JP3890293B2 - Propulsion method and connection structure for propulsion method tube - Google Patents
Propulsion method and connection structure for propulsion method tube Download PDFInfo
- Publication number
- JP3890293B2 JP3890293B2 JP2002350090A JP2002350090A JP3890293B2 JP 3890293 B2 JP3890293 B2 JP 3890293B2 JP 2002350090 A JP2002350090 A JP 2002350090A JP 2002350090 A JP2002350090 A JP 2002350090A JP 3890293 B2 JP3890293 B2 JP 3890293B2
- Authority
- JP
- Japan
- Prior art keywords
- water
- steel collar
- tubular body
- circumferential direction
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Joints With Pressure Members (AREA)
- Joints With Sleeves (AREA)
Description
【0001】
【発明の属する技術分野】
本願に係る発明は、管体を地中に押し込んで地中管路を構築する推進工法及び推進工法に用いる管体の接続構造に係り、特に周方向に分割された複数のセグメントを組み立てて構成された管体を用いる推進工法及びこのような管体の接続構造に関するものである。
【0002】
【従来の技術】
上下水道として用いられる管渠、電力ケーブル・通信ケーブル・ガス管等を配設するための管渠の構築方法として、推進工法が広く知られている。この工法は、立坑から横方向に推進管を地中に押し込むとともに、後方端に順次管体を継ぎ足し、所定長の地中管路を構築するものである。
【0003】
この工法で用いられる管体は、一般にコンクリートからなり、工場で所定長に分割して形成され、現場に搬入される。そして、立坑内で先に押し込まれた管の後方端に接合され、さらに後方からジャッキで横方向に押し込まれる。
【0004】
上記管体は、一方の端部に他の管体との接続部を外側から覆うように鋼製カラーが取り付けられているものがある。この鋼製カラーは、接続部における止水性を確保するために設けられるものである。
【0005】
推進工法によって形成される管渠が曲線部を有する場合、後方から推進される管体は曲線部に差し掛かった時に接続部に角度が設けられ、所定長の管体が曲線状に連なったものとして推進されてゆく。このため管体の接続部で対向する端面は常に密着しているものではなく、曲線部の外側では接続された管体の二つの端面間に隙間を生じることになる。このため、接続された管体の端面間に隙間があっても地下水の流入を防ぐことができる止水性が求められ、上記鋼製カラーで止水性を確保するものとなっている。
【0006】
上記鋼製カラー及びこの鋼製カラーを用いた管体の接続構造については、いくつかの提案がなされており(例えば、特許文献1、特許文献2、特許文献3)、鋼製カラーが接続される管体の一方の外周部に固着されている。そして、他方の管体がこの鋼製カラーの内側に挿入され、この鋼製カラーの内周面と挿入された管体の外周面との間に止水材が介挿されるものとなっている。
【0007】
【特許文献1】
特開2002−276286号公報
【特許文献2】
特開2001−342795号公報
【特許文献3】
特開平10−212897号公報
【特許文献4】
特開平10−159487号公報
【0008】
【発明が解決しようとする課題】
上記のような推進工法で従来から構築されている管渠は、径が約3m以下のものがほとんどである。これは、工場で構築され、現場へ輸送される管体の径が3mを超えると輸送が困難になることに起因している。しかし、都市部における共同溝の普及等にともない、大口径の管渠を推進工法で構築することが求められるようになっている。
【0009】
一般に、大口径の管渠又は都市部におけるトンネルの構築はシールド工法によるものが多く、このシールド工法では覆工体つまり管体は周方向に複数のセグメント組み合わせて形成される。しかし、シールド工法では、セグメントは掘削を行っている切羽のすぐ後方で組み立て、建て込まれる。そして、管体は移動するものではない。このため、セグメントの接合部で地下水の流入を防止するための止水性を確保することも比較的に簡単である。
【0010】
これに対し、推進工法では、管体が軸線方向に強く押し込まれ、大きな応力が生じるとともに、管渠の軸線方向に移動する。そして、曲線部では接続された各管体間で、間隙が生じたり、この隙間が消滅したりすることになる。このため、軸線方向の接続部では、上記特許文献に記載されているような特有の止水構造が必要となる。そして、周方向に複数のセグメント組み立てて管体を構成するとセグメント間の接合部にも止水性が要求され、施工中における止水性の確保等に困難があると考えられてきた。
【0011】
本願に係る発明は、上記のような事情に鑑みてなされたものであり、その目的は、大口径の地中管路を構築することができるとともに、充分な止水性を維持することができる推進工法及びこの工法で好適に用いることができる管体の接続構造を提供するものである。
【0012】
【課題を解決するための手段】
上記課題を解決するために、請求項1に係る発明は、 地中管路の覆工体となる推進管をその中心軸線方向の地中に押し出すとともに、所定長の管体を順次押し出しの後方側に接続して押し出し動作を繰り返す推進工法であって、 前記管体は、周方向に複数に分割されたコンクリートセグメントを組み立てて形成するものとし、 該セグメントの製作時には、管体の推進方向の後方端に、隣接される管体との接続部を外側から囲む鋼製カラーを該セグメントの周方向に沿って固定するとともに、該セグメントと前記鋼製カラーとの間には該鋼製カラーに密着させて周方向に第1の止水材を介挿しておき、 該セグメントを組み立てて管体とする時には、前記鋼製カラーを管状に接合するとともに、周方向の前記第1の止水材が管体の全周にわたって連続するものとし、該セグメントの接合部には該管体の推進方向と平行な端面に沿って双方のセグメント間に第2の止水材を介挿し、該第2の止水材と周方向に配置された前記第1の止水材とを連続させ、 前記管体を推進方向に接合する時には、管状となった前記鋼製カラーの内側に接合する他の管体の前方端を挿入し、この接合する管体の前方端付近の外周面と管状となった前記鋼製カラーの内周面との間にリング状となった第3の止水材を介挿し、前記管体の推進方向に沿って配置された第2の止水材をリング状の前記第3の止水材と連続させる推進工法を提供する。
【0013】
この推進工法では、順次接続される所定長の管体は、複数のセグメントを組み立てて形成するので、管体の口径が大きなものであっても、工場で製作したそれぞれのセグメントは容易に現場に搬送することができる。そして組み立てた管体を接続して地中に押し込んでゆくことによって大口径の地中管路を構築することができる。
【0014】
また、セグメントを組み立てて管体とするときの接合部には、第2の止水材を管体の中心軸線方向に介挿するので、接合部での高い止水性が維持され、施工中及び施工完了後にもこの部分からの浸水を防止することができる。
さらに、推進方向に接続する管体には、その接続部の外側を囲むように鋼製のカラーを設け、この鋼製カラーとコンクリートの管体との間にも周方向に第1の止水材及び第3の止水材を配置するので、施工中の接続部で止水性が確保される。つまり、鋼製カラーとこれが固定されたコンクリートの管体との間は双方が密着していても鋼製カラーの内周面に沿って漏水が生じるおそれがあるが、鋼製カラーに密着して第1の止水材を配置するので、鋼製カラーの内面に沿った浸水が防止される。また、管体の前方部と、この管体が挿入される鋼製カラーとの間には、リング状の止水材を介挿するので鋼製カラーと接続されるコンクリート管体との間の止水性も維持される。
そして、セグメントを組み立てた接合部に沿って介挿した第2の止水材の後方及び前方の端部は、それぞれが円周方向に配置した第1の止水材及び第3の止水材に連続するので、セグメントの接合部の両端部でも高い止水性を維持することができる。
【0015】
請求項2に係る発明は、請求項1に記載の推進工法において、 前記セグメントを組み立てて管体とするときには、セグメント間に介挿する前記第2の止水材を管体の前方端付近で外周面に露出するように配置し、 前記管体を推進方向に接合するときには、リング状の前記第3の止水材を、前記第2の止水材の露出部に装着して密着させるものである。
【0016】
この推進工法では、セグメントを組み立てて管体とした後、前方端付近にリング状の第3の止水材を装着することによって、この第3の止水材が、管体の外周面に露出した第2の止水材と密着し、双方を連続したものとすることができる。したがって、セグメント接合部の前方端での止水性を容易に確保することができる。
【0017】
請求項3に係る発明は、請求項1に記載の推進工法において、 前記セグメントを組み立てて管体とする時には、 該セグメントのコンクリート中に配置された緊張材によって周方向にプレストレスを導入し、 その後、前記鋼製カラーを溶接によって周方向に連続するように接合するものである。
【0018】
この推進工法では、コンクリートのセグメントを周方向のプレストレスを導入することによって組み立てるので、セグメントの端面は互いに密着し、強固に一体化される。また、これらの端面間に第2の止水材を介挿するので、この第2の止水材とコンクリートとの密着性も良好となり、高い止水性が確保される。
また、鋼製カラーは溶接によって接合するので接合部の止水性を確実に得ることができる。
【0019】
請求項4に係る発明は、請求項3に記載の推進工法において、 前記セグメントの製作時には、前記鋼製カラーの接合部の内周面と前記セグメントのコンクリートとの間に空隙を設けておき、 前記鋼製カラーを溶接によって接合した後、前記空隙に止水性を有する充填材を充填することによって、周方向に配置された前記第1の止水材を全周にわたって連続したものとする。
【0020】
一般に止水材は熱によって損傷を受けやすいものが多く、鋼製カラーの溶接をする時に、この鋼製カラーに密着するように配置した第1の止水材を溶接時の加熱で損傷することが考えられる。しかし、この推進工法では、鋼製カラーの接合部の内側に空隙が設けられた状態で溶接を行う。そして、溶接による鋼製カラーの接合が完了した後に充填材を充填するので、この部分では第1の止水材を切り欠いておき、充填材で第2の止水材を周方向に連続したものとすることができる。したがって、止水材が溶接による熱の影響をうけて欠陥を生じることもなく、止水性を確保することができる。
【0021】
請求項5に係る発明は、 中心軸方向に順次接続され、地中に押し込まれて地中管路の覆工体となる推進工法用管体の接続構造であって、 前記管体は、周方向に複数に分割されたコンクリートのセグメントを組み立てて形成されたものであり、 前記管体の推進方向における後方の端部には、他の管体との接続部を外側から囲む管状の鋼製カラーが、一部を突き出して固着されており、 管状の鋼製カラーとこの鋼製カラーが固定されたコンクリートの管体との間には、全周にわたって周方向に連続する第1の止水材が介挿され、 前記管体を構成する複数のセグメントの接合部には、管体の推進方向に沿って第2の止水材が介挿され、前記第1の止水材と前記第2の止水材とが連続しており、 接続される他の管体の前方部は、前記鋼製カラーの突き出した部分の内側に挿入され、該管体の外周面と前記鋼製カラーの内周面との間にリング状の第3の止水材が介挿されている推進工法用管体の接続構造を提供するものである。
【0022】
この接続構造では、推進方向に接続される管体には、その接続部の外側を囲むように鋼製のカラーが設けられており、この鋼製カラーとコンクリートの管体との間には周方向に第1の止水材及び第3の止水材が配置されているので、施工中における接続部での止水性が確保される。
また、セグメントを組み立てて管体とするときの接合部には、第2の止水材が管体の中心軸線方向に介挿され、接合部での高い止水性が維持されるとともに、この第2の止水材が、周方向に配置された第1の止水材及び第3の止水材と連続するものとなっているので、施工中及び施工完了後にも接合される管体の両端付近におけるセグメント接合部から浸水するのを防止することができる。
【0023】
請求項6に係る発明は、請求項5に記載の接続構造において、 前記セグメント間に介挿された前記第2の止水材は、管体の前方端付近で外周面に露出するように配置され、 リング状の前記第3の止水材は、前記第2の止水材の露出部に装着され密着しているものとする。
【0024】
この接続構造では、管体の前方端付近に装着されたリング状の第3の止水材が、管体の外周面に露出した第2の止水材と密着し、双方が連続したものとなっている。したがって、リング状となった第3の止水材でコンクリートの管体と鋼製のカラーとの間の止水性が保たれるとともに、セグメントの接合位置の前方側端部でも高い止水性が維持される。
【0025】
請求項7に係る発明は、請求項5に記載の接続構造において、 前記鋼製カラーは、前記セグメントの組み立て時に溶接によって管状に連結されたものであり、 該鋼製カラーが取り付けられたコンクリートからなる管体の後方の端部は、該鋼製カラーの溶接による連結部付近の内周面とコンクリートからなる管体との間に空隙が設けられており、 前記鋼製カラーが溶接によって周方向に接合された後に前記空隙に充填された止水性を有する充填材により、周方向に配置された前記第1の止水材が全周にわたって連続するものとする。
【0026】
この接続構造では、鋼製カラーの溶接による接合後に、その内側に充填された充填材によって、鋼製カラーに密着して周方向に配置された第1の止水材が周方向に連続したものとなる。このため、セグメントを周方向に接合した部分でも確実に周方向の止水材が連続し、鋼製カラーに密着したものとなる。したがって、鋼製カラーとこれが固着されたコンクリートの管体との間の止水性が良好に維持される。また、この周方向の第1の止水材がセグメントの接合部に介挿された第2の止水材とも連続しているので、セグメント接合部の後方端付近での止水性も確保される。
なお、周方向の第1の止水材とセグメント接合部に介挿された第2の止水材との間も、鋼製カラーの溶接接合後に充填された充填材によって連結されるものとするのが望ましい。これによって、第1の止水材と第2の止水材と連続性も、溶接による熱の影響を受けることなく、確実に維持される。
【0027】
請求項8に係る発明は、請求項5に記載の接続構造において、 前記鋼製カラーは、前記セグメントの組み立て時に溶接によって管状に連結されたものであり、該鋼製カラーの内周面から内側のコンクリート中に突き出し、周方向に連続した板状の埋め込み部を有し、 周方向に配置された前記第1の止水材は、該埋め込み部に密着してコンクリート中に埋め込まれているものとする。
【0028】
この接続構造では、第1の止水材は鋼製カラーの管状部から内側に突き出した部分に密着しているので、セグメントを組み立てて接合するときに、上記鋼製カラーの管状部を溶接によって連結しても、その熱の影響を受けにくい。したがって、セグメントの接合部で周方向に連続した第1の止水材が損傷を受けることがなく、止水性が確実に維持される。
【0029】
請求項9に係る発明は、請求項8に記載の接続構造において、 前記鋼製カラーの溶接による連結部分とこの鋼製カラーが固定されるコンクリートとの間に、該コンクリートを切り欠いて該管体の外周面側に開放された空隙が設けられており、 鋼製カラーが溶接によって周方向に接合された後に前記空隙に充填された止水性を有する充填材により、周方向に配置された前記第1の止水材と前記鋼製カラーとが連続するものとする。
【0030】
この接続構造では、第1の止水材が鋼製カラーの管状部から内側に離れた位置に配置されるので、セグメントの接合部で第1の止水材と鋼製カラーの管状部との間に、セグメントの接合面に沿って水が侵入するおそれがある。しかし、鋼製カラーとコンククリートとの間に設けられた空隙に充填された充填材によって、鋼製カラーと第1の止水材とが連続したものとなっているのでこの部分からの浸水は防止され、止水性が維持される。
【0031】
【発明の実施の形態】
以下、本願に係る発明の実施の形態を図に基づいて説明する。
図1は、請求項1から請求項4までに記載の発明の一実施形態である推進工法の概要を示す概略説明図である。
この推進工法は、推進を開始する位置に立坑1を設け、この立坑の一方の壁面からほぼ水平方向に連続した管(推進管2)を押し込み、地中に推進させるものである。立坑1の反対側の壁面には反力壁3を設け、この反力壁3と推進管2の後方端との間に介挿したジャッキ4により管を押し進める。そして、順次所定長の管体20を、押し込まれた管2の後方端とジャッキ4との間に継ぎ足し、所定の距離まで押し込んで管路を形成するものである。
【0032】
上記立坑1は、山留め11及び腹おこし12等によって壁面が崩壊しないように保持され、その壁面に開口を設けて、ここから水平方向に推進管2を押し出す。そして、反対側の壁面に形成したコンクリートの反力壁3にはジャッキ台5を介して押し出し用のジャッキ4を配備し、このジャッキ4によりストラッド6を介して推進管2に推力を与える。上記ストラッド6は、ジャッキ4のストロークに限界があるため推進管2の移動にともなって管2の後端とジャッキ4との間に介挿し、ジャッキ4の推力を管に伝達するものである。
【0033】
立坑1の上部には門型クレーン7を配備し、所定長の管体20を吊り上げて、立坑1内に搬入する。また、管2の推進にともなって構内から掘り出された土砂8を上記門型クレーン7を用いて排出する。
【0034】
地中に押し込む推進管2はコンクリートからなるものであり、推進が進行するのにともなって既に押し込まれている管2の後方端に順次所定長の管体20を接続する。図2は、上記管体20の側面図及び横断面であり、図3は縦断面図である。
それぞれ管体20の後方端には鋼製カラー21を設けておき、後方に接続する管体20aの前方部22は、前方にある管体20bに固着された鋼製カラー21bの内側に挿入し、この鋼製カラー21bが接合部を外側から覆うものとしている。そして、この鋼製カラー21bと、これが固着されたコンクリートの管体20bとの間には、セグメントの製作時に、鋼製カラー21bに密着するように第1の止水材23を周方向に連続して介挿しておき、鋼製カラー21とコンクリートの管体20との間から地下水が侵入するのを防止する。また、鋼製カラー21bの内周面と、内側に挿入された後続の管体20aの外周面との間にリング状の第3の止水材25を介挿し、これらの間から管体の内側に水が侵入するのを防止する。
なお、図3中に示す符号33は、鋼製カラー21をコンクリートと強固に一体化するために、鋼製カラー21の周方向に沿って溶接された棒鋼を示すものである。
【0035】
上記管体20の製作は工場において行われ、図2に示すように、管を軸線方向に2つに分割して製作し、現場で管状に組み立てるものである。分割されたセグメント20’は、口径が大きなものであっても、図4に示すようにトレーラー9等で搬送することが可能となる。そして現場では、図5に示すように、組み合わせる一方のセグメント20’aを固定支持した上に他のセグメント20’bを上方から接合し、周方向にPC緊張材27で締め付けて強固に一体化する。このとき双方のセグメント20’a,20’bの接合面間には、管体の軸線方向に沿って第2の止水材24を介挿する。また、接合する双方のセグメント20’a,20’bに貫入するようにせん断キー26を装着する。PC緊張材27は、セグメント20にあらかじめ形成しておいたダクト内に現場で挿通し、ジャッキで緊張力を導入した後、セグメント20の外周面側に固着されたアンカー28に定着する。
【0036】
次に上記管体20を構成するセグメント20’の製作及びこれらを管状に組み立てて推進方向に接続する構造及び方法について説明する。なお、この管体の接続構造は、請求項5から請求項7までのそれぞれに記載の発明の実施形態である。
鋼製カラー21は、分割したセグメントに合わせて全周を1/2ずつに分割して製作し、これを型枠と連続するように配置する。そして、鋼製カラーの内周面に密着して周方向に連続する第1の止水材23を配置し、この止水材を埋め込むとともにこの半割りにされた鋼製カラーと一体となるようにコンクリートを打設してコンクリート製のセグメント20’を形成する。上記第1の止水材23は、鋼製カラー21及びコンクリートと密着してこれらの間に水が侵入するのを遮断するものであり、柔軟な合成樹脂、ゴム等を用いることができる。
【0037】
図6は、上記セグメント20’の接合面を示す端面図及びセグメント20’の接合部を外側から見た図である。この半割りにされたセグメント20’の周方向端部には、鋼製カラー21とコンクリートとの間に空隙31を設けておき、周方向に配置した第1の止水材23はこの空隙31内に露出させておく。また、セグメント20’を管状に組み立てるときの接合面には、管体20’の中心軸線と平行に溝32を形成しておき、この溝32内に第2の止水材24を接着し、接合するセグメント間に挟み込むように介挿する。この第2の止水材24は、管体20の後方の端部では、外周面に向けて連続するように配置し、鋼製カラー21とコンクリートとの間に形成された上記空隙31内に露出するように配置する。また、前方の端部22では、第2の止水材24が外周面に向かって連続するように配置し、セグメントを組み立てたときに、第2の止水材24を外周面に露出して多少突出させる。
【0038】
二つの半割りにされたセグメント20’a,20’bを管状に組み立てて、プレストレスの導入により一体化すると、鋼製カラー21は、図7に示すようにセグメント20’の接合部で周方向の端面が突き合わされており、これらの両端を溶接によって接合し、鋼製カラー21を管状に連続したものとする。このとき接合部の内側は、コンクリートとの間に空隙31が設けられており、周方向の第1の止水材23及びセグメント20’の接合面に沿って配置された第2の止水材24とは隔離しているので、外側から溶接によって鋼製カラー21を接合しても、止水材23,24には溶接の熱による影響は及ばない。また、溶接時にはこの空隙31内にバックアップ用の鋼板材を挿入し、鋼製カラーの背面に当接させることができるので、良好な条件で溶接を行うことができる。
【0039】
溶接による鋼製カラー21の接合が完了すると、鋼製カラー21の内側の空隙31内に充填材を充填する。この充填材は、充填時には空隙内の隅々にまで充填できる流動性を有し、充填後には硬度は大きくなるがある程度の柔軟性を有するもので、この充填部分の止水性を保持できるものを用いる。上記充填材を空隙に充填することにより周方向に配置された第1の止水材23は周方向に連続して止水性を有するものとなり、さらにこの第1の止水材23とセグメント20’の接合面間に介挿された第2の止水材24とが連続したものとなる。これによって管体の後端部における止水性が確保される。
【0040】
一方、管体20の前方端付近には、ゴム製のリング状となった第3の止水材25を装着する。そして、第2の止水材24が管体20の外周面に露出している部分の上に巻きつけ、双方の止水材25,24を密着させる。この第3の止水材25は、接合される前方の管体20bの鋼製カラー21bの内側に挿入され、内周面に当接される。これによって、隣接する管体20bの鋼製カラー21bとの間の止水性が確保されるとともに、セグメントの接合部の前方端部での止水性も確保される。また、第3の止水材25は、鋼製カラー21bの内周面との間で摺動が可能であり、管体20の接合部で軸線方向に相対的な移動が生じても、止水性が保持される。
【0041】
次に、図1に示す推進工法で用いることができる他の管体の接合構造であって、請求項8又は請求項9に記載の発明の一実施形態である接続構造について説明する。
図8は、この接続構造で用いられる管体の縦断面図であり、図9は、この管体を構成するセグメントの接合端面を示す概略図である。また、図10は、図9中に示すA−A線での断面図であり、図11は、図9中に示すB−B線での断面図である。
【0042】
この管体40は、図2及び図3に示す管体20と同様に、2つのセグメントを組み合わせて形成されたものであり、後方の端部に鋼製カラー41が固着されている。鋼製カラー41は、管体40の内側に突出してコンクリート中に埋め込まれた埋め込み部51を有している。この埋め込み部51は周方向に連続して鋼製カラー41の内周面とほぼ直角に突き出しており、推進方向における前方側の面に第1の止水材43が密着し、周方向に連続している。したがって、コンクリートと鋼製カラー41との間に地下水が侵入しても上記第1の止水材43によって遮蔽され、管体の内側への漏水が防止される。
【0043】
このような構造の管体40を構成するセグメント40’の周方向の端面は、図9に示すように管体40の軸線方向に溝52が形成されており、この部分に第2の止水材44が配置され、2つのセグメント間に挟み込むように介挿される。この第2の止水材44は、後方側の端部では、図11に示すように周方向に配置された第1の止水材43に当接され、連続したものとなっている。また、前方の端部では外周面側に露出し、管体40の前方部42で外周面に装着されるリング状の第3の止水材45に当接される。これにより、セグメントの接合面における両端部での止水性が確保される。
【0044】
セグメントの周方向における端部では、図10に示すように鋼製カラー41は溶接によって管状に接合されるものであり、溶接接合を良好に行うことができるように鋼製カラー41の内側に、あて板53が介挿されている。また、図12に示すように、推進方向における鋼製カラー41の前方部にはコンクリートの管体の外周面に開口する切り欠き54を設けておくのが望ましい。この切り欠き54は、鋼製カラー41の内側で、埋め込み部51の前面及び第1の止水材43、第2の止水材44に連続するものとなっている。そして、この切り欠き54には、鋼製カラー41を溶接によって接合した後に柔軟な充填材が充填され、鋼製カラー41と第1の止水材43との間が止水性のある充填材で連続したものとなる。これにより、埋め込み部51はセグメントの接合部で溶接されていないが、鋼製カラー41と第1の止水材43との間から管体内に地下水が侵入するのを防止することができる。
【0045】
このように組み立てられた管体40は、図2から図7までに示す管体20と同様に、推進にともなって推進管の後端に接続されるものであり、図9に示すようにそれぞれの管体40の後方端部に設けられた鋼製カラー41の内側に後続の管体40aの前方部42が挿入される。そして、鋼製カラー41の内周面が後続の管体40aの前方部に装着されたリング状の第3の止水材45と密着し、この第3の止水材45が推進方向に摺動可能となる。したがって、接続された双方の管体40a,40bが中心軸線方向に相対的な変位を生じても止水性が維持される。
【0046】
【発明の効果】
以上説明したように、本願発明に係る推進工法及びこれに用いる管体の接続構造では、管体は複数のセグメントを周方向に組み立てて形成されており、各セグメントは工場で製作しても容易に現場に搬入することができる。したがって、大口径の管体を用いて地中管路を構築することができる。また、セグメントの接合部では推進方向の接合面に沿って第2の止水材が介挿され、これらの両端部は周方向に連続した第1の止水材及び第3の止水材と連続したものとなるので、セグメントの接合部及び管体の接続部で高い止水性が得られる。
【図面の簡単な説明】
【図1】本願に係る発明の一実施形態である推進工法の概要を示す概略断面図である。
【図2】本願に係る発明の推進工法で用いられる管体の側面図及び横断面図である。
【図3】図2に示す管体及びこの管体を軸線方向に接続する部分の縦断面図である。
【図4】図2に示す管体を構成するセグメントの輸送状態を示す概略図である。
【図5】図2に示す管体を組み立てる状態を示す概略図である。
【図6】図2に示す管体を構成するセグメントの接合面を示す概略図及び接合部を外側から見た図である。
【図7】図2に示す管体の後方端付近におけるセグメント接合部の横断面図である。
【図8】図1に示す推進工法で用いることができる管体の他の例を示す縦断面図である。
【図9】図8に示す管体を構成するセグメントの接合端面を示す概略図である。
【図10】図9中に示すA−A線での断面図である。
【図11】図9中に示すB−B線での断面図である。
【図12】図8に示す管体を構成するセグメントの後方端付近の端面を示す概略図、及びセグメントの接合部における後方端付近の外周面を示す概略図である。
【符号の説明】
1 立坑
2 推進管
3 反力壁
4 ジャッキ
5 ジャッキ台
6 ストラット
7 門型クレーン
8 土砂
9 トレーラー
11 山留め
12 腹おこし
20,40 管体
20’、40’ 管体を構成するセグメント
21,41 鋼製カラー
22,42 管体の前方部
23,43 第1の止水材
24,44 第2の止水材
25,45 第3の止水材
26 せん断キー
27 PC緊張材
28 アンカー
31 空隙
32 周方向に溶接された棒鋼
33 溝
51 埋め込み部
52 溝
53 あて板
54 切り欠き[0001]
BACKGROUND OF THE INVENTION
The invention according to the present application relates to a propulsion method that pushes a tube into the ground and constructs an underground conduit, and a tube connection structure used in the propulsion method, and particularly includes a plurality of segments divided in the circumferential direction. The present invention relates to a propulsion method using such a tubular body and a connection structure for such a tubular body.
[0002]
[Prior art]
A propulsion method is widely known as a method for constructing pipes used for water and sewage, pipes for arranging power cables, communication cables, gas pipes, and the like. In this method, the propelling pipe is pushed into the ground laterally from the vertical shaft, and the pipe body is sequentially added to the rear end to construct the underground pipe having a predetermined length.
[0003]
The tubular body used in this construction method is generally made of concrete, is divided into predetermined lengths at a factory, and is carried to the site. And it is joined to the rear end of the pipe pushed in first in the shaft, and further pushed in the lateral direction with a jack from the rear.
[0004]
Some of the above-mentioned tubular bodies have a steel collar attached to one end so as to cover the connecting portion with the other tubular body from the outside. This steel collar is provided in order to ensure water-stopping at the connecting portion.
[0005]
When the pipe rod formed by the propulsion method has a curved part, the pipe body propelled from the rear is provided with an angle at the connection part when it reaches the curved part, and the pipe body of a predetermined length is connected in a curved shape. It will be promoted. For this reason, the end faces facing each other at the connecting portion of the tubular body are not always in close contact with each other, and a gap is formed between the two end faces of the connected tubular bodies outside the curved portion. For this reason, even if there is a gap between the end faces of the connected pipe bodies, water stoppage that can prevent the inflow of groundwater is required, and the water stoppage is ensured by the steel collar.
[0006]
Several proposals have been made on the steel collar and the pipe connecting structure using the steel collar (for example, Patent Document 1,
[0007]
[Patent Document 1]
JP 2002-276286 A
[Patent Document 2]
Japanese Patent Laid-Open No. 2001-342795
[Patent Document 3]
Japanese Patent Laid-Open No. 10-212897
[Patent Document 4]
Japanese Patent Laid-Open No. 10-159487
[0008]
[Problems to be solved by the invention]
Most pipe rods that have been constructed by the above-described propulsion method have a diameter of about 3 m or less. This is due to the fact that transportation becomes difficult when the diameter of the pipe body constructed at the factory and transported to the site exceeds 3 m. However, with the widespread use of common grooves in urban areas, it has become necessary to construct large-diameter pipes with the propulsion method.
[0009]
In general, large-diameter pipes or tunnels in urban areas are often constructed by a shield method, and in this shield method, a lining body, that is, a pipe body, is formed by combining a plurality of segments in the circumferential direction. However, in the shield method, the segments are assembled and built just behind the face that is being excavated. And the tube does not move. For this reason, it is comparatively easy to ensure the water stoppage for preventing the inflow of groundwater at the junction of the segments.
[0010]
On the other hand, in the propulsion method, the tube body is strongly pushed in the axial direction, a large stress is generated, and the tube body moves in the axial direction of the pipe rod. And in a curve part, a gap | interval will arise between each connected pipe body, or this clearance gap will lose | disappear. For this reason, in the connection part of an axial direction, the specific water stop structure as described in the said patent document is needed. And when a pipe is constructed by assembling a plurality of segments in the circumferential direction, it has been considered that the joint between the segments is required to be water-tight, and it is difficult to ensure water-stopping during construction.
[0011]
The invention according to the present application has been made in view of the circumstances as described above, and its purpose is to promote a structure capable of constructing a large-diameter underground conduit and maintaining a sufficient water-stopping property. The present invention provides a connection method for a tubular body that can be suitably used in the construction method and this construction method.
[0012]
[Means for Solving the Problems]
In order to solve the above-mentioned problem, the invention according to claim 1 is to push a propulsion pipe as a lining body of an underground pipe line into the ground in the direction of its central axis, and sequentially push a predetermined length of the pipe body behind the extrusion. The pipe body is formed by assembling a concrete segment divided into a plurality of parts in the circumferential direction, and when the segment is manufactured, A steel collar that surrounds a connecting portion with an adjacent pipe body from the outside is fixed to the rear end along the circumferential direction of the segment, and the steel collar is interposed between the segment and the steel collar. When the first water-stopping material is inserted in the circumferential direction and the segments are assembled into a tubular body, the steel collar is joined in a tubular shape, and the first water-stopping material in the circumferential direction is joined. Over the entire circumference of the tube A second water-stopping material is inserted between the segments along the end surface parallel to the propulsion direction of the tube, and the second water-stopping material When the tube body is joined in the propulsion direction, the front end of another tube body that is joined to the inside of the steel collar that is tubular is inserted. Then, a third water-stopping material having a ring shape is interposed between the outer peripheral surface in the vicinity of the front end of the tubular body to be joined and the inner peripheral surface of the tubular steel collar, and the tubular body Provided is a propulsion method in which a second water stop material arranged along a propulsion direction is made continuous with the ring-shaped third water stop material.
[0013]
In this propulsion method, pipes of a predetermined length that are sequentially connected are formed by assembling a plurality of segments. Therefore, even if the pipe diameter is large, each segment manufactured at the factory can be easily put on the site. Can be transported. A large-diameter underground conduit can be constructed by connecting the assembled tubular bodies and pushing them into the ground.
[0014]
Moreover, since the 2nd water stop material is inserted in the center axis direction of a pipe body at the junction part when assembling a segment to make a pipe body, the high water stop at a junction part is maintained, and it is under construction and Even after the completion of construction, it is possible to prevent water from entering this portion.
Further, the tubular body connected in the propulsion direction is provided with a steel collar so as to surround the outside of the connecting portion, and the first water stop is also provided in the circumferential direction between the steel collar and the concrete tubular body. Since the material and the third water-stopping material are arranged, water-stopping is ensured at the connection portion under construction. In other words, there is a possibility that water leakage may occur along the inner peripheral surface of the steel collar even if both are in close contact between the steel collar and the concrete tube to which the steel collar is fixed. Since the 1st water stop material is arrange | positioned, the inundation along the inner surface of steel collars is prevented. In addition, since a ring-shaped water-stopping material is interposed between the front portion of the tubular body and the steel collar into which the tubular body is inserted, it is between the concrete tubular body connected to the steel collar. Waterstop is also maintained.
And the 1st water stop material and the 3rd water stop material which each arrange | positioned in the circumferential direction are the back part and the front edge part of the 2nd water stop material inserted along the junction part which assembled the segment, respectively. Therefore, it is possible to maintain a high water-stopping property at both ends of the joint portion of the segment.
[0015]
The invention according to
[0016]
In this propulsion method, after assembling the segments into a pipe body, a third water-stop material in the form of a ring is attached near the front end, so that the third water-stop material is exposed on the outer peripheral surface of the pipe body. The second water-stopping material is in close contact with each other and both can be made continuous. Therefore, it is possible to easily ensure water-stopping at the front end of the segment joint portion.
[0017]
The invention according to
[0018]
In this propulsion method, the concrete segments are assembled by introducing circumferential prestress, so that the end faces of the segments are in close contact with each other and firmly integrated. Moreover, since the 2nd water stop material is inserted between these end surfaces, the adhesiveness of this 2nd water stop material and concrete also becomes favorable, and high water stop property is ensured.
Further, since the steel collar is joined by welding, it is possible to reliably obtain the water stoppage of the joint portion.
[0019]
The invention according to claim 4 is the propulsion method according to
[0020]
Generally, there are many water-stopping materials that are easily damaged by heat, and when welding a steel collar, the first water-stopping material placed in close contact with the steel collar is damaged by heating during welding. Can be considered. However, in this propulsion method, welding is performed in a state where a gap is provided inside the joint portion of the steel collar. Then, since the filler is filled after the joining of the steel collar by welding is completed, the first water-stopping material is cut out at this portion, and the second water-stopping material is continued in the circumferential direction with the filler. Can be. Therefore, the water stop material can be secured without being affected by heat caused by welding and causing defects.
[0021]
The invention according to claim 5 is a connection structure for a tubular body for a propulsion method that is sequentially connected in the direction of the central axis and is pushed into the ground to become a covering body of the underground pipe line. It is formed by assembling concrete segments that are divided into a plurality of directions, and at the rear end in the propulsion direction of the tubular body, it is made of tubular steel that surrounds the connection portion with other tubular bodies from the outside. The collar protrudes partially and is fixed, and a first water stop that is circumferentially continuous over the entire circumference between the tubular steel collar and the concrete tube to which the steel collar is fixed. A material is inserted, and a second water-stopping material is inserted along the propulsion direction of the tube at the joint portion of the plurality of segments constituting the tube, and the first water-stopping material and the first water-stopping material The water stop material of 2 is continuous, and the front part of the other tubular body to be connected is made of the steel collar. A tubular body for a propulsion method, which is inserted inside the protruding portion, and a ring-shaped third water stop material is interposed between the outer peripheral surface of the tubular body and the inner peripheral surface of the steel collar A connection structure is provided.
[0022]
In this connection structure, the pipe body connected in the propulsion direction is provided with a steel collar so as to surround the outside of the connection portion, and there is no circumference between the steel collar and the concrete pipe body. Since the 1st water stop material and the 3rd water stop material are arrange | positioned in the direction, the water stop at the connection part in construction is ensured.
In addition, a second water-stopping material is inserted in the central axis direction of the tubular body at the joint portion when the segments are assembled into a tubular body, and high water-stopping performance at the joint portion is maintained. Since the two water-stopping materials are continuous with the first water-stopping material and the third water-stopping material arranged in the circumferential direction, both ends of the tubular body to be joined even during construction and after completion of construction It is possible to prevent water from entering from the segment joint in the vicinity.
[0023]
The invention according to
[0024]
In this connection structure, the ring-shaped third water-stopping material attached near the front end of the tube is in close contact with the second water-stopping material exposed on the outer peripheral surface of the tube, and both are continuous. It has become. Therefore, the third water-stopping material in the form of a ring maintains water-stopping between the concrete tube and the steel collar, and also maintains high water-stopping at the front end of the joining position of the segments. Is done.
[0025]
The invention according to claim 7 is the connection structure according to claim 5, wherein the steel collar is connected in a tubular shape by welding at the time of assembling the segment, and from the concrete to which the steel collar is attached. The rear end of the tubular body is provided with a gap between the inner peripheral surface in the vicinity of the connecting portion by welding of the steel collar and the tubular body made of concrete, and the steel collar is circumferentially welded. It is assumed that the first water-stopping material arranged in the circumferential direction is continuous over the entire circumference by the filler having the water-stopping property filled in the gap after being joined to the gap.
[0026]
In this connection structure, after joining by welding the steel collar, the first water-stopping material arranged in the circumferential direction in close contact with the steel collar by the filler filled inside is continuous in the circumferential direction. It becomes. For this reason, the water-stop material in the circumferential direction surely continues even at the portion where the segments are joined in the circumferential direction, and is in close contact with the steel collar. Therefore, the water-stopping property between the steel collar and the concrete tube to which the steel collar is fixed is well maintained. Moreover, since the 1st water stop material of this circumferential direction is also continuing with the 2nd water stop material inserted in the junction part of a segment, the water stop in the back end vicinity of a segment junction part is also ensured. .
In addition, between the 1st water stop material of the circumferential direction and the 2nd water stop material inserted by the segment junction part shall be connected by the filler with which the steel collar was welded and joined. Is desirable. As a result, the continuity between the first water-stopping material and the second water-stopping material is also reliably maintained without being affected by heat from welding.
[0027]
The invention according to
[0028]
In this connection structure, since the first waterstop material is in close contact with the portion protruding inward from the tubular portion of the steel collar, when the segments are assembled and joined, the tubular portion of the steel collar is welded. Even if connected, it is not easily affected by the heat. Therefore, the first water-stopping material continuous in the circumferential direction at the joint portion of the segment is not damaged, and the water-stopping property is reliably maintained.
[0029]
The invention according to
[0030]
In this connection structure, since the first water stop material is disposed at a position away from the tubular portion of the steel collar, the first water stop material and the tubular portion of the steel collar are joined at the joint portion of the segment. In the middle, water may enter along the joint surfaces of the segments. However, since the steel collar and the first water-stopping material are continuous by the filler filled in the gap provided between the steel collar and the concrete, the water from this portion is Is prevented and water-stopping is maintained.
[0031]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the invention according to the present application will be described with reference to the drawings.
FIG. 1 is a schematic explanatory diagram showing an outline of a propulsion method according to an embodiment of the invention described in claims 1 to 4.
In this propulsion method, a shaft 1 is provided at a position where propulsion is started, and a tube (propulsion tube 2) continuous in a substantially horizontal direction is pushed from one wall surface of the shaft to be propelled into the ground. A
[0032]
The vertical shaft 1 is held so that the wall surface is not collapsed by the retaining
[0033]
A portal crane 7 is provided above the vertical shaft 1, and a
[0034]
The
A
In addition, the code |
[0035]
The
[0036]
Next, the production of the
The
[0037]
FIG. 6 is an end view showing the joining surface of the
[0038]
When the two halved
[0039]
When the joining of the
[0040]
On the other hand, in the vicinity of the front end of the
[0041]
Next, a connecting structure of another embodiment of the invention according to
FIG. 8 is a longitudinal cross-sectional view of a tube used in this connection structure, and FIG. 9 is a schematic view showing a joining end surface of a segment constituting this tube. 10 is a cross-sectional view taken along the line AA shown in FIG. 9, and FIG. 11 is a cross-sectional view taken along the line BB shown in FIG.
[0042]
Similar to the
[0043]
As shown in FIG. 9, a
[0044]
At the end in the circumferential direction of the segment, as shown in FIG. 10, the
[0045]
The
[0046]
【The invention's effect】
As described above, in the propulsion method according to the present invention and the connection structure of the pipe used in the present invention, the pipe is formed by assembling a plurality of segments in the circumferential direction, and each segment can be easily manufactured at the factory. Can be brought to the site. Therefore, an underground conduit can be constructed using a large-diameter pipe. Moreover, the 2nd water stop material is inserted along the joint surface of a propulsion direction in the junction part of a segment, These both ends are the 1st water stop material and 3rd water stop material which continued in the circumferential direction. Since it becomes a continuous thing, high water-stopping property is obtained in the junction part of a segment, and the connection part of a tubular body.
[Brief description of the drawings]
FIG. 1 is a schematic cross-sectional view showing an outline of a propulsion method according to an embodiment of the present invention.
FIG. 2 is a side view and a cross-sectional view of a tubular body used in the propulsion method according to the present invention.
FIG. 3 is a longitudinal sectional view of the tubular body shown in FIG. 2 and a portion connecting the tubular body in the axial direction.
4 is a schematic view showing a transportation state of segments constituting the tubular body shown in FIG. 2. FIG.
FIG. 5 is a schematic view showing a state in which the tubular body shown in FIG. 2 is assembled.
6 is a schematic view showing a joining surface of segments constituting the tubular body shown in FIG. 2 and a view of the joining portion as seen from the outside.
7 is a cross-sectional view of the segment joint portion in the vicinity of the rear end of the tubular body shown in FIG. 2. FIG.
FIG. 8 is a longitudinal sectional view showing another example of a tubular body that can be used in the propulsion method shown in FIG. 1;
9 is a schematic view showing a joining end face of a segment constituting the tubular body shown in FIG.
10 is a cross-sectional view taken along line AA shown in FIG.
11 is a cross-sectional view taken along line BB shown in FIG.
12 is a schematic diagram showing an end surface near the rear end of the segment constituting the tubular body shown in FIG. 8, and a schematic diagram showing an outer peripheral surface near the rear end at the joining portion of the segment.
[Explanation of symbols]
1 shaft
2 propulsion pipe
3 reaction wall
4 Jack
5 Jack stand
6 struts
7 Portal crane
8 earth and sand
9 Trailer
11 Yamazume
12 Raise the stomach
20, 40 tube
20 ', 40' segments constituting the tube
21,41 Steel collar
22, 42 The front part of the tube
23, 43 First water stop material
24, 44 Second water stop material
25, 45 Third water stop material
26 Shear key
27 PC tendons
28 Anchor
31 gap
32 Steel bar welded circumferentially
33 groove
51 Embedded part
52 Groove
53 Address plate
54 Notch
Claims (9)
前記管体は、周方向に複数に分割されたコンクリートセグメントを組み立てて形成するものとし、
該セグメントの製作時には、管体の推進方向の後方端に、隣接される管体との接続部を外側から囲む鋼製カラーを該セグメントの周方向に沿って固定するとともに、該セグメントと前記鋼製カラーとの間には該鋼製カラーに密着させて周方向に第1の止水材を介挿しておき、
該セグメントを組み立てて管体とする時には、前記鋼製カラーを管状に接合するとともに、周方向の前記第1の止水材が管体の全周にわたって連続するものとし、該セグメントの接合部には該管体の推進方向と平行な端面に沿って双方のセグメント間に第2の止水材を介挿し、該第2の止水材と周方向に配置された前記第1の止水材とを連続させ、
前記管体を推進方向に接合する時には、管状となった前記鋼製カラーの内側に接合する他の管体の前方端を挿入し、この接合する管体の前方端付近の外周面と管状となった前記鋼製カラーの内周面との間にリング状となった第3の止水材を介挿し、前記管体の推進方向に沿って配置された第2の止水材をリング状の前記第3の止水材と連続させることを特徴とする推進工法。A propulsion method that extrudes the propulsion pipe that becomes the lining body of the underground pipe line into the ground in the direction of its central axis, and repeats the extruding operation by sequentially connecting a predetermined length of the pipe body to the rear side of the extrusion,
The tubular body is formed by assembling a concrete segment divided into a plurality in the circumferential direction,
At the time of manufacturing the segment, a steel collar that surrounds a connecting portion with an adjacent tube body from the outside is fixed to the rear end in the propelling direction of the tube body along the circumferential direction of the segment. The first water-stopping material is inserted in the circumferential direction in close contact with the steel collar,
When assembling the segment into a tubular body, the steel collar is joined in a tubular shape, and the first water stop material in the circumferential direction is continuous over the entire circumference of the tubular body. The first water-stopping material is disposed in a circumferential direction with the second water-stopping material by inserting a second water-stopping material between both segments along an end surface parallel to the propulsion direction of the pipe body. And
When joining the tubular body in the propulsion direction, the front end of another tubular body to be joined is inserted inside the tubular steel collar that is tubular, the outer peripheral surface near the forward end of the joined tubular body, A third water-stopping material in a ring shape is interposed between the inner peripheral surface of the steel collar and the second water-stopping material disposed along the propulsion direction of the tubular body is a ring shape. A propulsion method characterized in that it is made continuous with the third water-stopping material.
前記管体を推進方向に接合するときには、リング状の前記第3の止水材を、前記第2の止水材の露出部に装着して密着させることを特徴とする請求項1に記載の推進工法。When assembling the segments into a tubular body, the second water blocking material inserted between the segments is disposed so as to be exposed on the outer peripheral surface near the front end of the tubular body,
The ring-shaped third waterstop material is attached to an exposed portion of the second waterstop material and is brought into close contact with the pipe body when joined in the propulsion direction. Promotion method.
該セグメントのコンクリート中に配置された緊張材によって周方向にプレストレスを導入し、
その後、前記鋼製カラーを溶接によって周方向に連続するように接合することを特徴とする請求項1に記載の推進工法When assembling the segments into a tube,
Introducing prestress in the circumferential direction by tendons placed in the concrete of the segment,
Thereafter, the steel collar is joined by welding so as to be continuous in the circumferential direction.
前記鋼製カラーを溶接によって接合した後、前記空隙に止水性を有する充填材を充填することによって、周方向に配置された前記第1の止水材を全周にわたって連続したものとすることを特徴とする請求項3に記載の推進工法。During the production of the segment, a gap is provided between the inner peripheral surface of the joint portion of the steel collar and the concrete of the segment,
After joining the steel collar by welding, the first water-stopping material arranged in the circumferential direction is made continuous over the entire circumference by filling the gap with a filler having water-stopping properties. The propulsion method according to claim 3, wherein the propulsion method is characterized.
前記管体は、周方向に複数に分割されたコンクリートのセグメントを組み立てて形成されたものであり、
前記管体の推進方向における後方の端部には、他の管体との接続部を外側から囲む管状の鋼製カラーが、一部を突き出して固着されており、
管状の鋼製カラーとこの鋼製カラーが固定されたコンクリートの管体との間には、全周にわたって周方向に連続する第1の止水材が介挿され、
前記管体を構成する複数のセグメントの接合部には、管体の推進方向に沿って第2の止水材が介挿され、
前記第1の止水材と前記第2の止水材とが連続しており、
接続される他の管体の前方部は、前記鋼製カラーの突き出した部分の内側に挿入され、該管体の外周面と前記鋼製カラーの内周面との間にリング状の第3の止水材が介挿されていることを特徴とする推進工法用管体の接続構造。It is connected in the direction of the central axis, and is connected to the pipe for propulsion method that is pushed into the ground and becomes the lining body of the underground conduit,
The tubular body is formed by assembling a concrete segment divided into a plurality in the circumferential direction,
A tubular steel collar surrounding the connecting portion with the other tubular body from the outside is fixed to the rear end portion in the propelling direction of the tubular body, protruding partly,
Between the tubular steel collar and the concrete tube to which the steel collar is fixed, a first water stop material that is continuous in the circumferential direction is inserted over the entire circumference,
A second water stop material is inserted along the propulsion direction of the pipe body at the joint portion of the plurality of segments constituting the pipe body,
The first water stop material and the second water stop material are continuous,
The front portion of the other tubular body to be connected is inserted inside the protruding portion of the steel collar, and a ring-shaped third portion is interposed between the outer peripheral surface of the tubular body and the inner peripheral surface of the steel collar. A structure for connecting a tubular body for a propulsion method, characterized in that a water-stopping material is inserted.
リング状の前記第3の止水材は、前記第2の止水材の露出部に装着され密着していることを特徴とする請求項5に記載の推進工法用管体の接続構造。The second water blocking material inserted between the segments is disposed so as to be exposed to the outer peripheral surface near the front end of the tubular body,
6. The structure for connecting a tubular body for a propulsion method according to claim 5, wherein the ring-shaped third water stop material is attached to and closely contacts the exposed portion of the second water stop material.
該鋼製カラーが取り付けられたコンクリートからなる管体の後方の端部は、該鋼製カラーの溶接による連結部付近の内周面とコンクリートからなる管体との間に空隙が設けられており、
前記鋼製カラーが溶接によって周方向に接合された後に前記空隙に充填された止水性を有する充填材により、周方向に配置された前記第1の止水材が全周にわたって連続するものとなっていることを特徴とする請求項5に記載の推進工法用管体の接続構造。The steel collar is connected in a tubular shape by welding when the segments are assembled,
The rear end of the tube made of concrete to which the steel collar is attached is provided with a gap between the inner peripheral surface in the vicinity of the connecting portion by welding of the steel collar and the tube made of concrete. ,
After the steel collar is joined in the circumferential direction by welding, the first water-stopping material arranged in the circumferential direction is continuous over the entire circumference by the filler having the water-stopper filled in the gap. The tube connection structure for a propulsion method according to claim 5, wherein:
周方向に配置された前記第1の止水材は、該埋め込み部に密着してコンクリート中に埋め込まれていることを特徴とする請求項5に記載の推進工法用管体の接続構造。The steel collar is connected in a tubular shape by welding at the time of assembling the segments. The steel collar protrudes from the inner peripheral surface of the steel collar into the inner concrete and has a plate-like embedded portion continuous in the circumferential direction. And
The connection structure for a tubular body for a propulsion method according to claim 5, wherein the first water stop material arranged in the circumferential direction is embedded in concrete in close contact with the embedded portion.
鋼製カラーが溶接によって周方向に接合された後に前記空隙に充填された止水性を有する充填材により、周方向に配置された前記第1の止水材と前記鋼製カラーとが連続するものとなっていることを特徴とする請求項8に記載の推進工法用管体の接続構造。Between the connecting portion by welding of the steel collar and the concrete to which the steel collar is fixed, a gap is provided in the outer peripheral surface side of the tubular body by cutting out the concrete,
The steel collar is continuously connected to the first water-stop material disposed in the circumferential direction by a filler having water-stopper filled in the gap after the steel collar is joined in the circumferential direction by welding. The structure for connecting a tubular body for a propulsion method according to claim 8, wherein:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002350090A JP3890293B2 (en) | 2002-12-02 | 2002-12-02 | Propulsion method and connection structure for propulsion method tube |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002350090A JP3890293B2 (en) | 2002-12-02 | 2002-12-02 | Propulsion method and connection structure for propulsion method tube |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004183289A JP2004183289A (en) | 2004-07-02 |
| JP3890293B2 true JP3890293B2 (en) | 2007-03-07 |
Family
ID=32752427
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2002350090A Expired - Lifetime JP3890293B2 (en) | 2002-12-02 | 2002-12-02 | Propulsion method and connection structure for propulsion method tube |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3890293B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4580294B2 (en) * | 2005-07-05 | 2010-11-10 | 戸田建設株式会社 | Water sealing structure of lining pipe and water stopping method of lining pipe |
| CN102072359B (en) * | 2009-11-24 | 2014-12-10 | 上海市政工程设计研究总院 | Curved-jacked steel pipe section and jacking method |
| JP6161369B2 (en) * | 2013-04-02 | 2017-07-12 | Smcプレコンクリート株式会社 | Medium push pipe for propulsion method |
| JP6218180B2 (en) * | 2014-06-20 | 2017-10-25 | 株式会社アルファシビルエンジニアリング | Rectangular section propulsion method |
| CN119507938B (en) * | 2025-01-15 | 2025-05-23 | 石家庄铁道大学 | Precast steel shell concrete annular tunnel pipe joint structure |
-
2002
- 2002-12-02 JP JP2002350090A patent/JP3890293B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004183289A (en) | 2004-07-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6733862B2 (en) | Construction method of the underground widening part | |
| JP3890293B2 (en) | Propulsion method and connection structure for propulsion method tube | |
| GB1597534A (en) | Method for the manufacture of underground pipes or tunnels or large diameter | |
| JP6030470B2 (en) | Tunnel construction method | |
| FI91992B (en) | Reliningsrör | |
| JP2018150780A (en) | Construction method of underground structure | |
| JP6132672B2 (en) | Existing pipe renewal method | |
| JP4980851B2 (en) | Tube seal structure | |
| JP6161369B2 (en) | Medium push pipe for propulsion method | |
| KR100679165B1 (en) | Construction method of segment of shield construction method and pipeline using this | |
| JP2016020564A (en) | Construction method of large cross-sectional tunnel | |
| JP2740737B2 (en) | Cutter disk of different diameter shield machine for excavation of different diameter tunnel, its underground joining device and its underground joining method | |
| JP4128520B2 (en) | Flexible joint structure | |
| JP3639989B2 (en) | Structure of pipe joints for sheath pipe propulsion method | |
| JP2001295580A (en) | High-water-pressure joint structure of centrifugal reinforced concrete pipe for propulsion and manufacturing method of the pipe | |
| JP2001090173A (en) | Pipeline repair method | |
| JP2007023545A (en) | Propulsion pipe start entrance, start entrance structure and start entrance water stop method | |
| JP2002038893A (en) | Waterproof structure of steel segment axial joint | |
| JPH1151249A (en) | Propulsive construction method and pipe fitting structure | |
| JP6230284B2 (en) | Existing pipe renewal method | |
| JP3487645B2 (en) | Underground joining structure and underground joining method of different diameter shield machine | |
| JPH0516479Y2 (en) | ||
| JP3713094B2 (en) | Connection method of existing underground pipe and new pipe by shield method | |
| JP4344637B2 (en) | Concrete pipe | |
| JP5715542B2 (en) | Tunnel connection method and connection ring |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20041029 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20061117 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061128 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061204 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 3890293 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121208 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121208 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20151208 Year of fee payment: 9 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| EXPY | Cancellation because of completion of term |