JP3722387B2 - System synchronization pull-in method - Google Patents
System synchronization pull-in methodInfo
- Publication number
- JP3722387B2 JP3722387B2 JP18661096A JP18661096A JP3722387B2 JP 3722387 B2 JP3722387 B2 JP 3722387B2 JP 18661096 A JP18661096 A JP 18661096A JP 18661096 A JP18661096 A JP 18661096A JP 3722387 B2 JP3722387 B2 JP 3722387B2
- Authority
- JP
- Japan
- Prior art keywords
- systems
- generator
- route
- phase difference
- switching
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は連系線を介して接続された2つの系統が系統分離したとき、電源遮断等をすることなく同期化する系統の同期引き込み方法に関する。
【0002】
【従来の技術】
一般に、2回線送電線で故障が発生した場合には、高速度再閉路方式により当該送電線の事故相を遮断した後、所定の無電圧時間(消イオン時間で、例えば500kV以上の系統では1秒程度)経過後に事故相を再投入することにより、故障復旧させていた。
【0003】
【発明が解決しようとする課題】
上記従来技術による再閉路条件としては、各回線合計で事故相以外の異相2相残り以上で連系されている場合でなければならず、更に再閉路タイミングによっては、近傍発電機タービン軸にもショックを与えると言う問題があった。
【0004】
本発明は上記課題を解決するためになされたものであり、ルート断故障のように最も過酷な故障に対処できて、系統分離を回避すると共に、発電機タービン軸への影響を最小限に抑えることの可能な系統の同期引き込み方法を提供することを目的としている。
【0005】
【課題を解決するための手段】
本発明の請求項1に係る系統の同期引き込み方法は、1ルートの連係線を介して2つの系統が連係されている前記連係線にルート断故障が発生したとき、故障発生後に当該連係線の開放,投入を少なくとも1回以上複数回繰り返すと共に、前記連係線の開放,投入はルート断後、両系統の位相差が開いたことを条件に、下記とした。このようにすれば、一方の系統の蓄積エネルギーを他方の系統に放出することができ、両系統を同期に引き込むことができる。
記
【数1】
【0006】
本発明の請求項2に係る系統の同期引き込み方法は、請求項1において、前記2つの系統に代えて夫々をビル内の電気所とした。このようにすれば各ビル間における融通系統で事故時に連係が解除された場合にも、速やかな同期引き込みが可能となる。
【0008】
【発明の実施の形態】
図1は連系系統を説明する図であり、系統Aと系統Bが1ルートで連系された場合である。そして各系統間に流れる潮流をPT 、矢印は流れる方向を示し、各慣性中心は∠θ1 ,∠θ2 とする。
【0009】
先ず、連系線のルート断故障が発生した場合を考える。この時ルート断であるため事故前の連系線潮流PT に相当する需給アンバランスが、系統Aと系統B間に生ずる。事故前の潮流方向からわかるように、系統Aでは発電機群が加速し、系統Bでは減速する。
【0010】
したがって、これらの加減速を防ぐためには電源遮断等が必要となる。即ち、系統Aでは電源遮断し、系統Bでは負荷遮断を要する。ここで仮に、ルート断の発生後、直ちに連系線を投入することができれば、系統A,系統Bを同期させることができるはずである。
【0011】
しかし、故障直後の再投入は1秒の消イオン時間が必要となることを考慮すると実現不可能である。そこで両系統間の位相が開いて2π(360゜)となった時点で遮断器の再投入を行ない、その後、必要に応じて適切なタイミングで遮断器のOFF/ONを繰り返して、系統Aの蓄積エネルギーを系統Bに放出させるようにすれば、両系統を同時に引き込むことができるはずである。
【0012】
図2は連系系統での位相角の動きと放出・蓄積されるエネルギーとの関係図である。図2において縦軸は連系線潮流PT を示し、横軸は発電機群の回転子位相角差θを示す。なお、P0 は機械入力であり、最初は一定と考える。図2をもとに系統Aによる蓄積エネルギーを系統Bに放出させる作用について、等面積法を用いて説明する。
【0013】
PTを電力潮流とするとき、S0+S1が系統Aに蓄積されるエネルギーであり、S2が系統Aから放出されるエネルギーである。ここで各系統A,Bの発電機群の回転子位相角の慣性中心をθ1,θ2とすれば、これらの動作式は(1)式,(2)式で表わされる。
【0014】
【数2】
【0015】
(1)式,(2)式より系統A,Bの慣性中心の相対運動は(3)式で表わされる。
【数3】
(3)式は等価的に慣性定数M,機械入力P0,電気出力PTの発電機の動揺方程式となっており、等面積法によって過渡安定度を論じることができる。
【0016】
今、調速手段(GOV)の動作を無視し、負荷が定電力特性をもつとすれば、上記(3)式の機械入力P0は一定値となる。ここでルート断後に両系統の位相差が開き角度が2π(360度)となった時点で遮断器を再投入し、その後も位相が開いていく場合を考える。
【0017】
この状態において、遮断器を(4)式のように動作させれば1回のOFF/ONにて、図2に示されるS2−S1に相当する分だけ、系統Aの蓄積エネルギーを系統Bに放出できるので、両系統を同期に引き込むことができる。なお、OFF/ONの繰り返し動作は位相差が開いている場合であり、その開閉のタイミングは(4)式の通りとし減少に転じたときは後述する。
【0018】
【数4】
【0019】
これらの動作をさせるにはS1 <S2 となる必要がある。PT =Psin θが成立する場合にはこの条件は(5)式で表わせる。
【数5】
P0 /P<1/π …………………(5)
【0020】
しかし実際には調速手段(GOV)と負荷変動の影響があるため、P0 の値は一定ではなくて時間と共に減少してゆく。又、等価慣性定数Mに対する連系線潮流の比が小さいほど、両系統間の加速が緩やかになるため、系統A,Bが共に大規模系統になるほど、スイッチングのタイミングはゆっくりでよい。逆に一機無限大母線系統の場合(系統Aが対象発電機,系統Bが無限大母線)が、この制御を行なう上で制御速度の面で最も厳しくなる。
【0021】
次に開閉制御の終了条件について説明する。遮断器投入後の系統A,B間の位相差が増加から減少に転じた後(即ち、両系統が同期に引き込まれた後)には(4)式の条件により遮断器のOFF/ONを前記同様に繰り返すと、かえって動揺が大きくなるため制御を終了する必要がある。
【0022】
このことを図を用いて前記同様等面積法にて説明する。先ず、図3のA点において、系統A,B間の位相差は減少に転じ、系統の状態は電力曲線に沿って左下の方向に動いていく。この時、前記した(4)式の条件によりB点で連系線を開放すると、系統Bに蓄えられた蓄積エネルギーを放出し終わるC点まで、BC線上を矢印に沿って位相差は減少し再び位相差が開いていく。
【0023】
一方、B点での連系線開放を行なわなかった場合には、電力曲線に沿ってA→B→Dと進み、系統Bの蓄積エネルギーを放出し終わるので、結果として動揺が小さくなる。
【0024】
次に発電機軸トルクへの影響について説明する。同期引き込みのためのスイッチングは遮断器の開閉と同様に発電機のエアーギャップに過渡的な電磁トルクを発生させ、軸疲労をまねく可能性がある。特に、遮断器投入時には通常大きな商用周波数の振動トルクが生じるため、チェックが必要である。
【0025】
図4にほぼ理想的なタイミング(位相差360度)でスイッチングが行われた場合(a)と、スイッチングが3サイクル遅れた場合(b)の発電機トルクを示す。なお、縦軸は発電機トルク[pu]を、又、横軸は時間[秒]を示す。
【0026】
図4からわかるように、前者(a)では殆ど商用周波数の過渡振動分が見られないが、スイッチングが遅れた場合(b)には大きな過渡振動トルクが現れている。これは、理想的なタイミングでは、母線間の位相差がなくなって、発電機出力の変化が0になっているのに対して、スイッチングが遅れると位相が開いて発電機出力がステップ上に変化しようとするためであると考えられる。又、スイッチングのタイミングが早過ぎた場合にも同様の過渡振動トルクが発生する。
【0027】
上記図4(b)に示されるような50Hz振動分が発電機に加わると、発電機の軸にねじり力が働き、その結果ショックを加えることとなるが、同期引き込みのタイミングを合わせると図4(a)に示されるように殆ど50Hz振動分はなく、発電機へのショックもないことがわかった。
【0028】
図5はスイッチングタイミングのずれと発電機に生じる過渡振動トルクの関係図である。図5において縦軸は振動トルク[pu]を示し、横軸は時間[ms]を示す。図5からわかることは、過渡振動トルクはスイッチングのタイミングのずれに比例して大きくなる傾向にある、ということである。
【0029】
上記実施の形態によれば、連系線のルート断後に少なくとも1回以上数回のスイッチングを繰り返すことで、電源遮断及び負荷遮断等の対策なしに、速やかに分離した系統を同期化することができるばかりか、遮断器の開閉タイミングが理想的であれば、発電機の電磁トルクの過渡振動分は非常に小さく、軸系の消耗への影響が小さくなることである。
【0030】
上記実施の形態に示す同期化引き込みスイッチングの電力系統シミュレータ試験結果を以下に説明する。スイッチングによる同期化引き込み制御について、一機無限大母線系統による電力系統シミュレータ試験を実施して、その実現可能性を確認する。合わせて制御ロジックの検証と、ディジタル解析との比較検討を行なう。
【0031】
図6はシミュレータ試験用モデル系統図であり、これを用いて試験を行なった。先ず、母線N2 ,N4 のa相電圧を検出して、母線間の位相差を計算し、これを基に遮断器開閉信号を発生させている。位相差計算等を含むスイッチング制御ブロックは、パソコン上の制御系を用いて作成し、これをDSP(Digital Signal Processor)上で動作させることで実現している。
【0032】
位相差の検出は母線N2 及びN4 間の位相差θ=θ1 −θ2 の検出を行なった。この場合、V1 V2 ×sin (θ1 −θ2 )=V1 sin (ωt+θ1 )×V2 cos (ωt+θ2 )−V1 cos (ωt+θ1 )×V2 sin (ωt+θ2 )となることを利用して、信号V1 V2 ×sin (θ1 −θ2 )を計算するものである。
【0033】
ルート断故障の発生後、位相差θ1 −θ2 が増加して360度を越える瞬間に遮断器を投入する。これらのブロックをコンピュータを用いて作成し、これをDSPプログラムに変換することで、位相差の検出を行なっている。なお、DSPのサンプリング時間は0.5msである。
【0034】
図7に試験結果を示す。図7(a)は発電機の内部状態を示す図であり、縦軸は発電機有効電力[pu]と発電機角速度偏差(%)である。又、図7(b)はDSPによるV1 V2 sin (θ1 −θ2 )の計算値であり、縦軸はV1 V2 sin (θ)の値[pu]を、又、横軸は時間(s)を示している。
【0035】
故障除去後ほぼ1秒後に、制御ロジックにしたがって遮断器が投入され、系統は過渡脱調せずに安定に保たれていることがわかる。又、DSPによって計算されているV1 V2 ×sin (θ1 −θ2 )の信号を見ると、遮断器が投入されている状態では、発電機有効電力出力に比例した値となっており、正しく計算が行なわれていることがわかる。
【0036】
又、位相差が360度となる瞬間に、遮断器が投入されていることも確認できる。遮断器投入後の発電機出力には商用周波数成分が殆ど含まれず、振動性の過渡電磁トルクが殆ど発生していないことがわかる。したがって軸系へのショックも小さい。
【0037】
次にディジタル解析結果との比較結果を示す。シミュレーション試験と同じ系統について、EMTP(電磁過渡現象解析プログラム)による瞬時値ディジタルシミュレーションと実効値ディジタルシミュレーションを実施した。結果を図8,図9に示す。これらはいずれも図7のシミュレータ試験結果とほぼ完全に一致していることがわかる。
【0038】
以上のシミュレーション結果によれば、以下(イ),(ロ),(ハ)に列挙する事項が確認できた。
(イ)スイッチング制御の実現可能性と制御ロジックの妥当性をシミュレータ試験により確認できた。
(ロ)アナログシミュレータ試験結果は、EMTPによる瞬時値ディジタルシミュレーション結果及び実効値ディジタルシミュレーション結果とほぼ一致し、これらの解析ツールを用いての検討が可能であることが明らかになった。振動性の軸トルクを計算する必要がない場合には、実効値シミュレーションで十分な精度が得られる。
(ハ)理想的なタイミングでスイッチングを行なえば、発電機に発生する振動性の過渡電磁トルクは非常に小さく、軸系に与える影響は少ない。
【0039】
上記実施の形態によれば、送電系統についてのみの説明をしたが、本発明はこれに限定されるものではない。即ち、近年の都市においては各ビル単位に発電設備を有して、互いに隣接するビルとの間で連系する局地的な融通系統があるが、これらの各系統間においても本方法は適用できる。
【0040】
この場合は系統A,系統Bをそっくりそのままビル単位の電気所(発電設備、あるいは発電機単体を有する)に置き換えるだけで、連系系統のOFF/ONは上記実施の形態で説明した通りでよいことは明らかである。
【0041】
【発明の効果】
以上説明したように、本発明によれば連系線のルート断後に所定位相差に合わせて遮断器のオフ・オンを複数回繰り返すことにより、系統間の蓄積エネルギーを放出するようにしたので、各系統間の位相差が順次なくなって同期引き込みが可能となる。
【図面の簡単な説明】
【図1】連系系統を説明する図。
【図2】連系系統での位相角の動きと放出・蓄積エネルギーの関係図。
【図3】開閉制御の終了条件を説明する図。
【図4】スイッチングのタイミングによる過渡振動トルクの差を説明する図。
【図5】スイッチングのタイミングのずれを発電機に生じる過渡振動トルクの関係図。
【図6】電力系統シミュレータ用モデル系統図。
【図7】シミュレータの試験結果を示す図。
【図8】瞬時値ディジタルシミュレータ結果を示す図。
【図9】実効値ディジタルシミュレーション結果を示す図。[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a synchronization pull-in method for a system that synchronizes without disconnecting a power source when two systems connected via a connection line are separated from each other.
[0002]
[Prior art]
In general, when a failure occurs in a two-line transmission line, the accident phase of the transmission line is interrupted by a high-speed reclosing method, and then a predetermined no-voltage time (deionization time, for example, 1 in a system of 500 kV or higher) The failure was recovered by re-introducing the accident phase after a lapse of about a second).
[0003]
[Problems to be solved by the invention]
The reclosing condition according to the above-mentioned prior art must be the case where the total of each line is linked with more than two remaining phases other than the accident phase. Furthermore, depending on the reclosing timing, the adjacent generator turbine shaft may also be connected. There was a problem of shocking.
[0004]
The present invention has been made to solve the above-mentioned problems, can cope with the most severe failure such as a route breakage failure, avoids system separation, and minimizes the influence on the generator turbine shaft. It is an object of the present invention to provide a synchronization pull-in method for a possible system.
[0005]
[Means for Solving the Problems]
The system synchronous pull-in method according to
Record
[Expression 1]
[0006]
A system synchronous pull-in method according to
[0008]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 is a diagram for explaining an interconnected system, in which system A and system B are interconnected through one route. P T indicates the tidal current flowing between the systems, the arrows indicate the flow directions, and the centers of inertia are ∠θ 1 and ∠θ 2 .
[0009]
First, consider a case where a route disconnection failure of the interconnection line occurs. At this time, since the route is cut off, an imbalance between supply and demand corresponding to the grid line flow PT before the accident occurs between the system A and the system B. As can be seen from the tidal current direction before the accident, the generator group accelerates in the system A and decelerates in the system B.
[0010]
Therefore, in order to prevent such acceleration / deceleration, it is necessary to shut off the power supply. That is, the power supply is cut off in the system A, and the load is cut off in the system B. Here, if the interconnection line can be turned on immediately after the occurrence of the route disconnection, the system A and the system B should be able to be synchronized.
[0011]
However, recharging immediately after a failure is not feasible considering that a deionization time of 1 second is required. Therefore, when the phase between the two systems opens and reaches 2π (360 °), the circuit breaker is turned on again. After that, the circuit breaker is repeatedly turned off / on at an appropriate timing as necessary. If the stored energy is released to the system B, both systems should be able to be drawn simultaneously.
[0012]
FIG. 2 is a diagram showing the relationship between the movement of the phase angle in the interconnection system and the energy released and stored. In FIG. 2, the vertical axis represents the interconnection power flow PT , and the horizontal axis represents the rotor phase angle difference θ of the generator group. Note that P 0 is a machine input and is initially assumed to be constant. Based on FIG. 2, the action of releasing the stored energy by the system A to the system B will be described using the equal area method.
[0013]
When PT is the power flow, S 0 + S 1 is energy stored in the grid A, and S 2 is energy released from the grid A. Here, assuming that the inertia centers of the rotor phase angles of the generator groups of the systems A and B are θ 1 and θ 2 , these operation equations are expressed by the equations (1) and (2).
[0014]
[Expression 2]
[0015]
From the equations (1) and (2), the relative motion of the centers of inertia of the systems A and B is expressed by the equation (3).
[Equation 3]
Equation (3) is equivalent to a generator oscillation equation of inertia constant M, mechanical input P 0 , and electrical output P T , and transient stability can be discussed by the equal area method.
[0016]
Now, ignoring the operation of the governing means (GOV) and assuming that the load has a constant power characteristic, the mechanical input P 0 in the above equation (3) becomes a constant value. Here, consider a case where the circuit breaker is turned on again when the phase difference between the two systems becomes an open angle of 2π (360 degrees) after the route is cut off, and the phase opens thereafter.
[0017]
In this state, if the circuit breaker is operated as shown in equation (4), the stored energy of the system A is supplied to the system by an amount corresponding to S 2 -S 1 shown in FIG. Since it can be released to B, both systems can be pulled in synchronously. Note that the OFF / ON repetitive operation is when the phase difference is open, and the opening / closing timing is as shown in equation (4), and will be described later when it starts to decrease.
[0018]
[Expression 4]
[0019]
In order to perform these operations, it is necessary to satisfy S 1 <S 2 . If P T = Psin θ holds, this condition can be expressed by equation (5).
[Equation 5]
P 0 / P <1 / π (5)
[0020]
However, in reality, there is an influence of the speed control means (GOV) and load fluctuation, so the value of P 0 is not constant but decreases with time. Further, the smaller the ratio of the interconnected power flow to the equivalent inertia constant M, the slower the acceleration between the two systems. Therefore, the switching timing may be slower as the systems A and B are both larger systems. Conversely, in the case of a one-machine infinite bus system (system A is the target generator and system B is an infinite bus), the control speed is most severe in performing this control.
[0021]
Next, the end condition of the opening / closing control will be described. After the phase difference between the systems A and B after turning on the circuit breaker has changed from increasing to decreasing (that is, after both systems have been pulled in synchronously), the circuit breaker is turned OFF / ON according to the condition of equation (4). If it is repeated in the same manner as described above, the control will need to be terminated because the fluctuation will increase.
[0022]
This will be described with the same area method as described above with reference to the drawings. First, at point A in FIG. 3, the phase difference between the systems A and B starts to decrease, and the system state moves in the lower left direction along the power curve. At this time, if the interconnection line is opened at the point B according to the condition of the above-described equation (4), the phase difference on the BC line decreases along the arrow until the point C at which the stored energy stored in the system B is completely released. The phase difference opens again.
[0023]
On the other hand, when the connection line is not opened at the point B, the process proceeds from A to B to D along the power curve, and the accumulated energy of the system B is completely released. As a result, the fluctuation is reduced.
[0024]
Next, the influence on the generator shaft torque will be described. Switching for synchronous pulling may cause transient electromagnetic torque in the air gap of the generator as well as opening and closing of the circuit breaker, leading to shaft fatigue. In particular, when a breaker is turned on, a vibration torque having a large commercial frequency is usually generated, and therefore a check is necessary.
[0025]
FIG. 4 shows the generator torque when switching is performed at almost ideal timing (phase difference of 360 degrees) (a) and when switching is delayed by three cycles (b). The vertical axis represents generator torque [pu], and the horizontal axis represents time [second].
[0026]
As can be seen from FIG. 4, in the former (a), there is almost no commercial frequency transient vibration, but when the switching is delayed (b), a large transient vibration torque appears. This is because, at ideal timing, the phase difference between the buses disappears and the change in the generator output is 0, whereas when the switching is delayed, the phase opens and the generator output changes on the step. It is thought that it is for trying. A similar transient vibration torque is also generated when the switching timing is too early.
[0027]
When 50 Hz vibration as shown in FIG. 4 (b) is applied to the generator, a torsional force is applied to the generator shaft, resulting in a shock. As shown in (a), it was found that there was almost no 50 Hz vibration and no shock to the generator.
[0028]
FIG. 5 is a relationship diagram of the switching timing deviation and the transient vibration torque generated in the generator. In FIG. 5, the vertical axis represents vibration torque [pu], and the horizontal axis represents time [ms]. It can be seen from FIG. 5 that the transient vibration torque tends to increase in proportion to the timing of switching.
[0029]
According to the above-described embodiment, it is possible to quickly synchronize separated systems without countermeasures such as power interruption and load interruption by repeating switching at least once or several times after disconnection of the route of the interconnection line. In addition, if the circuit breaker opening / closing timing is ideal, the transient vibration of the electromagnetic torque of the generator is very small and the influence on the wear of the shaft system is small.
[0030]
The results of the power system simulator test of the synchronous pull-in switching shown in the above embodiment will be described below. For synchronized pull-in control by switching, a power system simulator test using an infinite bus system will be conducted to confirm its feasibility. At the same time, verification of control logic and comparison with digital analysis will be conducted.
[0031]
FIG. 6 is a model diagram for a simulator test, and the test was performed using the model diagram. First, the a-phase voltage of the buses N 2 and N 4 is detected, the phase difference between the buses is calculated, and a circuit breaker switching signal is generated based on this. A switching control block including a phase difference calculation is created by using a control system on a personal computer and is operated on a DSP (Digital Signal Processor).
[0032]
The phase difference was detected by detecting the phase difference θ = θ 1 −θ 2 between the buses N 2 and N 4 . In this case, V 1 V 2 × sin (θ 1 −θ 2 ) = V 1 sin (ωt + θ 1 ) × V 2 cos (ωt + θ 2 ) −V 1 cos (ωt + θ 1 ) × V 2 sin (ωt + θ 2 ) By utilizing this fact, the signal V 1 V 2 × sin (θ 1 −θ 2 ) is calculated.
[0033]
After the occurrence of the route break failure, the circuit breaker is inserted at the moment when the phase difference θ 1 −θ 2 increases and exceeds 360 degrees. These blocks are created by using a computer and converted into a DSP program to detect a phase difference. The DSP sampling time is 0.5 ms.
[0034]
FIG. 7 shows the test results. FIG. 7A shows the internal state of the generator, and the vertical axis shows the generator active power [pu] and the generator angular velocity deviation (%). FIG. 7B shows a calculated value of V 1 V 2 sin (θ 1 −θ 2 ) by a DSP, the vertical axis represents the value [pu] of V 1 V 2 sin (θ), and the horizontal axis Indicates time (s).
[0035]
It can be seen that, approximately one second after the failure is removed, the circuit breaker is turned on according to the control logic, and the system is kept stable without transient step-out. Also, looking at the signal of V 1 V 2 × sin (θ 1 −θ 2 ) calculated by the DSP, the value is proportional to the generator active power output when the breaker is turned on. It can be seen that the calculation is performed correctly.
[0036]
It can also be confirmed that the circuit breaker is turned on at the moment when the phase difference reaches 360 degrees. It can be seen that the generator output after turning on the circuit breaker contains almost no commercial frequency component, and hardly generates oscillating transient electromagnetic torque. Therefore, the shock to the shaft system is small.
[0037]
Next, the comparison result with the digital analysis result is shown. For the same system as the simulation test, instantaneous value digital simulation and effective value digital simulation by EMTP (electromagnetic transient analysis program) were performed. The results are shown in FIGS. It can be seen that these are almost completely consistent with the simulator test results of FIG.
[0038]
According to the above simulation results, the following items (a), (b), and (c) were confirmed.
(B) The feasibility of switching control and the validity of the control logic were confirmed by simulator tests.
(B) The analog simulator test results almost coincided with the EMTP instantaneous value and effective value digital simulation results, and it became clear that the analysis using these analysis tools was possible. When it is not necessary to calculate the oscillating shaft torque, sufficient accuracy can be obtained by effective value simulation.
(C) If switching is performed at an ideal timing, the oscillating transient electromagnetic torque generated in the generator is very small and has little influence on the shaft system.
[0039]
Although only the power transmission system has been described according to the above embodiment, the present invention is not limited to this. That is, in recent cities, each building has a power generation facility, and there is a local interchange system that is linked to buildings adjacent to each other. However, this method is also applicable to each of these systems. it can.
[0040]
In this case, the system A and the system B are simply replaced with the building-wide electric station (having a power generation facility or a single generator), and the interconnection system can be turned OFF / ON as described in the above embodiment. It is clear.
[0041]
【The invention's effect】
As described above, according to the present invention, the accumulated energy between the systems is released by repeating the circuit breaker off and on multiple times in accordance with the predetermined phase difference after the disconnection of the route of the interconnection line. The phase difference between the systems disappears sequentially, and synchronization pull-in becomes possible.
[Brief description of the drawings]
FIG. 1 is a diagram for explaining an interconnection system.
FIG. 2 is a diagram showing the relationship between the movement of the phase angle and the released / stored energy in the interconnection system.
FIG. 3 is a diagram for explaining an end condition of opening / closing control.
FIG. 4 is a diagram for explaining a difference in transient vibration torque depending on switching timing.
FIG. 5 is a relationship diagram of transient vibration torque that causes a deviation in switching timing in a generator.
FIG. 6 is a model system diagram for a power system simulator.
FIG. 7 is a diagram showing a test result of a simulator.
FIG. 8 is a diagram showing a result of an instantaneous value digital simulator.
FIG. 9 is a diagram showing a result of effective value digital simulation.
Claims (2)
記
Record
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18661096A JP3722387B2 (en) | 1996-06-27 | 1996-06-27 | System synchronization pull-in method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18661096A JP3722387B2 (en) | 1996-06-27 | 1996-06-27 | System synchronization pull-in method |
Publications (3)
| Publication Number | Publication Date |
|---|---|
| JPH1014107A JPH1014107A (en) | 1998-01-16 |
| JPH1014107A5 JPH1014107A5 (en) | 2004-07-15 |
| JP3722387B2 true JP3722387B2 (en) | 2005-11-30 |
Family
ID=16191595
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP18661096A Expired - Fee Related JP3722387B2 (en) | 1996-06-27 | 1996-06-27 | System synchronization pull-in method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3722387B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114755494A (en) * | 2022-04-15 | 2022-07-15 | 西安热工研究院有限公司 | A Synchronous Phasing Method Based on GCB Electrical System |
-
1996
- 1996-06-27 JP JP18661096A patent/JP3722387B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH1014107A (en) | 1998-01-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Das | Effects of momentary voltage dips on the operation of induction and synchronous motors | |
| US8736090B2 (en) | Protection arrangement of an electric power system | |
| Weckesser et al. | Impact of model detail of synchronous machines on real-time transient stability assessment | |
| So et al. | Out-of-step detection algorithm using frequency deviation of voltage | |
| Gardell et al. | Motor bus transfer applications issues and considerations | |
| JP3722387B2 (en) | System synchronization pull-in method | |
| Robak et al. | Enhancement of power system stability by real-time prediction of instability and early activation of steam turbine fast valving | |
| AU2021442185B2 (en) | Method of controlling a power converter, converter arrangement and computer program product | |
| Gunadin et al. | Transient stability improvement using allocation power generation methods based on moment inertia | |
| Cheng et al. | Out-of-step protection using the equal area criterion | |
| Annakkage et al. | Transient stability in power systems | |
| CN113013927B (en) | A three-phase reclosing control method and system for generator | |
| Shilling | Electrical transient stability and underfrequency load shedding analysis for a large pump station | |
| Stringer | Voltage considerations during generator synchronizing | |
| Mullane et al. | Modifying the inertial response of power-converter based wind turbine generators | |
| Sidhu et al. | A modern automatic bus transfer scheme | |
| Pala et al. | Power Swing and out of step Protection using Equal area Criteria | |
| KR100629617B1 (en) | Out-of-Step detecting method using frequency deviation of the voltage | |
| KR20050020070A (en) | An adaptive autoreclosure scheme in a protective relay system | |
| Jhumka et al. | Rotor angle and inertia analysis in presence of renewable energy source | |
| CN113270850B (en) | Three-phase reclosing method of generator based on transient energy method | |
| Park et al. | A Study on Communication Impact in the Excitation Signal Chain of a 3-phase Synchronous Generator | |
| Hasni et al. | Dynamic stability assessment of a medium size power system towards large disturbances case study of the blackout of August 2014 of the Tunisian power system | |
| Breedlove et al. | Protection of the induction motor/generator | |
| Doi et al. | Study of fast synchronous-reclosing method for parallel AC line fault in AC/DC poer transmission system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20041222 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050105 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050302 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050909 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050909 |
|
| R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080922 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090922 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100922 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100922 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110922 Year of fee payment: 6 |
|
| LAPS | Cancellation because of no payment of annual fees |