JP3763897B2 - Assembly and installation method of beam reinforcement - Google Patents
Assembly and installation method of beam reinforcement Download PDFInfo
- Publication number
- JP3763897B2 JP3763897B2 JP24132596A JP24132596A JP3763897B2 JP 3763897 B2 JP3763897 B2 JP 3763897B2 JP 24132596 A JP24132596 A JP 24132596A JP 24132596 A JP24132596 A JP 24132596A JP 3763897 B2 JP3763897 B2 JP 3763897B2
- Authority
- JP
- Japan
- Prior art keywords
- stirrup
- reinforcing bar
- rebar
- muscle
- beam reinforcing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title claims description 25
- 238000009434 installation Methods 0.000 title claims description 6
- 230000002787 reinforcement Effects 0.000 title description 15
- 230000003014 reinforcing effect Effects 0.000 claims description 18
- 238000009415 formwork Methods 0.000 claims description 14
- 210000003205 muscle Anatomy 0.000 claims description 12
- 210000003489 abdominal muscle Anatomy 0.000 claims description 4
- 239000000725 suspension Substances 0.000 description 5
- 238000010276 construction Methods 0.000 description 3
- 125000006850 spacer group Chemical group 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、建設現場にて梁鉄筋を組立てて梁型枠内に設置する梁鉄筋の組立て設置方法に関する。
【0002】
【従来の技術】
従来、ビル建設等における梁鉄筋の設置作業においては、その建設現場の所定位置に組付けられた目的の梁型枠の上方などに支持しながら梁鉄筋を組立て、その組立てた梁鉄筋の適数箇所を梁型枠の両側に立設される支柱とそれらの支柱間に架設された横架部材と該横架部材の略中央部に付設された吊り下げ機構から構成される門型の梁鉄筋降下装置等を用いて吊り上げ、前記梁型枠内の所定位置に下降することにより梁鉄筋を所定位置に設置するという施工方法が広く知られている。
【0003】
しかしながら、この梁鉄筋に関する従来の設置方法では、組立て後の梁鉄筋を梁型枠内の所定位置に下降するための門型の梁鉄筋降下装置などのほかに、梁鉄筋の組立て時に上端筋や下端筋あるいはスターラップなどの梁鉄筋を構成する各部材を支持するための別の支持手段が必要とされた。
【0004】
【発明が解決しようとする課題】
本発明は、以上のような従来の技術的事情に鑑みて開発したもので、その目的とするところは、梁鉄筋の組立て設置作業において使用する支持手段の必要数を削減した簡便な梁鉄筋の組立て設置方法を提供する点にある。
【0005】
【課題を解決するための手段】
前記課題を解決するため、本発明では、梁型枠の両側のスラブ型枠間に渡し筋を支持し、その渡し筋上に下端筋をスターラップに挿通した状態で載置するとともに、該下端筋上に掛止部材とその上方に上端筋を前記スターラップに挿通した状態で重ねて載置し、しかる後、前記梁型枠を跨ぐように立設した梁鉄筋昇降装置により前記掛止部材を介して初め上端筋とスターラップを上昇し、途中で前記渡し筋を抜いて更に上昇して下端筋をスターラップの下辺部で支持することにより、梁鉄筋を構成する前記各部材を吊上げた状態において、それら部材を所定の位置に配置し、前記上端筋及び下端筋をスターラップに結束するとともに、必要に応じて腹筋等を設置して梁鉄筋を組立てた上、その梁鉄筋を前記梁鉄筋昇降装置により下降して前記梁型枠内の所定位置に設置するという技術手段を採用した。さらに、前記梁鉄筋昇降装置を構成する横架部材に揺動レバー式のチェーンブロックを回転可能に支持し、前記揺動レバーを操作し易い方向に回転して揺動操作するようにすれば、作業性の向上に有効である。
【0006】
【発明の実施の形態】
図1〜図5は本発明における作業工程の手順を例示した概略説明図である。図1は梁鉄筋の組立て開始前の状態を示したもので、図中1は梁型枠、2はスラブ型枠である。梁鉄筋の組立てに当っては、先ず図2に示したように、梁型枠1の両側のスラブ型枠2の端部間に複数の渡し筋3を間隔をあけて支持し、それらの渡し筋3を介してその上にスターラップ4に挿通した状態で重ねて載置した下端筋5、掛止部材6、及び上端筋7を前記スターラップ4と共に支持する。すなわち、梁型枠1の両側のスラブ型枠2の端部間に支持した渡し筋3を介してスターラップ4に挿通した下端筋5、掛止部材6、及び上端筋7を下から順に載置した状態に支持することにより梁鉄筋を構成する各部材を支持する。
【0007】
しかる後、図3に示した工程に進み、図示のように支柱8,9と、その間に架設された横架部材10と、該横架部材10の略中央部に付設されたチェーンブロックを用いた吊り下げ機構11から構成される梁鉄筋昇降装置12を梁型枠1を跨ぐように立設し、チェーン13の下端部を適宜の連結手段で前記掛止部材6に結合して、揺動レバー14を上下に揺動しながらチェーン13を巻上げることにより梁鉄筋を構成する前記各部材を吊上げることになる。この場合、初め掛止部材6を介して上端筋7とスターラップ4を上昇し、下端筋5がスターラップ4の下辺部に接近した時点で前記渡し筋3を抜き、更に上昇して図4の工程に移行する。
【0008】
図4に示した工程においては、図示のように掛止部材6を介して下端筋5、掛止部材6、上端筋7やスターラップ4等の各部材を吊上げ、その吊上げ状態において、それらの部材を所定の位置に配置した後、前記上端筋7及び下端筋5をスターラップ4に結束し、更に必要に応じて腹筋15を通して巾止筋16を用いて所定位置に結束することにより、梁鉄筋17を組立て形成する。
【0009】
以上の工程により梁鉄筋17の組立てが完了した場合には図5の工程に移行し、図示のように吊り下げ機構11によって梁鉄筋17を下降させて梁型枠1内の所定位置に設置することにより、梁鉄筋の組立てと所定位置への設置作業が終了することになる。なお、図中18はスペーサであり、図4の工程あたりで予め前記スターラップ4の下部に装着しておいてもよい。
【0010】
なお、以上の形態例においては、前記吊り下げ機構11として揺動レバー式、すなわち揺動レバー14をその自由端部を上下に揺動することによりチェーン13を介して組立て中あるいは組立て後の梁鉄筋を昇降するチェーンブロックを採用したが、このチェーンブロックを前記横架部材10に対して回転可能に支持すれば、前述の組立て設置作業において、必要に応じて揺動レバー14を操作し易い方向に回転し、身を乗出すことなくその場において揺動レバー14を上下に揺動し得るので使い勝手がきわめてよい。また、前記支柱8,9の下部にはL形鋼などからなるベース体が付設されており、図面において紙面に直角方向の傾斜が抑制され、梁鉄筋昇降装置12が自立し得るように構成されている。また、前記横架部材10の両端部には連結管19,20を設け、支柱8,9に外嵌して高さ調整可能に構成している。
【0011】
【発明の効果】
本発明によれば、梁型枠の内部空間を利用して、その内部空間内に梁鉄筋を構成する各部材を前記渡し筋及び掛止部材を用いて支持した上、それらの各部材を前記掛止部材を介して梁鉄筋昇降装置により吊上げて梁鉄筋の組立てを完成させ、しかる後その組立てられた梁鉄筋を前記梁鉄筋昇降装置により下降して梁型枠内の所定位置に設置するという方法を採用したので、前記梁鉄筋昇降装置のほかに従来必要とされた別の支持手段を省略することができ、梁鉄筋の組立て設置作業において必要とされる支持手段の使用数を削減した簡便な梁鉄筋の組立て設置方法を提供することができる。さらに、梁鉄筋の吊り下げ機構として揺動レバー式のチェーンブロックを採用し、前記横架部材に対して回転可能に支持するように構成すれば、揺動レバーを操作し易い方向に回転して上下に揺動操作するだけで組立て中あるいは組立て後の梁鉄筋の吊上げが可能なことから作業性の向上に有効である。
【図面の簡単な説明】
【図1】 本発明における作業工程の手順を例示した概略説明図である。
【図2】 同作業工程の手順を例示した概略説明図である。
【図3】 同作業工程の手順を例示した概略説明図である。
【図4】 同作業工程の手順を例示した概略説明図である。
【図5】 同作業工程の手順を例示した概略説明図である。
【符号の説明】
1…梁型枠、2…スラブ型枠、3…渡し筋、4…スターラップ、5…下端筋、6…掛止部材、7…上端筋、8,9…支柱、10…横架部材、11…吊り下げ機構、12…梁鉄筋昇降装置、13…チェーン、14…揺動レバー、15…腹筋、16…巾止筋、17…梁鉄筋、18…スペーサ、19,20…連結管[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for assembling and installing a beam reinforcing bar in which a beam reinforcing bar is assembled and installed in a beam formwork at a construction site.
[0002]
[Prior art]
Conventionally, when installing beam reinforcement in building construction, etc., the beam rebar is assembled while supporting it above the target beam formwork assembled at a predetermined position at the construction site, and the appropriate number of beam reinforcements assembled. A portal-type beam rebar consisting of struts erected on both sides of the beam formwork, horizontal members erected between these struts, and a suspension mechanism attached to a substantially central portion of the horizontal members A construction method is widely known in which a beam rebar is installed at a predetermined position by lifting it using a descent device or the like and lowering it to a predetermined position in the beam formwork.
[0003]
However, in the conventional installation method related to the beam reinforcement, in addition to the gate-type beam reinforcement lowering device for lowering the assembled beam reinforcement to a predetermined position in the beam form frame, There is a need for a separate support means for supporting each member constituting the beam reinforcing bar such as the bottom bar or the stirrup.
[0004]
[Problems to be solved by the invention]
The present invention was developed in view of the above-described conventional technical circumstances, and the object of the present invention is to provide a simple beam rebar with a reduced number of support means used in the assembly work of the beam rebar. It is in providing an assembly and installation method.
[0005]
[Means for Solving the Problems]
In order to solve the above problems, in the present invention, a transfer bar is supported between the slab molds on both sides of the beam frame, and the lower bar is placed on the transfer bar in a state of being inserted into the stirrup, and the lower end the upper muscle latching member and its upward musculature placed on top while inserted into the stirrup, thereafter, the latch member by the beam reinforcement lifting device provided upright so as to cross the beam formwork First, the upper end bars and stirrups are raised through, the intermediate bars are pulled out on the way, and the lower bars are further supported by the lower side of the stirrup, thereby lifting each member constituting the beam reinforcing bar. In the state, the members are arranged at predetermined positions, the upper and lower bars are bound to the stirrup, and abdominal muscles are installed as necessary to assemble the beam reinforcing bars. It is lowered by the reinforcing bar lifting device Employing the technical means that is placed at a predetermined position in the mold. Furthermore, if a swing lever type chain block is rotatably supported on a horizontal member constituting the beam reinforcing bar lifting device, and the swing lever is rotated in a direction that is easy to operate, the swing operation is performed. Effective for improving workability.
[0006]
DETAILED DESCRIPTION OF THE INVENTION
1 to 5 are schematic explanatory views illustrating the procedure of the work process in the present invention. FIG. 1 shows a state before the start of the assembly of the beam reinforcement. In the figure, 1 is a beam formwork and 2 is a slab formwork. In assembling the beam reinforcing bars, first, as shown in FIG. 2, a plurality of
[0007]
Thereafter, the process proceeds to the step shown in FIG. 3, and the
[0008]
In the process shown in FIG. 4, the members such as the
[0009]
When the assembly of the
[0010]
In the above embodiment, the
[0011]
【The invention's effect】
According to the present invention, by utilizing the internal space of the beam-type frame, on which supporting the members constituting the beam reinforcement in its internal space with the passing muscle and latch member, each of those members said The beam rebar lifting device is lifted through the latching member to complete the assembly of the beam rebar, and then the assembled beam rebar is lowered by the beam rebar lifting device and installed at a predetermined position in the beam formwork. Since the method is adopted, in addition to the beam rebar lifting and lowering device, another conventionally required support means can be omitted, and the number of use of the support means required for the assembly work of the beam rebar is reduced. It is possible to provide a method for assembling and installing a simple beam rebar. Furthermore, if a swing lever type chain block is adopted as a beam rebar suspension mechanism and is configured to be rotatably supported with respect to the horizontal member, the swing lever can be rotated in an easy-to-operate direction. The beam rebar can be lifted during or after assembly by simply swinging up and down, which is effective in improving workability.
[Brief description of the drawings]
FIG. 1 is a schematic explanatory view illustrating the procedure of a work process in the present invention.
FIG. 2 is a schematic explanatory view illustrating the procedure of the work process.
FIG. 3 is a schematic explanatory view illustrating the procedure of the work process.
FIG. 4 is a schematic explanatory view illustrating the procedure of the work process.
FIG. 5 is a schematic explanatory view illustrating the procedure of the work process.
[Explanation of symbols]
DESCRIPTION OF
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP24132596A JP3763897B2 (en) | 1996-08-23 | 1996-08-23 | Assembly and installation method of beam reinforcement |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP24132596A JP3763897B2 (en) | 1996-08-23 | 1996-08-23 | Assembly and installation method of beam reinforcement |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH1061187A JPH1061187A (en) | 1998-03-03 |
| JP3763897B2 true JP3763897B2 (en) | 2006-04-05 |
Family
ID=17072624
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP24132596A Expired - Fee Related JP3763897B2 (en) | 1996-08-23 | 1996-08-23 | Assembly and installation method of beam reinforcement |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3763897B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102383608A (en) * | 2011-08-19 | 2012-03-21 | 中建三局第二建设工程有限责任公司 | Lifting device capable of being repeatedly used for steel reinforcement cage |
| CN113685035B (en) * | 2021-09-18 | 2024-11-05 | 中国五冶集团有限公司 | A lifting device for adjusting the position of steel bars at a construction site |
| CN116181072A (en) * | 2023-01-04 | 2023-05-30 | 中国建筑第八工程局有限公司 | A reinforcement tool for beam main reinforcement |
-
1996
- 1996-08-23 JP JP24132596A patent/JP3763897B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH1061187A (en) | 1998-03-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204644884U (en) | High pier over-form construction reinforced bar installs mobile stock | |
| CN105415489B (en) | A kind of column prefabrication system and method for prefabricating | |
| JP4252177B2 (en) | Steel / concrete composite structure pier construction method | |
| KR101889064B1 (en) | Construction method of a long span bridge main tower | |
| CN118327021A (en) | Prestressed concrete pipe pile foundation for power transmission line and its construction method | |
| JP3763897B2 (en) | Assembly and installation method of beam reinforcement | |
| JPH08134848A (en) | Execution method of steel pipe-concrete composite structure pier | |
| CN114892735B (en) | A method for in-situ treatment of quality defects in transmission tower pile foundations | |
| JP4057724B2 (en) | Support structure of bridge girder in extrusion method | |
| JP2001254516A (en) | Piling method for SRC steel columns to be PC concreted on the ground. | |
| CN107338863B (en) | A kind of construction method of the horizontal prefabricated components of prefabricated concrete structure | |
| CN114753299A (en) | Pile-cap-free fully-assembled wharf structure and construction method thereof | |
| CN219604686U (en) | Hollow steel skeleton prefabricated column with built-in combined metal template | |
| JP2009299346A (en) | Construction method of building | |
| JPH07217080A (en) | Two-layer type reinforcing steel net | |
| CN211713706U (en) | A large cantilever prefabricated cover beam installation lattice support device | |
| JP2648937B2 (en) | Reinforcing bar for long span beams | |
| CN115852830A (en) | Special-shaped arch pier column template and mounting method of supporting system thereof | |
| CN205219410U (en) | Prefabricated system of stand | |
| CN113073553A (en) | Pile cap embedded upright post steel bar positioning device and construction method thereof | |
| CN111877126A (en) | Arch bridge arch ring installation method | |
| JP3716657B2 (en) | Furnace block suspension device | |
| CN112916771B (en) | A one-piece tire frame for tying steel bars of assembled cover culvert wall | |
| CN117513758B (en) | Support device and construction method for beam reinforcement binding | |
| CN209873782U (en) | Finished product controller for protective layer of cast-in-situ bored pile |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20041111 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20041130 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050127 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050802 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050930 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060112 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060118 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100127 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100127 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110127 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120127 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130127 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140127 Year of fee payment: 8 |
|
| LAPS | Cancellation because of no payment of annual fees |