JP3798332B2 - Method for assembling tunnel lining segments - Google Patents
Method for assembling tunnel lining segments Download PDFInfo
- Publication number
- JP3798332B2 JP3798332B2 JP2002102889A JP2002102889A JP3798332B2 JP 3798332 B2 JP3798332 B2 JP 3798332B2 JP 2002102889 A JP2002102889 A JP 2002102889A JP 2002102889 A JP2002102889 A JP 2002102889A JP 3798332 B2 JP3798332 B2 JP 3798332B2
- Authority
- JP
- Japan
- Prior art keywords
- segment
- ring
- steel material
- tunnel
- tunnel lining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000000034 method Methods 0.000 title claims description 13
- 229910000831 Steel Inorganic materials 0.000 claims description 27
- 239000010959 steel Substances 0.000 claims description 27
- 239000000463 material Substances 0.000 claims description 21
- 238000010586 diagram Methods 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、トンネル覆工用セグメントの組立方法に関する。
【0002】
【従来の技術】
従来、プレストレスを導入するトンネル覆工用セグメントは、セグメントリングを形成し、円周方向ストランドを一円周に亘って挿通し、この円周方向ストランドに緊張力を加えて、一体リングを形成し、これを切羽側からジャッキ等で既設セグメントリングに押圧して位置を保ち、複数列の一体リングをトンネル推進方向に連結して形成されていた。
【0003】
以上のトンネルセグメント形成に際し、
(1)セグメントを切羽側からシールドジャッキ等にて既設セグメントリングに押圧しながら組立てるが、周方向ストランドを挿入してはじめてセグメントリングが安定するので、それまで、不安定要素があり、危険な作業であった。
(2)また、推進方向は複数列のセグメントリングを緊張材を挿通して緊張するが、その作業が容易でなかった。
(3)セグメントリングの周方向緊張を円周上の1個所で行うので、周方向ストランドの挿入に手間を要し、定着部のセグメントに設ける切欠が大きく、また緊張には強力な重装備のジャッキを装着する必要があり、作業性が劣っていた。
【0004】
【発明が解決しようとする課題】
本発明は、トンネル推進方向に対してX字状にPC鋼材を配設したトンネル覆工用セグメントを用いて、セグメントリングの組立作業を安全に安定的に容易に行うことができるように改善した技術を提供することを目的とする。
【0005】
【課題を解決するための手段】
本発明は、上記問題を解決するためになされたもので、セグメントのほぼ中央部を通ってトンネル推進方向に対してX字状にセグメント内に配設され、両端に接続具を備えたポストテンション方式のPC鋼材を備えたトンネル覆工用セグメントを用いて、安定的に作業を行う技術を提供する。ここでトンネル推進方向にX字状に配設とは、セグメントの展開図において、トンネル推進方向に対してそれぞれ同一の正負の傾き角を有する斜方向PC鋼材がに配設され、隣接セグメントと背悦属するようになっており、セグメント全体に付いてみるとPC鋼材が菱形網目状を形成して配設されていることを云う。
【0006】
本発明のセグメントの組立方法は次の通りである。すなわち、両端に接続具を備えたポストテンション方式のPC鋼材がセグメントのほぼ中央部を通ってトンネル推進方向に対してX字状にセグメント内に配設されたトンネル覆工用セグメントを用い、新設セグメントリングの各セグメントピースを1個づつ切羽側からシールドジャッキで既設セグメントリングに押圧し、押圧したセグメントピースに内蔵するPC鋼材を既設セグメントリングのPC鋼材端部に連結して仮緊張仮定着し、新設セグメントリングの組立終了後、該セグメントリング全体をシールドジャッキで一体に押圧しながら、前記PC鋼材を本緊張して定着し、セグメントのトンネル推進方向と円周方向の応力導入及び定着を同時に達成することを特徴とするトンネル覆工用セグメントの組立方法である。
【0007】
【発明の実施の形態】
以下図面を参照して本発明の実施の形態を説明する。
【0008】
図1は本発明の1実施例のセグメントピース100の模式的正面図である。このセグメントピース100はトンネル推進方向にX字状にPC鋼材2を内蔵しており、このPC鋼材2の一端には、接続具3を備えている。このセグメントピース100に隣接する既設セグメントリングのセグメントピース110は千鳥配列でこのセグメントピース100に接し、PC鋼材2は互いに連結可能な位置に配設されている。
【0009】
図2〜図4は、実施例のセグメント100の組立工程を示す工程図である。図2〜図4はトンネルライニングの展開図を示している。図2に示すように、既設セグメントリング110の切羽側に新設セグメントピース100aを取付ける。このとき、シールドマシンの掘削ヘッド31からシールドジャッキ33でセグメントピース100aを押圧し、X字状に内蔵しているPC鋼材2aを電動トルクレンチ34を用いて既設セグメントリング110のPC鋼材2aと結合させ、仮緊張する。掘削ヘッド31はカッタービット32が切羽に接している。
【0010】
図3は、図2で連結したセグメントピース100aの隣に別のセグメントピース100bを設置した状態を示している。電動又はエアトルクレンチ34を用いて、PC鋼材2と既設セグメントリング110のPC鋼材2aとを結合し、仮緊張する工程は図2と同様である。次々とセグメントピースを取付ける。図4は一列のセグメントリング100が既設セグメントリング110に接続され、PC鋼材2が結合され、油圧トルクレンチ43等によって新設セグメントリング100のPC鋼材2に緊張力を導入する状態を示している。このようにして、セグメントのトンネル推進方向及び円周方向に一様に適正なプレストレスを付与することが可能である。
【0011】
【発明の効果】
本発明によれば、PC鋼材をセグメントピース内にX字状に形成しておき、既設PC鋼材と連結することによって、簡単に安全にセグメントピースを既設セグメントリングに接続、緊張できる。このPC鋼材を仮緊張することによってセグメントピースを固定することができる。緊張は切羽側で行うために、セグメント内面に切欠を必要としない。セグメントリングの各PC鋼材を本緊張することにより推進方向及び円周方向プレストレスを確実に均一に導入することが可能である。緊張は、トルクレンチで緊張するために、緊張に要する作業は簡単、軽作業であり、また小さいスペースで済むと言う利点がある。
【図面の簡単な説明】
【図1】実施例のセグメントピースの模式的正面図である。
【図2】実施例のセグメントピースの組立工程図である。
【図3】実施例のセグメントピースの組立工程図である。
【図4】実施例のセグメントピースの組立工程図である。
【符号の説明】
2 PC鋼材
3 連結装置
31 掘削ヘッド
32 カッタービット
33 シールドジャッキ
34 電動又はエアトルクレンチ
43 油圧トルクレンチ
100 新設セグメントピース
110 既設セグメントリング[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method of assembling segment tunnel lining.
[0002]
[Prior art]
Conventionally, tunnel lining segments that introduce pre-stress form a segment ring, insert a circumferential strand over one circumference, and apply tension to this circumferential strand to form an integral ring However, this was pressed from the face side to the existing segment ring with a jack or the like to maintain the position, and a plurality of rows of integral rings were connected in the tunnel propulsion direction.
[0003]
When forming the above tunnel segment,
(1) While assembling the segment while pressing it against the existing segment ring with a shield jack from the face side, the segment ring is stable only after the circumferential strand is inserted. Met.
(2) In addition, the propulsion direction is strained by inserting a tension material through a plurality of rows of segment rings, but the operation is not easy.
(3) Since the circumferential tension of the segment ring is performed at one place on the circumference, it takes time to insert the circumferential strand, the notch provided in the anchoring segment is large, and the tension is strong and heavy equipment It was necessary to wear a jack, and workability was inferior.
[0004]
[Problems to be solved by the invention]
The present invention uses the tunnel lining for segments arranged an X-shape PC steel for the tunnel propulsion direction, so that assembly of the segment ring can be safely and stably carried out easily be The aim is to provide improved technology.
[0005]
[Means for Solving the Problems]
The present invention has been made to solve the above problems, is disposed in the segment through a substantially central portion in an X shape for the tunnel propulsion direction of the segment, the post having a connector on both ends using tunnel lining for segment with PC steel tension method provides a technique to work stably. Here, the arrangement in the X shape in the tunnel propulsion direction means that, in the development view of the segments, oblique PC steel materials having the same positive and negative inclination angles with respect to the tunnel propulsion direction are arranged on the adjacent segments and the back side. When the entire segment is attached, it means that the PC steel material is arranged in a rhombus network.
[0006]
The segment assembling method of the present invention is as follows. In other words, using a tunnel lining segment in which a post-tension PC steel material with connectors at both ends passes through the center of the segment and is arranged in the segment in an X shape with respect to the tunnel propulsion direction. Each segment piece of the segment ring is pressed against the existing segment ring with a shield jack from the face side one by one, and the PC steel material built in the pressed segment piece is connected to the end of the PC steel material of the existing segment ring, and a temporary tension is assumed. after completion of assembly of the newly established segment ring, while the entire the segment ring pressed together with the shield jack fixed to the tension the PC steel stress introduction and fixing of the tunnel propulsion direction and the circumferential direction of the segment A method for assembling a tunnel lining segment, which is achieved simultaneously.
[0007]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings.
[0008]
FIG. 1 is a schematic front view of a
[0009]
2 to 4 are process diagrams showing an assembly process of the
[0010]
FIG. 3 shows a state in which another
[0011]
【The invention's effect】
According to the present invention, a PC steel material is formed in an X shape in a segment piece and connected to an existing PC steel material, whereby the segment piece can be easily and safely connected to an existing segment ring. The segment piece can be fixed by temporarily tensioning the PC steel material. Since tension is applied on the face side, no cutout is required on the inner surface of the segment. It is possible to introduce the propulsion direction and the circumferential prestress uniformly evenly by fully tensioning each PC steel material of the segment ring. Since tension is tensioned with a torque wrench, there is an advantage that the work required for tension is simple and light, and requires a small space.
[Brief description of the drawings]
FIG. 1 is a schematic front view of a segment piece of an embodiment.
FIG. 2 is an assembly process diagram of the segment piece of the embodiment.
FIG. 3 is an assembly process diagram of the segment piece of the embodiment.
FIG. 4 is an assembly process diagram of the segment piece of the embodiment.
[Explanation of symbols]
2
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002102889A JP3798332B2 (en) | 2002-04-04 | 2002-04-04 | Method for assembling tunnel lining segments |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002102889A JP3798332B2 (en) | 2002-04-04 | 2002-04-04 | Method for assembling tunnel lining segments |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2003293697A JP2003293697A (en) | 2003-10-15 |
| JP3798332B2 true JP3798332B2 (en) | 2006-07-19 |
Family
ID=29242442
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2002102889A Expired - Lifetime JP3798332B2 (en) | 2002-04-04 | 2002-04-04 | Method for assembling tunnel lining segments |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3798332B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2005155010A (en) * | 2003-11-20 | 2005-06-16 | Kajima Corp | Prestressed concrete segment for tunnel lining |
| JP4452170B2 (en) * | 2004-12-17 | 2010-04-21 | 株式会社ピーエス三菱 | Construction method of shaft |
| CN113551986B (en) * | 2021-07-24 | 2024-01-19 | 郑州大学 | Indoor testing device and method for static soil pressure coefficient under complex stress state |
-
2002
- 2002-04-04 JP JP2002102889A patent/JP3798332B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2003293697A (en) | 2003-10-15 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3798332B2 (en) | Method for assembling tunnel lining segments | |
| CN115522750B (en) | Carbon fiber tendon anchor pre-tensioning and tensioning integrated system and pre-tensioning and tensioning method | |
| CN116122810A (en) | Pick-shaped cutting pick for coal rock exploitation and mounting and dismounting method thereof | |
| CN108708283B (en) | Method for installing bridge prestressed porous anchorage | |
| CN114833937B (en) | Casting mold for shield tunnel scale model and use method thereof | |
| CN110230498A (en) | A kind of fast disassembly type shield tail brush and tail sealing device of shield | |
| CN210369872U (en) | High mortise-tenon joint formula scaffold frame of security | |
| CN2856580Y (en) | Scraper wire rope connector | |
| CN116084280B (en) | Cable buckling and arranging device and cable buckling saddle system | |
| CN218953319U (en) | Shield constructs quick-witted pipe piece connecting device | |
| CN208326436U (en) | A kind of stage loader connector component | |
| CN220909726U (en) | A quick installation mechanism for steel arch frame used in tunnel | |
| JPH02153167A (en) | Built-up pc twist steel wire tenser, tension work thereof, retension work thereof, and jack chair | |
| CN223225089U (en) | Flat chain connecting ring for mining high-strength round-link chain | |
| CN219173362U (en) | Conveniently-detached chain connecting ring | |
| CN214303865U (en) | Tunnel big pipe shed reinforced structure | |
| JP2002013392A (en) | Shield tunnel lining method and segment for lining body | |
| JP2015040372A (en) | Inner form for cast-in-place lining concrete construction method by shield | |
| CN222256588U (en) | Guard plate for cement dry method rotary kiln with long service life | |
| CN105986548B (en) | A kind of low retraction anchorage tensioning equipment and method for stretching | |
| CN220365015U (en) | Auxiliary device of slope active protective net | |
| CN218540418U (en) | Prestressed steel strand releasing and tensioning device | |
| JPH0623512Y2 (en) | Track link device for tracked vehicle | |
| JP3771997B2 (en) | PC fixing device and PC fixing method | |
| RU2142563C1 (en) | Reusable roof pinning |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20051219 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20051227 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060227 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060411 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060419 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 3798332 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120428 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150428 Year of fee payment: 9 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| EXPY | Cancellation because of completion of term |