JP3894906B2 - Drainage channel and drainage system for tunnel and its construction method - Google Patents
Drainage channel and drainage system for tunnel and its construction method Download PDFInfo
- Publication number
- JP3894906B2 JP3894906B2 JP2003148809A JP2003148809A JP3894906B2 JP 3894906 B2 JP3894906 B2 JP 3894906B2 JP 2003148809 A JP2003148809 A JP 2003148809A JP 2003148809 A JP2003148809 A JP 2003148809A JP 3894906 B2 JP3894906 B2 JP 3894906B2
- Authority
- JP
- Japan
- Prior art keywords
- flow path
- tunnel
- drainage
- pair
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims description 19
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 73
- 238000003780 insertion Methods 0.000 claims description 61
- 230000037431 insertion Effects 0.000 claims description 61
- 125000006850 spacer group Chemical group 0.000 claims description 40
- 238000007789 sealing Methods 0.000 claims description 11
- 239000003566 sealing material Substances 0.000 claims description 6
- 239000011347 resin Substances 0.000 description 30
- 229920005989 resin Polymers 0.000 description 30
- 239000000853 adhesive Substances 0.000 description 12
- 230000001070 adhesive effect Effects 0.000 description 11
- 230000000694 effects Effects 0.000 description 11
- 238000010586 diagram Methods 0.000 description 8
- 239000000463 material Substances 0.000 description 6
- 230000007797 corrosion Effects 0.000 description 5
- 238000005260 corrosion Methods 0.000 description 5
- 229920002430 Fibre-reinforced plastic Polymers 0.000 description 4
- 239000011151 fibre-reinforced plastic Substances 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 230000006378 damage Effects 0.000 description 2
- 230000008014 freezing Effects 0.000 description 2
- 238000007710 freezing Methods 0.000 description 2
- 238000007654 immersion Methods 0.000 description 2
- 239000002990 reinforced plastic Substances 0.000 description 2
- 230000003139 buffering effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 239000006261 foam material Substances 0.000 description 1
- 239000011810 insulating material Substances 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 239000007779 soft material Substances 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、トンネル内に発生する漏水を排水するための排水流路と排水システムとその造築工法に係わり、特に、設置が簡単で工期が早く確実に排水できる排水流路と排水システムとその造築工法に関する。
【0002】
【従来の技術】
一般に、トンネルの内壁はコンクリートで覆われているが、経時とともにコンクリートが脆化することもあって所々にクラックを生じる。そして、このクラックの隙間から雨水等が漏水し、走行中の車体に滴下してドライバーの視界を妨げたり、特に、冬期には、路面を凍結させる原因にもなり危険性が指摘されている。また、打継部と呼ばれる主にトンネルの長手方向に存在するコンクリートの境界においても同様に漏水が起こるので、これらの漏水を排水する構造や工法が考えられている。
【0003】
例えば、特許文献1には、トンネル内壁面に設けられた断面がコの字形の排水溝に、断面がコの字形のシール部材を開放面を奥側にして排水溝の前面開放面を遮蔽するように取付け、また、このシール部材の側壁を排水溝の両内側壁に密着させたトンネル内漏水の排水構造が開示されている。
この特許文献1に開示された発明では、コの字形の排水構造を、トンネルに削成したコの字形の排水溝に開放面を奥側にして嵌合させることにより、トンネル内で生じる漏水をこの排水構造を流路として確実に排出させることができる。また、この排水構造には断熱性の高いシール部材が用いられているので、冬期でも水を凍結させることなく流下させることができる。
【0004】
また、特許文献2には、トンネル内の側壁や側壁近傍の床面にトンネルの長手方向に沿ってカッターで切り溝を設け、この切り溝に軟質材料の導水部材の下端基部を接着剤を介して嵌め込んで、トンネル側壁に排水用受け溝やトンネル側壁と導水部材間に排水用導水溝を形成するトンネル内の導水工法が開示されている。
この特許文献2に開示された発明では、トンネルの床面や側壁にカッターにより切り溝を設け、この切り溝に導水部材を嵌め込む方式なので、施工が簡単で低コストを実現し、トンネル内壁からの漏水を容易に一定方向に導水し排水できる。また、導水部材の基部が接着剤によって強固に固定されているので、止水効率がよく、さらに、導水部材が軟質成形品からなるので、緩衝効果を有し、歩行者等が導水部材に接触しても安全であり、その他外力がかかっても容易に復元する。
【0005】
【特許文献1】
特開平5−340200号公報
【特許文献2】
特開平8−135399号公報
【0006】
【発明が解決しようとする課題】
しかしながら、特許文献1に記載された従来の技術では、トンネルのコンクリート内壁に矩形断面の溝を削成する必要があり、この削成には手間と時間がかかるという課題があった。また、排水構造を接着剤によって固定しているが、特に水が介在する環境なので、接着力が低下しやすく、固定が十分でないという課題があった。
また、特許文献2では、導水部材に軟質成形品を用いており、確かに、ある程度の外力がかかっても復元するが、塑性変形してしまうと復元は困難であり、排水用受け溝や排水用導水溝は流路を確保できず、排水できないという課題があった。また、特許文献1と同様に、接着剤を用いて固定しているので、漏水に曝されながら経時とともに接着剤が脆化し、固定が十分でないという課題があった。
【0007】
本発明はかかる従来の事情に対処してなされたものであり、設置が簡単で工期が早く、耐久性を備えてなおかつ確実に排水できる排水流路と排水システムとその造築工法を提供することを目的とする。
【0008】
【課題を解決するための手段】
上記目的を達成するため、請求項1記載の発明である排水流路は、トンネルの内壁部において発生するクラックに間隙を形成して覆設される平板状の流路部と、クラックを挟んで内壁部に削成される一対の溝部に押入可能に流路部の端部よりも内側に垂設される一対の差込部と、この差込部の外側に設置されるとともに内壁部と流路部に間挿されて流路部と内壁部との間に空間を形成するスペーサと、流路部とスペーサを貫通して流路部を内壁部に固定する固定部と、流路部を内壁部に固定する固定部と、一対の溝部と一対の差込部の間に形成される封水部とを有するものである。
上記構成の排水流路は、流路部がトンネルの内壁部のクラックを覆い、このクラックからの漏水を保持部によって形成される流路で受け止めて導水するという作用を有する。また、封水部によって一対の溝部と一対の差込部の間が封水され、固定部は一対の差込部よりも外側の流路部で漏水に曝されることなく流路部と内壁部を固定するという作用を有する。
【0009】
また、請求項2に記載の発明である排水流路は、一対の差込部は、複数の切込みが設けられるものである。
上記構成の排水流路は、請求項1に記載の発明の作用に加えて、一対の差込部に複数の切込みがあるので、平板状の流路部は長手方向に湾曲しやすいという作用を有する。
【0010】
そして、請求項3の発明である排水流路は、トンネルの内壁部の長手方向に形成される打継部に間隙を形成して覆設される平板状の流路部と、打継部の下側に打継部と略平行に削成される溝部に押入可能に流路部の下端部よりも上側に垂設される差込部と、この差込部の外側に設置されるとともに内壁部と流路部に間挿されて流路部と内壁部との間に空間を形成するスペーサと、流路部とスペーサを貫通して流路部を内壁部に固定する固定部と、溝部と差込部の間に形成される封水部とを有するものである。
上記構成の排水流路は、流路部がトンネルの内壁部の打継部を覆い、この打継部からの漏水を保持部によって形成される流路で受け止めて導水するという作用を有する。また、封水部によって溝部と差込部の間が封水されるという作用を有する。
【0011】
請求項4に記載の発明である排水システムは、トンネルの内壁部において、トンネル長手方向に対して略垂直に請求項1又は請求項2に記載のトンネル用排水流路を第1の排水流路として設置し、この第1の排水流路の下端部に、トンネル長手方向に対して略水平に請求項3に記載のトンネル用排水流路を第2の排水流路として接続し、この第2の排水流路の一部に排水口を設けて排水するものである。
上記構成の排水システムは、略垂直に設ける第1の排水流路と略水平に設ける第2の排水流路を自在に接続し、トンネル内に発生するクラックからの漏水を第1の排水流路によって導水し、打継部からの漏水を第2の排水流路によって導水し、第2の排水流路の排水口より排水するという作用を有する。
【0012】
最後に、請求項5に記載の発明である排水システムの造築工法は、トンネルの内壁に略平行に一対の溝部を削成する工程と、一対の溝部に封水材を注入する工程と、端部よりも内側に一対の差込部が垂設される流路部において、この差込部を封水材が注入された一対の溝部に嵌入する工程と、差込部の外側で、かつ、流路部と内壁部との間にスペーサを設置して空間を形成する工程と、流路部とスペーサを貫通する固定具によって差込部よりも外側の流路部を内壁部に固定する工程とを有するものである。
上記構成の排水システムの造築工法は、トンネルの内壁に略平行に一対の溝部を削成し、この一対の溝部に封水材を注入して一対の差込部を端部よりも内側に垂設する流路部を押入することによって一対の差込部よりも外側の流路部を封水し、さらに、一対の差込部よりも外側の流路部を固定することによって固定手段を防水するという作用を有する。
【0013】
【発明の実施の形態】
以下に、本発明に係る排水流路及び排水システムの実施の形態を図1乃至図5に基づき説明する。(請求項1乃至請求項4に対応)
図1(a)は本実施の形態に係る排水システムの概念図であり、(b)は図1中の矢印Aで示される方向からみた排水システムの側面を示す概念図である。
図1(a)において、排水システム1は、垂直部用排水流路2a,2bと平行部用排水流路3を組合わせて連結したものである。
垂直部用排水流路2aは、トンネルの天井等の内壁部4に生じるクラックを覆い、このクラックからの漏水を垂直部用排水流路2a内に具備する流路で受け止めて導水するものであり、トンネルの長手方向に対して垂直方向に設置され、平行部用排水流路3に接続されている。
一方、平行部用排水流路3は、トンネルのアーチ状の天井部分と垂直な壁部分のコンクリートの境界となる打継部5を覆い、この打継部5からの漏水を平行部用排水流路3内の流路で受け止めて導水するものであり、トンネルの長手方向に対して平行方向に設置されている。
そして、垂直部用排水流路2bは、垂直部用排水流路2aと同様に、トンネルの長手方向に対して垂直に配置されて平行部用排水流路3の下方に連結され、図示していないが、トンネル内に設置される排水溝に接続されている。垂直部用排水流路2bは、垂直部用排水流路2a及び平行部用排水流路3からの流水を排水溝へ導水し排水するとともに、平行部用排水流路3の下方に発生するクラックを覆ってこのクラックからの漏水を導水し排水する。
なお、図1(a)中では垂直部用排水流路2a,2bはトンネルの長手方向に等間隔に配置されているが、等間隔でなくてもよく、不特定な位置に発生するクラックを覆って設置することができ、また、トンネルの長手方向に対して垂直方向だけでなく、斜めに設置することも可能であり、垂直部用排水流路2a,2bはずらして設置することも可能である。
また、符号6は、垂直部用排水流路2a,2b及び平行部用排水流路3を内壁部4へ固定するためのアンカーボルトであり、複数設置される。
【0014】
次に、図1(b)において、排水システム1では、垂直部用排水流路2aはトンネル内壁部4の天井の曲面7に沿って設置され、続いて、この垂直部用排水流路2aの下端を覆って平行部用排水流路3が打継部5を挟んで設置され、そして、この平行部用排水流路3の下部を覆って垂直部用排水流路2bが設置され、図示していないが、トンネル内の排水溝へ接続されている。
なお、後述するが、垂直部用排水流路2aは、複数の切込み8を有した差込板9によって天井の曲面に沿わせて設置することができる。
【0015】
ここで、図2を用いて、垂直部用排水流路と平行部用排水流路の接続について説明する。
図2は、図1中の符号Bで囲まれた部分の拡大図である。
図2において、垂直部用排水流路2aは、その下端を平行部用排水流路3に覆われるようにして平行部用排水流路3に接続されている。なお、この接続は平行部用排水流路3のアンカーボルト6が打込まれていない開放された部分において行われるので、流路10aは閉塞されない。そして、平行部用排水流路3は、後述する差込板9とスペーサ11の一部が切欠きされた部分に、垂直部用排水流路2bの流路10bが合致するように、垂直部用排水流路2bの上端が平行部用排水流路3を覆うように接続されている。そして、これらの境界は、後述の樹脂によって漏水しないように封水されている。なお、この封水には、排水流路の材料であるFRP等の強化プラスチックを用いてもよいし、耐水性の接着剤等を用いてもよい。
【0016】
したがって、このように構成された排水システム1では、トンネル内壁部4のクラックからの漏水は垂直部用排水流路2aを通り、平行部用排水流路3を経由して、垂直部用排水流路2bへ導水され、途中でトンネル内に漏れることなく排水溝へ確実に排水される。また、同じく、打継部5からの漏水もトンネル内に漏れることなく平行部用排水流路3を通り、垂直部用排水流路2bへ導水され、排水溝へ排水されるのである。
【0017】
次に、垂直部用排水流路について図3を参照しながら詳細に説明する。
図3は、図1中の矢印Cで示される方向からみた垂直部用排水流路の矢視断面図である。
図3において、垂直部用排水流路2aは、平板状の流路板12の両端に設けられた一対の差込板9a、9bがトンネルの内壁部4に発生したクラック13を挟んで削成された一対の溝14a、14bに嵌入されて設置されている。
そして、流路板12と内壁部4の間で、一対の差込板9a、9bの外側に一対のスペーサ11a、内側に一対のスペーサ11bが挿入されており、この外側の一対のスペーサ11aを各々貫通してアンカーボルト6が流路板12と内壁部4を固定している。
また、一対の差込板9a、9bと一対の溝14a、14bとの間には各々樹脂15が狭入されている。
【0018】
流路板12及び一対の差込板9a、9bに用いる材料は、FRP(Fiber Reinforced Plastics)等の強化プラスチックが好ましく、特に、FRPを用いると、耐久性があり、さらに、弾力があるので、トンネルの内壁部4のコンクリート表面が変位してもある程度追随することができる。また、流路板12の内面に発泡材等の保温材を取付けると、冬期における水の凍結を防止することができる。そして、流路板12の外面はトンネルの内壁部4と同系色に塗装等によって着色することが可能である。なお、流路板12及び一対の差込板9a、9bは一体成形によって作製する方がよい。
【0019】
二対のスペーサ11a、11bは流路板12と内壁部4との間に空間をつくるもので、特にスペーサ11bに挟まれる空間が流路10aとなる。
また、本実施の形態ではスペーサ11a、11bはゴム製であり、外部から衝撃がかかった場合にその衝撃を吸収し、流路板12の損傷を防ぐことができる。なお、使用する材料はゴムに限定されるものではない。そして、設置数についても二対に限定されるものではなく、流路板12と内壁部4に空間を保持できれば1個でも構わない。
【0020】
樹脂15は、一対の差込板9a、9bと一対の溝14a、14bの間に隙間なく狭入されるので、一対の差込板9a、9bよりも外側は封水され、流路10aからの漏水を防止することができる。
また、樹脂15は固化する液状のものであるが、耐久性があればゴム等でもよく、好ましくは、一対の差込板9a、9bと内壁部4が接着可能な接着剤を選定すると、封水効果に加えて接着効果も得られる。
なお、この樹脂15は、一対の差込板9a、9bと一対の溝14a、14bの間だけでなく、内側の一対のスペーサ11b,11bの周囲に狭入するか、或いは、内側と外側と両方のスペーサ11a、11bの周囲に狭入するとさらに封水性が向上し、なおかつ、スペーサ11a、11b自体の耐久性も向上する。あるいは、外側の一対のスペーサ11a,11aに代えて流路板12と内壁部4の間に狭入するようにしてもよい。
【0021】
そして、アンカーボルト6は、樹脂15によって封水された一対の差込板9a、9bの外側に設置されているので、浸水による腐食が防止され、垂直部用排水流路2aと内壁部4との固定を長期間にわたって維持することができる。
また、アンカーボルト6は、スペーサ11aを貫通することによって、前述のように、打込み時の衝撃がゴム製のスペーサ11aに吸収され垂直部用排水流路2aへの損傷を低減できる。しかも、スペーサ11aに覆われるので防錆等の腐食も低減できる。なお、スペーサ11aに代えて樹脂15を用いた場合でも同様の効果がある。
【0022】
このように構成された垂直部用排水流路2aでは、トンネルの内壁部4からの漏水は、スペーサ11a、11bによって保持される流路10aを流下するが、この際、樹脂15によって、一対の差込板9a、9bよりも外側が完全に封水されているので、トンネル内へ漏水することがない。
そして、アンカーボルト6は、樹脂によって封水される一対の差込板9a、9bの外側に設置されるので、水による腐食がなく、流路板12と内壁部4を長期間にわたって固定し、垂直部用排水流路2aの耐久性を高めることができる。
なお、説明は省略するが、垂直部用排水流路2bについても垂直部用排水流路2aと同様の構造と作用、効果を有している。
【0023】
続いて、平行部用排水流路について図4を参照しながら説明する。図4(a)は、図1中の矢印Dで示される方向からみた平行部用排水流路の矢視断面図であり、(b)は同じく、図1中の矢印Eで示される方向からみた平行部用排水流路の矢視断面図である。
図4(a)において、平行部用排水流路3は、トンネルの内壁部4のコンクリートの打継部5に覆設されており、詳しくは、平板状の流路板12の下端に設けられた差込板9が、打継部5の下方に削成された溝14に嵌入されて設置されている。
そして、流路板12と内壁部4の間で、流路板12の上部にスペーサ11c、差込板9の外側にスペーサ11dが挿入されており、これらのスペーサ11c、11dを各々貫通してアンカーボルト6が流路板12と内壁部4を固定している。
また、差込板9と溝14の間には樹脂15が狭入されている。
スペーサ11c、11dによって流路板12と内壁部4との間には空間がつくられ、この空間が流路10となる。なお、スペーサ11cは、流路板12に対して不連続に複数設けられるものであり、流路10の上方は開放される。また、差込板9の内側にもスペーサを設けてもよい。さらに、図に示すとおり打継部5の上下でコンクリートの段差がある場合でも、スペーサ11c、11dの大きさと溝14の切込み深さを変えることで平行部用排水流路3を設置することができる。
樹脂15は、差込板9と溝14の間に隙間なく狭入されるので、差込板9の下側は完全に封水され、流路10を流れる水が漏水することはない。
そして、図4(a)中では、平行部用排水流路3と内壁部4の固定を上下二箇所のアンカーボルト6で行っているが、漏水量が少なく、平行部用排水流路3から水が溢れることがない場合は、上側のアンカーボルト6のみの固定でもよい。この場合、上側のアンカーボルト6は浸水する可能性が低く、仮に水が撥ねることがあってもスペーサ11cに覆われているので腐食しにくい。逆に、漏水量が多い場合は、樹脂15によって封水される下側のアンカーボルト6を用いて固定すると、下側のアンカーボルト6は、水による腐食がないので、平行部用排水流路3と内壁部4を長期間にわたって固定することができる。もちろん、漏水量が少ない場合に、下側のアンカーボルト6によってのみ固定してもよいことは言うまでもない。
なお、流路板10、差込板9、スペーサ11c、11d及び樹脂15は、垂直部用排水流路2aと同じ材料が用いられ、その効果についても同様である。
【0024】
次に、図4(b)において、平行部用排水流路3を上方からみると、平行部用排水流路3は、流路板12と内壁部4の間にスペーサ11cが間挿され、このスペーサ11cを貫通するアンカーボルト6によって内壁部4に固定されている。そして、流路板12の上方は開放されているので、下方に接続されている垂直部用排水流路2bの流路10bが見えている。
【0025】
このように構成された平行部用排水流路3では、トンネルの打継部5からの漏水は、樹脂15によって差込板9よりも下側が完全に封水されているので、トンネル内に漏水することがなく、スペーサ11c、11dによって保持される流路10を流れるのである。
また、アンカーボルト6は、浸水しない上部と、樹脂15によって封水される差込板9の下側に設置されるので、水による腐食がなく、流路板12と内壁部4を長期間にわたって固定し、平行部用排水流路3の耐久性を高めることができる。
【0026】
次に、図5を用いて垂直部用排水流路の切込みについて説明する。図5(a)は、本実施の形態に係る垂直部用排水流路の外形図であり、(b)は同じく垂直部用排水流路を天井の曲面部に設置した場合の概念図である。
図5(a)において、垂直部用排水流路2は、流路板12と一対の差込板9を有しており、そして、この差込板9には、長手方向に対して垂直に複数の切込み8が設けられている。
これらの切込み8によって流路板12は湾曲しやすくなるので、図5(b)に示すように、曲面を有する天井に容易に垂直部用排水流路2を設置することが可能となる。なお、予め、設置するトンネルの天井の形状に合わせて垂直部用排水流路2を形取っておくとさらに簡単に設置できる。また、切込みによって生じる差込板の隙間には前述の樹脂を狭入するので、流路からの漏水はない。
【0027】
このように、差込板9に複数の切込み8を設けると、流路板12は湾曲しやすく、設置作業が容易になる上に、無理に曲げる場合に比べて応力が分散され易いので、応力集中による材料破壊はなく、耐用寿命が長くなる。
【0028】
最後に、本発明に係る排水システムの造築工法の実施の形態について図6を参照しながら説明する。(請求項5に対応)
図6は、本実施の形態に係る排水システムの造築工法の工程を示す概念図である。
図6において、ステップS1は、トンネル内壁部に溝を削成する工程を示している。このステップS1では、トンネル内壁部に発生するクラックを挟んで一対の溝を平行にカッターを用いて削成する。この溝には、垂直部用排水流路に設けられる凸状の差込板が内壁部に対して垂直に押入されるので、溝の形状は幅狭でよく、したがって、短時間で削成できる。また、削成する体積が小さいので、トンネルの強度を低下させない。なお、防塵対策として水をかけながら行うとよい。
【0029】
次にステップS2は、溝に樹脂を注入する工程を示している。このステップS2では、ステップS1において削成された溝に樹脂を注入する。なお、このステップS2の工程を行う前に、溝にプライマーを塗布しておくと、樹脂の溝への接着力が強化される。
【0030】
ステップS3は、垂直部用排水流路を押入する工程を示している。このステップS3では、ステップS2において樹脂が注入された溝に、垂直部用排水流路を押入する。この垂直部用排水流路の押入は流路板に垂設される一対の差込板を樹脂が注入された溝に嵌入することによって行われるので、作業が簡単で短時間に行われる。
また、溝に注入された樹脂は差込板によって溝の奥側へ移動するので、ステップS3において垂直部用排水流路を押入した後、再度、樹脂を注入し、その後、はみ出した部分を除去する。そうすると、樹脂によって一対の差込板から外側が完全に封水されるので、垂直部用排水流路からの漏水が防止される。
なお、ステップS2と同様に、一対の差込板の各々の外面にプライマーを塗布しておくと、樹脂と差込板との接着力が強化される。さらに、一対の差込板に両面テープ等の接着手段を施しておくと、樹脂が固化されるまでの接着力が確保される。
【0031】
最後にステップS4はアンカーボルトを打込む工程を示している。このステップS4においては、押入された垂直部用排水流路にアンカーボルトを打込み、垂直部用排水流路をトンネルの内壁部に固定する。アンカーボルトは樹脂によって封水された差込板の外側に打込まれるので、浸水による腐食が防止され、垂直部用排水流路と内壁部を長期間にわたって固定することができる。
なお、平行部用排水流路を設置する場合においてもほぼ同様の工程で行うことができる。
【0032】
このように構成された排水システムの造築工法においては、溝の形状が幅狭でかつ体積が小さいので、短時間で削成することができ、そして、トンネルの強度を低下させずに排水システムを造築することができる。また、垂直部用排水流路の押入も容易であるので、工期が短縮され、その結果、施工コストを低減できる。
そして、排水システムでは樹脂によって流路の周囲を完全に封水するので、垂直部用排水流路からのトンネル内の漏水がなく、トンネル内では、車両が安全に走行することができる。
また、垂直部用排水流路と内壁部を固定するためのアンカーボルトを樹脂によって封水される部分に打込むので、アンカーボルトの浸水による腐食が防止され、垂直部用排水流路と内壁部を長期間にわたって固定し、排水システムの耐久性を向上させる。
【0033】
【発明の効果】
以上説明したように、本発明の請求項1又は請求項2に記載の排水流路は、トンネルの内壁部に発生するクラックからの漏水を、内壁部と流路部の間に保持部によって保持される空間を流路として流下させることができる。また、封水部によって流路の外側が封水されるので、排水流路からトンネル内へ漏水することがなく、さらに、封水される部分に固定部を設けるので、固定部の浸水による腐食が防止され、長期間にわたって流路部を内壁部に固定することができる。
【0034】
また、本発明の請求項2に記載の排水流路においては、差込部に設けられる複数の切込みよって流路部は湾曲しやすく、トンネルの天井等の曲面への設置が容易となる。
【0035】
本発明の請求項3に記載の排水流路においては、トンネルの打継部からの漏水を、内壁部と流路部の間に保持部によって保持される空間を流路として導水させることができる。また、封水部によって流路の下側が封水されるので、排水流路からトンネル内へ漏水することはない。
【0036】
本発明の請求項4に記載の排水システムにおいては、トンネル長手方向に対して垂直に設置される第1の排水流路によってトンネルの内壁部において発生するクラックからの漏水が導水され、そして、この第1の排水流路の下端部に連結されるトンネル長手方向に対して水平に設置される第2の排水流路によってトンネルの打継部からの漏水が導水され、第2の排水流路の一部に設けられる排水口からこれらの漏水を確実に排水することができる。
【0037】
そして、本発明の請求項5に記載の排水システムの造築工法においては、溝の削成や排水流路の設置が容易であるので、工期が短く、施工コストを低減できる。
また、流路の外側を封水材によって完全に封水するので、トンネル内では、流路部からの漏水がなく、車両が安全に走行することができる。
【図面の簡単な説明】
【図1】(a)は本発明の本実施の形態に係る排水システムの概念図であり、(b)は図1中の矢印Aで示される方向からみた排水システムの側面を示す概念図である。
【図2】図1中の符号Bで囲まれた部分の拡大図である。
【図3】図1中の矢印Cで示される方向からみた垂直部用排水流路の矢視断面図である。
【図4】(a)は、図1中の矢印Dで示される方向からみた平行部用排水流路の矢視断面図であり、(b)は同じく、図1中の矢印Eで示される方向からみた平行部用排水流路の矢視断面図である。
【図5】(a)は、本実施の形態に係る垂直部用排水流路の外形図であり、(b)は同じく垂直部用排水流路を天井の曲面部に設置した場合の概念図である。
【図6】本発明の本実施の形態に係る排水システムの造築工法の工程を示す概念図である。
【符号の説明】
1…排水システム 2,2a,2b…垂直部用排水流路 3…平行部用排水流路 4…内壁部 5…打継部 6…アンカーボルト 7…天井の曲面 8…切込み 9,9a,9b…差込板 10,10a,10b…流路 11,11a,11b,11c,11d…スペーサ 12…流路板 13…クラック 14,14a,14b…溝 15…樹脂[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a drainage channel and drainage system for draining water leaking in a tunnel, and a construction method thereof, and more particularly, a drainage channel and drainage system that can be drained quickly and reliably and can be drained quickly. Concerning construction methods.
[0002]
[Prior art]
Generally, the inner wall of the tunnel is covered with concrete, but cracks occur in some places because the concrete becomes brittle over time. In addition, it has been pointed out that there is a danger that rainwater or the like leaks from the crack gap and drops on the running vehicle body to obstruct the driver's field of view. In addition, since water leaks in the same manner at the boundary of the concrete, which is called the joint, mainly in the longitudinal direction of the tunnel, a structure and construction method for draining these water leaks are considered.
[0003]
For example, in
In the invention disclosed in
[0004]
Further, in
In the invention disclosed in this
[0005]
[Patent Document 1]
JP-A-5-340200
[Patent Document 2]
JP-A-8-135399
[0006]
[Problems to be solved by the invention]
However, in the conventional technique described in
Further, in
[0007]
The present invention has been made in response to such a conventional situation, and provides a drainage channel, a drainage system, and a construction method thereof that are easy to install, have a fast construction period, have durability, and can reliably drain water. With the goal.
[0008]
[Means for Solving the Problems]
In order to achieve the above object, the drainage channel according to the first aspect of the present invention includes a flat channel portion that is covered with a crack formed in an inner wall portion of the tunnel, and a crack is sandwiched between the flat channel portion. A pair of insertion parts that are suspended from the end of the flow path so as to be able to be pushed into a pair of grooves cut on the inner wall, and Installed outside this plug-in Inserted between the inner wall and the channel. Spacer that forms a space between the flow path part and the inner wall part When, Through the channel and spacer It has a fixing part for fixing the flow path part to the inner wall part, a fixing part for fixing the flow path part to the inner wall part, and a sealing part formed between the pair of groove parts and the pair of insertion parts. .
The drainage channel configured as described above has an effect that the channel portion covers a crack in the inner wall portion of the tunnel, and water leakage from the crack is received by the channel formed by the holding portion to guide water. Further, the sealing portion seals between the pair of groove portions and the pair of insertion portions, and the fixing portion is not exposed to water leakage in the passage portion outside the pair of insertion portions. It has the effect of fixing the part.
[0009]
In the drainage channel according to the second aspect of the present invention, the pair of insertion portions are provided with a plurality of cuts.
In addition to the operation of the invention according to
[0010]
The drainage flow channel according to the invention of
The drainage channel having the above-described structure has an effect that the channel portion covers the joint portion of the inner wall portion of the tunnel, and water leakage from the joint portion is received and guided by the channel formed by the holding portion. Moreover, it has the effect | action that between a groove part and an insertion part is sealed by the sealing part.
[0011]
According to a fourth aspect of the present invention, there is provided a drainage system in which the tunnel drainage channel according to
The drainage system having the above configuration freely connects a first drainage channel provided substantially vertically and a second drainage channel provided substantially horizontally, and leaks water from a crack generated in the tunnel to the first drainage channel. In this case, the water is led by the second drainage flow path, and the water leaked from the joint portion is drained from the drainage port of the second drainage flow path.
[0012]
Finally, the construction method of the drainage system according to
The construction method of the drainage system having the above configuration is to cut a pair of grooves substantially parallel to the inner wall of the tunnel, and to inject a sealing material into the pair of grooves, so that the pair of insertion portions are located inside the ends. Sealing the flow path part outside the pair of insertion parts by pushing the flow path part to be suspended, and further fixing the flow means part by fixing the flow path part outside the pair of insertion parts. Has the effect of waterproofing.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of a drainage channel and a drainage system according to the present invention will be described with reference to FIGS. 1 to 5. (Corresponding to
FIG. 1A is a conceptual diagram of a drainage system according to the present embodiment, and FIG. 1B is a conceptual diagram showing a side surface of the drainage system viewed from the direction indicated by arrow A in FIG.
In FIG. 1A, a
The vertical drainage channel 2a covers the cracks generated in the
On the other hand, the parallel part
The
In FIG. 1 (a), the
[0014]
Next, in FIG. 1B, in the
In addition, although mentioned later, the vertical part drainage flow path 2a can be installed along the curved surface of the ceiling by the
[0015]
Here, the connection of the drainage channel for vertical parts and the drainage channel for parallel parts is demonstrated using FIG.
FIG. 2 is an enlarged view of a portion surrounded by a symbol B in FIG.
In FIG. 2, the vertical part drainage channel 2 a is connected to the parallel
[0016]
Therefore, in the
[0017]
Next, the vertical drainage channel will be described in detail with reference to FIG.
FIG. 3 is a cross-sectional view of the vertical portion drainage channel as seen from the direction indicated by the arrow C in FIG.
In FIG. 3, the vertical drainage channel 2 a is formed by sandwiching a
And between the
A resin 15 is inserted between the pair of insertion plates 9a and 9b and the pair of grooves 14a and 14b.
[0018]
The material used for the
[0019]
The two pairs of
Further, in the present embodiment, the
[0020]
Since the resin 15 is narrowly inserted between the pair of insertion plates 9a and 9b and the pair of grooves 14a and 14b, the outside of the pair of insertion plates 9a and 9b is sealed with water from the channel 10a. Water leakage can be prevented.
The resin 15 is a solidified liquid, but may be rubber or the like as long as it has durability. Preferably, when an adhesive capable of adhering the pair of insertion plates 9a and 9b and the
The resin 15 is not only between the pair of insertion plates 9a and 9b and the pair of grooves 14a and 14b, but also is narrowly inserted around the inner pair of
[0021]
And since the
Further, as described above, the
[0022]
In the vertical part drainage flow path 2a configured as described above, water leakage from the
And since the
In addition, although description is abbreviate | omitted, it has the structure, an effect | action, and effect similar to the vertical part drainage flow path 2a also about the vertical part
[0023]
Next, the parallel part drainage flow path will be described with reference to FIG. 4A is a cross-sectional view of the parallel part drainage channel as viewed from the direction indicated by arrow D in FIG. 1, and FIG. 4B is also from the direction indicated by arrow E in FIG. It is the arrow directional cross-sectional view of the drainage flow path for parallel parts.
In FIG. 4 (a), the parallel part
And between the
A resin 15 is inserted between the
Spaces are created between the
Since the resin 15 is narrowly inserted between the
In FIG. 4A, the parallel part
The
[0024]
Next, in FIG. 4B, when the parallel part
[0025]
In the parallel part
In addition, the
[0026]
Next, the cutting of the vertical drainage flow path will be described with reference to FIG. FIG. 5A is an outline view of the vertical drainage channel according to the present embodiment, and FIG. 5B is a conceptual diagram when the vertical drainage channel is similarly installed on the curved surface portion of the ceiling. .
In FIG. 5A, the vertical
Since the
[0027]
As described above, when the plurality of cuts 8 are provided in the
[0028]
Finally, an embodiment of the drainage system construction method according to the present invention will be described with reference to FIG. (Corresponding to claim 5)
FIG. 6 is a conceptual diagram showing the steps of the drainage system construction method according to the present embodiment.
In FIG. 6, step S <b> 1 shows a step of cutting a groove in the tunnel inner wall. In this step S1, a pair of grooves are cut in parallel using a cutter with a crack generated in the inner wall of the tunnel interposed therebetween. Since the convex insertion plate provided in the vertical drainage flow path is pushed into the groove perpendicularly to the inner wall portion, the groove shape may be narrow and can be cut in a short time. . Further, since the volume to be cut is small, the strength of the tunnel is not reduced. In addition, it is good to carry out with water as a dust-proof measure.
[0029]
Next, step S2 shows a step of injecting resin into the groove. In step S2, resin is injected into the groove cut in step S1. In addition, if the primer is applied to the groove before the step S2 is performed, the adhesive force of the resin to the groove is enhanced.
[0030]
Step S3 shows a step of pushing in the vertical part drainage flow path. In this step S3, the vertical part drainage channel is pushed into the groove into which the resin has been injected in step S2. Since the vertical drainage channel is pushed in by inserting a pair of insertion plates suspended from the channel plate into the groove into which the resin is injected, the operation is simple and performed in a short time.
In addition, since the resin injected into the groove moves to the back side of the groove by the insertion plate, the resin is injected again after pushing the vertical drainage channel in step S3, and then the protruding portion is removed. To do. Then, since the outside is completely sealed from the pair of insertion plates by the resin, water leakage from the vertical drainage channel is prevented.
As in step S2, if a primer is applied to the outer surface of each of the pair of insertion plates, the adhesive force between the resin and the insertion plate is enhanced. Furthermore, if an adhesive means such as a double-sided tape is applied to the pair of insertion plates, an adhesive force until the resin is solidified is secured.
[0031]
Finally, step S4 shows a step of driving an anchor bolt. In this step S4, anchor bolts are driven into the pushed vertical drainage channel, and the vertical drainage channel is fixed to the inner wall of the tunnel. Since the anchor bolt is driven into the outside of the insertion plate sealed with resin, corrosion due to water immersion is prevented and the vertical drainage channel and the inner wall portion can be fixed over a long period of time.
In addition, when installing the parallel part drainage flow path, it can be performed in substantially the same process.
[0032]
In the construction method of the drainage system constructed in this way, the groove shape is narrow and the volume is small, so that it can be cut in a short time and the drainage system without reducing the strength of the tunnel Can be built. Further, since the vertical drainage channel can be easily pushed in, the construction period is shortened, and as a result, the construction cost can be reduced.
In the drainage system, the periphery of the flow path is completely sealed by the resin, so that there is no water leakage in the tunnel from the vertical drainage flow path, and the vehicle can travel safely in the tunnel.
In addition, the anchor bolt for fixing the vertical drainage channel and the inner wall portion is driven into the portion sealed by the resin, so that the anchor bolt is prevented from being corroded by water, and the vertical drainage channel and the inner wall portion are prevented. To improve the durability of the drainage system.
[0033]
【The invention's effect】
As described above, the drainage channel according to
[0034]
Further, in the drainage channel according to the second aspect of the present invention, the channel portion is easily bent by the plurality of cuts provided in the insertion portion, and installation on a curved surface such as a tunnel ceiling is facilitated.
[0035]
In the drainage channel according to the third aspect of the present invention, it is possible to introduce water leakage from the joint portion of the tunnel using the space held by the holding unit between the inner wall and the channel unit as the channel. . Moreover, since the lower side of the flow path is sealed by the sealing portion, water does not leak from the drain flow path into the tunnel.
[0036]
In the drainage system according to
[0037]
And in the construction method of the drainage system of
Further, since the outside of the flow path is completely sealed with the water sealing material, there is no water leakage from the flow path portion in the tunnel, and the vehicle can travel safely.
[Brief description of the drawings]
FIG. 1A is a conceptual diagram of a drainage system according to the present embodiment of the present invention, and FIG. 1B is a conceptual diagram showing a side surface of the drainage system as viewed from the direction indicated by arrow A in FIG. is there.
FIG. 2 is an enlarged view of a portion surrounded by a symbol B in FIG.
3 is a cross-sectional view of the vertical portion drainage channel as seen from the direction indicated by arrow C in FIG.
4A is a cross-sectional view of the parallel portion drainage channel as viewed from the direction indicated by the arrow D in FIG. 1, and FIG. 4B is also indicated by the arrow E in FIG. It is arrow sectional drawing of the drainage flow path for parallel parts seen from the direction.
5A is an external view of a vertical drainage channel according to the present embodiment, and FIG. 5B is a conceptual diagram when the vertical drainage channel is similarly installed on a curved surface portion of a ceiling. It is.
FIG. 6 is a conceptual diagram showing a process of a construction method for a drainage system according to the present embodiment of the present invention.
[Explanation of symbols]
DESCRIPTION OF
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003148809A JP3894906B2 (en) | 2003-05-27 | 2003-05-27 | Drainage channel and drainage system for tunnel and its construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003148809A JP3894906B2 (en) | 2003-05-27 | 2003-05-27 | Drainage channel and drainage system for tunnel and its construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004353175A JP2004353175A (en) | 2004-12-16 |
| JP3894906B2 true JP3894906B2 (en) | 2007-03-22 |
Family
ID=34045084
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2003148809A Expired - Fee Related JP3894906B2 (en) | 2003-05-27 | 2003-05-27 | Drainage channel and drainage system for tunnel and its construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3894906B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104088663A (en) * | 2014-06-24 | 2014-10-08 | 高渐飞 | Method and device for monitoring dropping water flow of karst cave |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4582585B2 (en) * | 2005-08-26 | 2010-11-17 | ショーボンド建設株式会社 | Fasteners for joint members |
| JP4573788B2 (en) * | 2006-03-14 | 2010-11-04 | ショーボンド建設株式会社 | Water conveyance method using fiber reinforced resin (FRP) plate in concrete structures |
| CN106988758B (en) * | 2017-05-08 | 2023-09-01 | 中铁五局集团第五工程有限责任公司 | Construction method for crossing large-scale vertical karst cave group tunnel |
-
2003
- 2003-05-27 JP JP2003148809A patent/JP3894906B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104088663A (en) * | 2014-06-24 | 2014-10-08 | 高渐飞 | Method and device for monitoring dropping water flow of karst cave |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004353175A (en) | 2004-12-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6093808B2 (en) | Piping structure of foundation and piping method of foundation | |
| US8683773B2 (en) | System and method for leaking crack repair | |
| KR101776152B1 (en) | Waterproofing apparatus for expantion joint repairing of concrete constructure block | |
| KR101186104B1 (en) | Method for repairing expansion joint part between concrete structures using inducing conduct pipe | |
| JP3894906B2 (en) | Drainage channel and drainage system for tunnel and its construction method | |
| KR101731873B1 (en) | Structure constructing lining member for concrete water tank | |
| EP3963142B1 (en) | Watertight joint and method of installing a watertight joint | |
| JP4982232B2 (en) | How to install the anode | |
| JP3865276B2 (en) | Resin-coated synthetic segment with drainage function | |
| JPH11350477A (en) | Ground surface side fixing device for ground anchor | |
| JP6913940B2 (en) | Water guide panel unit and water guide | |
| JP2009203715A (en) | Waterproof sealing member for clearance between concrete walls, and waterproof sealing method | |
| JP2015038281A (en) | U-shaped groove cover capable of preventing salt damage by antifreezing agent spread on express highway surface, and construction method of the same | |
| JP6206899B2 (en) | Earth retaining pipe for reaching mine and underground pipe construction method using the same | |
| KR101497228B1 (en) | Sealant preferred filling waterproofing method of prefabricated structure joint | |
| JP6242110B2 (en) | Waterway repair structure and repair method | |
| KR20110092783A (en) | Index packer with water-expandable index material and strand holding device using the same | |
| KR100664494B1 (en) | Manhole pipeline sealing construction method | |
| CN221219097U (en) | Basement bottom plate sealing device | |
| JP5210429B1 (en) | Water stop structure and water stop construction method | |
| JPH11323833A (en) | Headrace gutter | |
| JP2010270481A (en) | Water cut-off plate | |
| JP3413588B2 (en) | Water stop method in the ground wire | |
| JP5604281B2 (en) | Water-return structure of extruded cement board | |
| JP5197662B2 (en) | Rehabilitation panel member and method for rehabilitation of wall of deteriorated structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060526 |
|
| A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20060622 |
|
| A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20060711 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060718 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060919 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061122 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061212 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 3894906 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091222 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101222 Year of fee payment: 4 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111222 Year of fee payment: 5 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111222 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121222 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121222 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131222 Year of fee payment: 7 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S631 | Written request for registration of reclamation of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313631 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |