Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP3604736B2 - Exterior wall construction method - Google Patents
[go: Go Back, main page]

JP3604736B2 - Exterior wall construction method - Google Patents

Exterior wall construction method Download PDF

Info

Publication number
JP3604736B2
JP3604736B2 JP17191894A JP17191894A JP3604736B2 JP 3604736 B2 JP3604736 B2 JP 3604736B2 JP 17191894 A JP17191894 A JP 17191894A JP 17191894 A JP17191894 A JP 17191894A JP 3604736 B2 JP3604736 B2 JP 3604736B2
Authority
JP
Japan
Prior art keywords
wall
wall material
building
packing
corner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP17191894A
Other languages
Japanese (ja)
Other versions
JPH0819995A (en
Inventor
義雄 小島
信比古 野口
達雄 矢田
明 江澤
光明 金沢
幹夫 木原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
AGC Inc
Original Assignee
Asahi Glass Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Glass Co Ltd filed Critical Asahi Glass Co Ltd
Priority to JP17191894A priority Critical patent/JP3604736B2/en
Publication of JPH0819995A publication Critical patent/JPH0819995A/en
Application granted granted Critical
Publication of JP3604736B2 publication Critical patent/JP3604736B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Finishing Walls (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【0001】
【産業上の利用分野】
本発明は外壁工法に係り、さらに詳しくは、建築物の外周面に壁面を形成しようとする際、現場における作業手順を規格化して高い品質の外壁を構築するために有効な外壁工法に関する。
【0002】
【従来の技術】
標準規格品として供給されるサイディングボードなどの窯業系板材からなる単位壁材は、耐火性や耐久性に優れているばかりでなく、外観意匠的にも好ましい造形効果を発揮させることができることから、近時、建築物の外壁材として好んで用いられるようになってきている。
【0003】
ところで、サイディングボードなどの窯業系板材からなる単位壁材を建築物の外壁材として用いる場合には、通常、建築現場で寸法合わせし、標準規格品が直ちに取り付けられる壁面部位にはそのままこれを使用し、標準規格品のままでは大き過ぎて取り付けることができない壁面部位には不要部位を切除して使用に供されていた。
【0004】
しかし、上記工法による場合には、建築現場でいちいち寸法合わせをする必要があり作業的に煩雑であるほか、端材が残材として発生して省資源を志向する時代の要請に反するのみならず、これを廃棄するための処理コストも別途にかかってしまうなどの欠点があった。
【0005】
また、このような欠点を解消する手法としては、標準規格品である単位壁材としての外壁材を建築現場に搬出する前に、建築物に形成しようとしている壁面との関係を勘案し、必要のあるものは工場にて所望するサイズにプレカットし、このプレカット壁材として用意される外壁材を規格品としての外壁材と共に建築現場に搬入して建築物に取り付け、残材となる端材の発生を極力少なくした外壁工法も既に提案されるに至っている。
【0006】
しかも、この場合、標準規格品である単位壁材としての外壁材と、プレカット壁材としての外壁材とが混在した状態のもとで建築現場に搬入されることになるため、各外壁材には、その裏面側に壁面を形成する際に割り当てられるべき個々の壁面部位を示す識別記号が付され、この識別記号により各外壁材を仕分けることで正しい壁面位置に取り付けられるようになっていた。
【0007】
【発明が解決しようとする課題】
ところで、各外壁材の裏面に識別記号を付して行われる上記従来工法によっても、建築現場に端材を残材として発生させることなく建築物の壁面を正しい位置関係のもとで形成することはできる。
【0008】
しかし、上記従来工法による場合、前記識別記号は、各外壁材の裏面に付されているので、各外壁材を積み重ねた状態のもとで建築現場に搬入した際、いちいち1枚ずつ取り出してその裏面側に付されている識別記号を個別に確認しながら取付け作業を遂行する必要があり、作業効率を高める上での阻害要因となる不都合があった。
【0009】
さらには、建築物の躯体の側の精度如何によっては、外壁材を所定の手順に従って順次取り付けていくうちに、寸法の合わない外壁材が出てくる可能性もあり、その際の調整作業に労力がさかれてしまう不具合もあった。
【0010】
特に、窓等の開口部を壁面に備える建築物にあっては、プレカット壁材を前記開口部回りの外壁材として用いる際、結果的にプレカット寸法が合わなくなってしまうこともあり、このような場合における寸法合わせのための再調整作業が煩雑になる問題あった。
【0011】
また、建築物における出隅部分や入り隅部分に位置する壁面は、対応する外壁材相互が突き合わされる部位であり、プレカット壁材をこのような隅部に外壁材として用いる場合には、取り付けて壁面を形成した際に突き合わされる端部相互が不揃いになってしまうこともあり、これを調整するための作業が必要になる不都合もあった。
【0012】
【課題を解決するための手段】
本発明は従来技術にみられた上記課題に鑑みてなされたものであり、そのうち、請求項1記載の外壁工法の構成上の特徴は、それぞれを水平載置して積み重ねた際に表出する端面の側に建築物に壁面を形成する際の割当て位置との関係で定まる必要情報を個別に教示するための識別記号が付された標準規格品としての単位壁材と、この単位壁材の裏面にカット位置を割り付けるために予め墨付けして同様に識別記号が付された墨付け壁材と、前記単位壁材から不要部分のすべてもしくは一部を事前に切除して同様に識別記号が付されたプレカット壁材との少なくともいずれか一種もしくは二種以上を任意に組み合わせて構成される複数枚の外壁材が用いられ、これら複数枚の外壁材は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねる積重ね梱包により梱包し、その施工時には、梱包状態を解除して最上位に位置する外壁材から順次取り出し、必要があれば所定のカット処理を行い、その端面に付された前記識別記号が教示する壁面部位が建築物における窓等の開口部が位置する部位を含み、この開口部の開口縁部と突き合わされる外壁材の対応部位は、開口部の周縁部に予め配設されている囲枠材が備える受け溝部内に納めながら取り付けることで壁面を形成することにある。 なお、本発明に用いられる各外壁材は、前記積重ね梱包をさらに建築物の各壁面が向いている方位の別に仕分けた方位別梱包により用意したり、前記積重ね梱包または前記方位別梱包をさらに建築物の各階別に仕分けた各階別梱包により用意することができる。
【0013】
また、請求項記載の外壁工法の構成上の特徴は、それぞれを水平載置して積み重ねた際に表出する端面の側に建築物に壁面を形成する際の割当て位置との関係で定まる必要情報を個別に教示するための識別記号が付された標準規格品としての単位壁材と、この単位壁材の裏面にカット位置を割り付けるために予め墨付けして同様に識別記号が付された墨付け壁材と、前記単位壁材から不要部分のすべてもしくは一部を事前に切除して同様に識別記号が付されたプレカット壁材との少なくともいずれか一種もしくは二種以上を任意に組み合わせて構成される複数枚の外壁材が用いられ、これら複数枚の外壁材は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねる積重ね梱包により梱包し、その施工時には、梱包状態を解除して最上位に位置する外壁材から順次取り出し、必要があれば所定のカット処理を行い、その端面に付された前記識別記号が教示する壁面部位が建築物において出隅もしくは入隅が位置する隅部を含み、この隅部にて突き合わされる外壁材の対応部位は、前記隅部に外側から配設される役物材により隠蔽して取り付けることで壁面を形成すること にある。なお、本発明に用いられる各外壁材は、前記積重ね梱包をさらに建築物の各壁面が向いている方位の別に仕分けた方位別梱包により用意したり、前記積重ね梱包または前記方位別梱包をさらに建築物の各階別に仕分けた各階別梱包により用意することができる。
【0014】
【0015】
【0016】
【作用】
このため、請求項1記載の外壁工法によれば、端面に識別記号が付された単位壁材と墨付け壁材とプレカット壁材とで構成される外壁材が用いられ、しかも、これら各外壁材は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねて梱包されているので、梱包を解いた際に最上位に位置している外壁材から順に取り出し、その端面に付されている前記識別記号を確認することで予め割り当てられている壁面部位との関係で定まる必要情報を容易に知ることができ、したがって、誰もが手際よく正確に壁面を形成することができる。
【0017】
また、請求項記載の外壁工法によれば、上記作用効果に加え、建築物の開口部を区画している開口縁部と突き合わされる外壁材の対応部位を囲枠材の受け溝部内に納めて取り付けることができるので、特にプレカット壁材を前記開口部回りの外壁材として用いる際にプレカット寸法が合わなくなってしまうことがあっても、これを受け溝部内に納めることで不揃いになる外壁材の端部を目隠しつつ、その寸法誤差を吸収しながら開口部回りに外壁材を取り付けることで作業性の向上を図ることができる。
【0018】
一方、請求項4記載の外壁工法によれば、請求項1記載の外壁工法と同様に端面に識別記号が付された単位壁材と墨付け壁材とプレカット壁材とで構成される外壁材が用いられ、しかも、これら各外壁材は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねて梱包されているので、梱包を解いた際に最上位に位置している外壁材から順に取り出し、その端面に付されている前記識別記号を確認することで予め割り当てられている壁面部位との関係で定まる必要情報を容易に知ることができ、したがって、誰もが手際よく正確に壁面を形成することができる。
【0019】
た、請求項記載の外壁工法によれば、上記作用効果に加え、建築物の出隅もしくは入隅が位置する隅部にて突き合わされる外壁材の突合せ端部が仮に不揃いになってしまうことがあっても、これら突合せ端部を含む隅部を外側から役物材により隠蔽することができるので、その調整作業を不必要なものとすることで作業性の向上を図ることができる。なお、請求項1記載の外壁工法と請求項4記載の外壁工法とのいずれにおいても、前記各外壁材が建築物の各壁面が向いている方位の別に細分化して梱包(方位別梱包)されている場合には、例えば東西南北の別に外壁材を搬入することができるので、外壁材の混在をなくして作業性の向上を図ることができ、また、前記積重ね梱包または前記方位別梱包をさらに建築物の各階別に仕分けた各階別梱包により用意されている場合には、現場での仕分け作業をなくして作業能率をより高めることができる。
【0020】
【実施例】
本発明に係る外壁工法に用いられる外壁材は、建築物の外周面に壁面を形成する際に用いるべく例えば2730mm(横)×455mm(縦)×16mm(厚み)など、適宜の規格サイズからなる標準規格品として用意される窯業系板材としての単位壁材と、この単位壁材の裏面にカット位置を割り付けるために予め墨付けして用意される墨付け壁材と、前記単位壁材から不要部分のすべてもしくは一部を事前に切除して用意されるプレカット壁材とを含むものである。なお、前記外壁材は、窯業系板材のほか、必要に応じコンクリート系板材など、他の適宜の素材からなる板材を用いるものであってもよい。
【0021】
図1は、上記外壁材についての一例を示す一部を省略した斜視図であり、前記単位壁材や墨付け壁材やプレカット壁材からなる外壁材11は、その表面12の側に例えば本物のレンガ積みと同じような意匠的な雰囲気を醸成することができる凹凸模様や色彩を付すなどした適宜の意匠的な処理が施されているものを用いるのが好ましく、通常、建築物の側に取り付けるために必要な適宜の構造的な加工を施すことでその全体が形成されている。
【0022】
また、前記外壁材11は、小口を含む端面13のいずれか一箇所もしくは複数箇所に前記壁面を形成する際に割り当てられている個々の壁面部位との関係で定まる必要情報を教示するための識別記号15を直接マーキングし、あるいは図示例のように「イ−1−a」などの識別記号15が予め印字手段やスタンピング手段などの適宜の表示手段により表示されている貼着用テープ片14を貼り付けるなどして形成されており、複数の外壁材11を水平載置して積み重ねた際に各外壁材11に付されている識別記号15の目視確認が自在となっている。
【0023】
なお、識別記号15は、壁面における最下側を意味するものを「イ」とし、この最下側での右隅部を意味するものを「1」とし、その際の取付け手法の種類を特定するものを「a」として「イ−1−a」と表示するなど、組み合わされるそれぞれの記号に特定の意味を付与し、これを見る作業者がその意味することを理解できる適宜のパターンのもとで施工作業上必要となる情報を表示することができる。
【0024】
発明における請求項1および4に記載の外壁工法は、上記外壁材を用いて行われる。
【0025】
すなわち、本発明方法において外壁材11は、それぞれを水平載置して積み重ねた際に表出する端面13の側に建築物に壁面を形成する際の割当て位置との関係で定まる施工作業上必要な情報を個別に教示するための識別記号15が付された標準規格品としての単位壁材11aと、この単位壁材の裏面にカット位置を割り付けるために予め墨付けして同様に識別記号15が付された墨付け壁材11cと、前記単位壁材から不要部分のすべてもしくは一部を事前に切除して同様に識別記号15が付されたプレカット壁材11bとの少なくともいずれか一種もしくは二種以上を任意に組み合わせて使用される。
【0026】
この場合、各外壁材11(11a,11b,11c)は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねて、例えば止着バンド16を巻き付けるなど、適宜の梱包手段により積重ね梱包することで図2に示すようにワンパック化して用意されることになる。
【0027】
因に、外壁材11を土台が位置する基礎側から屋根側へと順に積み上げられながら壁面が形成される場合にあっては、図2において識別記号15が「ホ−2−a」として示される最下位に位置する外壁材11はワンパック化されて梱包状態にある当該各外壁材11のなかで最後に取り付けられるべきものとなり、識別記号15が「イ−1−a」として示される最上位に位置する外壁材11は最初に取り付けられるべきものとなる。
【0028】
このようにワンパック化して梱包された各外壁材11は、建築現場に搬入された後、その梱包状態が解かれ、最上位に位置する外壁材11(11a)から順次取り出し、その端面13に付された前記識別記号15が教示する壁面部位との関係で定まる必要情報に従った所定の段取りのもとで取付け施工され、壁面が形成される。
【0029】
