Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP3697348B2 - Improvement method for soft ground - Google Patents
[go: Go Back, main page]

JP3697348B2 - Improvement method for soft ground - Google Patents

Improvement method for soft ground Download PDF

Info

Publication number
JP3697348B2
JP3697348B2 JP09519498A JP9519498A JP3697348B2 JP 3697348 B2 JP3697348 B2 JP 3697348B2 JP 09519498 A JP09519498 A JP 09519498A JP 9519498 A JP9519498 A JP 9519498A JP 3697348 B2 JP3697348 B2 JP 3697348B2
Authority
JP
Japan
Prior art keywords
soft ground
ground
drilling
stirring
improved
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP09519498A
Other languages
Japanese (ja)
Other versions
JPH11269865A (en
Inventor
鉄雄 川人
伸行 藤澤
弘 一色
隆 遠藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Penta Ocean Construction Co Ltd
Original Assignee
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Penta Ocean Construction Co Ltd filed Critical Penta Ocean Construction Co Ltd
Priority to JP09519498A priority Critical patent/JP3697348B2/en
Publication of JPH11269865A publication Critical patent/JPH11269865A/en
Application granted granted Critical
Publication of JP3697348B2 publication Critical patent/JP3697348B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、土木・建築分野において用いられる機械攪拌による軟弱地盤の改良工法に属する。
【0002】
【従来の技術】
従来より、土木・建築構造物の構築に際して、地盤支持力の増大、地盤の変形(沈下、膨れ上がり、はらみ出し)、水圧・透水性の減少ないし除去、耐久性の維持・増進等を目的として、軟弱地盤の改良が行われている。
【0003】
ここで、軟弱地盤とは、固有の地盤に限定されるものではなく、構築しようとする構造物と地盤の性質の相対性によって決まるものであるため、一義的に決定されるものではないが、通常、土粒子が微細で間隙比の大きいシルトや粘土、圧縮性の極めて大きい泥炭などの特殊土、地震時に液状化しやすい地下水位の高い緩い砂地盤などを総称するものである。
【0004】
このような軟弱地盤の改良を行う場合、施工現場の状況に適した工法を適用することが重要であり、数多くの軟弱地盤の改良工法が提案されている。例えば、改良が不要である硬い表層下にある軟弱地盤を改良する場合、開翼式機械攪拌工法が適用されている。
この工法は、攪拌軸に開翼式攪拌翼とオーガーヘッドを装備した1台の機械で、地盤の削孔と攪拌が可能であり、セメントスラリ−などの改良材を吐出・攪拌し、軟弱地盤を固結土として改良することによって改良層を造成するものである。その工程は以下のような手順で行われる。
(a)硬い地表の改良不要層は、攪拌軸に装備した攪拌翼を閉翼して小口径で削孔する。
(b)改良が必要な軟弱地盤の下端まで閉翼した状態で削孔し、軟弱地盤の下端で全開に開翼し、軟弱地盤の上端まで改良材を吐出しながら攪拌し、改良体を造成する。
(c)改良が必要な軟弱地盤の所定の深度まで改良体を造成した後、攪拌翼を縮翼し、攪拌軸を逆回転にして攪拌しながら攪拌軸を引き抜く。
【0005】
【発明が解決しようとする課題】
しかしながら、従来の開翼式機械攪拌工法は、改良が必要な軟弱地盤の下端で攪拌翼を全開にするため、軟弱地盤の改良時に中間に硬い岩などの障害物が存在した場合、攪拌翼に大きな負荷がかかり、場合によっては攪拌翼の駆動が不能となることもあった。このような場合、攪拌翼を引き抜き、再び軟弱地盤へ挿入・攪拌するという工程を繰り返し行うため、軟弱地盤の改良に多大な労力と時間を費やさなければならないという問題点があった。
また、軟弱地盤の改良径を拡大する場合、それに従い削孔機や削孔軸が大型化し、また、改良不要な表層における削孔径も、それに比例して大きなものとなってしまう。
【0006】
本発明は、このような問題に鑑みてなされたものであり、改良不要な表層地盤の掘削、変位を低減し、改良を完了できる機械撹拌工法を提供することを目的とする。
【0007】
【課題を解決するための手段】
本発明は上記課題を解決すべく、以下に揚げる構成とした。
請求項1記載の発明の要旨は、地盤を掘削・撹拌可能な撹拌翼を備えた掘削・撹拌装置を用いた軟弱地盤の改良工法であって、改良が必要な軟弱地盤まで、攪拌翼を閉翼した状態で削孔した後、改良が必要な軟弱地盤の上端から下端まで、前記攪拌翼を所定角度開き、地盤を削孔する掘進工程と、前記撹拌翼をさらに所定角度開き、回転させながら引き上げて削孔する引上工程とを交互に繰り返すことを特徴とする軟弱地盤の改良工法に存する。
請求項2記載の発明の要旨は、地盤を掘削・撹拌可能な撹拌翼を備えた掘削・撹拌装置を用いた軟弱地盤の改良工法であって、改良が必要な軟弱地盤まで、攪拌翼を閉翼した状態で削孔する工程と、改良が必要な軟弱地盤の上端から下端まで、前記攪拌翼を所定角度開き、地盤を削孔する掘進工程と、前記撹拌翼を全開し、回転させながら引き上げて削孔する引上工程とを備えたことを特徴とする軟弱地盤の改良工法に存する。
請求項3記載の発明の要旨は、前記掘削工程においては、改良材を前記軟弱地盤中に吐出しつつ撹拌翼を回転させて地盤を改良することを特徴とする請求項1又は2に記載の軟弱地盤の改良工法に存する。
請求項4記載の発明の要旨は、前記引上工程においては、改良材を前記軟弱地盤中に吐出しつつ撹拌翼を回転させて地盤を改良することを特徴とする請求項1乃至3のいずれかに記載の軟弱地盤の改良工法に存する。
【0008】
【発明の実施の形態】
以下、本発明の実施の形態を図面に基づいて詳細に説明する。
図1〜図4は本発明の実施の形態に係る軟弱地盤の改良工法を示す工程図である。
まず、図1に示すように、改良不要層1の下にある改良が必要な軟弱地盤2を改良するにあたり、攪拌翼3を閉翼して小口径で改良不要層1を削孔する。この攪拌翼3は、開閉することによって拡径及び縮径可能な構造となっている。この拡縮径構造は、パンタグラフ式等と既に種々の構造のものがあるが、特定のものに限定されない。
次いで、図2に示すように、改良が必要な軟弱地盤2の上端から所定の深度まで攪拌翼3を回転させながら半開し、状態を維持しつつ軟弱地盤2を削孔する。削孔しながら、セメントスラリー等の改良材を吐出し撹拌して1次撹拌する(掘進工程)。本工程においては径が約200mm〜800mmにて削孔を行う。
次いで、図3のように、改良が必要な軟弱地盤2の所定の深度で回転させながら攪拌翼3を全開にして、引き上げつつ改良材を吐出し撹拌して、2次攪拌を開始する(引上工程)。本工程では、最大径1200mm程度の削孔を行う。
最後に、図4に示すように、改良材を吐出・攪拌しながら所定の引き抜き速度にて改良が必要な軟弱地盤2の上端まで改良体4を造成する。
【0009】
本発明の実施の形態に係る軟弱地盤2の改良工法は、前述のような工程で行われるので、削孔時に攪拌翼にかかる負荷が小さく、トルクを低減でき、岩などの障害物等の影響を受けにくく、短時間でしかも大口径の軟弱地盤の改良を行うことができる効果を奏するものである。
また、全開ではなく半開状態で削孔することによって、掘削時、攪拌時にこの種攪拌翼かかる負荷が小さくてすむため、攪拌翼本体委及びこの攪拌翼の開閉機構を頑強とする必要がなく、削孔機や削孔軸ロッドがそれほど大きくならず、また、改良不要な表層における削孔径も、従来技術の如く大きなものとなることはない。
【0010】
なお、上記実施の形態においては、掘進工程と、引上工程の2工程で地盤を改良させたが、本発明はそれに限定されることなく、改良工程が3工程以上であっても良い。その際には工程数に応じて撹拌翼の開く角度を小さくすることができる。
【0011】
また、掘進工程と、引上工程の両工程で改良材の吐出を行ったが、本発明はそれに限定されることなく、引上工程のみで改良材の吐出を行うことができる。掘進工程と引上工程とを複数回繰り返す場合については最終工程のみ、或いは所定工程のみにおいて改良材の吐出を繰り返すこともできる。
【0012】
また、図1〜4では、本発明の略鉛直方向に掘削する地盤改良方法を図示したが、本発明においては、略天井方向以外、水平方向、斜方向等あらゆる方向に施工可能である。これは、全開状態とする前に半開状態での掘削・攪拌工程を経るため、結果的に削孔ロッドが小径なものですみ、また削孔機も比較的小型のものが使用できることによる。
【0013】
また、上記構成部材の数、位置、形状等は上記実施の形態に限定されず、本発明を実施する上で好適な数、位置、形状等にすることができる。なお、各図において、同一構成要素には同一符号を付している。
【0014】
さらに、本発明では、施工箇所の状況によって、本発明の軟弱地盤2の改良工法と併せて、各種脱水工法、各種置換工法、各種締め固め工法、各種固結工法、及び各種止水工法等の軟弱地盤の改良工法のうちの1種または2種以上を併用することが可能である。
【0015】
【発明の効果】
本実施の形態は以上のように構成されているので、以下に掲げる効果を奏する。
攪拌翼を半開状態として削孔したのち、攪拌翼を全開状態で削孔を行うので、削孔時に攪拌翼にかかる負荷が小さく、トルクを低減でき、岩などの障害物等の影響を受けにくく、最短時間で軟弱地盤の改良を完了することができる効果を奏するものである。
また、従来工法と比較して、仮に同じ大きさの改良径を造成する場合、本発明によれば、改良不要層の削孔径を小さくできるので、表層地盤の掘削・変位を最低限に留めることができる。
【図面の簡単な説明】
【図1】本実施の形態に係る改良不要層を、攪拌翼を閉翼して小口径で削孔する工程を示す断面図である。
【図2】本実施の形態に係る軟弱地盤を、攪拌翼を全開せずに削孔・一次攪拌する工程を示す断面図である。
【図3】本実施の形態に係る軟弱地盤の所定の深度において、攪拌翼を全開し、改良材の吐出を開始する工程を示す断面図である。
【図4】本実施の形態に係る改良材を吐出・攪拌することによる改良体の造成の工程を示す断面図である。
【符号の説明】
1 改良不要層
2 軟弱地盤
3 攪拌翼
4 改良体
[0001]
BACKGROUND OF THE INVENTION
The present invention belongs to a method for improving soft ground by mechanical stirring used in the field of civil engineering and construction.
[0002]
[Prior art]
Conventionally, in the construction of civil engineering and building structures, for the purpose of increasing the ground support capacity, deforming the ground (sinking, swelling, protruding), reducing or eliminating water pressure and water permeability, maintaining and enhancing durability, etc. The soft ground has been improved.
[0003]
Here, the soft ground is not limited to a specific ground, but is determined by the relative nature of the structure to be built and the nature of the ground, so it is not uniquely determined. Generally, it is a generic term for silt or clay with fine soil particles and a large pore ratio, special soil such as peat with extremely high compressibility, and loose sand ground with a high groundwater level that tends to liquefy during an earthquake.
[0004]
When such soft ground is improved, it is important to apply a construction method suitable for the situation at the construction site, and many methods for improving soft ground have been proposed. For example, when improving soft ground under a hard surface layer that does not require improvement, an open-blade mechanical stirring method is applied.
This construction method is a single machine equipped with an agitating shaft and an auger head on the agitation shaft, which enables drilling and agitation of the ground. Discharge and agitation of improved materials such as cement slurry, and soft ground. An improved layer is created by improving the soil as consolidated soil. The process is performed according to the following procedure.
(A) The improvement unnecessary layer on the hard surface is closed with a stirring blade provided on the stirring shaft and drilled with a small diameter.
(B) Drilling with the blade closed to the bottom of the soft ground that needs improvement, opening the blade fully open at the bottom of the soft ground, stirring while discharging the improvement material to the top of the soft ground, and creating an improved body To do.
(C) After constructing the improved body to a predetermined depth of the soft ground that requires improvement, the stirring blade is contracted, the stirring shaft is rotated in the reverse direction, and the stirring shaft is pulled out while stirring.
[0005]
[Problems to be solved by the invention]
However, the conventional open-blade mechanical agitation method fully opens the stirring blade at the lower end of the soft ground that needs to be improved, so if there is an obstacle such as a hard rock in the middle when the soft ground is improved, A large load was applied, and in some cases, the stirring blade could not be driven. In such a case, since the process of drawing out the stirring blade, inserting it into the soft ground again, and repeating the process is repeated, there is a problem that much labor and time must be spent for improving the soft ground.
Further, when the improved diameter of the soft ground is expanded, the drilling machine and the drilling shaft are enlarged accordingly, and the drilling diameter in the surface layer that does not require improvement becomes proportionally larger.
[0006]
This invention is made | formed in view of such a problem, and it aims at providing the mechanical stirring construction method which can reduce excavation and displacement of the surface layer ground which need not be improved, and can complete improvement.
[0007]
[Means for Solving the Problems]
In order to solve the above-described problems, the present invention has the following configuration.
The gist of the invention described in claim 1 is a soft ground improvement method using a drilling / stirring device equipped with a stirring blade capable of excavating and stirring the ground, and the stirring blade is closed to the soft ground requiring improvement. After drilling in the bladed state, from the upper end to the lower end of the soft ground that needs improvement, the stirring blade is opened at a predetermined angle, the excavation step of drilling the ground, and the stirring blade is further opened at a predetermined angle while rotating There exists in the improvement method of the soft ground characterized by alternately repeating the pulling-up process which pulls up and drills.
The gist of the invention described in claim 2 is a soft ground improvement method using a drilling / stirring device equipped with a stirring blade capable of excavating and stirring the ground, and the stirring blade is closed to the soft ground that needs improvement. Drilling in the bladed state, opening the stirring blade at a predetermined angle from the upper end to the lower end of the soft ground that needs improvement, drilling step for drilling the ground, fully opening the stirring blade, and pulling up while rotating The present invention resides in an improved construction method for soft ground, characterized by comprising a pulling-up process for drilling holes.
The gist of the invention described in claim 3 is that, in the excavation step, the ground is improved by rotating the stirring blade while discharging the improvement material into the soft ground. It exists in the improvement method of soft ground.
According to a fourth aspect of the present invention, in the pulling-up step, the ground is improved by rotating the stirring blade while discharging the improving material into the soft ground. It exists in the improved construction method of soft ground described in Crab.
[0008]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
1 to 4 are process diagrams showing an improved construction method for soft ground according to an embodiment of the present invention.
First, as shown in FIG. 1, in improving the soft ground 2 that needs to be improved under the improvement unnecessary layer 1, the stirring blade 3 is closed and the improvement unnecessary layer 1 is drilled with a small diameter. The stirring blade 3 has a structure capable of expanding and reducing the diameter by opening and closing. The expansion / contraction diameter structure includes various structures such as a pantograph type, but is not limited to a specific structure.
Next, as shown in FIG. 2, the agitating blade 3 is half-opened while rotating from the upper end of the soft ground 2 requiring improvement to a predetermined depth, and the soft ground 2 is drilled while maintaining the state. While drilling, the improved material such as cement slurry is discharged and stirred for primary stirring (digging process). In this step, drilling is performed with a diameter of about 200 mm to 800 mm.
Next, as shown in FIG. 3, the stirring blade 3 is fully opened while rotating at a predetermined depth of the soft ground 2 that needs to be improved, and the improved material is discharged and stirred while being pulled up to start secondary stirring. Upper process). In this step, drilling with a maximum diameter of about 1200 mm is performed.
Finally, as shown in FIG. 4, the improved body 4 is created up to the upper end of the soft ground 2 that needs to be improved at a predetermined drawing speed while discharging and stirring the improved material.
[0009]
Since the improvement method of the soft ground 2 according to the embodiment of the present invention is performed in the steps as described above, the load applied to the stirring blade during drilling is small, the torque can be reduced, and the influence of obstacles such as rocks This is advantageous in that the soft ground having a large diameter can be improved in a short time.
In addition, by drilling in a half-open state rather than fully open, the load applied to this type of stirring blade during excavation and stirring can be reduced, so there is no need to make the stirring blade body committee and the opening and closing mechanism of this stirring blade robust. The drilling machine and the drilling shaft rod do not become so large, and the drilling diameter in the surface layer that does not require improvement does not become large as in the prior art.
[0010]
In addition, in the said embodiment, although the ground was improved in 2 steps, an excavation process and a pulling-up process, this invention is not limited to it, The improvement process may be 3 steps or more. In that case, the opening angle of the stirring blade can be reduced according to the number of steps.
[0011]
Moreover, although the improvement material was discharged in both the excavation process and the pulling-up process, the present invention is not limited thereto, and the improvement material can be discharged only in the pulling process. In the case where the digging process and the pulling process are repeated a plurality of times, the discharge of the improving material can be repeated only in the final process or only in the predetermined process.
[0012]
Moreover, although the ground improvement method excavated in the substantially vertical direction of this invention was illustrated in FIGS. 1-4, in this invention, it can construct in all directions, such as a horizontal direction and a diagonal direction other than a substantially ceiling direction. This is because the drilling and agitation process in the half-open state is performed before the fully open state, and as a result, the drilling rod has a small diameter, and the drilling machine can be used with a relatively small size.
[0013]
In addition, the number, position, shape, and the like of the constituent members are not limited to the above-described embodiment, and can be set to a number, position, shape, and the like that are suitable for implementing the present invention. In each figure, the same numerals are given to the same component.
[0014]
Furthermore, in the present invention, depending on the situation of the construction site, in addition to the improved construction method of the soft ground 2 of the present invention, various dehydration methods, various replacement methods, various compaction methods, various consolidation methods, various waterstop methods, etc. It is possible to use one or more of the improved construction methods for soft ground in combination.
[0015]
【The invention's effect】
Since the present embodiment is configured as described above, the following effects can be obtained.
After drilling with the stirring blade in the half-open state, drilling is performed with the stirring blade in the fully open state, so the load on the stirring blade during drilling is small, torque can be reduced, and it is not easily affected by obstacles such as rocks. The effect that the improvement of the soft ground can be completed in the shortest time is achieved.
In addition, when creating an improved diameter of the same size as compared with the conventional method, according to the present invention, the drilling diameter of the improvement unnecessary layer can be reduced, so that excavation / displacement of the surface ground is kept to a minimum. Can do.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing a step of drilling a non-improvement layer according to the present embodiment with a small diameter by closing a stirring blade.
FIG. 2 is a cross-sectional view showing a step of drilling and primary stirring the soft ground according to the present embodiment without fully opening the stirring blades.
FIG. 3 is a cross-sectional view showing a process of fully opening a stirring blade and starting discharge of an improved material at a predetermined depth of a soft ground according to the present embodiment.
FIG. 4 is a cross-sectional view showing a process of creating an improved body by discharging and stirring the improved material according to the present embodiment.
[Explanation of symbols]
1 Improvement unnecessary layer 2 Soft ground 3 Stirring blade 4 Improved body

Claims (4)

地盤を掘削・撹拌可能な撹拌翼を備えた掘削・撹拌装置を用いた軟弱地盤の改良工法であって、
改良が必要な軟弱地盤まで、攪拌翼を閉翼した状態で削孔した後、
改良が必要な軟弱地盤の上端から下端まで、前記攪拌翼を所定角度開き、地盤を削孔する掘進工程と、
前記撹拌翼をさらに所定角度開き、回転させながら引き上げて削孔する引上工程とを交互に繰り返すことを特徴とする軟弱地盤の改良工法。
An improved construction method for soft ground using a drilling / stirring device equipped with a stirring blade capable of excavating and stirring the ground,
After drilling with the stirring blade closed, until soft ground that needs improvement,
From the upper end to the lower end of the soft ground that needs to be improved, the stirring blade is opened at a predetermined angle, and the excavation process for drilling the ground,
A method for improving soft ground, wherein the agitating blade is further opened at a predetermined angle, and a pulling-up step of drilling and drilling while rotating is alternately repeated.
地盤を掘削・撹拌可能な撹拌翼を備えた掘削・撹拌装置を用いた軟弱地盤の改良工法であって、
改良が必要な軟弱地盤まで、攪拌翼を閉翼した状態で削孔する工程と、
改良が必要な軟弱地盤の上端から下端まで、前記攪拌翼を所定角度開き、地盤を削孔する掘進工程と、
前記撹拌翼を全開し、回転させながら引き上げて削孔する引上工程とを備えたことを特徴とする軟弱地盤の改良工法。
An improved construction method for soft ground using a drilling / stirring device equipped with a stirring blade capable of excavating and stirring the ground,
Drilling with the agitator blade closed until the soft ground needs improvement,
From the upper end to the lower end of the soft ground that needs to be improved, the stirring blade is opened at a predetermined angle, and the excavation process for drilling the ground,
A method for improving soft ground, comprising: a step of lifting the stirring blades fully open and pulling them up while rotating.
前記掘削工程においては、改良材を前記軟弱地盤中に吐出しつつ撹拌翼を回転させて地盤を改良することを特徴とする請求項1又は2に記載の軟弱地盤の改良工法。3. The soft ground improvement method according to claim 1 or 2, wherein in the excavation step, the ground is improved by rotating a stirring blade while discharging the improvement material into the soft ground. 前記引上工程においては、改良材を前記軟弱地盤中に吐出しつつ撹拌翼を回転させて地盤を改良することを特徴とする請求項1乃至3のいずれかに記載の軟弱地盤の改良工法。The soft ground improvement method according to any one of claims 1 to 3, wherein, in the pulling up step, the ground is improved by rotating a stirring blade while discharging the improvement material into the soft ground.
JP09519498A 1998-03-25 1998-03-25 Improvement method for soft ground Expired - Lifetime JP3697348B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP09519498A JP3697348B2 (en) 1998-03-25 1998-03-25 Improvement method for soft ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP09519498A JP3697348B2 (en) 1998-03-25 1998-03-25 Improvement method for soft ground

Publications (2)

Publication Number Publication Date
JPH11269865A JPH11269865A (en) 1999-10-05
JP3697348B2 true JP3697348B2 (en) 2005-09-21

Family

ID=14130952

Family Applications (1)

Application Number Title Priority Date Filing Date
JP09519498A Expired - Lifetime JP3697348B2 (en) 1998-03-25 1998-03-25 Improvement method for soft ground

Country Status (1)

Country Link
JP (1) JP3697348B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019138047A (en) * 2018-02-09 2019-08-22 株式会社竹中土木 Ground improvement method and ground improvement device using mechanical stirring deep layer mixing method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5746577B2 (en) * 2011-07-04 2015-07-08 大成建設株式会社 Ground improvement method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019138047A (en) * 2018-02-09 2019-08-22 株式会社竹中土木 Ground improvement method and ground improvement device using mechanical stirring deep layer mixing method

Also Published As

Publication number Publication date
JPH11269865A (en) 1999-10-05

Similar Documents

Publication Publication Date Title
JP5520347B2 (en) Pile digging method
CN108026709B (en) An improved ground anchor construction method for expanding the anchorage area by using the expanding excavation mixing device
JP2005282063A (en) Composite site construction pile, its construction method, and composite field construction pile construction device
JP3697348B2 (en) Improvement method for soft ground
JP5024692B2 (en) Construction method of foundation pile, ready-made pile, pile hole drilling rod
JP4074198B2 (en) How to remove existing piles
CN109763513A (en) A kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall and its construction method
JPH08199566A (en) Construction method of pile
JPH0470422A (en) Open caisson method
JP2548617B2 (en) Concrete pile installation method and excavation equipment by medium excavation method
JPH0485413A (en) Earth retaining method
JPH03257215A (en) Pile constructing method
JPH0280710A (en) Preparing cast-in-place concrete pile
JP4872561B2 (en) Construction method of ready-made piles
JPH0325121A (en) Sinking of pile in inner drilling pile method
JPH0627405B2 (en) Ready-made pile burying method
JPH0384115A (en) Excavated casing
JPH05125891A (en) Large-diameter underground wall, construction method thereof, and pipe digging device
JPH0629509B2 (en) Construction method of field construction pile
CN110219304A (en) Foundation ditch excavation method for soft modeling soil
JPH0442493B2 (en)
JPH0414513A (en) Ground consolidating method and ground consolidating device used therefor
JP2002275889A (en) Construction method of replacement material pile and rotary press-fit steel pipe pile
JPS6321796B2 (en)
JPS62178620A (en) Formation of improved angular ground

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050614

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050704

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090708

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090708

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100708

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110708

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110708

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110708

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120708

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120708

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120708

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130708

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term