JP3843592B2 - Construction management method for cast concrete - Google Patents

Construction management method for cast concrete Download PDF

Info

Publication number
JP3843592B2
JP3843592B2 JP08900198A JP8900198A JP3843592B2 JP 3843592 B2 JP3843592 B2 JP 3843592B2 JP 08900198 A JP08900198 A JP 08900198A JP 8900198 A JP8900198 A JP 8900198A JP 3843592 B2 JP3843592 B2 JP 3843592B2
Authority
JP
Japan
Prior art keywords
concrete
management method
construction management
height
cast concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP08900198A
Other languages
Japanese (ja)
Other versions
JPH11287045A (en
Inventor
隆祥 平田
岳 若松
茂幸 十河
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP08900198A priority Critical patent/JP3843592B2/en
Publication of JPH11287045A publication Critical patent/JPH11287045A/en
Application granted granted Critical
Publication of JP3843592B2 publication Critical patent/JP3843592B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Investigating Or Analyzing Materials By The Use Of Electric Means (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は、打設コンクリートの施工管理方法に関し、特に、客観的なデータに基づいて打設コンクリートの品質を保証する施工管理方法に関するものである。
【0002】
【従来の技術】
性能規定により設計されたコンクリート構造物の品質保証を行うためには、その構造物の個々の性能が、要求性能を満たしている品質であることを客観的に証明する必要がある。
【0003】
このような品質保証を行う際には、コンクリートの硬化後に破壊試験を行うことができないので、コンクリートの打設段階における施工管理が非常に重要になる。
【0004】
コンクリートの打設段階の施工管理では、以下に示す3つの項目が品質保証を行う際に必要となる。
▲1▼.打込み材料の確認(コンクリートとブリーディング水,雨水,油,もしくは材料がない状態の識別)
▲2▼.コンクリート打設の締固め度
▲3▼.コールドジョイントの発生の有無
このような項目の施工管理を行う手段としては、例えば、コンクリート打設の締固め度は、締固めを担当している技術者が、目視により局所的な打設状態を観察することにより行っている。
【0005】
しかしながら、このような従来の施工管理方法には、以下に説明する技術的な問題があった。
【0006】
【発明が解決しようとする課題】
すなわち、技術者による目視観察では、一回に多量のコンクリートを打設する場合には、技術者の目が隅々まで行き届かないことが多く、このような施工管理方法では、第三者が客観的に判断することができないので、コンクリート構造物の品質保証としては、極めて不十分なものであった。
【0007】
ところで、近年、自己充填性を有し、締固めの不要な高流動コンクリートが開発され、普及し始めている。高流動コンクリートでは、締固めが不要なので、施工管理においては、締固め度の測定は不要になるものの、充填状況の把握が重要な要件となるので、電気抵抗や静電容量式のセンサーを用いて、局所的な充填状況を測定している。
【0008】
ところが、このようなセンサーを用いたとしても、コンクリート構造物全体の品質保証を担保することができないという問題があった。
【0009】
本発明は、このような問題点に鑑みてなされたものであって、その目的とするところは、客観的な判断が可能なデータに基づいて品質保証が行えるコンクリート打設の施工管理方法を提供することにある。
【0010】
【課題を解決するための手段】
上記目的を達成するために、本発明は、打設コンクリートの施工管理方法において、打設されるコンクリートの高さ方向に沿って対向延設される一対の電極棒を備えたレベルセンサーを設置し、1つの前記レベルセンサーで、前記電極棒間の静電容量に基づいて、前記コンクリートの打込み材料を確認し、前記静電容量の変化に基づいて、前記打設コンクリートの打ち上がり高さを測定し、打設されたコンクリートの締固め前後の前記静電容量の変化からコンクリートの締固め度を求め、前記打ち上がり高さの経時的変化を測定することにより、コールドジョイントの発生可能性の有無を判断するようにした。
このように構成した打設コンクリートの施工管理方法によれば、レベルセンサーの電極棒間の静電容量に基づいて、コンクリートの打込み材料を確認し、静電容量の変化に基づいて、打設コンクリートの打ち上がり高さを測定し、打設されたコンクリートの締固め前後の静電容量の変化からコンクリートの締固め度を求め、打ち上がり高さの経時的変化を測定することにより、コールドジョイントの発生の有無を判断するので、第三者が客観的に施工状態を確認することができる。
ここで、本発明のコンクリートの打込み材料の確認は、コンクリートとブリーディング水,雨水,油,もしくは材料がない状態の識別を意味している。
前記打設コンクリートは、高流動コンクリートであって、打設方向に配置された圧送管に設けられた開閉可能な複数の投入口から打設され、前記電極棒を前記投入口の前後に配置して、前記打ち上がり高さを測定することができる。
この構成によれば、高流動コンクリートの流動距離を管理することができる。
【0011】
【発明の実施の形態】
以下、本発明の好適な実施の形態について、添付図面に基づいて詳細に説明する。図1は、本発明にかかる打設コンクリートの施工管理方法の一実施例を示している。
【0012】
同図に示した施工管理方法は、LNGタンクの防液堤の施工に本発明を適用した場合を示している。同防液堤は、高さが約38m,内径が約84m,壁厚が約80cmの円筒形であり、打設コンクリートの1回の打ち込み高さが約4.3mであって、高さ方向に沿って9ロットに分け、かつ、周方向に沿って6分化さした状態でコンクリートを打設する。
【0013】
本実施例の施工管理方法では、打設コンクリート中に少なくとも一対のレベルセンサー10を設置して、レベルセンサー10間の静電容量の変化に基づく残留電圧の違いを測定する。
【0014】
ここで、本発明者らは、高流動コンクリートで実用化されているコンクリート充填感知センサでは、鉄筋が交錯し、散水や振動がある施工現場で、数メートルの高さが可能で、かつ、経済的に多数点での計測結果が得られる適当なセンサがないことを知得し、図2に示すようなレベルセンサー10を試作し、予備実験をすることにした。
【0015】
図2に示したレベルセンサー10は、一対の対向配置された電極棒10aと、凹形断面の電極支持板10bとを備えている。電極棒10aは、実施工に即して4.5mの長さを有し、下端と上端側とが間隔保持用の固定部材10cにより支持板10bに固定されている。
【0016】
電極棒10aの上端は、中継端子ボックス10dに接続され、中継端子ボックス10dからは、電極棒10aと個別に電気的に接続されたケーブル10eが延設されている。
【0017】
このケーブル10eには、図6に示す、スイッチボックス12,データロガー14,パソコン16が接続されている。スイッチボックス12は、電極棒10aに設定された電圧を印加するとともに、スイッチの切替により、電極棒10a間の出力電圧を取出す。
【0018】
データロガー14は、スイッチボックス12から送出されるデータを収集する。パソコン16は、データロガー14で収集されたデータに必要な演算処理を施し、打ち上がり高さなどをグラフィック表示する。
【0019】
予備実験では、水:セメント:細骨材を1:1:3の質量比で練り混ぜたモルタルを、15分毎に下端側から10cmずつ増加させ、1時間当たり40cmの速度で、打ち上がり高さが高くなるようにした。
【0020】
この予備試験で用いたレベルセンサー10の打ち上がり高さの測定原理は、以下のように説明される。フレッシュコンクリート(モルタル)中には、多数のイオンが存在しており、電極棒10a間にコンクリートが介在すると、コンクリートを電解質とするコンデンサが形成される。
【0021】
このコンデンサは、コンクリートの打ち上がりに伴って変化するので、レベルセンサー10は、図3に示すように、ある電気抵抗(固有抵抗)を有するコンデンサが並列に接続されたものと考えられる。
【0022】
つまり、コンクリートが電極棒10a間に打設されて、打ち上がり高さが高くなるに従って、並列接続されるコンデンサの数が増し、静電容量が大きくなる。
【0023】
このような静電容量の変化を測定すると、コンクリートの打ち上がり高さが判る。そこで、まず、電極棒10a間に一定電圧を一定時間印加し、電極棒10aに電荷を与え、一定時間経過後に電極棒10a間の電圧を測定することにした。
【0024】
この計測回路の模式図を図4に示している。この計測回路では、Vin≒E(t)と、Vout=E(t)/(R+2r)×Rの関係が成り立つ。ただし、Vin:印加電圧,Vout:出力電圧,E(t):充電電圧,R:固定抵抗,r:固有抵抗
そこで、予備試験では、まず、データロガー14からスイッチボックス12を介して、電極棒10a間にVin=2vの直流電圧を20msec印加した後に、80msecの非印加時間を設ける方式で、1回の計測に付きこれを21回繰り返すようにした。
【0025】
そして、別のチャンネルを用いて、電圧の印加終了後180msec経過した後の電極棒10a間の出力電圧Voutを側と測定した。このときの測定結果を図4に示している。
【0026】
図5に示した結果から明らかなように、電極棒10a間の出力電圧Voutとモルタルの打ち上がり高さとが、ほぼ比例関係に近い3次曲線となり、このような方式でコンクリートの打ち上がり高さの測定ができることを確認した。
【0027】
また、上述した測定原理に基づくレベルセンサー10では、測定原理が電極棒10a間に介在する測定対象材料の充電特性に依存しているため、材料の種類が異なる較正曲線を予め作成しておくと、コンクリートの使用材料を確認することができるとともに、より一層正確にンクリートの打ち上がり高さを測定することができる。
【0028】
以上の予備試験を踏まえて、防液堤に対する実施工では、図1に●示すように、全周のほぼ1/6、周長さが45mの範囲内に、全長が約7mの電極棒(L0〜L8)10aを9本設置した。
【0029】
各電極棒10aは、図6に示すように、打設コンクリートの圧送配管20に設けられた開閉可能な投入口22を挟んで、その両側に位置するように配置した。
【0030】
電極棒10aには、スイッチボックス12,データロガー14,パソコン16が接続されている。また、各投入口22には、電動ゲートバルブ24が設けられていて、この電動ゲートバルブ24は、パソコン16から送出される制御信号により、その開閉度合いがコントロールされる。
【0031】
実施工に用いた打設コンクリートは、低熱ポルトランドセメントと膨張材とを併用したスランプフロー65cm,設計基準強度60N/mm2の自己充填性を有する高強度,高流動コンクリートである。
【0032】
各電極棒10aの印加電圧および出力電圧の測定は、上述した予備試験と同じ条件で打設コンクリートの打ち上がり高さを測定した。図7に各電極棒10aの測定結果の平均値を示している。
【0033】
図8および図9は、測定区間における施工状態のモニタ画面(パソコン16)の一例を示している。このようなモニタリングを行うと、以下の制御が可能になる。
【0034】
(1)モニタ画像により、防液堤を構築する際の全般的なコンクリートの打設状態が把握できるとともに、型枠内のコンクリートの平均打ち上がり速度をリアルタイムに確認することができ、図8,9に示した例では、平均打ち上がり速度が1m/hで、安定したコンクリートの打設が行われたことを客観的に判断することができる。
【0035】
(2)モニタ画像を見て、ある打設個所が著しく速く打ち上がったり、あるいは、遅く打ち上がる場合には、型枠の変形や偏荷重を回避するために、パソコン16から電動ゲートバルブ24に制御信号を送出して、バルブ24の開度を調節して、このような不都合を回避することができる。
【0036】
(3)打設コンクリートの品質面では、図8に示すように、ある個所の30分当たりの変化量を求めることにより、打ち上がりが停止している個所を見つけ出すことができるため、コールドジョイントの発生の有無は、直接確認できないものの、投入口22の制御により、その発生を回避することができる。
【0037】
(4)電極棒10aが設置された区間のそれぞれの流動勾配の変化が、図10に示すように求められるので、簡易的に打設中の高流動コンクリートのスランプフローの程度を判断することができる。
【0038】
なお、上記実施例では、高流動コンクリートを用いた防液堤の構築に本発明を適用したので、締固め度合いの測定は、行わなかったが、締固めが必要なコンクリートを用いた場合には、締固め作業の前後で静電容量,残留電圧の変化を測定すると、客観的な締固め度の確認も可能である。
【0041】
【発明の効果】
以上、詳細に説明したように、本発明にかかる打設コンクリートの施工管理方法によれば、客観的な判断が可能なデータに基づいて品質保証が行える。
【図面の簡単な説明】
【図1】本発明にかかる打設コンクリートの施工管理方法を適用した防液堤の平面説明図である。
【図2】本発明にかかる施工管理方法で用いる電極の一例を示す平面図と側面図である。
【図3】同電極の測定原理を示す説明図である。
【図4】同電極の測定状態の電気回路の説明図である。
【図5】同電極を用いたモルタルの打ち上がり高さの測定結果を示すグラフである。
【図6】図1に示した防液堤における施工管理方法に用いる装置類の全体配置図である。
【図7】図6に示した施工管理の方法における打設コンクリートの打ち上がり高さの経時変化を示すグラフである。
【図8】図6に示した施工管理方法における打設コンクリートの打ち上がり高さのモニタ画面の一例を示す図である。
【図9】図6に示した施工管理方法における打設コンクリートの打ち上がり高さのモニタ画面の他の例を示す図である。
【図10】図6に示した施工管理方法における電極棒間の勾配の経時変化を示すグラフである。
【符号の説明】
10 電極
10a 電極棒
12 スイッチボックス
14 データロガー
16 パソコン
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction management method for cast concrete, and more particularly to a construction management method for guaranteeing the quality of cast concrete based on objective data.
[0002]
[Prior art]
In order to guarantee the quality of a concrete structure designed according to the performance regulations, it is necessary to objectively prove that the individual performance of the structure satisfies the required performance.
[0003]
When such quality assurance is performed, a destructive test cannot be performed after the concrete is hardened. Therefore, construction management at the concrete placing stage is very important.
[0004]
In the construction management at the concrete placement stage, the following three items are necessary for quality assurance.
(1). Confirmation of driving material (identification of concrete and bleeding water, rainwater, oil, or no material)
(2). Concrete compaction degree (3). Presence or absence of occurrence of cold joints As a means of performing construction management of such items, for example, the degree of compaction of concrete placement is determined by the engineer in charge of compaction by checking the local placement state visually. This is done by observing.
[0005]
However, such a conventional construction management method has the following technical problems.
[0006]
[Problems to be solved by the invention]
That is, in visual observation by engineers, when placing a large amount of concrete at once, the engineer's eyes often do not reach every corner. Since it cannot be judged objectively, the quality assurance of the concrete structure was extremely insufficient.
[0007]
By the way, in recent years, high-fluidity concrete that has self-filling properties and does not need to be compacted has been developed and is beginning to spread. In high-fluidity concrete, compaction is not required, so it is not necessary to measure the degree of compaction in construction management, but grasping the filling status is an important requirement, so electrical resistance and capacitance sensors are used. The local filling situation is measured.
[0008]
However, even if such a sensor is used, there is a problem that quality assurance of the entire concrete structure cannot be guaranteed.
[0009]
The present invention has been made in view of such problems, and an object of the present invention is to provide a concrete placement construction management method capable of quality assurance based on data capable of objective judgment. There is to do.
[0010]
[Means for Solving the Problems]
In order to achieve the above-mentioned object, the present invention provides a method for managing construction of cast concrete, in which a level sensor including a pair of electrode rods extending opposite to each other along the height direction of the cast concrete is installed. One level sensor checks the concrete placement material based on the capacitance between the electrode bars, and measures the height of the cast concrete based on the change in capacitance. The presence or absence of the possibility of the occurrence of cold joints is obtained by determining the degree of compaction of the concrete from the change in capacitance before and after compacting the placed concrete and measuring the change over time in the launch height. Judgment was made.
According to the construction management method for the cast concrete thus configured, the concrete placement material is confirmed based on the capacitance between the electrode rods of the level sensor, and the cast concrete is determined based on the change in the capacitance. By measuring the launch height of the concrete, determining the degree of compaction of the concrete from the change in capacitance before and after compaction of the placed concrete, and measuring the time-dependent change in the launch height, Since the presence or absence of occurrence is judged, a third party can objectively confirm the construction state.
Here, the confirmation of the placing material of the concrete of the present invention means the identification of the state where there is no concrete and bleeding water, rainwater, oil or material.
The cast concrete is high-fluidity concrete, and is placed from a plurality of openable / closable inlets provided in a pressure feed pipe arranged in a placement direction, and the electrode rods are arranged before and after the inlet. Thus, the launch height can be measured.
According to this structure, the flow distance of the high fluidity concrete can be managed.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, preferred embodiments of the invention will be described in detail with reference to the accompanying drawings. FIG. 1 shows an embodiment of a construction management method for cast concrete according to the present invention.
[0012]
The construction management method shown in the figure shows a case where the present invention is applied to construction of a LNG tank breakwater. The breakwater has a cylindrical shape with a height of about 38m, an inner diameter of about 84m, and a wall thickness of about 80cm. The concrete is placed in a state of being divided into 9 lots along the line and divided into 6 lots along the circumferential direction.
[0013]
In the construction management method of the present embodiment, at least a pair of level sensors 10 are installed in the cast concrete, and a difference in residual voltage based on a change in capacitance between the level sensors 10 is measured.
[0014]
Here, the inventors of the present invention have a concrete filling sensor that has been put to practical use in high-fluidity concrete. Therefore, it was learned that there is no suitable sensor that can obtain measurement results at many points, and a level sensor 10 as shown in FIG.
[0015]
The level sensor 10 shown in FIG. 2 includes a pair of opposed electrode rods 10a and an electrode support plate 10b having a concave cross section. The electrode rod 10a has a length of 4.5 m in accordance with the work, and a lower end and an upper end side are fixed to the support plate 10b by a fixing member 10c for maintaining a gap.
[0016]
The upper end of the electrode rod 10a is connected to a relay terminal box 10d, and a cable 10e electrically connected to the electrode rod 10a is extended from the relay terminal box 10d.
[0017]
A switch box 12, a data logger 14, and a personal computer 16 shown in FIG. 6 are connected to the cable 10e. The switch box 12 applies a set voltage to the electrode rod 10a and takes out an output voltage between the electrode rods 10a by switching the switch.
[0018]
The data logger 14 collects data sent from the switch box 12. The personal computer 16 performs necessary arithmetic processing on the data collected by the data logger 14 and graphically displays the launch height and the like.
[0019]
In the preliminary experiment, mortar in which water: cement: fine aggregate was mixed at a mass ratio of 1: 1: 3 was increased by 10 cm from the lower end side every 15 minutes, and the launch height was increased at a rate of 40 cm per hour. The height was made higher.
[0020]
The measurement principle of the launch height of the level sensor 10 used in this preliminary test will be described as follows. A large number of ions are present in fresh concrete (mortar), and when concrete is interposed between the electrode bars 10a, a capacitor using concrete as an electrolyte is formed.
[0021]
Since this capacitor changes as concrete is launched, it is considered that the level sensor 10 has capacitors having a certain electric resistance (specific resistance) connected in parallel as shown in FIG.
[0022]
That is, as concrete is placed between the electrode rods 10a and the launch height increases, the number of capacitors connected in parallel increases and the capacitance increases.
[0023]
When such a change in capacitance is measured, the concrete launch height can be determined. Therefore, first, a constant voltage is applied between the electrode rods 10a for a certain period of time, an electric charge is applied to the electrode rods 10a, and the voltage between the electrode rods 10a is measured after a certain period of time has elapsed.
[0024]
A schematic diagram of this measurement circuit is shown in FIG. In this measurement circuit, the relationship Vin≈E (t) and Vout = E (t) / (R + 2r) × R is established. However, Vin: applied voltage, Vout: output voltage, E (t): charging voltage, R: fixed resistance, r: specific resistance Therefore, in the preliminary test, first, the electrode rod from the data logger 14 through the switch box 12 In this method, after applying a DC voltage of Vin = 2v for 10 msec for 10 msec and providing a non-application time of 80 msec, this was repeated 21 times per measurement.
[0025]
Then, using another channel, the output voltage Vout between the electrode rods 10a after 180 msec had elapsed from the end of voltage application was measured to the side. The measurement result at this time is shown in FIG.
[0026]
As is apparent from the results shown in FIG. 5, the output voltage Vout between the electrode rods 10a and the mortar launch height become a cubic curve having a substantially proportional relationship. It was confirmed that measurement was possible.
[0027]
Further, in the level sensor 10 based on the measurement principle described above, since the measurement principle depends on the charging characteristics of the material to be measured interposed between the electrode rods 10a, if calibration curves having different material types are prepared in advance. The material used for the concrete can be confirmed, and the height of the concrete rise can be measured more accurately.
[0028]
Based on the above preliminary tests, in the construction work on the breakwater, as shown in FIG. 1 ●, an electrode rod having a total length of about 7 m within a range of about 1/6 of the entire circumference and a circumference of 45 m. Nine L0 to L8) 10a were installed.
[0029]
As shown in FIG. 6, each electrode rod 10 a was disposed so as to be located on both sides of an openable / closable inlet 22 provided in the pressure feeding pipe 20 of the cast concrete.
[0030]
A switch box 12, a data logger 14, and a personal computer 16 are connected to the electrode rod 10a. Each charging port 22 is provided with an electric gate valve 24, and the degree of opening and closing of the electric gate valve 24 is controlled by a control signal sent from the personal computer 16.
[0031]
The cast concrete used in the construction is a high strength, high fluidity concrete having a self-filling property of a slump flow of 65 cm and a design standard strength of 60 N / mm 2 using a combination of low heat Portland cement and an expansion material.
[0032]
The applied voltage and output voltage of each electrode rod 10a were measured by measuring the height of the cast concrete under the same conditions as in the preliminary test described above. FIG. 7 shows the average value of the measurement results of each electrode rod 10a.
[0033]
8 and 9 show an example of the monitor screen (PC 16) of the construction state in the measurement section. By performing such monitoring, the following control becomes possible.
[0034]
(1) From the monitor image, it is possible to grasp the general concrete placement condition when constructing the breakwater, and to confirm the average concrete rise speed in the formwork in real time. In the example shown in Fig. 9, it is possible to objectively determine that the concrete has been placed stably with an average launch speed of 1 m / h.
[0035]
(2) Looking at the monitor image, if a certain place is launched extremely fast or launches slowly, control is performed from the personal computer 16 to the electric gate valve 24 to avoid deformation of the formwork and uneven load. Such an inconvenience can be avoided by sending a signal and adjusting the opening of the valve 24.
[0036]
(3) In terms of the quality of the cast concrete, as shown in Fig. 8, by finding the amount of change per 30 minutes at a certain location, it is possible to find the location where the launch has stopped. Although the presence or absence of the occurrence cannot be confirmed directly, the occurrence can be avoided by controlling the insertion port 22.
[0037]
(4) Since the change of each flow gradient in the section where the electrode rod 10a is installed is obtained as shown in FIG. 10, it is possible to easily determine the degree of slump flow of the high-fluidity concrete being placed. it can.
[0038]
In the above example, since the present invention was applied to the construction of a breakwater using high-fluidity concrete, the degree of compaction was not measured, but when concrete that requires compaction was used. By measuring changes in capacitance and residual voltage before and after the compacting operation, it is possible to confirm the degree of compaction objectively.
[0041]
【The invention's effect】
As described above in detail, according to the construction management method for cast concrete according to the present invention, quality assurance can be performed based on data that can be objectively determined.
[Brief description of the drawings]
FIG. 1 is an explanatory plan view of a breakwater to which a construction management method for cast concrete according to the present invention is applied.
2A and 2B are a plan view and a side view showing an example of an electrode used in the construction management method according to the present invention.
FIG. 3 is an explanatory diagram showing the measurement principle of the same electrode.
FIG. 4 is an explanatory diagram of an electric circuit in a measurement state of the electrode.
FIG. 5 is a graph showing the measurement results of the mortar launch height using the same electrode.
6 is an overall layout view of devices used in the construction management method for the breakwater shown in FIG. 1. FIG.
7 is a graph showing a change with time of the height of cast concrete in the construction management method shown in FIG. 6. FIG.
8 is a diagram showing an example of a monitor screen for the height of cast concrete in the construction management method shown in FIG. 6. FIG.
FIG. 9 is a diagram showing another example of a monitor screen for the height of cast concrete that has been placed in the construction management method shown in FIG. 6;
10 is a graph showing the change with time of the gradient between electrode rods in the construction management method shown in FIG. 6. FIG.
[Explanation of symbols]
10 electrode 10a electrode rod 12 switch box 14 data logger 16 personal computer

Claims (2)

打設コンクリートの施工管理方法において、
打設されるコンクリートの高さ方向に沿って対向延設される一対の電極棒を備えたレベルセンサーを設置し、
1つの前記レベルセンサーで、記電極棒間の静電容量に基づいて、前記コンクリートの打込み材料を確認し、前記静電容量の変化に基づいて、前記打設コンクリートの打ち上がり高さを測定し、打設されたコンクリートの締固め前後の前記静電容量の変化からコンクリートの締固め度を求め、
前記打ち上がり高さの経時的変化を測定することにより、コールドジョイントの発生可能性の有無を判断することを特徴とする打設コンクリートの施工管理方法。
In the construction management method for cast concrete,
Installed a level sensor with a pair of electrode rods that face each other along the height direction of the concrete to be placed,
With one level sensor, the concrete placement material is confirmed based on the capacitance between the electrode bars, and the height of the cast concrete is measured based on the change in capacitance. Determining the degree of compaction of the concrete from the change in capacitance before and after compaction of the placed concrete;
A construction management method for placing concrete, wherein whether or not there is a possibility of occurrence of a cold joint is determined by measuring a change with time of the launch height.
前記打設コンクリートは、高流動コンクリートであって、打設方向に配置された圧送管に設けられた開閉可能な複数の投入口から打設され、前記電極棒を前記投入口の前後に配置して、前記打ち上がり高さを測定することを特徴とする請求項1記載の打設コンクリートの施工管理方法。  The cast concrete is high-fluidity concrete, and is placed from a plurality of openable / closable inlets provided in a pressure feeding pipe arranged in a placement direction, and the electrode rods are arranged before and after the inlet. The method for managing construction of cast concrete according to claim 1, wherein the launch height is measured.
JP08900198A 1998-04-01 1998-04-01 Construction management method for cast concrete Expired - Fee Related JP3843592B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08900198A JP3843592B2 (en) 1998-04-01 1998-04-01 Construction management method for cast concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08900198A JP3843592B2 (en) 1998-04-01 1998-04-01 Construction management method for cast concrete

Publications (2)

Publication Number Publication Date
JPH11287045A JPH11287045A (en) 1999-10-19
JP3843592B2 true JP3843592B2 (en) 2006-11-08

Family

ID=13958578

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08900198A Expired - Fee Related JP3843592B2 (en) 1998-04-01 1998-04-01 Construction management method for cast concrete

Country Status (1)

Country Link
JP (1) JP3843592B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5214493B2 (en) * 2009-02-27 2013-06-19 五洋建設株式会社 Measuring method, measuring device and underwater structure construction method for filling material in structure
JP5391457B2 (en) * 2009-12-07 2014-01-15 飛島建設株式会社 Concrete stacking management method
JP5748499B2 (en) * 2011-02-21 2015-07-15 株式会社フジタ Concrete placement management method and apparatus
CN111948289B (en) * 2020-08-24 2023-07-21 四川升拓检测技术股份有限公司 Concrete cold joint quality detection method, device and system based on shock elastic waves

Also Published As

Publication number Publication date
JPH11287045A (en) 1999-10-19

Similar Documents

Publication Publication Date Title
Teomete et al. Tensile strain sensitivity of steel fiber reinforced cement matrix composites tested by split tensile test
Daniel et al. Laboratory evaluation of fatigue damage and healing of asphalt mixtures
Madhavi et al. Electrical conductivity of concrete
Zhang In situ fatigue crack detection using piezoelectric paint sensor
US20140111231A1 (en) Systems and methods utilizing carbon nanofiber aggregate for performance monitoring of concrete structures
CN108956684B (en) Embedded concrete early-stage freezing and icing nondestructive testing method
Barden et al. Use of free ends in triaxial testing of clays
JP3843592B2 (en) Construction management method for cast concrete
Liu et al. Resistivity signature of graphene-based fiber-reinforced composite subjected to mechanical loading
Huang et al. EIS based assessment of electrodeposition effect of concrete cracks: experiment and equivalent model
Ferdiansyah et al. An experimental approach for characterisation of concrete damage using the wheatstone bridge circuit
Said et al. Induced corrosion techniques for two-way slabs
Van Belleghem et al. Resistivity of repair materials for concrete repair prior to the application of a cathodic protection system
JPH095269A (en) Device and method for measuring water content ratio of sample
JPH05340938A (en) Method and device for judging leveling timing of concrete
Aboumoussa et al. Thermal movements in concrete: Case study of multistory underground car park
Dury Effects of Aging on Concrete Containment Structures: An Investigation of Shrinkage and Leakage
CA2155471C (en) Method and apparatus for testing concrete expansion
JP3014596B2 (en) Method for determining the presence or absence of fresh concrete
CN115684279B (en) Cement-based material crack self-repairing effect quantitative test device and method
JPH10119029A (en) Test method for pumpability of cement mixture
Terzić et al. Application of results of nondestructive testing methods in the investigation of microstructure of refractory concretes
JPS63117260A (en) Concrete strength control method and control device
Jones et al. Review of estimating of chloride ingress into concrete
JPH01297529A (en) Testing device for quality of concrete

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050210

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050713

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050726

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050922

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060328

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060526

A911 Transfer of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20060605

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060725

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060807

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100825

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100825

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110825

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110825

Year of fee payment: 5

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110825

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120825

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120825

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130825

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130825

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140825

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees