JP3718538B2 - Management method of supply aggregate in asphalt plant - Google Patents
Management method of supply aggregate in asphalt plant Download PDFInfo
- Publication number
- JP3718538B2 JP3718538B2 JP10953995A JP10953995A JP3718538B2 JP 3718538 B2 JP3718538 B2 JP 3718538B2 JP 10953995 A JP10953995 A JP 10953995A JP 10953995 A JP10953995 A JP 10953995A JP 3718538 B2 JP3718538 B2 JP 3718538B2
- Authority
- JP
- Japan
- Prior art keywords
- aggregate
- particle size
- limit value
- allowable
- synthesized
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Road Paving Machines (AREA)
Description
【0001】
【産業上の利用分野】
本発明は、道路舗装材であるアスファルト合材の製造時にプラント本体の骨材貯蔵ビンに供給する骨材の供給管理に関するものである。
【0002】
【従来の技術】
アスファルトプラントは概略図7に示すように構成されており、アスファルト合材の製造時には、骨材を種類毎に貯蔵する複数の骨材ホッパ1a〜1dより切り出しフィーダ2a〜2dを駆動して所定の割合で骨材を切り出し、切り出した骨材を引き出しコンベヤ3、計量コンベヤ4を経由して骨材加熱装置であるドライヤ5に投入し、所望の温度まで加熱してバケットエレベータ6によりプラント本体上部に持ち上げる。プラント本体上部には振動篩7を配設しており、該振動篩7により骨材を粒径別に篩い分け、内部に区画を設けた骨材貯蔵ビン8に粒径別に貯蔵する。
【0003】
そして骨材貯蔵ビン8に貯蔵した各種粒径の骨材を計量槽9に適宜払い出して所定量計量し、別途計量したアスファルトや石粉等の他の材料と共にミキサ10に投入し、混合調整して所定のアスファルト合材として出荷している。
【0004】
この時、プラント操作盤の記憶部には、出荷するアスファルト合材の種類に応じて骨材ホッパ1a〜1dよりの切り出し速度が予め登録されており、出荷開始となれば出荷予約されたアスファルト合材の種類に応じて切り出し速度が操作盤に設定され、その切り出し速度によって各骨材ホッパから骨材が切り出されるようになっている。
【0005】
【発明が解決しようとする課題】
しかしながら、オペレ−タはプラント本体の骨材貯蔵ビンの貯蔵状況により骨材の切り出し割合を手動操作して変更することがある。この操作によって貯蔵量の少ないビンには多めの骨材が供給され、また貯蔵量の多いビンには少なめの骨材が供給され、各ビンの貯蔵量の過不足が一時的に解消されることとなるのであるが、この供給割合が更に継続されると各ビンの貯蔵量に再度アンバランスが生じる。そこで、オペレ−タは再度手動にて切り出し割り合いを調整するのであるが、熟練したオペレ−タであれば徐々に切り出し割合を修正して適切に対応できるが、未熟なオペレ−タでは適切に対応できずに不安定な骨材供給を続けることも考えられる。
【0006】
本発明は上記の点に鑑み、出荷合材の品種に見合った適切な骨材供給ができていなければ警報を出力してオペレ−タの骨材供給調整操作をうまく誘導し、適切な骨材供給管理を行うことができるようにしたものである。
【0007】
【課題を解決するための手段】
本発明は上記の目的を達成するために、骨材を種類毎に貯蔵する複数の骨材ホッパより各種骨材を切り出し、加熱装置であるドライヤにて加熱乾燥し、プラント本体上部に配設した振動篩により粒径別に篩い分け、複数に区画された骨材貯蔵ビンの各区画室に粒径別に貯蔵するアスファルトプラントにおいて、前記骨材ホッパより切り出される各種骨材の粒度構成及び切り出し割合より合成された骨材の粒度構成を演算すると共に、配合設計に基づいて決定した合成された骨材の予定の粒度構成の許容上限値及び許容下限値を予め記憶しておき、この合成された骨材の予定の粒度構成の許容上限値及び許容下限値と前記演算にて求めた合成された骨材の粒度構成とを比較し、合成された骨材の粒度構成が合成された骨材の予定の粒度構成の許容上限値又は許容下限値を越える時には警報を出力するようにしたことを特徴としている。
【0008】
【作用】
本発明の供給骨材の管理方法によれば、骨材ホッパよりプラント本体の骨材貯蔵ビンに骨材を供給する時、骨材ホッパに貯蔵する各種骨材の粒度構成と切り出し割合とから合成された骨材の粒度構成(以下、合成粒度という)を演算し、この演算した合成粒度が予め決定している合成された骨材の予定の粒度構成(以下、予定合成粒度という)の許容上限値、或は許容下限値を越えるとオペレータに対して警報を発し、オペレ−タに骨材の切り出し割合の修正を促すようにしており、これによってオペレ−タは出荷合材に対応した適切な骨材供給管理を行うことができる。
【0009】
【実施例】
以下、本発明の実施例を図面に基づいて説明する。
【0010】
図1の11は公知のアスファルトプラントの操作盤であって、該操作盤11には骨材の合成粒度を演算する合成粒度演算手段12を備えている。合成粒度演算手段12は各種データを入力するデータ入力部13と、入力された各種データを記憶する記憶部14と、各種データより合成粒度を演算する演算部15と、演算した結果を表示したり警報音を出力したりする出力表示部16を備えている。
【0011】
アスファルト合材が製造される前には、予め配合設計により合材の品種毎に予定合成粒度が決定されるのであるが、この時に予定合成粒度よりある程度の粒度範囲を持たせて各粒度毎の許容上限値、及び許容下限値を適宜決定しておく。
【0012】
この予定合成粒度の許容上限値及び許容下限値は、例えば、密粒合材の一例を図2のグラフにて説明すると、図中の二点鎖線は製造する密粒合材の予定粒度を示し、各種粒径の骨材や石粉を合成した時にそれらの材料が篩網の網目サイズ、20mm、13mm、5mm、2.5mm、0.6mm、0.3mm、0.15mm、0.074mmを通過する重量を通過重量百分率として表わしたものであり、この密粒合材を製造する際に合材の品質を維持するために許容上限値及び許容下限値が決定されるが、本発明の許容上限値及び許容下限値はこれと同様の値、もしくは近似する値を適宜決定する。
【0013】
そして図3に示すような上限値、下限値のデータを製造する合材の品種毎に決定し、データ入力部13を介して合成粒度演算手段12に入力してその記憶部14に記憶させておく。
【0014】
また、予め、骨材ホッパ1a〜1dに貯蔵する骨材の粒度構成を篩網の網目サイズに対応させた通過重量百分率にて測定しておく。この通過重量百分率の例を図4に示しており、前記予定合成粒度と同様に、6号砕石、7号砕石、及び川砂といった骨材の種類毎に網目サイズ、20mm、13mm、5mm、2.5mm、0.6mm、0.3mm、0.15mm、0.074mmを通過する骨材量を通過重量百分率として算出している。
【0015】
また、上記骨材ホッパ1a〜1dの粒度構成から出荷合材の品種毎に骨材ホッパ1a〜1dよりの切り出し割合を算出できるので、これを予め決定しておく。例えば、図4では、密粒合材出荷時には6号砕石は34%、7号砕石は30%、川砂は29%、石粉は7%といった切り出し割合を決定しておき、自動運転であればこの切り出し割合にて各ホッパから骨材を切り出せば、密粒合材の製造に見合った骨材供給が行える。
【0016】
記予定合成粒度の許容上限値及び許容下限値、骨材ホッパ1a〜1dの骨材粒度構成、骨材ホッパの切り出し割合等のデ−タを出荷合材の品種毎にデータ入力部4を介して合成粒度演算手段12に予め記憶させておく。
【0017】
そして、アスファルト合材の製造開始となれば、出荷合材の品種に対応した切り出し割合が記憶部14より呼び込まれて操作盤に設定され、その切り出し割合にて骨材ホッパ1a〜1dから各骨材が切り出される。
【0018】
そして運転開始となれば図5のフロ−チャ−トに示すように、先ず、合成粒度演算手段12において骨材ホッパ1a〜1dの粒度構成のデ−タを読み込み(S1)、更に骨材ホッパ1a〜1dから切り出している各種骨材の切り出し割合を読み込む(S2)。
【0019】
これらのデータが読み込まれると演算部15ではその骨材ホッパの粒度構成と切り出し割合から図6に示すような合成粒度を演算して出力表示部16に表示する(S3)。
【0020】
そして、予め記憶させている合材品種毎の予定合成粒度の許容上限値と許容下限値のデ−タ群から出荷合材品種に対応する許容上限値と許容下限値を記憶部14から読み込み(S4)、出力表示部16に表示する(S5)と共に、演算により求めた合成粒度と読み込んだ予定合成粒度の許容上限値と許容下限値とを比較する(S6)。例えば、図6に示す合成粒度の値と、図3に示す予定合材合成粒度の上限値と下限値の値を比較する。
【0021】
そして演算により求めた合成粒度が予定合成粒度の許容上限値または許容下限値を越えているか否かを判断し(S7)、その限界値を越える場合には出力表示部16に警報音を出力し(S8)、オペレータに供給している骨材の供給割合が許容値を越えていることを警告し、骨材ホッパ1a〜1dより切り出される各種骨材の切り出し割合の修正を促す。この警報は予め合材品種毎に設定した切り出し割合にて骨材を切り出した時には出力されないが、オペレ−タが切り出し割合の変更を限界値を越えて行った時に出力される。なお、出力表示部16には必要に応じて現在の切り出し割合、及び修正されるべき切り出し割合等の各種データを表示してオペレ−タの運転修正の参考となるようにすると良い。
【0022】
そしてフロ−では操作終了か否かを判断しており(S9)、終了でなければ、骨材の切り出し割合(切り出し量)が変更されているかをチェックし(S10)、変更されていなければ変更待ちとなり、変更があれば、ステップS2に進み、合成粒度の演算、予定合成粒度の許容上限値、下限値との比較、適否の判断と前記操作を繰り返すのである。
【0023】
このように、本発明によれば出荷合材に見合った骨材供給をしている時には警報は出力されないが、オペレ−タが骨材貯蔵ビンの貯蔵状況により骨材の切り出し割合を大幅に変更した時に警報が出力される。したがって、骨材貯蔵ビンの貯蔵状況により切り出し割合を変更する時には、警報が出力されない許容値範囲内にて適宜修正するか、また、警報出力を一旦OFFにして切り出し割合を大幅に変更し、貯蔵状況が好転してから警報出力をONにして切り出し割合が所定範囲内に収まるように修正を行う。このように、警報が出力されていない時には適切な骨材供給が行われているということであってオペレ−タの運転操作の負担も大変軽減される。
【0024】
【発明の効果】
以上のように本発明に係る供給骨材の管理方法にあっては、骨材ホッパより切り出される各種骨材の粒度構成及び切り出し割合より合成粒度を演算し、該合成粒度が予め配合設計に基づいて決定した予定合成粒度の許容上限値又は許容下限値を越える時には警報を出力するようにしたので、出荷合材の品種に見合った適切な骨材供給ができなていなければ警報が出力されてオペレ−タに注意を促すと共に、骨材供給量の調整操作をうまく誘導して出荷合材に見合った適切な骨材供給を行うことができ、かつオペレ−タの運転操作の負担も軽減することができる。
【図面の簡単な説明】
【図1】本発明を説明するアスファルトプラントの一実施例を示す説明図である。
【図2】予定合成粒度の許容上限値または許容下限値の一例を示すグラフである。
【図3】予定合成粒度の許容上限値または許容下限値の一例を示す図表である。
【図4】骨材の粒度構成の一例を示す図表である。
【図5】本発明の供給骨材の管理方法の手順を示すフローチャートである。
【図6】演算により求めた合成粒度の一例を示す図表である。
【図7】公知のアスファルトプラントを説明する説明図である。
【符号の説明】
1a、1b、1c、1d…骨材ホッパ
5…ドライヤ 7…振動篩
8…骨材貯蔵ビン 11…操作盤
12…合成粒度演算手段[0001]
[Industrial application fields]
The present invention relates to the supply management of aggregate to be supplied to an aggregate storage bin of a plant body when manufacturing asphalt composite material which is a road pavement material.
[0002]
[Prior art]
The asphalt plant is configured as schematically shown in FIG. 7, and at the time of manufacturing asphalt mixture, a plurality of aggregate hoppers 1 a to 1 d storing aggregates for each type are driven to drive feeders 2 a to 2 d. The aggregate is cut out at a predetermined ratio, and the cut-out aggregate is put into a
[0003]
Then, the aggregates of various particle sizes stored in the
[0004]
In this case, the storage unit of the plant control panel has cut rate than the aggregate hopper 1A~1 d is previously registered in accordance with the type of asphalt mixture to ship, shipped reserved if the ship starts asphalt The cutting speed is set on the operation panel according to the type of the composite, and the aggregate is cut out from each aggregate hopper by the cutting speed.
[0005]
[Problems to be solved by the invention]
However, the operator may manually change the cutting ratio of the aggregate depending on the storage status of the aggregate storage bin of the plant body. By this operation, a large amount of aggregate is supplied to bins with a small amount of storage, and a small amount of aggregate is supplied to bins with a large amount of storage, so that excess or deficiency of the storage amount of each bin is temporarily eliminated. However, if this supply ratio is further continued, an unbalance occurs again in the storage amount of each bin. Therefore, the operator manually adjusts the cutout ratio again, but if it is an experienced operator, the cutout rate can be corrected gradually, but it can be handled appropriately. It may be possible to continue supplying unstable aggregates without being able to cope.
[0006]
In view of the above-mentioned points, the present invention outputs an alarm and successfully guides the operator's aggregate supply adjustment operation if an appropriate aggregate supply corresponding to the type of the shipping composite is not made. Supply management can be performed.
[0007]
[Means for Solving the Problems]
In order to achieve the above-mentioned object, the present invention cuts out various aggregates from a plurality of aggregate hoppers that store aggregates for each type, heat-drys them with a dryer that is a heating device, and arranges them at the upper part of the plant body. In an asphalt plant that screens by particle size with a vibrating sieve and stores by particle size in each compartment of the aggregate storage bin divided into multiple parts, it is synthesized from the particle size composition and cutting ratio of various aggregates cut out from the aggregate hopper And calculating an allowable upper limit value and an allowable lower limit value of the planned granularity composition of the synthesized aggregate determined based on the blending design , and calculating the aggregate composition of the aggregate. Comparing the allowable upper limit value and the allowable lower limit value of the planned particle size configuration with the particle size configuration of the synthesized aggregate obtained by the above calculation, the planned particle size of the aggregate obtained by synthesizing the synthesized particle size configuration the configuration of the allowed When exceeding the upper limit or the allowable lower limit value is characterized in that so as to output an alarm.
[0008]
[Action]
According to the supply aggregate management method of the present invention, when the aggregate is supplied from the aggregate hopper to the aggregate storage bin of the plant body, it is synthesized from the particle size configuration and the cutting ratio of various aggregates stored in the aggregate hopper. has been size structure of the aggregate (hereinafter, synthetic particle size hereinafter) calculates the allowable upper limit of the computed composite particle size predetermined to have synthesized granularity construction plan aggregate (hereinafter referred to as planned synthesis particle size) When the value or the allowable lower limit value is exceeded, an alarm is issued to the operator, and the operator is urged to correct the cutting ratio of the aggregate. Aggregate supply management can be performed.
[0009]
【Example】
Embodiments of the present invention will be described below with reference to the drawings.
[0010]
[0011]
Before the asphalt mixture is manufactured, the planned synthesis particle size is determined for each type of mixture by blending design in advance, but at this time, a certain particle size range is given from the planned synthesis particle size for each particle size. The allowable upper limit value and the allowable lower limit value are appropriately determined.
[0012]
The allowable upper limit value and the allowable lower limit value of the planned composite grain size are, for example, an example of a dense-grained composite material described in the graph of FIG. When synthesizing aggregates and stone powders of various particle sizes, these materials pass the mesh size of sieve mesh, 20mm, 13mm, 5mm, 2.5mm, 0.6mm, 0.3mm, 0.15mm, 0.074mm The weight to pass is expressed as a percentage by weight of passing, and the upper and lower allowable limits are determined in order to maintain the quality of the composite when producing this dense-grained composite, but the allowable upper limit of the present invention The value and the allowable lower limit value are appropriately determined as similar values or approximate values.
[0013]
Then, the upper limit value and lower limit value data as shown in FIG. 3 is determined for each kind of compound material to be manufactured, and is input to the composite particle size calculation means 12 through the
[0014]
Further, in advance by measuring the particle size configuration of the aggregate to be stored in the aggregate hopper 1A~1 d at passage weight percentages were corresponding to the mesh size of the sieve screen. An example of the passing weight percentage is shown in FIG. 4, and the mesh size, 20 mm, 13 mm, 5 mm, and 2. for each type of aggregate such as No. 6 crushed stone, No. 7 crushed stone, and river sand, similar to the planned synthetic particle size. The amount of aggregate passing through 5 mm, 0.6 mm, 0.3 mm, 0.15 mm, and 0.074 mm is calculated as a passing weight percentage.
[0015]
Since we calculate the cut rate than the aggregate hopper 1A~1 d to each type of ship mixed material from the particle size configuration of the aggregate hopper 1A~1 d, advance determine this. For example, in FIG. 4 , when the dense-grain mixture is shipped, the cutting ratios such as 34% for No. 6 crushed stone, 30% for No. 7 crushed stone, 29% for river sand, and 7% for stone powder are determined. If the aggregate is cut out from each hopper at the cutting rate, the aggregate can be supplied in accordance with the production of the dense granular material.
[0016]
Serial schedule synthesis particle size of the allowable upper limit and the allowable lower limit, the aggregate hopper 1A~1 d aggregate particle size structure of, such as cut rate of the aggregate hopper de -
[0017]
Then, if the start of production of the asphalt mixture, cut rate corresponding to the type of the shipment mixture member is set in the operation panel is invoked from the
[0018]
And in Figure 5 if the operation start flow - Cha - as shown in bets, first, data of the particle size configuration of the aggregate hopper 1A~1 d in the synthesis particle size computing means 12 - read the data (S1), further aggregate read cut proportions of the various aggregates that are cut out from the hopper 1a~1 d (S2).
[0019]
When these data are read, the
[0020]
Then, the allowable upper limit value and the allowable lower limit value corresponding to the shipping composite material type are read from the
[0021]
Then, it is determined whether or not the composite particle size obtained by the calculation exceeds the allowable upper limit value or the allowable lower limit value of the planned composite particle size (S7), and if it exceeds the limit value, an alarm sound is output to the
[0022]
In the flow, it is determined whether or not the operation is finished (S9). If not finished, it is checked whether or not the aggregate cutout ratio (cutout amount) is changed (S10). If there is a change, the process proceeds to step S2, and the calculation of the composite granularity, the comparison with the allowable upper limit value and the lower limit value of the planned composite granularity, the determination of suitability, and the above operation are repeated.
[0023]
As described above, according to the present invention, an alarm is not output when the aggregate supply corresponding to the shipping composite is being performed, but the operator greatly changes the aggregate cutting ratio depending on the storage status of the aggregate storage bin. An alarm is output when Therefore, when changing the cut-out ratio depending on the storage status of the aggregate storage bin, correct it appropriately within the allowable range where no alarm is output, or turn off the alarm output and change the cut-out ratio significantly to store it. After the situation improves, the alarm output is turned on and correction is performed so that the cut-out ratio is within a predetermined range. As described above, when the alarm is not output, an appropriate aggregate is being supplied, and the burden on the operation of the operator is greatly reduced.
[0024]
【The invention's effect】
As described above, in the management method of the aggregate supply according to the present invention, the composite particle size is calculated from the particle size configuration and the cutting ratio of various aggregates cut out from the aggregate hopper, and the composite particle size is based on the blending design in advance. Since the warning is output when the allowable upper limit value or the allowable lower limit value of the planned composite particle size determined in the above is exceeded, an alarm is output if appropriate aggregate supply suitable for the type of shipping composite is not made. The operator can be alerted, the aggregate supply amount can be adjusted properly, and the aggregate can be supplied appropriately for the shipping mix, and the operator's operation load can be reduced. be able to.
[Brief description of the drawings]
FIG. 1 is an explanatory view showing an embodiment of an asphalt plant for explaining the present invention.
FIG. 2 is a graph showing an example of an allowable upper limit value or an allowable lower limit value of a planned synthesis granularity.
FIG. 3 is a chart showing an example of an allowable upper limit value or an allowable lower limit value of a planned synthesis granularity.
FIG. 4 is a chart showing an example of the aggregate composition of aggregates.
FIG. 5 is a flowchart showing the procedure of the supply aggregate management method of the present invention.
FIG. 6 is a chart showing an example of a composite particle size obtained by calculation.
FIG. 7 is an explanatory diagram for explaining a known asphalt plant.
[Explanation of symbols]
DESCRIPTION OF
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10953995A JP3718538B2 (en) | 1995-05-08 | 1995-05-08 | Management method of supply aggregate in asphalt plant |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10953995A JP3718538B2 (en) | 1995-05-08 | 1995-05-08 | Management method of supply aggregate in asphalt plant |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH08302611A JPH08302611A (en) | 1996-11-19 |
| JP3718538B2 true JP3718538B2 (en) | 2005-11-24 |
Family
ID=14512820
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP10953995A Expired - Fee Related JP3718538B2 (en) | 1995-05-08 | 1995-05-08 | Management method of supply aggregate in asphalt plant |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3718538B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7017834B2 (en) * | 2018-03-09 | 2022-02-09 | 日工株式会社 | How to display the amount of aggregate stored in the aggregate storage bottle of an asphalt plant |
-
1995
- 1995-05-08 JP JP10953995A patent/JP3718538B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH08302611A (en) | 1996-11-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US20070014185A1 (en) | Blending system | |
| CA2378387C (en) | Apparatus for sorting and recombining minerals | |
| CN101441445B (en) | Sintering material balance method and system | |
| JP3718538B2 (en) | Management method of supply aggregate in asphalt plant | |
| JP7017834B2 (en) | How to display the amount of aggregate stored in the aggregate storage bottle of an asphalt plant | |
| NL9201183A (en) | METHOD FOR MANUFACTURING A DRY AGGREGATE FOR THE PRODUCTION OF ELECTRODES | |
| JPH08177008A (en) | Aggregate supply control method in asphalt plant | |
| JP3595969B2 (en) | Simple blending method for fluidized soil | |
| JPH03262605A (en) | Manufacture and device for artificial ground material | |
| JPH08302610A (en) | Management method of supply aggregate in asphalt plant | |
| JP3712431B2 (en) | Aggregate supply control method in asphalt plant | |
| JP2002129516A (en) | Method and apparatus for producing asphalt mixture | |
| JP4582388B2 (en) | Concrete consistency management method | |
| JP4533523B2 (en) | Method for producing asphalt mixture | |
| JPH05179612A (en) | Asphalt mix production method | |
| JPH072648Y2 (en) | Sieving and storage equipment for aggregates in asphalt plants | |
| JP3712432B2 (en) | Aggregate supply control method in asphalt plant | |
| JPH07103531B2 (en) | Sieving and storage equipment for aggregates in asphalt plants | |
| JPH03236407A (en) | Method and device for controlling pulverization of reduced iron powder for powder metallurgy | |
| JPH0724405Y2 (en) | Sieving and storage equipment for aggregates in asphalt plants | |
| JPH01158103A (en) | Relay device for asphalt plied timber | |
| JP2577662B2 (en) | Aggregate supply method in asphalt plant | |
| JPH07247511A (en) | Product management method in asphalt plant | |
| JP2569793Y2 (en) | Asphalt plant | |
| JP2574133Y2 (en) | Asphalt plant |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050120 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050127 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050328 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050829 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050905 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090909 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100909 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100909 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110909 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110909 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120909 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120909 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130909 Year of fee payment: 8 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |