JP3606535B2 - Assembling method of pier reinforcement frame - Google Patents
Assembling method of pier reinforcement frame Download PDFInfo
- Publication number
- JP3606535B2 JP3606535B2 JP27016395A JP27016395A JP3606535B2 JP 3606535 B2 JP3606535 B2 JP 3606535B2 JP 27016395 A JP27016395 A JP 27016395A JP 27016395 A JP27016395 A JP 27016395A JP 3606535 B2 JP3606535 B2 JP 3606535B2
- Authority
- JP
- Japan
- Prior art keywords
- reinforcing frame
- frame
- wire
- reinforcement
- reinforcement frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明はコンクリート及び鋼製高架橋を支える橋脚柱の補強枠の組み立て方法に関する。
【0002】
【従来の技術】
コンクリート及び鋼製高架橋を支える柱の補強のために、柱の周囲に鋼板を巻き付けて補強枠とすることが行われている。この補強枠の組み立て方法として、従来、図1に示すように、現地に搬入された鋼製、FRP等のコの字形をした補強枠2をクレーン等により吊り下げて橋脚柱1の側面に建て込み、アンカーボルトや溶接、仮固定金具などに仮固定して所定位置に設置後、添接板を用いて溶接やボルト等で補強枠相互を連結する方法が用いられている。
【0003】
【発明が解決しようとする課題】
しかしこの方法では、まず補強枠部材を組み立てるために、図2に示すように、組み立て作業員の足場が必要となる。それもクレーン作業に支障を生じないように配置しなければならない。図2(a)は足場の斜視図、図2(b)は側面から見た図、図2(c)は平面図である。このように足場は補強枠の周囲に設けられるが、補強枠部材がかなりの重量であるため、相当の強度に耐えられるものが必要であるとともに、足場の高さも相当の高さとなるため、転落、墜落といった労働災害の可能性もある。その上、補強枠部材を連結し、一体構造とするために溶接やボルトなどにより接合する必要があり、補強枠部材相互を所定の位置に突き合わせる作業が伴う。その上で図3に示すように、添接板3を補強枠部材の位置を考慮しながら所定の精度により設置しなければならない。さらに設置した添接板3と補強枠2とを溶接棒5を用いて溶接したり、ボルト等で接合作業をしないと、補強枠部材相互が完全に一体化されないため、例えば、鋼板部材相互を添接板の継手を介して溶接で連結する場合、部材と添接板の継手を密着させて溶接を行わなければならず、多大な時間と費用を要する。このような補強枠を設置し、組み立てるに際して相当の精度を施工の際に求められる。しかし、熟練工が減少する昨今の現状の中で施工精度を求めるのは非常に厳しくなる現状にあり、工事費が増大傾向にある。このため、作業安全性の向上、施工精度の向上、工期の短縮などによるコスト削減等が図れる施工方法が求められている。
【0004】
本発明は上記課題を解決するためのもので、作業安全性の向上、施工精度の向上、工期の短縮、コスト削減等が図れる橋脚補強枠の組み立て方法を提供することを目的とする。
【0005】
【課題を解決するための手段】
本発明の橋脚補強枠の組み立て方法は、補強枠を橋脚柱の両側地上に対向して据え付けるとともに、補強枠下端に補強枠相互を連結する連結装置を取り付ける段階、各補強枠上部に、滑車を設けた組み立て装置を取り付けて滑車相互にワイヤーを巻き付ける段階、巻き上げ装置によってワイヤーを巻き取ることにより、補強枠相互を立ち上げて突き合わせ、連結する段階とからなっている。このように、本発明の組み立て方法は、従来の部材吊り下げ組み立て方法と発想を異にするものであり、地上作業のみによって補強枠部材を建て込み組み立て、部材相互を精度よく突き合わせることができる。そして、対向する補強枠に凹型継手、凸型継手を設けることにより、組み立てと同時に補強枠部材相互の連結が完了し、補強枠部材と継手との一体化が可能となる。
【0006】
【発明の実施の形態】
以下、本発明の実施の形態について説明する。
まず、本発明で使用する補強枠の一例について図4により説明する。
図4(a)において、継手10は、断面コの字形で、開口部に内側に鋭角または直角に突出した引っ掛かり突起部10a、10bを有する鋼材からなる凹形継手であり、鋼板2が溶接やボルト等で接合されている。また、継手20は先端部に、引っ掛かり突起部10a、10bと係合する張り出し突起部20a、20bを有する鋼材からなる凸形継手であり、鋼板2が溶接やボルト等で接合され、継手が張り出した状態になっている。これら鋼板2が接合された継手10、20はあらかじめ工場で製作される。工場で製作され、凹形継手10、凸形継手20を接合した鋼板は、現場においてクレーン車等の作業車により、橋脚柱1を囲むようにして対向させ、図4(b)に示すように、鋼板を接合した継手20を継手10の開口を通して継手軸線方向に挿入する。挿入時に継手10のバネ作用によりその開口が拡がって継手20が挿入され、継手10に継手20が入りきるとバネ作用により開口が復元する。こうして挿入が完了すると、継手10の引っ掛かり突起部10a,10bと、継手20の張り出し突起部20a,20bが引っ掛かり、引き離すような力が働いても抜け出してしまうことはない。これにより鋼板相互が突き合わされて連結される。
【0007】
図5は本発明の補強枠組み立て方法の1つの実施形態を示す図で、図5(a)は正面図、図5(b)は平断面図である。なお、図5において、1はコンクリート高架橋を支える橋脚柱、2は鋼材等からなる補強枠、4は橋脚柱の基礎、Gは地面、6は補強枠相互を連結する連結装置、6aは補強枠に連結装置を取り付けるためのピン、7は補強枠を立ち上げるための補強枠組み立て装置、7aは治具、7bは滑車、8はワイヤー、9はワイヤーを巻き上げるための巻き上げ装置を示している。
使用する補強枠は、図4で説明したような継手が設けられた断面コの字形のものであり、図5(a)に示すように、橋脚柱1の根本部分の土を一部掘削して基礎4を露出させ、補強枠2の下端部が橋脚柱1を囲むようにその両側に対向して傾斜させて据える。
【0008】
次いで、両補強枠の下端に補強枠相互を連結する鋼材、木材等からなる連結装置6をピン6aによって取り付ける。
次いで、各補強枠2の上部背面には、補強枠を立ち上げるための補強枠組み立て装置7を取り付ける。補強枠組み立て装置7は、治具7aと、治具7aに取付けられた滑車7bからなっている。治具7aは滑車にかかる荷重のために比較的薄い補強枠鋼板が曲がったりしないように設けられるものであり、補強枠にあらかじめ孔を開けておき、この孔にボルト等で取り付けるか、あるいは補強枠にフックを設けておき、これに治具を引っかけて取り付けるなど簡単な構造のものでよい。
【0009】
次いで、橋脚柱の両側に据え付けられた両補強枠の滑車に対してワイヤー8を渡して複数回巻き付け、その一端を巻き上げ装置9に接続し、他端を補強枠に対して巻き上げ装置と反対側の位置Pで固定する。なお、滑車間に複数回ワイヤーを巻き付けることにより、ワイヤー1本当たりの荷重を減らすことができ、細いワイヤーが使用可能となるので取り扱いが便利となる。
【0010】
次いで、巻き上げ装置9でワイヤー8の巻き取りを行う。補強枠2は上端部が下端部に対して高くなるように傾斜して置かれているため、ワイヤーの巻取りにより滑車相互間が接近するように引っ張られると、ピン6aを中心に回動し、地上より立ち上がる。この立ち上がりの過程で、図4に示した凸形継手と凹形継手とが下端部の方から上端部に向けて徐々に接合し、立ち上がり終わったときには連結が完了する。なお、継手の接合の過程で、凸形継手が凹形継手に挿入される箇所は下側から上側に順次移動し、挿入のために摩擦を生じている箇所は一部であるため、挿入に要する力は少なくてすむことになる。また、継手同士の遊びを大きくして接合を容易にしておき、接合後に、図6に示すように、ボルト30等を使用して補強枠同士を引き離すように力を加えて接合部の遊びを無くすようにすれば、接合を容易にし、かつ堅固な接合を得ることができる。また、連結後は補強枠2と基礎4との間にくさび等を入れてピン6aを外して補強枠は基礎4で直接受けるようにする。
こうして、足場を必要とせず、またクレーンのようなものは使用せずに簡単な装置で組み立てを行うことができる。
【0011】
図7は本発明の他の実施の形態を説明する図である。図7において、図6と同一番号は同一内容を示している。
図7に示す方法は、立ち上げ補助装置40を使用した点以外は図6と同じである。図6においては、橋脚柱の根元部分を掘削して窪みをつくり、この部分に補強枠端部を置くことにより補強枠を傾斜させて据えるようにしたので、ワイヤーの巻取りにより補強枠を立ち上げることが可能になっている。しかし、例えば、2層構造や3層構造の高架橋で、その2段目、3段目等に補強枠を設置する場合には、傾斜させて据えつけることができない。補強枠を水平に据えつけ、図6に示した方法でワイヤーを渡するワイヤーも水平に張られ、これを巻き取っても補強枠同士が接近しようとするだけで補強枠は立ち上がらない。
【0012】
そこで、図7においては、補強枠を据え付けて連結装置6で補強枠相互を連結し、補強枠上部に滑車を取り付けた組み立て装置7を取り付けるとともに、立ち上げ補助装置40を連結装置6の位置に設置し、組み立て装置間に張るワイヤー8を立ち上げ補助装置40の上に載せてワイヤーの中心部を両端部に対して高くする。なお、立ち上げ補助装置のワイヤーが載る部分は、ワイヤーの動きが両方向であるため、ワイヤーが動けるような滑面とする。
【0013】
この状態で巻き上げ装置9でワイヤーの巻き取りを行うと、滑車に対してワイヤーから垂直分力が働いて補強枠が立ち上がり始める。一旦、立ち上がってしまえば、図7と同様に、ワイヤーの巻取りにより滑車相互間が接近するように引っ張られ、補強枠2はピン6aを中心に回動して立ち上がり、この立ち上がりの過程で、図4に示した凸形継手と凹形継手とが下端部の方から上端部に向けて徐々に接合し、立ち上がり終わったときには連結が完了する。
【0014】
図8はこうして連結された状態を示し、橋脚柱1と鋼板2の間にはエポキシ樹脂やモルタルなどの充填材を充填し、一体化して補強工事が完了する。
なお、上記では補強枠として凸形継手、凹形継手を有するものを例にして説明したが、本発明はこれに限定されるものではなく、従来のように、添接板を使用してボルトや溶接により連結する場合にも適用することが可能である。
【0015】
【発明の効果】
以上のように本発明によれば、補強枠部材を建て込み組み立てと同時に所定精度内に設置でき、また、作業のほとんどは地上での作業となるため、作業用足場が不要となり、作業員の転落、墜落といった労働災害の発生を防止することができる。また、足場が不要となるため、工事費を大幅に節減でき、さらに、補強枠に継手装置を設けることにより、大幅な工期短縮が可能となる。
【図面の簡単な説明】
【図1】従来の橋脚補強枠の組み立て方法を説明する図である。
【図2】従来の組み立て方法において使用する足場を示す図である。
【図3】従来の橋脚柱の補強方法を説明する図である。
【図4】本発明で使用する補強枠の例を示す図である。
【図5】本発明による補強枠組み立て方法の例を示す図である。
【図6】本発明による補強枠組み立て方法を説明する図である。
【図7】本発明による補強枠組み立て方法の他の例を示す図である。
【図8】連結した状態を示す図である。
【符号の説明】
1…橋脚柱、2…補強枠、4…基礎、6…連結装置、6a…ピン、7…補強枠組み立て装置、7a…治具、7b…滑車、8…ワイヤー、9…巻き上げ装置、30…ボルト、40…立ち上げ補助装置。[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for assembling a reinforcement frame of a pier column supporting concrete and steel viaducts.
[0002]
[Prior art]
In order to reinforce pillars that support concrete and steel viaducts, steel frames are wound around pillars to form reinforcing frames. As a method of assembling this reinforcing frame, conventionally, as shown in FIG. 1, a
[0003]
[Problems to be solved by the invention]
However, in this method, in order to assemble the reinforcing frame member, as shown in FIG. 2, a scaffold for an assembly worker is required. It must also be arranged so as not to interfere with the crane operation. 2A is a perspective view of the scaffold, FIG. 2B is a side view, and FIG. 2C is a plan view. As described above, the scaffolding is provided around the reinforcement frame. However, since the reinforcement frame member has a considerable weight, it needs to be able to withstand a considerable strength, and the height of the scaffolding also becomes a considerable height. There is also the possibility of occupational accidents such as crashes. In addition, in order to connect the reinforcing frame members to form an integral structure, it is necessary to join them by welding, bolts, or the like. In addition, as shown in FIG. 3, the attachment plate 3 must be installed with a predetermined accuracy in consideration of the position of the reinforcing frame member. Furthermore, if the installed attachment plate 3 and the reinforcing
[0004]
An object of the present invention is to provide a method for assembling a pier reinforcement frame capable of improving work safety, improving construction accuracy, shortening a construction period, and reducing costs.
[0005]
[Means for Solving the Problems]
The method of assembling the pier reinforcement frame according to the present invention includes the steps of installing the reinforcement frame opposite to the ground on both sides of the pier column, attaching a connecting device for connecting the reinforcement frames to the lower end of the reinforcement frame, and installing a pulley on each reinforcement frame. A step of attaching the provided assembly device and winding the wire between the pulleys, and a step of winding up the wire by the winding device to bring up the reinforcing frames to face each other and connect them. Thus, the assembling method of the present invention is different in concept from the conventional member hanging assembling method, and the reinforcement frame member can be built and assembled only by ground work, and the members can be abutted with each other with high accuracy. . By providing the concave joint and the convex joint on the opposing reinforcing frame, the connection between the reinforcing frame members is completed simultaneously with the assembly, and the reinforcing frame member and the joint can be integrated.
[0006]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention are described below.
First, an example of a reinforcing frame used in the present invention will be described with reference to FIG.
In FIG. 4 (a), the
[0007]
FIG. 5 is a view showing one embodiment of the reinforcing frame assembling method of the present invention, FIG. 5 (a) is a front view, and FIG. 5 (b) is a plan sectional view. In FIG. 5, 1 is the pier column supporting the concrete viaduct, 2 is the reinforcing frame made of steel, 4 is the foundation of the pier column, G is the ground, 6 is a connecting device for connecting the reinforcing frames, and 6a is the reinforcing frame. A pin for attaching the connecting device to the frame, 7 is a reinforcing frame assembling device for raising the reinforcing frame, 7a is a jig, 7b is a pulley, 8 is a wire, and 9 is a winding device for winding the wire.
The reinforcing frame to be used is a U-shaped cross section provided with a joint as described in FIG. 4, and as shown in FIG. 5A, a part of the soil at the base portion of the
[0008]
Next, a connecting
Next, a reinforcing
[0009]
Next, the
[0010]
Next, the
Thus, the assembly can be performed with a simple device without using a scaffold and without using a crane.
[0011]
FIG. 7 is a diagram for explaining another embodiment of the present invention. In FIG. 7, the same numbers as those in FIG. 6 indicate the same contents.
The method shown in FIG. 7 is the same as that in FIG. 6 except that the startup assisting device 40 is used. In FIG. 6, the base portion of the pier column is excavated to form a recess, and the reinforcement frame is inclined by placing the end of the reinforcement frame in this portion. It is possible to raise. However, for example, in the case of a two-layer structure or a three-layer structure viaduct and when a reinforcing frame is installed at the second, third, etc., it cannot be tilted. The reinforcing frame is installed horizontally, and the wire passing the wire by the method shown in FIG. 6 is also stretched horizontally, and even if the wire is wound up, the reinforcing frame is merely brought closer to each other and the reinforcing frame does not stand up.
[0012]
Therefore, in FIG. 7, the reinforcing frames are installed, the reinforcing frames are connected to each other by the connecting
[0013]
When the wire is wound up by the winding device 9 in this state, a vertical component force acts on the pulley from the wire and the reinforcing frame starts to rise. Once standing up, as in FIG. 7, the pulleys are pulled so as to approach each other by winding the wire, and the reinforcing
[0014]
FIG. 8 shows a state of being connected in this way, and a filler such as epoxy resin or mortar is filled between the
In the above description, the reinforcing frame has a convex joint and a concave joint as an example. However, the present invention is not limited to this, and a bolt using an attachment plate as in the prior art. It is also possible to apply it when connecting by welding.
[0015]
【The invention's effect】
As described above, according to the present invention, the reinforcing frame member can be installed within a predetermined accuracy simultaneously with the erection and assembly, and since most of the work is performed on the ground, there is no need for a work scaffold. Occurrence of occupational accidents such as falls and crashes can be prevented. In addition, since no scaffold is required, the construction cost can be greatly reduced, and further, the construction period can be significantly shortened by providing a joint device on the reinforcing frame.
[Brief description of the drawings]
FIG. 1 is a view for explaining a conventional method of assembling a pier reinforcement frame.
FIG. 2 is a view showing a scaffold used in a conventional assembling method.
FIG. 3 is a diagram for explaining a conventional method for reinforcing a pier column.
FIG. 4 is a diagram showing an example of a reinforcing frame used in the present invention.
FIG. 5 is a diagram showing an example of a reinforcing frame assembling method according to the present invention.
FIG. 6 is a diagram illustrating a reinforcing frame assembling method according to the present invention.
FIG. 7 is a view showing another example of a reinforcing frame assembling method according to the present invention.
FIG. 8 is a diagram showing a connected state.
[Explanation of symbols]
DESCRIPTION OF
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP27016395A JP3606535B2 (en) | 1995-10-18 | 1995-10-18 | Assembling method of pier reinforcement frame |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP27016395A JP3606535B2 (en) | 1995-10-18 | 1995-10-18 | Assembling method of pier reinforcement frame |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH09111718A JPH09111718A (en) | 1997-04-28 |
| JP3606535B2 true JP3606535B2 (en) | 2005-01-05 |
Family
ID=17482420
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP27016395A Expired - Fee Related JP3606535B2 (en) | 1995-10-18 | 1995-10-18 | Assembling method of pier reinforcement frame |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3606535B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH09143927A (en) * | 1995-11-17 | 1997-06-03 | J R Higashi Nippon Shoji:Kk | Column reinforcing metal piece |
| JP5653835B2 (en) * | 2011-05-13 | 2015-01-14 | 三菱重工鉄構エンジニアリング株式会社 | Bridge pier reconstruction method and rebuild pier structure |
| CN115233576A (en) * | 2022-07-13 | 2022-10-25 | 天津鑫路桥建设工程有限公司 | Prefabricated assembled pier segment reinforcing device and repairing process thereof |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS61270646A (en) * | 1985-05-24 | 1986-11-29 | Fuji Photo Film Co Ltd | Chemical analyzing instrument |
| JPH0978852A (en) * | 1995-09-11 | 1997-03-25 | Tokyo Eruguude Kk | Method of earthquake-proof reinforcement of concrete stud by steel plate and member therefor |
-
1995
- 1995-10-18 JP JP27016395A patent/JP3606535B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH09111718A (en) | 1997-04-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3606535B2 (en) | Assembling method of pier reinforcement frame | |
| JPH10331437A (en) | Seismic reinforcement structure of existing columns and beams | |
| JPH0711710A (en) | Connection structure of reinforced concrete columns and steel beams and method of building construction | |
| KR20220166451A (en) | Steel beam jointing device connecting reinforced concrete beams and steel beams regardless of concrete curing, and construction method using the same | |
| JP3436104B2 (en) | Steel pipe construction method | |
| JP2893406B2 (en) | Precast concrete beam-column joining method | |
| JP3020343B2 (en) | Column base structure using hollow tube and method of constructing the same | |
| JP2886376B2 (en) | Anchor structure of pile head | |
| KR20030052868A (en) | Joint of base concrete structure and bridge pier and its jointing method | |
| JP2004270377A (en) | Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same | |
| JP3941612B2 (en) | Anchoring structure between circular steel pipe and concrete | |
| JPS5952044A (en) | Construction of structure | |
| JPH06264511A (en) | Pressure joining work method for post and beam | |
| JP3284391B2 (en) | Reinforced concrete frame and construction method | |
| JP3512222B2 (en) | Ramen precast structure and its beam construction method | |
| JPH06316966A (en) | Structure of beam-column joint | |
| JP2907038B2 (en) | Joint structure and joining method between precast beam and column | |
| JPH08239807A (en) | Composite column base structure | |
| JP2968952B2 (en) | Column and beam joint structure and joining method | |
| JP2926148B2 (en) | Joint structure of prestressed structure | |
| JP2972673B2 (en) | Capital in pillar and its construction method | |
| JP4669954B2 (en) | Hole down anchor | |
| JPS5846970B2 (en) | Connection method between RC columns, Pca girders in the column direction, and cast-in-place girders in the span direction | |
| JP4183344B2 (en) | Leg structure of steel reinforced concrete columns | |
| JPH10266336A (en) | Reinforcing method of existing beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040913 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20041001 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20041004 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081015 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091015 Year of fee payment: 5 |
|
| LAPS | Cancellation because of no payment of annual fees |