Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP3971879B2 - Multiple valves - Google Patents
[go: Go Back, main page]

JP3971879B2 - Multiple valves - Google Patents

Multiple valves Download PDF

Info

Publication number
JP3971879B2
JP3971879B2 JP33794699A JP33794699A JP3971879B2 JP 3971879 B2 JP3971879 B2 JP 3971879B2 JP 33794699 A JP33794699 A JP 33794699A JP 33794699 A JP33794699 A JP 33794699A JP 3971879 B2 JP3971879 B2 JP 3971879B2
Authority
JP
Japan
Prior art keywords
passage
switching valve
center bypass
sub
valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP33794699A
Other languages
Japanese (ja)
Other versions
JP2001153102A (en
Inventor
雅夫 柏木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KYB Corp
Original Assignee
KYB Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KYB Corp filed Critical KYB Corp
Priority to JP33794699A priority Critical patent/JP3971879B2/en
Publication of JP2001153102A publication Critical patent/JP2001153102A/en
Application granted granted Critical
Publication of JP3971879B2 publication Critical patent/JP3971879B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Fluid-Pressure Circuits (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は、建設車両等に用いるのに最適な多連弁に関する。
【0002】
【従来の技術】
この種の多連弁として、特開平11−257302号公報に記載されたものが従来から知られている。そして、この従来の多連弁の回路を示したのが、図3である。
図3からも明らかなように、この多連弁は、メインセクションブロック1とカバー2との間に、サブセクションブロック3を介在させている。
上記メインセクションブロック1には、複数のメイン切換弁4を組み込むとともに、これらメイン切換弁4のセンタバイパス通路5を直列に接続している。
【0003】
また、サブセクションブロック3には、サブ切換弁6を組み込むとともに、このサブ切換弁6のセンタバイパス通路7を、メイン切換弁4のセンタバイパス通路5の延長上に直接連通させている。
そして、サブ切換弁6のセンタバイパス通路7は、カバー2に形成した第1戻り通路8→サブセクションブロック3に形成した第2戻り通路9→メインセクションバルブ1に形成した第3戻り通路10を経由してタンクTに連通させている。
【0004】
上記第3戻り通路10には、ポンプPの吐出量を減少させるためのパイロット圧を発生させるパイロット圧発生手段11を設けている。したがって、各切換弁4および6の総てが中立位置にあれば、ポンプPの吐出油が、第1〜第3戻り通路8〜10を経由してタンクTに戻されるが、その過程で、上記吐出油はパイロット圧発生手段11を経由するので、そこでパイロット圧が発生する。
このパイロット圧の作用で、レギュレータ12が動作して、ポンプPの吐出量を減少させる。つまり、各切換弁を中立位置に保って、アクチュエータに仕事をさせていない状況では、ポンプPの吐出量を最小に保つようにしている。
【0005】
なお、建設車両において通常必要とされるアクチュエータ以外に、特別なアクチュエータをオプションで接続することがある。このようなときに、オプションのアクチュエータを簡単に接続できるようにするために、サブセクションブロック3を必要とする。つまり、上記のようにサブセクションブロック3を設けたのは、あくまでもオプション用のアクチュエータを接続するためである。
【0006】
【発明が解決しようとする課題】
上記のようにした従来の多連弁では、サブ切換弁6のセンタバイパス通路7を、メイン切換弁4のセンタバイパス通路5の延長上に直接連通させているので、センタバイパス通路5と7とを接続する通路13が、メインセクションブロック1の真ん中を通ってしまう。そのために、メインセクションブロック1の通路13の周囲では、その有効スペースがどうしても少なくなる。
【0007】
上記のように有効スペースが少ないので、この部分に、他の機器を組み込んだりできなくなる。そのために、パイロット圧発生手段11も、図3に示すように、第3戻り通路10側に設けなければならない。
このようにパイロット圧発生手段11を第3戻り通路10側に設けると、その分、メインセクションブロック1の幅が大きくならざるを得ない。言い換えると、この従来の多連弁によれば、全体が大型化するという問題があった。
【0008】
また、この従来の多連弁では、各切換弁4,6の中立時の戻り油を、第1戻り通路8→第2戻り通路9→第3戻り通路10を経由してタンクに戻す経路を取りながら、最下流の第3戻り通路10にパイロット圧発生手段11を設けている。そのために、サブセクションブロック3のサブ切換弁6からパイロット圧発生手段11までの距離が長くなってしまう。このようにパイロット圧発生手段11までの距離が長くなってしまうと、その分、圧力損失が大きくなる。圧力損失が大きくなればなるほど、パイロット圧発生手段11で発生するパイロット圧が、油温の変化に影響を受けやすくなる。そのために、ポンプ吐出量の制御も不安定になるという問題があった。
【0009】
この発明の第1の目的は、メインセクションブロックの下流側の有効スペースを大きくとれるようにすることである。
第2の目的は、上記有効スペースに種々の制御機器を組み込めるようにすることである。
第3の目的は、上記有効スペースにポンプ吐出量を制御するためのパイロット圧発生手段を組み込んで、安定したパイロット圧を検出できるようにすることである。
第4の目的は、パイロット圧発生手段の上流側に、中立カット弁を組み込み、この多連弁に接続したポンプの吐出油を、他の回路系統に合流させることができるようにすることである。
【0010】
【課題を解決するための手段】
この発明は、次の、多連弁を前提にするものである。すなわち、メインセクションブロックとカバーとの間に、サブセクションブロックを介在させる。そして、上記メインセクションブロックには、センタバイパス通路を直列に接続してなる複数のメイン切換弁を組み込む。上記サブセクションブロックには1または複数のサブ切換弁を組み込むとともに、このサブ切換弁のセンタバイパス通路を、連通路を介してメイン切換弁のセンタバイパス通路に接続する。しかも、このサブ切換弁のセンタバイパス通路を、メインセクションブロックに形成した戻り通路を経由してタンクに戻す構造にしたものである。
【0011】
上記多連弁を前提にしつつ、第1の発明は、最下流に位置するメイン切換弁のセンタバイパス通路の下流側に第1連通路を形成し、この第1連通路をサブセクションブロックに形成した第2連通路およびカバーに形成した第3連通路を介して、サブ切換弁のセンターバイパス通路に接続し、このサブ切換弁のセンタバイパス通路を、メインセクションブロックに形成した第1戻り通路および第2戻り通路を介してタンクに連通させてなり、しかも、上記第1連通路は、メイン切換弁およびサブ切換弁のセンタバイパス通路に対してオフセットさせた点に特徴を有する。
【0012】
第2の発明は、サブ切換弁のセンタバイパス通路の延長上に、第1戻り通路の開口部を形成するとともに、第2戻り通路はメインセクションブロックの各切換弁の側方を経由してタンクに導いた点に特徴を有する。
第3の発明は、第1戻り通路に、ポンプ吐出量を制御するためのパイロット圧発生手段を設けた点に特徴を有する。
第4の発明は、第1戻り通路であって、パイロット圧発生手段の上流側に中立カット弁を設けた点に特徴を有する。
【0013】
【発明の実施の形態】
図1に示した第1の実施態様は、メインセクションブロック21およびカバー22の間に2つのサブセクションブロック23を介在させている。そして、メインセクションブロック21には、複数のメイン切換弁24を組み込むとともに、これらメイン切換弁24のセンタバイパス通路25を直列に接続している。
なお、この実施態様では、サブセクションブロック23を2つ設けている。このサブセクションブロックは、図示のように一つのサブセクションブロックに一つのサブ切換弁を設けてもよいし、一つのサブセクションブロックに複数のサブ切換弁を組み込むようにしてもよい。
また、サブセクションブロック23に、サブ切換弁26を組み込んでいる点も、従来と同様である。ただし、この実施態様では、そのセンタバイパス通路27の流れの方向を従来と相違させている。この点については、この後で、詳しく説明する。
【0014】
上記メインセクションブロック21に組み込んだメイン切換弁24であって、その最下流に位置するメイン切換弁のセンタバイパス通路25は、第1連通路28に接続している。
この第1連通路28は、メインセクションブロック21内に形成するとともに、この第1連通路28を、上記センタバイパス通路25に対してオフセットさせている。つまり、図面上では、この第1連通路28を、センタバイパス通路25よりも、右側に寄せて形成している。このように第1連通路28を、メインセクションブロック21の右側に寄せて形成したので、メインセクションブロック21の下流側に有効スペースSが確保されることになる。
【0015】
また、上記第1連通路28は、サブセクションブロック23に形成した第2連通路29を経由して、いったん、カバー22に形成した第3連通路30に連通させている。そして、このカバー22に形成した第3連通路30から、再びサブセクションブロック23側に戻すようにして、第3連通路30をサブ切換弁26のセンタバイパス通路27に接続している。
【0016】
サブセクションブロック23の最下流に位置するサブ切換弁26のセンタバイパス通路27は、メインセクションブロック21に形成した第1戻り通路31および第2戻り通路32を経由してタンクTに連通している。
上記第1戻り通路31の開口部31aは、サブ切換弁26のセンタバイパス通路27の延長上に形成している。そして、この開口部31aから少し下流側に伸びてから、図面左方向に直角に曲がって、メイン切換弁24の側方を経由してなる第2戻り通路32に連通している。
【0017】
上記のようにした第1戻り通路31には、ポンプ吐出量を制御するためのパイロット圧発生手段33を設けている。このように第1戻り通路31にパイロット圧発生手段33を設けたのは、次の理由からである。すなわち、最下流のサブ切換弁26に最も近いところに、パイロット圧発生手段33を設けて、その間の圧力損失を最小限に抑えるためである。
圧油がパイロット圧発生手段33に到達する過程での圧力損失を最小限に抑えれば、それだけパイロット圧が油温の変化に影響されにくくなる。
【0018】
一方において、上記第1戻り通路31に、パイロット圧発生手段33を設けることができたのは、第1連通路28をオフセットさせて、有効スペースSを確保したからである。
なお、図1において、ポンプPの吐出量を制御するためのレギュレータを示していないが、それは図3に示した従来の場合と全く同様である。したがって、パイロット圧発生手段のパイロット圧が高くなれば、ポンプ吐出量が減少し、パイロット圧が低くなれば、ポンプ吐出量が増大することになる。
【0019】
上記のようにした第1の実施態様によれば、メインセクションブロック21に有効スペースSを確保できるので、そこにポンプ吐出量を制御するためのパイロット圧発生手段33を設けることができる。この有効スペースSは、メインセクションブロック21の下流側、すなわち最下流に位置するサブ切換弁26の至近位置にあるので、パイロット圧発生手段33に至るまでの圧力損失を最小限に抑えることができる。したがって、油温などの影響されずに、安定したパイロット圧を発生させることができる。
【0020】
図3に示した第2の実施態様は、第1戻り通路31であって、パイロット圧発生手段33の上流側に中立カット弁34を設けた点が、第1の実施態様と異なる。それ以外の構成は、第1の実施態様と総て同じである。
上記中立カット弁34は、第1戻り通路31の連通状態を保つ開位置と、その連通を遮断する閉位置とに切り換えられるようにしている。
【0021】
中立カット弁34が図示の開位置にあるときには、第1実施例と同様に、パイロット圧発生手段33が、ポンプ吐出量を制御するためのパイロット圧を発生させる。
中立カット弁34を閉位置に切り換えるのは、次の場合である。すなわち、この多連弁に接続したポンプPの吐出油を、他の回路系統に接続したアクチュエータに合流させるような場合である。
【0022】
例えば、第1の実施態様において、総ての切換弁24,26を中立に保てば、ポンプPの吐出油はパイロット圧発生手段33を経由してタンクTに戻されるが、このときにパイロット圧発生手段33の圧力でポンプPの吐出油は最少に保たれる。言い換えると、総ての切換弁を中立に保っていたのでは、ポンプPの吐出量がいつまでたっても上昇しない。ポンプPの吐出量が上がってこなければ、他の回路系統に対する合流油を供給することもできない。
【0023】
そこで、この第2の実施態様においては、中立カット弁34を設け、必要に応じて、第1戻り通路31の連通を遮断するようにしたものである。第1戻り通路31を遮断すれば、ポンプ吐出量を減少させるためのパイロット圧が発生しないので、ポンプPの吐出量が上昇することになる。この上昇した吐出量が、他の回路系統に供給されることになる。
この第2の実施態様においても、第1の実施態様と同様に、有効スペースSを確保した結果、中立カット弁34を設けることができるようになったものである。
【0024】
【発明の効果】
第1の発明によれば、メインセクションブロックに形成した第1連通路を、メイン切換弁およびサブ切換弁のセンタバイパス通路に対してオフセットさせたので、メインセクションブロックの下流側に有効スペースを確保できる。したがって、この有効スペースに、目的に応じた種々の機器を組み込むことができ、それだけ、いろいろな用途に対応できることになる。
【0025】
第2の発明によれば、上記有効スペースに種々の機器を組み込んでも、メインセクションブロックの幅を広くしなくてもよい。言い換えれば、いろいろな機器を組み込んでも、全体を小型に維持できる。
第3の発明によれば、多1戻り通路にポンプ吐出量を制御するためのパイロット圧発生手段を設けたので、このパイロット圧発生手段に至るまでの圧力損失を最小限に抑えることができる。したがって、油温などの影響されずに、安定したパイロット圧を発生させることができる。
第4の発明によれば、中立カット弁を用いて第1戻り通路を遮断すれば、他の回路系統に圧油を合流させることができる。
【図面の簡単な説明】
【図1】第1の実施態様を示す回路図である。
【図2】第2の実施態様を示す回路図である。
【図3】従来の多連弁の回路図である。
【符号の説明】
21 メインセクションブロック
22 カバー
23 サブセクションブロック
24 メイン切換弁
25 センタバイパス通路
26 サブ切換弁
27 センタバイパス通路
28 第1連通路
29 第2連通路
30 第3連通路
31 第1戻り通路
31a 開口部
32 第2戻り通路
33 パイロット圧発生手段
34 中立カット弁
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a multiple valve optimum for use in a construction vehicle or the like.
[0002]
[Prior art]
As this type of multiple valves, those described in Japanese Patent Application Laid-Open No. 11-257302 are conventionally known. FIG. 3 shows a circuit of this conventional multiple valve.
As is apparent from FIG. 3, this multiple valve has a subsection block 3 interposed between the main section block 1 and the cover 2.
The main section block 1 incorporates a plurality of main switching valves 4 and a center bypass passage 5 of the main switching valves 4 is connected in series.
[0003]
Further, the sub section block 3 incorporates a sub switching valve 6, and a center bypass passage 7 of the sub switching valve 6 is directly communicated with an extension of the center bypass passage 5 of the main switching valve 4.
The center bypass passage 7 of the sub switching valve 6 includes a first return passage 8 formed in the cover 2 → a second return passage 9 formed in the subsection block 3 → a third return passage 10 formed in the main section valve 1. It communicates with the tank T via.
[0004]
The third return passage 10 is provided with a pilot pressure generating means 11 for generating a pilot pressure for reducing the discharge amount of the pump P. Accordingly, if all of the switching valves 4 and 6 are in the neutral position, the discharge oil of the pump P is returned to the tank T via the first to third return passages 8 to 10. Since the discharged oil passes through the pilot pressure generating means 11, the pilot pressure is generated there.
The regulator 12 operates by the action of the pilot pressure, and the discharge amount of the pump P is reduced. That is, the discharge amount of the pump P is kept to the minimum in the situation where each switching valve is kept at the neutral position and the actuator is not working.
[0005]
In addition to the actuators normally required in construction vehicles, special actuators may be optionally connected. In such a case, the subsection block 3 is required so that an optional actuator can be easily connected. That is, the reason why the subsection block 3 is provided as described above is to connect an optional actuator to the last.
[0006]
[Problems to be solved by the invention]
In the conventional multiple valve as described above, the center bypass passage 7 of the sub switching valve 6 is directly communicated with the extension of the center bypass passage 5 of the main switching valve 4, so that the center bypass passages 5 and 7 and Will pass through the middle of the main section block 1. Therefore, the effective space is inevitably reduced around the passage 13 of the main section block 1.
[0007]
Since the effective space is small as described above, it becomes impossible to incorporate other devices in this portion. Therefore, the pilot pressure generating means 11 must also be provided on the third return passage 10 side as shown in FIG.
When the pilot pressure generating means 11 is provided on the third return passage 10 side in this way, the width of the main section block 1 must be increased accordingly. In other words, according to this conventional multiple valve, there is a problem that the whole is increased in size.
[0008]
Further, in this conventional multiple valve, there is a path for returning the return oil when the switching valves 4 and 6 are neutral to the tank via the first return passage 8 → the second return passage 9 → the third return passage 10. The pilot pressure generating means 11 is provided in the third downstream return passage 10 at the most downstream side. Therefore, the distance from the sub switching valve 6 of the subsection block 3 to the pilot pressure generating means 11 becomes long. Thus, if the distance to the pilot pressure generating means 11 becomes long, the pressure loss increases accordingly. As the pressure loss increases, the pilot pressure generated by the pilot pressure generating means 11 is more susceptible to changes in the oil temperature. For this reason, there is a problem that the control of the pump discharge amount becomes unstable.
[0009]
A first object of the present invention is to enable a large effective space on the downstream side of the main section block.
The second object is to allow various control devices to be incorporated in the effective space.
A third object is to incorporate a pilot pressure generating means for controlling the pump discharge amount into the effective space so that a stable pilot pressure can be detected.
A fourth object is to incorporate a neutral cut valve upstream of the pilot pressure generating means so that the discharge oil of the pump connected to this multiple valve can be merged with another circuit system. .
[0010]
[Means for Solving the Problems]
The present invention is based on the following multiple valve. That is, the sub section block is interposed between the main section block and the cover. The main section block incorporates a plurality of main switching valves formed by connecting center bypass passages in series. One or a plurality of sub switching valves are incorporated in the sub section block, and the center bypass passage of the sub switching valve is connected to the center bypass passage of the main switching valve via the communication path. In addition, the center bypass passage of the sub switching valve is returned to the tank via a return passage formed in the main section block.
[0011]
Based on the above multi-valve, the first invention forms a first communication passage downstream of the center bypass passage of the main switching valve located at the most downstream, and the first communication passage is formed in a subsection block. The second communication passage and the third communication passage formed in the cover are connected to the center bypass passage of the sub switching valve, and the center bypass passage of the sub switching valve is connected to the first return passage formed in the main section block and The tank is communicated with the tank via the second return passage, and the first communication passage is characterized by being offset with respect to the center bypass passage of the main switching valve and the sub switching valve.
[0012]
According to a second aspect of the present invention, an opening of the first return passage is formed on the extension of the center bypass passage of the sub switching valve, and the second return passage is connected to the tank via the side of each switching valve of the main section block. It has the feature in the point led to.
The third invention is characterized in that pilot pressure generating means for controlling the pump discharge amount is provided in the first return passage.
4th invention is the 1st return path, Comprising: It has the characteristics in the point which provided the neutral cut valve in the upstream of the pilot pressure generation means.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
In the first embodiment shown in FIG. 1, two subsection blocks 23 are interposed between the main section block 21 and the cover 22. The main section block 21 incorporates a plurality of main switching valves 24, and a center bypass passage 25 of the main switching valves 24 is connected in series.
In this embodiment, two subsection blocks 23 are provided. This subsection block may be provided with one sub-switching valve in one subsection block as shown, or a plurality of sub-switching valves may be incorporated in one subsection block.
The point that the sub switching valve 26 is incorporated in the sub section block 23 is the same as in the prior art. However, in this embodiment, the flow direction of the center bypass passage 27 is different from the conventional one. This point will be described in detail later.
[0014]
The main switching valve 24 incorporated in the main section block 21 and the center bypass passage 25 of the main switching valve located on the most downstream side thereof is connected to the first communication passage 28.
The first communication path 28 is formed in the main section block 21, and the first communication path 28 is offset with respect to the center bypass path 25. That is, in the drawing, the first communication passage 28 is formed closer to the right side than the center bypass passage 25. Since the first communication path 28 is formed close to the right side of the main section block 21 as described above, an effective space S is secured on the downstream side of the main section block 21.
[0015]
The first communication path 28 is once communicated with a third communication path 30 formed in the cover 22 via a second communication path 29 formed in the subsection block 23. The third communication passage 30 is connected to the center bypass passage 27 of the sub switching valve 26 so as to return to the subsection block 23 side again from the third communication passage 30 formed in the cover 22.
[0016]
The center bypass passage 27 of the sub switching valve 26 located on the most downstream side of the sub section block 23 communicates with the tank T via the first return passage 31 and the second return passage 32 formed in the main section block 21. .
The opening 31 a of the first return passage 31 is formed on the extension of the center bypass passage 27 of the sub switching valve 26. Then, after extending slightly downstream from the opening 31a, it bends at a right angle in the left direction of the drawing and communicates with the second return passage 32 via the side of the main switching valve 24.
[0017]
The first return passage 31 as described above is provided with a pilot pressure generating means 33 for controlling the pump discharge amount. The reason why the pilot pressure generating means 33 is provided in the first return passage 31 in this way is as follows. That is, the pilot pressure generating means 33 is provided at a position closest to the most downstream sub switching valve 26, and the pressure loss therebetween is minimized.
If the pressure loss in the process in which the pressure oil reaches the pilot pressure generating means 33 is minimized, the pilot pressure is less affected by changes in the oil temperature.
[0018]
On the other hand, the pilot pressure generating means 33 could be provided in the first return passage 31 because the effective space S was secured by offsetting the first communication passage 28.
In FIG. 1, a regulator for controlling the discharge amount of the pump P is not shown, but it is exactly the same as the conventional case shown in FIG. Therefore, if the pilot pressure of the pilot pressure generating means increases, the pump discharge amount decreases, and if the pilot pressure decreases, the pump discharge amount increases.
[0019]
According to the first embodiment as described above, since the effective space S can be secured in the main section block 21, the pilot pressure generating means 33 for controlling the pump discharge amount can be provided there. Since this effective space S is at the downstream side of the main section block 21, that is, at the closest position to the sub switching valve 26 located at the most downstream side, the pressure loss up to the pilot pressure generating means 33 can be minimized. . Therefore, a stable pilot pressure can be generated without being affected by the oil temperature or the like.
[0020]
The second embodiment shown in FIG. 3 is different from the first embodiment in that a neutral cut valve 34 is provided on the upstream side of the pilot pressure generating means 33 in the first return passage 31. The other configuration is the same as that of the first embodiment.
The neutral cut valve 34 is switched between an open position for maintaining the communication state of the first return passage 31 and a closed position for blocking the communication.
[0021]
When the neutral cut valve 34 is in the open position shown in the drawing, the pilot pressure generating means 33 generates a pilot pressure for controlling the pump discharge amount, as in the first embodiment.
The neutral cut valve 34 is switched to the closed position in the following case. That is, it is a case where the discharge oil of the pump P connected to this multiple valve is merged with an actuator connected to another circuit system.
[0022]
For example, in the first embodiment, if all the switching valves 24 and 26 are kept neutral, the discharge oil of the pump P is returned to the tank T via the pilot pressure generating means 33. The pressure of the pressure generating means 33 keeps the oil discharged from the pump P to a minimum. In other words, if all the switching valves are kept neutral, the discharge amount of the pump P does not rise any time. If the discharge amount of the pump P does not increase, the combined oil for the other circuit systems cannot be supplied.
[0023]
Therefore, in the second embodiment, a neutral cut valve 34 is provided so as to block communication of the first return passage 31 as necessary. If the first return passage 31 is shut off, the pilot pressure for reducing the pump discharge amount is not generated, so that the discharge amount of the pump P increases. This increased discharge amount is supplied to another circuit system.
Also in the second embodiment, as in the first embodiment, as a result of securing the effective space S, the neutral cut valve 34 can be provided.
[0024]
【The invention's effect】
According to the first invention, the first communication passage formed in the main section block is offset with respect to the center bypass passage of the main switching valve and the sub switching valve, so that an effective space is secured on the downstream side of the main section block. it can. Therefore, various devices according to the purpose can be incorporated into this effective space, and accordingly, various applications can be handled.
[0025]
According to the second invention, it is not necessary to increase the width of the main section block even if various devices are incorporated in the effective space. In other words, even if various devices are incorporated, the whole can be kept small.
According to the third aspect of the present invention, the pilot pressure generating means for controlling the pump discharge amount is provided in the multiple return passage, so that the pressure loss up to the pilot pressure generating means can be minimized. Therefore, a stable pilot pressure can be generated without being affected by the oil temperature or the like.
According to the fourth aspect, if the first return passage is shut off using the neutral cut valve, the pressure oil can be merged into another circuit system.
[Brief description of the drawings]
FIG. 1 is a circuit diagram showing a first embodiment;
FIG. 2 is a circuit diagram showing a second embodiment.
FIG. 3 is a circuit diagram of a conventional multiple valve.
[Explanation of symbols]
21 Main section block 22 Cover 23 Sub section block 24 Main switching valve 25 Center bypass passage 26 Sub switching valve 27 Center bypass passage 28 First communication passage 29 Second communication passage 30 Third communication passage 31 First return passage 31a Opening 32 Second return passage 33 Pilot pressure generating means 34 Neutral cut valve

Claims (4)

メインセクションブロックとカバーとの間に、1または複数のサブセクションブロックを介在させ、上記メインセクションブロックには複数のメイン切換弁を組み込み、上記サブセクションブロックには1または複数のサブ切換弁を組み込むとともに、このサブ切換弁のセンタバイパス通路を、連通路を介してメイン切換弁のセンタバイパス通路に接続し、しかも、このサブ切換弁のセンタバイパス通路を、メインセクションブロックに形成した戻り通路を経由してタンクに戻す構造にした多連弁において、最下流に位置するメイン切換弁のセンタバイパス通路の下流側に第1連通路を形成し、この第1連通路をサブセクションブロックに形成した第2連通路およびカバーに形成した第3連通路を介して、サブ切換弁のセンターバイパス通路に接続し、このサブ切換弁のセンタバイパス通路を、メインセクションブロックに形成した第1戻り通路および第2戻り通路を介してタンクに連通させてなり、しかも、上記第1連通路は、メイン切換弁およびサブ切換弁のセンタバイパス通路に対してオフセットさせたことを特徴とする多連弁。One or more subsection blocks are interposed between the main section block and the cover, a plurality of main switching valves are incorporated in the main section block, and one or more subswitching valves are incorporated in the subsection block. At the same time, the center bypass passage of the sub switching valve is connected to the center bypass passage of the main switching valve via the communication passage, and the center bypass passage of the sub switching valve is routed through a return passage formed in the main section block. In the multiple valve structured to return to the tank, a first communication path is formed on the downstream side of the center bypass path of the main switching valve located on the most downstream side, and the first communication path is formed in the subsection block. Center bypass passage of the sub-switching valve through the second communication passage and the third communication passage formed in the cover The center bypass passage of the sub switching valve is connected to the tank via a first return passage and a second return passage formed in the main section block, and the first communication passage is connected to the main switching valve. And a multiple valve characterized by being offset with respect to the center bypass passage of the sub-switching valve. サブ切換弁のセンタバイパス通路の延長上に、第1戻り通路の開口部を形成するとともに、第2戻り通路はメインセクションブロックの各切換弁の側方を経由してタンクに導いてなる請求項1記載の多連弁。An opening of the first return passage is formed on the extension of the center bypass passage of the sub switching valve, and the second return passage is led to the tank via the side of each switching valve of the main section block. The multiple valve according to 1. 第1戻り通路に、ポンプ吐出量を制御するためのパイロット圧発生手段を設けた請求項1または2記載の多連弁。The multiple valve according to claim 1 or 2, wherein a pilot pressure generating means for controlling a pump discharge amount is provided in the first return passage. 第1戻り通路であって、パイロット圧発生手段の上流側に中立カット弁を設けた請求項3記載の多連弁。4. The multiple valve according to claim 3, wherein a neutral cut valve is provided on the upstream side of the pilot pressure generating means in the first return passage.
JP33794699A 1999-11-29 1999-11-29 Multiple valves Expired - Fee Related JP3971879B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33794699A JP3971879B2 (en) 1999-11-29 1999-11-29 Multiple valves

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33794699A JP3971879B2 (en) 1999-11-29 1999-11-29 Multiple valves

Publications (2)

Publication Number Publication Date
JP2001153102A JP2001153102A (en) 2001-06-08
JP3971879B2 true JP3971879B2 (en) 2007-09-05

Family

ID=18313499

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33794699A Expired - Fee Related JP3971879B2 (en) 1999-11-29 1999-11-29 Multiple valves

Country Status (1)

Country Link
JP (1) JP3971879B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10336334B3 (en) * 2003-08-08 2005-08-04 Cnh Baumaschinen Gmbh Hydraulic control system for construction machinery, in particular for excavators
JP7121642B2 (en) * 2018-11-20 2022-08-18 Kyb株式会社 Fluid pressure controller
JP7121641B2 (en) * 2018-11-20 2022-08-18 Kyb株式会社 Fluid pressure controller

Also Published As

Publication number Publication date
JP2001153102A (en) 2001-06-08

Similar Documents

Publication Publication Date Title
JP4106011B2 (en) Hydraulic circuit and junction valve
JP3971879B2 (en) Multiple valves
JP2002181008A (en) Hydraulic control device
KR100749316B1 (en) Hydraulic circuit
JP2001027203A (en) Directional switching valve device with hydraulic regeneration circuit
JP4859786B2 (en) Control device
JP2631125B2 (en) Load pressure compensation pump discharge flow control circuit
JPH031522B2 (en)
US11339884B2 (en) Valve device
JP2002295405A (en) Hydraulic controller, construction machine, and hydraulic shovel
JP3662623B2 (en) Load sensing circuit
JP3752350B2 (en) Hydraulic control circuit
JP4090429B2 (en) Hydraulic control circuit
JPH04119604U (en) Load sensing hydraulic circuit
JP5112280B2 (en) Travel system control circuit
KR102817754B1 (en) Hydraulic circuit
JP3798187B2 (en) Hydraulic drive
JP2005127413A (en) Hydraulic control device
JP3727738B2 (en) Hydraulic control circuit
JP3447130B2 (en) Travel circuit
JPH07197906A (en) Load sensing circuit
JP4859432B2 (en) Forklift control circuit
JPH05214745A (en) Direct advance running control circuit of vehicle
JPH0463932B2 (en)
JP2002276609A (en) Hydraulic control device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051227

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070425

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070515

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070611

R151 Written notification of patent or utility model registration

Ref document number: 3971879

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R151

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100615

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100615

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110615

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110615

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120615

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120615

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130615

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130615

Year of fee payment: 6

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees