JP3760010B2 - Arch culvert construction method - Google Patents
[go: Go Back, main page]

JP3760010B2 - Arch culvert construction method - Google Patents

Arch culvert construction method Download PDF

Info

Publication number
JP3760010B2
JP3760010B2 JP33314796A JP33314796A JP3760010B2 JP 3760010 B2 JP3760010 B2 JP 3760010B2 JP 33314796 A JP33314796 A JP 33314796A JP 33314796 A JP33314796 A JP 33314796A JP 3760010 B2 JP3760010 B2 JP 3760010B2
Authority
JP
Japan
Prior art keywords
concrete
waterproof sheet
sheet
arch
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP33314796A
Other languages
Japanese (ja)
Other versions
JPH10159073A (en
Inventor
英太郎 吉富
実 菊地
光雄 望月
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP33314796A priority Critical patent/JP3760010B2/en
Publication of JPH10159073A publication Critical patent/JPH10159073A/en
Application granted granted Critical
Publication of JP3760010B2 publication Critical patent/JP3760010B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、地中に埋設されて水路等の用途に使用されるアーチカルバートの施工技術に関するものである。
【0002】
【従来の技術】
アーチカルバートは、上部断面がアーチ状を呈するコンクリート製の管渠であって、従来この種のアーチカルバートは、地盤上にベースコンクリートを施工してから、その上に型枠をアーチ状に組み立てて、この型枠内にコンクリートを打設することによって施工される。また、アーチカルバートは周囲の地盤に対して防水対策が必要であるため、打設したコンクリートが硬化して所定の強度が発現されたら型枠を解体・撤去し、このコンクリート(アーチ状躯体コンクリート)の外側に防水工事のための仮設足場を組み立て、この足場を利用して、前記アーチ状躯体コンクリートの外周面に防水シートを敷設して定着させるか、アスファルト等で被覆することによって防水工事を施す。防水工事が終わったら、前記仮設足場を撤去し、前記アーチ状躯体コンクリートの上に土材を埋め戻しもしくは盛り立てる。
【0003】
【発明が解決しようとする課題】
上記従来工法によれば、アーチ状躯体コンクリートの外周に防水工事を施すため、次のような問題が指摘される。
(1) アーチ状躯体コンクリートが、打設後の所要の養生期間を経て硬化するのを待ってから防水工事を行わなければならない。
(2) アーチ状躯体コンクリートの外側に防水工事用の仮設足場を組み立てなければならず、また防水工事終了後はこの仮設足場を解体・撤去しなければならないため、施工が煩雑で時間がかかる。
【0004】
本発明は、上記のような事情のもとになされたもので、その技術的課題とするところは、アーチカルバートの施工において、打設したアーチ状躯体コンクリートの硬化を待つことなく防水工事を行うことができ、かつ防水工事のための足場組立や撤去作業を不要とすることによって、工期の短縮を図ることにある。
【0005】
【課題を解決するための手段】
上述した技術的課題を有効に解決するため、本発明に係るアーチカルバートの施工方法においては、まずベースコンクリートを施工したらその上に可撓性シートからなる躯体成形用シートを敷設してその周縁部をベースコンクリートに固定し、更にその上に防水シートを敷設し、前記ベースコンクリートと躯体成形用シートの間に形成された密閉空間に空気圧を印加する。これによって前記躯体成形用シートは、前記防水シートと共にアーチ状に膨らんだ状態で前記空気圧により支保される。次に、前記防水シートの外周に沿ったアーチ状のコンクリート打設領域に鉄筋や金網等の補強筋を配設してから、前記コンクリート打設領域にコンクリートを吹き付けて打設することによって、前記ベースコンクリート及び防水シートを一体化したアーチ状躯体コンクリートを形成し、その外側を土材で埋めるものである。
【0006】
すなわち本発明によれば、アーチ状躯体コンクリートを形成するための型枠として、空気圧によってアーチ状に膨らませて支保する躯体成形用シートを用い、この躯体成形用シートをアーチ状に膨らませて型枠を形成する前に防水シートを敷設することができるので、防水シート施工のための作業足場は不要である。また、防水シートは、その外周にコンクリートを吹き付けることによって形成されるアーチ状躯体コンクリートと一体接合状態となるものであるため、アーチ状躯体コンクリートの打設とその防水工事が同時に行われることになる。なお、アーチ状躯体コンクリートの硬化後は、前記空気圧を解除すれば、躯体成形用シートを容易に脱型することができる。
【0007】
本発明において、防水シートには、その外周面に予め所定間隔で多数のアンカーを突設しておくことが好ましい。このアンカーは、打設されたコンクリートに埋設状態となることによって、前記防水シートをアーチ状躯体コンクリートの内周面にしっかり定着することができる。
【0008】
【発明の実施の形態】
以下、本発明に係るアーチカルバートの施工方法の好適な一実施形態を、図1乃至図4を参照しながら説明する。まず図1は、本実施形態によるアーチカルバートの施工過程を示すもので、すなわちこのアーチカルバート10は、ベースコンクリート11と、その上に一体に形成されたアーチ状躯体コンクリート12と、このアーチ状躯体コンクリート12の内周面に接合された防水シート13とを有し、アーチ状躯体コンクリート12には金網及び鉄筋等の内側補強筋15及び外側補強筋16が埋設されている。
【0009】
上記アーチカルバート10の施工においては、まず、その施工方向(図1の断面と直交する方向)に延びる溝状に掘削した地盤G上に、既知の方法によって平坦なベースコンクリート11を打設する。そしてこのベースコンクリート11が硬化したら、その上に、図2に示すように、引っ張り強度が大きくかつ可撓性を有する高分子材料等からなる躯体成形用シート1を敷設し、更にその上に水密性を有する高分子材料等からなる防水シート13を敷設し、前記躯体成形用シート1の周縁及び防水シート13の周縁1a,13aを、ベースコンクリート11の上面の幅方向両端部に固定する。
【0010】
躯体成形用シート1は、空気圧の導入によってかまぼこ形に膨らむように成形されている。また、防水シート13は前記躯体成形用シート1の円周方向の面を展開した大きさを有するものであって、図3にも示すように、その外側面に多数のフック14が一定間隔で突設されている。フック14は金属製として、その基部14aを防水シート13に埋設一体化したものなどが考えられる。
【0011】
躯体成形用シート1の周縁1a(及び防水シート13の周縁13a)をベースコンクリート11に固定する方法としては、ベースコンクリート11の打設の際に、その上面部における躯体成形用シート1の固定位置に沿って、所定間隔でアンカーボルト2を植設しておき、予めボルト挿通用の穴を開設した棒状の木材3を介して、前記アンカーボルト2に螺合するナット4により緊結する。このようにすれば、躯体成形用シート1の周縁1a(又は防水シート13の周縁13a)は前記木材3によって全面がベースコンクリート11の上面に押し付けられ、密接状態に固定される。
【0012】
なお、図2における参照符号17,18は、ベースコンクリート11に埋設した鉄筋の一部をアーチ状躯体コンクリート12の立ち上がり部を形成する施工領域へ向けて突出させ、図1に示す内側補強筋15及び外側補強筋16と連結するための鉄筋継手部である。
【0013】
上述のようにして躯体成形用シート1及び防水シート13を敷設したら、図2に示すベースコンクリート11と躯体成形用シート1との間に形成された密閉空間Sに多量の空気を圧入することによって空気圧Pを印加する。これによって図4に示すように、躯体成形用シート1はその外側の防水シート13と共にアーチ状に膨らんで行く。そして躯体成形用シート1及び防水シート13が完全に膨らんだ後も前記密閉空間Sを所定の高圧状態に維持することによって、前記アーチ形状に支保する。
【0014】
防水シート13の外周には、金網あるいは鉄筋等による内側補強筋15を配設する。このとき、防水シート13の外周面に突設された多数のフック14が一種のスペーサとして機能し、このため、前記内側補強筋15は防水シート13の外周面から適当に浮上した位置に配設される。また、前記内側補強筋15の両端は、図2に示す内側の鉄筋継手部17に溶接等によって固定する。
【0015】
内側補強筋15の配設が終了したら、防水シート13の外周面に、図4に一点鎖線で示す領域zまで、図示されていない吹き付け機を用いてコンクリートを均一に吹き付ける。このとき、防水シート13から突出している多数のフック14及び前記内側補強筋15が、防水シート13の外周面に付着したコンリートに適当な流動抵抗を与える。かまぼこ形に膨らんだ躯体成形用シート1は、防水シート13を介してアーチ状躯体コンクリート12の内面を成形する型枠として機能するものであり、このため、防水シート13の外周面に吹き付けられたコンクリートはアーチ状に保持された状態で経時的に硬化して行く。また、防水シート13の外周面は、コンクリートが硬化して行くのに伴ってこのコンクリートに接合され、しかもコンクリート中に埋設状態となったフック14がアンカーとして機能するので、防水シート13がしっかり保持される。
【0016】
前記領域zへのコンクリート打設が終了したら、更にその外周に外側補強筋16を配設し、その両端を図2に示す外側の鉄筋継手部18に溶接等によって固定し、その後コンクリートの吹き付けを再開し、最終的な打設厚さ(例えば40〜50mm程度)となる領域まで打設する。これによって、図5(A)(B)に示すように、内側補強筋15及び外側補強筋16が埋設され、内周面の全面に防水シート13が一体的に接合され、両側の立ち上がり部12aがベースコンクリート11の幅方向両側の上面に一体的に接合されたアーチ状躯体コンクリート12が形成される。
【0017】
アーチ状躯体コンクリート12が硬化して所要の強度が発現されたら、ベースコンクリート11と躯体成形用シート1との間の密閉空間Sへの圧縮空気供給を停止し、この密閉空間Sを大気開放する。これによって、躯体成形用シート1は空気圧Pによる支保力が解除され、しかもアーチ状躯体コンクリート12の内面と接触状態にはないことから、防水シート13の内周面から容易に脱型することができる。脱型された躯体成形用シート1は、次の施工区間でのアーチ状躯体コンクリート12の施工に転用される。
【0018】
上述の一連の工程によって、図1に示すようなアーチカルバート10が構築されたら、その外側に一点鎖線で示す高さまで土材G’を埋め戻す。この土材G’の埋め戻しは、25〜30cm程度の層厚で撒き出し、転圧して締め固めるといった作業の繰り返しによって行われる。
【0019】
なお、上記実施形態では補強筋を内側及び外側の二層としたが、これは当然ながら限定されるものではなく、アーチ状躯体コンクリート12の肉厚等に応じて適宜に決定される。また、フック14やその他の細部の構造等も、図示のものには特に限定されない。
【0020】
【発明の効果】
本発明によると、次のような効果が実現される。
(1) アーチ状躯体コンクリートの打設と、防水シートの敷設による防水工事が同時に行われるので工期が短縮される。
(2) 防水工事のための仮設足場の組み立て作業や、その解体・撤去作業が不要である。
(3) アーチ状躯体コンクリートの打設のための型枠として、空気圧でアーチ状に膨らませる躯体成形用シートを用いるため、多数の部材による型枠組み立てや解体等の作業が不要である。
(4) 防水シートがアーチ状躯体コンクリートの内周に設けられるため、外周側に防水を施す場合に比較して耐久性が良い。
【図面の簡単な説明】
【図1】本発明に係るアーチカルバートの施工方法の一実施形態によるアーチカルバートの施工過程を示す説明図である。
【図2】上記実施形態における躯体成形用シート及び防水シートの固定構造を示す説明図である。
【図3】上記実施形態において使用する防水シートの部分的な平面図である。
【図4】上記実施形態において躯体成形用シート及び防水シートを空気圧で膨らませた状態を示す部分的な断面図である。
【図5】図1におけるA部及びB部を拡大して示す断面図である。
【符号の説明】
1 躯体成形用シート
10 アーチカルバート
11 ベースコンクリート
12 アーチ状躯体コンクリート
13 防水シート
14 フック(アンカー)
15 内側補強筋
16 外側補強筋
S 密閉空間
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an arch culvert construction technique that is buried in the ground and used for applications such as waterways.
[0002]
[Prior art]
An arch culvert is a concrete pipe with an arched upper section. Conventionally, this type of arch culvert is constructed by laying a base concrete on the ground and then assembling a formwork on it. It is constructed by placing concrete in this formwork. Also, since the arch culvert needs to be waterproofed against the surrounding ground, when the cast concrete hardens and exhibits the specified strength, the formwork is dismantled and removed, and this concrete (arch-shaped concrete) Assemble a temporary scaffold for waterproofing work on the outside of the arch, and use this scaffold to lay and fix a waterproof sheet on the outer peripheral surface of the arch-shaped concrete, or to apply waterproof work by covering with asphalt or the like . When the waterproofing work is finished, the temporary scaffold is removed, and a soil material is backfilled or raised on the arched concrete.
[0003]
[Problems to be solved by the invention]
According to the above conventional method, the following problems are pointed out because waterproofing work is performed on the outer periphery of the arched concrete.
(1) It is necessary to wait for the arched concrete to harden after the required curing period after placing, before waterproofing.
(2) Temporary scaffolding for waterproofing work must be assembled on the outside of the arch-shaped concrete frame, and after the waterproofing work is completed, the temporary scaffolding must be dismantled and removed.
[0004]
The present invention has been made under the circumstances as described above, and the technical problem is that in the construction of the arch culvert, the waterproof construction is performed without waiting for the setting of the arched skeleton-like concrete to be cured. The construction period can be shortened by eliminating the need for scaffold assembly and removal work for waterproofing.
[0005]
[Means for Solving the Problems]
In order to effectively solve the above technical problem, in the construction method of the arch culvert according to the present invention, first, after constructing the base concrete, a frame forming sheet made of a flexible sheet is laid on the base concrete and the peripheral portion thereof. Is fixed to the base concrete, and a waterproof sheet is further laid thereon, and air pressure is applied to the sealed space formed between the base concrete and the casing forming sheet. As a result, the casing forming sheet is supported by the air pressure in a state of bulging together with the waterproof sheet. Next, after arranging reinforcing bars such as reinforcing bars and wire nets in the arch-shaped concrete placement region along the outer periphery of the waterproof sheet, by blowing concrete into the concrete placement region, An arch-shaped frame concrete in which base concrete and a waterproof sheet are integrated is formed, and the outside thereof is filled with a soil material.
[0006]
That is, according to the present invention, as a mold for forming the arch-shaped frame concrete, a frame-forming sheet that is inflated and supported by an air pressure is used, and the frame-forming sheet is expanded in an arch shape. Since the waterproof sheet can be laid before forming, a work scaffold for the waterproof sheet construction is unnecessary. Moreover, since the waterproof sheet is in an integrally joined state with the arch-shaped skeleton concrete formed by spraying concrete on the outer periphery thereof, the placement of the arch-shaped skeleton concrete and its waterproofing work are performed simultaneously. . In addition, after hardening of the arch-shaped frame concrete, if the said air pressure is cancelled | released, the sheet | seat for frame forming can be easily demolded.
[0007]
In the present invention, it is preferable that a large number of anchors protrude in advance on the outer peripheral surface of the waterproof sheet at predetermined intervals. When this anchor is buried in the cast concrete, the waterproof sheet can be firmly fixed to the inner peripheral surface of the arched concrete.
[0008]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, a preferred embodiment of an arch culvert construction method according to the present invention will be described with reference to FIGS. 1 to 4. First, FIG. 1 shows a construction process of an arch culvert according to the present embodiment, that is, the arch culvert 10 is composed of a base concrete 11, an arch-shaped concrete concrete 12 integrally formed thereon, and the arch-shaped concrete. A waterproof sheet 13 joined to the inner peripheral surface of the concrete 12 is provided, and the arch-shaped frame concrete 12 is embedded with an inner reinforcing bar 15 and an outer reinforcing bar 16 such as a wire mesh and a reinforcing bar.
[0009]
In the construction of the arch culvert 10, first, a flat base concrete 11 is placed on a ground G excavated in a groove shape extending in the construction direction (direction orthogonal to the cross section of FIG. 1) by a known method. When the base concrete 11 is cured, as shown in FIG. 2, a casing forming sheet 1 made of a polymer material having a high tensile strength and a high flexibility is laid on the base concrete 11 and further watertight. A waterproof sheet 13 made of a polymer material having properties is laid, and the peripheral edge of the casing forming sheet 1 and the peripheral edges 1a and 13a of the waterproof sheet 13 are fixed to both ends in the width direction of the upper surface of the base concrete 11.
[0010]
The casing forming sheet 1 is formed so as to swell in a kamaboko shape by introducing air pressure. Further, the waterproof sheet 13 has a size obtained by developing the circumferential surface of the casing molding sheet 1, and as shown in FIG. Projected. The hook 14 may be made of metal, and the base portion 14a may be embedded in the waterproof sheet 13 and integrated.
[0011]
As a method of fixing the peripheral edge 1a of the casing forming sheet 1 (and the peripheral edge 13a of the waterproof sheet 13) to the base concrete 11, when the base concrete 11 is placed, the fixing position of the casing forming sheet 1 on the upper surface portion thereof. The anchor bolts 2 are planted at predetermined intervals, and are fastened by nuts 4 that are screwed into the anchor bolts 2 through a rod-like wood 3 in which holes for inserting bolts are previously opened. In this way, the entire periphery of the peripheral edge 1a of the casing-forming sheet 1 (or the peripheral edge 13a of the waterproof sheet 13) is pressed against the upper surface of the base concrete 11 by the wood 3 and fixed in close contact.
[0012]
Note that reference numerals 17 and 18 in FIG. 2 project a part of the reinforcing bars embedded in the base concrete 11 toward the construction area where the rising portions of the arch-shaped frame concrete 12 are formed, and the inner reinforcing bars 15 shown in FIG. And a reinforcing bar joint for connecting to the outer reinforcing bar 16.
[0013]
When the casing forming sheet 1 and the waterproof sheet 13 are laid as described above, a large amount of air is press-fitted into the sealed space S formed between the base concrete 11 and the casing forming sheet 1 shown in FIG. Air pressure P is applied. As a result, as shown in FIG. 4, the casing-forming sheet 1 swells in an arch shape together with the outer waterproof sheet 13. And even after the casing forming sheet 1 and the waterproof sheet 13 are completely inflated, the sealed space S is maintained in a predetermined high pressure state, thereby supporting the arch shape.
[0014]
On the outer periphery of the waterproof sheet 13, inner reinforcing bars 15 such as a wire mesh or a reinforcing bar are disposed. At this time, a large number of hooks 14 projecting from the outer peripheral surface of the waterproof sheet 13 function as a kind of spacer, and therefore, the inner reinforcing bars 15 are disposed at positions appropriately floating from the outer peripheral surface of the waterproof sheet 13. Is done. Further, both ends of the inner reinforcing bar 15 are fixed to the inner reinforcing bar joint portion 17 shown in FIG. 2 by welding or the like.
[0015]
When the inner reinforcing bars 15 are disposed, the concrete is uniformly sprayed onto the outer peripheral surface of the waterproof sheet 13 using a sprayer (not shown) up to a region z indicated by a one-dot chain line in FIG. At this time, the numerous hooks 14 protruding from the waterproof sheet 13 and the inner reinforcing bars 15 provide appropriate flow resistance to the concrete attached to the outer peripheral surface of the waterproof sheet 13. The casing-forming sheet 1 swelled in a kamaboko shape functions as a mold for molding the inner surface of the arch-shaped casing concrete 12 via the waterproof sheet 13, and is thus sprayed on the outer peripheral surface of the waterproof sheet 13. The concrete hardens over time while being held in an arch shape. Further, the outer peripheral surface of the waterproof sheet 13 is joined to the concrete as the concrete hardens, and the hook 14 embedded in the concrete functions as an anchor, so the waterproof sheet 13 is firmly held. Is done.
[0016]
When the placement of the concrete in the region z is completed, the outer reinforcing bars 16 are further arranged on the outer periphery, and both ends thereof are fixed to the outer reinforcing bar joint portion 18 shown in FIG. 2 by welding or the like, and then the concrete is sprayed. The process is resumed, and the casting is performed up to the final casting thickness (for example, about 40 to 50 mm). As a result, as shown in FIGS. 5A and 5B, the inner reinforcing bars 15 and the outer reinforcing bars 16 are embedded, and the waterproof sheet 13 is integrally joined to the entire inner peripheral surface, so that the rising portions 12a on both sides. The arched concrete body 12 is integrally joined to the upper surfaces on both sides in the width direction of the base concrete 11.
[0017]
When the arch-shaped frame concrete 12 is hardened and a required strength is expressed, the supply of compressed air to the sealed space S between the base concrete 11 and the frame forming sheet 1 is stopped, and the sealed space S is opened to the atmosphere. . As a result, the supporting force by the air pressure P is released from the casing forming sheet 1 and is not in contact with the inner surface of the arch-shaped casing concrete 12, so that it can be easily removed from the inner peripheral surface of the waterproof sheet 13. it can. The demolded frame-forming sheet 1 is diverted to the construction of the arch-shaped frame concrete 12 in the next construction section.
[0018]
When the arch culvert 10 as shown in FIG. 1 is constructed by the above-described series of steps, the earth material G ′ is backfilled to the height indicated by the alternate long and short dash line. This backfilling of the earth material G ′ is performed by repeating operations such as rolling out with a layer thickness of about 25 to 30 cm, rolling and compacting.
[0019]
In the above-described embodiment, the reinforcing bars are two layers of the inner side and the outer side. However, this is not limited naturally, and is appropriately determined according to the thickness of the arched concrete body 12. Further, the structure of the hook 14 and other details is not particularly limited to the illustrated one.
[0020]
【The invention's effect】
According to the present invention, the following effects are realized.
(1) The construction period will be shortened because the construction of the arched concrete and the waterproofing work by laying the waterproof sheet are performed at the same time.
(2) There is no need to assemble a temporary scaffold for waterproofing work or to dismantle and remove it.
(3) Since a frame forming sheet that is inflated into an arch shape by air pressure is used as a mold for placing the arch-shaped frame concrete, work such as assembling and dismantling the mold using a large number of members is unnecessary.
(4) Since the waterproof sheet is provided on the inner periphery of the arched concrete, durability is better than when waterproofing is applied to the outer peripheral side.
[Brief description of the drawings]
FIG. 1 is an explanatory view showing an arch culvert construction process according to an embodiment of an arch culvert construction method according to the present invention;
FIG. 2 is an explanatory view showing a fixing structure for a casing forming sheet and a waterproof sheet in the embodiment.
FIG. 3 is a partial plan view of a waterproof sheet used in the embodiment.
FIG. 4 is a partial cross-sectional view showing a state in which the casing forming sheet and the waterproof sheet are inflated with air pressure in the embodiment.
5 is an enlarged cross-sectional view showing a portion A and a portion B in FIG. 1. FIG.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Sheet | seat for frame forming 10 Arch culvert 11 Base concrete 12 Arch-shaped frame concrete 13 Waterproof sheet 14 Hook (anchor)
15 Inner reinforcement 16 Outer reinforcement S Sealed space

Claims (2)

ベースコンクリートの上に可撓性を有する躯体成形用シートを敷設してその周縁部を前記ベースコンクリートに固定する工程と、
前記躯体成形用シートの上に防水シートを敷設する工程と、
前記ベースコンクリートと躯体成形用シートとの間に形成された密閉空間に空気圧を印加することよって前記躯体成形用シートを前記防水シートと共にアーチ状に膨らませて支保する工程と、
前記防水シートの外周に沿ったコンクリート打設領域に補強筋を配設する工程と、
前記コンクリート打設領域にコンクリートを吹き付けて前記ベースコンクリート、補強筋及び防水シートと一体のアーチ状躯体コンクリートを形成する工程と、
硬化した前記アーチ状躯体コンクリートの外側に土材を埋め戻す工程と、
からなることを特徴とするアーチカルバートの施工方法。
Laying a flexible casing-forming sheet on the base concrete and fixing the peripheral edge to the base concrete;
Laying a waterproof sheet on the housing molding sheet;
A step of inflating and supporting the casing molding sheet together with the waterproof sheet by applying air pressure to a sealed space formed between the base concrete and the casing molding sheet; and
Disposing reinforcing bars in the concrete placement region along the outer periphery of the waterproof sheet;
Spraying concrete onto the concrete placement area to form an arch-shaped skeleton concrete integral with the base concrete, reinforcing bars and waterproof sheet;
Backfilling earth material outside the hardened arched concrete, and
An arch culvert construction method characterized by comprising:
請求項1の記載において、
防水シートには、その外周面に予め所定間隔で多数のアンカーが突設されていることを特徴とするアーチカルバートの施工方法。
In the description of claim 1,
The waterproof sheet has an arch culvert construction method characterized in that a large number of anchors are projected in advance on the outer peripheral surface at predetermined intervals.
JP33314796A 1996-11-29 1996-11-29 Arch culvert construction method Expired - Fee Related JP3760010B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33314796A JP3760010B2 (en) 1996-11-29 1996-11-29 Arch culvert construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33314796A JP3760010B2 (en) 1996-11-29 1996-11-29 Arch culvert construction method

Publications (2)

Publication Number Publication Date
JPH10159073A JPH10159073A (en) 1998-06-16
JP3760010B2 true JP3760010B2 (en) 2006-03-29

Family

ID=18262827

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33314796A Expired - Fee Related JP3760010B2 (en) 1996-11-29 1996-11-29 Arch culvert construction method

Country Status (1)

Country Link
JP (1) JP3760010B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100491470B1 (en) * 2002-05-06 2005-05-30 (주)아이팝엔지니어링종합건축사사무소 Formwork for water and sewage or passage through the road

Also Published As

Publication number Publication date
JPH10159073A (en) 1998-06-16

Similar Documents

Publication Publication Date Title
US3031801A (en) Method of installing swimming pools
JP5576207B2 (en) Installation foundation and its construction method
WO2001084037A1 (en) Duct repairing material, repairing structure, and repairing method
JP3760010B2 (en) Arch culvert construction method
JP2003328381A (en) Flexible rubber joint, its mounting structure and its construction method
JPH0849237A (en) Slope face covering structure and mat
JP3037442B2 (en) Structural material and joining method
KR20070077824A (en) Construction method of precast concrete box culvert with bolted structure
JP3777549B2 (en) Synthetic underground wall, its construction method, and water expansion waterproofing material
KR20040091241A (en) Supportor for supporti ng synthetic resin pipe and method for laying pipes using thereof
JPH04306398A (en) Repairing method of concrete wall surface
JP3695549B2 (en) Connection method of frame in reverse hammering method
JP2839138B2 (en) Tunnel support material support method and support device
JPH08105053A (en) Slope protection construction method
JPH0978531A (en) Work execution method for arch bridge
JPH08184016A (en) Execution method of concrete guardrail and mold for concrete guardrail
JP2764252B2 (en) Underground concrete structure repair material and repair method
JP2005126954A (en) Manufacturing method for shield tunnel segment
JP3101920B2 (en) Artificial stone connecting block and method of manufacturing the same
JP3025942U (en) Reinforcing bar for expansion joints
JP2818846B2 (en) Repair and reinforcement method of asbestos cement pipe
JP3091829B2 (en) Landscape panel and method of constructing landscape using the panel
JP2854457B2 (en) Water stop structure and water stop method
JPH0718226B2 (en) Method for manufacturing tiled panel
KR101364807B1 (en) Construction method for expansion joint in the waterway

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20051130

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051207

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060106

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100113

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100113

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110113

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110113

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120113

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120113

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130113

Year of fee payment: 7

LAPS Cancellation because of no payment of annual fees