JP3609364B2 - Tunnel connection method - Google Patents
Tunnel connection method Download PDFInfo
- Publication number
- JP3609364B2 JP3609364B2 JP2001316813A JP2001316813A JP3609364B2 JP 3609364 B2 JP3609364 B2 JP 3609364B2 JP 2001316813 A JP2001316813 A JP 2001316813A JP 2001316813 A JP2001316813 A JP 2001316813A JP 3609364 B2 JP3609364 B2 JP 3609364B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- segment
- female
- male
- connection member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、トンネルの接続方法に関する。
【0002】
【従来の技術】
従来より、都市部の地下利用策の一つとして道路、鉄道等の地下化が挙げられる。そして、そのような道路、鉄道用のトンネルは、用地が十分ではなく、地上の制約が多い上に地盤が軟弱である等の理由からシールド工法によって構築されている。
シールド工法によって構築されるトンネルは、力学的に円形断面が最も効率の良い形状とされている。しかし、道路、鉄道を構築する上で求められているトンネルの形状は矩形(横長の長方形)であるため、予め、必要以上に大きな直径の円形トンネルを構築して、その円形トンネルの内方に矩形形状のトンネルを構築するようになっていた。
【0003】
そこで、最近では、矩形のトンネルを接続して外周トンネルを矩形に構築するMMST(マルチマイクロシールドトンネル)工法(特開2000−328899号公報参照)や、また、多円形MF(マルチフェイス)工法、DOT(ダブルオーチューブ)工法といった円形トンネルを複数組合せた形状のトンネルを構築する工法などが考案され、実施されている。
【発明が解決しようとする課題】
しかしながら、例えばMMST工法では、複数のセグメント(図2参照)から構成された小口径トンネルどうしの接続を行う際に、地盤改良を行って安全性を確保する必要があるが、薬液注入等の地盤改良工法によって安全性を確保するのが難しいといった問題があった。
また、例えば多円形MF工法では、構築するトンネルの形状に合わせてシールド機を製作するために、そのシールド機に汎用性がなく転用でき難かった。また、そのシールド機の製作費用が高いために、トンネル構築に高額の費用がかかるといった問題もあった。
【0004】
本発明は、上記実状に鑑みてなされたもので、少なくとも2つ以上のトンネルどうしの接続を容易に、且つ安全に行うことができ、トンネル構築にかかる費用を低減可能なトンネルの接続方法を提供することを目的としている。
【0005】
【課題を解決するための手段】
上記課題を解決するため、
請求項1に記載の発明は、例えば図1に示すように、
地山を掘削して形成された地下空洞の内面を履工する複数のセグメント50から構成されるトンネルどうしを雌型セグメント10及び雄型セグメント20を用いて接続するトンネルの接続方法であって、
前記雌型セグメント10の内部の地山側には凹状の雌型接続部材11が設けられ、
前記雄型セグメント20の地山側の部分には、トンネルの軸方向に移動させることにより前記雌型接続部材11に係合する略T字状の雄型接続部材21が設けられ、
先ず、前記雌型セグメント20を含んで構成される第1トンネルを構築し、次に、前記第1トンネルに設けられた前記雌型接続部材11に前記雄型接続部材21を係合させながら前記雄型セグメント20を前記第1トンネルの軸方向に移動させて、当該雄型セグメント20を含んで構成される第2トンネルを構築することによって、前記第1トンネルと前記第2トンネルとを接続することを特徴としている。
【0006】
ここで、セグメントは、鋼製のセグメントやRC(鉄筋コンクリート)製のセグメントなど、如何なる材質のものであっても良い。また、セグメントの形状は、矩形形状や多角形形状など、隣接するセグメントどうしが接続可能であれば如何なる形状のセグメントであっても良い。
また、雌型接続部材及び雄型接続部材は、軽量、且つ強度と靭性を有する材料から成形されている。その材料としては、例えば金属や、塩化ビニル等の樹脂により成形されたプラスチックや、セラミック等が挙げられる。
【0007】
請求項1に記載の発明によれば、雌型セグメントを含んで構成される第1トンネルを構築し、次に、第1トンネルに設けられた雌型接続部材に雄型接続部材を係合させるようにして第2トンネルを後行して構築することによって、第1トンネルと第2トンネルとを接続する。つまり、雌型セグメントの雌型接続部材に雄型接続部材を係合させながら雄型セグメントを第1トンネルの軸方向に移動させるように当該雄型セグメントの履工を行うことによって、第2トンネルの構築及び当該第2トンネルと第1トンネルとの接続を行うことができる。従って、トンネルを接続する際に、安全性を確保する目的で薬液注入等による地盤改良を行う必要がなくなり、少なくとも2つ以上のトンネルどうしの接続を容易に、且つ安全に行うことができる。
さらに、地盤改良工法を行う必要がないだけでなく、例えば、多円形MF工法のように専用のシールド機を作成する必要がなく汎用型のシールド機を利用してトンネルを構築することができるので、それらにかかる費用を低減することができる。
【0008】
ここで、地盤改良に用いられる薬液としては、例えばセメントミルク等が挙げられる。
【0009】
請求項2に記載の発明は、請求項1に記載のトンネルの接続方法において、例えば図1に示すように、
前記雌型接続部材11及び前記雄型接続部材21は、トンネルの軸方向に延在するように設けられていることを特徴としている。
【0010】
請求項2に記載の発明によれば、雌型接続部材及び雄型接続部材は、トンネルの軸方向に延在するように設けられているので、雌型セグメントと雄型セグメントとの接続が強固になる。従って、2つのトンネルを強固に接続することができる。
【0011】
請求項3に記載の発明は、請求項1又は2に記載のトンネルの接続方法において、例えば図1に示すように、
前記雌型接続部材11及び前記雄型接続部材21は、金属成形されていることを特徴としている。
【0012】
請求項3に記載の発明によれば、雌型接続部材及び雄型接続部材は、金属成形されているので、雌型セグメントと雄型セグメントとの接続がより強固になる。従って、2つのトンネルをより強固に接続することができる。
【0015】
【発明の実施の形態】
以下、図面を参照して、本発明の実施の形態について詳細に説明する。
本発明を適用したトンネル接続用セグメント1は、地山を掘削して形成された地下空洞の内面を履工する複数のセグメント50から構成されるトンネルどうしを接続するものである。
図1は、トンネル接続用セグメント1の全体を説明する概略斜視図である。図2は、鋼製のセグメント50を示す概略斜視図である。図3は、雌型セグメント10に設けられた雌型接続部材11の要部断面図である。図4は、トンネル接続用セグメント1を用いて構築するトンネルの施工方法を示す図である。
【0016】
先ず、トンネル接続用セグメント1の構成について説明する。
トンネル接続用セグメント1は、例えば図1に示すように、接続される2つのトンネル(図4参照)の接続部分のうちの先行して構築される第1トンネル(一方)に設けられる雌型セグメント10と、後行して構築される第2トンネル(他方)に設けられる雄型セグメント20と、から構成されている。
【0017】
雌型セグメント10は、セグメント本体12と、該セグメント本体50の地山側の部分に設けられた雌型接続部材11と、から概略構成されている。
セグメント本体12は、例えば図2に示すように、円弧形状の鋼製のセグメント50である。
雌型接続部材11は、セグメント本体12の手前側の端部から奥側の端部に亘るようにトンネルの軸方向に延在する断面略T字状に凹んだ(凹状の)部材である。図3(a)では、セグメント本体12の地山側の端面(スキンプレート51:後述)に設けられた開口部11aと、該セグメント本体12の内方(内部)に設けられた断面略コ字状の板状部11bと、から構成された雌型接続部材11が示されている。
【0018】
なお、セグメント50は、地山側の端面であるスキンプレート51、隣接するセグメントリング(後述)どうしの接続部となる主桁52、スキンプレート51及び主桁52の補強を目的とする縦リブ53、セグメント50どうしの接続部となる継手板54、継手板54の補強を目的とする補強リブ55、当該セグメント50を運搬するときに用いられるつり手金具56、例えばモルタルなどの裏込め材を注入する注入孔57等から構成されている。
【0019】
一方、雄型セグメント20は、セグメント本体22と、該セグメント本体22の地山側の部分に設けられた雄型接続部材21と、から概略構成されている。
セグメント本体22は、前述した雌型セグメント10と同様に、円弧形状の鋼製のセグメント50から構成され、雌型セグメント10のセグメント本体12と略等しい大きさとなっている。
雄型接続部材21は、雌型接続部材11に対応する位置に、この雌型接続部材11に係合されるように設けられる断面略T字状の凸状部材であり、セグメント本体22の手前側の端部から奥側の端部に亘るようにトンネルの軸方向に延在している。
【0020】
なお、雌型及び雄型接続部材11、21の各々は、鋼板等によって成形(金属成形)されている。
【0021】
従って、雌型セグメント10と雄型セグメント20のいずれか一方をトンネルの軸方向に移動させることに伴って、雌型接続部材11と雄型接続部材21とが係合され、第1トンネルと第2トンネル(2つのトンネル)とが接続されることになる。
【0022】
次に、トンネル接続用セグメント1を用いたトンネルの接続方法について説明する。
【0023】
先ず、接続される第1トンネルと第2トンネルのうち、第1トンネルが先行して構築される。
第1トンネルは、雌型セグメント10を含んで構成されている。また、この第1トンネルの構築は、シールド工法によって行われる。
具体的には、掘削機(図示略)によって地山を掘削して地下空洞を形成し、その内面に複数のセグメント50を履工する際に、予め、後行して構築される第2トンネル(詳細後述)との接続部分に雌型セグメント10を設けるようにして、順次セグメント50を履工する。
この動作を順次行うことによって、第1トンネルが構築される。
従って、第1トンネルの第2トンネルとの接続部には、雌型接続部材11が軸方向に一列に並んだ状態となっている。
【0024】
なお、このとき履工される雌型セグメント10の地山側の端面(スキンプレート50)には、注入孔57を介して注入される裏込め材の侵入を防止する裏込め侵入防止板58が雌型接続部材11の開口部11aを覆う状態で設けられている。
【0025】
次いで、第2トンネルが後行して構築される。
第2トンネルは、雄型セグメント20を含んで構成され、第1トンネルに設けられた雌型接続部材11に雄型接続部材21が係合されるようにして構築される。
【0026】
この第2トンネルは推進工法によって構築される。
具体的には、先ず、立坑(図示略)等で雄型セグメント20を含んで構成されたセグメントリング(図示略;以後、第1セグメントリングと略称する)を組み立てる。そして、雄型セグメント20に設けられた雄型接続部材21が第1トンネルの手前側の端部に設けられた雌型接続部材11に係合するように、第1セグメントリングの位置決めを行う。その後、掘進機(図示略)と第1セグメントリングとを、第1セグメントリングの後端を押すようにしてジャッキ(図示略)等によって地盤中に押し込む。これにより、掘進機によって地盤が掘削され、掘削とともに地盤中に形成された地下空洞には第1セグメントリングが押し込まれる。この結果、第1セグメントリングの雄型接続部材21と第1トンネルの雌型接続部材11とが係合される。
【0027】
続いて、第1セグメントリングと同様に、次に押し込まれるセグメントリング(図示略;以下、第2セグメントリングと略称する)を立坑で組み立て、位置決めを行い、第2セグメントリングの後端を押すようにしてジャッキ等によって地盤中に押し込む。これにより、掘進機によって地盤がさらに掘削され、掘削とともに地盤中に形成された地下空洞には第1セグメントリングがさらに押し込まれるとともに、第2セグメントリングが第1セグメントリングに続いて押し込まれる。この結果、第1セグメントリングは、第1トンネルに軸方向に並んだ状態で設けられた雌型接続部材11に係合された状態で、地下空洞の奥側に押し込まれるとともに、第2セグメントリングの雄型接続部材21と第1トンネルの最も手前側の端部の雌型接続部材11とが係合される。
【0028】
この動作を順次行うことによって、第2トンネルは第1トンネルと接続された状態で構築される。
【0029】
以上のように、この実施の形態によれば、トンネル接続用セグメント1である雌型セグメント10を含んで構成される第1トンネルを構築して、次に、第2トンネルの構築を、第1トンネルの地山側に該第1トンネルの軸方向に延在するように設けられた雌型接続部材11に第2トンネルの地山側に該第2トンネルの軸方向に延在するように設けられた雄型接続部材12を係合させるようにして行うことにより、第1トンネルと第2トンネルとが強固に接続される。つまり、第1トンネルを構成する雌型セグメント10の雌型接続部材11に雄型接続部材21を係合させながら雄型セグメント20を第1トンネルの軸方向に移動させるように当該雄型セグメント20の履工を行うことによって、第2トンネルの構築及び当該第2トンネルと第1トンネルとの接続が行われることとなる。従って、トンネルを接続する際に、安全性を確保する目的で薬液注入等による地盤改良を行う必要がなくなり、作業員の地中での作業の安全性を高めることができ、これにより、少なくとも2つ以上のトンネルどうしの接続を容易に、且つ安全に行うことができる。
さらに、地盤改良工法を行う必要がないだけでなく、例えば、多円形MF工法のように専用のシールド機を作成する必要がなく汎用型のシールド機を利用してトンネルを構築することができるので、それらにかかる費用を低減することができる。
また、雌型及び雄型接続部材11、21は、雌型及び雄型セグメント10、20の各々に別部材で設けられているので、構築するトンネルの形状に応じて取り替えることができる。さらに、雌型及び雄型接続部材11、21は、鋼によって成形されているので、雌型セグメント10と雄型セグメント20との接続がより強固になる。
【0030】
また、この実施の形態のトンネルの接続方法によれば、従来のトンネルの施工方法に代わる方法でトンネルを構築することができる。
例えば、従来のMMST工法に代わるトンネルの施工方法を、図4(a)を参照して説明する。
先ず、矩形シールドトンネル61、62を先行して構築する。このとき、後行して構築されるトンネルとの接続部分71、72、73、74の各々に雌型セグメント10が設けられるようにする。その後、矩形形状のトンネル63を、矩形形状のトンネル63に設けられている雄型接続部材21を雌型接続部材11に係合させるようにして推進工法によって構築する。これによって、先行して構築された矩形シールドトンネル61、62と後行して構築された矩形形状のトンネル63とが接続された状態となる。
この動作を、他の接続部分75、76、77、78でも同様に行うことによって、従来のMMST工法と同様の矩形形状の大きなトンネルを施工できる。
また、例えば従来の3連型MFシールド工法に代わるトンネルの施工方法を図4(b)に示す。
具体的には、先ず、円形シールドトンネル81、82を地盤中に所定の間隔を空けて構築する。このとき、後行して構築されるトンネルとの接続部分91、92、93、94の各々に雌型セグメント10が設けられるようにする。その後、円形シールドトンネル81、82の間に設けられるルーフシールド83、84を、ルーフシールド83、84に設けられている雄型接続部材21を雌型接続部材11に係合させるようにして構築する。これによって、先行して構築された円形シールドトンネル81、82と後行して構築されたルーフシールド83、84とが接続された状態となる。
これによって、従来の3連型MF工法と同様の大きなトンネルを施工できる。
【0031】
なお、本発明は本実施例に限定されるものではなく、本発明の趣旨を逸脱しない範囲で任意の変形が可能である。
例えば、この実施の形態では、雌型及び雄型セグメント10、20が鋼製のセグメント50から構成されるようにしたが、これに限られるものではなく、例えば、RC(鉄筋コンクリート)製のセグメント(図示略)から構成されるようにしてもよい。また、図3(b)には、RC製の雌型セグメント110に設けられている雌型接続部材111を示す。この雌型接続部材111は、セグメント本体112の内部の地山側に設けられた凹部113と、その内面を覆うように配設された金属板114と、によって構成されている。
また、この実施の形態では、雌型及び雄型接続部材11、21を成形する材料として鋼板を例示したが、これに限られるものではなく、軽量、且つ所定の強度と靭性を有するものであれば如何なる材料であっても良い。例えば塩化ビニル等の樹脂により成形されたプラスチックや、セラミック等でも良い。
【0032】
【発明の効果】
請求項1に記載の発明によれば、雌型セグメントを含んで構成される第1トンネルを構築し、次に、第1トンネルに設けられた雌型接続部材に雄型接続部材を係合させるようにして第2トンネルを後行して構築することによって、第1トンネルと第2トンネルとを接続する。つまり、雌型セグメントの雌型接続部材に雄型接続部材を係合させながら雄型セグメントを第1トンネルの軸方向に移動させるように当該雄型セグメントの履工を行うことによって、第2トンネルの構築及び当該第2トンネルと第1トンネルとの接続を行うことができる。従って、トンネルを接続する際に、安全性を確保する目的で薬液注入等による地盤改良を行う必要がなくなり、少なくとも2つ以上のトンネルどうしの接続を容易に、且つ安全に行うことができる。
さらに、地盤改良工法を行う必要がないだけでなく、例えば、多円形MF工法のように専用のシールド機を作成する必要がなく汎用型のシールド機を利用してトンネルを構築することができるので、それらにかかる費用を低減することができる。
【0033】
請求項2に記載の発明によれば、雌型接続部材及び雄型接続部材は、トンネルの軸方向に延在するように設けられているので、雌型セグメントと雄型セグメントとの接続が強固になる。従って、2つのトンネルを強固に接続することができる。
【0034】
請求項3に記載の発明によれば、雌型接続部材及び雄型接続部材は、金属成形されているので、雌型セグメントと雄型セグメントとの接続がより強固になる。従って、2つのトンネルをより強固に接続することができる。
【図面の簡単な説明】
【図1】トンネル接続用セグメントの全体を説明する概略斜視図である。
【図2】鋼製のセグメントを示す概略斜視図である。
【図3】図3は、雌型セグメントに設けられた雌型接続部材の要部断面図であり、(a)は図2の鋼製のセグメント本体に設けられた雌型接続部材の要部断面図であり、(b)はRC製のセグメント本体に設けられた雌型接続部材の要部断面図である。
【図4】トンネル接続用セグメントを用いて構築するトンネルの施工方法を示す図であり、(a)はMMST工法に代わる施工方法であり、(b)は3連型MFシールド工法に代わる施工方法である。
【符号の説明】
1 トンネル接続用セグメント
10 雌型セグメント
11、111 雌型接続部材
12、22 セグメント本体
20 雄型セグメント
21 雄型接続部材
50 セグメント[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a tunnel connection method.
[0002]
[Prior art]
Conventionally, underground use of roads, railways, etc. has been mentioned as one of the underground usage measures in urban areas. Such road and railway tunnels are constructed by the shield method because the land is not sufficient, there are many ground restrictions, and the ground is soft.
The tunnel constructed by the shield method has a mechanically circular cross section that has the most efficient shape. However, since the shape of the tunnel required for building roads and railways is rectangular (horizontal rectangle), a circular tunnel with a diameter larger than necessary is constructed in advance, and the inside of the circular tunnel is It was supposed to build a rectangular tunnel.
[0003]
Therefore, recently, an MMST (multi-micro shield tunnel) method (see Japanese Patent Application Laid-Open No. 2000-328899) for connecting rectangular tunnels to form a peripheral tunnel into a rectangle, and a multi-circular MF (multi-face) method A construction method such as a DOT (double oh tube) construction method for constructing a tunnel having a combination of a plurality of circular tunnels has been devised and implemented.
[Problems to be solved by the invention]
However, in the MMST method, for example, when connecting small-diameter tunnels composed of a plurality of segments (see FIG. 2), it is necessary to improve the ground to ensure safety. There was a problem that it was difficult to ensure safety by the improved construction method.
Further, for example, in the multi-circular MF construction method, since the shield machine is manufactured in accordance with the shape of the tunnel to be constructed, the shield machine is not versatile and difficult to divert. Another problem is that the construction cost of the shield machine is high due to the high production cost of the shield machine.
[0004]
The present invention has been made in view of the above circumstances, and provides a tunnel connection method capable of easily and safely connecting at least two tunnels and reducing the cost of tunnel construction. The purpose is to do.
[0005]
[Means for Solving the Problems]
To solve the above problem,
The invention of
A tunnel connection method for connecting tunnels composed of a plurality of
A concave
A portion of the
First, a first tunnel configured to include the
[0006]
Here, the segment may be made of any material such as a steel segment or an RC (reinforced concrete) segment. Further, the shape of the segment may be any shape such as a rectangular shape or a polygonal shape as long as adjacent segments can be connected.
Further, the female connection member and the male connection member are molded from a material that is lightweight and has strength and toughness. Examples of the material include metals, plastics molded from resins such as vinyl chloride, and ceramics.
[0007]
According to the first aspect of the present invention, the first tunnel configured to include the female segment is constructed, and then the male connection member is engaged with the female connection member provided in the first tunnel. Thus, the first tunnel and the second tunnel are connected by constructing the second tunnel behind the scenes. In other words, the second tunnel is constructed by mounting the male segment so as to move the male segment in the axial direction of the first tunnel while engaging the male connection member with the female connection member of the female segment. And the connection between the second tunnel and the first tunnel can be performed. Therefore, when connecting the tunnels, it is not necessary to perform ground improvement by injecting a chemical solution or the like for the purpose of ensuring safety, and at least two or more tunnels can be easily and safely connected.
Furthermore, it is not only necessary to perform ground improvement method, but for example, it is not necessary to create a dedicated shield machine like the multi-circular MF method, and a tunnel can be constructed using a general-purpose shield machine. , They can reduce the cost.
[0008]
Here, as a chemical | medical solution used for ground improvement, cement milk etc. are mentioned, for example.
[0009]
The invention according to claim 2 is the tunnel connection method according to
The
[0010]
According to the invention described in claim 2, since the female connection member and the male connection member are provided so as to extend in the axial direction of the tunnel, the connection between the female segment and the male segment is strong. become. Therefore, the two tunnels can be firmly connected.
[0011]
The invention according to claim 3 is the tunnel connection method according to
The
[0012]
According to the third aspect of the present invention, since the female connection member and the male connection member are metal-formed, the connection between the female segment and the male segment becomes stronger. Therefore, the two tunnels can be connected more firmly.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
The
FIG. 1 is a schematic perspective view illustrating the entire
[0016]
First, the configuration of the
For example, as shown in FIG. 1, the
[0017]
The female-
The
The
[0018]
The
[0019]
On the other hand, the
Similar to the
The
[0020]
Each of the female mold and the
[0021]
Therefore, as one of the
[0022]
Next, a tunnel connection method using the
[0023]
First, the first tunnel is constructed in advance among the first and second tunnels to be connected.
The first tunnel is configured to include a
Specifically, the second tunnel is constructed in advance by excavating a natural ground by an excavator (not shown) to form an underground cavity and mounting a plurality of
The first tunnel is constructed by sequentially performing this operation.
Accordingly, the
[0024]
A back-filling
[0025]
The second tunnel is then constructed following.
The second tunnel is configured to include the
[0026]
This second tunnel is constructed by the propulsion method.
Specifically, first, a segment ring (not shown; hereinafter abbreviated as a first segment ring) configured to include the
[0027]
Subsequently, similarly to the first segment ring, the segment ring to be pushed next (not shown; hereinafter abbreviated as second segment ring) is assembled and positioned by the shaft, and the rear end of the second segment ring is pushed. And push it into the ground with a jack. Accordingly, the ground is further excavated by the excavator, and the first segment ring is further pushed into the underground cavity formed in the ground along with the excavation, and the second segment ring is pushed after the first segment ring. As a result, the first segment ring is pushed into the back side of the underground cavity while being engaged with the
[0028]
By sequentially performing this operation, the second tunnel is constructed in a state of being connected to the first tunnel.
[0029]
As described above, according to this embodiment, the first tunnel configured to include the
Furthermore, it is not only necessary to perform ground improvement method, but for example, it is not necessary to create a dedicated shield machine like the multi-circular MF method, and a tunnel can be constructed using a general-purpose shield machine. , They can reduce the cost.
Further, since the female and
[0030]
Further, according to the tunnel connection method of this embodiment, the tunnel can be constructed by a method that is an alternative to the conventional tunnel construction method.
For example, a tunnel construction method that replaces the conventional MMST method will be described with reference to FIG.
First, the
By carrying out this operation in the
Further, for example, FIG. 4B shows a tunnel construction method that replaces the conventional triple MF shield method.
Specifically, first, the
As a result, a large tunnel similar to the conventional triple MF method can be constructed.
[0031]
In addition, this invention is not limited to a present Example, Arbitrary deformation | transformation is possible in the range which does not deviate from the meaning of this invention.
For example, in this embodiment, the female and
In this embodiment, a steel plate is exemplified as a material for forming the female and
[0032]
【The invention's effect】
According to the first aspect of the present invention, the first tunnel configured to include the female segment is constructed, and then the male connection member is engaged with the female connection member provided in the first tunnel. Thus, the first tunnel and the second tunnel are connected by constructing the second tunnel behind the scenes. In other words, the second tunnel is constructed by mounting the male segment so as to move the male segment in the axial direction of the first tunnel while engaging the male connection member with the female connection member of the female segment. And the connection between the second tunnel and the first tunnel can be performed. Therefore, when connecting the tunnels, it is not necessary to perform ground improvement by injecting a chemical solution or the like for the purpose of ensuring safety, and at least two or more tunnels can be easily and safely connected.
Furthermore, it is not only necessary to perform ground improvement method, but for example, it is not necessary to create a dedicated shield machine like the multi-circular MF method, and a tunnel can be constructed using a general-purpose shield machine. , They can reduce the cost.
[0033]
According to the invention described in claim 2, since the female connection member and the male connection member are provided so as to extend in the axial direction of the tunnel, the connection between the female segment and the male segment is strong. become. Therefore, the two tunnels can be firmly connected.
[0034]
According to the third aspect of the present invention, since the female connection member and the male connection member are metal-formed, the connection between the female segment and the male segment becomes stronger. Therefore, the two tunnels can be connected more firmly.
[Brief description of the drawings]
FIG. 1 is a schematic perspective view illustrating an entire tunnel connection segment.
FIG. 2 is a schematic perspective view showing a steel segment.
3 is a cross-sectional view of the main part of the female connection member provided in the female segment; FIG. 3A is a main part of the female connection member provided in the steel segment body of FIG. 2; It is sectional drawing, (b) is principal part sectional drawing of the female type | mold connection member provided in the segment main body made from RC.
FIG. 4 is a diagram showing a tunnel construction method constructed using tunnel connection segments, (a) is a construction method that replaces the MMST method, and (b) is a construction method that replaces the triple MF shield method. It is.
[Explanation of symbols]
DESCRIPTION OF
Claims (3)
前記雌型セグメントの内部の地山側には凹状の雌型接続部材が設けられ、
前記雄型セグメントの地山側の部分には、トンネルの軸方向に移動させることにより前記雌型接続部材に係合する略T字状の雄型接続部材が設けられ、
先ず、前記雌型セグメントを含んで構成される第1トンネルを構築し、次に、前記第1トンネルに設けられた前記雌型接続部材に前記雄型接続部材を係合させながら前記雄型セグメントを前記第1トンネルの軸方向に移動させて、当該雄型セグメントを含んで構成される第2トンネルを構築することによって、前記第1トンネルと前記第2トンネルとを接続することを特徴とするトンネルの接続方法。A tunnel connection method for connecting tunnels composed of a plurality of segments for mounting the inner surface of an underground cavity formed by excavating natural ground using a female segment and a male segment,
A concave female connection member is provided on the natural ground side inside the female segment,
A portion of the male segment on the ground mountain side is provided with a substantially T-shaped male connecting member that engages with the female connecting member by moving in the axial direction of the tunnel,
First, a first tunnel configured to include the female segment is constructed, and then the male segment is engaged while the male connection member is engaged with the female connection member provided in the first tunnel. By moving the first tunnel in the axial direction of the first tunnel to construct a second tunnel including the male segment, thereby connecting the first tunnel and the second tunnel. Tunnel connection method.
前記雌型接続部材及び前記雄型接続部材は、トンネルの軸方向に延在するように設けられていることを特徴とするトンネルの接続方法。The tunnel connection method according to claim 1,
The female connection member and the male connection member are provided so as to extend in the axial direction of the tunnel.
前記雌型接続部材及び前記雄型接続部材は、金属成形されていることを特徴とするトンネルの接続方法。In the tunnel connection method according to claim 1 or 2,
The method for connecting tunnels, wherein the female connection member and the male connection member are formed of metal.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2001316813A JP3609364B2 (en) | 2001-10-15 | 2001-10-15 | Tunnel connection method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2001316813A JP3609364B2 (en) | 2001-10-15 | 2001-10-15 | Tunnel connection method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2003120192A JP2003120192A (en) | 2003-04-23 |
| JP3609364B2 true JP3609364B2 (en) | 2005-01-12 |
Family
ID=19134767
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2001316813A Expired - Lifetime JP3609364B2 (en) | 2001-10-15 | 2001-10-15 | Tunnel connection method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3609364B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4500142B2 (en) * | 2004-09-27 | 2010-07-14 | 大成建設株式会社 | Underground structure and its construction method |
| JP4746601B2 (en) * | 2007-03-29 | 2011-08-10 | 新日本製鐵株式会社 | Segment connection structure |
-
2001
- 2001-10-15 JP JP2001316813A patent/JP3609364B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2003120192A (en) | 2003-04-23 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3609364B2 (en) | Tunnel connection method | |
| JP2751636B2 (en) | Tunnel construction method and underground space construction method | |
| JP2007077677A (en) | Construction method of underground structure | |
| JP5136344B2 (en) | Construction method of rectangular tunnel and rectangular tunnel | |
| JP2942874B2 (en) | How to join tunnels | |
| JP4074210B2 (en) | Shield tunnel and shield tunnel connection method | |
| JP5117369B2 (en) | Underpass construction method | |
| JP3765048B2 (en) | How to build a tunnel | |
| JP4264049B2 (en) | Branch construction method of shield tunnel and slide gate device | |
| JP2663106B2 (en) | Construction method of outer wall of propulsion pipe and large cavity | |
| JPH02153196A (en) | Tunnel excavation method and shield excavation machine | |
| JP4243989B2 (en) | Outer shell structure of underground structure | |
| JP2000220400A (en) | Construction method for underground structures | |
| JP2755772B2 (en) | Bonding method and device between shield tunnel and structure or shield tunnel | |
| KR100625037B1 (en) | Split Messer Plate and Tunnel Excavation Method Using the Same | |
| JP4563332B2 (en) | Tunnel variable section construction method and tunnel excavator used in the construction method | |
| JP2011080310A (en) | Construction method of tunnel | |
| JPH09317397A (en) | Large section tunnel and its construction method | |
| JP3580381B2 (en) | Pre-installation method of tunnel and its supporting method | |
| JPH0747512Y2 (en) | Concrete segment | |
| JP6940341B2 (en) | Tunnel excavator and tunnel construction method | |
| JPH10220194A (en) | Large section tunnel and its construction method | |
| JP2002013384A (en) | Separate united tunnel machine and construction method of tunnel branch | |
| JPH10121881A (en) | Tunnel widening method | |
| JP2004308250A (en) | Construction method for tunnel branch confluence part and structure of tunnel branch confluent part |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040213 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040224 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040422 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20040525 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040720 |
|
| A911 | Transfer of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20040729 |
|
| A912 | Removal of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A912 Effective date: 20040820 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20041013 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 3609364 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101022 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101022 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111022 Year of fee payment: 7 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111022 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121022 Year of fee payment: 8 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121022 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141022 Year of fee payment: 10 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |