JP3750042B2 - Construction pillar erection device - Google Patents
Construction pillar erection device Download PDFInfo
- Publication number
- JP3750042B2 JP3750042B2 JP16740998A JP16740998A JP3750042B2 JP 3750042 B2 JP3750042 B2 JP 3750042B2 JP 16740998 A JP16740998 A JP 16740998A JP 16740998 A JP16740998 A JP 16740998A JP 3750042 B2 JP3750042 B2 JP 3750042B2
- Authority
- JP
- Japan
- Prior art keywords
- level
- guide pipe
- pillar
- gantry
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、地盤に形成した掘削孔内に構真柱を高精度で建入れるときに用いて好適な構真柱建入れ装置に関するものである
【0002】
【従来の技術】
従来、例えば、逆打ち工法で高層ビルの地下部や地下構造物を構築するに際しては、地盤に掘削孔を形成して構真柱(本設の鉄骨柱)を所定精度で建て入れた後に、バックホー等を用いて掘削孔を土砂で埋め戻し、その後、施工の進捗に伴って地盤を根切りしながら、上方から下方に向けて本設の鉄骨梁を前記構真柱に順次取り付けるようにしている。
【0003】
このような構真柱の建入れは、その平面上の位置(通り芯位置)と鉛直度および上下レベルを精度良く維持した状態で、構真柱の少なくとも下端部をコンクリートで固める必要がある。そのため、例えば掘削孔の周縁部に筒状のスタンドパイプを略鉛直にセットし、構真柱の側面にジャッキ等を取り付けてこれを水平方向に伸縮させ、その反力をスタンドパイプに取ることによって構真柱の鉛直度の調整を行う工法等が開発されている。
【0004】
ところで、構真柱を建入れるに際しては、掘削孔内に構真柱を建入れた後にコンクリートを後打ちするコンクリート後打ち式と、掘削孔内にコンクリートを先打ちした後に構真柱を建入れるコンクリート先打ち式とがある。このうち、コンクリート後打ち式では、構真柱を挿入した後の狭い空間にコンクリート打設用のトレミー管等を挿入しなければならず、作業に手間が掛かるものとなっている。一方、コンクリート先打ち式ではこのような問題は生じないものの、当然のことながら先打ちしたコンクリートが硬化するまでの間に構真柱の建入れ調整を完了する必要がある。ところが、前記工法では、ジャッキ等を用いて構真柱の鉛直度の調整を行っていたのでは時間が掛かるため、コンクリート先打ち方式に適していない。
【0005】
しかも、前記工法では、建入れる構真柱のサイズに合わせてジャッキを取り付けるためのブラケット等を用意しなければならず、これにも手間とコストがかかるという問題がある。
【0006】
この問題を解決するため、本出願人は、内周面にガイドレールを備えたガイドパイプを予め鉛直に建て込み、構真柱をガイドレールに沿って掘削孔内に挿入することによって鉛直に建て入れる装置および工法を既に出願している(特願平8−163511号)。
【0007】
【発明が解決しようとする課題】
しかしながら、上述したような本出願人が提案した技術においても、以下に示すような問題が残されている。
ガイドパイプやこれを支持する架台は切削等の機械加工によって製作されるわけではなく、それ自体に高い精度を要求することができない。したがって掘削孔の周縁部に架台を設置した状態で架台の水平を出したとしても、その後ガイドパイプをセットしたときに鉛直が出るとは限らず、このため、架台にガイドパイプをセットした状態でガイドパイプの鉛直出しを行わなければならない。また、他の位置に構真柱を建入れるため、ガイドパイプと架台を移動させた場合にも、その度にガイドパイプの位置出しを行う必要がある。
そして、ガイドパイプの鉛直出しにはレーザ管等の機器を用いなければならず、その準備や測定に手間が掛かり、さらなる改善の余地がある。
【0008】
しかも、地盤沈下等によりガイドパイプのレベルがズレた場合、その位置修正に再度手間がかかるのはいうまでもなく、またガイドパイプの通り芯位置がずれると、ガイドパイプの位置を水平方向に修正する手段がないため、その修正は非常に困難である。
【0009】
本発明は、以上のような点を考慮してなされたもので、構真柱の建入れおよび地盤沈下時等の修正等を容易に行うことのできる構真柱建入れ装置を提供することを課題とする。
【0010】
【課題を解決するための手段】
請求項1に係る発明は、地盤中に形成された掘削孔内に構真柱を建て入れる装置であって、前記構真柱を建入れるときにこれをガイドする筒状のガイドパイプと、前記掘削孔の周縁の地表面に設置されて前記ガイドパイプを支持する架台と、を備えて構成され、前記架台には、該架台の水平面に対する傾斜レベルを調整するレベル調整手段と、前記架台の傾斜レベルを示すレベル表示手段とが備えられ、前記レベル表示手段が、前記架台の複数箇所にそれぞれ設置されたレベル測定器と、これらのレベル測定器間に設けられて前記各レベル測定器で傾斜レベルを測定するための液体等の媒体を互いに連通させる連通管と、前記各レベル測定器での測定レベルを表示する表示器とを備えて構成されていることを特徴としている。
【0011】
これにより、ガイドパイプの位置出しを一度行い、そのときレベル表示手段によって示される架台の傾斜レベルを記録しておき、再度位置出しをする場合には、記録した傾斜レベルに合わせてレベル調整手段で架台の傾斜レベルを調整すればよい。このようにして、一度位置出しを行えば、ガイドパイプの位置がずれたりしても、レーザ管等を用いることなく、レベル表示手段によって示される傾斜レベルにあわせるのみでガイドパイプの位置出しを行うことができる。
なお、一回目に位置出しを行うとき、および再度位置出しするときには、いずれも架台の傾斜レベルを水平に合わせるのではなく、あくまでもガイドパイプが鉛直となるようにする。したがって、レベル表示手段で表示される傾斜レベルは、ガイドパイプが鉛直となった状態での架台の傾斜レベルを表示する。
【0013】
加えて、各レベル測定器においては、媒体の液面レベルが等しくなり、すなわち同一水平面に対する複数箇所のレベルを知ることができる。また、このようなレベル表示手段は、従来使用していたレーザ管等に比較して非常に簡易な構成となっている。
【0014】
請求項2に係る発明は、請求項1記載の構真柱建入れ装置であって、前記架台が三本の脚部によって立脚した構成となっていることを特徴としている。
【0015】
これにより、脚部を四本以上備えた場合に対し、ガタつきが生じたりすることもなく、また各脚部で分担する荷重も均一となる。また、三本脚なので、レベル出しも容易である。
【0016】
請求項3に係る発明は、請求項2記載の構真柱建入れ装置であって、前記脚部の下端部が、略球面状をなしていることを特徴としている。
【0017】
これにより、脚部の下端部とこの架台の設置面とが点接触することとなり、ガタつき等が防止できる。
【0018】
請求項4に係る発明は、請求項1から3のいずれかに記載の構真柱建入れ装置であって、前記ガイドパイプと前記架台との間には、前記ガイドパイプの水平面内における通り芯位置を調整する芯調整手段が備えられていることを特徴としている。
【0019】
これにより、ガイドパイプの通り芯位置がずれた場合にも、芯調整手段で調整することができる。
【0022】
【発明の実施の形態】
以下、本発明に係る構真柱建入れ装置の実施の形態の一例を、図1ないし図6を参照して説明する。
これらの図において、符号Cは構真柱、Gは地盤、Hは構真柱Cを建て込むため地盤Gに形成された掘削孔、1は構真柱Cを所定の精度で建入れるための構真柱建入れ装置、2は周囲の地盤Gの崩壊を防ぐため掘削孔Hの上部に設けられた円筒状の鋼管からなるスタンドパイプ、をそれぞれ示している。
【0023】
図1に示すように、構真柱建入れ装置1は、スタンドパイプ2内に挿入されて所定の通り芯位置Lに鉛直に位置出し保持されることで後から挿入される構真柱Cを通り芯位置Lに鉛直に直接ガイドするガイドパイプ4と、掘削孔Hの周縁の地表面に設置されてガイドパイプ4を支持するベース架台5とを備えて構成されている。
【0024】
図1および図2に示すように、ベース架台5は、地表面に敷設された敷鉄板6上に設置される下部架台7と、下部架台7上に設置される上部架台(架台)8とから構成されている。
【0025】
下部架台7はスタンドパイプ2を囲むよう平面視ロ字状に形成されており、その上面には三つの受け台9が略正三角形の位置関係をなすよう配置されている。
【0026】
上部架台8は、下部架台7と同様に平面視ロ字状をなしており、その下面には、各受け台9上に立脚する三つの脚部10が略正三角形の位置関係をなすよう備えられている。三つのうち、二つの脚部10には、上下方向に伸縮駆動される昇降ジャッキ(レベル調整手段)11が備えられている。そして、各脚部10の上端部はフランジ継手12を介して上部架台8に連結されている。また、各脚部10の下端部10aは球面状に形成され、一方、受け台9側もその受け面が球面状に形成されて、互いにボールジョイントされるようになっている。さらに、上部架台8の上面には、その四隅にそれぞれ二カ所ずつ、ジャッキベース14が備えられている。
【0027】
このような上部架台8は、二つの脚部10に備えられた昇降ジャッキ11を昇降駆動させることによって、上部架台8の水平面に対する傾斜レベルを調整できるようになっている。しかもこのとき、各脚部10の下端部10aは球面状であるので、上部架台8が傾斜しても下部架台7の受け台9上に点接触して確実に接地し、ガタつき等が発生しないようになっている。
【0028】
図1および図3に示すように、上部架台8上には、平面視ロ字状のピン架台15がセットされるようになっており、ピン架台15の各辺の中央部には、板状のピン取付ベース16が備えられている。図1および図4に示すように、各ピン取付ベース16には上方に向けて突出する位置決めピン17が着脱自在に取り付けられるようになっている。なおこの位置決めピン17は、基端部から先端部に向けてその径寸法が漸次小さくなるテーパ形状とされている。
【0029】
このピン架台15は、上部架台8の上面の各脚部10付近に備えられた板状の受けブラケット(図示なし)の上面に、摩擦低減材(図示なし)を介してセットされている。摩擦低減材としては、例えばテフロン板や、ステンレススチールあるいは銅板等にグリース材を塗布したもの等が用いられる。これにより、ピン架台15は、上部架台8上で略水平方向に移動自在にセットされている。
【0030】
そして、ピン架台15と上部架台8との間には、前記各ジャッキベース14にセットされた水平ジャッキ(芯調整手段)19が介装されている。これら計8本の水平ジャッキ19を伸長状態とすることによってピン架台15は上部架台8に一体に固定され、またこれら水平ジャッキ19を伸縮駆動させることによってピン架台15は水平方向に移動可能となっている。
【0031】
図1に示したように、上記ベース架台5に支持されるガイドパイプ4は、スタンドパイプ2よりも所定寸法小径の円筒状の鋼管からなり、その上端部の外周面には、ピン架台15よりも所定寸法大きな外形寸法を有した平面視矩形の受けプレート20が一体に設けられている。受けプレート20には、位置決めピン17に対応した所定位置にピン穴22が形成されている。各ピン穴22はガイドパイプ4の径方向に長い長穴とされ、その幅(短径)は、位置決めピン17の外径と略同寸に設定されている。そして、受けプレート20の各ピン穴22に位置決めピン17を挿入することによって、受けプレート20がピン架台15に対して水平面内で一体に固定されるようになっている。また、ピン17を通り芯軸上に配置することにより、ガイドパイプ4の位置を通り芯に適合させることができるようになっている。
【0032】
このようにして、ガイドパイプ4は、ベース架台5にその全荷重が支持され、さらにベース架台5の昇降ジャッキ11を駆動させると上部架台8と一体に動いて鉛直度が調整され、また水平ジャッキ19を駆動させるとピン架台15と一体に移動して水平面内での位置、つまり通り芯位置Lの調整がなされるようになっている。
【0033】
さらに、上記ベース架台5には、自身の水平面に対する傾斜レベルを表示するレベル表示装置(レベル表示手段)30が備えられている。
図5に示すように、レベル表示装置30は、例えば上部架台8の各脚部10(図1参照)の上端部近傍に備えられた計3台のレベル測定器31と、これらレベル測定器31を互いに連通する連通管32と、監視盤(表示器)33とから構成されている。これらレベル測定器31には、水W等の計測用媒体が所定量注入されており、水Wの水面レベルが例えば超音波等によって計測されるようになっている。そして、各レベル測定器31で計測された水面レベルは信号出力され、監視盤33において各レベル測定器31での水面レベルがインジケータ34に一括して表示されるようになっている。
【0034】
このレベル表示装置30では、連通管32によって3台のレベル測定器31が互いに連通しているので、監視盤33で表示される各レベル測定器31における水面レベルは、同一水平面に位置することとなる。つまり、レベル表示装置30では、同一水平面に対する各部(レベル測定器31を備えた3カ所)のレベルを表示するのであって、このときベース架台5自体は水平であるとは限らない。
【0035】
また、図1に示したように、前記ガイドパイプ4の内周面には、上下方向に所定長延在する二本一対のガイドレール35が一体に形成されている。これらガイドレール35に沿って、建入れるべき構真柱Cの上端部に着脱自在に取り付けられたガイド部材36が走行するようになっており、これによって構真柱Cがガイドパイプ4の通り芯位置Lに沿って建入れられるようになっている。
【0036】
次に、上記構成からなる構真柱建入れ装置1を用いた構真柱Cの建入れ工法について説明する。
まず、図6に示すように、地盤Gに、地盤Gの崩落を防止する目的としたスタンドパイプ2を建て込み、次いで掘削孔Hを略鉛直に削坑する。
【0037】
そして、図2に示したように、掘削孔Hの周縁部にベース架台5を構成する下部架台7を敷鉄板6上に設置し、さらにその上に上部架台8をセットする。
【0038】
続いて、図3に示したように、上部架台8上にピン架台15を載せた後、上部架台8の各ジャッキベース14に水平ジャッキ19をセットし、これら水平ジャッキ19を伸ばしてピン架台15の位置を固定する。
【0039】
この状態で、図4に示したように、トランシット等でピン架台15の水平方向の位置を視準し、各ピン取付ベース16上に、位置決めピン17をそれぞれ通り芯位置L上に位置するようボルト等で取り付ける。
【0040】
この後、図1に示したように、ガイドパイプ4を吊り込み、これを掘削孔H内に下ろしていき、その上端部に形成されている受けプレート20の各ピン穴22に、位置決めピン17を挿入させて嵌合させる。このときに、各位置決めピン17がテーパ状とされているので、各ピン穴22への挿入を容易かつ確実に行うことができるようになっている。これによりガイドパイプ4が通り芯位置Lに位置合わせされた状態となる。
【0041】
次いで、ガイドパイプ4の鉛直度を、例えばレーザ管(図示なし)等で計測し、傾斜している場合には、上部架台8の脚部10の昇降ジャッキ11を伸縮駆動させることによってガイドパイプ4を上部架台8と一体に傾動させ、ガイドパイプ4の鉛直を出す。そして、各位置決めピン17の位置が通り芯位置L上に位置しているか、再度トランシットで視準し、もしガイドパイプ4の傾動にともなって通り芯位置Lから水平方向にズレたときには、水平ジャッキ19を操作してピン架台15を位置修正する。
【0042】
これにより、ガイドパイプ4が、鉛直に、かつ通り芯位置L上に位置出しされた状態となるので、このときのベース架台5の傾斜レベルを前記レベル表示装置30で計測し、監視盤33に表示される各レベル測定器31の水面レベルを、ベース架台5の初期設定レベルとして記録、または初期設定レベルの状態を水平レベルとなるようレベル計を設定しておく。なお、このときのベース架台5の傾斜レベルは、あくまでもガイドパイプ4が鉛直状態であるときの傾斜レベルであるので、水平であるとは限らない。
【0043】
しかる後には、例えばコンクリート先打ち式を採用する場合、コンクリートを掘削孔Hの底部にトレミー管等で所定レベルまで打設した後、直ちに、建て込むべき構真柱Cを吊り込んでガイドパイプ4内に挿入する。
このとき、構真柱Cの上部と下部にはガイド部材36を取り付けておき、これをガイドパイプ4のガイドレール35でガイドさせることによって、構真柱Cが通り芯位置L通りに挿入されることとなる。
【0044】
このようにして構真柱Cを鉛直に建て込んでいき、その下端部がコンクリート中に挿入され、かつ天端が所定レベルに到達した時点で、この構真柱Cを図示しないジャーナルジャッキ等の仮受け材で保持する。この状態で、構真柱Cは、鉛直に、かつ所定のレベルで建て込まれた状態となっている。
【0045】
コンクリートが硬化して所定の強度が発現したら、ガイドパイプ4を吊り上げて引き抜き、ベース架台5を撤去し、構真柱Cの頭部をスタンドパイプ2に仮固定した後、掘削孔Hを埋め戻し、その後スタンドパイプ2を引き抜いて撤去することによって構真柱Cの建入れ作業が完了する。
【0046】
なお、ガイドパイプ4を鉛直かつ通り芯位置L上に位置出ししてベース架台5の初期設定レベルを記録したよりも以降において、例えば吊り込んだ構真柱Cの荷重によって地盤沈下等が生じ、ガイドパイプ4がズレたときには、ベース架台5の脚部10の昇降ジャッキ11を操作して上部架台8を傾動させ、レベル表示装置30で表示される各レベル測定器31のレベルが、前記初期設定レベルに合うよう調整する。この調整によって、ガイドパイプ4が鉛直かつ通り芯位置L上に位置修正される。
【0047】
また、引き続き、他の位置に構真柱Cを建入れるときには、上記と同様にガイドパイプ4の位置出しを行う必要がある。このときには、ベース架台5の傾斜レベルを、レベル表示装置30での表示レベルが前記初期設定レベルに合うよう昇降ジャッキ11で調整するとともに、位置決めピン17の位置を通り芯位置L上に位置するようピン架台15の位置を水平ジャッキ19で調整すればよく、ガイドパイプ4の鉛直出しをレーザー管で行う必要はない。もちろん、このときには、ガイドパイプ4とベース架台5のセット方向を統一しておく必要がある。
【0048】
上述した構真柱建入れ装置1および構真柱Cの建入れ工法では、構真柱建入れ装置1がガイドパイプ4とベース架台5とを備えて構成され、ベース架台5には、その傾斜レベルを調整する昇降ジャッキ11と、傾斜レベルを示すレベル表示装置30とが備えられた構成となっている。そして、ベース架台5とガイドパイプ4とを一体にセットした状態でガイドパイプ4の位置出しを一回行い、このときレベル表示装置30で表示されるベース架台5の傾斜レベルを記録しておき、しかる後に、ズレや他の位置への移動によってガイドパイプ4を再度位置出しする必要が生じたときには、記録した初期設定レベルに合わせてベース架台5をレベル調整する構成となっている。
したがって、最初の一回を除き、レーザ管等を用いることなくガイドパイプ4の位置出しを容易かつ確実に行うことができ、施工の迅速化を図ることが可能となる。しかもガイドパイプ4をベース架台5にセットした状態で位置出しおよび初期設定レベルの記録を行うので、ガイドパイプ4,ベース架台5自体に高い精度が要求されることもなく、これらを低コストで製作することが可能となる。
【0049】
また、レベル表示装置30が、複数のレベル測定器31と、これらを互いに連通させる連通管32と、各レベル測定器31での測定レベルを表示する監視盤33とを備えた構成となっている。
このようにレベル表示装置30は、従来使用していたレーザ管等に比較して非常に簡易な構成となっている。したがって、その準備等の作業を容易に行うことができ、より一層の施工の迅速化を図ることができ、加えて機材コストも削減することができる。
【0050】
さらに、上部架台8が三本の脚部10によって立脚した構成となっている。これにより、四本以上の脚部を備えた場合に比較して、ガタつきが生じたりすることもなく、また各脚部10で分担する荷重も均一となる。したがって、ガイドパイプ4の鉛直出しをより高精度で行うことができる。加えて、荷重のばらつきによる周囲地盤の沈下等も防止できるので、ガイドパイプ4の位置ズレ等も抑制することができる。また、レベル出しを短時間で容易に行うことが可能となる。
【0051】
しかも、各脚部10の下端部10aが略球面状をなした構成となっている。これによって上部架台8が昇降ジャッキ11の駆動により傾動したときにも、なめらかな動きを実現できる。
【0052】
また、ピン架台15と上部架台8との間、つまりガイドパイプ4とベース架台5との間に、水平ジャッキ19が備えられた構成となっている。これにより、ガイドパイプ4の通り芯位置Lがずれた場合にも調整することが可能となり、ガイドパイプ4をより容易かつ正確に位置出しすることが可能となる。
【0053】
加えて、ガイドパイプ4にはその内周面に二本一対のガイドレール35,35を形成しておき、構真柱Cにはガイドレール35,35によってガイドされるガイド部材36,36を着脱自在に装着する構成となっている。このようにして、鉛直に建て込んだガイドパイプ4のガイドレール35,35をガイドとして構真柱Cを建入れることにより、構真柱Cをスムーズに挿入することができ、また従来手間がかかっていた建入れ調整作業を廃して、先打ちしたコンクリートが凝結するまでの間に構真柱Cを容易かつ迅速に高精度で建入れることができる。しかも、ガイド部材36が着脱可能な構成となっているので、このガイド部材36を転用することにより、コストダウンを図ることができる。
【0054】
なお、上記実施の形態において、レベル表示装置30の構成については上記したもの以外であっても良い。例えば監視盤33で各レベル測定器31の測定レベルを一括して表示する構成としたが、もちろん、各レベル測定器31で表示するようにしても良い。また、用いるレベル測定器31の種類も何ら限定するものではない。
【0055】
また、昇降ジャッキ11や水平ジャッキ19を設置する場所も、上記実施の形態で示したものに限らず、他の箇所であっても良い。
【0056】
さらに、上記実施の形態において、構真柱Cを建入れるに際してコンクリートを先打ちする構成としたが、もちろん、コンクリートを後打ちする場合においても適用可能である。この場合には、ガイドパイプ4を建入れ、これに沿って構真柱Cを所定レベルまで挿入し、これを仮受け材等で保持した後、ガイドパイプ4内の所定位置にトレミー管等を建て込んで、コンクリートの打設を行えばよい。また、本発明に係る構真柱建入れ装置は、例えばこれを充填鋼管コンクリート構造とする場合には、前記に引き続いてガイドパイプ4内にコンクリートを打ち上げればよい。
【0057】
また、上記実施の形態では、ベース架台5を下部架台7と上部架台8とから構成し、上部架台8でピン架台15を設置し、このピン架台15でガイドパイプ4を支持する構成としたが、ガイドパイプ4を所定の位置に位置決めすることができるのであれば、その構造については何ら限定するものではなく、構真柱建入れ装置1に他の構造を採用しても良い。
【0058】
加えて、ガイドパイプ4で構真柱Cをガイドする構造について、ガイドレール35およびガイド部材36を用いる構成としたが、その具体的な構成については、本出願人が先に出願した特願平8−163511号の技術等を適宜採用すれば良く、もちろんこれ以外にも、他の構造を適宜用いることができる。
【0059】
これ以外にも、本発明の主旨を逸脱しない範囲内であれば、いかなる構成を採用しても良く、また上記したような構成を適宜選択的に組み合わせたものとしても良いのは言うまでもない。
【0060】
【発明の効果】
以上説明したように、請求項1に係る構真柱建入れ装置によれば、ガイドパイプと、ガイドパイプを支持する架台とを備えて構成され、架台には、その傾斜レベルを調整するレベル調整手段と、傾斜レベルを示すレベル表示手段とが備えられた構成となっている。これにより、ガイドパイプの位置出しを一度行って、そのときレベル表示手段によって示される架台の傾斜レベルを記録しておけば、再度位置修正をする場合、あるいは別の位置に構真柱建入れ装置を設置する場合に、記録した傾斜レベルに合わせてレベル調整手段で架台の傾斜レベルを調整すればよい。このように、レーザ管等を用いることなく、ガイドパイプの位置出しを容易かつ確実に行うことができるので、施工の迅速化を図ることが可能となる。しかもガイドパイプを架台にセットした状態で位置出しおよび初期設定レベルの記録を行うので、ガイドパイプおよび架台に高い精度が要求されることもなく、これらを低コストで製作することが可能となる。
【0061】
また、請求項1に係る構真柱建入れ装置によれば、レベル表示手段が、複数のレベル測定器と、各レベル測定器どうしで測定用の媒体を連通させる連通管と、各レベル測定器での測定レベルを表示する表示器とを備えた構成となっている。これにより、レベル表示手段が、従来使用していたレーザ管等に比較して非常に簡易な構成となっており、その準備等の作業を容易に行え、上記効果をより顕著なものとすることができるばかりか、工費を削減することも可能となる。
【0062】
請求項2に係る構真柱建入れ装置によれば、架台が三本の脚部によって立脚した構成となっている。これにより、脚部を四本以上備えた場合に対し、ガタつきが生じたりすることもなく、また各脚部で分担する荷重も均一となる。したがって、ガイドパイプの鉛直出しをより高速高精度で行うことができ、しかも荷重のばらつきによる周囲地盤の沈下等も防止できる。
【0063】
請求項3に係る構真柱建入れ装置によれば、脚部の下端部が略球面状をなした構成となっている。これにより、脚部の下端部とこの架台の設置面とが点接触することとなり、レベル調整手段によって架台が傾動したときにも、スムーズな調整レベル出しを実現できる。
【0064】
請求項4に係る構真柱建入れ装置によれば、ガイドパイプと架台との間に、ガイドパイプの通り芯位置を調整する芯調整手段が備えられた構成となっている。これにより、ガイドパイプの通り芯位置がずれた場合にも、芯調整手段で調整することができ、ガイドパイプをより容易かつ正確に位置出しすることが可能となる。
【図面の簡単な説明】
【図1】 本発明に係る構真柱建入れ装置の一例を示す平面図および立断面図(半断面図)である。
【図2】 構真柱建入れ工法において、架台をセットした状態を示す平面図および立断面図(半断面図)である。
【図3】 同、架台上にピン架台をセットした状態を示す平面図および立断面図(半断面図)である。
【図4】 同、ピン架台上に位置決めピンをセットした状態を示す平面図および立断面図(半断面図)である。
【図5】 同、用いるレベル表示手段の構成を示す図である。
【図6】 同、スタンドパイプを設置した状態を示す平面図および立断面図(半断面図)である。
【符号の説明】
1 構真柱建入れ装置
4 ガイドパイプ
8 上部架台(架台)
10 脚部
11 昇降ジャッキ(レベル調整手段)
19 水平ジャッキ(芯調整手段)
30 レベル表示装置(レベル表示手段)
31 レベル測定器
32 連通管
33 監視盤(表示器)
C 構真柱
H 掘削孔
L 通り芯位置[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a frame built-in column suitable for building a frame column with high accuracy in an excavation hole formed in the ground. In place Related to
[0002]
[Prior art]
Conventionally, for example, when constructing an underground part or an underground structure of a high-rise building by the reverse driving method, after forming a construction column (main steel column) with a predetermined accuracy by forming an excavation hole in the ground, Backfill the excavation hole with earth and sand using a backhoe, etc., and then attach the main steel beam to the construction column sequentially from the top to the bottom, while rooting the ground as construction progresses Yes.
[0003]
In order to install such a structural pillar, it is necessary to solidify at least the lower end of the structural pillar with concrete in a state where the position on the plane (core position), the verticality, and the vertical level are maintained accurately. Therefore, for example, by setting a cylindrical stand pipe substantially vertically at the peripheral edge of the excavation hole, attaching a jack etc. to the side of the stem pillar, expanding and contracting it horizontally, and taking the reaction force on the stand pipe Construction methods that adjust the verticality of the structural pillar have been developed.
[0004]
By the way, when erected pillars are erected, the concrete post-placement type in which concrete is struck after the erection pillar is erected in the excavation hole and the erection pillar is erected after the concrete is erected in the excavation hole. There is a concrete pre-casting type. Among these, in the concrete post-casting type, a tremey tube for placing concrete must be inserted into a narrow space after the construction column is inserted, which takes time and effort. On the other hand, although such a problem does not occur in the concrete pre-casting type, it is needless to say that it is necessary to complete the construction adjustment of the structural pillar before the pre-cast concrete is cured. However, in the above construction method, adjusting the verticality of the structural pillar using a jack or the like takes time, and thus is not suitable for the concrete pre-coating method.
[0005]
Moreover, in the above construction method, it is necessary to prepare a bracket or the like for attaching a jack in accordance with the size of the structural pillar to be built, and this also has a problem that it takes time and cost.
[0006]
In order to solve this problem, the present applicant built a guide pipe with a guide rail on the inner peripheral surface in a vertical manner, and built a vertical column in the excavation hole along the guide rail. An application for an apparatus and a construction method have already been filed (Japanese Patent Application No. 8-163511).
[0007]
[Problems to be solved by the invention]
However, even the techniques proposed by the present applicant as described above still have the following problems.
The guide pipe and the gantry supporting the guide pipe are not manufactured by machining such as cutting, and cannot require high accuracy. Therefore, even if the gantry is leveled with the gantry installed at the peripheral edge of the excavation hole, the vertical does not always come out when the guide pipe is set after that. Therefore, with the guide pipe set on the gantry, The guide pipe must be placed vertically. In addition, since the structural pillar is installed at another position, it is necessary to position the guide pipe every time the guide pipe and the gantry are moved.
Further, a device such as a laser tube has to be used for the vertical extraction of the guide pipe, which requires time and effort for preparation and measurement, and there is room for further improvement.
[0008]
Moreover, if the guide pipe level is shifted due to ground subsidence, etc., it goes without saying that it will take time to correct the position again, and if the guide pipe's center position shifts, the position of the guide pipe will be corrected horizontally. The correction is very difficult because there is no means to do so.
[0009]
The present invention has been made in consideration of the above points, and a built-in column that can easily be installed and corrected during subsidence. Place The issue is to provide.
[0010]
[Means for Solving the Problems]
The invention according to
[0011]
As a result, the guide pipe is positioned once, and the tilt level of the gantry indicated by the level display means is recorded at that time, and when positioning is performed again, the level adjusting means matches the recorded tilt level. What is necessary is just to adjust the inclination level of a mount frame. In this way, once positioning is performed, the guide pipe is positioned only by adjusting to the inclination level indicated by the level display means without using a laser tube or the like even if the position of the guide pipe is shifted. be able to.
When positioning is performed for the first time and when positioning is performed again, the inclination level of the gantry is not adjusted to be horizontal, but the guide pipe is set to be vertical. Therefore, the inclination level displayed by the level display means displays the inclination level of the gantry when the guide pipe is vertical.
[0013]
in addition In each level measuring device, the liquid level of the medium becomes equal, that is, it is possible to know the levels at a plurality of locations with respect to the same horizontal plane. Further, such a level display means has a very simple configuration as compared with a conventionally used laser tube or the like.
[0014]
[0015]
Thereby, with respect to the case where four or more leg portions are provided, there is no backlash and the load shared by each leg portion is uniform. Also, since it has three legs, leveling is easy.
[0016]
Claim 3 The invention according to
[0017]
Thereby, the lower end part of a leg part and the installation surface of this mount will be in point contact, and rattling etc. can be prevented.
[0018]
[0019]
Thereby, even when the lead position of the guide pipe is shifted, it can be adjusted by the lead adjusting means.
[0022]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the erected pillar construction according to the present invention Set An example of the embodiment will be described with reference to FIGS.
In these drawings, reference numeral C is a structural pillar, G is the ground, H is an excavation hole formed in the ground G for the construction of the structural pillar C, and 1 is for constructing the structural pillar C with a predetermined accuracy. The structural
[0023]
As shown in FIG. 1, the erected
[0024]
As shown in FIGS. 1 and 2, the
[0025]
The
[0026]
The
[0027]
Such an
[0028]
As shown in FIGS. 1 and 3, a
[0029]
The
[0030]
A horizontal jack (core adjusting means) 19 set on each
[0031]
As shown in FIG. 1, the
[0032]
In this way, the
[0033]
Further, the
As shown in FIG. 5, the
[0034]
In this
[0035]
As shown in FIG. 1, a pair of two
[0036]
Next, the construction method of the construction pillar C using the construction
First, as shown in FIG. 6, the
[0037]
Then, as shown in FIG. 2, the
[0038]
Subsequently, as shown in FIG. 3, after the
[0039]
In this state, as shown in FIG. 4, the horizontal position of the
[0040]
Thereafter, as shown in FIG. 1, the
[0041]
Next, the vertical degree of the
[0042]
As a result, the
[0043]
After that, for example, when adopting a concrete pre-casting type, after placing concrete to a predetermined level with a tremmy pipe or the like at the bottom of the excavation hole H, the
At this time,
[0044]
In this way, when the true pillar C is vertically built, the lower end thereof is inserted into the concrete, and when the top end reaches a predetermined level, the true pillar C is not shown in a journal jack or the like. Hold with temporary support. In this state, the true pillar C is vertically built at a predetermined level.
[0045]
When the concrete has hardened and a predetermined strength is developed, the
[0046]
In addition, after the
[0047]
Further, when the erected column C is subsequently erected at another position, it is necessary to position the
[0048]
In the above-described construction method of the structural
Therefore, except for the first time, the
[0049]
In addition, the
Thus, the
[0050]
Further, the
[0051]
Moreover, the
[0052]
Further, a
[0053]
In addition, the
[0054]
In the above embodiment, the configuration of the
[0055]
Further, the place where the lifting
[0056]
Furthermore, in the above-described embodiment, the construction is such that the concrete is preliminarily placed when the structural pillar C is erected, but of course, the present invention can also be applied to the case where concrete is post-placed. In this case, the
[0057]
In the above embodiment, the
[0058]
In addition, the structure in which the
[0059]
In addition to this, it is needless to say that any configuration may be adopted as long as it does not depart from the gist of the present invention, and the above-described configurations may be appropriately combined.
[0060]
【The invention's effect】
As described above, according to the frame pillar erection device according to
[0061]
Also,
[0062]
[0063]
Claim 3 According to the erected column erection device according to the present invention, the lower end portion of the leg portion has a substantially spherical shape. As a result, the lower end of the leg and the installation surface of the pedestal come into point contact, and even when the pedestal is tilted by the level adjusting means, smooth adjustment leveling can be realized.
[0064]
[Brief description of the drawings]
BRIEF DESCRIPTION OF THE DRAWINGS FIG. Set It is the top view and elevation sectional view (half sectional view) which show an example.
[Figure 2] Structure In a true pillar construction method, it is the top view and standing sectional view (half sectional view) which show the state which set the mount frame.
FIG. 3 is a plan view and an elevational sectional view (half-sectional view) showing a state where the pin mount is set on the mount.
FIG. 4 is a plan view and an elevational sectional view (half sectional view) showing a state where a positioning pin is set on the pin mount.
FIG. 5 is a diagram showing the configuration of level display means used.
FIG. 6 is a plan view and an elevational sectional view (half sectional view) showing a state where a stand pipe is installed.
[Explanation of symbols]
1 Construction pillar erection device
4 Guide pipe
8 Upper frame (frame)
10 legs
11 Lifting jack (level adjustment means)
19 Horizontal jack (core adjustment means)
30 level display device (level display means)
31 level measuring instrument
32 communication pipe
33 Monitoring panel (display)
C
H Drilling hole
L Street core position
Claims (4)
前記構真柱を建入れるときにこれをガイドする筒状のガイドパイプと、
前記掘削孔の周縁の地表面に設置されて前記ガイドパイプを支持する架台と、を備えて構成され、
前記架台には、該架台の水平面に対する傾斜レベルを調整するレベル調整手段と、前記架台の傾斜レベルを示すレベル表示手段とが備えられ、
前記レベル表示手段が、前記架台の複数箇所にそれぞれ設置されたレベル測定器と、これらのレベル測定器間に設けられて前記各レベル測定器で傾斜レベルを測定するための液体等の媒体を互いに連通させる連通管と、前記各レベル測定器での測定レベルを表示する表示器とを備えて構成されていることを特徴とする構真柱建入れ装置。A device for erected a pillar in a borehole formed in the ground,
A cylindrical guide pipe that guides the construction pillar when installing it,
A pedestal installed on the ground surface at the periphery of the excavation hole and supporting the guide pipe,
The gantry includes level adjusting means for adjusting an inclination level of the gantry with respect to a horizontal plane, and level display means for indicating an inclination level of the gantry ,
The level display means includes a level measuring device installed at each of a plurality of locations of the gantry, and a medium such as a liquid provided between the level measuring devices for measuring an inclination level by the level measuring devices. A constructional column erection device comprising a communication pipe for communication and a display for displaying a measurement level of each level measuring device.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16740998A JP3750042B2 (en) | 1998-06-15 | 1998-06-15 | Construction pillar erection device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16740998A JP3750042B2 (en) | 1998-06-15 | 1998-06-15 | Construction pillar erection device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2000001854A JP2000001854A (en) | 2000-01-07 |
| JP3750042B2 true JP3750042B2 (en) | 2006-03-01 |
Family
ID=15849169
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16740998A Expired - Fee Related JP3750042B2 (en) | 1998-06-15 | 1998-06-15 | Construction pillar erection device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3750042B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE102004038369B4 (en) * | 2004-08-06 | 2018-04-05 | Austriamicrosystems Ag | High-voltage NMOS transistor and manufacturing process |
| CN102767182B (en) * | 2012-07-18 | 2015-01-07 | 上海建工二建集团有限公司 | Verticality adjustment system for lattice column correcting mount and construction method thereof |
| CN104110035A (en) * | 2013-04-16 | 2014-10-22 | 中冶天工上海十三冶建设有限公司 | Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device |
| JP7181069B2 (en) * | 2018-12-05 | 2022-11-30 | 株式会社フジタ | Reversed strut positioning jig |
| CN114319439B (en) * | 2022-02-16 | 2023-12-22 | 广西珠委南宁勘测设计院有限公司 | Geotechnical engineering positioning and supporting device |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62133255A (en) * | 1985-12-03 | 1987-06-16 | 清水建設株式会社 | Steel column erection method and equipment |
| JP3366927B2 (en) * | 1993-10-14 | 2003-01-14 | 株式会社竹中工務店 | Centering jig for building a vertical column |
| JP3030377B2 (en) * | 1995-02-01 | 2000-04-10 | 日特建設株式会社 | Construction and repair equipment for trussed pillars |
| JPH09125391A (en) * | 1995-11-02 | 1997-05-13 | Shimizu Corp | Construction method of structure pillar and jig used for it |
| JP2764573B2 (en) * | 1996-04-25 | 1998-06-11 | 長野油機株式会社 | A device that embeds a cylindrical casing in the ground |
-
1998
- 1998-06-15 JP JP16740998A patent/JP3750042B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2000001854A (en) | 2000-01-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104264902B (en) | Steel pipe concrete column and pile foundation connection structure | |
| CN114277803B (en) | Post-insertion method positioning construction method for reverse construction method steel pipe structural column | |
| CN104631338A (en) | Steel boxed cofferdam and positioning construction method | |
| US7484913B2 (en) | Placing elements in piles | |
| KR101436119B1 (en) | Holding apparatus for CFT column and the construction method of the CFT column using it | |
| JP3750042B2 (en) | Construction pillar erection device | |
| CN114277802B (en) | Post-insertion method positioning construction structure for reverse construction method steel pipe structural column | |
| JP2019131990A (en) | Permanent sub-structural column erection method and permanent sub-structural column erection apparatus | |
| CN111945714A (en) | Steel sleeve guiding method combined with steel upright column inserting construction method | |
| JP3030377B2 (en) | Construction and repair equipment for trussed pillars | |
| CN116905726A (en) | Reverse construction method steel pipe column installation method | |
| CN108179749B (en) | Lattice column positioner and positioning method thereof | |
| JP3616895B2 (en) | Construction pillar erection device | |
| JP2747566B2 (en) | Construction method of straight pillar | |
| CN117449611B (en) | Measurement and installation method for large-diameter long-inclined embedded bolt and angle adjusting device | |
| JP2556215B2 (en) | Construction method | |
| CN217150251U (en) | Digital verticality adjusting system for reverse steel stand column | |
| CN216194782U (en) | A steel pipe column positioning system | |
| JPH0531631B2 (en) | ||
| CN114541374A (en) | A kind of pre-embedded steel column vertical adjustment system and construction method thereof | |
| CN115961622A (en) | Pile foundation steel column positioning and verticality adjusting device and construction method thereof | |
| JPH04281916A (en) | Frame device for constructing structural pillars | |
| CN117266241B (en) | Reverse construction method for lattice columns | |
| JPH07122273B2 (en) | Structure pillar built-in stand | |
| JP3030374B2 (en) | Construction method and equipment for trussed pillar |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050705 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050815 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20051101 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20051122 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111216 Year of fee payment: 6 |
|
| LAPS | Cancellation because of no payment of annual fees |