silty foundation | |
| JP2004108142A (en) | Method for construction of a control type revetment | |
| JP3579807B2 (en) | Method of reducing lateral pressure on underground structures in aerial landfill method | |
| CN204282295U (en) | Pile formula case cylinder breakwater structure | |
| CN107165121A (en) | Shallow slotting formula steel cylinder bank protection structure construction method | |
| JP3999628B2 (en) | Construction method of caisson dyke | |
| CN110080234A (en) | A method of it is excavated in the secondary central island of deep foundation pit of soft soil foundation | |
| CN107119716A (en) | Tidal land tidal bore area vcehicular tunnel builds structure and its method | |
| JPH08184022A (en) | Air reclamation method | |
| CN106677216B (en) | Access gallery structure and its construction method under deep water | |
| CN219327071U (en) | Combined hydraulic structure | |
| JP2546110B2 (en) | Levee structure using excavated sludge and its construction method | |
| CN110284511A (en) | The cofferdam open cutting construction method of the more storehouse rollers of overlength lake Tunnel | |
| JP2002038465A (en) | Excavation, solidification, and replacement method for foundation | |
| CN211080266U (en) | Coastal waters soft soil foundation cofferdam structure of permeating water | |
| JP4606454B2 (en) | Construction method of managed revetment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040623 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040629 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20040707 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080730 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100730 Year of fee payment: 6 |
|
| LAPS | Cancellation because of no payment of annual fees |