JP3938702B2 - Rotating buried pile driving device - Google Patents
Rotating buried pile driving device Download PDFInfo
- Publication number
- JP3938702B2 JP3938702B2 JP2002090087A JP2002090087A JP3938702B2 JP 3938702 B2 JP3938702 B2 JP 3938702B2 JP 2002090087 A JP2002090087 A JP 2002090087A JP 2002090087 A JP2002090087 A JP 2002090087A JP 3938702 B2 JP3938702 B2 JP 3938702B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- rotary
- unit
- driving device
- guide column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000007373 indentation Methods 0.000 claims description 11
- 238000005259 measurement Methods 0.000 claims description 10
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- 238000012790 confirmation Methods 0.000 claims description 5
- 238000000034 method Methods 0.000 description 12
- 238000010276 construction Methods 0.000 description 4
- 230000003028 elevating effect Effects 0.000 description 4
- 239000002689 soil Substances 0.000 description 3
- 230000008602 contraction Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000000691 measurement method Methods 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は支持層確認装置を設けた回転埋設杭の杭打ち装置に関するものである。
【0002】
【従来の技術】
一般に、住宅やビルなどの建物を建設する場合、地盤の弱い所では、コンクリート基礎の下に、基礎形状に沿って所定の間隔で杭を打ち込むことが行なわれている。この杭は、地盤の強度に応じて、支持層に達するまで地中に埋設する必要があり、その杭の長さも建設現場の地盤強度により異なっている。
【0003】
このため建設の前に予め現場の地質調査を行なっている。この調査方法としては種々の方法があるが、最も一般的に行なわれている方法はスエーデンサウンディング方式の地質調査が行なわれている。この方法は、先端に三角錐状のスクリューポイントを取付けたロッドを、例えば100Kgの一定の荷重を加えながら回転させてロッドを地中に押し込み、例えば25cm毎の単位沈下量に達するまでのロッドの回転数から深さ方向の地盤強度を測定している。
【0004】
例えば地表から25cm押し込むまでにロッドの回転数が30回、25cmから50cmまで押し込むのにロッドの回転数が25回、50cmから75cmまで押し込むのにロッドの回転数が24回というように順次測定していき、回転数が多いほど地盤強度が高いことになる。このようにして支持層として狙うN値に達する深さまで測定している。このN値は標準貫入試験において、ハンマーを落下させて所定の深さまで杭を貫入するのに必要な打撃数により地盤強度を示すもので、スエーデンサウンディング方式で測定した回転数を換算して求めることができる。
【0005】
この地質調査の結果から、埋設する杭の管径や長さを決定し、これを杭打ち装置で回転させながら押し込んで建設現場に埋設している。しかしながら、スエーデンサウンディング方式による調査ポイントは数カ所であり、これに対して杭は基礎形状に沿って例えば180cmの間隔で多数埋設するため、調査していない場所にも杭を打ち込むことになり、また杭頭が地面から露出するように単に押し込むだけで、支持層まで杭の先端が達しているかどうか確認することができなかった。また地質調査の結果に基づいて決定された長さの杭が、1本ずつ正確に打ち込まれているかどうかは、建物を建築した後には確認できない問題があった。
【0006】
【発明が解決しようとする課題】
本発明は上記問題を改善し、スエーデンサウンディング方式による測定装置と同様の機構を杭打ち装置に組込んで、杭打ちしながら地盤の強度を測定して地質調査結果の通りに支持層まで1本ずつ杭打ちされているか確認することができる回転埋設杭の杭打ち装置を提供するものである。
【0007】
【課題を解決するための手段】
本発明の請求項1記載の回転埋設杭の杭打ち装置は、回転埋設杭の上端を保持して回転させる杭回転駆動部を、垂直に支持したガイド支柱に沿って上下動自在に取付けると共に、杭回転駆動部をガイド支柱に沿って移動させる昇降機構を設け、杭を回転させながら地中に押し込む回転埋設杭の杭打ち装置において、前記回転埋設杭を一定の圧力で押し込む押し込み圧制御部と、杭の回転数を測定する回転数測定部と、杭の沈下量を測定する沈下量測定部と、単位沈下量に対する回転数から地盤強度を演算する地盤強度演算部とからなる支持層確認装置を設けたことを特徴とするものである。
【0008】
本発明の請求項2記載の回転埋設杭の杭打ち装置は、杭回転駆動部をガイド支柱に沿って移動させる駆動部が、ガイド支柱に沿って掛け回したチェ−ンと、これを回転させる油圧モータとで構成され、押し込み圧制御部は、前記油圧モータを駆動させる油圧ポンプの圧力を測定して押し込み圧を制御することを特徴とするものである。
【0009】
更に請求項3記載の回転埋設杭の杭打ち装置は、回転埋設杭が、鋼管の下端をプレス成形して複数枚のブレードが放射状に突設されていることを特徴とするものである。
【0010】
【発明の実施の形態】
以下本発明の実施の一形態を図1を参照して詳細に説明する。図において1は回転埋設杭の杭打ち装置を示すもので、クローラ2で走行する車体3に支持部4が取付けられ、この先端にヒンジを介してガイド支柱6が回動自在に支持され、油圧シリンダー7によりガイド支柱6の角度を調整するようになっている。
【0011】
ガイド支柱6の下部には、油圧モータ8が取付けられ、この出力軸に下部スプロケット9Aが接続されている。またガイド支柱6の上部には上部スプロケット9Bが取付けられ、前記下部スプロケット9Aとの間にチェーン10が掛け回されている。またガイド支柱6の側面にはガイドレール12が取付けられ、ここに、前記チェーン10に接続されたブラケット13が上下動自在に取付けられて昇降機構5が形成されている。
【0012】
このブラケット13には杭回転駆動部14が取付けられている。杭回転駆動部14は、油圧モータ15と、この下部に設けられたキャッチャー16とで構成され、このキャッチャー16で回転埋設杭17の上部を支持して回転させるようになっている。また18はガイド支柱6の下部に取付けられ、回転埋設杭17を回転自在に支持する支持リングである。
【0013】
また支持層確認装置19は図2に示すように、昇降機構5の油圧ポンプ11に接続された押し込み圧制御部20と、昇降機構5の油圧モータ8に接続された沈下量測定部21、杭回転駆動部14のキャッチャー16に接続された回転数測定部22、これと前記沈下量測定部21に接続された地盤強度演算部23および、これに接続されたプリンターなどの表示部24とから構成されている。
【0014】
前記押し込み圧制御部20は、油圧ポンプ11の油吐出回路に設けた圧力センサーで油圧を検出し、回転埋設杭17の直径から定められた一定の押し込み圧になるように油圧ポンプ11の油圧を制御するようになっている。また沈下量測定部21は、チェーン10を回転駆動させる油圧モータ8の出力軸や下部スプロケット9Aに取付けられた静電容量センサーなどの非接触型のセンサーや、リミットスイッチなどの接触型のセンサーで、回転量を検出することにより、チェーン10の移動量、即ち回転埋設杭17の沈下量を測定するものである。
【0015】
また前記回転数測定部22は、杭回転駆動部14のキャッチャー16に取付けられた静電容量センサーなどの非接触型のセンサーや、リミットスイッチなどの接触型のセンサーで、回転埋設杭17の上部に取付けたキャッチャー16の回転数を検出することにより、回転埋設杭17の回転数を測定するものである。
【0016】
また地盤強度演算部23は、回転数測定部22で測定した回転埋設杭17の回転数nと、沈下量測定部21で検出した回転埋設杭17の沈下量から、例えばスエーデンサウンディング方式による測定方法と同じ25cm毎の単位沈下量Lに対する回転数nを測定して、地盤の強度を演算するものである。この演算した地盤強度はプリンターなどの表示部24に出力されてプリントアウトされるようになっている。なおこの場合、N値に換算したデータをプリントアウトするようにしても良い。
【0017】
また埋設する回転埋設杭17としては、例えば図1に示すように円筒状の鋼管の先端側に、外周の3方向から中心に向かって斜めに陥没した谷部を形成し、これら隣接する谷部の間に、先端側が閉塞し、後方側が順次、周方向に膨出した3枚のブレード25が放射状に形成されたものを使用する。
【0018】
次に上記構成の回転埋設杭の杭打ち装置で杭打ちする方法について説明する。建物を建設する現場の地質をスエーデンサウンディング方式により予め地質調査しておく。このスエーデンサウンディング方式による地質調査方法は、先端に三角錐状のスクリューポイントを取付けたロッドを、例えば100Kgの一定の荷重を加えながら回転させてロッドを地中に押し込み、25cm毎の単位沈下量に達するまでのロッド回転数から深さ方向の地盤強度を測定する。
【0019】
この地質調査の結果と、建物の重量、および支持層として狙うN値に達するまでの深さから、埋設する回転埋設杭17の管径と長さを決定し、これを工場で加工して現場に搬入する。なお回転埋設杭17が長い場合には現場で鋼管を継ぎ足しても良い。現場では、底面断面積Dの回転埋設杭17に加える荷重、つまり押し込み圧Pを、スエーデンサウンディング方式により荷重100Kgに対するスクリューポイントの断面積d当りの荷重、100Kg/d=P/Dと等しくなるように設定する。
【0020】
このように押し込み圧Pを、押し込み圧制御部20で一定に設定して、回転埋設杭17をキャッチャー16と支持リング18で保持してガイド支柱6に沿って支持する。この後回転埋設杭17の先端を地面の埋設点に合わせて、図2に示す昇降機構5の油圧ポンプ11と杭回転駆動部14の油圧ポンプ12を運転する。
【0021】
昇降機構5の油圧ポンプ11を運転すると、油圧により油圧モータ8が回転し、これに接続した下部スプロケット9Aが回転し、これと上部スプロケット9Bとの間に掛け回されたチェーン10がガイド支柱6の内側を回転する。このチェーン10には杭回転駆動部14のブラケット13が接続され、ここに支持した油圧モータ15とキャッチャー16が下降する。
【0022】
この時のキャッチャー16により回転埋設杭17に加わる荷重、即ち押し込み圧Pは、押し込み圧制御部20により油圧ポンプ11の吐出圧を制御することにより、一定にすることができる。また杭回転駆動部14の油圧ポンプ12により回転する油圧モータ15と一体にキャッチャー16が回転するので、これに支持された回転埋設杭17は、一定の押し込み圧Pで回転しながら地中に打ち込まれていく。
【0023】
回転埋設杭17の先端には、3枚のブレード25…が等間隔に突設されているので、ブレード25が回転して土を掻き取り、孔の内壁面に掻き取った土を押し付けて周囲地盤を締め固めながら埋設されていく。このように建物の基礎形状に沿って所定の間隔で回転埋設杭17を打ち込んでいく。
【0024】
この打ち込み過程で、チェーン10を回転駆動させる油圧モータ8の出力軸や下部スプロケット9Aに取付けられた静電容量センサーなどの非接触型のセンサーや、リミットスイッチなどの接触型のセンサーで、出力軸の回転量を検出して、これから沈下量測定部21で回転埋設杭17の沈下量を測定する。
【0025】
また同時に杭回転駆動部14のキャッチャー16に取付けられた静電容量センサーなどの非接触型のセンサーや、リミットスイッチなどの接触型のセンサーで、キャッチャー16の回転数を検出することにより、回転埋設杭17の回転数nを回転数測定部22で測定する。
【0026】
この回転数測定部22で測定した回転埋設杭17の回転数nと、沈下量測定部21で検出した回転埋設杭17の沈下量を地盤強度演算部23で、25cm毎の単位沈下量Lに対する回転数nを測定して、地盤の強度を演算し、この演算した地盤強度を表示部24のプリンターでプリントアウトする。
【0027】
このプリントアウトされた結果と、予め行なったスエーデンサウンディング方式による地質調査の結果を対比することにより、回転埋設杭17が支持層に達しているか1本毎に確認することができると共に、打ち込みデーターとして管理することができ、後日、補償問題が生じた時の施工記録となる。
【0028】
なお上記実施例では、昇降機構5として油圧モータ8とチェーン10を組み合わせた構造の場合について示したが、ラックとピニオンを組合せた構造、またはガイド支柱6に油圧シリンダーを取付けて杭回転駆動部14を昇降させる構造のものでも良い。この場合、沈下量測定部21は油圧シリンダーのロッドの伸縮量を測定すれば良い。また回転数を測定するセンサーを、回転駆動部14のキャッチャー16に取付けた場合について示したが、油圧モータ15の出力軸や、回転埋設杭17に取付けた構造でも良い。また上記実施例では、回転埋設杭17として鋼管の下端をプレス成形して3枚のブレードを放射状に突設したものについて示したが、2枚突設したものでも良く、また杭頭にらせん状のブレードを取付けたものなど回転埋設形の杭であれば、全てに適用することができる。
【0029】
【発明の効果】
以上説明した如く本発明に係る請求項1記載の回転埋設杭の杭打ち装置によれば、スエーデンサウンディング方式による測定装置と同様の機構を杭打ち装置に組込んで、一定の圧力で回転数を測定し、地盤の強度を測定しながら杭打ちするので、地質調査結果の通りに支持層まで1本ずつ杭打ちされているか確認することができると共に、打ち込みデーターを施工記録として管理することができる。
【0030】
また請求項2記載の回転埋設杭の杭打ち装置によれば、杭回転駆動部をガイド支柱に沿って移動させる駆動部が、ガイド支柱に沿って掛け回したチェ−ンと、これを回転させる油圧モータで構成され、押し込み圧制御部は、前記油圧モータを駆動させる油圧ポンプの圧力を測定して押し込み圧を制御するようにしたので、長い回転埋設杭を打ち込むことができると共に、押し込み圧を一定に制御することができる。
【0031】
また請求項3記載の回転埋設杭の杭打ち装置によれば、回転埋設杭が、鋼管の下端をプレス成形して複数枚のブレードが放射状に突設されているので、加工が容易で安価に製造できると共に、埋設速度が速く、残土の排出もほとんどなく、しかも摩擦支持力を大幅に向上させることができる。
【図面の簡単な説明】
【図1】本発明の実施の一形態による回転埋設杭の杭打ち装置を示す側面図である。
【図2】図1の杭打ち装置に設けた支持層確認装置の構成を示すブロック図である。
【符号の説明】
1 回転埋設杭の杭打ち装置
3 車体
4 支持部
5 昇降機構
6 ガイド支柱
7 油圧シリンダー
8 油圧モータ
9A 下部スプロケット
10 チェーン
11 油圧ポンプ
12 油圧ポンプ
13 ブラケット
14 杭回転駆動部
15 油圧モータ
16 キャッチャー
17 回転埋設杭
18 支持リング
19 支持層確認装置
20 押し込み圧制御部
21 沈下量測定部
22 回転数測定部
23 地盤強度演算部
24 表示部[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a pile driving device for a rotary buried pile provided with a support layer confirmation device.
[0002]
[Prior art]
In general, when a building such as a house or a building is constructed, a pile is driven at a predetermined interval along a foundation shape under a concrete foundation in a place where the ground is weak. Depending on the strength of the ground, this pile must be buried in the ground until it reaches the support layer, and the length of the pile also depends on the ground strength at the construction site.
[0003]
For this reason, a geological survey is conducted in advance before construction. There are various survey methods, but the most common method is the Swedish sounding type geological survey. In this method, a rod with a triangular pyramid-shaped screw point attached to the tip is rotated while applying a constant load of, for example, 100 kg, and the rod is pushed into the ground. The ground strength in the depth direction is measured from the rotational speed.
[0004]
For example, the rod rotation speed is measured 30 times before being pushed 25 cm from the ground surface, the rod rotation speed is 25 times to push from 25 cm to 50 cm, and the rod rotation speed is 24 times to push from 50 cm to 75 cm. As the number of rotations increases, the ground strength increases. In this way, measurement is performed up to the depth reaching the N value aimed at as the support layer. This N value indicates the ground strength based on the number of hits required to penetrate the pile to the specified depth by dropping the hammer in the standard penetration test, and is obtained by converting the rotation speed measured by the Swedish sounding method. Can do.
[0005]
From the results of this geological survey, the pipe diameter and length of the pile to be buried are determined, and the pile is pushed in while being rotated by a pile driving device and buried at the construction site. However, there are several survey points by the Swedish sounding method. On the other hand, piles are buried along the foundation shape at intervals of 180 cm, for example, so that piles are driven into unexamined places. It was not possible to confirm whether the tip of the pile had reached the support layer by simply pushing it so that the head was exposed from the ground. In addition, there was a problem that it was not possible to confirm whether the piles of the length determined based on the results of the geological survey were driven accurately one by one after building the building.
[0006]
[Problems to be solved by the invention]
The present invention improves the above-mentioned problem, incorporates a mechanism similar to the Swedish sounding-type measuring device into the pile driving device, measures the strength of the ground while driving the pile, and supports one piece as far as the geological survey results. The present invention provides a pile driving device for rotating buried piles that can be confirmed whether piled one by one.
[0007]
[Means for Solving the Problems]
The pile driving device of the rotary buried pile according to
[0008]
In the pile driving device for rotary buried piles according to
[0009]
Furthermore, the pile driving device for the rotary buried pile according to
[0010]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of the present invention will be described in detail with reference to FIG. In the figure,
[0011]
A
[0012]
A pile
[0013]
As shown in FIG. 2, the support
[0014]
The indentation
[0015]
The rotational
[0016]
In addition, the ground
[0017]
In addition, as the rotating buried
[0018]
Next, a method of pile driving with the pile driving device of the rotary buried pile having the above configuration will be described. The geology of the site where the building will be constructed is surveyed in advance using the Swedish sounding method. In this Swedish sounding method, the rod with a triangular pyramid screw point attached to the tip is rotated while applying a constant load of 100 kg, for example, and the rod is pushed into the ground to obtain a unit settlement of 25 cm. Measure the ground strength in the depth direction from the number of rod rotations to reach.
[0019]
Based on the results of this geological survey, the weight of the building, and the depth to reach the target N value as the support layer, the pipe diameter and length of the rotary buried
[0020]
In this way, the indentation pressure P is set to be constant by the indentation
[0021]
When the hydraulic pump 11 of the elevating
[0022]
At this time, the load applied to the rotary buried
[0023]
Since the three
[0024]
In this driving process, the output shaft of the
[0025]
At the same time, by detecting the number of rotations of the
[0026]
The rotation number n of the rotary buried
[0027]
By comparing the result of this printout with the result of the geological survey conducted in advance by the Swedish sounding method, it is possible to check whether the rotary buried
[0028]
In the above embodiment, the
[0029]
【The invention's effect】
As described above, according to the pile driving device of the rotary buried pile according to the first aspect of the present invention, a mechanism similar to the measuring device by the Swedish sounding method is incorporated in the pile driving device, and the rotation speed is adjusted with a constant pressure. Since the piles are measured while measuring the strength of the ground, it is possible to check whether the piles are piled up one by one up to the support layer according to the geological survey results, and the driving data can be managed as construction records. .
[0030]
Moreover, according to the pile driving device of the rotary buried pile according to
[0031]
Further, according to the piled driving device of the rotary buried pile according to
[Brief description of the drawings]
FIG. 1 is a side view showing a pile driving device for a rotary buried pile according to an embodiment of the present invention.
FIG. 2 is a block diagram showing a configuration of a support layer confirmation device provided in the pile driving device of FIG. 1;
[Explanation of symbols]
DESCRIPTION OF
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002090087A JP3938702B2 (en) | 2002-03-28 | 2002-03-28 | Rotating buried pile driving device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002090087A JP3938702B2 (en) | 2002-03-28 | 2002-03-28 | Rotating buried pile driving device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2003286722A JP2003286722A (en) | 2003-10-10 |
| JP3938702B2 true JP3938702B2 (en) | 2007-06-27 |
Family
ID=29235468
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2002090087A Expired - Fee Related JP3938702B2 (en) | 2002-03-28 | 2002-03-28 | Rotating buried pile driving device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3938702B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2011174313A (en) * | 2010-02-25 | 2011-09-08 | Shinei Kk | Bearing capacity measuring device of hydraulic press-in machine |
| CN113863311A (en) * | 2021-09-24 | 2021-12-31 | 上海城建职业学院 | Construction method for rapid hole forming of anti-slide pile rotary drilling rig and self-soil-taking edger |
-
2002
- 2002-03-28 JP JP2002090087A patent/JP3938702B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2003286722A (en) | 2003-10-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN214583012U (en) | Building engineering stake hole detection device | |
| CN112647966B (en) | Full-automatic detection device for long-distance pipe jacking construction quality control | |
| KR102511014B1 (en) | Apparatus and method for settlement of ground | |
| US8380461B2 (en) | Construction modulus testing apparatus and method | |
| CN113529824B (en) | Device and method for detecting thickness of sediment at bottom of drilled pile | |
| JP3938702B2 (en) | Rotating buried pile driving device | |
| JP7112888B2 (en) | Confirmation method of supporting ground at the time of foundation pile construction and auger for it | |
| CN215169958U (en) | Geological survey device is used in mine | |
| CN221480901U (en) | Foundation pit deviation detection device | |
| KR100768686B1 (en) | A picking apparatus of a soil sample | |
| CN114991130B (en) | Pulling-resistant carrier pile and construction method thereof | |
| CN104655100B (en) | Metal mark head installer for stratum settlement monitoring | |
| JP7237218B2 (en) | Confirmation method of supporting ground during foundation pile construction | |
| Wardle et al. | 14. Effect of time and maintained load on the ultimate capacity of piles in stiff clay | |
| EP4189171B1 (en) | Testing system | |
| CN216558628U (en) | Automatic monitoring devices of deep level displacement | |
| CN115710899B (en) | A kind of hard rock pile foundation construction technology | |
| KR200419428Y1 (en) | Soil Sampler | |
| JP2003213687A (en) | Drilling torque reduction press-fitting method for rotary press-fit steel pipe piles | |
| CN116837915B (en) | Device and method for detecting pile bottom sediment and pile end foundation of cast-in-place pile | |
| JP3525185B2 (en) | Earth strength measurement device | |
| CN217932753U (en) | Dynamic compaction machine tamping depth and frequency synchronous detection device | |
| CN223061661U (en) | A cement mixing pile monitoring device | |
| EP4189170B1 (en) | Testing system | |
| JP2004324311A (en) | Checking method for bearing capacity of pile |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050223 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20061221 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070313 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070323 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100406 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120406 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120406 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130406 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130406 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140406 Year of fee payment: 7 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |