JP3938658B2 - A method for predicting blow-through phenomena associated with blast furnace wind pressure fluctuations. - Google Patents
A method for predicting blow-through phenomena associated with blast furnace wind pressure fluctuations. Download PDFInfo
- Publication number
- JP3938658B2 JP3938658B2 JP2000309953A JP2000309953A JP3938658B2 JP 3938658 B2 JP3938658 B2 JP 3938658B2 JP 2000309953 A JP2000309953 A JP 2000309953A JP 2000309953 A JP2000309953 A JP 2000309953A JP 3938658 B2 JP3938658 B2 JP 3938658B2
- Authority
- JP
- Japan
- Prior art keywords
- blast furnace
- differential pressure
- blow
- measuring device
- stage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Blast Furnaces (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、高炉の風圧変動に伴う操業異常予知方法に関し、特に吹き抜け現象を予知して操業異常を予防しようとするものである。
【0002】
【従来の技術】
近年の高炉操業においては、使用するコークス量を減少させて低コスト化を図るために、粉炭比を135〜140kg/t程度まで増加させる操業が行われている。
しかしながら、高生産を行うと、融着帯下部が限界付近にまで低下し、粉炭の熱レベルの調整のために炉壁が煽られて風圧変動が発生してしまう。このような風圧変動が発生すると、いわゆる吹き抜け現象が生じて操業異常となり、安定した高炉操業を行うことができない。
【0003】
このような吹き抜け現象が発生する原因には、以下のものが考えられる。
第1に、原材料の装入トラブルや出銑のトラブル、あるいは原材料の装入において円周方向のバランスが乱れていることが、吹き抜け現象の原因となる。
第2に、コークス比(コークス/出銑量)を低くし、オアバイコークス(鉱石量とコークス量の比)を高くすることにより、コークスベッドの形成不良が発生し、これが吹き抜け現象の原因となる。
第3に、コークス粉化や焼結鉱還元粉化による粉の蓄積が、吹き抜け現象の原因となる。
第4に、高生産すなわち高ボッシュガス量により炉下部の通気不良が発生し、これが吹き抜け現象の原因となる。
【0004】
高炉の安定操業を行うためには、これらの吹き抜け現象の原因を特定して、予め除去する必要がある。また、吹き抜け現象の原因を特定するためには、吹き抜け部位を特定しなければならない。
従来より、この種の操業異常を予知するための方法として、例えば特公昭60−41123号公報、特公平3−126806号公報等に、その技術が開示されている。このような従来の操業異常の予知方法では、炉内に、温度、圧力、ガス組成等を検出するためのセンサを設置し、これらのセンサの測定値に基づいて設定基準値や理論値との比較を行い、操業異常を予知していた。
【0005】
【発明が解決しようとする課題】
しかしながら、上述した従来の操業異常の予知方法では、操業異常が発生しようとしているにもかかわらず、センサの測定値が異常を示さないこともあり、操業異常の発生を的確に予知することができなかった。
また、センサの測定値が異常を示した場合であっても、その解析には専門的知識を必要とし、誰もが操業異常の発生を読みとることができるものではなかった。
このため、センサを設置した場合であっても、操業異常の発生を予知するためには、結局、熟練した作業者の勘に頼らざるを得ず、安定した高炉操業の維持を難しいものとしていた。
本発明に係る高炉の風圧変動に伴う異常操業予知方法は、上述した事情に鑑み提案されたもので、高炉の風圧変動に伴う操業異常を容易かつ的確に予知することにより、安定した高炉操業を行うことを目的とする。
【0006】
【課題を解決するための手段】
本発明に係る高炉の風圧変動に伴う吹き抜け現象予知方法は、上述した目的を達成するためのもので、高炉側壁の高さ方向に、高炉内の圧力を測定するための圧力測定装置およびステーブ温度を測定するための温度測定装置を複数段設けて測定装置群とするとともに、該測定装置群を高炉の周方向に複数箇所設置し、前記複数段設けた測定装置群毎に各段の差圧およびステーブ温度を測定し、かつ前記各段の差圧の測定では、各段の絶対圧の差を各段間の距離で除すことにより基準化して各段の差圧を求め、該各段の差圧およびステーブ温度の時間経過に伴う変化を差圧およびステーブ温度毎に区別して表示し、該表示した各段の差圧およびステーブ温度の変化を監視することにより、吹き抜け現象を予知することを特徴とするものである。このよう吹き抜け現象予知方法を採用することにより、3次元表示された差圧およびステーブ温度の時間経過に伴う変化を監視するだけで、専門的知識を必要とせず、また熟練した技術者の勘に頼ることなく、安定した高炉操業を行うことができる。
【0009】
【発明の実施の形態】
以下、図面に基づいて、本発明に係る高炉の風圧変動に伴う異常操業予知方法の一実施形態を説明する。
図1は、本発明に係る異常操業予知方法に使用する測定装置等の配置を示す説明図であり、図1(a)は、高炉の縦断面を示す説明図、図1(b)は、高炉の横断面を示す説明図である。
【0010】
高炉1の側壁には、図1(a)に示すように、高炉1内の圧力を測定するための圧力測定装置2とステーブ温度を測定するための温度測定装置3とを、高さ方向に複数段設けて測定装置群4を構成している。また、この測定装置群4は、図1(b)に示すように、高炉1の周方向に複数箇所設置されている。
図1に示す例では、高炉1の高さ方向に10個の測定装置群4を設け、この測定装置群4を高炉1の周方向に等間隔で4カ所設置している。また、各測定装置群4は、測定した圧力情報および温度情報を収集して処理するための処理装置5に接続されている。
【0011】
この処理装置5は、例えばキーボードやマウス等の入力手段と、CRTディスプレイやプリンタ等の出力手段と、ハードディスク記憶装置等の記憶手段とを備えたコンピュータから構成される。
各測定装置群4で測定された圧力情報および温度情報は、処理装置5に送信されて演算処理され、3次元表示されたグラフとして出力される。
処理装置5における演算処理では、各段の絶対圧の差を各段間の距離で除すことにより基準化して差圧を求めている。
【0012】
なお、各測定装置群4における圧力測定装置2と温度測定装置3の配置個数および配置位置は、適宜変更して実施することができる。また、各測定装置群4において、圧力測定装置2のみ、あるいは温度測定装置3のみを設置した箇所が存在していてもかまわない。
さらに、高炉1の周方向に設置する測定装置群4の配置個数および配置位置も、適宜変更して実施することができる。
また、処理装置5は、必ずしも1つの機器により構成する必要はなく、情報を収集する機器と、収集した情報を処理して3次元グラフを出力する機器等のように、複数の機器により構成することもできる。
【0013】
処理装置5により出力された3次元グラフを、図2に基づいて説明する。
図2は、測定した情報の時間経過に伴う変化を3次元表示したグラフで、図2(a)は、差圧の3次元グラフ、図2(b)はステーブ温度の3次元グラフである。
図2(a)に示す例は、270度方向に設置された測定装置群4における差圧の測定結果を表したもので、横軸に時間、縦軸に差圧をとり、時間経過に伴う差圧の変化を示している。
【0014】
横軸に示す(i)〜(iii)は日にちを表し、1200,1400等の数字は時刻を表している。
縦軸に示すBP〜B3,S1〜S5,TPは、測定装置群4における圧力測定装置2の設置位置を表し、下方から上方に向かって、BP,B2,B3,S1,S3,S5,TPの順に設置されている。したがって、例えばS5−TPとは、TPとS5との差圧であり、S3−S5とは、S5とS3との差圧のことである。
また、差圧は、図2(a)中に示すように、0.00〜0.25kg/cm3の範囲で0.05kg/cm3毎に区別して表示されている。
【0015】
同様に、図2(b)に示す例は、270度方向に設置された測定装置群4におけるステーブ温度の測定結果を表したもので、横軸に時間、縦軸にステーブ温度をとり、時間経過に伴う差圧の変化を示している。
横軸に示す(i)〜(iii)は日にちを表し、1200,1400等の数字は時刻を表している。
縦軸に示すB1L〜B3U,S1〜S5は、測定装置群4における温度測定装置3の設置位置を表し、下方から上方に向かって、B1L,B1U,B2L,B2U,B3L,B3U,S1,S2,S3,S4,S5の順に設置されている。
また、ステーブ温度は、図2(b)中に示すように、0〜500℃の範囲で100℃毎に区別して表示されている。
なお、図2(a)(b)において、縦の破線の位置において、吹き抜け現象が発生している。
【0016】
図2(a)(b)の3次元グラフによれば、(ii)日目の17時30分頃に吹き抜け現象が発生しており、B2−B3間の差圧が極端に上昇している。
また、この吹き抜け現象が発生する以前に、(ii)日目の10時30分頃からB2−B3間の差圧が上昇しており、特に(ii)日目の13時30分頃と14時30分頃にB2−B3間の差圧が極端に上昇している。これに対応して、(ii)日目の11時頃からB2Uのステーブ温度が上昇しており、特に(ii)日目の13時頃にB2Uのステーブ温度が極端に上昇している。
また、同様の現象が(i)日目の6時頃にも発生している。
【0017】
上述したように、図2(a)(b)の3次元グラフに基づく分析結果を総合的に判断すると、B2レベルにおいて、例えば羽口直上で温度は高いが、鉱石の軟化により通気性の悪い層、すなわち融着帯が何らかの要因で降下停滞を起こして停滞層となり、この停滞層が時間の経過とともに部分的に崩壊したり、部分的に空洞を生じたりして、この部分を高速のガスが通過することにより吹き抜け現象を誘発したことが推測される。
ただし、図示しないが、270度方向以外では変化が見られないので、局所的な降下停滞と考えることができる。
【0018】
このような停滞層が生じる原因が、高炉1操業の限界を示唆していると考えられる。上述した例では、羽口近傍の熱レベルとガス分布、鉱石の還元、融け落ち能の整合性が取れないことが原因であると推測することができ、高炉全体の熱還元バランスは取れていても、部分的な非整合が生じると破綻を来す例と考えることができる。
また、図2(a)に示す例では、270度方向の各段毎に差圧が周期的に変動している。このような10時間以上の周期的な差圧変動は、原料の装入や操業変更の影響と推定することができる。
【0019】
上述したような3次元グラフの変化は、専門的な知識や、長年の経験を持たない者であっても容易に読みとることができる。したがって、このような3次元グラフの変化に基づいて異常操業を予知して、吹き抜け現象が発生する原因を除去することにより、安定した高炉操業を行うことができる。
なお、上述した図2に示す例において吹き抜け現象が発生しているが、これは、本発明に係る異常操業予知方法を説明するためであり、本発明に係る異常操業予知方法では、実際に吹き抜け現象が発生する以前に、その原因を除去することにより吹き抜け現象の発生を未然に防ぐことができる。
【0020】
【発明の効果】
本発明に係る高炉の風圧変動に伴う吹き抜け現象予知方法は、上記した構成を有するので、以下に示すような効果を奏することができる。すなわち、本発明に係る高炉の風圧変動に伴う吹き抜け現象予知方法では、高炉の高さ方向に複数段にわたって設けた圧力測定装置およびステーブ温度を測定するための温度測定装置により高炉内の各段の差圧およびステーブ温度を測定し、かつ前記各段の差圧の測定では、各段の絶対圧の差を各段間の距離で除すことにより基準化して各段の差圧を求め、該各段の差圧およびステーブ温度の時間経過に伴う変化を差圧およびステーブ温度毎に区別して表示し、該表示した各段の差圧およびステーブ温度の変化を監視している。したがって、各段の差圧およびステーブ温度の変化を該表示することにより、各段の差圧およびステーブ温度の変化を一目で認識することができるので、専門的知識を必要とせず、また熟練した技術者の勘に頼ることなく、安定した高炉操業を行うことができる。
【図面の簡単な説明】
【図1】本発明に係る異常操業予知方法に使用する測定装置等の配置を示す説明図であり、(a)は、高炉の縦断面を示す説明図、(b)は、高炉の横断面を示す説明図である。
【図2】測定した情報の時間経過に伴う変化を3次元表示したグラフで、(a)は、差圧の3次元グラフ、(b)はステーブ温度の3次元グラフである。
【符号の説明】
1 高炉
2 圧力測定装置
3 温度測定装置
4 測定装置群
5 処理装置[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for predicting an operation abnormality associated with fluctuations in wind pressure in a blast furnace, and particularly to predicting a blow-through phenomenon to prevent an operation abnormality.
[0002]
[Prior art]
In recent blast furnace operation, in order to reduce the amount of coke to be used and to reduce the cost, operation to increase the pulverized coal ratio to about 135 to 140 kg / t is performed.
However, when high production is performed, the lower part of the cohesive zone is lowered to near the limit, and the furnace wall is beaten to adjust the heat level of the pulverized coal, resulting in fluctuations in wind pressure. When such wind pressure fluctuations occur, a so-called blow-through phenomenon occurs, resulting in abnormal operation, and stable blast furnace operation cannot be performed.
[0003]
The following can be considered as causes of such a blow-through phenomenon.
First, troubles in charging the raw materials, troubles in coming out of the raw materials, or the disturbance of the balance in the circumferential direction during the charging of the raw materials cause the blow-through phenomenon.
Secondly, by reducing the coke ratio (coke / slag amount) and increasing the ore-by-coke (ratio of ore and coke amount), poor coke bed formation occurs, which is the cause of the blow-through phenomenon. Become.
Third, accumulation of powder due to coke pulverization or reduced sinter ore pulverization causes a blow-through phenomenon.
Fourth, high production, that is, high Bosch gas amount, causes poor ventilation in the lower part of the furnace, which causes a blow-through phenomenon.
[0004]
In order to perform stable operation of the blast furnace, it is necessary to identify the causes of these blow-through phenomena and remove them in advance. Further, in order to specify the cause of the blow-through phenomenon, the blow-through portion must be specified.
Conventionally, as a method for predicting this type of operation abnormality, for example, Japanese Patent Publication No. 60-41123 and Japanese Patent Publication No. 3-126806 have disclosed the technology. In such a conventional method of predicting operational abnormalities, sensors for detecting temperature, pressure, gas composition, etc. are installed in the furnace, and based on the measured values of these sensors, set reference values and theoretical values are detected. A comparison was made to predict operational abnormalities.
[0005]
[Problems to be solved by the invention]
However, in the above-described conventional operation abnormality prediction method, even though an operation abnormality is about to occur, the measured value of the sensor may not indicate an abnormality, so the occurrence of the operation abnormality can be accurately predicted. There wasn't.
Further, even when the measured value of the sensor indicates an abnormality, the analysis requires specialized knowledge, and no one can read out the occurrence of an operation abnormality.
For this reason, even if a sensor is installed, in order to predict the occurrence of abnormal operation, it is ultimately necessary to rely on the intuition of skilled workers, making it difficult to maintain stable blast furnace operation. .
The method for predicting abnormal operation associated with wind pressure fluctuations in a blast furnace according to the present invention has been proposed in view of the above-described circumstances, and stable and reliable operation of blast furnaces can be achieved by easily and accurately predicting operational abnormalities associated with wind pressure fluctuations in a blast furnace. The purpose is to do.
[0006]
[Means for Solving the Problems]
A method for predicting a blow-through phenomenon associated with a wind pressure fluctuation of a blast furnace according to the present invention is for achieving the above-described object, and a pressure measuring device and a stave temperature for measuring the pressure in the blast furnace in the height direction of the blast furnace side wall. A plurality of temperature measuring devices for measuring the temperature are provided as a measuring device group, and the measuring device group is installed in a plurality of locations in the circumferential direction of the blast furnace, and the differential pressure of each stage is provided for each measuring device group provided in the plurality of steps. In the measurement of the differential pressure of each stage, the difference in absolute pressure of each stage is divided by the distance between each stage to obtain the differential pressure of each stage. of the change with time of the differential pressure and stave temperature displayed by distinguishing each differential pressure and stave temperature, by monitoring the change in the differential pressure and stave temperature of each stage that the display, to predict the blow phenomena It is characterized by. By adopting such a blow-through phenomenon prediction method, it is only necessary to monitor the change of the three-dimensionally displayed differential pressure and stave temperature with the passage of time. Stable blast furnace operation can be performed without reliance.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, based on the drawings, an embodiment of a method for predicting abnormal operation associated with wind pressure fluctuations in a blast furnace according to the present invention will be described.
FIG. 1 is an explanatory view showing the arrangement of measuring devices and the like used in the abnormal operation prediction method according to the present invention, FIG. 1 (a) is an explanatory view showing a longitudinal section of a blast furnace, and FIG. It is explanatory drawing which shows the cross section of a blast furnace.
[0010]
On the side wall of the blast furnace 1, as shown in FIG. 1A, a
In the example shown in FIG. 1, ten
[0011]
The
The pressure information and temperature information measured by each
In the arithmetic processing in the
[0012]
In addition, the arrangement | positioning number and arrangement position of the
Furthermore, the number of arrangements and the arrangement positions of the
The
[0013]
The three-dimensional graph output by the
FIG. 2 is a graph that three-dimensionally displays changes in measured information over time, FIG. 2A is a three-dimensional graph of differential pressure, and FIG. 2B is a three-dimensional graph of stave temperature.
The example shown in FIG. 2A represents the measurement result of the differential pressure in the
[0014]
(I) to (iii) shown on the horizontal axis represent the date, and numbers such as 1200 and 1400 represent time.
BP to B3, S1 to S5, and TP shown on the vertical axis represent the installation position of the
Further, differential pressure, as shown in FIG. 2 (a), are presented separately for each 0.05 kg / cm 3 in the range of 0.00~0.25kg / cm 3.
[0015]
Similarly, the example shown in FIG. 2B represents the measurement result of the stave temperature in the
(I) to (iii) shown on the horizontal axis represent the date, and numbers such as 1200 and 1400 represent time.
B1L to B3U and S1 to S5 shown on the vertical axis represent the installation positions of the
Further, the stave temperature is displayed separately for each 100 ° C. in the range of 0 to 500 ° C. as shown in FIG.
In FIGS. 2A and 2B, a blow-through phenomenon occurs at the position of the vertical broken line.
[0016]
According to the three-dimensional graphs of FIGS. 2 (a) and 2 (b), a blow-through phenomenon has occurred around 17:30 on day (ii), and the differential pressure between B2 and B3 has increased extremely. .
In addition, before this blow-through phenomenon occurs, the differential pressure between B2 and B3 has increased from about 10:30 on the day (ii), and in particular, (13) about 13:30 on the day and 14 At about 30 minutes, the differential pressure between B2 and B3 increases extremely. Correspondingly, (2) the B2U stave temperature has risen from about 11 o'clock on the day (ii), and in particular, the B2U stave temperature has risen extremely at around 13:00 on the (ii) day.
A similar phenomenon occurs at about 6 o'clock on day (i).
[0017]
As described above, when the analysis results based on the three-dimensional graphs of FIGS. 2A and 2B are comprehensively judged, at the B2 level, for example, the temperature is high immediately above the tuyere, but the air permeability is poor due to the softening of the ore. The layer, that is, the cohesive zone, is caused to stagnate due to some reason and becomes a stagnation layer.This stagnation layer partially collapses over time or partially creates cavities. It is speculated that the blow-through phenomenon was induced by passing.
However, although not shown, since no change is seen except in the direction of 270 degrees, it can be considered as a local descent stagnation.
[0018]
It is thought that the cause of such a stagnant layer suggests the limit of one blast furnace operation. In the above example, it can be inferred that the heat level and gas distribution in the vicinity of the tuyere and the consistency of ore reduction and melting ability cannot be achieved, and the thermal reduction balance of the entire blast furnace is balanced. However, it can be considered as an example of failure when partial inconsistencies occur.
Further, in the example shown in FIG. 2A, the differential pressure periodically fluctuates for each stage in the 270 degree direction. Such a cyclic differential pressure fluctuation of 10 hours or more can be estimated as the influence of the charging of raw materials or operation change.
[0019]
The changes in the three-dimensional graph as described above can be easily read even by those who have no specialized knowledge or many years of experience. Therefore, it is possible to perform stable blast furnace operation by predicting abnormal operation based on such a change in the three-dimensional graph and removing the cause of the blow-through phenomenon.
Note that the blow-through phenomenon occurs in the example shown in FIG. 2 described above, but this is for explaining the abnormal operation prediction method according to the present invention. In the abnormal operation prediction method according to the present invention, the blow-through phenomenon is actually performed. By removing the cause before the phenomenon occurs, it is possible to prevent the occurrence of the blow-through phenomenon.
[0020]
【The invention's effect】
Since the method for predicting the blow-through phenomenon associated with the wind pressure fluctuation of the blast furnace according to the present invention has the above-described configuration, the following effects can be achieved. That is, in the method for predicting a blow-through phenomenon associated with wind pressure fluctuation of a blast furnace according to the present invention, a pressure measuring device provided in a plurality of stages in the height direction of the blast furnace and a temperature measuring device for measuring a stave temperature are used for each stage in the blast furnace. In the measurement of the differential pressure and the stave temperature , and the measurement of the differential pressure of each stage, the difference in absolute pressure of each stage is divided by the distance between each stage to obtain the differential pressure of each stage, the change with time of the differential pressure and stave temperature of each stage is presented separately for each differential pressure and stave temperature monitors the changes in differential pressure and stave temperature of each stage that the display. Therefore, by the display changes in differential pressure and stave temperature of each stage, it is possible to recognize the change in the differential pressure and stave temperature of each stage at a glance, without the need for specialized knowledge and skilled Stable blast furnace operation can be performed without relying on the intuition of engineers.
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is an explanatory view showing the arrangement of measuring devices used in an abnormal operation prediction method according to the present invention, (a) is an explanatory view showing a longitudinal section of a blast furnace, and (b) is a transverse section of the blast furnace. It is explanatory drawing which shows.
FIGS. 2A and 2B are graphs in which changes with time of measured information are three-dimensionally displayed. FIG. 2A is a three-dimensional graph of differential pressure, and FIG. 2B is a three-dimensional graph of stave temperature.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2000309953A JP3938658B2 (en) | 2000-10-10 | 2000-10-10 | A method for predicting blow-through phenomena associated with blast furnace wind pressure fluctuations. |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2000309953A JP3938658B2 (en) | 2000-10-10 | 2000-10-10 | A method for predicting blow-through phenomena associated with blast furnace wind pressure fluctuations. |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2002115006A JP2002115006A (en) | 2002-04-19 |
| JP3938658B2 true JP3938658B2 (en) | 2007-06-27 |
Family
ID=18789997
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2000309953A Expired - Lifetime JP3938658B2 (en) | 2000-10-10 | 2000-10-10 | A method for predicting blow-through phenomena associated with blast furnace wind pressure fluctuations. |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3938658B2 (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101267692B1 (en) | 2011-06-29 | 2013-05-27 | 현대제철 주식회사 | Method for controlling and prejudgement of blowing pressure in blast furnace |
| KR101321926B1 (en) * | 2011-12-07 | 2013-10-28 | 주식회사 포스코 | Method for calculating fluctuation of gas flow in furnace |
| JP6690081B2 (en) * | 2016-07-14 | 2020-04-28 | 株式会社神戸製鋼所 | Operation status evaluation system |
| JP7307341B2 (en) * | 2019-04-04 | 2023-07-12 | 日本製鉄株式会社 | Furnace gas pressure fluctuation detection method |
-
2000
- 2000-10-10 JP JP2000309953A patent/JP3938658B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2002115006A (en) | 2002-04-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US12332636B2 (en) | Production facilities monitoring method, production facilities monitoring device, and operation method for production facilities | |
| JP2018009224A (en) | Operation condition evaluation system | |
| JP6607821B2 (en) | Blast furnace sensor failure detection method and abnormal situation prediction method | |
| JP2017128805A (en) | Blast furnace operation method | |
| JP3938658B2 (en) | A method for predicting blow-through phenomena associated with blast furnace wind pressure fluctuations. | |
| EP4282988B1 (en) | Blast furnace abnormality determination device, method and data carrier associated | |
| CN114730180B (en) | Operating methods and operating systems of production equipment | |
| CN118829733A (en) | Method for predicting molten iron temperature of blast furnace, learning method for molten iron temperature prediction model of blast furnace, method for operating blast furnace, device for predicting molten iron temperature of blast furnace, molten iron temperature prediction system and terminal device | |
| KR101412403B1 (en) | Dropping judgment method of charging material into blast furnace | |
| JP6686947B2 (en) | Blast furnace state determination device and blast furnace operating method | |
| KR20140002212A (en) | Judgment method of gas distribution of blast furnace | |
| JP4336262B2 (en) | In-furnace pressure fluctuation prediction method and apparatus | |
| JP4738309B2 (en) | Plant operation data monitoring device | |
| RU2801735C1 (en) | Control method and control system for production plants | |
| BR112022007991B1 (en) | METHOD OF OPERATION AND OPERATING SYSTEM FOR STEEL MILLS | |
| JP3487203B2 (en) | Blast furnace condition prediction method | |
| KR100711781B1 (en) | Gas pressure measuring device for coke oven | |
| EP4640851A1 (en) | Method for measuring level of molten material in furnace of blast furnace, device for measuring level of molten material in furnace of blast furnace, and method for operating blast furnace | |
| BR112022006940B1 (en) | PRODUCTION FACILITY MONITORING METHOD, PRODUCTION FACILITY MONITORING DEVICE, AND METHOD OF OPERATION FOR PRODUCTION FACILITIES | |
| RU2800300C1 (en) | Method of control of production facilities, device of control of production facilities and method of operation of production facilities | |
| JPH04365807A (en) | Method for predicting lowering of furnace heat accompanying wall falling in high temperature furnace | |
| KR20100078809A (en) | System for estimating the level of melt | |
| JPS59221583A (en) | Method of monitoring internal state of vertical type furnace | |
| JP2017165999A (en) | Blast furnace operation method | |
| KR101185330B1 (en) | Method of detecting distribution of gas stream in blast furnace |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040901 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20051018 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20051026 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051226 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070320 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070323 |
|
| R151 | Written notification of patent or utility model registration |
Ref document number: 3938658 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R151 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110406 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120406 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130406 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130406 Year of fee payment: 6 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130406 Year of fee payment: 6 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130406 Year of fee payment: 6 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140406 Year of fee payment: 7 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |