JP3629130B2 - Load prediction method and load status display method - Google Patents
Load prediction method and load status display method Download PDFInfo
- Publication number
- JP3629130B2 JP3629130B2 JP00236298A JP236298A JP3629130B2 JP 3629130 B2 JP3629130 B2 JP 3629130B2 JP 00236298 A JP00236298 A JP 00236298A JP 236298 A JP236298 A JP 236298A JP 3629130 B2 JP3629130 B2 JP 3629130B2
- Authority
- JP
- Japan
- Prior art keywords
- load
- amount
- rate
- estimated
- distribution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Description
【0001】
【発明の属する技術分野】
この発明は将来の負荷を予測する負荷予測方法と、その予測結果を表示する負荷状況表示方法に関するもので、変電所の設置および増強等の設備増強計画の策定、検討を支援するものである。
【0002】
【従来の技術】
図7は、例えば特開平6−197451号公報等に示されている配電系統計画支援装置の機能ブロック図である。
図7において、15は配電設備データ13と需要家データ14より設備の接続データを用いて配電系統データを生成する配電系統データ生成手段、16は配電系統データ生成手段15により生成される系統データ、17は系統データ16を配電系統図として表示する表示装置である。
18は表示装置17で表示される系統図上にて作成する配電設備増強計画を行う配電設備増強計画手段である。
【0003】
次に配電系統計画支援装置22の動作を説明する。
(1)まず図8により配電設備増強計画をする場合の動作例を説明する。
a. 配電設備増強計画手段18は、既設の配電線23があり需要家24に対して配電する場合、需要家24に対して配電線25の布設を計画配電線として表示装置17に入力する。
b. 入力された計画設備は、計画設備データ21として保存される。
【0004】
(2)次に、図9により配電系統の変更をする場合について動作を説明する。
配電系統変更手段19は、表示装置17で表示される系統図上の設備絵を操作することにより供給する配電系統の変更を行う手段であり次の動作を行う。
【0005】
▲1▼変更前に配電線26から開閉器27を通って配電線28、需要家29に供給していた系統を開閉器27を入→切に、開閉器30を切→入にすることにより、配電線31から開閉器30を通って配電線28、需要家29に供給していた系統に変更する。
▲2▼変更された開閉器データおよび系統データは、計画設備データ21として保存される。
【0006】
(3)供給支障判定装置20について説明する。
配電設備増強計画手段18、配電系統変更手段19により増設・変更する場合、供給支障判定装置20は需要家24の増加または需要家29の系統変更により、供給する配電系統について系統の持つ供給力を超えていないか、需要家までの電圧降下が既定値を超えていないかを判定する。
【0007】
以上のように、配電系統計画支援装置22は、上記(1)〜(3)に説明した一連の操作により将来、需要家の増加、変更が発生した際に、配電系統の供給計画を策定する。
【0008】
【発明が解決しようとする課題】
上記の様な配電系統計画支援装置は需要家の増加、変更に対する配電系統の変更、または新規供給設備の計画を系統レベルで行うことができるが、宅地や工業団地など大規模な配電系統の計画の際には変電所、または系統全体といった広域エリアでの負荷状況の把握、また負荷状況により変電所または系統等大規模な設備計画を行わねばならない場合があり現状の系統単位での支援装置では対応しきれず、上記配電系統計画支援装置の系統図面を用いて手作業にて広域の計画を策定しなければならない問題点があった。
【0009】
本発明は上記の様な問題点を解決するためになされたものであり、変電所、系統全体または任意の範囲のエリアに対する現在、将来の負荷状況を策定する負荷予測方法を得ることを目的とし、また、表示装置を用いて視覚的に表す負荷状況表示方法を得ることを目的とする。
【0010】
【発明を解決するための手段】
(1)この発明に係る負荷予測方法は、変電所単位あるいは系統単位内に存在する複数の需要家(負荷)の負荷契約容量の総和と負荷実績量との比に応じて按分率を算出し、上記按分率を各需要家契約容量に掛けて各負荷の平均使用量を算出し、上記各負荷平均使用量に各負荷の所定期間における伸び率を掛けて所定期間後の負荷想定量を導出するようにしたものである。
【0011】
(2)また、変電所単位あるいは系統単位内に存在する複数の需要家(負荷)の負荷契約容量の総和と負荷実績量との比に応じて按分率を算出し、上記所定単位内を任意の区域に分割し、上記所定単位内の任意の区域毎の負荷契約容量に上記按分率を掛けて各負荷の平均使用量を算出し、上記各負荷平均使用量に地域毎の所定期間における各負荷の伸び率を掛けて上記任意区域単位の所定期間後の負荷想定量を導出するようにしたものである。
【0012】
(3)また、上記(1)または(2)において、所定単位の各負荷毎または任意の区域毎の所定期間後の負荷想定量を集計して、上記所定単位の所定期間後の負荷想定量を導出するようにしたものである。
【0013】
(4)この発明に係る負荷状況表示方法は、表示装置を用いて、表示対象とする変電所、系統、負荷等を含む系統図を表示すると共に、上記(1)〜(3)のいずれか1項の負荷予測方法で導出した各負荷毎または任意の区域毎の負荷想定量を表示して、この負荷想定量の分布状況が表示されるようにしたものである。
【0014】
(5)また、表示装置を用いて、対象とする変電所、系統、負荷などの系統図を表示すると共に、上記(1)〜(3)のいずれか1項の負荷予測方法で導出した各負荷毎または任意の区域毎の負荷想定量と現在の負荷実績量との比較に応じて負荷増加量または負荷増加率を求めて表示し、この負荷増加量または負荷増加率の分布状況が表示されるようにしたものである。
【0015】
(6)また、上記(4)または(5)において、
負荷想定量または負荷増加量或いは負荷増加率に応じて、この負荷想定量または負荷増加量或いは負荷増加率に対応する画面上の部分を色別・明暗別・フリッカなどの識別可能な区分表示とするものである。
【0016】
(7)また、上記(4)〜(6)のいずれか1項において、
想定した負荷の分布状況または増加する負荷の分布状況の表示画面上で、任意の範囲を指定するとその範囲内の負荷想定量または負荷増加量或いは負荷増加率を表示するものである。
【0017】
【発明の実施の形態】
実施の形態1.
以下この発明の実施の形態1を図に基づいて説明する。
図1は負荷状況表示装置12の機能ブロック図である。
図において、3は配電設備データ1と需要家データ2より設備の接続データを用いて配電系統データを生成する系統データ生成手段、4は系統データ生成手段3により生成される系統データである。
【0018】
7は負荷想定量算出手段で、系統データ4、負荷実績データ5、想定伸び率データ6より負荷想定量を算出する。
8は負荷分布状況表示手段で、負荷想定量算出手段7により算出された負荷想定量に基づいて負荷分布状況を表示装置10で表示する。
9は任意範囲負荷想定量表示手段で、負荷想定量算出手段7により算出された負荷想定量に基づいて所望の範囲内の負荷分布状況を表示装置10で表示する。
【0019】
図2、図3はこの実施の形態の負荷想定量算出手段により算出した3年後の変電所単位の負荷想定量計算例である。
(1)図2(a)のように、変電所32供給エリア33に配電系統34〜38があり、それぞれの系統に39〜48の需要家(負荷)がある状態が表示装置10の画面上に表示される。
(2)図2(b)のように、需要家39〜48の需要家データ2より契約容量を取り出し、変電所32の供給エリア33の負荷契約量総和(200kW)を計算する。
【0020】
(3)一方、変電所32の負荷実績量データの値が150kWであるとすると、下記の式(1)により、按分率を算出する。
負荷実績量(kW)/需要家契約容量総和(kW)=按分率−−−(1)
具体的には、
負荷実績量150kW/需要家契約容量総和200kW=按分率0.75
となる。
【0021】
(4)按分率は契約容量に対する実際の使用量を変電所単位で平均化した値であり、この按分率を39〜48の需要家契約容量に掛け、各負荷の変電所単位で平準化した使用量を算出する。
図2(c)は各負荷(各需要家)の変電所単位で平準化した使用量である。
なお、按分率は1以下の値となる。
【0022】
(5)次に、図3の表示のように、上記算出された需要家平均使用量に各地域単位で所有する伸び率データを掛け、変電所単位の3年後の負荷想定量を算出し、表示する。
変電所供給エリア33内は49,50,51の3つの地域(想定伸び率データを持つ単位地域)があり、各需要家の属する地域の伸び率を掛け合わせることになる。
【0023】
これを具体的に説明すると、図3において、地域49の3年後の負荷伸び率を1.0%、地域50の3年後の負荷伸び率を2.0%、地域51の3年後の負荷伸び率を4.0%として計算され、その結果が図3のように表示される。
伸び率が考慮された各需要家の負荷想定量を33の変電所供給エリアに対して総和を取ると3年後の変電所32の負荷想定量153.3kWが求められる。
【0024】
この算出方法を算式で表わすと、次の式(2)となる。
なお、右辺の第1項は按分率である。
【0025】
(6)上記負荷想定値の算出方法を1〜N年後に対して行い、変電所単位で表示装置10により算出結果を表示することにより、複数変電所供給エリア間での負荷想定量の推移の違いが確認できる。
【0026】
(7)また、上記負荷想定値の算出方法において、集計単位と負荷実績量を配電系統単位の値に置き換えることにより、配電系統単位で1〜N年後に対して負荷想定値を表示装置に表すことにより推移が確認できる。
【0027】
以上のように、変電所単位、配電系統単位、または任意の地域等の将来の負荷想定量を算出すると共に、その算出結果を負荷分布状況として表示することにより、設備計画を効率的に行うことができる。
従って、変電所または系統等大規模な設備計画の効率化を支援することが可能となる。
【0028】
実施の形態2.
以下この発明の実施の形態2を図に基づいて説明する。
負荷状況表示装置の機能ブロック図は図1と同一である。
図4はこの実施の形態2の負荷分布状況表示手段を適用した表示装置における表示例で、図4(a)は変電所のエリア77と78との2つある例を示し、91はその変電所供給エリアの境界を示している。これを図4(b)のように表示する。
【0029】
図4(b)において、表示されている地域を52〜76で区切られたメッシュに分け、実施の形態1の負荷想定量算出方法にて各需要家単位の負荷想定量をメッシュ単位で集計することにより、メッシュ単位の負荷想定量を算出する。
図4(b)ではメッシュ表示の際に負荷想定量に応じて3色に色別していて、その色分けは「負荷想定量の少ない地域」「負荷想定量の平均的な地域」「負荷想定量の多い地域」としている。
【0030】
この表示を1〜N年後に対して行うことにより、変電所供給エリア77、78のように複数変電所供給エリア間と対比させて、変電所単位の負荷想定量のみに捕われることなく、負荷量増加による対策地域の特定を行うことが可能である。
【0031】
なお、上記では負荷想定量に応じて色別表示したが、これは色別以外に、画面上の明暗別で表示してもよく、また、明暗の繰り返し即ちフリッカーをしてもよくフリッカーの有無や頻度(時間間隔)の違いなどで区分して表示するようにしてもよい。
【0032】
実施の形態3.
以下この発明の実施の形態3を図に基づいて説明する。
図5は図1に示す任意範囲負荷想定量表示手段を適用した表示装置における表示例である。
【0033】
表示装置上に表された変電所供給エリア79、80に対して、新規に変電所の設置を計画して供給エリアを分割する際に、81に示したような任意のエリアをマウス等により表示装置上で描画し、実施の形態1の負荷想定量算出方法にて各需要家単位の負荷想定量を指定エリア81内で集計し、指定エリアを変化させながら随時エリア内の負荷想定値(例えば、任意設定エリア81で102kW)を確認することにより、新設計画変電所の供給エリアを視覚的に瞬時に表示し確認することが可能である。
【0034】
実施の形態4.
以下この発明の実施の形態4を図に基づいて説明する。
図6は図1に示す負荷分布状況表示手段8の応用表示例である。
【0035】
52〜76で区切られたメッシュ表示の色別を行う場合、下記の式(3)により、現在と比較し、
を算出し、算出されたメッシュ内負荷増加量に応じて3色(図中では白黒濃淡で表示)に色別する。但し、色数は3色以外に任意に設定できる。
【0036】
この表示を1〜N年後に対して行うことにより負荷量増加の著しい対策必要地域をより容易に特定することが可能である。
【0037】
また、上記式(3)の代わりに、次の式(4)でその比率を算出してもよい。
【0038】
なお、この説明ではメッシュ内の負荷増加量(率)としたが、メッシュ以外に、変電所エリア毎、配電系統毎、任意のエリア毎等のの負荷増加量(または負荷増加率)を求めるようにしてもよい。
【0039】
実施の形態5.
上記実施の形態では、配電系統の場合について説明したが、送電系統も含め電力系統全般に適用することができる。
【0040】
【発明の効果】
以上のように、この発明によれば将来の負荷想定量を算出し、また、その算出結果を表示することにより、変電所、系統全体または任意の範囲の供給エリアに対する将来の負荷状況を策定することを支援する効果がある。
【図面の簡単な説明】
【図1】この発明の実施の形態1によ負荷状況表示装置を示す機能ブロック図である。
【図2】この発明の実施の形態1による負荷想定量算出手段を説明するための図である。
【図3】この発明の実施の形態1による負荷想定量算出手段を説明するための図である。
【図4】この発明の実施の形態2による負荷分布状況表示手段を用いた表示画面の図である。
【図5】この発明の実施の形態3による任意負荷想定量表示手段を用いた表示画面の図である。
【図6】この発明の実施の形態4による負荷分布状況表示手段を用いた表示画面の図である。
【図7】従来の配電系統計画支援装置を示す機能ブロック図である。
【図8】従来の配電系統計画支援装置において系統図上にて作成する配電設備増強計画手段の表示画面の図である。
【図9】従来の配電系統計画支援装置において系統図上にて作成する配電系統変更手段の表示画面の図である。
【符号の説明】
1 設備データ 2 需要家データ
3 系統データ生成手段 4 系統データ
5 負荷実績データ 6 想定伸び率データ
7 負荷想定量算出手段 8 負荷分布状況表示手段
9 任意範囲負荷想定量表示手段 10 表示装置
11 計画設備データ 32 変電所
33 変電所供給エリア 34〜38 配電系統
39〜48 需要家 49,50,51 想定伸び率データを持つ単位地域
52〜76 単位メッシュ 77,78,79,80 変電所供給エリア
81 任意設定エリア 91 変電所供給エリア境界[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a load prediction method for predicting a future load and a load status display method for displaying the prediction result, and supports the development and examination of a facility enhancement plan such as installation and enhancement of a substation.
[0002]
[Prior art]
FIG. 7 is a functional block diagram of a distribution system planning support apparatus disclosed in, for example, Japanese Patent Laid-Open No. 6-197451.
In FIG. 7, 15 is a distribution system data generating means for generating distribution system data using the connection data of the equipment from the distribution equipment data 13 and the customer data 14, and 16 is system data generated by the distribution system data generating means 15. A
Reference numeral 18 denotes distribution facility enhancement plan means for performing a distribution facility enhancement plan created on the system diagram displayed on the
[0003]
Next, the operation of the distribution system plan support device 22 will be described.
(1) First, an operation example in the case where a distribution facility enhancement plan is made will be described with reference to FIG.
a. The distribution facility enhancement plan means 18 inputs the installation of the
b. The inputted planned equipment is stored as the planned
[0004]
(2) Next, the operation in the case of changing the distribution system will be described with reference to FIG.
The distribution system changing means 19 is a means for changing the distribution system to be supplied by operating the equipment picture on the system diagram displayed on the
[0005]
(1) By switching the
(2) The changed switch data and system data are stored as the planned
[0006]
(3) The supply
When expansion / change is made by the distribution facility enhancement planning means 18 and the distribution system changing means 19, the supply
[0007]
As described above, the distribution system planning support apparatus 22 formulates a distribution system supply plan when the number of consumers increases or changes in the future by the series of operations described in (1) to (3) above. .
[0008]
[Problems to be solved by the invention]
The distribution system planning support device as described above can increase the number of consumers, change the distribution system in response to the change, or plan new supply facilities at the system level, but plans for large-scale distribution systems such as residential land and industrial parks. In this case, it may be necessary to grasp the load situation in a wide area such as a substation or the entire grid, and to make a large-scale facility plan such as a substation or grid depending on the load situation. There was a problem that a wide area plan had to be developed manually using the system drawing of the distribution system planning support device.
[0009]
The present invention has been made to solve the above-described problems, and an object of the present invention is to obtain a load prediction method for formulating current and future load situations for a substation, the entire system, or an area of an arbitrary range. Another object of the present invention is to obtain a load status display method that is visually expressed using a display device.
[0010]
[Means for Solving the Invention]
(1) In the load prediction method according to the present invention, a distribution ratio is calculated according to a ratio between a total load contract capacity of a plurality of consumers (loads) existing in a substation unit or system unit and a load actual amount. The average usage of each load is calculated by multiplying the apportionment rate by each customer contract capacity, and the expected load after a predetermined period is derived by multiplying the average usage of each load by the growth rate of each load for a predetermined period. It is what you do.
[0011]
(2) In addition, the distribution ratio is calculated according to the ratio of the total load contract capacity of multiple customers (loads) existing in the substation unit or system unit and the actual load amount, and the predetermined unit is arbitrarily selected. And calculate the average usage amount of each load by multiplying the load contract capacity for each arbitrary area within the predetermined unit by the apportionment rate, and calculate the average usage amount of each load for each predetermined period for each region. By multiplying the rate of load increase, an estimated load after a predetermined period of the above-mentioned arbitrary area unit is derived.
[0012]
(3) In addition, in (1) or (2) above, the estimated load after a predetermined period of the predetermined unit is totaled by summing up the estimated load after a predetermined period for each load of a predetermined unit or for each arbitrary area. Is derived.
[0013]
(4) The load status display method according to the present invention displays a system diagram including a substation, a system, a load, and the like to be displayed using a display device, and any one of the above (1) to (3) The assumed load amount for each load or any area derived by the load prediction method of
[0014]
(5) Moreover, while displaying system diagrams, such as a target substation, a system | strain, and load, using a display apparatus, each derived | led-out by the load prediction method of any one of said (1)-(3) The load increase amount or load increase rate is obtained and displayed according to the comparison between the estimated load amount for each load or any area and the current actual load amount, and the distribution status of this load increase amount or load increase rate is displayed. It was made to do.
[0015]
(6) In the above (4) or (5),
Depending on the estimated load, load increase, or load increase rate, the portion on the screen corresponding to this estimated load, load increase, or load increase rate can be identified by color, light / dark, flicker, etc. To do.
[0016]
(7) Also, in any one of the above (4) to (6),
When an arbitrary range is specified on the display screen of the assumed load distribution state or the increasing load distribution state, the assumed load amount, the load increase amount, or the load increase rate within the range is displayed.
[0017]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 is a functional block diagram of the load status display device 12.
In the figure, 3 is system data generating means for generating distribution system data from the
[0018]
7 is an assumed load amount calculation means, which calculates an estimated load amount from the
[0019]
FIG. 2 and FIG. 3 are examples of load assumption calculation for each substation after three years calculated by the load assumption calculation means of this embodiment.
(1) As shown in FIG. 2 (a), there is a distribution system 34-38 in the
(2) As shown in FIG. 2B, the contract capacity is extracted from the
[0020]
(3) On the other hand, when the value of the load actual amount data of the
Actual load (kW) / Total customer contract capacity (kW) = Proportional rate --- (1)
In particular,
Actual load 150 kW / Total customer contract capacity 200 kW = Apportion rate 0.75
It becomes.
[0021]
(4) The apportioning rate is a value obtained by averaging the actual usage with respect to the contracted capacity in units of substations. The apportioning rate is multiplied by 39 to 48 customer contracted capacities and leveled in units of substations for each load. Calculate usage.
FIG. 2 (c) shows the amount of use leveled in units of substations for each load (each customer).
Note that the proration rate is a value of 1 or less.
[0022]
(5) Next, as shown in Fig. 3, multiply the calculated average consumer usage by the growth rate data owned for each region, and calculate the estimated load after 3 years for each substation. ,indicate.
The
[0023]
Specifically, in FIG. 3, the load growth rate after 3 years in the region 49 is 1.0%, the load growth rate after 3 years in the region 50 is 2.0%, and after 3 years in the region 51. The load elongation rate is calculated as 4.0%, and the result is displayed as shown in FIG.
When the load assumption amount of each customer in consideration of the growth rate is summed for the 33 substation supply areas, the load assumption amount 153.3 kW of the
[0024]
This calculation method is expressed by the following formula (2).
The first term on the right side is the proration rate.
[0025]
(6) The estimated load value is calculated for 1 to N years later, and the calculation result is displayed on the
[0026]
(7) Moreover, in the calculation method of the estimated load value described above, the estimated load value is represented on the display device for 1 to N years after the distribution system unit by replacing the total unit and the actual load amount with the value of the distribution system unit. The transition can be confirmed.
[0027]
As described above, calculate the expected load for the future in each substation, distribution system, or any area, and display the calculation result as the load distribution status to efficiently plan the facility. Can do.
Therefore, it is possible to support the efficiency improvement of a large-scale facility plan such as a substation or a system.
[0028]
The functional block diagram of the load status display device is the same as FIG.
FIG. 4 is a display example in a display device to which the load distribution status display means of the second embodiment is applied. FIG. 4 (a) shows two examples of
[0029]
In FIG.4 (b), the displayed area is divided | segmented into the mesh divided | segmented by 52-76, and the load assumption amount of each consumer is totaled in mesh unit by the load assumption amount calculation method of
In FIG. 4B, the mesh display is classified into three colors according to the load assumption amount, and the color classification is “region with a small load assumption amount”, “average region of load assumption amount”, “load assumption amount”. Many areas ”.
[0030]
By performing this display for 1 to N years later, the load is not captured by only the estimated load for each substation as compared to the substation supply areas such as the
[0031]
In the above, display is performed according to the color according to the assumed load, but this may be displayed according to the light and darkness on the screen in addition to the color, and the light may be repeated, that is, flicker may be performed. It is also possible to display it by dividing it according to the difference in frequency or time (time interval).
[0032]
FIG. 5 is a display example in a display device to which the arbitrary range load assumed amount display means shown in FIG. 1 is applied.
[0033]
When planning to newly install a substation for the substation supply areas 79 and 80 shown on the display device and dividing the supply area, an arbitrary area as shown in 81 is displayed with a mouse or the like. Drawing on the apparatus, the estimated load amount for each customer is aggregated in the designated
[0034]
FIG. 6 shows an application display example of the load distribution status display means 8 shown in FIG.
[0035]
When performing color display of the mesh display divided by 52 to 76, the following expression (3) is used to compare with the present,
And is classified into three colors (displayed in black and white in the drawing) according to the calculated load increase in the mesh. However, the number of colors can be arbitrarily set other than three colors.
[0036]
By performing this display for 1 to N years later, it is possible to more easily identify areas requiring significant countermeasures for increasing load.
[0037]
Further, the ratio may be calculated by the following equation (4) instead of the above equation (3).
[0038]
In this description, the load increase amount (rate) in the mesh is used. However, in addition to the mesh, the load increase amount (or load increase rate) for each substation area, each distribution system, each arbitrary area, etc. is obtained. It may be.
[0039]
Although the case of the distribution system has been described in the above embodiment, the present invention can be applied to the entire power system including the power transmission system.
[0040]
【The invention's effect】
As described above, according to the present invention, the future load situation is formulated for the substation, the entire system, or the supply area in an arbitrary range by calculating the estimated future load and displaying the calculation result. There is an effect to support that.
[Brief description of the drawings]
FIG. 1 is a functional block diagram showing a load status display device according to
FIG. 2 is a diagram for explaining an assumed load amount calculating means according to the first embodiment of the present invention.
FIG. 3 is a diagram for explaining an assumed load amount calculating means according to the first embodiment of the present invention.
FIG. 4 is a diagram of a display screen using load distribution status display means according to
FIG. 5 is a diagram of a display screen using an arbitrary load assumed amount display unit according to
FIG. 6 is a diagram of a display screen using load distribution status display means according to
FIG. 7 is a functional block diagram showing a conventional distribution system planning support apparatus.
FIG. 8 is a diagram of a display screen of distribution facility enhancement planning means created on a system diagram in a conventional distribution system planning support apparatus.
FIG. 9 is a diagram of a display screen of a distribution system changing means created on a system diagram in a conventional distribution system planning support apparatus.
[Explanation of symbols]
DESCRIPTION OF
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP00236298A JP3629130B2 (en) | 1998-01-08 | 1998-01-08 | Load prediction method and load status display method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP00236298A JP3629130B2 (en) | 1998-01-08 | 1998-01-08 | Load prediction method and load status display method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH11206016A JPH11206016A (en) | 1999-07-30 |
| JP3629130B2 true JP3629130B2 (en) | 2005-03-16 |
Family
ID=11527156
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP00236298A Expired - Fee Related JP3629130B2 (en) | 1998-01-08 | 1998-01-08 | Load prediction method and load status display method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3629130B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20220011506A (en) * | 2020-07-21 | 2022-01-28 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2013124973A1 (en) * | 2012-02-21 | 2013-08-29 | 株式会社日立製作所 | Device for displaying electric power system information, and method for displaying electric power system information |
| JP6853981B2 (en) * | 2017-06-08 | 2021-04-07 | 清水建設株式会社 | Surplus power evaluation device and surplus power evaluation method |
| CN110751388A (en) * | 2019-10-14 | 2020-02-04 | 国网山东省电力公司泰安供电公司 | A method and system for calculating the distribution variable capacity index per household of a distribution network |
-
1998
- 1998-01-08 JP JP00236298A patent/JP3629130B2/en not_active Expired - Fee Related
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20220011506A (en) * | 2020-07-21 | 2022-01-28 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR102464083B1 (en) * | 2020-07-21 | 2022-11-08 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR20220150260A (en) * | 2020-07-21 | 2022-11-10 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR20220150259A (en) * | 2020-07-21 | 2022-11-10 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR20220150261A (en) * | 2020-07-21 | 2022-11-10 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR20220150861A (en) * | 2020-07-21 | 2022-11-11 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR20220153527A (en) * | 2020-07-21 | 2022-11-18 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR102511704B1 (en) * | 2020-07-21 | 2023-03-21 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR102512188B1 (en) * | 2020-07-21 | 2023-03-22 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR102512790B1 (en) * | 2020-07-21 | 2023-03-23 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR102513738B1 (en) * | 2020-07-21 | 2023-03-27 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
| KR102514243B1 (en) * | 2020-07-21 | 2023-03-29 | 한국전력공사 | System and Method for estimating power demand over the long term, Computer readable storage medium |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH11206016A (en) | 1999-07-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US10090704B2 (en) | Display device and display method of electric power system information | |
| Overbye et al. | New methods for the visualization of electric power system information | |
| Dam et al. | Intelligent demand response scheme for customer side load management | |
| Salehi et al. | Long term distribution network planning considering urbanity uncertainties | |
| US20140114489A1 (en) | Sustainable energy efficiency management system | |
| WO1996033544A1 (en) | Dynamic method for preventing voltage collapse in electrical power systems | |
| KR20100018444A (en) | Apparatus and method for real-time intelligent and autonomous load management | |
| Zidan et al. | Incorporating load variation and variable wind generation in service restoration plans for distribution systems | |
| Simonov | Dynamic partitioning of DC microgrid in resilient clusters using event-driven approach | |
| JP2004012376A (en) | Solar power system | |
| CN108182194A (en) | The management method that a kind of gridding based on power grid GIS divides | |
| KR20150028436A (en) | Apparatus and method for calculating connection possible capacity of distributed generator | |
| JP3629130B2 (en) | Load prediction method and load status display method | |
| Seema et al. | Implementation of consumer level intelligence in a smart micro-grid along with HEMS based price prediction scheme | |
| He et al. | Resilient distribution network with degradation-aware mobile energy storage systems | |
| JP6549896B2 (en) | Electric power demand adjustment device, electric power demand adjustment method and electric power demand adjustment program | |
| KR102210165B1 (en) | Method for deriving individual peak reduction for economic demand management of multiple customers | |
| Raju et al. | Implementation of demand response management in microgrids using iot and machine learning | |
| JP6919347B2 (en) | Display processing device, display processing method and display processing program | |
| CN106157180A (en) | The early warning system of platform district low-voltage problem | |
| Tran et al. | Model predictive energy management for building microgrids with IoT-based controllable loads | |
| Chitra et al. | A realistic approach for reduction of energy losses in low voltage distribution network | |
| bin Khamis et al. | Electricity forecasting for small scale power system using fuzzy logic | |
| Khelifa et al. | An energy monitoring and management system based on key performance indicators | |
| Avramidis et al. | Demand side flexibility prospects in modern LV networks: A probabilistic assessment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040305 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040309 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040426 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20041207 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20041210 |
|
| LAPS | Cancellation because of no payment of annual fees |