JP3791719B2 - Directly connected track construction method and track structure using construction girders - Google Patents
Directly connected track construction method and track structure using construction girders Download PDFInfo
- Publication number
- JP3791719B2 JP3791719B2 JP08684097A JP8684097A JP3791719B2 JP 3791719 B2 JP3791719 B2 JP 3791719B2 JP 08684097 A JP08684097 A JP 08684097A JP 8684097 A JP8684097 A JP 8684097A JP 3791719 B2 JP3791719 B2 JP 3791719B2
- Authority
- JP
- Japan
- Prior art keywords
- construction
- girder
- girders
- track
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
- E01B1/005—Ballastless track, e.g. concrete slab trackway, or with asphalt layers with sleeper shoes
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2/00—General structure of permanent way
- E01B2/006—Deep foundation of tracks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は工事桁工法及び鉄道軌道構造に係り、特に、工事桁架設及び撤去、メンテナンスフリーの軌道構造の構築作業に好適な直結軌道化工法及び軌道構造に関するものである。
【0002】
【従来の技術】
既設の鉄道軌道の下に構造物を構築する場合、工事桁で軌道を仮受けしておく工法がある。この工事桁としては、一般的に枕木抱き込み式工事桁が用いられているが、この工事桁を用いた工法の手順を、図1により概略説明する。
図1は道床1の断面を示す図である。通常、枕木としてPC枕木が使用されているが、PC枕木では工事桁として重量が重くなってしまうこと、また、その重量のために横桁(枕木受け桁)の挿入作業が大変になることなどから、まず、PC枕木を木枕木2に交換してレール3を支持し、さらに、試掘して土留め杭4を打設する(図1(a))。次いで、主桁架設用に道床1の両側を掘削し(図1(b))、主桁5を架設もしくは仮置きし(図1(c))、次いで、枕木2を抱き込む横桁6を挿入して架設し、主桁5を横移動して横桁6を支持し、工事桁が完成する。
【0003】
工事桁により仮受けされていた軌道の直下に構造物(高架橋等)が完成した後、工事桁は撤去される。工事桁の撤去は、まず、主桁5、横桁6を撤去し、木枕木2をPC枕木に取り替えてレールを受け替え、バラストを投入し、軌道整備を行うという手順で行われる。
【0004】
【発明が解決しようとする課題】
このように、従来の枕木抱き込み式工事桁による工法では、工事桁により仮受けされていたレールは、新設構造物に受け替える場合、その軌道構造はバラスト軌道(有道床軌道)にせざるを得なかったのが実情である。
【0005】
しかし、近年、軌道構造をメンテナンスフリーとするニーズが強まっていることから、このニーズに応えようとすると、従来の枕木抱き込み式工事桁による工法では、工事桁により仮受けされた軌道をバラスト軌道に復旧した後、メンテナンスフリーの軌道構造へ替えるための作業を改めて行わなければならなかった。この場合も、夜間保守間合いで、枕木・バラストを撤去して本体構造物の軌道の直結化の作業を行うため、作業範囲を広くとれず、多くの作業日数を要してしまう。また、直結軌道化を行う場合の材料も短時間で所定の強度を有するものでなければならないため、コスト面に関しても割高となってしまう。
【0006】
本発明は上記課題を解決するためのもので、工事桁により仮受けされていた軌道をバラスト軌道に変更することなく、新設構造物と直結軌道化し、メンテナンスフリーの軌道構造とすることにより、夜間作業およびコストの低減を図ることを目的とする。
【0007】
【課題を解決するための手段】
本発明は、PC枕木、合成枕木を横桁(枕木受け桁)に設置し、レールを取り付けて主桁との組み立てを行っておき、工事桁架設時には、組み立ててある工事桁を台車等により架設箇所へ移動し、工事桁設置箇所のレール、枕木を撤去し、主桁受桁のレベルまで掘削し、操重車により工事桁を一括架設して工事桁により軌道を仮受けし、工事桁の下に新設構造物が完成し、工事桁により仮受けされていた軌道を新設構造物へ受け替えるときに、工事桁の主桁、さらに横桁端部を撤去し、枕木と枕木が乗っている横桁部分はそのまま残しておくようにしたことを特徴としている。
【0008】
【発明の実施の形態】
以下、本発明の実施の形態について説明する。
図2は本発明の工法を説明する図である。
図2(a)(縦断面図)、図2(b)(横断面図)は、予めPC枕木7が設置された横桁(枕木受け桁)6と主桁5を組み立てた工事桁を一括架設して、横桁6と床板との間にコンクリート8を打設した状態を示している。この工事桁の一括架設に先立って、工事桁設置箇所のレール、枕木は撤去し、主桁受桁のレベルまで掘削しておき、主桁を受桁(図示せず)に設置している。長期間使用可能なPC枕木(または合成枕木等)7を鋼製の横桁6に設置する場合、枕木下面にゴム製マット等の緩衝材9を配置し衝撃を和らげるようにする。また、枕木の横ずれ防止のための樹脂注入等を行ったり、必要に応じて鋼製の横桁6にボルト締めする。
【0009】
工事桁の下に新設構造物が完成し、工事桁により仮受けされていた軌道を新設構造物へ受け替えるときに、工事桁の撤去を行うが、本発明においては、主桁と横桁端部のみを撤去し、枕木と枕木が乗っている横桁部分はそのまま残しておくようにする。主桁を撤去するときには、主桁により工事桁全体を支承しているため、軌道を受ける構造を構築する必要がある。そこで、工事桁が主桁により支承されている間に、横桁6の下の主桁間に型枠を構築し(図示せず)、横桁6、枕木7を巻き込むように、コンクリート8上に間詰めコンクリート10を打設して新設構造物と一体化し、コンクリート養生後、主桁5へ横桁6を締結しているボルトを撤去して主桁5を撤去する(図2(c)(縦断面図)、図2(d)(横断面図))。なお、横桁間の間詰め材と横桁の間には、緩衝材を配置して列車の繰り返し荷重による間詰め材の劣化を防止することが望ましい。また、曲線区間などにより軌道に横荷重が作用する場合、片側の主桁のみ撤去し、横桁端部を巻き込むように型枠を構築してコンクリートを打設し、コンクリート養生後に他方の主桁を撤去し、同様に横桁端部を巻き込むように型枠を構築し、コンクリートを打設する。
【0010】
次いで、横桁6のはみ出ている端部を切断し(図2(e)(縦断面図)、図2(f)(横断面図))、枕木、横桁端部をコンクリート11を打設して横方向を拘束し、同時に横桁と枕木を見えなくする。
【0011】
なお、上記においては、横桁端部を切断するようにしたが、切断せずにこのまま残すようにしてもよく、また、間詰めコンクリートの打設を横桁端部のコンクリート仕上げと同時に行うようにしてもよい。
【0012】
図3は本発明の他の実施の形態を説明する図である。
この例も基本的には図2の工法と同じであるが、主桁撤去後に新設構造物と一体化するようにした点のみ異なっている。
まず、予めPC枕木7が設置された横桁6と主桁5を組み立てた工事桁を一括架設して、横桁6と床板との間にコンクリート8を打設する。次いで、図3(c)、図3(d)に示すように、主桁撤去前に、コンクリート8上に仮支承材20を設置して横桁6を仮受けし、横桁間に土のう21を詰めて軌道の移動を防止し、その後、主桁を撤去する。次いで、横桁6のはみ出ている端部を切断し(図3(e)、図3(f))、次いで、横桁6、枕木7を巻き込むように間詰めコンクリートを打設して新設構造物と一体化し、横桁と枕木端部にコンクリート11を打設して仕上げる。
【0013】
【発明の効果】
以上のように本発明によれば、事前に工事桁の組み立てを行い、一括架設して軌道を仮受けし、軌道を新設構造物へ受け替えるときに、工事桁の主桁と横桁端部のみ撤去し、枕木と枕木が乗っている横桁部分はそのまま残して新設構造物と一体化することにより、工事桁により仮受けされていた軌道をバラスト軌道に変更することなく、メンテナンスフリーの軌道構造とすることができ、夜間作業およびコストの低減を図ることを可能となる。
【図面の簡単な説明】
【図1】 枕木抱き込み式工事桁を用いた工法を説明する図である。
【図2】 本発明の工法の例を説明する図である。
【図3】 本発明の工法の他の例を説明する図である。
【符号の説明】
3…レール、5…主桁、6…横桁、7…PC枕木、8…コンクリート、9…緩衝材、10…間詰めコンクリート、11…コンクリート、20…仮支承材、21…土のう。[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction girder method and a railroad track structure, and more particularly to a direct connection track construction method and a track structure suitable for construction work of construction girder construction and removal, and maintenance-free track structure.
[0002]
[Prior art]
When constructing a structure under an existing railway track, there is a method of temporarily receiving the track with a construction girder. As this construction girder, a sleeper-embedding construction girder is generally used. The procedure of the construction method using this construction girder will be schematically described with reference to FIG.
FIG. 1 is a view showing a cross section of the roadbed 1. PC sleepers are usually used as sleepers, but PC sleepers are heavy as construction girders, and because of their weight, it is difficult to insert horizontal girders (sleeper support girders). Therefore, first, the PC sleepers are replaced with wooden sleepers 2 to support the rails 3, and further, the earth retaining piles 4 are driven by digging (FIG. 1A). Next, both sides of the road bed 1 are excavated for erection of the main girder (FIG. 1 (b)), the main girder 5 is erected or temporarily placed (FIG. 1 (c)), and then the
[0003]
The construction girder will be removed after the construction (bypass, etc.) is completed directly under the track temporarily received by the construction girder. The construction girder is first removed by removing the main girder 5 and the
[0004]
[Problems to be solved by the invention]
As described above, in the conventional construction method using a sleeper-embedded construction girder, when the rail temporarily received by the construction girder is replaced with a new structure, the track structure must be a ballast track (a roadbed track). There was no actual situation.
[0005]
However, in recent years, the need to make the track structure maintenance-free has increased, so in order to meet this need, in the conventional construction method using a sleeper-embedded construction girder, the trajectory temporarily received by the construction girder is the ballast track. After the recovery, the work to change to a maintenance-free track structure had to be performed again. Also in this case, since the sleepers and ballasts are removed and the track of the main body structure is directly connected during night maintenance, the work range cannot be widened and a lot of work days are required. In addition, since the material for forming the direct connection track has to have a predetermined strength in a short time, the cost is expensive.
[0006]
The present invention is to solve the above-mentioned problems, and without changing the track temporarily received by the construction girder to the ballast track, the track is directly connected to the newly-constructed structure, thereby providing a maintenance-free track structure. The purpose is to reduce work and cost.
[0007]
[Means for Solving the Problems]
In the present invention, PC sleepers and synthetic sleepers are installed on a horizontal girder (sleeper support girder), and a rail is attached to assemble the main girder. When constructing a construction girder, the assembled construction girder is constructed by a carriage or the like. Move to the location, remove the rails and sleepers at the location where the construction girder is installed, excavate to the level of the main girder girder, install the construction girder collectively with a heavy vehicle, temporarily receive the track with the construction girder, The new structure is completed below, and when the track temporarily received by the construction girder is replaced with the new structure, the main girder of the construction girder and the end of the horizontal girder are removed, and sleepers and sleepers are on board. It is characterized in that the horizontal beam part is left as it is.
[0008]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below.
FIG. 2 is a diagram for explaining the construction method of the present invention.
2 (a) (longitudinal sectional view) and FIG. 2 (b) (transverse sectional view) are a group of construction girders in which a horizontal girder (sleeper receiving girder) 6 on which a PC sleeper 7 is previously installed and a main girder 5 are assembled. A state in which the
[0009]
When a new structure is completed under the work girder and the track temporarily received by the work girder is replaced with the new structure, the work girder is removed. Remove only the part, and leave the cross-beam part on which the sleepers and sleepers are on as they are. When removing the main girder, the entire construction girder is supported by the main girder, so it is necessary to construct a structure that receives the track. Therefore, while the construction girder is supported by the main girder, a formwork is constructed between the main girder under the cross girder 6 (not shown), and the
[0010]
Next, the protruding end of the
[0011]
In the above, the end of the cross beam is cut, but it may be left as it is without being cut, and the filling concrete is placed simultaneously with the concrete finishing of the end of the cross beam. It may be.
[0012]
FIG. 3 is a diagram for explaining another embodiment of the present invention.
This example is also basically the same as the method shown in FIG. 2, except that the main girder is removed and integrated with the new structure.
First, a construction girder in which a
[0013]
【The invention's effect】
As described above, according to the present invention, when the construction girders are assembled in advance, temporarily installed to temporarily receive the track, and when the track is transferred to a new structure, the main girder and cross beam end portions of the work beam Only by removing the sleeper and the cross beam on which the sleeper is placed, it is integrated with the newly constructed structure, so that the track temporarily received by the work girder is not changed to a ballast track. It can be set as a structure, and it becomes possible to aim at night work and cost reduction.
[Brief description of the drawings]
FIG. 1 is a diagram for explaining a construction method using a sleeper-embedding construction girder.
FIG. 2 is a diagram illustrating an example of a construction method according to the present invention.
FIG. 3 is a diagram for explaining another example of the construction method of the present invention.
[Explanation of symbols]
3 ... rails, 5 ... main girders, 6 ... cross girders, 7 ... PC sleepers, 8 ... concrete, 9 ... cushioning material, 10 ... stuffed concrete, 11 ... concrete, 20 ... temporary support materials, 21 ... clay.
Claims (3)
組み立てた工事桁を一括架設する段階、
横桁と床版間にコンクリートを打設する段階、
工事桁により軌道を受けている状態で、横桁を巻き込むように前記コンクリート上に間詰めコンクリートを打設して一体化する段階、
主桁を撤去する段階、
主桁撤去後、横桁端部を切断し、切断部をコンクリート仕上げする段階、
を含む工事桁を利用した直結軌道化工法。 A stage where PC sleepers or synthetic sleepers are installed on the horizontal girders, fixed to the main girders, and the construction girders are assembled before installation,
The stage to build the assembled construction girder at once,
Placing concrete between the cross beam and floor slab,
While undergoing orbital by construction of digits, the step of integrating by Da設between filling concrete on the concrete to involve crossbeam,
Removing the main girder,
After removing the main girder, the end of the cross beam is cut and the cut part is concrete finished,
Directly connected track construction method using construction girders including
組み立てた工事桁を一括架設する段階、
横桁と床版間にコンクリートを打設する段階、
工事桁により軌道を受けている状態で、仮支承材を設置して前記コンクリートで横桁を受けるとともに、横桁間に間詰めをして横桁を固定する段階、
主桁を撤去する段階、
主桁撤去後、横桁端部を切断し、切断部をコンクリート仕上げする段階、
前記間詰めをした横桁間に間詰めコンクリートを打設して一体化する段階、
を含む工事桁を利用した直結軌道化工法。 A stage where PC sleepers or synthetic sleepers are installed on the horizontal girders, fixed to the main girders, and the construction girders are assembled before installation,
The stage to build the assembled construction girder at once,
Placing concrete between the cross beam and floor slab,
While receiving the track by the construction girder, installing the temporary support material and receiving the cross beam with the concrete, fixing the cross beam between the cross beams and fixing the cross beam,
Removing the main girder,
After removing the main girder, the end of the cross beam is cut and the cut part is concrete finished,
Placing and integrating interstitial concrete between the interstitial cross beams,
Directly connected track construction method using construction girders including
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP08684097A JP3791719B2 (en) | 1997-04-04 | 1997-04-04 | Directly connected track construction method and track structure using construction girders |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP08684097A JP3791719B2 (en) | 1997-04-04 | 1997-04-04 | Directly connected track construction method and track structure using construction girders |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH10280304A JPH10280304A (en) | 1998-10-20 |
| JP3791719B2 true JP3791719B2 (en) | 2006-06-28 |
Family
ID=13898022
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP08684097A Expired - Fee Related JP3791719B2 (en) | 1997-04-04 | 1997-04-04 | Directly connected track construction method and track structure using construction girders |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3791719B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102425123B (en) * | 2011-09-14 | 2013-07-10 | 中铁四局集团第一工程有限公司 | Combined type protection shed frame and construction method thereof |
| CN105735056A (en) * | 2016-03-02 | 2016-07-06 | 沈阳铁道勘察设计院有限公司 | Method for reinforcing railway through piling girders combined with I-steel cross girders |
-
1997
- 1997-04-04 JP JP08684097A patent/JP3791719B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH10280304A (en) | 1998-10-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN100464026C (en) | Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process | |
| CN101333801A (en) | Cast-in-situ beam-making construction method of assembled support | |
| CA1336424C (en) | Railroad roadway for high speed rail-mounted vehicles | |
| KR100454405B1 (en) | Method for changing steel bridge of supporting rail into concreat bridge | |
| KR102105230B1 (en) | Railroad bridge construction method for keeping preexistence railroad track and rail service | |
| KR101780224B1 (en) | Concrete long sleeper block of fast-hardening track for improving rail track considering train operation construction method | |
| KR100891961B1 (en) | Bridge replacement method and its apparatus for inducing image of old bridge or ballless bridge of road or railway using temporary structure | |
| KR101187282B1 (en) | Railway bridge constructing method using 2 post type abutment structure | |
| US4911360A (en) | Precast railway crossing slab | |
| JP4540632B2 (en) | Erection girder | |
| CZ319492A3 (en) | Load-bearing structure of a permanent way and a prefabricated platform thereof | |
| KR20050108867A (en) | A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents. | |
| EP1558815B1 (en) | Fixed track for rail vehicles and method for production thereof | |
| EP1700954A2 (en) | Prefabricated modular member, permanent railway for tramways and subways including said member, and process for laying the same | |
| US20050252985A1 (en) | Rail sleeper and ballast-free track structure | |
| JP4162291B2 (en) | Railway work girder cradle and rail work girder cradle construction method | |
| KR100603901B1 (en) | Structure and construction method of plate girder bridge using part of existing girder | |
| KR100595429B1 (en) | Railway rail concrete track structure and construction method | |
| JP3791719B2 (en) | Directly connected track construction method and track structure using construction girders | |
| JP4136959B2 (en) | "How to build underground structures and installation girder" | |
| JP2006112086A (en) | Bridge structure and its replacement method | |
| KR100638578B1 (en) | Construction method for replacing superstructure of railway bridge | |
| JP3788774B2 (en) | Railroad track structure and railroad track construction method | |
| KR102314401B1 (en) | Construction method of fast-hardening rail track for improving ballast rail track | |
| DE19625249C2 (en) | Positionally stable track body made of precast concrete parts and use of precast concrete parts for this track body |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040402 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050928 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20051207 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060206 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060329 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060330 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100414 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100414 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110414 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120414 Year of fee payment: 6 |
|
| LAPS | Cancellation because of no payment of annual fees |