JP3589199B2 - Slab cutting control device and continuous cast slab manufacturing method - Google Patents
[go: Go Back, main page]

JP3589199B2 - Slab cutting control device and continuous cast slab manufacturing method - Google Patents

Slab cutting control device and continuous cast slab manufacturing method Download PDF

Info

Publication number
JP3589199B2
JP3589199B2 JP2001181614A JP2001181614A JP3589199B2 JP 3589199 B2 JP3589199 B2 JP 3589199B2 JP 2001181614 A JP2001181614 A JP 2001181614A JP 2001181614 A JP2001181614 A JP 2001181614A JP 3589199 B2 JP3589199 B2 JP 3589199B2
Authority
JP
Japan
Prior art keywords
slab
molten steel
amount
cutting
instruction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001181614A
Other languages
Japanese (ja)
Other versions
JP2003001384A (en
Inventor
収 山口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
JFE Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp filed Critical JFE Steel Corp
Priority to JP2001181614A priority Critical patent/JP3589199B2/en
Publication of JP2003001384A publication Critical patent/JP2003001384A/en
Application granted granted Critical
Publication of JP3589199B2 publication Critical patent/JP3589199B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Continuous Casting (AREA)
  • Feedback Control In General (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、連続鋳造される鋳片の切断を自動制御する鋳片切断制御装置、及び、自動制御切断により連続鋳造される鋳片を切断して鋳片を製造する連続鋳造鋳片の製造方法に関するものである。
【0002】
【従来の技術】
鋼の連続鋳造工程では、鋳造した鋳片を連続鋳造機出側に設けた鋳片切断機により所定の長さに切断して、注文の鋼製品に見合った連続鋳造鋳片を製造している。この鋳片切断のための従来のシステムを図2に示す。図2に示すように、鋳片切断のためのシステムは、大別して日程或いは週間と云う期間で製造計画を行うビジネスコンピューター51と、製造指示を行うプロセスコンピューター52とから構成され、プロセスコンピューター52は、製造指示データ情報記憶部53と製造指示再計算部54と切断指示部55とを備えている。
【0003】
ビジネスコンピューター51で作成された日程計画はプロセスコンピューター52の製造指示データ情報記憶部53へ送付され、製造指示再計算部54は、製造指示データ情報記憶部53から送信された製造指示データと秤量機57からの実績溶鋼量とを対比し、必要に応じて当該チャージのスラブ構成を再計算する。切断指示部55は、製造指示再計算部54での再計算結果を含め、製造指示再計算部54からチャージ構成に関するデータを受け、このデータに基づき鋳片の切断指示を鋳片切断機56に送信して、計画に沿った連続鋳造鋳片が採取される。尚、本発明においては「鋳片」と「スラブ」の2つの単語を用いているが、原則として、連続鋳造機により鋳造された現物を「鋳片」と呼び、一方、製造指示データ等の製造指示工程では「スラブ」と呼ぶこととする。
【0004】
このようなシステム構成を用いた鋳片の切断制御装置として、例えば特開平7−204815号公報、特開平9−94646号公報、及び特開平11−57961号公報等に開示された技術がある。特開平7−204815号公報には、鋳造チャージと使用溶鋼鍋とが紐付いた時点で、同一鋳造チャンス内のチャージ間でスラブを入れ替え、計画したスラブが未採取にならないようにする技術が開示され、特開平9−94646号公報には、評価関数を設定し、遺伝的アルゴリズムを用いて歩留まり優先或いは直行率優先等の条件を満足する切断パターンで切断する方法が開示され、特開平11−57961号公報には、遺伝的アルゴリズムに、更にヒルクライムアルゴリズムサーチ部を追加した切断制御装置が開示されている。
【0005】
【発明が解決しようとする課題】
しかしながら、これらの技術においては、プロセスコンピューターに送られるデータは日程の範囲のデータのみであり、その日に鋳造が予定されなかった同一鋼種の他の注文に関する情報は送付されておらず、又、注文に関する情報も注文番号、スラブ幅、スラブ長さと云った基本情報のみであり、その注文の納期に基づく優先度情報等は付与されていない。即ち、これら技術はプロセスコンピューターに送付された注文同士で入れ替えするのみであった。
【0006】
従って、これらの技術では、計画溶鋼量に対して実際の溶鋼量が不足の場合には、納期の逼迫しているスラブと納期に余裕のあるスラブとの識別を行うことができず、又、実際の溶鋼量が計画溶鋼量に対して過剰の場合には、注文情報が不明のために注文に基づかない適当な長さの鋳片を採取せざるを得ない。そのため、納期逼迫のスラブを採取できなかったり、余剰として採取された鋳片は注文のスラブ長さと一致せず、余剰として採取した鋳片を注文に引き当て難いと云った不具合が発生していた。
【0007】
本発明は上記事情に鑑みなされたもので、その目的とするところは、連続鋳造機により鋳片を鋳造する際に、計画溶鋼量と実績溶鋼量とに較差が生じた場合にも、注文の納期を考慮した最適な鋳片を採取することが可能であり、又、余剰で採取される鋳片も注文に基づく長さで採取することが可能となる鋳片切断制御装置及び連続鋳造鋳片の製造方法を提供することである。
【0008】
【課題を解決するための手段】
第1の発明による鋳片切断制御装置は、連続鋳造される鋳片の切断を制御する鋳片切断制御装置において、注文の納期に関する情報を付与された製造指示データを格納する製造指示データ情報記憶部と、製造未指示注文のスラブ幅及びスラブ長さの情報を格納する未指示スラブ情報記憶部と、計画溶鋼量と実績溶鋼量とに較差が生じた場合に前記製造指示データを再計算する製造指示再計算部と、製造指示再計算部での再計算結果に基づき鋳片の切断指示を発信する切断指示部と、からなることを特徴とするものである。
【0010】
の発明による鋳片切断制御装置は、連続鋳造される鋳片の切断を制御する鋳片切断制御装置において、製造指示データを格納する製造指示データ情報記憶部と、製造未指示注文のスラブ幅及びスラブ長さの情報を格納する未指示スラブ情報記憶部と、計画溶鋼量に対して実績溶鋼量が過剰の場合には未指示スラブ情報記憶部に格納されたスラブのデータの中から実績溶鋼量と計画溶鋼量との差が小さくなるようなスラブを選択し、選択したスラブを加えて前記製造指示データを再計算する製造指示再計算部と、製造指示再計算部での再計算結果に基づき鋳片の切断指示を発信する切断指示部と、からなることを特徴とするものである。
【0012】
の発明による連続鋳造鋳片の製造方法は、取鍋内に収容された溶鋼を連続鋳造する際に、予め取鍋内溶鋼の重量を測定して、測定した取鍋内の実績溶鋼量と当該チャージの計画溶鋼量とを対比し、計画溶鋼量に対して実績溶鋼量が過剰の場合には、製造指示をしていない注文に該当するスラブの中から実績溶鋼量と計画溶鋼量との差が小さくなるようなスラブを選択し、選択したスラブを加えて当該チャージの構成を修正し、修正したチャージ構成に基づき連続鋳造される鋳片を切断することを特徴とするものである。
【0013】
本発明では、計画溶鋼量と実績溶鋼量とに較差が生じ、計画溶鋼量に対して実績溶鋼量が不足した場合には、納期の優先度の高い注文に該当するスラブが採取されるように当該チャージ構成を修正し、一方、計画溶鋼量に対して実績溶鋼量が過剰の場合には、製造指示をしていない注文に該当するスラブの中から実績溶鋼量と計画溶鋼量との差に対応するようなスラブを選択し、選択したスラブを加えて当該チャージの構成を修正し、修正したチャージ構成に基づき連続鋳造される鋳片を切断するので、納期逼迫のスラブを確実に採取することができ、又、余剰として採取された鋳片は注文に対応するスラブ長さと一致しており、余剰鋳片を注文に引き当てにくいと云った不具合が防止される。
【0014】
【発明の実施の形態】
以下、本発明の実施の形態を図面を参照して説明する。図1は、本発明の実施の形態を示す図であって、本発明による鋳片切断制御装置を備えた鋳片切断設備全体の概略構成図である。
【0015】
図1に示すように、本発明による鋳片切断制御装置2は、生産管理を司るビジネスコンピューター1から送信される製造指示データを格納する製造指示データ情報記憶部3と、ビジネスコンピューター1から送信される製造未指示注文の情報を格納する未指示スラブ情報記憶部4と、製造指示データを再計算する製造指示再計算部5と、製造指示再計算部5での再計算結果に基づき鋳片の切断指示を発信する切断指示部6とから構成される。切断指示部6の信号は、連続鋳造機(図示せず)の出側に設けられた、鋳片引き抜き速度と同調して移動する鋳片切断機7に送られ、この信号に基づき連続鋳造されつつある鋳片が切断される。
【0016】
ビジネスコンピューター1から送信される製造指示データには、注文の計画No.、品種、鋼種、納期、スラブ幅、スラブ長さ、鋳造位置等の情報が含まれ、こられの情報は製造指示データ情報記憶部3に記憶される。又、ビジネスコンピューター1から送信される製造未指示注文の情報には、品種、鋼種、スラブ幅、スラブ長さ等の情報が含まれ、これらの情報は未指示スラブ情報記憶部4に記憶される。尚、製造未指示注文とは、今回の製造指示データの中には送信されていなかった注文であり、製造指示データ情報記憶部3には記憶されていない情報である。製造未指示注文の情報は多いほど再計算が行い易く、従って、少なくとも1日分程度の製造未指示注文の情報を未指示スラブ情報記憶部4に記憶させることが好ましい。又、鋳造位置とは、連続鋳造機の鋳造において鋳造開始域、定常域、鋳造終了域等で区分される識別である。
【0017】
連続鋳造機による鋳造に先立ち、転炉や電気炉等から出鋼され、取鍋に収容された溶鋼の重量を測定する。溶鋼の重量測定は秤量機8により行うことができる。溶鋼を収容していない時(空状態)の重量を予め測定しておき、溶鋼を収納した時の測定値から空状態の測定値を差し引くことで求めることができる。但し、この場合には取鍋内のスラグ量も測定値に含まれるので、スラグ厚み等の測定によりスラグ重量を算出し、溶鋼を収納した時の測定値からスラグ重量を差し引くことで、溶鋼量を正確に把握することができる。このようにして測定した溶鋼重量を実績溶鋼量と定義する。秤量機8は実績溶鋼量を製造指示再計算部5に送信する。尚、実績溶鋼量は取鍋上端位置と溶鋼湯面位置との間の距離からも算出することができるが、この場合には誤差が大きく好ましくない。
【0018】
製造指示再計算部5は、秤量機8から送信されてきた実績溶鋼量と、製造指示データ情報記憶部3から送信されてきた計画溶鋼量とを対比する。計画溶鋼量とは、当該チャージを構成するスラブの重量の総和であり、クロップ等が必要な場合にはクロップ等の重量も加えた総量である。
【0019】
計画溶鋼量と実績溶鋼量とを対比して両者に較差があった場合には、製造指示再計算部5は、以下に示す2種類のうちのどちらかの方法により再計算を行って当該チャージのスラブ構成を修正し、再計算結果を切断指示部6に送信する。一方、計画溶鋼量と実績溶鋼量とに較差がない場合には、製造指示再計算部5は製造指示データ情報記憶部3から送信されてきた製造指示データをそのまま切断指示部6に送信する。
【0020】
以下に、具体的な例を参照して製造指示再計算部5における2種類の再計算方法を説明する。
【0021】
1.実績溶鋼量が計画溶鋼量に対して不足する場合:
表1に、製造指示データ情報記憶部3から製造指示再計算部5に送信されてきた当該チャージの製造指示データを示す。尚、当該チャージは同一鋼種の3チャージの連続連続鋳造(以下「連々鋳」と記す)の2チャージ目であり、クロップ分は必要とせず、表1にはクロップ分が含まれていない。
【0022】
【表1】

Figure 0003589199
【0023】
表1に示すように当該チャージの計画溶鋼量は255トンであり、各々の計画No.にはスラブ幅、スラブ重量、納期余裕度が付与されている。納期余裕度は、その数値が大きいほど余裕があることを示している。ここで、秤量機8によって計測された実績溶鋼量が240トンであったとする。
【0024】
計画溶鋼量に対して実績溶鋼量が不足しているため、計画された注文の全てに対応する鋳片を採取できないことが明らかである。この場合には、鋳造順制約を破らない範囲で、納期的に余裕のある注文に該当するスラブを計画から取り除く。尚、鋳造順制約とは、鋳片の上端部と下端部との寸法差に起因して屑化される鋳片を発生することなく、連続鋳造機の鋳型の鋳造中幅変更により異なる幅の鋳片を同一鋳造チャンスで鋳造するための制約であり、例えば1チャージを構成するスラブの幅の差が50mm以下の間隔であること等々、連続鋳造機の仕様と熱間圧延機の仕様とに応じて変化するものである。本実施の形態ではスラブ幅の差が50mm以下の条件を鋳造順制約とする。
【0025】
表1を参照してスラブを計画から除外する方法を具体的に説明する。スラブ幅の大きい順から納期余裕度の大きい順に選択すると、第1候補として計画No.LLLLが選択される。この場合、計画No.LLLLと同一スラブ幅の計画のスラブ本数を数えると、1600mm幅のスラブは計画No.LLLL以外には1本しかないため、仮に計画No.LLLLを取り除いた場合には、スラブ幅が50mm間隔以内であると云う鋳造順制約を満足することができない。
【0026】
そこで、次の候補を探すと計画No.FFFFが第2候補として選択される。計画No.FFFFについても同様に鋳造順制約を満足するかを判定する。計画No.FFFFを取り除いても計画No.FFFFと同一スラブ幅の計画が計画No.FFFF以外に3本あり、鋳造順制約を満足することが分かる。又、計画No.FFFFを取り除くことにより、計画溶鋼量と実績溶鋼量とが合致する。
【0027】
この例では、1本のスラブを計画から取り除くことにより、計画溶鋼量と実績溶鋼量とが合致したが、一般的には合致しないケースが多い。その場合には、鋳造順制約を満足する範囲で納期余裕度の大きいスラブを計画から取り除き、溶鋼の余剰量をスラブ1本分未満の量とした上で、例えば、鋳造中に各鋳片の鋳造履歴を把握・認識して各鋳片の手入れロス量に応じて各鋳片に余剰分を振り分けるようにスラブ長さを再計算する、若しくは、各鋳片に余剰分を均等に振り分けるようにスラブ長さを再計算すれば良い。
【0028】
このような手順で再計算することにより、納期の逼迫した注文を取りこぼすことなく鋳片を採取することができる。
【0029】
2.実績溶鋼量が計画溶鋼量に対して過剰の場合:
この場合には、余剰として採取する鋳片の長さをどのようにして決めるかが問題となる。当該チャージのチャージ構成として、表2に示す製造指示データが製造指示データ情報記憶部3から製造指示再計算部5に送信されており、秤量された実績溶鋼量が256トンだったとする。この場合、計画溶鋼量は241トンであり、溶鋼の余剰分は15トンとなる。尚、当該チャージは同一鋼種の3チャージの連々鋳の2チャージ目であり、クロップ分は必要とせず、表2にはクロップ分が含まれていない。
【0030】
【表2】
Figure 0003589199
【0031】
未指示スラブ情報記憶部4には、表3に示すように当該チャージと同一鋼種であって、製造指示されていない注文のスラブ幅及びスラブ重量が記憶されており、これらのスラブの中から、前述した鋳造順制約並びにスラブ重量≦余剰溶鋼量の関係の両者を満足するスラブを選択して、当該チャージに組み入れることにより、余剰鋳片を実際の注文にすぐに引き当てることができ、無駄のない鋳片採りが可能となる。
【0032】
【表3】
Figure 0003589199
【0033】
表2及び表3を参照してスラブを計画に組み入れる方法を具体的に説明する。スラブ幅が当該チャージの鋳造開始時と鋳造終了時との間の範囲内であり、スラブ重量が余剰溶鋼量以下であるスラブを表3のスラブ群の中から探索する。余剰溶鋼量がスラブ2本分以上の場合にはスラブの組み合わせを探索する。表3に示す連番1及び連番5は、当該チャージのスラブ幅の範囲外であり候補から除外される。又、残ったスラブの内でその重量が余剰溶鋼量以下のスラブは連番4のみであるため、連番4のスラブに該当する鋳片を当該チャージから採取することとする。このケースでは、連番4のスラブをNo.1ストランドの最後の位置に挿入することにより、計画溶鋼量と実績溶鋼量とが合致する。
【0034】
この例でも、1本のスラブを計画に組み込むことにより、計画溶鋼量と実績溶鋼量とが合致したが、余剰溶鋼量がスラブ1本分に満たない場合もあり、一般的には合致しないケースが多い。その場合には、上記の条件を満足するスラブを計画に組み入れる等を実施して、少なくとも溶鋼の余剰量をスラブ1本分未満の量とした上で、例えば、鋳造中に各鋳片の鋳造履歴を把握・認識して各鋳片の手入れロス量に応じて各鋳片に余剰分を振り分けるようにスラブ長さを再計算する、若しくは、各鋳片に余剰分を均等に振り分けるようにスラブ長さを再計算すれば良い。
【0035】
このような手順で再計算することにより、余剰鋳片は注文のスラブ長さとなり、余剰鋳片を注文に引き当てにくいと云った不具合を未然に防止することが可能となる。
【0036】
【発明の効果】
本発明によれば、実績溶鋼量が計画溶鋼量に対して不足する場合には、納期に関する情報を使用して納期の早い順に鋳片を切断するので、注文の納期遅れを抑制することができ、又、実績溶鋼量が計画溶鋼量に対して過剰の場合には、他の注文に基づくスラブ長さで鋳片を切断するので、余剰として採取された鋳片の注文への引き当てを円滑に行うことができる。
【図面の簡単な説明】
【図1】本発明による鋳片切断制御装置を備えた切断設備全体の概略構成図である。
【図2】従来の連続鋳造鋳片切断のためのシステム構成図である
【符号の説明】
1 ビジネスコンピューター
2 鋳片切断制御装置
3 製造指示データ情報記憶部
4 未指示スラブ情報記憶部
5 製造指示再計算部
6 切断指示部
7 鋳片切断機
8 秤量機[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a slab cutting control device for automatically controlling the cutting of a continuously cast slab, and a method for producing a slab by cutting a continuously cast slab by automatic control cutting. It is about.
[0002]
[Prior art]
In the continuous casting process of steel, the cast slab is cut into a predetermined length by a slab cutting machine provided on the continuous casting machine outlet side to produce a continuous cast slab suitable for the ordered steel product. . FIG. 2 shows a conventional system for cutting the slab. As shown in FIG. 2, the system for cutting a slab is roughly divided into a business computer 51 for performing a production plan in a period called a schedule or a week, and a process computer 52 for performing a production instruction. , A production instruction data information storage unit 53, a production instruction recalculation unit 54, and a cutting instruction unit 55.
[0003]
The schedule created by the business computer 51 is sent to the manufacturing instruction data information storage unit 53 of the process computer 52, and the manufacturing instruction recalculation unit 54 compares the manufacturing instruction data transmitted from the manufacturing instruction data information storage unit 53 with the weighing machine. Compare the actual molten steel amount from 57 and recalculate the slab configuration of the charge as needed. The cutting instructing unit 55 receives data on the charge configuration from the manufacturing instruction recalculating unit 54, including the recalculation result in the manufacturing instruction recalculating unit 54, and sends a slab cutting instruction to the slab cutting machine 56 based on this data. By transmitting, the continuous cast slab according to the plan is collected. In the present invention, the two words "slab" and "slab" are used. In principle, the actual product cast by the continuous casting machine is called "slab", while the production instruction data and the like are used. In the manufacturing instruction process, it is called “slab”.
[0004]
As a slab cutting control device using such a system configuration, there are techniques disclosed in, for example, JP-A-7-204815, JP-A-9-94646, and JP-A-11-57961. Japanese Patent Application Laid-Open No. Hei 7-204815 discloses a technique in which slabs are replaced between charges in the same casting chance when a casting charge and a molten steel pot are tied, so that a planned slab is not uncollected. Japanese Patent Application Laid-Open No. 9-94646 discloses a method of setting an evaluation function and using a genetic algorithm to perform cutting with a cutting pattern that satisfies conditions such as yield priority or direct rate priority. The publication discloses a cutting control device in which a hill climb algorithm search unit is further added to the genetic algorithm.
[0005]
[Problems to be solved by the invention]
However, in these technologies, the data sent to the process computer is only the data in the range of the schedule, and information on other orders of the same steel type that were not scheduled to be cast on that day is not sent, and Is only basic information such as an order number, a slab width, and a slab length, and priority information based on the delivery date of the order is not given. That is, these techniques only exchanged orders sent to the process computer.
[0006]
Therefore, in these techniques, if the actual molten steel amount is insufficient with respect to the planned molten steel amount, it is not possible to distinguish between a slab having a tight delivery date and a slab having a sufficient delivery date, and If the actual amount of molten steel is excessive with respect to the planned amount of molten steel, the order information is unknown, so that a slab of an appropriate length that is not based on the order must be collected. For this reason, slabs with tight delivery deadlines could not be collected, or the slabs collected as surplus did not match the slab length of the order, and it was difficult to allocate the slabs collected as surplus to the order.
[0007]
The present invention has been made in view of the above circumstances, and an object of the present invention is to make an order even when a difference occurs between a planned molten steel amount and an actual molten steel amount when casting a slab by a continuous casting machine. A slab cutting control device and a continuous cast slab capable of collecting an optimal slab in consideration of a delivery date, and also capable of collecting a surplus slab in a length based on an order. Is to provide a manufacturing method.
[0008]
[Means for Solving the Problems]
A slab cutting control device according to a first aspect of the present invention is a slab cutting control device for controlling cutting of a slab to be continuously cast, wherein the manufacturing instruction data information storage stores manufacturing instruction data provided with information on an order delivery date. Part, a non-designated slab information storage unit that stores information on the slab width and slab length of the production unspecified order, and recalculates the production instruction data when a difference occurs between the planned molten steel amount and the actual molten steel amount. It is characterized by comprising a production instruction recalculation unit and a cutting instruction unit for transmitting a cutting instruction of the slab based on the recalculation result in the production instruction recalculation unit.
[0010]
A slab cutting control device according to a second aspect of the present invention is a slab cutting control device for controlling cutting of a continuously cast slab, wherein a slab for manufacturing instruction data information storing a manufacturing instruction data is provided. An undesignated slab information storage unit that stores information on width and slab length, and an actual slab data stored in the undesignated slab information storage unit when the actual molten steel amount is excessive with respect to the planned molten steel amount. A production instruction recalculation unit that selects a slab in which the difference between the molten steel amount and the planned molten steel amount is small, adds the selected slab, and recalculates the production instruction data, and a recalculation result in the production instruction recalculation unit And a cutting instruction unit for transmitting a cutting instruction of the slab based on the cutting instruction.
[0012]
In the method for producing a continuous cast slab according to the third invention, when continuously casting molten steel accommodated in a ladle, the weight of the molten steel in the ladle is measured in advance, and the measured actual amount of molten steel in the ladle is measured. When the actual molten steel amount is excessive with respect to the planned molten steel amount, the actual molten steel amount and the planned molten steel amount are selected from the slab corresponding to the order for which no production instruction is given. Is selected so that the difference between the slabs is small, the selected slab is added, the configuration of the charge is corrected, and the slab that is continuously cast is cut based on the corrected charge configuration.
[0013]
In the present invention, a difference occurs between the planned molten steel amount and the actual molten steel amount, and when the actual molten steel amount is insufficient with respect to the planned molten steel amount, a slab corresponding to a high priority order of delivery date is collected. The charge configuration is modified, but if the actual molten steel amount is excessive with respect to the planned molten steel amount, the difference between the actual molten steel amount and the planned molten steel amount is selected from the slabs corresponding to the orders for which production instructions have not been issued. Select the corresponding slab, add the selected slab, modify the configuration of the charge, and cut the slab that is continuously cast based on the modified charge configuration. In addition, the slab collected as surplus matches the slab length corresponding to the order, and the problem that it is difficult to attract the surplus slab to the order is prevented.
[0014]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1 is a view showing an embodiment of the present invention, and is a schematic configuration diagram of the entire slab cutting equipment provided with a slab cutting control device according to the present invention.
[0015]
As shown in FIG. 1, a slab cutting control device 2 according to the present invention includes a manufacturing instruction data information storage unit 3 that stores manufacturing instruction data transmitted from a business computer 1 that manages production management, and a business instruction data transmission unit 3 that transmits the manufacturing instruction data. Unscheduled slab information storage unit 4 for storing information on non-manufactured instruction orders, manufacturing instruction recalculation unit 5 for recalculating manufacturing instruction data, and slab And a disconnection instruction section 6 for transmitting a disconnection instruction. The signal of the cutting instruction unit 6 is sent to a slab cutting machine 7 provided on the output side of a continuous casting machine (not shown), which moves in synchronization with the slab drawing speed, and is continuously cast based on this signal. The slab is being cut.
[0016]
The production instruction data transmitted from the business computer 1 includes an order plan No. , Type, steel type, delivery date, slab width, slab length, casting position, etc., are stored in the manufacturing instruction data information storage unit 3. The information on the non-manufactured order sent from the business computer 1 includes information such as a product type, a steel type, a slab width, and a slab length, and these information are stored in the undesignated slab information storage unit 4. . The non-manufacturing order is an order that has not been transmitted in the current manufacturing instruction data, and is information that is not stored in the manufacturing instruction data information storage unit 3. Recalculation is easier to perform as the information on the non-manufactured order is larger. Therefore, it is preferable to store at least one day's worth of information on the unmanaged order in the non-managed slab information storage unit 4. The casting position is an identification that is divided into a casting start area, a steady area, a casting end area, and the like in casting by a continuous casting machine.
[0017]
Prior to casting by a continuous casting machine, the weight of molten steel discharged from a converter or an electric furnace and stored in a ladle is measured. The weight measurement of the molten steel can be performed by the weighing machine 8. The weight when the molten steel is not accommodated (empty state) is measured in advance, and it can be obtained by subtracting the measured value in the empty state from the measured value when the molten steel is accommodated. However, in this case, since the amount of slag in the ladle is also included in the measured value, the slag weight is calculated by measuring the slag thickness, etc., and the slag weight is subtracted from the measured value when the molten steel is stored, so that the amount of molten steel is calculated. Can be accurately grasped. The molten steel weight thus measured is defined as the actual molten steel amount. The weighing machine 8 transmits the actual molten steel amount to the production instruction recalculation unit 5. The actual molten steel amount can also be calculated from the distance between the upper end position of the ladle and the position of the molten steel surface, but in this case, a large error is not preferable.
[0018]
The production instruction recalculating unit 5 compares the actual molten steel amount transmitted from the weighing machine 8 with the planned molten steel amount transmitted from the production instruction data information storage unit 3. The planned amount of molten steel is the total weight of the slabs constituting the charge, and is the total amount including the weight of the crop when a crop or the like is required.
[0019]
If there is a difference between the planned molten steel amount and the actual molten steel amount, the production instruction recalculation unit 5 performs recalculation by one of the following two methods to charge the charge. Is corrected, and the recalculation result is transmitted to the cutting instruction unit 6. On the other hand, when there is no difference between the planned molten steel amount and the actual molten steel amount, the production instruction recalculating unit 5 transmits the production instruction data transmitted from the production instruction data information storage unit 3 to the cutting instruction unit 6 as it is.
[0020]
Hereinafter, two types of recalculation methods in the manufacturing instruction recalculation unit 5 will be described with reference to specific examples.
[0021]
1. When the actual molten steel amount is insufficient for the planned molten steel amount:
Table 1 shows the manufacturing instruction data of the charge transmitted from the manufacturing instruction data information storage unit 3 to the manufacturing instruction recalculation unit 5. Note that this charge is the second charge of continuous casting of three charges of the same steel type (hereinafter referred to as “continuous casting”), no crop is required, and Table 1 does not include the crop.
[0022]
[Table 1]
Figure 0003589199
[0023]
As shown in Table 1, the planned molten steel amount of the charge is 255 tons. Are given a slab width, a slab weight, and a margin for delivery. The delivery date margin indicates that the larger the numerical value is, the more room there is. Here, it is assumed that the actual molten steel amount measured by the weighing machine 8 is 240 tons.
[0024]
It is clear that the slabs corresponding to all the planned orders cannot be collected due to the lack of the actual amount of molten steel with respect to the planned amount of molten steel. In this case, a slab corresponding to an order with a sufficient delivery date is removed from the plan as long as the casting order constraint is not violated. In addition, the casting order constraint is defined as a difference in width due to a change in width during casting of a casting mold of a continuous casting machine without generating a slab which is debris due to a dimensional difference between an upper end portion and a lower end portion of the slab. This is a restriction for casting slabs at the same casting chance. For example, the difference between the widths of slabs constituting one charge is an interval of 50 mm or less. It changes according to. In the present embodiment, the condition that the difference in slab width is 50 mm or less is defined as the casting order constraint.
[0025]
A method for excluding a slab from a plan will be specifically described with reference to Table 1. If the slab width is selected in descending order from the largest slab width, the plan No. is selected as the first candidate. LLLL is selected. In this case, the plan No. When the number of slabs in the plan having the same slab width as that of LLLL is counted, the slab having the width of 1600 mm corresponds to plan No. Since there is only one other than LLLL, plan No. When the LLLL is removed, the casting order restriction that the slab width is not more than 50 mm cannot be satisfied.
[0026]
Therefore, when the next candidate is searched, the plan No. FFFF is selected as the second candidate. Plan No. Similarly, it is determined whether or not FFFF satisfies the casting order constraint. Plan No. Even if FFFF is removed, plan No. The plan with the same slab width as FFFF is Plan No. It can be seen that there are three pieces other than FFFF, which satisfies the casting order constraint. In addition, the plan No. By removing FFFF, the planned molten steel amount and the actual molten steel amount match.
[0027]
In this example, by removing one slab from the plan, the planned amount of molten steel and the actual amount of molten steel match, but in general there are many cases where they do not match. In that case, slabs with large delivery margins are removed from the plan within the range that satisfies the casting order constraint, and the surplus amount of molten steel is reduced to less than one slab. Recalculate the slab length so that the casting history is grasped and recognized and the surplus is distributed to each slab according to the amount of maintenance loss of each slab, or the surplus is evenly distributed to each slab What is necessary is just to recalculate the slab length.
[0028]
By recalculating according to such a procedure, a slab can be collected without dropping an order with a tight delivery date.
[0029]
2. When the actual molten steel amount is excessive with respect to the planned molten steel amount:
In this case, the problem is how to determine the length of the slab to be collected as surplus. As the charge configuration of the charge, it is assumed that the production instruction data shown in Table 2 has been transmitted from the production instruction data information storage unit 3 to the production instruction recalculation unit 5, and the weighed actual molten steel amount was 256 tons. In this case, the planned molten steel amount is 241 tons, and the surplus of molten steel is 15 tons. Note that this charge is the second charge of three consecutive castings of the same steel type, no crop is required, and Table 2 does not include the crop.
[0030]
[Table 2]
Figure 0003589199
[0031]
As shown in Table 3, the unspecified slab information storage unit 4 stores slab widths and slab weights of orders that are the same steel type as the charge and have not been instructed to manufacture, and among these slabs, By selecting a slab that satisfies both the relationship of the above-described casting order and the relationship of slab weight ≦ excess molten steel amount and incorporating it into the charge, the excess slab can be immediately allocated to the actual order, and there is no waste. It is possible to take a slab.
[0032]
[Table 3]
Figure 0003589199
[0033]
A method for incorporating a slab into a plan will be specifically described with reference to Tables 2 and 3. A slab whose slab width is within the range between the start of casting and the end of casting of the charge and whose slab weight is equal to or less than the amount of excess molten steel is searched from the slab group in Table 3. When the amount of excess molten steel is equal to or more than two slabs, a combination of slabs is searched. The serial numbers 1 and 5 shown in Table 3 are outside the range of the slab width of the charge and are excluded from the candidates. Further, among the remaining slabs, the slab whose weight is equal to or less than the amount of excess molten steel is only the serial number 4, so that the slab corresponding to the slab with the serial number 4 is collected from the charge. In this case, the slab with the serial number 4 is No. By inserting at the last position of one strand, the planned molten steel amount and the actual molten steel amount match.
[0034]
Also in this example, the planned molten steel amount and the actual molten steel amount matched by incorporating one slab into the plan, but the excess molten steel amount may be less than one slab, and generally the case does not match. There are many. In that case, slabs satisfying the above conditions are incorporated into the plan, etc., and at least the surplus amount of molten steel is reduced to less than one slab. Re-calculate the slab length so that the surplus is allocated to each slab according to the maintenance loss of each slab by grasping and recognizing the history, or slab so that the surplus is evenly distributed to each slab Just recalculate the length.
[0035]
By performing the recalculation in such a procedure, the surplus slab becomes the slab length of the order, and it is possible to prevent a problem that it is difficult to attract the surplus slab to the order.
[0036]
【The invention's effect】
According to the present invention, when the actual molten steel amount is insufficient with respect to the planned molten steel amount, the slabs are cut in the order of the earliest delivery date using the information on the delivery date, so it is possible to suppress a delay in the delivery date of the order. In addition, if the actual molten steel amount is excessive with respect to the planned molten steel amount, the slab is cut with the slab length based on another order, so the allocation of excess slab to the order is smooth. It can be carried out.
[Brief description of the drawings]
FIG. 1 is a schematic configuration diagram of an entire cutting facility including a slab cutting control device according to the present invention.
FIG. 2 is a configuration diagram of a conventional system for cutting continuous cast slabs.
DESCRIPTION OF SYMBOLS 1 Business computer 2 Slab cutting control device 3 Manufacturing instruction data information storage unit 4 Undesignated slab information storage unit 5 Manufacturing instruction recalculation unit 6 Cutting instruction unit 7 Slab cutting machine 8 Weighing machine

Claims (3)

連続鋳造される鋳片の切断を制御する鋳片切断制御装置において、注文の納期に関する情報を付与された製造指示データを格納する製造指示データ情報記憶部と、製造未指示注文のスラブ幅及びスラブ長さの情報を格納する未指示スラブ情報記憶部と、計画溶鋼量と実績溶鋼量とに較差が生じた場合に前記製造指示データを再計算する製造指示再計算部と、製造指示再計算部での再計算結果に基づき鋳片の切断指示を発信する切断指示部と、からなることを特徴とする鋳片切断制御装置。In a slab cutting control device for controlling cutting of a slab to be continuously cast, a manufacturing instruction data information storage unit for storing manufacturing instruction data provided with information on order delivery date, a slab width and a slab of an unmanufactured order. An uninstructed slab information storage unit that stores length information, a production instruction recalculation unit that recalculates the production instruction data when a difference occurs between the planned molten steel amount and the actual molten steel amount, and a production instruction recalculation unit And a cutting instruction unit for transmitting a cutting instruction of the slab based on the recalculation result of the slab. 連続鋳造される鋳片の切断を制御する鋳片切断制御装置において、製造指示データを格納する製造指示データ情報記憶部と、製造未指示注文のスラブ幅及びスラブ長さの情報を格納する未指示スラブ情報記憶部と、計画溶鋼量に対して実績溶鋼量が過剰の場合には未指示スラブ情報記憶部に格納されたスラブのデータの中から実績溶鋼量と計画溶鋼量との差が小さくなるようなスラブを選択し、選択したスラブを加えて前記製造指示データを再計算する製造指示再計算部と、製造指示再計算部での再計算結果に基づき鋳片の切断指示を発信する切断指示部と、からなることを特徴とする鋳片切断制御装置。In a slab cutting control device for controlling cutting of a slab to be continuously cast, a production instruction data information storage unit for storing production instruction data, and an uninstruction for storing information on a slab width and a slab length of an uninstructed order for production. If the actual molten steel amount is excessive with respect to the slab information storage unit and the planned molten steel amount, the difference between the actual molten steel amount and the planned molten steel amount becomes smaller from the slab data stored in the undesignated slab information storage unit. A production instruction recalculation unit for selecting such a slab, recalculating the production instruction data by adding the selected slab, and a cutting instruction for transmitting a slab cutting instruction based on a recalculation result in the production instruction recalculation unit. A slab cutting control device, comprising: 取鍋内に収容された溶鋼を連続鋳造する際に、予め取鍋内溶鋼の重量を測定して、測定した取鍋内の実績溶鋼量と当該チャージの計画溶鋼量とを対比し、計画溶鋼量に対して実績溶鋼量が過剰の場合には、製造指示をしていない注文に該当するスラブの中から実績溶鋼量と計画溶鋼量との差が小さくなるようなスラブを選択し、選択したスラブを加えて当該チャージの構成を修正し、修正したチャージ構成に基づき連続鋳造される鋳片を切断することを特徴とする連続鋳造鋳片の製造方法。When continuously casting molten steel stored in a ladle, the weight of the molten steel in the ladle is measured in advance, and the measured actual amount of molten steel in the ladle is compared with the planned amount of molten steel in the charge. When the actual molten steel amount was excessive with respect to the amount, a slab that reduced the difference between the actual molten steel amount and the planned molten steel amount was selected from the slabs corresponding to the order for which no production instruction was given, and selected. A method of manufacturing a continuously cast slab, wherein a configuration of the charge is modified by adding a slab, and a slab continuously cast is cut based on the modified charge configuration.
JP2001181614A 2001-06-15 2001-06-15 Slab cutting control device and continuous cast slab manufacturing method Expired - Fee Related JP3589199B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001181614A JP3589199B2 (en) 2001-06-15 2001-06-15 Slab cutting control device and continuous cast slab manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001181614A JP3589199B2 (en) 2001-06-15 2001-06-15 Slab cutting control device and continuous cast slab manufacturing method

Publications (2)

Publication Number Publication Date
JP2003001384A JP2003001384A (en) 2003-01-07
JP3589199B2 true JP3589199B2 (en) 2004-11-17

Family

ID=19021849

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001181614A Expired - Fee Related JP3589199B2 (en) 2001-06-15 2001-06-15 Slab cutting control device and continuous cast slab manufacturing method

Country Status (1)

Country Link
JP (1) JP3589199B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5338269B2 (en) * 2008-11-20 2013-11-13 Jfeスチール株式会社 Slab sampling control method
JP5428743B2 (en) * 2009-10-20 2014-02-26 Jfeスチール株式会社 Method and apparatus for knitting and determining cast for continuous casting
JP7196663B2 (en) * 2019-02-13 2022-12-27 日本製鉄株式会社 Control device, method and program for continuous casting process
EP3893068A1 (en) * 2020-04-09 2021-10-13 Primetals Technologies Austria GmbH Method for dynamic production planning in continuous casting plants
CN114247861B (en) * 2020-09-23 2023-09-05 上海梅山钢铁股份有限公司 Optimized cutting method for mixed casting continuous casting slab of different steel types
CN116174670A (en) * 2023-02-22 2023-05-30 北京首钢自动化信息技术有限公司 Casting blank production method for optimizing production plan during slab iron inserting

Also Published As

Publication number Publication date
JP2003001384A (en) 2003-01-07

Similar Documents

Publication Publication Date Title
JP5786724B2 (en) Steelmaking process operation schedule creation method, steelmaking process operation schedule creation system, steelmaking process operation method, and steel manufacturing method
JP3589199B2 (en) Slab cutting control device and continuous cast slab manufacturing method
JP7156024B2 (en) Plan creation device, plan creation method, and program
JP2018101389A (en) Plan creation device, plan creation method, and program
JP6904157B2 (en) Operation schedule creation method, equipment and programs
JP2017211834A (en) Plan creation device, plan creation method, and program
JP6724858B2 (en) Transportation container allocation plan creation method, transportation container allocation plan creation device, and steel mill operation method
US11045868B2 (en) Method for controlling a continuous casting system
JP6070766B2 (en) Allocation plan creation method and allocation plan creation device for molten steel pan
JP3068830B2 (en) Slab cutting method in continuous casting
JP7077827B2 (en) Manufacturing schedule determination device, manufacturing schedule determination method and program
JP4492332B2 (en) Cast knitting apparatus and cast knitting method
JP5569413B2 (en) Production plan creation device and production plan creation method
JP7234721B2 (en) PLANNING DEVICE, PLANNING METHOD, AND PROGRAM
JP2011081624A (en) Production plan preparing method, production plan preparing device, and computer program
JP2019098350A (en) Plan creation device, plan creation method, and program
JP7196663B2 (en) Control device, method and program for continuous casting process
JP4658525B2 (en) Production planning program
JP4025449B2 (en) Production planning organization
JP5862596B2 (en) Billet cutting plan creation device and billet cutting plan creation method
JP3705009B2 (en) Production plan creation method
Gagné et al. Scheduling a single machine where setup times are sequence dependent using an ant-colony heuristic
JP5338269B2 (en) Slab sampling control method
JP2007179519A (en) Production plan creation method and apparatus
JP2007206980A (en) Lot planning method, lot planning device, and computer program

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040520

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040601

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040625

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040727

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040809

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3589199

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070827

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080827

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080827

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090827

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090827

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100827

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110827

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120827

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120827

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130827

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees