JP3740904B2 - Concrete dam construction management system - Google Patents
[go: Go Back, main page]

JP3740904B2 - Concrete dam construction management system - Google Patents

Concrete dam construction management system Download PDF

Info

Publication number
JP3740904B2
JP3740904B2 JP23985399A JP23985399A JP3740904B2 JP 3740904 B2 JP3740904 B2 JP 3740904B2 JP 23985399 A JP23985399 A JP 23985399A JP 23985399 A JP23985399 A JP 23985399A JP 3740904 B2 JP3740904 B2 JP 3740904B2
Authority
JP
Japan
Prior art keywords
area
concrete
construction
formwork
dam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP23985399A
Other languages
Japanese (ja)
Other versions
JP2001064947A (en
Inventor
よう子 葛谷
誠治 松田
良一 岩崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP23985399A priority Critical patent/JP3740904B2/en
Publication of JP2001064947A publication Critical patent/JP2001064947A/en
Application granted granted Critical
Publication of JP3740904B2 publication Critical patent/JP3740904B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【0001】
【発明の属する技術分野】
本発明はコンクリートダムの施工管理システムに関する。
【0002】
【従来の技術】
山間部の谷間等を利用して構築される大規模構造物にコンクリートダムがあり、河川流路が短く、従って流下勾配も急な我が国においては、強大な耐水圧性能と耐候性を備えた係るコンクリートダムは広く建設され実用に供されている。このコンクリートダムを建設するにあたり、ダム堤体を適宜区画に分割して施工することが一般的であり、本明細書中ではこの適宜分割された区画をコンクリート打設作業と絡めて打設ブロックと称している。実際の施工の際には、該打設ブロック毎に、コンクリート数量、型枠面積、目地型枠面積、岩着処理面積等を適当な施工区間、あるいは施工期間について算出集計し、各々について数量表を作成して施工計画及び施工管理、或いは施主への出来高報告等に反映させていた。
【0003】
従来、上記の数量表作成の作業にあたっては、堤体構築、つまりはコンクリート打設が進行するに伴って上昇するリフト標高に応じて、打設ブロックの上下面を捉えた打設平面図をいちいち作成し、その打設平面図に基づいて寸法、形状等を考慮しつつ手計算で膨大な数量計算を行って前記数量表を作成していた。
【0004】
【発明が解決しようとする課題】
しかしながら、従来のコンクリートダム施工管理システムにあっては、上記数量表を全て手計算にて作成することとなっておりその膨大な作業に要する手間は甚だ大きく、費やされる人件費や作業時間も自ずと多大なものとなる。
【0005】
更には、数量表を作成する時点で行われる各種計算作業についても、打設ブロック毎に、或いはコンクリート数量や型枠面積等の数量種別に別個に計算が行われることが普通であって、同施工区間、同施工期間において類似してはいるが異なる計算パターンを多数繰り返し行うことも多く、自然、人為的計算ミスいわゆるケアレスミスが頻発し正確な数量算出を期することは困難となる。また、作成された数量表自体、数量種別に独立しており、相互にリンクして即時的かつ正確なデータ参照や集計作業などを行える環境になかった。
【0006】
そこで、本発明はこのような従来の課題に着目してなされたもので、打設平面図に基づき各種数量表を全て手計算にて作成するといった煩雑な手間が不要であり、しかも該数量表がシステム的に統合一体化されて、施工区間や施工期間等に応じて随意に自動算出及び集計等が可能であるコンクリートダム施工管理システムを提供するものである。
【0007】
【課題を解決するための手段】
この発明は上記目的を達成するためになされたもので、ダム堤体の寸法及び形状にそった3次元コンピュータ図面である堤体図面を作成する堤体図面作成過程と、前記堤体図面から自動取得される堤体各所の寸法より、各打設ブロックについて前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積を算出し、各々打設コンクリート数量表、型枠数量表、目地型枠数量表、及び岩着処理面積計算書を自動作成する数量表作成過程と、該数量表作成過程において算出された前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積をその種別毎に分類整理しつつデータベースに蓄積記憶させるデータベース構築過程と、前記データベースに蓄積記憶された前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積を随意に取り出して、施工区間または施工期間に応じて再集計しコンクリートダムの施工状況確認や出来高確認等を行うことで実際の施工をフィードバック管理する施工管理過程とからなることを特徴とする。
【0008】
また、前記堤体図面について、堤体の標高を指定することで、前記打設ブロックの上面および下面の打設平面図を台形区画の集合体として示し、更に該台形区画の各辺に沿ってその寸法を、前記数量表作成過程において自動取得可能な寸法データとして表示すると好適である。
【0009】
更に、前記堤体図面のうち、堤体外表面に沿って作成される型枠線及び目地型枠線について、各部各線を型枠の種類に応じて色別表示し、前記数量表作成過程において自動取得可能な型枠データとして表示すると良い。
【0010】
加えて、前記堤体図面において、堤体外形の曲面に基づく、任意の標高における上下打設平面の高低差による型枠表面の傾斜長を、前記数量表作成過程において自動算出し型枠面積の計算を行うこととする。
【0011】
【発明の実施の形態】
以下、本発明の好ましい実施の形態につき、添付図面を参照して詳細に説明する。図1は本発明のコンクリートダム施工管理システム10を示す流れ図である。
【0012】
本発明のコンクリートダム施工管理システム10の初期過程である、堤体図面作成過程11は、その図面作成の手段等については特に図示しないが、例えば、3次元描画処理が可能なCADシステムなどを用いて、施工管理対象となるダム堤体の寸法及び形状を正確な縮尺にてコンピュータ図面化処理を施すことにより堤体図面を完成させるものである。その描画手段については、まったく初期の段階からCAD入力システムのみを利用して作図を行ってもよく、或いは下図等をデジタイズ処理することで全体像を簡便に捉えることを併用していくなどの手段を用いても、図面の正確性が確保可能であれば勿論問題ない。
【0013】
作成される堤体図面はコンピュータ上の図面ファイルとしてひとまず保存されることとなるが、例えばそのフォーマットはDXF形式とするのが好適である。この図面ファイルは、後に作成される全数量表のデータの元となる。1図面ファイルには、1打設ブロックまたは1日毎に打設した複数打設ブロックの打設平面図20が上下面に分けられて打設平面図20a、20bとして入力されている(図2参照)。図中では、上下の打設平面図20a、20b各々について、紙面右上方向(該図を立体的に捉えると紙面奥方向)に、堤体が周辺岩盤と接合一体化する岩着部21が縁状に示され、それとは反対側の紙面左下方向(該図を立体的に捉えると紙面手前方向)には、隣接する打設ブロックとの境界たる目地型枠線22が直線として描かれ、更に、その目地型枠線22から紙面奥方向に向かって型枠線23が複数延びて、打設平面図20a、20b内を台形区画24に区分している。なお、各々の線22、23には寸法線25が付されているものとし、前記型枠線23及び目地型枠線22については、各部各線を型枠の種類に応じて色別表示することとする。