また、本発明方法において前記各外壁材11は、建築物の各壁面が向いている例えば東西南北からなる方位の別に細分化して梱包する方位別梱包により行ってもよく、その場合の識別記号15は、例えば図3の(イ)に示すように南面を意味する「S」と、壁面の最下側を意味する「イ」と、この最下側での右隅部を意味する「1」と、その際の取付け手法の種類を特定する「a」とを組み合わせた「S−イ−1−a」などとして表示されることになる。
【0030】
さらに、建築物が二階建て以上のものである場合は、当該建築物の階数の別にさらに細分化して梱包する各階別梱包によって行ってもよく、その場合の識別記号15は、例えば図3の(ロ)に示すように階数が一階であることを示す「F1 」と、その方位が南面であることを意味する「S」と、取り付けるべき壁面部位が壁面の最下側を意味する「イ」と、そのなかでの右隅部を意味する「1」と、その際の取付け手法の種類を特定する「a」とを組み合わせた「F1 −S−イ−1−a」などとして表示されることになる。
【0031】
しかも、前記識別記号15が教示する壁面部位には、図4に示すように建築物21におけるサッシ窓27などが配設される開口部23が位置する部位を含むものであり、図5と図6とからも明らかなように開口部23を区画している開口縁部24と突き合わされる外壁材11の対応部位17は、開口部23の周縁部に予め配設されている囲枠材25の側に納め入れながら取り付けることで壁面22として形成される
【0032】
すなわち、外壁材11と同様な窯業系板材などの素材のほか、アルミニウム等の金属材や合成樹脂材や木材など用いて形成される前記囲枠材25は、止着用釘材28を用いることで開口縁部24の近傍に配置されている構造木材29の側に固着されている。
【0033】
しかも、前記囲枠材25は、前記開口縁部24と突き合わされるような配置関係のもとで対面する外壁材11の対応部位17の側に向けて開口する受け溝部26を有しており、この受け溝部26内に外壁材11の前記対応部位17を納め入れることで開口部23回りの壁面22が形成されることになる。
【0034】
なお、外壁材11の前記対応部位17は、水膨張性ゴム材などからなる第1止水材30やシーリング材などからなる第2止水材31を介在させるなど、適宜のシーリング処理を施すことで囲枠材25の受け溝部26内に納め入れるのが望ましい。
【0035】
一方、請求項記載の発明は、請求項1記載の外壁工法に用いられる外壁材と同じ外壁材を用いて行われるものであり、前記識別記号15が教示する壁面部位には建築物21において出隅33aもしくは入隅33bが位置する隅部33を含み、この隅部33にて突き合わされる外壁材11の対応部位は、図7と図8とに示すように前記隅部33に外側から配設される役物材34により隠蔽して取り付けることで壁面を形成することに特徴がある。
【0036】
すなわち、外壁材11と同様な窯業系板材などの素材のほか、アルミニウム等の金属材や合成樹脂材や木材など用いて形成される前記役物材34は、隅部33にて突き合わされる外壁材11の対応部位をその外側から覆設するようにして配設され、止着用釘材を用いるなどして構造木材の側に固着され、役物材34の外縁部をシーリング材35で封止して壁面22が形成されることになる。なお、役物材34は、例えば図示例のように出隅33aに形成される稜角や入隅33bに形成される内角に対応させた断面L字形を呈するものなど、適宜の断面形状を呈するものを採用することができる。
【0037】
また、本発明方法においも前記各外壁材11は、建築物の各壁面が向いている例えば東西南北からなる方位の別に細分化して梱包する方位別梱包により行ってもよく、その場合の識別記号15は、例えば図3の(イ)に示すように南面を意味する「S」と、壁面の最下側を意味する「イ」と、この最下側での右隅部を意味する「1」と、その際の取付け手法の種類を特定する「a」とを組み合わせた「S−イ−1−a」などとして表示されることになる。さらに、建築物が二階建て以上のものである場合は、当該建築物の階数の別にさらに細分化して梱包する各階別梱包によって行ってもよく、その場合の識別記号15は、例えば図3の(ロ)に示すように階数が一階であることを示す「F 1 」と、その方位が南面であることを意味する「S」と、取り付けるべき壁面部位が壁面の最下側を意味する「イ」と、そのなかでの右隅部を意味する「1」と、その際の取付け手法の種類を特定する「a」とを組み合わせた「F 1 −S−イ−1−a」などとして表示されることになる。
【0038】
本発明は上述したようにして構成されているので、請求項1記載の外壁工法によれば、端面13に識別記号15が付された単位壁材11aとプレカット壁材11bと墨付け壁材11cとで構成される外壁材11が用いられ、しかも、これら各外壁材11(11a,11b,11c)は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねて梱包されているので、梱包を解いた際に図2に示すように最上位に位置している外壁材11(11a)から順に取り出し、その端面13に付されている前記識別記号15を確認することで、それぞれの外壁材11(11a,11b,11c)に予め割り当てられている壁面部位との関係で定まる施工作業上必要とされる情報を容易に知ることができる。
【0039】
したがって、本発明方法によれば、前記識別記号15から与えられる情報に従い、熟練の程度とは無関係に誰もが手際よく、かつ、正確に壁面を形成することができる。
【0040】
なお、前記各外壁材11が識別記号15に従い建築物の各壁面が向いている例えば東西南北の方位の別に細分化して梱包(方位別梱包)されている場合には、方位の別に外壁材11を搬入することができるので、在庫管理を容易化して外壁材の混在をなくすことで作業性の向上を図ることができる。
【0041】
また、前記識別記号15に従いさらに細分化して建築物の各階別に各外壁材11が梱包(各階別梱包)されている場合には、現場での仕分け作業をなくして作業能率をより高めることができる。
【0042】
しかも、請求項記載の外壁工法によれば、上記作用効果に加え、建築物21の開口部23を区画している開口縁部24と突き合わされる外壁材11の対応部位17は、囲枠材25の受け溝部26内に納め入れて取り付けることができる。
【0043】
このため、特にプレカット壁材11bを前記開口部23回りの外壁材11として用いる場合には、仮にプレカット寸法が合わなくなってしまうことがあっても、これを受け溝部26内に納め入れることで不揃いになる外壁材11の端部を目隠しすることができ、しかも、このような寸法誤差を受け溝部26内に納め入れることで吸収することができるので、開口部23回りに外壁材11を取り付けて壁面22を形成する際の作業性の向上を図ることができる。
【0044】
一方、請求項記載の外壁工法によれば、請求項記載の外壁工法が奏する作用効果に加え、建築物の躯体の側の精度との関係もあって、建築物の出隅33aもしくは入隅33bが位置する隅部33にて突き合わされる外壁材11の突合せ端部が仮に不揃いになってしまうことがあっても、これら外壁材11の突合せ端部を含む隅部33を、出隅33aの場合は図7に示すように、入隅33bの場合は図8に示すようにそれぞれ外側から役物材34により隠蔽することができるので、その調整作業を不必要なものとすることで作業性の向上を図ることができる。なお、前記各外壁材11が請求項1記載の外壁工法と同様に方位別梱包や各階別梱包により梱包されている場合は、既に述べた請求項1記載の外壁工法におけると同様な作用効果を得ることができる。
【0045】
【発明の効果】
【0046】
以上述べたように本発明における請求項1および4に記載の外壁工法によれば、端面に識別記号が付された単位壁材と墨付け壁材とプレカット壁材とで構成される外壁材が用いられ、しかも、これら各外壁材は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねて梱包されているので、梱包を解いた際に最上位に位置している外壁材から順に取り出し、その端面に付されている前記識別記号を確認することで予め割り当てられている壁面部位との関係で定まる必要情報を容易に知ることができ、したがって、誰もが手際よく正確に壁面を形成することができる。
【0047】
また、本発明の請求項1および4に記載の外壁工法において、前記各外壁材が建築物の各壁面が向いている方位の別に細分化して梱包(方位別梱包)されている場合には、例えば東西南北の別に外壁材を搬入することができるので、外壁材の混在をなくして作業性の向上を図ることができ、さらに、本発明の請求項1および4に記載の外壁工法において、前記積重ね梱包または前記方位別梱包をさらに建築物の各階別に仕分けた各階別梱包によ り用意されている場合には、現場での仕分け作業をなくして作業能率をより高めることができる。
【0048】
しかも、請求項記載の外壁工法によれば、上記作用効果に加え、建築物の開口部を区画している開口縁部と突き合わされる外壁材の対応部位を囲枠材の受け溝内に納めて取り付けることができるので、特にプレカット壁材を前記開口部回りの外壁材として用いる際にプレカット寸法が合わなくなってしまうことがあっても、これを受け溝内に納めることで不揃いになる外壁材の端部を目隠しつつ、その寸法誤差を吸収しながら開口部回りに外壁材を取り付けることで作業性の向上を図ることができる。
【0049】
一方、請求項記載の外壁工法によれば、建築物の出隅もしくは入隅が位置する隅部にて突き合わされる外壁材の突合せ端部が仮に不揃いになってしまうことがあっても、これら突合せ端部を含む隅部を外側から役物材により隠蔽することができるので、その調整作業を不必要なものとすることで作業性の向上を図ることができる。
【図面の簡単な説明】
【図1】本発明における請求項1および4記載の外壁工法に用いられる外壁材の一例を示す一部を省略した斜視図である。
【図2】本発明における請求項1および4記載の外壁工法に用いられる外壁材の積重ね梱包時における状態例を示す説明図である。
【図3】本発明における請求項1および4記載の外壁工法に用いられる外壁材の端面に付された識別記号の表示例を示す説明図であり、このうち、(イ)は方位別梱包時における表示例を、(ロ)は各階別梱包時における表示例をそれぞれ示す。
【図4】本発明における請求項記載の外壁工法により実現される建築物の開口部回りを示す正面説明図である。
【図5】図4における一例としてのA−A線断面図である。
【図6】図4における一例としてのB−B線断面図である。
【図7】本発明における請求項記載の外壁工法により実現される建築物の出隅部分の状態を示す説明図である。
【図8】本発明における請求項記載の外壁工法により実現される建築物の入隅部分の状態を示す説明図である。
【符号の説明】
11 外壁材
11a 単位壁材
11b プレカット壁材
11c 墨付け壁材
12 表面
13 端面
14 貼着用テープ片
15 識別記号
16 止着バンド
17 対応部位
21 建築物
22 壁面
23 開口部
24 開口縁部
25 囲枠材
26 受け溝部
27 サッシ窓
28 止着用釘材
29 構造木材
30 第1止水材
31 第2止水材
33 隅部
33a 出隅
33b 入隅
34 役物材
35 シーリング材
[0001]
[Industrial applications]
The present inventionIs outsideRegarding the wall construction method, more specifically, when forming a wall on the outer peripheral surface of a building, it is effective to standardize work procedures on site and build high quality outer wallsExterior wallConcerning the construction method.
[0002]
[Prior art]
Unit wall materials made of ceramic-type board materials such as siding boards supplied as standard products are not only excellent in fire resistance and durability, but also can exert favorable modeling effects in appearance design, Recently, it has come to be used as an outer wall material of buildings.
[0003]
By the way, when a unit wall material made of ceramic board such as siding board is used as an outer wall material of a building, it is usually necessary to adjust the dimensions at the construction site and use it as it is on the wall part where standard products can be installed immediately. However, unnecessary portions were cut off from the wall portions that cannot be attached because they were too large to be used as standard products.
[0004]
However, in the case of the above-mentioned construction method, it is necessary to adjust the dimensions at the construction site, which is troublesome in terms of work. However, there is a drawback that the processing cost for discarding this is separately required.
[0005]
Also, as a method of solving such disadvantages, it is necessary to consider the relationship with the wall to be formed on the building before transporting the outer wall material as a unit wall material, which is a standard product, to the building site. Some of the pre-cut materials are precut to the desired size at the factory, and the outer wall material prepared as this pre-cut wall material is carried into the building site together with the outer wall material as a standard product, attached to the building, and the remaining material Exterior wall construction methods that minimize the occurrence have already been proposed.
[0006]
Moreover, in this case, the outer wall material as a unit wall material, which is a standard specification product, and the outer wall material as a pre-cut wall material are transported to the building site in a mixed state, so that each outer wall material is On the back surface side, an identification code indicating an individual wall surface portion to be allocated when forming a wall surface is attached, and each of the outer wall materials is sorted by the identification code so that the outer wall material can be attached to a correct wall position.
[0007]
[Problems to be solved by the invention]
By the way, even with the above-mentioned conventional method, which is performed by attaching an identification code to the back surface of each outer wall material, it is necessary to form the wall surface of the building with the correct positional relationship without generating scrap materials at the building site as residual material. Can.
[0008]
However, in the case of the above-mentioned conventional method, since the identification symbol is attached to the back surface of each outer wall material, when each of the outer wall materials is transported to a building site in a stacked state, it is taken out one by one and the outer wall material is taken out one by one. It is necessary to perform the mounting work while individually checking the identification symbols attached to the back surface side, and there is a disadvantage that it becomes a hindrance factor in improving work efficiency.
[0009]
Furthermore, depending on the accuracy of the building's skeleton, there is a possibility that the outer wall material that does not match the dimensions may come out as the outer wall material is sequentially attached according to the predetermined procedure. There was also a problem that labor was saved.
[0010]
In particular, in a building having an opening such as a window on a wall surface, when a precut wall material is used as an outer wall material around the opening, the precut dimensions may not be matched as a result. Problem that readjustment work for size adjustment in case is complicatedButthere were.
[0011]
In addition, the walls located at the outer corner and the inner corner of the building are portions where the corresponding outer wall materials are abutted with each other, and when a precut wall material is used as an outer wall material at such a corner, the wall is attached. When the wall surfaces are formed, the abutting ends sometimes become irregular, and there is also a disadvantage that an operation for adjusting the ends is required.
[0012]
[Means for Solving the Problems]
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems in the prior art.Construction methodThe structural features ofA standard with an identification symbol attached on the side of the end face that is exposed when they are horizontally placed and stacked, to individually teach necessary information that is determined in relation to the assigned position when forming the wall surface on the building A unit wall material as a standard product, a blackened wall material that has been previously blackened and similarly identified with an identification code in order to assign a cut position to the back surface of the unit wall material, and all unnecessary parts from the unit wall material Alternatively, a plurality of outer wall materials, which are configured by arbitrarily combining at least one kind or two or more kinds with a precut wall material similarly cut out and affixed with an identification symbol are used. The outer wall material is packed by stacking packing in the order of use so that the last used at the site is the lowest, the first used is the highest, and the packing state is released at the time of construction do it Take out sequentially from the outer wall material located on the upper layer, perform a predetermined cutting process if necessary, and the wall surface part taught by the identification symbol attached to the end surface includes the part where the opening such as the window in the building is located. The corresponding portion of the outer wall material that is brought into contact with the opening edge of the opening is attached to the receiving groove provided in the surrounding frame material provided in advance on the peripheral edge of the opening to form a wall surface. It is in. In addition, each outer wall material used in the present invention may be prepared by azimuth packing in which the stacked packing is further sorted according to the direction in which each wall face of the building faces, or the stacked packing or the azimuth packing is further constructed. It can be prepared by packing on each floor sorted by each floor of the goods.
[0013]
Claims4The structural features of the exterior wall method described are that the necessary information that is determined by the relationship with the assigned position when forming the wall surface on the building on the side of the end face that appears when each is placed horizontally and stacked is individually A unit wall material as a standard product to which an identification code for teaching is attached, and a blackened wall material which has been previously blackened and similarly assigned an identification code for allocating a cut position to the back surface of the unit wall material A plurality of pre-cut wall materials, which are previously cut out of all or a part of unnecessary portions from the unit wall material and similarly labeled with an identification code, and arbitrarily combined with at least one kind or two or more kinds. The outer wall materials are stacked in the order in which they are used, with the last used on site at the bottom and the first used at the top.By stackingAt the time of packing, at the time of construction, the packing state is released and sequentially taken out from the outermost wall material located at the highest position, if necessary, a predetermined cutting process is performed, and the wall surface portion taught by the identification symbol attached to the end surface thereofIncludes a corner where an outgoing corner or an incoming corner is located in a building, and the corresponding portion of the outer wall material abutted at this corner is concealed by an accessory material arranged from the outside at the corner.It is to form a wall surface by attaching.In addition, each outer wall material used in the present invention may be prepared by azimuth packing in which the stacked packing is further sorted according to the direction in which each wall face of the building faces, or the stacked packing or the azimuth packing is further constructed. It can be prepared by packing on each floor sorted by each floor of the goods.
[0014]
[0015]
[0016]
[Action]
Therefore, the outer wall according to claim 1Construction methodAccording toAn outer wall material composed of a unit wall material with an identification symbol attached to an end face, a blackened wall material, and a precut wall material is used, and each of these outer wall materials is the one used last on site at the lowest order. Since the first used items are stacked and packed in the order of their use so that they are located at the highest level, when unpacking, take out the outer wall material located at the highest position in order and attach it to the end face. By confirming the identification symbol, it is possible to easily know necessary information determined in relation to the previously assigned wall surface portion, and therefore, anyone can form the wall surface efficiently and accurately.
[0017]
Claims1According to the described exterior wall method,In addition to the above functions and effects, the corresponding portion of the outer wall material, which is brought into contact with the opening edge parting the opening of the building, can be accommodated in the receiving groove of the surrounding frame material and attached. Even if the pre-cut dimensions may not fit when used as the outer wall material around the opening, the dimensional error is absorbed while the end of the outer wall material, which becomes irregular by being accommodated in the groove, is closed. By attaching the outer wall material around the opening, workability can be improved.
[0018]
On the other hand, according to the outer wall construction method according to the fourth aspect, similarly to the outer wall construction method according to the first aspect, an outer wall material composed of a unit wall material, an inking wall material, and a precut wall material, each of which has an identification symbol attached to an end surface. Are used, and these outer wall materials are stacked in the order of use so that the one used last on the site is located at the bottom and the one used first is located at the top, and are packed. When unpacking, take out the outer wall material located in the highest position in order, and check the identification symbol attached to the end face to easily obtain the necessary information determined in relation to the pre-assigned wall part. Therefore, anyone can form the wall surface efficiently and accurately.
[0019]
MaClaims4According to the described exterior wall method,the aboveIn addition to the function and effect, even if the abutting ends of the outer wall material abutted at the corner where the outgoing corner or the inward corner of the building is located may become irregular, the corners including these abutting ends Can be concealed from the outside by the accessory material, so that the adjustment work is unnecessary, and the workability can be improved.In both of the outer wall method according to claim 1 and the outer wall method according to claim 4, each of the outer wall materials is subdivided and packed according to the direction of each wall surface of the building (packing by direction). In the case of, for example, since the outer wall material can be carried separately in the east, west, north and south, the workability can be improved by eliminating the mixture of the outer wall material, and the stacked packing or the packing according to the orientation can be further performed. In the case where the building is prepared by packing each floor sorted by each floor, the work efficiency can be further improved by eliminating the sorting work on site.
[0020]
【Example】
In the present inventionUsed for such external wall construction methodThe outer wall material is a ceramic type material prepared as a standard product having an appropriate standard size such as 2730 mm (horizontal) × 455 mm (vertical) × 16 mm (thickness) to be used when forming a wall surface on the outer peripheral surface of a building. A unit wall material as a plate material, a blackened wall material prepared by blacking in advance to allocate a cut position to the back surface of the unit wall material, and all or a part of unnecessary portions from the unit wall material in advance And a precut wall material prepared by cutting. In addition, as the outer wall material, a plate material made of another appropriate material such as a concrete plate material as needed may be used in addition to the ceramic plate material.
[0021]
FIG. 1 shows the outer wall material.One caseIt is a perspective view in which a part of the wall material is omitted, and the outer wall material 11 made of the unit wall material, the blackened wall material, and the pre-cut wall material has a design similar to a real brickwork on the surface 12 side thereof. It is preferable to use one that has been subjected to an appropriate design treatment such as adding a concavo-convex pattern or color that can create an atmosphere, and usually, an appropriate structural structure necessary for attaching to the building side The whole is formed by performing the processing.
[0022]
Further, the outer wall material 11 is an identification for teaching necessary information determined in relation to individual wall portions assigned when forming the wall surface at any one or more of the end faces 13 including the forehead. The mark 15 is directly marked, or a sticking tape piece 14 on which the identification mark 15 such as "I-1-a" is displayed in advance by an appropriate display means such as a printing means or a stamping means as shown in the figure is attached. When the plurality of outer wall materials 11 are horizontally placed and stacked, the identification symbols 15 attached to the respective outer wall materials 11 can be visually checked.
[0023]
Note that the identification symbol 15 is "a" for the lowermost side of the wall surface and is "1" for the right corner at the lowermost side, and specifies the type of mounting method at that time. For example, an appropriate pattern that gives a specific meaning to each symbol to be combined, such as displaying “a” as “a” as “a”, and allowing an operator who sees this to understand the meaning, is also used. Thus, information necessary for the construction work can be displayed.
[0024]
BookClaims in the invention1 and 4The described outer wall method isthe aboveThis is performed using an outer wall material.
[0025]
That is, in the method of the present invention, the outer wall material 11 is necessary for construction work determined by the relationship with the assigned position when forming the wall surface on the building on the side of the end face 13 that is exposed when they are horizontally placed and stacked. Unit material 11a as a standard product to which an identification symbol 15 for individually teaching important information is attached, and the identification symbol 15 is similarly applied by blacking in advance to assign a cut position to the back surface of the unit wall material. , And at least one or both of a precut wall material 11b to which all or a part of an unnecessary portion is previously cut off from the unit wall material and the identification symbol 15 is similarly attached. Any combination of more than one species is used.
[0026]
In this case, the outer wall materials 11 (11a, 11b, 11c) are stacked in the order of use such that the one used last in the field is located at the bottom and the one used first is located at the top, for example, By appropriate packing means such as winding the fastening band 16StackBy packing, as shown in FIG. 2, one pack is prepared.
[0027]
In the case where the wall surface is formed while the outer wall materials 11 are sequentially stacked from the foundation side where the base is located to the roof side, the identification symbol 15 is indicated as “e-2-a” in FIG. 2. The outermost wall material 11 located at the lowest position is to be attached last in each of the outer wall materials 11 in a packed state in a packed state, and the identification symbol 15 is the uppermost one indicated by “A-1-a”. Is to be attached first.
[0028]
Each of the outer wall materials 11 packed in a single pack in this manner is transported to a construction site, and then unpacked, taken out from the outermost wall material 11 (11a) positioned at the top, and sequentially taken out to the end face 13. The wall is formed under a predetermined setup in accordance with necessary information determined in relation to the wall surface portion taught by the attached identification symbol 15 to form a wall surface.
[0029]
In the method of the present invention, each of the outer wall materials 11 is subdivided and packed according to a direction, for example, east, west, north and south, where each wall of the building faces.Go by packing by directionIn this case, the identification symbol 15 may be, for example, "S" meaning the south side as shown in FIG. 3A, "A" meaning the bottom side of the wall, and "I" indicating the bottom side of the wall. It is displayed as "S-I-1-a" or the like in which "1" meaning the right corner and "a" specifying the type of attachment method at that time are combined.
[0030]
In addition, if the building is more than two stories high, it is further subdivided according to the number of floors of the building and packed.Go by packing each floorIn this case, the identification symbol 15 may be, for example, "F1" indicating that the floor is the first floor as shown in (b) of FIG. Combination of "A", which means the bottom wall of the wall to be attached, "1", which means the right corner of the wall, and "a", which specifies the type of attachment method at that time Will be displayed as "F1-S-1-a".
[0031]
And beforeThe wall part taught by the identification symbol 15InAs shown in FIG. 4, it includes a portion where the opening 23 where the sash window 27 and the like in the building 21 are disposed is located, and the opening 23 is partitioned as is clear from FIGS. 5 and 6. The corresponding portion 17 of the outer wall material 11, which abuts against the opening edge portion 24, is attached to the surrounding edge portion of the opening portion 23 while being inserted into the side of the surrounding frame member 25, thereby mounting the wall surface 22.Formed as.
[0032]
That is, in addition to materials such as ceramic plate materials similar to the outer wall material 11, the surrounding frame material 25 formed using a metal material such as aluminum, a synthetic resin material, wood, or the like is obtained by using a fastening nail material 28. It is fixed to the side of the structural wood 29 arranged near the opening edge 24.
[0033]
In addition, the surrounding frame member 25 has a receiving groove portion 26 that opens toward the corresponding portion 17 of the outer wall member 11 facing the opening edge portion 24 in an arrangement relationship such that the surrounding frame member 25 faces the opening edge portion 24. By fitting the corresponding portion 17 of the outer wall material 11 into the receiving groove 26, the wall surface 22 around the opening 23 is formed.
[0034]
The corresponding portion 17 of the outer wall material 11 is subjected to an appropriate sealing treatment such as interposing a first water-stopping material 30 made of a water-expandable rubber material or the like and a second water-stopping material 31 made of a sealing material or the like. It is desirable to put it in the receiving groove 26 of the surrounding frame member 25 with the above.
[0035]
on the other hand, Claims4The invention described in the claims1 is performed using the same outer wall material as the outer wall material used in the outer wall method.The wall portion taught by the identification symbol 15 includes a corner 33 where the outgoing corner 33a or the entering corner 33b is located in the building 21, and the corresponding portion of the outer wall material 11 abutted at the corner 33 is shown in FIG. As shown in FIG. 8 and FIG. 8, it is characterized in that the wall surface is formed by concealing and attaching to the corner portion 33 with the accessory material 34 arranged from the outside.
[0036]
That is, in addition to a material such as a ceramic plate material similar to the outer wall material 11, the accessory material 34 formed by using a metal material such as aluminum, a synthetic resin material, or wood, the outer wall abutted at the corner 33. It is arranged so as to cover the corresponding portion of the material 11 from the outside, and is fixed to the structural wood side using a fastening nail material or the like, and the outer edge of the accessory material 34 is sealed with a sealing material 35. As a result, the wall surface 22 is formed. The accessory material 34 has an appropriate cross-sectional shape such as an L-shaped cross-section corresponding to a ridge angle formed at the protruding corner 33a or an inner angle formed at the entering corner 33b as shown in the illustrated example. Can be adopted.
[0037]
Also, in the method of the present invention, each of the outer wall materials 11 may be formed by directional packing in which each wall of the building faces, for example, the east, west, north and south directions. Reference numeral 15 denotes, for example, "S" meaning the south face as shown in FIG. 3A, "A" meaning the lowermost side of the wall surface, and "1" meaning the right corner at the lowermost side. ”And“ a ”that specifies the type of attachment method at that time are displayed as“ S-i-1-a ”or the like. Further, when the building has two or more floors, the building may be divided into floors according to the number of floors of the building and packed by each floor. As shown in b), "F" indicating that the floor is the first floor 1 ", Which means that the azimuth is on the south side," I ", which means that the wall part to be attached is at the bottom of the wall, and" 1 ", which means the right corner in it. , "F" in combination with "a" that specifies the type of attachment method at that time 1 -S-a-1-a "or the like.
[0038]
Since the present invention is configured as described above,According to the outer wall method according to the first aspect, the outer wall material 11 composed of the unit wall material 11a, the precut wall material 11b, and the blackened wall material 11c having the identification symbol 15 attached to the end face 13 is used. Each of these outer wall materials 11 (11a, 11b, 11c) is stacked in the order of use so that the one used last on the site is located at the bottom and the one used first is located at the top. As shown in FIG. 2, when the package is unpacked, it is taken out in order from the outermost wall material 11 (11a) located at the highest position, and the identification symbol 15 attached to the end face 13 is confirmed. It is possible to easily know the information required for the construction work determined by the relationship with the wall surface portion previously allocated to each outer wall material 11 (11a, 11b, 11c).
[0039]
Therefore, according to the method of the present invention, anyone can form the wall surface skillfully and accurately according to the information given from the identification symbol 15 regardless of the level of skill.
[0040]
In addition, each outer wall material 11 faces each wall surface of the building according to the identification code 15, for example, subdivides according to the east, west, north and south directions and packs.(Packing by direction)In this case, since the outer wall material 11 can be carried in different directions, the workability can be improved by simplifying inventory management and eliminating the mixture of the outer wall material.
[0041]
In addition, each outer wall material 11 is further subdivided according to the identification symbol 15 and packed for each floor of the building.(Packing for each floor)In such a case, the sorting efficiency at the site can be eliminated, and the work efficiency can be further improved.
[0042]
Moreover, Claims1According to the described exterior wall method,the aboveIn addition to the function and effect, the corresponding portion 17 of the outer wall material 11, which abuts against the opening edge portion 24 that defines the opening portion 23 of the building 21, can be housed in the receiving groove portion 26 of the surrounding frame material 25 and attached. it can.
[0043]
For this reason, especially when the precut wall material 11b is used as the outer wall material 11 around the opening 23, even if the precut dimensions may not be matched, the precut dimensions may be received in the groove 26 to make the precut dimensions uneven. The end portion of the outer wall material 11 can be blindfolded, and furthermore, such a dimensional error can be absorbed by receiving it in the groove 26, so that the outer wall material 11 can be attached around the opening 23. Workability when forming the wall surface 22 can be improved.
[0044]
on the other hand, Claims4Claims according to the described exterior wall method1In addition to the action and effect of the described outer wall method, there is also a relationship with the accuracy of the building frame side, and the outer wall material 11 abutted at the corner 33 where the outgoing corner 33a or the entering corner 33b of the building is located. Even if the abutting ends of the outer wall material 11 may become irregular, the corners 33 including the abutting ends of the outer wall materials 11 may be replaced with the outgoing corners 33a as shown in FIG. 8 can be concealed from the outside by the accessory material 34, as shown in FIG.In the case where each of the outer wall materials 11 is packed by azimuth packing or floor-by-floor packing as in the case of the outer wall method of the first aspect, the same operation and effect as in the outer wall method of the first aspect described above are obtained. Obtainable.
[0045]
【The invention's effect】
[0046]
As described above, according to claims 1 and 4 of the present invention,According to the described outer wall method, an outer wall material composed of a unit wall material, an inking wall material, and a precut wall material with an identification symbol attached to an end face is used, and each of these outer wall materials is last The outer wall material that is located at the top when unpacking is packed because it is stacked in the order of use so that the one used for the bottom is placed at the bottom and the one used first is located at the top From the order, and by checking the identification symbol attached to the end face, it is possible to easily know necessary information determined in relation to the pre-assigned wall surface portion, and therefore, anyone can accurately and accurately Wall surfaces can be formed.
[0047]
AlsoClaims of the present invention1 and 4In the outer wall construction method described above, each outer wall material is subdivided according to the direction in which each wall surface of the building faces and packed.(Packing by direction)If it is, for example, since it is possible to carry in the outer wall material separately in the north, south, east and west, it is possible to improve the workability by eliminating the mixture of the outer wall material,furtherClaims of the present invention1 and 4In the described exterior wall method,The stacking packing or the packing according to the orientation is further classified according to each floor of the building. ReadyIn such a case, the sorting efficiency at the site can be eliminated, and the work efficiency can be further improved.
[0048]
Moreover, Claims1According to the described exterior wall method,the aboveIn addition to the function and effect, the corresponding portion of the outer wall material, which is brought into contact with the opening edge parting the opening of the building, can be fitted and mounted in the receiving groove of the surrounding frame material. Even if the precut dimensions may not match when used as the outer wall material around the opening, it is accommodated in the groove to cover the uneven end of the outer wall material and absorb the dimensional error. By attaching the outer wall material around the opening, workability can be improved.
[0049]
on the other hand, Claims4According to the described exterior wall method,Even if the abutting ends of the outer wall material abutted at the corner where the outgoing corner or the inset corner of the building are located may be irregular, the corners including these abutting ends may be taken from outside. Since it can be concealed by a material, it is possible to improve the workability by making the adjustment work unnecessary.
[Brief description of the drawings]
FIG. 1 Claims in the present invention1 and 4Exterior wall describedUsed for construction methodIt is the perspective view which omitted some which shows an example of an outer wall material.
FIG. 2 Claims in the present invention1 and 4Of the outer wall material used for the described outer wall methodExample of condition when stacking and packingFIG.
FIG. 3 Claims in the present invention1 and 4It is explanatory drawing which shows the example of a display of the identification symbol attached to the end surface of the exterior wall material used for the exterior wall construction method of description, Among these, (a) isWhen packing by directionThe display example, (b)When packing by floorDisplay examples are shown below.
FIG. 4 Claims in the present invention1It is a front explanatory view showing around an opening of a building realized by the exterior wall method described.
FIG. 5 is a sectional view taken along line AA as an example in FIG. 4;
FIG. 6 is a sectional view taken along line BB in FIG. 4 as an example.
FIG. 7: Claims in the present invention4It is explanatory drawing which shows the state of the protruding corner part of the building implement | achieved by the described outer wall method.
FIG. 8 Claims in the present invention4It is explanatory drawing which shows the state of the inside corner part of the building implement | achieved by the described outer wall construction method.
[Explanation of symbols]
11 Exterior wall material
11a Unit wall material
11b Precut wall material
11c Black wall material
12 Surface
13 End face
14 Adhesive tape pieces
15 Identification code
16 fastening bands
17 Corresponding parts
21 Building
22 walls
23 opening
24 Opening edge
25 frame material
26 Receiving groove
27 Sash window
28 Nail material for fastening
29 Structural wood
30 First water stop material
31 2nd waterproof material
33 corner
33a
33b
34 Materials
35 Sealing material

Claims (6)

それぞれを水平載置して積み重ねた際に表出する端面の側に建築物に壁面を形成する際の割当て位置との関係で定まる必要情報を個別に教示するための識別記号が付された標準規格品としての単位壁材と、この単位壁材の裏面にカット位置を割り付けるために予め墨付けして同様に識別記号が付された墨付け壁材と、前記単位壁材から不要部分のすべてもしくは一部を事前に切除して同様に識別記号が付されたプレカット壁材との少なくともいずれか一種もしくは二種以上を任意に組み合わせて構成される複数枚の外壁材が用いられ、
これら複数枚の外壁材は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねる積重ね梱包により梱包し、
その施工時には、梱包状態を解除して最上位に位置する外壁材から順次取り出し、必要があれば所定のカット処理を行い、
その端面に付された前記識別記号が教示する壁面部位が建築物における窓等の開口部が位置する部位を含み、この開口部の開口縁部と突き合わされる外壁材の対応部位は、開口部の周縁部に予め配設されている囲枠材が備える受け溝部内に納めながら取り付けることで壁面を形成することを特徴とする外壁工法。
A standard with an identification symbol attached on the side of the end face that is exposed when they are horizontally placed and stacked, to individually teach necessary information that is determined in relation to the assigned position when forming the wall surface on the building A unit wall material as a standard product, a blackened wall material that has been previously blackened and similarly identified with an identification code in order to assign a cut position to the back surface of the unit wall material, and all unnecessary parts from the unit wall material Or, a plurality of outer wall materials configured by arbitrarily combining at least one or two or more of precut wall materials with the identification symbol similarly cut out in advance are used,
These plurality of exterior wall materials, the lowest of those used last in the field, what is used first to pack by stacking Ru stacking packaged in its order of use as at the top,
At the time of construction, release the packing state and take it out sequentially from the outermost wall material located at the top, perform a predetermined cutting process if necessary,
The wall portion taught by the identification symbol attached to the end surface includes a portion where an opening such as a window in a building is located, and a corresponding portion of an outer wall material which is brought into contact with an opening edge of the opening is an opening. An outer wall construction method, wherein a wall surface is formed by being mounted in a receiving groove provided in a surrounding frame material provided in advance on a peripheral edge of the wall.
前記各外壁材は、前記積重ね梱包をさらに建築物の各壁面が向いている方位の別に仕分けた方位別梱包により用意されることを特徴とする請求項記載の外壁工法。Each exterior wall material, the outer wall construction method according to claim 1, characterized in that it is prepared by separate the sorting orientations different packing orientations respective wall surfaces of the further building the stack package is oriented. 前記各外壁材は、前記積重ね梱包または前記方位別梱包をさらに建築物の各階別に仕分けた各階別梱包により用意されることを特徴とする請求項1または2に記載の外壁工法。 Each exterior wall material, the outer wall method according to claim 1 or 2, characterized in that it is prepared by each floor-specific packaging which sorted by each floor of the stacking packaging or the azimuth by packing more buildings. それぞれを水平載置して積み重ねた際に表出する端面の側に建築物に壁面を形成する際の割当て位置との関係で定まる必要情報を個別に教示するための識別記号が付された標準規格品としての単位壁材と、この単位壁材の裏面にカット位置を割り付けるために予め墨付けして同様に識別記号が付された墨付け壁材と、前記単位壁材から不要部分のすべてもしくは一部を事前に切除して同様に識別記号が付されたプレカット壁材との少なくともいずれか一種もしくは二種以上を任意に組み合わせて構成される複数枚の外壁材が用いられ、
これら複数枚の外壁材は、現場で最後に使用されるものを最下位に、最初に使用されるものを最上位に位置するようにその使用順に積み重ねる積重ね梱包により梱包し、
その施工時には、梱包状態を解除して最上位に位置する外壁材から順次取り出し、必要があれば所定のカット処理を行い、
その端面に付された前記識別記号が教示する壁面部位が建築物において出隅もしくは入隅が位置する隅部を含み、この隅部にて突き合わされる外壁材の対応部位は、前記隅部に外側から配設される役物材により隠蔽して取り付けることで壁面を形成することを特徴とする外壁工法。
A standard with an identification symbol attached on the side of the end face that is exposed when they are horizontally placed and stacked, to individually teach necessary information that is determined in relation to the assigned position when forming the wall surface on the building A unit wall material as a standard product, a blackened wall material that has been previously blackened and similarly identified with an identification code in order to assign a cut position to the back surface of the unit wall material, and all unnecessary parts from the unit wall material Or, a plurality of outer wall materials configured by arbitrarily combining at least one or two or more of precut wall materials with the identification symbol similarly cut out in advance are used,
These multiple pieces of outer wall material are packed by stacking packaging in which the last used in the field is used at the bottom, the first used at the top is the order of use so that it is located at the top ,
At the time of construction, release the packing state and take it out sequentially from the outermost wall material located at the top, perform a predetermined cutting process if necessary,
The wall surface portion taught by the identification symbol attached to the end surface includes a corner where an outgoing corner or an incoming corner is located in a building, and a corresponding portion of an outer wall material abutted at this corner is located at the corner. An outer wall construction method , wherein a wall surface is formed by concealing and attaching an accessory material arranged from the outside .
前記各外壁材は、前記積重ね梱包をさらに建築物の各壁面が向いている方位の別に仕分けた方位別梱包により用意されることを特徴とする請求項4記載の外壁工法。 The outer wall construction method according to claim 4, wherein each of the outer wall materials is prepared by azimuth-specific packing in which the stacked packing is further sorted according to the azimuth of each wall of the building . 前記各外壁材は、前記積重ね梱包または前記方位別梱包をさらに建築物の各階別に仕分けた各階別梱包により用意されることを特徴とする請求項4または5に記載の外壁工法。 The outer wall construction method according to claim 4 or 5, wherein each of the outer wall materials is prepared by floor-by-floor packing in which the stacked packing or the packing by direction is further sorted by each floor of a building .
JP17191894A 1994-06-30 1994-06-30 Exterior wall construction method Expired - Fee Related JP3604736B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17191894A JP3604736B2 (en) 1994-06-30 1994-06-30 Exterior wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17191894A JP3604736B2 (en) 1994-06-30 1994-06-30 Exterior wall construction method

Publications (2)

Publication Number Publication Date
JPH0819995A JPH0819995A (en) 1996-01-23
JP3604736B2 true JP3604736B2 (en) 2004-12-22

Family

ID=15932264

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17191894A Expired - Fee Related JP3604736B2 (en) 1994-06-30 1994-06-30 Exterior wall construction method

Country Status (1)

Country Link
JP (1) JP3604736B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2018137C (en) * 1989-06-14 2000-01-11 Thomas Scholl L-carnitine magnesium citrate
JP4794744B2 (en) * 2001-03-26 2011-10-19 住友林業株式会社 Material processing management system
JP7160270B2 (en) * 2018-10-01 2022-10-25 宮川工機株式会社 PLATE-LIKE PARTS MOVEMENT DEVICE, CONTROL DEVICE FOR PLATE-LIKE PARTS MOVEMENT DEVICE, AND PLATE-LIKE PARTS MOVEMENT PROGRAM
JP2021073398A (en) * 2021-02-09 2021-05-13 住友ベークライト株式会社 Construction method and decorative material set
WO2024162269A1 (en) * 2023-01-31 2024-08-08 ケイミュー株式会社 Decorative sheet set, decorative structure, method for constructing decorative structure, and method for producing decorative sheet

Also Published As

Publication number Publication date
JPH0819995A (en) 1996-01-23

Similar Documents

Publication Publication Date Title
US5195249A (en) Wall panel template
US20080010910A1 (en) Framing lumber product and a bundle of pre-marked framing lumber products
US20070144102A1 (en) Method of fabricating a dimension lumber product
US4072548A (en) Panel door and method of construction
JP3604736B2 (en) Exterior wall construction method
JPH09162585A (en) Magnetic shield room and its assembling method
CA2404414A1 (en) Cedar impression siding corner
US10870993B2 (en) Individual polymer masonry panels, and methods of manufacture and installation
US6305132B1 (en) Molded interior window frame assembly
JP5523653B2 (en) Building facade structure and facade panels
US20010049894A1 (en) Base sign with integral signage and method for its fabrication
GB2051194A (en) Facing for a Door Frame
US4573295A (en) Set of building articles and method of making and using the set to construct a predesigned, pre-engineered structure
US3260400A (en) Electrical outlet box
JPS63503220A (en) System for interconnecting container panels
JP2585259Y2 (en) Multifunctional end block
JPH07317202A (en) Material for building and structure
JP3150060B2 (en) Magnetic shield room and method of assembling the same
CN220117633U (en) Spliced decorative plate
JPS642891Y2 (en)
JP2019210731A (en) Termite prevention coating material for timber construction and construction method of timber construction using the same
KR200277722Y1 (en) Art Wall
GB2141472A (en) Panel-like member
JPH07197620A (en) Exterior backing sheets
JPH0754415A (en) Substrate material for external wall of building and building structure equipped with it

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040224

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040303

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040506

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040908

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040930

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees