brine
liquid
heat exchanger
slurry
temperature
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP19805499A
Other languages
Japanese (ja)
Other versions
JP2001027468A (en
Inventor
剛 川口
和弘 関口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanyo Electric Co Ltd
Original Assignee
Sanyo Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanyo Electric Co Ltd filed Critical Sanyo Electric Co Ltd
Priority to JP19805499A priority Critical patent/JP3813384B2/en
Publication of JP2001027468A publication Critical patent/JP2001027468A/en
Application granted granted Critical
Publication of JP3813384B2 publication Critical patent/JP3813384B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Devices That Are Associated With Refrigeration Equipment (AREA)
  • Production, Working, Storing, Or Distribution Of Ice (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、液体、即ちブラインにて熱交換するブラインショーケースに関する。
【0002】
【従来の技術】
従来この種ショーケースとして、特開平10−274463号公報(F25D17/02)には、ブラインを用いて複数のショーケースの冷却を行うようにしたブラインを用いた冷却システムにおいて、ブラインチラーユニットと、 このブラインチラーユニットから流出するブラインを流す1次往路と前記前記ブラインチラーユニットに流入するブラインを流す1次復路とを閉回路に構成した1次回路と、この1次回路中にブラインを循環させる1次ポンプと、前記各ショーケースに設けられ、前記1次往路からブラインを取り込んで熱交換器に流す2次往路と前記熱交換器からブラインを1次復路に戻す2次復路とを有するに2次回路とを備えるブラインを用いた冷却システムが開示されている。
【0003】
そして、この冷却システムのブラインとしては、プロピレングリコールまたはエチレングリコールまたはエタノール等と水とを混合した不凍液を用いている。
【0004】
【発明が解決しようとする課題】
上述した様な従来技術では、不凍液を用いている関係上、ショーケースの冷却を行う場合、常にブラインチラーユニットにてブラインを冷却する必要がある。
【0005】
このため、外気温が高い時など、ブラインチラーユニットが所望の冷却能力を発揮しにくい場合、ショーケースの冷却不足となる恐れがある。
【0006】
本発明は上述した問題点に鑑みてなされたもので、冷却能力不足を極力防止することを目的としたブラインショーケースを提供する。
【0007】
【課題を解決するための手段】
上記目的を達成するための手段として、本発明の請求項1では、液体を用いてショーケースの冷却を行うようにしたものであって、冷凍機にて液体を冷却すると共に、冷凍して液体の一部を固体化させるスラリーブライン生成槽と、このスラリーブライン生成槽にて冷却された液体をショーケースの熱交換器に循環供給する搬送ポンプと、前記スラリーブライン生成槽内の上部の液体を前記熱交換器に供給するためのブライン供給管と、スラリーブライン生成槽内の下部の液体を熱交換器に供給するための下ブライン供給管とを備え、スラリーブライン生成槽と熱交換器との間に温度センサを設け、この温度センサの検知温度が所定温度以上であった場合、下ブライン供給管から液体を熱交換器に供給するブラインショーケースを提供する。
【0008】
この様に、スラリーブライン生成槽にて、液体の一部を液体の温度よりも更に低温とする事で固体化させ、この固体の融解潜熱で冷却された液体を熱交換器に循環供給する。
【0009】
また、スラリーブライン生成槽内では、固体がある場合、上部に位置する液体が低温で、下部に位置する液体は高温となるため、使い分けることができる。
【0010】
更に通常、冷却時には、スラリーブライン生成槽内の上部に位置する液体を熱交換器に送るが、スラリーブライン生成槽内の固体が溶けきってしまった場合、スラリーブライン生成槽内の下部に位置する液体の方が低温となるため、温度センサにて熱交換器に流入する液体の温度を検知し、所定温度以上であった場合、下ブライン供給管から液体を熱交換器に供給する。
【0011】
また、請求項2の発明では、搬送ポンプを複数台設けると共に、スラリーブライン生成槽と熱交換器との間に温度センサを設け、この温度センサの検知温度が所定温度以上であった場合、複数台の搬送ポンプを運転する請求項1記載のブラインショーケースを提供する。
【0012】
この様に、熱交換器に流入する液体の温度が所定温度以上となった場合、冷却能力不足を防止するため、複数台の搬送ポンプを運転して流量を増やす。
【0013】
また、請求項3の発明では、熱交換器のデフロスト直前は、下ブライン供給管から液体を熱交換器に供給する請求項2記載のブラインショーケースを提供する。
【0014】
この様に、デフロスト直前に、ブライン生成槽内のより高温の液体、即ち下部の液体を下ブライン供給管から熱交換器に供給して予熱しておく。
【0015】
【発明の実施の形態】
以下、本発明の実施の形態を図面に基づいて説明する。
【0016】
図1は本発明の冷却回路、図2は氷の有無によるポンプ及び電磁弁の動作図、図3はデフロスト時のポンプ及び電磁弁の動作図、図4はブライン温度と冷却時間の関係図、図5はブラインの製氷率とブライン温度の関係図である。
【0017】
図1に示す1は内部に液体(ブライン)、例えば水などを貯留するスラリーブライン生成槽で、このスラリーブライン生成槽1内には、冷凍機2に設けられた図示しない圧縮機、凝縮器と共に冷凍サイクルを形成する蒸発器3が設けられている。そして、この蒸発器3はスラリーブライン生成槽1のブライン上部に位置している。
【0018】
本発明の冷却回路には、前述したスラリーブライン生成槽1、店舗などに複数台設置されるショーケースの熱交換器4、4、4…、2台のブライン搬送ポンプ5A、5Bがブライン配管6にて接続されている。そして、これら熱交換器4、4、4…及びブライン搬送ポンプ5A、5Bは並列に接続されるものである。
【0019】
また、前記スラリーブライン生成槽1には、上部と下部に上ブライン供給管7と下ブライン供給管8が設けられており、これら各ブライン供給管7、8には電磁弁9A、9Bが設けられている。
【0020】
そして、前記各ブライン供給管7、8は、温度センサ10を備えた一本のブライン供給配管11に合流している。
【0021】
ここで、ブラインの流れは、図1中の矢印に示す方向に流れるものである。即ち、スラリーブライン生成槽1、ショーケースの熱交換器4、4、4…、ブライン搬送ポンプ5A、5Bと循環している。
【0022】
以上の構成にして、ブライン搬送ポンプ5A、5Bと電磁弁9A、9Bの動作などを図2乃至図5を参照して説明する。
【0023】
尚、特に一面以上が開口したオープンショーケースでは、営業終了後、ナイトカバーと称するカバーにて開口を覆いながら、弱冷却運転を行い、ショーケースに陳列された商品を保冷するものであり、扉を有するショーケースも同様に、夜間でも保冷運転を行うものである。
【0024】
本発明の場合、特に電力料金の安い夜間、積極的にブラインを固体化、即ち製氷しており、この際にも、ブラインの循環を行い、弱冷却運転を行っている。従って、ランニングコストの低減を図る事ができる。
【0025】
そして、図4に示す如く、プルダウン時などのブラインが全て液体の状態(図中、液体と記載のエリア)であれば、冷凍機2にて蒸発器3を冷却して製氷を行い、前記温度センサ10の検知温度が所定温度、即ち蒸発器3の周囲が氷結する温度帯となるまで(図中、固体と記載のエリア)冷却を継続する。そして、固体の状態では、冷凍機2による冷却は行わず、氷の融解潜熱でもってブラインの冷却を行っている。
【0026】
また、氷が融解して、固体の状態から液体、固体混合の状態(図中、液体+固体と記載のエリア)となり、極めて氷量が少ないと判断する温度になった場合、再度冷凍機2にて蒸発器3の冷却を行って製氷する。
【0027】
ここで、蒸発器3の冷却を開始し、図4中の液体の状態(図中、液体と記載のエリア)から液体、固体混合に移った後は、図5に示す如く、製氷率が上昇していく。
【0028】
以上の様に製氷されて氷がある通常運転状態では、図2に示す如く、ブライン搬送ポンプ5AがON、ブライン搬送ポンプ5BがOFFであり、上ブライン供給管7の電磁弁9Aが開で、下ブライン供給管8の電磁弁9Bが閉となっている。
【0029】
即ち、単一のブライン搬送ポンプ5Aのみでもって、スラリーブライン生成槽1の氷が有る上部からのブラインを、上ブライン供給管7から前記熱交換器4、4、4…に循環供給している。
【0030】
これは、前記スラリーブライン生成槽1の上部には氷が有り、この氷の融解潜熱でブライン温度が十分に低い状態であり、上ブライン供給管7から氷と熱交換した直後の冷水を前記熱交換器4、4、4…に送る事ができるためである。
【0031】
そして、所定時間経過する毎に、ブライン搬送ポンプ5AをOFF、ブライン搬送ポンプ5BをONというように、交互に切り替え運転を行う。この様に、所定時間毎の切り替え運転を行う事により、ブライン搬送ポンプ5A、5Bの寿命を延ばす事ができる。
【0032】
ここで、前述した氷量が少ないと判断する温度になった場合、蒸発器3が再度冷却されるが、すぐに氷は生成されないため、図2中点線で示す如く、ブライン搬送ポンプ5AがOFF、ブライン搬送ポンプ5BがONであれば、ブライン搬送ポンプ5BをONのまま、停止中のブライン搬送ポンプ5AをONにする。
【0033】
そして、このブライン搬送ポンプ5A、5B両方での運転は、蒸発器3の周囲が氷結する温度帯を、前記温度センサ10が検知するまで継続する。
【0034】
この様に、氷量が不足して冷却不足となる恐れがある場合、両方のブライン搬送ポンプ5A、5Bを運転してブライン循環量を増加させ、ショーケースの熱交換器4、4、4…の冷却能力の低下を極力防止する事ができる。
【0035】
更に、電磁弁9Aを閉じて、電磁弁9Bを開とする事で、氷の無くなったスラリーブライン生成槽1の底部側、即ちより低温のブラインを前記熱交換器4、4、4…に循環供給する。
【0036】
ここで、氷が無くなった状態では、暖かい水は上へ、冷たい水は下へくるため、スラリーブライン生成槽1内の底部側のブラインを循環供給する事で、前記熱交換器4、4、4…の冷却能力の低下を極力防止できる。
【0037】
次に、熱交換器4、4、4…のデフロスト時について、図3を参照して説明する。
【0038】
氷が有る状態の通常運転において、デフロスト直前の所定時間は、電磁弁9Aを閉じて、上ブライン供給管7からのより低温のブライン供給を停止し、電磁弁9Bを開いて、下ブライン供給管8からのより高温のブライン供給を開始する。
【0039】
これは、熱交換器4、4、4…のデフロストを速やかに行うため、予め予熱しておくために行う。
【0040】
そして、所定時間経過後、デフロスト運転に移行すると、ブライン搬送ポンプ5A、5Bの運転を停止し、下ブライン供給管8の電磁弁9Bを閉、上ブライン供給管7の電磁弁9Aを開とする。
【0041】
次いで、デフロスト運転終了後、ブライン搬送ポンプ5A、5Bの運転を再開する事で、すぐにスラリーブライン生成槽1内上部のより低温のブラインを熱交換器4、4、4…に供給する事ができる。
【0042】
従って、ショーケースに陳列する商品が、特に生鮮食品などの場合、デフロストによる熱の影響を極力防止する事ができる。
【0043】
尚、前述したデフロストは、熱交換器4、4、4…に取り付けられた電気ヒータなどにより行う事が一般的であるが、他の加熱手段を用いても良い。また、ブラインとして本実施形態では水を用いて説明したが、凍結可能であれば他の液体でも良い。更に、本実施形態では、循環するブライン温度を単一の温度センサ10にて検知しているが、スラリーブライン生成槽1内に静電容量センサなどの別のセンサを設けて、氷の有無を検知しても良い。
【0044】
【発明の効果】
以上詳述した如く、請求項1の発明によると、この様に、スラリーブライン生成槽にて、液体の一部を液体の温度よりも更に低温とする事で固体化させ、この固体の融解潜熱で冷却された液体を熱交換器に循環供給する。
【0045】
従って、安定して熱交換器の冷却を行うことができると共に、外気温が高くとも、所望の冷却能力を発揮する事ができる。
【0046】
また、スラリーブライン生成槽内では、固体がある場合、上部に位置する液体が低温で、下部に位置する液体は高温となる。
【0047】
従って、通常運転時は、より低温の液体を用い、デフロスト時はより高温の液体を用いるなどの使い分けができる。
【0048】
更に、通常、冷却時には、スラリーブライン生成槽内の上部に位置する液体を熱交換器に送るが、スラリーブライン生成槽内の固体が溶けきってしまった場合、スラリーブライン生成槽内の下部に位置する液体の方が低温となるため、温度センサにて熱交換器に流入する液体の温度を検知し、所定温度以上であった場合、下ブライン供給管から液体を熱交換器に供給する。
【0049】
従って、熱交換器には、スラリーブライン生成槽内の最適な位置の液体が供給されるため、所望の冷却能力を発揮する事ができる。
【0050】
請求項2の発明によると、熱交換器に流入する液体の温度が所定温度以上となった場合、冷却能力不足を防止するため、複数台の搬送ポンプを運転して流量を増やすため、熱交換器は所望の冷却能力を発揮する事ができる。
【0051】
請求項3の発明によると、デフロスト直前に、ブライン生成槽内のより高温の液体、即ち下部の液体を下ブライン供給管から熱交換器に供給して予熱しておく。
【0052】
従って、デフロストへの移行をスムーズに行う事ができる。
【図面の簡単な説明】
【図1】 本発明の冷却回路である。
【図2】 氷の有無によるポンプ及び電磁弁の動作図である。
【図3】 デフロスト時のポンプ及び電磁弁の動作図である。
【図4】 ブライン温度と冷却時間の関係図である。
【図5】 ブラインの製氷率とブライン温度の関係図である。
【符号の説明】
1 スラリーブライン生成槽
2 冷凍機
4 熱交換器
5A、5B 搬送ポンプ
7 上ブライン供給管
8 下ブライン供給管
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a brine showcase for heat exchange in a liquid, ie brine.
[0002]
[Prior art]
Conventionally, as this type of showcase, Japanese Patent Laid-Open No. 10-274463 (F25D17 / 02) discloses a cooling system using brine in which a plurality of showcases are cooled using brine, A primary circuit in which a primary forward path for flowing brine flowing out of the Blainchler unit and a primary return path for flowing brine flowing into the Blainchler unit are configured as a closed circuit, and the brine is circulated in the primary circuit. A primary pump, a secondary forward path that is provided in each showcase and takes in brine from the primary forward path and flows to the heat exchanger, and a secondary return path that returns the brine from the heat exchanger to the primary return path A cooling system using brine with a secondary circuit is disclosed.
[0003]
And as a brine of this cooling system, the antifreeze which mixed propylene glycol, ethylene glycol, ethanol, etc. and water is used.
[0004]
[Problems to be solved by the invention]
In the related art as described above, when the showcase is cooled because of the use of the antifreeze liquid, it is necessary to always cool the brine by the Blainchler unit.
[0005]
For this reason, there is a risk that the showcase will be insufficiently cooled when it is difficult for the Blinchler unit to exhibit the desired cooling capacity, such as when the outside air temperature is high.
[0006]
The present invention has been made in view of the above-described problems, and provides a brine showcase aimed at preventing a cooling capacity shortage as much as possible.
[0007]
[Means for Solving the Problems]
As means for achieving the above object, according to claim 1 of the present invention, the showcase is cooled using a liquid, and the liquid is cooled by a refrigerator and frozen to be liquid. A slurry brine generation tank that solidifies a part of the slurry brine, a transport pump that circulates the liquid cooled in the slurry brine generation tank to the heat exchanger of the showcase, and an upper liquid in the slurry brine generation tank. A brine supply pipe for supplying to the heat exchanger, and a lower brine supply pipe for supplying the lower liquid in the slurry brine generation tank to the heat exchanger, the slurry brine generation tank and the heat exchanger A temperature sensor is provided in between, and when the temperature detected by the temperature sensor is equal to or higher than a predetermined temperature, a brine showcase for supplying liquid from the lower brine supply pipe to the heat exchanger is provided.
[0008]
In this way, in the slurry brine generation tank, a part of the liquid is solidified by lowering the temperature of the liquid, and the liquid cooled by the solid latent heat of melting is circulated and supplied to the heat exchanger.
[0009]
Further, in the slurry brine generation tank, when there is a solid, the liquid located in the upper part is at a low temperature and the liquid located in the lower part is at a high temperature.
[0010]
Furthermore, normally, at the time of cooling, the liquid located in the upper part in the slurry brine generation tank is sent to the heat exchanger, but when the solid in the slurry brine generation tank has completely melted, it is located in the lower part in the slurry brine generation tank. Since the temperature of the liquid is lower, the temperature of the liquid flowing into the heat exchanger is detected by the temperature sensor. If the temperature is equal to or higher than the predetermined temperature, the liquid is supplied from the lower brine supply pipe to the heat exchanger.
[0011]
In the invention of claim 2, a plurality of transfer pumps are provided, a temperature sensor is provided between the slurry brine generation tank and the heat exchanger, and when the detected temperature of the temperature sensor is equal to or higher than a predetermined temperature, a plurality of transfer pumps are provided. The brine showcase according to claim 1, wherein the carrier pump is operated.
[0012]
As described above, when the temperature of the liquid flowing into the heat exchanger becomes equal to or higher than a predetermined temperature, a plurality of transport pumps are operated to increase the flow rate in order to prevent the cooling capacity from being insufficient.
[0013]
According to a third aspect of the present invention, there is provided the brine showcase according to the second aspect, wherein the liquid is supplied from the lower brine supply pipe to the heat exchanger immediately before the defrost of the heat exchanger.
[0014]
Thus, immediately before defrosting, the higher temperature liquid in the brine generation tank, that is, the lower liquid is supplied from the lower brine supply pipe to the heat exchanger and preheated.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0016]
FIG. 1 is a cooling circuit of the present invention, FIG. 2 is an operation diagram of a pump and a solenoid valve according to the presence or absence of ice, FIG. 3 is an operation diagram of the pump and the solenoid valve at the time of defrosting, and FIG. FIG. 5 is a relationship diagram of the ice making rate of brine and the brine temperature.
[0017]
1 is a slurry brine generation tank 1 for storing a liquid (brine), for example, water, etc., in the slurry brine generation tank 1, together with a compressor and a condenser (not shown) provided in the refrigerator 2. An evaporator 3 forming a refrigeration cycle is provided. The evaporator 3 is located above the brine in the slurry brine generation tank 1.
[0018]
In the cooling circuit of the present invention, the above-described slurry brine generation tank 1, a plurality of showcase heat exchangers 4, 4, 4,... Connected at. These heat exchangers 4, 4, 4,... And brine transfer pumps 5A, 5B are connected in parallel.
[0019]
The slurry brine generation tank 1 is provided with an upper brine supply pipe 7 and a lower brine supply pipe 8 at the upper and lower parts, and the brine supply pipes 7 and 8 are provided with electromagnetic valves 9A and 9B. ing.
[0020]
The brine supply pipes 7 and 8 are joined to a single brine supply pipe 11 provided with a temperature sensor 10.
[0021]
Here, the flow of the brine flows in the direction indicated by the arrow in FIG. That is, it circulates with the slurry brine production tank 1, the heat exchangers 4, 4, 4,... Of the showcase, and the brine transfer pumps 5A, 5B.
[0022]
The operation of the brine transport pumps 5A, 5B and the electromagnetic valves 9A, 9B, etc., with the above configuration will be described with reference to FIGS.
[0023]
In particular, in an open showcase with one or more sides open, after the end of business, the door is covered with a cover called a night cover and a weak cooling operation is performed to keep the products displayed in the showcase cold. Similarly, a showcase having a refrigeration operation is also performed at night.
[0024]
In the case of the present invention, the brine is actively solidified, that is, ice-making, especially at night when the electricity rate is low, and at this time, the brine is circulated and the weak cooling operation is performed. Accordingly, the running cost can be reduced.
[0025]
Then, as shown in FIG. 4, if the brine at the time of pull-down is all in a liquid state (in the drawing, the area described as liquid), the evaporator 3 is cooled in the refrigerator 2 to make ice, and the temperature Cooling is continued until the detected temperature of the sensor 10 reaches a predetermined temperature, that is, a temperature zone in which the periphery of the evaporator 3 is frozen (in the drawing, an area described as solid). In the solid state, the cooling by the refrigerator 2 is not performed, and the brine is cooled by the melting latent heat of ice.
[0026]
In addition, when the ice melts and changes from a solid state to a liquid / solid mixture state (in the figure, an area described as liquid + solid) and reaches a temperature at which it is determined that the amount of ice is extremely small, the refrigerator 2 is again used. To cool the evaporator 3 and make ice.
[0027]
Here, the cooling of the evaporator 3 is started, and after moving from the liquid state in FIG. 4 (area indicated as “liquid” in the figure) to the liquid / solid mixing, the ice making rate increases as shown in FIG. I will do it.
[0028]
In the normal operation state where ice is made and ice is present as described above, the brine transfer pump 5A is ON, the brine transfer pump 5B is OFF, and the electromagnetic valve 9A of the upper brine supply pipe 7 is open, as shown in FIG. The electromagnetic valve 9B of the lower brine supply pipe 8 is closed.
[0029]
That is, the brine from the upper part where the ice in the slurry brine generation tank 1 is circulated is supplied from the upper brine supply pipe 7 to the heat exchangers 4, 4, 4. .
[0030]
This is because ice is present in the upper portion of the slurry brine generation tank 1 and the brine temperature is sufficiently low due to the latent heat of melting of the ice, and the cold water immediately after heat exchange with ice from the upper brine supply pipe 7 is heated to the heat. This is because it can be sent to the exchanges 4, 4, 4.
[0031]
Then, every time a predetermined time elapses, the switching operation is alternately performed such that the brine transfer pump 5A is turned OFF and the brine transfer pump 5B is turned ON. In this way, the life of the brine transfer pumps 5A and 5B can be extended by performing the switching operation every predetermined time.
[0032]
Here, when the temperature at which it is determined that the amount of ice is small is reached, the evaporator 3 is cooled again, but since ice is not immediately generated, the brine transfer pump 5A is turned off as indicated by the dotted line in FIG. If the brine transfer pump 5B is ON, the stopped brine transfer pump 5A is turned ON while the brine transfer pump 5B remains ON.
[0033]
The operation of both the brine transfer pumps 5A and 5B is continued until the temperature sensor 10 detects a temperature zone in which the periphery of the evaporator 3 is frozen.
[0034]
In this way, when there is a possibility that the ice amount is insufficient and the cooling is insufficient, both brine transfer pumps 5A, 5B are operated to increase the brine circulation amount, and the showcase heat exchangers 4, 4, 4,. It is possible to prevent a decrease in the cooling capacity as much as possible.
[0035]
Further, by closing the electromagnetic valve 9A and opening the electromagnetic valve 9B, the bottom side of the slurry brine generating tank 1 without ice, that is, the cooler brine is circulated to the heat exchangers 4, 4, 4,. Supply.
[0036]
Here, in the state where the ice has disappeared, since warm water goes up and cold water goes down, the heat exchangers 4, 4, It is possible to prevent a decrease in the cooling capacity of 4.
[0037]
Next, the defrosting of the heat exchangers 4, 4, 4,... Will be described with reference to FIG.
[0038]
In normal operation with ice, for a predetermined time immediately before defrosting, the solenoid valve 9A is closed, the cooler brine supply from the upper brine supply pipe 7 is stopped, the solenoid valve 9B is opened, and the lower brine supply pipe is opened. Start hotter brine feed from 8.
[0039]
This is performed in order to preheat the heat exchangers 4, 4, 4,.
[0040]
When the defrost operation is started after a predetermined time has elapsed, the operation of the brine transport pumps 5A and 5B is stopped, the electromagnetic valve 9B of the lower brine supply pipe 8 is closed, and the electromagnetic valve 9A of the upper brine supply pipe 7 is opened. .
[0041]
Next, after the defrost operation is completed, the operation of the brine transfer pumps 5A, 5B is restarted, so that the lower temperature brine in the upper part of the slurry brine generation tank 1 can be immediately supplied to the heat exchangers 4, 4, 4,. it can.
[0042]
Therefore, when the goods displayed in the showcase are fresh foods in particular, the influence of heat due to defrost can be prevented as much as possible.
[0043]
In addition, although it is common to perform the defrost mentioned above with the electric heater etc. which were attached to the heat exchangers 4, 4, 4, ..., you may use another heating means. In the present embodiment, water is used as the brine, but other liquids may be used as long as they can be frozen. Furthermore, in the present embodiment, the circulating brine temperature is detected by the single temperature sensor 10, but another sensor such as a capacitance sensor is provided in the slurry brine generation tank 1 to check the presence or absence of ice. It may be detected.
[0044]
【The invention's effect】
As described above in detail, according to the invention of claim 1, in this way, in the slurry brine generation tank, a part of the liquid is solidified by making it lower than the temperature of the liquid, and the latent heat of fusion of this solid The liquid cooled in step 1 is circulated and supplied to the heat exchanger.
[0045]
Therefore, the heat exchanger can be stably cooled, and a desired cooling capacity can be exhibited even when the outside air temperature is high.
[0046]
Further, in the slurry brine generation tank, when there is a solid, the liquid located in the upper part has a low temperature and the liquid located in the lower part has a high temperature.
[0047]
Accordingly, it is possible to properly use a lower temperature liquid during normal operation and a higher temperature liquid during defrost.
[0048]
Furthermore, normally, at the time of cooling, the liquid located in the upper part of the slurry brine generation tank is sent to the heat exchanger, but when the solid in the slurry brine generation tank has completely melted, the liquid is positioned in the lower part of the slurry brine generation tank. Since the temperature of the liquid is lower, the temperature of the liquid flowing into the heat exchanger is detected by the temperature sensor, and when the temperature is equal to or higher than the predetermined temperature, the liquid is supplied to the heat exchanger from the lower brine supply pipe.
[0049]
Therefore, since the liquid at the optimum position in the slurry brine generation tank is supplied to the heat exchanger, a desired cooling capacity can be exhibited.
[0050]
According to the invention of claim 2, when the temperature of the liquid flowing into the heat exchanger becomes equal to or higher than a predetermined temperature, in order to prevent insufficient cooling capacity, heat exchange is performed to increase the flow rate by operating a plurality of transport pumps. The vessel can exhibit the desired cooling capacity.
[0051]
According to the invention of claim 3, immediately before defrosting, the higher temperature liquid in the brine generation tank, that is, the lower liquid is supplied from the lower brine supply pipe to the heat exchanger and preheated.
[0052]
Therefore, the transition to defrost can be performed smoothly.
[Brief description of the drawings]
FIG. 1 is a cooling circuit according to the present invention.
FIG. 2 is an operation diagram of a pump and a solenoid valve with and without ice.
FIG. 3 is an operation diagram of a pump and a solenoid valve at the time of defrosting.
FIG. 4 is a relationship diagram between brine temperature and cooling time.
FIG. 5 is a diagram showing the relationship between the ice making rate of brine and the brine temperature.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Slurry brine production tank 2 Refrigerator 4 Heat exchanger 5A, 5B Conveyance pump 7 Upper brine supply pipe 8 Lower brine supply pipe

Claims (3)

液体を用いてショーケースの冷却を行うようにしたブラインショーケースにおいて、冷凍機にて液体を冷却すると共に、冷凍して液体の一部を固体化させるスラリーブライン生成槽と、このスラリーブライン生成槽にて冷却された液体をショーケースの熱交換器に循環供給する搬送ポンプと、前記スラリーブライン生成槽内の上部の液体を前記熱交換器に供給するためのブライン供給管と、スラリーブライン生成槽内の下部の液体を熱交換器に供給するための下ブライン供給管とを備え、スラリーブライン生成槽と熱交換器との間に温度センサを設け、この温度センサの検知温度が所定温度以上であった場合、下ブライン供給管から液体を熱交換器に供給することを特徴とするブラインショーケース。 In a brine showcase in which the showcase is cooled using a liquid, the slurry brine generation tank that cools the liquid with a refrigerator and solidifies a part of the liquid by freezing, and the slurry brine generation tank A pump for circulating and supplying the liquid cooled in the heat exchanger of the showcase, a brine supply pipe for supplying the upper liquid in the slurry brine generation tank to the heat exchanger, and a slurry brine generation tank A lower brine supply pipe for supplying the lower liquid in the heat exchanger to the heat exchanger, and a temperature sensor is provided between the slurry brine generation tank and the heat exchanger, and the detected temperature of the temperature sensor is a predetermined temperature or higher. If present, the brine showcase is characterized in that liquid is supplied to the heat exchanger from the lower brine supply pipe. 搬送ポンプを複数台設けると共に、スラリーブライン生成槽と熱交換器との間に温度センサを設け、この温度センサの検知温度が所定温度以上であった場合、複数台の搬送ポンプを運転することを特徴とする請求項1記載のブラインショーケース。  In addition to providing a plurality of transport pumps, a temperature sensor is provided between the slurry brine generation tank and the heat exchanger. The brine showcase according to claim 1, wherein: 熱交換器のデフロスト直前は、下ブライン供給管から液体を熱交換器に供給することを特徴とする請求項2記載のブラインショーケース。  The brine showcase according to claim 2, wherein the liquid is supplied from the lower brine supply pipe to the heat exchanger immediately before defrosting of the heat exchanger.
JP19805499A 1999-07-12 1999-07-12 Brine showcase Expired - Fee Related JP3813384B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19805499A JP3813384B2 (en) 1999-07-12 1999-07-12 Brine showcase

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19805499A JP3813384B2 (en) 1999-07-12 1999-07-12 Brine showcase

Publications (2)

Publication Number Publication Date
JP2001027468A JP2001027468A (en) 2001-01-30
JP3813384B2 true JP3813384B2 (en) 2006-08-23

Family

ID=16384773

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19805499A Expired - Fee Related JP3813384B2 (en) 1999-07-12 1999-07-12 Brine showcase

Country Status (1)

Country Link
JP (1) JP3813384B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002303440A (en) * 2001-03-30 2002-10-18 Sanyo Electric Co Ltd Ice storage system

Also Published As

Publication number Publication date
JP2001027468A (en) 2001-01-30

Similar Documents

Publication Publication Date Title
US9127873B2 (en) Temperature controlled compartment and method for a refrigerator
CN102954645B (en) Refrigerator
US5941085A (en) Refrigerator having an apparatus for defrosting
US20090293508A1 (en) Refrigerator including high capacity ice maker
US7814763B2 (en) Refrigeration appliance with a water dispenser
JP2019138510A (en) refrigerator
JP3813384B2 (en) Brine showcase
JP4033219B2 (en) vending machine
KR101209482B1 (en) Refrigeration show case having the thermal storage system
JP5157418B2 (en) vending machine
JP4103384B2 (en) refrigerator
JP3695888B2 (en) Cooling system using brine
JP2000205731A (en) Cooling system employing brine
JP2002213832A (en) Cooling system
JPH08285440A (en) Refrigerator
KR970002649B1 (en) Defrost Control Method of High Case Management Showcase
JP3856572B2 (en) Heat storage system
JPS6225660Y2 (en)
JP3710982B2 (en) Brine showcase
JP3742043B2 (en) Apparatus and method for removing frost and ice from cooler in cooling facility
JP2017058940A (en) Vendor
JP3326685B2 (en) Refrigeration methods for open showcases, refrigerators, etc.
JPH0618107A (en) Ice / hot water double heat storage system
JP2001263737A (en) Cold storage device for cold reserving compartment
JP2019138509A (en) refrigerator

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040507

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20051101

RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7421

Effective date: 20051226

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20051227

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060111

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060516

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060531

LAPS Cancellation because of no payment of annual fees