【0014】
実際に打設ブロック毎に打設コンクリート体積計算を行う場合、まずは打設ブロックの上下打設平面図20a、20b内を上記台形区画24として区分してその台形区画24毎に面積計算を行うこととなるが、この台形区画24のことを本実施例においては計算面30と称している。係る計算面30に関しては、複数の台形区画24が集合したものであっても良い。実際には該計算面30は、コンクリート配合や打設順序など施工上の技術的必要性に応じて決定されるものである。
【0015】
つまり本実施例の堤体図面作成過程11において、最終的には図2に示すように、堤体図面について堤体の標高を指定することで、打設ブロックの上面および下面の打設平面図20a、20bを、台形区画24の集合体として示し、更に該台形区画24の各辺に沿ってその寸法を、後の数量表作成過程において自動取得可能な寸法データとして表示することになる。
【0016】
以下に、各数量種別に打設平面図20よりデータ自動取得が行われる過程を概略述べる。まず、打設コンクリート数量計算に際し必要なデータとして、図3に示す様に打設ブロックの計算面30内における台形区画24の各辺に記された寸法線25がある。該寸法線25については、型枠線23や目地型枠線22と違って種別はないので色分けされている必要は特にない。本発明の施工管理システム10と連動したコンピュータシステム等が、打設平面図20中の前記寸法線25に自動的にソーティングなどを行うことで、各所寸法値をデータとして読み込みすることになる。これにより得られた台形区画24の寸法データを元に実施される数量計算における計算式及び手順については、図中の計算過程31に示す通り、通常の台形面積の公式を適用したものである。台形区画24が例えば矩形区画となったとしても基本的手順に相違は無く、ダム堤体を施工する上で常識的範囲の区画分けがなされた多角形状であればいずれの形状の場合にも特に問題無い。
【0017】
次に、型枠数量計算に際して行われるデータの自動取得は、打設平面図20に示された上述の型枠線23より型枠種類及び寸法情報等を取得することで実行され、その後、取得されたデータに基づき面積計算処理を行う。手順としては下記の▲1▼から▲3▼に示すものとなる。
【0018】
▲1▼画層を分ける。
打設ブロックの上下打設平面図20a、20bで画層を分ける。
▲2▼線の色分け
型枠の種類によって型枠を表す型枠線23の色分けをする。
▲3▼型枠面積計算
前述したように台形公式、あるいは他の多角形の面積式等により型枠面積の算出を行うが、堤体外形の曲面に基づく、打設平面図20の上下面20a、20bの同一位置における型枠線23の平面位置ずれ(図4参照)を考慮しつつ、型枠の実際の長さ(傾斜長)を計算することが必要となる。本発明においては、任意の標高における上下打設平面20a、20bの高低差による型枠表面の傾斜長を、図4中の式1に基づいて自動算出し型枠面積の計算を行うことが可能である。また、目地型枠数量計算についても、上述の型枠数量計算の過程と同様に行われる。
【0019】
更に、岩着面積計算に際しては、まず、計測点51(予め定めた岩着面50の適宜箇所)の座標を打設平面図20中より自動取得して計算処理を行う。なお、上下の打設平面図20a、20bで寸法線25の色分けを行っておくと認識が容易となり誤認等が生じにくい。計測点51で閉じられた領域(岩着面50)の面積をその座標から算出するにあたっては、平面箇所については平面積の算出方法として、
計算式1:X’=Xi−X1
計算式2:X’i+1−X’i-1
計算式3:Y’=Yi−Y1
計算式4:(計算式2)×Y’
の各計算式を実行し、更に、計算式4で求められた値を合計して2で割ったものが平面積Sとなる(図5(a)、(b)参照)。斜面状箇所については、上記の通常の平面積の計算を行って得られた平面積Sに以下の手順を施すことで求める。
【0020】
斜面積SSの算出方法は以下の▲1▼〜▲5▼の通りである。
▲1▼打設平面図20における、上下面20a、20bの各岩着線の長さを求める。
▲2▼打設平面図20における、上下面20a、20bの岩着線の平均長(L3=(L1+L2)/2)を求める。
▲3▼平面積(S)/平均長(L3)よりL4を求める。
▲4▼斜面計数を求める。((c)図中の式2参照)
▲5▼斜面積:SS=S×k
【0021】
上記の如く、堤体図面より寸法データ等を自動取得し各種数量計算を終えた後は、作成しておいた(もしくは自動取得と同時に作成した)各数量表に各数量をダウンロードすることになる。これにより本発明における数量表作成過程12(図1参照)が完了し、引き続き、求められた打設コンクリート量、型枠面積、及び目地型枠面積等の数量をデータベースに転送し蓄積する(図1中、データベース構築過程13)ことで施工上の各種情報管理がなされる。蓄積された数量データは、任意の施工区間や施工期間等に応じて随意に取り出されて再集計されることとなり、その後の施工計画や施工管理、並びに出来高確認等に供されてコンクリートダムの施工を統合的に管理するのである。
【0022】
これより、実際に本発明のコンクリートダム施工管理システム10がソフト化された「ダム数量計算支援システム」をコンピュータ上で起動し、上述の各過程をふまえる様子を示す。本システムを起動するとメインメニュー60が表示される。最初に、対象となる数量の種別を、「コンクリート」、「型枠」、「目地」のチェックボックス61中から選択してチェックを付け、数量表の種類を決定する。数量表の新規作成、編集、追加、削除については、数量表の種類を選択した後、画面中の各実行ボタン62、63、64、65を押す。その他、月度集計処理、岩着部面積計算については、画面右半部分にある同名の実行ボタン66、67を押すことで次手順へと進む。
【0023】
次に、図面情報の入力手順が実行される。前記打設平面図20より寸法値データの自動取得を行うのであるが、例えば打設コンクリート数量に関しては図7に示す通り、図面情報入力ウィンドウ70が開き、係るウィンドウ70上部から打設日71、打設ブロック番号72、リフト番号73、補助番号74、計算ブロック数75、リフトの高さ76、コメント77、標高78等のブランクボックスが配置されている。データの自動取得を実施したい打設ブロックや、リフト番号、標高等々を指定すれば、先に作成されている堤体図面(打設平面図20)に自動的にソーティングがかかりデータ取得が行われるのである。
【0024】
このデータ取得の確認を行う際の取得確認ウィンドウ80は図8に示す様に、上端の操作フォーム81、その下方に連接するCAD図面82、そして、操作フォーム81及びCAD図面82の右上端に重なる形でデータ確認フォーム83がそれぞれ配置されたものとなっている。係るウィンドウと対応した操作としては、以下の▲1▼〜▲6▼に示す通りである。
【0025】
▲1▼操作フォーム81で、打設平面図20の上下面20a、20bの選択、面番号の指定、コンクリート配合の指定、モルタル厚選択をそれぞれ行って、フォーム右端下部の実行ボタン81aを押す。
▲2▼CAD図面82上の寸法線25を上辺、高さ、下辺の順に選択し、Enterキーを押す。ただし長方形の場合、上辺と下辺の寸法は同じであるから下辺の選択は省略してもよい。
▲3▼ここでデータ確認フォーム83が表示されるので、寸法値の正否を確認する。データを修正する場合はこのフォームで修正することが出来る。
▲4▼同じ計算面30の寸法値を選択する場合は、再度実行ボタンを押しCAD図面82上の寸法値を選択する。1つの計算面30で複数の台形区画24を選択する場合は、実行、上辺、高さ、下辺、Enterキー、実行、上辺、高さ、下辺、Enterキー・・・の繰り返しとなる。
▲5▼異なる計算面30の値を取得する場合は、操作フォーム81の設定条件を変更し、実行ボタン81aを押し、寸法線25の値を再度取得する。
▲6▼実行ボタン81aを押す前(データ取得状態ではない)であれば、CADを操作(画層の切り替え、視点の切り替え等)することができる。実行ボタン81aを押した後(データ取得中)はCADを操作することは出来ない。
【0026】
なお、取得したデータの表示・修正を行う場合は、
▲1▼表示したい計算面番号を操作フォーム81に入力し、データの表示・修正ボタン81bを押す。
▲2▼確認フォーム83に取得されている値が表示される。修正する場合は、データ確認フォーム83上の修正する寸法値を選択しテキストボックス上で値を修正する。
▲3▼修正が終わったらデータ更新ボタン83aを押し、データを更新する。
といった手順を実行することになる。
【0027】
全ての計算面30のデータを取得した後、操作フォーム81の「データシートへ出力」ボタン81cを押す。取得したデータをデータシートへと出力する。以下が出力したデータシートの一例である。
【0028】
【表1】

Figure 0003740904
【0029】
次に上記のデータシート中のデータをデータベースへ転送し蓄積することになる。データベースへと転送されるデータは、データシート中の、下面集計(データベース上はグリーンカット面積)の合計、体積の合計及び各コンクリート配合の合計が主に選択される。日付やブロック番号および各計算面の合計はこの表からは転送されない。データベースに転送される日付、ブロック番号は先の「図面情報の入力手順」で入力した値が転送される。この合計値が、後の集計処理の基本データとなるのである。このデータベースのデータ内容表示の一例を図9に示す。
【0030】
また、上述の打設コンクリート量についての数量計算と同様に、型枠数量計算も行うとすれば、まず図面情報の入力手順が実行される。図10は、型枠数量計算についての図面情報入力ウィンドウ100である。ここでは、型枠線23の色、打設ブロック名などを主に入力しておく。「計算するブロック数」欄101に入力した数だけ、画層名の一致フォーム110(図11参照)が表示される。例えば、「計算するブロック数」欄101に「2」を入力した場合、該フォーム110は2回表示され、それぞれにプルダウンメニュー111の中から型枠の形式を選択するなどして必要なデータを入力することとなる。型枠線23の色番号の入力方法は、まず入力したい「型枠の種類」欄102をピックアップし、その後色番号入力ボックス103から線色を入力する。
【0031】
型枠数量計算の結果得られたデータシートは、4シートの構成となり、
シート1:打設平面図上面20aの型枠線23の座標値、線の長さ、色及び画層名
シート2:同下面20bの型枠線23の座標値、線の長さ、色及び画層名
シート3:上面20a、下面20bの線のずれより高さを計算
シート4:計算結果
の内容となっている。表2にシート4の計算結果表を示す。
【0032】
【表2】
Figure 0003740904
【0033】
次に上記のデータシート中のデータをデータベースへ転送し蓄積することになる。データベースへと転送されるデータは、打設ブロック番号と各打設ブロック毎の各型枠面積の小計となる。日付やブロック番号および各計算面30の合計はこの表からは転送されない。このデータベースのデータ内容表示120の一例を図12に示す。その他、目地型枠数量計算、岩着部面積計算等も上記と同様に行われるとする。
【0034】
前記データベースに上述の如く蓄積記憶された各種数量を随意に取り出して、施工区間、施工期間等に応じて再集計しコンクリートダムの施工状況確認や出来高確認等を行うところの、集計処理作業14(施工管理過程として)をデータベス構築過程13に続いて行う。本実施例では、例えば、データベースに記憶されている各数量表毎または全ての数量表の集計を期間毎またはブロック毎に行う。
【0035】
図13に本発明の施工管理過程14における期間集計時に開かれる集計項目入力ウィンドウ130の一例を示す。該ウィンドウ130は、上端に集計項目として、コンクリート、型枠、目地、全部のそれぞれについてチェックボックス131を備え、その下方には集計期間の指定欄132とブロック番号欄133が配置されたものである。各数量表または全ての数量表の集計を、該ウィンドウ130にて入力された期間について実行することとなる。この結果集計された集計結果を集計結果表として表3として示す。表で分かる通り、左端列に打設日を順を追って示し、それに対応したブロック番号及び標高、そして順次右方列に堤体各部に対応した数量が記されて期間中の数量が明白となっている。
【0036】
【表3】
Figure 0003740904
【0038】
従って、本発明のコンクリートダム施工管理システム10によれば、任意の施工期間や施工区間等について多種に亘る数量集計を自動的に行うことが可能であり、更には、従来膨大な数量計算作業を伴っていた施工管理作業を大幅に低減及び簡便化させることができ、コンクリートダム施工効率の改善に著しい効果を発現するのである。
【0039】
【発明の効果】
以上詳細に説明したように、本発明のコンクリートダム施工管理システムは、コンクリートダムを構築する際に行われる所定打設ブロック毎のコンクリート打設に伴って考慮される、打設コンクリート数量、型枠面積、目地型枠面積、及び岩着処理面積について、これらを任意の施工区間や施工期間に応じて算出集計し、コンクリートダムの施工管理を統合的に行う施工管理システムであって、
ダム堤体の寸法及び形状にそった3次元コンピュータ図面である堤体図面を作成する堤体図面作成過程と、前記堤体図面から自動取得される堤体各所の寸法より、各打設ブロックについて前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積を算出し、各々打設コンクリート数量表、型枠数量表、目地型枠数量表、及び岩着処理面積計算書を自動作成する数量表作成過程と、該数量表作成過程において算出された前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積をその種別毎に分類整理しつつデータベースに蓄積記憶させるデータベース構築過程と、前記データベースに蓄積記憶された前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積を随意に取り出して、施工区間または施工期間に応じて再集計しコンクリートダムの施工状況確認や出来高確認等を行うことで実際の施工をフィードバック管理する施工管理過程とからなることを特徴とするものである。
【0040】
したがって本発明によれば、3次元コンピュータ図面にリフト標高を指定するだけで打設平面図も自動作成され、しかもその図面に基づき打設コンクリート数量表、型枠数量表、目地型枠数量表、及び岩着処理面積計算書の各数量表を全て自動計算にて作成することが可能であり、更には該数量表がシステム的に統合一体化されて、施工区間や施工期間等に応じて随意に自動算出及び集計等を行うことも出来るのである。これによりコンクリートダムの施工管理を正確かつ確実に行うことができ、ひいては施工効率や施工コストの改善にも資するものである。
【0041】
また、前記堤体図面について、堤体の標高を指定することで、前記打設ブロックの上面および下面の打設平面図を台形区画の集合体として示し、更に該台形区画の各辺に沿ってその寸法が、前記数量表作成過程において自動取得可能な寸法データとして表示されることとなれば、数量表自動作成時においても、状況に応じて人がデータ確認を行うこともでき、数量表作業効率の向上と共に、作業の確実性を更に高めることが出来る。
【0042】
更に、前記堤体図面のうち、堤体外表面に沿って作成される型枠線及び目地型枠線について、各部各線を型枠の種類に応じて色別表示し、前記数量表作成過程において自動取得可能な型枠データとして表示すれば、図中における型枠の識別効率が高まり、作業の迅速性及び確実性も向上する。
【0043】
加えて、前記堤体図面において、堤体外形の曲面に基づく、任意の標高における上下打設平面の高低差による型枠表面の傾斜長を、前記数量表作成過程において自動算出し型枠面積の計算を行うことになれば、ダム堤体形状の、例えばアーチ形等に対しても正確な数量計算を行うことができる。
【図面の簡単な説明】
【図1】本発明の本発明のコンクリートダム施工管理システムを示す流れ図である。
【図2】本発明の堤体図面作成過程において作成された打設平面図を示す。
【図3】打設ブロックの計算面内を台形区画に区分した例を示す示す説明図である。
【図4】堤体外形の曲面に基づく、打設平面図の上下面の同一位置における型枠線の平面位置ずれを示し、更にそれを考慮しつつ型枠の実際の長さ(傾斜長)を計算する様子を示す説明図である。
【図5】(a)、(b)、(c)は、本発明の数量表作成過程において行われる岩着面積計算に際し、計測点で閉じられた領域(岩着面)の面積をその座標から算出する様子を示す説明図である。
【図6】本発明のコンクリートダム施工管理システムがソフト化された「ダム数量計算支援システム」をコンピュータ上で起動した際に表示されるメインメニュー画面を示す説明図である。
【図7】ダム数量計算支援システムにおける図面情報入力ウィンドウを示す説明図である。
【図8】ダム数量計算支援システムにおけるデータ取得確認を行う取得確認ウィンドウを示す説明図である。
【図9】ダム数量計算支援システムにおいて打設コンクリート数量計算を行った際の、データベースのデータ内容表示の一例を示す説明図である。
【図10】ダム数量計算支援システムにおいて型枠数量計算についての図面情報入力ウィンドウを示す説明図である。
【図11】ダム数量計算支援システムにおいて型枠数量計算について画層名の一致フォームを示す説明図である。
【図12】ダム数量計算支援システムにおいて型枠数量計算を行った際の、データベースのデータ内容表示の一例を示す説明図である。
【図13】本発明の施工管理過程における期間集計時に開かれる集計項目入力ウィンドウの一例を示す説明図である。
【符号の説明】
11 堤体図面作成過程
12 数量表作成過程
13 データベース構築過程
14 施工管理過程[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a concrete dam construction management system.
[0002]
[Prior art]
In Japan, large-scale structures constructed using mountainous valleys, etc. have concrete dams, river channels are short, and therefore the slope of downflow is steep, so in Japan it has strong water pressure resistance and weather resistance. Concrete dams are widely built and put into practical use. When constructing this concrete dam, it is common to divide the dam body into appropriate sections, and in this specification, the appropriately divided sections are combined with the concrete placing work and the placement block. It is called. During actual construction, for each placement block, the concrete quantity, formwork area, joint formwork area, rock formation area, etc. are calculated and calculated for the appropriate construction section or construction period, and the quantity table for each Was reflected in the construction plan and construction management, or the volume report to the owner.
[0003]
Conventionally, in the above work for creating the quantity table, a plan view of the placement block that captures the upper and lower surfaces of the placement block according to the lift elevation that rises as the construction of the embankment, that is, the concrete placement progresses, has been carried out. The quantity table was created by performing a huge quantity calculation by hand calculation while taking into consideration the size, shape, etc. based on the placement plan.
[0004]
[Problems to be solved by the invention]
However, in the conventional concrete dam construction management system, all the above quantity tables are created by manual calculation, and the labor required for the enormous work is very large, and the labor cost and work time consumed are also naturally. It will be enormous.
[0005]
Furthermore, various calculation operations performed at the time of preparing the quantity table are usually performed separately for each placement block or for each quantity type such as concrete quantity and formwork area. In many cases, different calculation patterns that are similar but different in the construction section and the construction period are often repeated, and natural and artificial calculation mistakes, so-called careless mistakes, occur frequently, and it is difficult to calculate an accurate quantity. In addition, the created quantity table itself is independent of the quantity type, and there was no environment where the data could be linked to each other and used for quick and accurate data reference and aggregation work.
[0006]
Therefore, the present invention has been made paying attention to such a conventional problem, and does not require a complicated work such as manually creating various quantity tables based on the placement plan view. Are integrated and integrated systematically to provide a concrete dam construction management system that can be automatically calculated and tabulated at will according to the construction section and construction period.
[0007]
[Means for Solving the Problems]
The present invention has been made in order to achieve the above-described object, and includes a levee body drawing creation process for creating a dam body drawing, which is a three-dimensional computer drawing in accordance with the dimensions and shape of a dam dam body, and automatic from the dam body drawing. than the dimensions of the embankment various locations to be acquired, the punching set concrete amount for each pouring block, the mold area, calculates joint formwork area, and Iwagi treated surface product, each Da設concrete quantity table, mold quantity A quantity table creation process for automatically creating a table, joint mold form quantity table, and rock formation processing area calculation sheet, and the placement concrete amount, mold area, joint mold form area calculated in the quantity table creation process , and and database construction process to be accumulated and stored in a database while organizing classify rock deposition process area for each type thereof, the punching setting concrete amount accumulated stored in the database, the mold area, joint formwork area, and rock Remove the processing area optionally, characterized in that it consists of a construction management process of feedback managing the actual construction by performing re-aggregated construction status check or volume such as confirmation of the concrete dam according to inter construction section or construction phase And
[0008]
Moreover, about the said levee body drawing, by designating the elevation of the levee body, the placement plan view of the upper surface and the lower surface of the placement block is shown as an aggregate of trapezoidal sections, and further along each side of the trapezoidal sections It is preferable to display the dimensions as dimension data that can be automatically acquired in the quantity table creation process.
[0009]
Further, in the drawing of the levee body, for each of the formwork line and the joint formwork line created along the outer surface of the levee body, each part line is displayed by color according to the type of the formwork, and automatically in the quantity table creation process. It is good to display as obtainable formwork data.
[0010]
In addition, in the levee body drawing, the slope length of the formwork surface due to the height difference of the upper and lower placement planes at an arbitrary elevation based on the curved surface of the levee body outer shape is automatically calculated in the process of creating the quantity table, and the formwork area We will calculate.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. FIG. 1 is a flowchart showing a concrete dam construction management system 10 of the present invention.
[0012]
The levee body drawing creation process 11, which is an initial process of the concrete dam construction management system 10 of the present invention, is not particularly shown with respect to the means for creating the drawing, but for example, a CAD system capable of three-dimensional drawing processing is used. The dam body drawing is completed by subjecting the dimensions and shape of the dam body to be managed to a computer drawing process at an accurate scale. As for the drawing means, the drawing may be performed using only the CAD input system from the very beginning stage, or a method such as simply capturing the whole image by digitizing the following figure is used. Of course, there is no problem as long as the accuracy of the drawing can be secured.
[0013]
The created levee body drawing is first saved as a drawing file on a computer. For example, the format is preferably the DXF format. This drawing file is the basis for all quantity table data created later. In one drawing file, placement plan views 20 of one placement block or a plurality of placement blocks placed every day are input as placement plan views 20a and 20b divided into upper and lower surfaces (see FIG. 2). ). In the drawing, for each of the upper and lower placement plan views 20a and 20b, a rock formation 21 where the dam body is joined and integrated with the surrounding rock mass is in the upper right direction on the paper surface (the depth direction on the paper surface when the figure is viewed three-dimensionally). In the lower left direction on the opposite side of the drawing (the front side of the drawing when the figure is viewed three-dimensionally), a joint frame line 22 that is a boundary with an adjacent placement block is drawn as a straight line. A plurality of formwork lines 23 extend from the joint formwork line 22 toward the back of the paper surface, and the placement plan views 20 a and 20 b are divided into trapezoidal sections 24. In addition, it is assumed that a dimension line 25 is attached to each of the lines 22 and 23, and for the formwork line 23 and the joint formwork line 22, each line is displayed by color according to the type of formwork. And
[0014]
When actually calculating the placement concrete volume for each placement block, first, the upper and lower placement plan views 20a and 20b of the placement block are divided as the trapezoidal section 24 and the area calculation is performed for each trapezoidal section 24. However, the trapezoidal section 24 is referred to as a calculation surface 30 in this embodiment. The calculation surface 30 may be a collection of a plurality of trapezoidal sections 24. Actually, the calculation surface 30 is determined in accordance with technical needs in construction such as concrete mixing and placing order.
[0015]
That is, in the levee body drawing creation process 11 of the present embodiment, finally, as shown in FIG. 2, by designating the altitude of the levee body with respect to the levee body drawing, the plan view of the upper and lower surfaces of the laying block 20a and 20b are shown as a collection of trapezoidal sections 24, and the dimensions along each side of the trapezoidal sections 24 are displayed as dimension data that can be automatically acquired in a subsequent quantity table creation process.
[0016]
Below, the process of automatic data acquisition from the placement plan view 20 for each quantity type will be outlined. First, as necessary data for calculating the amount of cast concrete, there are dimension lines 25 written on each side of the trapezoidal section 24 in the calculation surface 30 of the cast block as shown in FIG. Unlike the formwork line 23 and the joint formwork line 22, the dimension line 25 need not be color-coded because there is no type. A computer system or the like interlocked with the construction management system 10 of the present invention automatically sorts the dimension line 25 in the placement plan view 20 to read the dimension values as data. About the calculation formula and procedure in the quantity calculation performed based on the dimension data of the trapezoidal section 24 obtained by this, as shown in the calculation process 31 in the figure, a normal trapezoid area formula is applied. Even if the trapezoidal section 24 becomes a rectangular section, for example, there is no difference in the basic procedure, and in particular in any shape as long as it is a polygonal shape that is divided into common sense ranges when constructing a dam dam body No problem.
[0017]
Next, the automatic acquisition of data performed in the calculation of the number of molds is performed by acquiring the form type and dimensional information from the above-described mold line 23 shown in the placement plan view 20, and thereafter acquiring the data. An area calculation process is performed based on the obtained data. The procedure is as shown in (1) to (3) below.
[0018]
(1) Divide the layers.
The layers are divided by the top and bottom placement plan views 20a and 20b of the placement block.
(2) Color coding of lines The color of the formwork line 23 representing the formwork is classified according to the type of formwork.
(3) Formwork area calculation As described above, the formwork area is calculated by the trapezoidal formula or other polygonal area formulas, etc., but the upper and lower surfaces 20a of the placement plan view 20 based on the curved surface of the outer shape of the dam body. 20b, it is necessary to calculate the actual length (inclination length) of the mold while taking into account the planar displacement (see FIG. 4) of the mold line 23 at the same position. In the present invention, it is possible to automatically calculate the inclination length of the mold surface due to the height difference between the upper and lower placement planes 20a and 20b at an arbitrary altitude and to calculate the mold area based on Expression 1 in FIG. It is. Further, the joint formwork quantity calculation is performed in the same manner as the above-described formwork quantity calculation process.
[0019]
Further, when calculating the rock formation area, first, the coordinates of the measurement point 51 (appropriate portion of the predetermined rock formation surface 50) are automatically acquired from the placement plan view 20 and calculation processing is performed. In addition, if the dimension lines 25 are color-coded in the upper and lower placement plan views 20a and 20b, recognition becomes easy and misidentification or the like hardly occurs. In calculating the area of the region (rocking surface 50) closed at the measurement point 51 from the coordinates,
Formula 1: X '= Xi-X1
Formula 2: X′i + 1−X′i−1
Formula 3: Y '= Yi-Y1
Formula 4: (Formula 2) × Y ′
Each of the following formulas is executed, and the values obtained by the formula 4 are summed and divided by 2 to obtain the plane area S (see FIGS. 5A and 5B). About a slope-shaped location, it calculates | requires by giving the following procedures to the plane area S obtained by calculating said normal plane area.
[0020]
The method of calculating the oblique area SS is as follows (1) to (5).
{Circle around (1)} The length of each rock formation line on the upper and lower surfaces 20a and 20b in the placement plan view 20 is obtained.
(2) The average length (L3 = (L1 + L2) / 2) of the rock formation lines on the upper and lower surfaces 20a, 20b in the placement plan view 20 is obtained.
(3) L4 is obtained from the plane area (S) / average length (L3).
(4) Calculate the slope count. ((C) Refer to Equation 2 in the figure)
(5) Oblique area: SS = S × k
[0021]
As described above, after automatically obtaining the dimension data from the levee drawing and completing various quantity calculations, each quantity will be downloaded to each quantity table that has been created (or created simultaneously with automatic acquisition). . This completes the quantity table creation process 12 (see FIG. 1) according to the present invention, and subsequently transfers and accumulates the calculated quantities of cast concrete, formwork area, joint formwork area, etc. to the database (see FIG. 1). 1, various information management in construction is performed by the database construction process 13). The accumulated quantity data will be taken out at any time according to any construction section and construction period, and will be re-calculated, and will be used for subsequent construction plans, construction management, volume confirmation, etc. Is managed in an integrated manner.
[0022]
From this, the “dam quantity calculation support system” in which the concrete dam construction management system 10 of the present invention is actually started up on a computer will be described based on the above-described processes. When this system is activated, a main menu 60 is displayed. First, the type of quantity to be targeted is selected and checked from the check boxes 61 of “concrete”, “formwork”, and “joint” to determine the type of quantity table. For new creation, editing, addition, and deletion of a quantity table, after selecting the type of quantity table, each execution button 62, 63, 64, 65 in the screen is pressed. In addition, with regard to monthly count processing and rock formation area calculation, the execution proceeds to the next procedure by pressing the execution buttons 66 and 67 having the same name in the right half of the screen.
[0023]
Next, a drawing information input procedure is executed. Dimensional value data is automatically acquired from the placement plan view 20. For example, with respect to the placement concrete quantity, as shown in FIG. 7, a drawing information input window 70 is opened. Blank boxes such as a placement block number 72, a lift number 73, an auxiliary number 74, a calculation block number 75, a lift height 76, a comment 77, and an altitude 78 are arranged. If you specify the placement block for which you want to automatically acquire data, the lift number, the elevation, etc., the previously created levee drawing (placement plan 20) is automatically sorted and the data is acquired. It is.
[0024]
As shown in FIG. 8, the acquisition confirmation window 80 for confirming the data acquisition overlaps the operation form 81 at the upper end, the CAD drawing 82 connected below it, and the upper right end of the operation form 81 and the CAD drawing 82. The data confirmation forms 83 are arranged in a form. The operations corresponding to such a window are as shown in (1) to (6) below.
[0025]
(1) On the operation form 81, the upper and lower surfaces 20a, 20b of the placement plan 20 are selected, the surface number is designated, the concrete composition is designated, and the mortar thickness is selected, and the execution button 81a at the lower right end of the form is pushed.
(2) Select the dimension line 25 on the CAD drawing 82 in the order of the upper side, the height, and the lower side, and press the Enter key. However, in the case of a rectangle, the dimensions of the upper side and the lower side are the same, so the selection of the lower side may be omitted.
(3) Since the data confirmation form 83 is displayed here, the correctness of the dimension value is confirmed. If you want to modify the data, you can use this form.
(4) When selecting the dimension value of the same calculation surface 30, the execution button is pressed again and the dimension value on the CAD drawing 82 is selected. When a plurality of trapezoidal sections 24 are selected on one calculation plane 30, execution, upper side, height, lower side, Enter key, execution, upper side, height, lower side, Enter key,... Are repeated.
(5) When acquiring a value of a different calculation surface 30, the setting condition of the operation form 81 is changed, the execution button 81a is pressed, and the value of the dimension line 25 is acquired again.
{Circle around (6)} Before the execution button 81a is pressed (not in the data acquisition state), the CAD can be operated (switching layers, switching viewpoints, etc.). The CAD cannot be operated after the execution button 81a is pressed (during data acquisition).
[0026]
If you want to display or modify the acquired data,
(1) Enter the calculation plane number to be displayed in the operation form 81 and press the data display / correction button 81b.
(2) The value acquired in the confirmation form 83 is displayed. In the case of correction, the dimension value to be corrected on the data confirmation form 83 is selected and the value is corrected on the text box.
(3) When the correction is completed, the data update button 83a is pressed to update the data.
The procedure is executed.
[0027]
After acquiring the data of all the calculation surfaces 30, the “output to data sheet” button 81c of the operation form 81 is pressed. Output the acquired data to a data sheet. The following is an example of the output data sheet.
[0028]
[Table 1]
Figure 0003740904
[0029]
Next, the data in the data sheet is transferred to the database and stored. The data to be transferred to the database is mainly selected from the sum of the bottom surface count (green cut area on the database), the sum of the volumes, and the sum of each concrete composition in the data sheet. Dates, block numbers and totals for each calculation are not transferred from this table. As the date and block number to be transferred to the database, the values input in the previous “drawing information input procedure” are transferred. This total value is the basic data for subsequent tabulation processing. An example of the data content display of this database is shown in FIG.
[0030]
If the quantity calculation for the formwork is also performed in the same manner as the quantity calculation for the amount of cast concrete described above, the drawing information input procedure is first executed. FIG. 10 is a drawing information input window 100 for calculating the form quantity. Here, the color of the formwork line 23, the placement block name, and the like are mainly input. The same number of layer name matching forms 110 (see FIG. 11) are displayed in the “number of blocks to be calculated” column 101. For example, if “2” is entered in the “number of blocks to be calculated” field 101, the form 110 is displayed twice, and the necessary data is obtained by selecting the form form from the pull-down menu 111. Will be entered. As a method for inputting the color number of the formwork line 23, first, the “type of formwork” field 102 to be inputted is picked up, and then the line color is inputted from the color number input box 103.
[0031]
The data sheet obtained as a result of form quantity calculation is composed of 4 sheets.
Sheet 1: Coordinate value, line length, color and layer name of the formwork line 23 on the top surface 20a of the placement plan sheet 2: Coordinate value, line length, color, and line name of the formwork line 23 on the bottom surface 20b Layer name sheet 3: The height is calculated based on the deviation between the lines of the upper surface 20a and the lower surface 20b. Table 2 shows a calculation result table of the sheet 4.
[0032]
[Table 2]
Figure 0003740904
[0033]
Next, the data in the data sheet is transferred to the database and stored. The data transferred to the database is a subtotal of the placement block number and each formwork area for each placement block. The date, block number and total of each calculation plane 30 are not transferred from this table. An example of the data content display 120 of this database is shown in FIG. In addition, it is assumed that joint mold quantity calculation, rock formation area calculation, and the like are performed in the same manner as described above.
[0034]
The total processing work 14 (where the various quantities stored and stored in the database as described above are arbitrarily taken out and recalculated according to the construction section, construction period, etc., to confirm the construction status of the concrete dam, check the volume, etc. As the construction management process), the database construction process 13 is performed. In this embodiment, for example, each quantity table stored in the database or all quantity tables are totaled for each period or block.
[0035]
FIG. 13 shows an example of a total item input window 130 that is opened during period totalization in the construction management process 14 of the present invention. The window 130 includes check boxes 131 for concrete, formwork, joints, and all as total items at the upper end, and a total period specification column 132 and a block number column 133 are arranged below the check boxes 131. . Aggregation of each quantity table or all quantity tables is executed for the period input in the window 130. Table 3 shows the tabulated results tabulated as a result of tabulation. As can be seen in the table, the placement date is shown in order in the leftmost column, the corresponding block number and elevation, and the number corresponding to each part of the levee body are written in the right column, making the quantity during the period clear. ing.
[0036]
[Table 3]
Figure 0003740904
[0038]
Therefore, according to the concrete dam construction management system 10 of the present invention, it is possible to automatically collect various quantities for an arbitrary construction period, construction section, and the like. The accompanying construction management work can be greatly reduced and simplified, and a remarkable effect is exhibited in improving the concrete dam construction efficiency.
[0039]
【The invention's effect】
As explained in detail above, the concrete dam construction management system of the present invention is the amount of cast concrete and the formwork that are taken into account with the concrete placement for each predetermined placement block performed when constructing the concrete dam. area, joint formwork area, and about the Iwagi treated surface product, these calculated aggregate according to any construction period and construction period, a construction management system for integrally the construction management of the concrete dam,
From the embankment drawing creation process to create a levee body drawing, which is a three-dimensional computer drawing according to the size and shape of the dam dam body, and the dimensions of each part of the levee body automatically acquired from the dam body drawing, about each placement block the punching setting concrete amount, mold area, joint formwork area, and calculates the Iwagi treated surface product, each Da設concrete quantity table, mold quantity table, joint formwork quantity table, and Iwagi processing area statement Quantitative table creation process to automatically create, and the placement concrete amount, formwork area, joint formwork area, and rock formation area calculated in the quantity table creation process are classified and organized for each type in the database and database construction process to be accumulated and stored, the punching setting concrete amount accumulated stored in the database, retrieves mold area, joint formwork area, and Iwagi processing area optionally construction section or construction phase And it is characterized in that comprising the construction management process of feedback managing the actual construction by performing construction conditions confirmed or volume confirmation of re-aggregated concrete dam according to.
[0040]
Therefore, according to the present invention, a placement plan view is automatically created simply by specifying a lift elevation in a three-dimensional computer drawing, and a placement concrete quantity table, a form quantity table, a joint form quantity table, based on the drawing , In addition, it is possible to create each quantity table of the rock treatment area calculation form by automatic calculation, and the quantity table is systematically integrated and integrated according to the construction section, construction period, etc. It is also possible to perform automatic calculation and aggregation. As a result, the construction management of the concrete dam can be performed accurately and reliably, which in turn contributes to the improvement of construction efficiency and construction cost.
[0041]
Moreover, about the said levee body drawing, by designating the elevation of the levee body, the placement plan view of the upper surface and the lower surface of the placement block is shown as an aggregate of trapezoidal sections, and further along each side of the trapezoidal sections If the dimensions are displayed as dimension data that can be automatically acquired in the process of creating the quantity table, the person can check the data according to the situation even when the quantity table is created automatically. Along with the improvement of efficiency, the certainty of work can be further increased.
[0042]
Further, in the drawing of the levee body, for each of the formwork line and the joint formwork line created along the outer surface of the levee body, each part line is displayed by color according to the type of the formwork, and automatically in the quantity table creation process. If displayed as obtainable formwork data, the form identification efficiency in the figure is increased, and the speed and certainty of the work are also improved.
[0043]
In addition, in the levee body drawing, the slope length of the formwork surface due to the height difference of the upper and lower placement planes at an arbitrary altitude based on the curved surface of the levee body outer shape is automatically calculated in the process of preparing the quantity table and the formwork area is calculated. If calculation is to be performed, accurate quantity calculation can be performed even for a dam body shape, such as an arch shape.
[Brief description of the drawings]
FIG. 1 is a flowchart showing a concrete dam construction management system according to the present invention.
FIG. 2 shows a placement plan view created in the embankment drawing creation process of the present invention.
FIG. 3 is an explanatory diagram showing an example in which a calculation surface of a placement block is divided into trapezoidal sections.
FIG. 4 shows the positional deviation of the formwork line at the same position on the upper and lower surfaces of the placement plan view based on the curved surface of the outer shape of the embankment, and further considers the actual length of the formwork (inclined length) It is explanatory drawing which shows a mode that it calculates.
5 (a), (b), and (c) are the coordinates of the area of the area (rock formation surface) closed at the measurement point in the calculation of the rock formation area performed in the quantity table creation process of the present invention. It is explanatory drawing which shows a mode that it calculates from.
FIG. 6 is an explanatory view showing a main menu screen displayed when a “dam quantity calculation support system” in which the concrete dam construction management system of the present invention is softwareized is started on a computer.
FIG. 7 is an explanatory diagram showing a drawing information input window in the dam quantity calculation support system.
FIG. 8 is an explanatory view showing an acquisition confirmation window for performing data acquisition confirmation in the dam quantity calculation support system.
FIG. 9 is an explanatory diagram showing an example of a data content display of a database when a concrete placement quantity calculation is performed in a dam quantity calculation support system.
FIG. 10 is an explanatory view showing a drawing information input window for form quantity calculation in the dam quantity calculation support system.
FIG. 11 is an explanatory diagram showing a layer name matching form for form quantity calculation in the dam quantity calculation support system;
FIG. 12 is an explanatory diagram showing an example of data content display of a database when form quantity calculation is performed in the dam quantity calculation support system.
FIG. 13 is an explanatory view showing an example of a total item input window opened at the time of totaling in the construction management process of the present invention.
[Explanation of symbols]
11 Drawer drawing creation process 12 Quantity table creation process 13 Database construction process 14 Construction management process

Claims (4)

コンクリートダムを構築する際に行われる所定打設ブロック毎のコンクリート打設に伴って考慮される、打設コンクリート数量、型枠面積、目地型枠面積、及び岩着処理面積について、これらを任意の施工区間や施工期間に応じて算出集計し、コンクリートダムの施工管理を統合的に行う施工管理システムであって、
ダム堤体の寸法及び形状にそった3次元コンピュータ図面である堤体図面を作成する堤体図面作成過程と、前記堤体図面から自動取得される堤体各所の寸法より、各打設ブロックについて前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積を算出し、各々打設コンクリート数量表、型枠数量表、目地型枠数量表、及び岩着処理面積計算書を自動作成する数量表作成過程と、該数量表作成過程において算出された前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積をその種別毎に分類整理しつつデータベースに蓄積記憶させるデータベース構築過程と、前記データベースに蓄積記憶された前記打設コンクリート量、型枠面積、目地型枠面積、及び岩着処理面積を随意に取り出して、施工区間または施工期間に応じて再集計しコンクリートダムの施工状況確認や出来高確認等を行うことで実際の施工をフィードバック管理する施工管理過程とからなることを特徴とするコンクリートダム施工管理システム。
Are considered along with the concreting of each predetermined strokes set block which is performed when building a concrete dam, pouring concrete quantities, with mold area, joint formwork area, and Iwagi treated surface product, these It is a construction management system that calculates and aggregates according to any construction section and construction period, and performs integrated construction management of concrete dams.
From the embankment drawing creation process to create a levee body drawing, which is a three-dimensional computer drawing according to the size and shape of the dam dam body, and the dimensions of each part of the levee body automatically acquired from the dam body drawing, about each placement block the punching setting concrete amount, mold area, joint formwork area, and calculates the Iwagi treated surface product, each Da設concrete quantity table, mold quantity table, joint formwork quantity table, and Iwagi processing area statement Quantitative table creation process to automatically create, and the placement concrete amount, formwork area, joint formwork area, and rock formation area calculated in the quantity table creation process are classified and organized for each type in the database and database construction process to be accumulated and stored, the punching setting concrete amount accumulated stored in the database, retrieves mold area, joint formwork area, and Iwagi processing area optionally construction section or construction phase Concrete dam construction management system characterized by comprising the construction management process of feedback managing the actual construction by performing construction conditions confirmed or volume confirmation of re-aggregated concrete dam according to.
前記堤体図面について、堤体の標高を指定することで、前記打設ブロックの上面および下面の打設平面図を台形区画の集合体として示し、更に該台形区画の各辺に沿ってその寸法を、前記数量表作成過程において自動取得可能な寸法データとして表示することを特徴とする請求項1に記載のコンクリートダム施工管理システム。For the levee body drawing, by specifying the elevation of the levee body, the plan view of the upper and lower surfaces of the laying block is shown as an aggregate of trapezoidal sections, and the dimensions along each side of the trapezoidal section Is displayed as dimension data that can be automatically acquired in the quantity table creation process. 前記堤体図面のうち、堤体外表面に沿って作成される型枠線及び目地型枠線について、各部各線を型枠の種類に応じて色別表示し、前記数量表作成過程において自動取得可能な型枠データとして表示することを特徴とする請求項1に記載のコンクリートダム施工管理システム。Among the levee body drawings, each line of each part is displayed according to the type of the formwork line and joint formwork line created along the outer surface of the levee body, and can be automatically acquired in the quantity table creation process The concrete dam construction management system according to claim 1, wherein the concrete dam construction management system is displayed as simple formwork data. 前記堤体図面において、堤体外形の曲面に基づく、任意の標高における上下打設平面の高低差による型枠表面の傾斜長を、前記数量表作成過程において自動算出し型枠面積の計算を行うことを特徴とする請求項1に記載のコンクリートダム施工管理システム。In the levee body drawing, the slope length of the formwork surface due to the height difference of the upper and lower placement planes at an arbitrary altitude based on the curved surface of the dam body outer shape is automatically calculated in the quantity table creation process to calculate the formwork area. The concrete dam construction management system according to claim 1.
JP23985399A 1999-08-26 1999-08-26 Concrete dam construction management system Expired - Fee Related JP3740904B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23985399A JP3740904B2 (en) 1999-08-26 1999-08-26 Concrete dam construction management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23985399A JP3740904B2 (en) 1999-08-26 1999-08-26 Concrete dam construction management system

Publications (2)

Publication Number Publication Date
JP2001064947A JP2001064947A (en) 2001-03-13
JP3740904B2 true JP3740904B2 (en) 2006-02-01

Family

ID=17050859

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23985399A Expired - Fee Related JP3740904B2 (en) 1999-08-26 1999-08-26 Concrete dam construction management system

Country Status (1)

Country Link
JP (1) JP3740904B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106587693A (en) * 2016-11-07 2017-04-26 广东省水利水电科学研究院 Preparation process and construction method of special external-adding hydraulic light burning magnesium oxide dam concrete having adjustable expanding process

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5148991B2 (en) * 2007-12-27 2013-02-20 株式会社間組 Quality information management system for concrete structures
JP2010203110A (en) * 2009-03-02 2010-09-16 Kumagai Gumi Co Ltd Construction information management processing program for concrete structure
CN111984909B (en) * 2020-08-11 2023-03-31 合肥电力规划设计院 Method for rapidly calculating civil engineering quantity in power distribution network cable engineering
CN113284225B (en) * 2021-04-30 2023-05-16 大连海事大学 Rock mass homogeneous region dividing method by improved column-linked list method
CN119293899A (en) * 2024-08-23 2025-01-10 华能澜沧江水电股份有限公司 A high arch dam construction progress management method, device and storage medium

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106587693A (en) * 2016-11-07 2017-04-26 广东省水利水电科学研究院 Preparation process and construction method of special external-adding hydraulic light burning magnesium oxide dam concrete having adjustable expanding process
CN106587693B (en) * 2016-11-07 2019-01-11 广东省水利水电科学研究院 A kind of expansion process adjustable outer water mixing working platform light calcined magnesia dam concrete preparing process and construction method

Also Published As

Publication number Publication date
JP2001064947A (en) 2001-03-13

Similar Documents

Publication Publication Date Title
CN109033671B (en) Revit-based building block filler wall model modeling method capable of calculating engineering quantity
CN109785436B (en) A management method of steel bar information full life cycle based on BIM technology
KR100435296B1 (en) 3-dimensional structure design system, method of designing 3-dimensional structure and computer readable medium for recording a program for executing the said method
CN109636906A (en) Concrete filling pile construction method and system based on BIM technology
CN111177831A (en) A 3D modeling and automatic calculation method of steel bars based on BIM technology
CN113221224B (en) Forward design method and system for foundation pit support based on information model technology
CN104778753B (en) The three-dimensional modeling implementation method of bridge reinforcement
JP3740904B2 (en) Concrete dam construction management system
CN114880752B (en) BIM-based quick layout of disc buckle supports and implementation method of engineering calculation amount
CN118094691A (en) Automated system for artificial rock structural design and manufacture
CN107012860A (en) A kind of construction method of the post Single Pile joint bar positioner based on BIM technology
CN115017580B (en) Rapid batching method for arc-shaped plate structural steel bars
CN118965515B (en) Rail transit roadbed parameterization design method and system
CN114741769B (en) Bridge engineering construction task planning method based on functional graphic object
CN119107423A (en) A three-dimensional modeling method, system, device and storage medium for airport pavement engineering
CN115422632A (en) Foundation pit construction full-flow working condition recording method based on BIM model
CN113378268A (en) Underground pipe gallery deformation joint reinforcing steel bar refined electric calculation method and system based on BIM
CN113609543B (en) BIM technology-based multi-connected water collecting well mapping method
CN114386135B (en) Concrete slab reinforcement construction arrangement method and system
CN114936396B (en) Automatic dredging engineering quantity generation method based on Civil3D
CN113468631B (en) Automatic arrangement method of cast-in-situ steel bar for one-way laminated slab close-jointed joint connection
CN113468636B (en) BIM-based basement double-door threshold steel bar refined electric calculation method and system
CN114065350B (en) Rectangular structure partition blanking refined arrangement method
JP3962833B2 (en) Tile roof accumulation program, computer-readable recording medium recording the program, and tile roof accumulation system
CN117993063B (en) Method and system for displaying elevation of structural floor slab based on BIM model

Legal Events

Date Code Title Description
RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20040922

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050719

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050916

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051018

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051031

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091118

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091118

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101118

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101118

Year of fee payment: 5

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111118

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees