Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP3974251B2 - Tunnel construction method - Google Patents
[go: Go Back, main page]

JP3974251B2 - Tunnel construction method - Google Patents

Tunnel construction method Download PDF

Info

Publication number
JP3974251B2
JP3974251B2 JP04567098A JP4567098A JP3974251B2 JP 3974251 B2 JP3974251 B2 JP 3974251B2 JP 04567098 A JP04567098 A JP 04567098A JP 4567098 A JP4567098 A JP 4567098A JP 3974251 B2 JP3974251 B2 JP 3974251B2
Authority
JP
Japan
Prior art keywords
tunnel
section
tunnels
small
small cross
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP04567098A
Other languages
Japanese (ja)
Other versions
JPH11247584A (en
Inventor
敏美 伊野
史生 宇野澤
登志彦 柄
隆志 輪違
俊夫 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
IHI Corp
Original Assignee
Taisei Corp
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, IHI Corp filed Critical Taisei Corp
Priority to JP04567098A priority Critical patent/JP3974251B2/en
Publication of JPH11247584A publication Critical patent/JPH11247584A/en
Application granted granted Critical
Publication of JP3974251B2 publication Critical patent/JP3974251B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、所謂MMST工法によって得られる大断面トンネルの断面を絞るようにしたトンネル構築方法に関する。
【0002】
【従来の技術】
MMST(マルチマイクロシールドトンネル)工法と称されるトンネル工法は、断面矩形状の小断面トンネルを所定間隔を隔てて複数形成した後、それら各小断面トンネルを接続して大断面トンネルを得るようにしたトンネル構築方法である。この工法は、各小断面トンネルを小断面のシールド掘進機で構築するため、掘削で生じる排土量を大幅に減少できる上に仮設備や立坑規模も小さくでき、特に市街地や都市部に大断面のトンネルを構築するときのトンネル工法として最適である。
【0003】
MMST工法は、先ず所定間隔を隔てて立坑を構築した後、図5(a) に示すように、断面矩形状のシールド掘進機を紙面裏表方向に掘進させ、断面矩形状の小断面トンネル1を所定間隔を隔ててリング状に複数構築する。小断面トンネル1は、図6に示すように複数の鋼板2を組み合わせて矩形状に形成された外殻3と、外殻3の内部に所定間隔を隔てて配置された複数の中桁4とからなり、内部を空洞を維持するようになっている。
【0004】
次に、図5(b),(c) に示すように、隣接する小断面トンネル1、1間を一部の鋼板2を撤去することで連結し、それらトンネル1内にコンクリートを打設して大断面トンネル13の外殻部を構成する矩形状のコンクリート製外殻部躯体5を構築する。その後、図5(d),(e) に示すように、外殻部躯体5内の土砂を通常の掘削機械を用いて掘削排土し、その内部に中壁7、中床8および隔壁9等の内部構造物を構築し、大断面トンネル13が完成する。
【0005】
【発明が解決しようとする課題】
ところで、上述したように隣接する小断面トンネル1、1間を連結するためには、例えば図7に示すように、先ずトンネル1、1間の土砂に止水剤を注入して止水ゾーンsを形成し、一方のトンネル1から圧入機械10を用いて矢板11、11をスライド圧入してトンネル1、1の肩部間に掛け渡し、その隔離部Rの土留を行う必要がある。その後、図7(b) に示すように隣接するトンネル1、1の縦鋼板2a、2aを取り外して隔離部Rの土砂を取り除き、図7(c) に示すようにそこに鉄筋12を配筋し、コンクリートを打設して大断面トンネル13の外殻部躯体5とするのである。
【0006】
しかしながら、このような工法では、各小断面トンネル1、1同士を薬剤注入による地山改良と矢板11の掛け渡しよる土留によって連結して大断面トンネル13を構築するため、図1に示すように、最終的に得られる大断面トンネル13の断面を絞るべく小断面トンネル1aを斜行させ、その斜行トンネル1aとそれの二つ隣のトンネル1bとを連結するとなると(図1中トンネル19はないものとする)、次のような問題が生じる。
【0007】
すなわち、連結すべきトンネル1a、1bの間隔が広がるため、図7に示す隔離部Rの掘削時における地盤の崩壊を防ぐためには、薬液注入等による地盤改良範囲の施工規模を大きくする必要があり、工事期間の長期化と工事費用の高騰を招く。また、作業空間が制約されたトンネル1a、1bの坑内から施工する地盤改良工事は、作業効率が悪く、高額な工事費用と長い工事期間が必要となる。
【0008】
以上の事情を考慮して創案された本発明の目的は、MMST工法を用いて断面を絞った大断面トンネルを構築するに際して、隣接するトンネル同士を接続するときの土留ための工期や費用や安全性を向上できるトンネル構築方法を提供することにある。
【0009】
【課題を解決するための手段】
上記目的を達成すべく本発明に係るトンネル構築方法は、複数の小断面トンネルを、各小断面トンネルの側部同士の間に所定間隔を隔てて環状に地山に配設し、それら各小断面トンネルの側部同士を接続すると共に各小断面トンネルの内部にコンクリートを打設して環状の外殻部躯体を形成し、該外殻部躯体の内方の土砂を除去して大断面トンネルを得るようにしたトンネル構築方法において、複数の小断面トンネルの内の任意の小断面トンネルを複数の掘進機を束ねた集合機によって他の小断面トンネルよりも短い所定距離形成した後、上記集合機から一部の掘進機を発進させることで、上記所定距離形成された小断面トンネルに繋げてその小断面トンネルよりも更に小断面のサブトンネルを形成し上記所定距離形成された小断面トンネル及び上記サブトンネルに隣接させてそれらに沿うように斜行された斜行トンネルを上記複数の小断面トンネルの一つとして形成し上記所定距離形成された小断面トンネルの側部及び上記サブトンネルの側部と上記斜行トンネルの側部とを接続することで、上記大断面トンネルの断面を絞るようにしたものである。
【0010】
本発明によれば、小断面トンネルおよびそれに連続形成されたサブトンネルに隣接させて、それらに沿うように斜行トンネルを形成するようにしたので、トンネル同士の間隔が狭まってそれらを接続する際の土留の工期や費用や安全性が向上する。また、上記小断面トンネルは、複数の掘進機を束ねた集合機によって形成され、上記サブトンネルは、集合機から発進した一部の掘進機によって形成されるので、掘進機を一部再利用することになって経済性が向上する。
【0011】
【発明の実施の形態】
以下、本発明の一実施形態を添付図面に基づいて説明する。
【0012】
図1に示すように、先ず、所定間隔を隔てて立坑14a、14bを形成する。そして、一方の立坑14aから図3(a) に示すような集合機15を発進させる。集合機15は、3個の独立したシールド掘進機16、17、18を並列に束ねたものであり、図5(a) に示すような断面矩形状の小断面トンネル1を構築する。そして、かかる集合機15が他方の立坑14bに到着したら、一方の立坑14aに向けて反転させて発進させ、すでに構築された小断面トンネル1に沿ってそれと所定間隔を隔てて、同様の小断面トンネル1bを構築する。
【0013】
そして、一方の立坑14aに到着したら、再び他方の立坑14bに向けて反転させて発進させ、同様に小断面トンネル1cを所定距離構築する。その後、図3(b),(c) に示すように、集合機15から中央のシールド掘進機17のみを切り離して発進させる。シールド掘進機17の後方には、断面略正方形状の更に小断面のトンネル19(サブトンネル)が、小断面トンネル1cに連続して構築される。他方、残りの右側および左側のシールド掘進機16、18はそのまま埋め殺しにされる。なお、シールド掘進機17は、図1では途中で掘進を終了しているが、立坑14bまで掘進させてもよい。但し、この場合、トンネル1aと1bとの立坑14bにおける間隔を図例のものより広げる必要がある。
【0014】
その後、図3(a) に示すもう1台の集合機15を、立坑14aから立坑14bに向けて発進させる。この集合機15は、上記小断面トンネル1cおよび更に小断面のトンネル19に沿うようにして途中から斜行して屈曲掘進し、その後方に別の小断面トンネル1a(斜行トンネル)をトンネル1c、19に隣接させて形成する。そして、図1に示す隣接する各トンネル1a、1c、19、1b、1を、図5(a),(b),(c),(d),(e)、図7 (a),(b),(c) に示すように薬注および矢板11を用いて土留して連通し、断面が途中で絞られた大断面トンネル13を構築する。
【0015】
こうすれば、トンネル1a、1b同士の間に、トンネル1c、19が介在することになり、それらがトンネル1a、1b同士を接続する際の土留補助壁となって、各トンネル1a、1c、19、1b、1同士の間隔が狭まるので、最終的に断面が途中で絞られた大断面トンネル13を得るべく、それらを接続する際の土留の工期や費用や安全性が向上する。すなわち、仮に、トンネル19がないとすると、トンネル1a、1b間の間隔が広がってしまい、薬注や矢板11による土留では対応できないのである。
【0016】
また、上記小断面トンネル1、1a、1b、1cは、図3(a) に示すように複数の掘進機16、17、18を束ねた集合機15によって形成され、上記更に小断面のトンネル19(サブトンネル)は、集合機15から発進した中央の掘進機17によって形成されるので、掘進機17を再利用することになって経済性が向上する。また、本実施形態では、集合機15を立坑14a、14b間で往復使用して低コスト化を図ったが、工期短縮を優先するならば各トンネル1、1a、1b、1cをそれぞれ別々の集合機で略同時に掘削形成してもよい。
【0017】
なお、図1は平面図として見てもよいが、側面図として見てもよい。すなわち、前者であれば平断面が絞られた大断面トンネル13が得られ、後者であれば側断面が絞られた大断面トンネル13が得られる。また、図1において屈曲したトンネル1a(斜行トンネル)から立坑14b内に到着した掘進機は、その後、図5(a) におけるいずれかの小断面トンネル1を構築する掘進機として用いられる。
【0018】
図2は、別の実施形態を示す図である。この実施形態では、図4(a) に示すように、トンネル1cを掘削形成する集合機15から、中央および右側のシールド掘進機16、17を一体的に発進させ、その後方に略2/3の断面積のトンネル20(サブトンネル)をトンネル1cに繋げて形成する。そして、図4(b),(c) に示すように、そこからさらに右側のシールド掘進機16のみを発進させ、その後方に略正方形状のトンネル21(サブトンネル)をトンネル20に繋げて形成する。
【0019】
その後、図2に示すように、もう1台の集合機15を、立坑14aから立坑14bに向けて発進させる。この集合機15は、上記各トンネル1c、20、21に隣接させて、それらに沿うように別の小断面トンネル1a(斜行トンネル)を斜行して形成する。そして、図2に示す隣接する各トンネル1a、1c、20、21、1b、1を、図5(a),(b),(c),(d),(e)、図7 (a),(b),(c) に示すように薬注および矢板11を用いて土留して連通し、断面が途中で絞られた大断面トンネル13を構築する。
【0020】
こうすれば、各トンネル1a、1bの間に土留補助壁としてのトンネル20、21が介在することになって、それらの間隔が図1のものよりもさらに小さくなる。すなわち、各トンネル1a、1c、20、21、1b間の間隔が、図1のものよりもさらに小さくなるため、断面を絞った大断面トンネルを構築すべくそれらを接続する際の土留工事が、一層容易に低コストでしかもより安全に施工できる。
【0021】
【発明の効果】
以上説明したように本発明に係るトンネル構築方法によれば、MMST工法を用いて断面を絞った大断面トンネルを構築するに際して、隣接するトンネル同士を接続するときの土留のための工期や費用や安全性を向上できる。
【図面の簡単な説明】
【図1】 本発明の一実施形態を示すトンネル構築方法の概要図である。
【図2】 別の実施形態を示すトンネル構築方法の概要図である。
【図3】 図1のトンネル構築方法に用いられる集合機の斜視図である。
【図4】 図2のトンネル構築方法に用いられる集合機の斜視図である。
【図5】 MMST工法の工程図である。
【図6】 小断面トンネルの拡大図である。
【図7】 小断面トンネル同士を接続する工程を示す説明図である。
【符号の説明】
1 小断面トンネル
1a 別の小断面トンネル(斜行トンネル)
1b 小断面トンネル
1c 小断面トンネル
5 外殻部躯体
13 大断面トンネル
15 集合機
16 掘進機
17 掘進機
18 掘進機
19 更に小断面のトンネル(サブトンネル)
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a tunnel construction method in which the cross section of a large section tunnel obtained by a so-called MMST method is narrowed down.
[0002]
[Prior art]
The tunnel method called MMST (Multi Micro Shield Tunnel) method is to form a plurality of small cross-section tunnels with a rectangular cross section at a predetermined interval, and then connect these small cross-section tunnels to obtain a large cross-section tunnel. Tunnel construction method. In this method, each small section tunnel is constructed with a shield tunneling machine with a small section, so the amount of soil generated by excavation can be greatly reduced, and the scale of temporary equipment and shafts can be reduced, especially in urban areas and urban areas. It is optimal as a tunnel construction method when constructing a tunnel.
[0003]
In the MMST method, first, a shaft is constructed at a predetermined interval, and then, as shown in FIG. A plurality of rings are constructed at predetermined intervals. As shown in FIG. 6, the small-section tunnel 1 includes an outer shell 3 formed in a rectangular shape by combining a plurality of steel plates 2, and a plurality of middle girders 4 arranged at predetermined intervals inside the outer shell 3. It is designed to maintain a hollow inside.
[0004]
Next, as shown in FIGS. 5 (b) and 5 (c), adjacent small-section tunnels 1, 1 are connected by removing some steel plates 2, and concrete is cast into these tunnels 1. A rectangular concrete outer shell housing 5 that constitutes the outer shell of the large-section tunnel 13 is constructed. After that, as shown in FIGS. 5 (d) and 5 (e), the earth and sand in the outer shell 5 is excavated and discharged using a normal excavating machine, and an inner wall 7, an inner floor 8 and a partition wall 9 are contained therein. An internal structure such as the above is constructed, and the large-section tunnel 13 is completed.
[0005]
[Problems to be solved by the invention]
By the way, in order to connect between the adjacent small-section tunnels 1 and 1 as described above, for example, as shown in FIG. It is necessary to slide the sheet piles 11 and 11 from one of the tunnels 1 using a press-fitting machine 10 and to hang them between the shoulders of the tunnels 1 and 1 to perform earth retaining of the isolation portion R. Then, as shown in FIG. 7 (b), the adjacent vertical steel plates 2a and 2a of the tunnels 1 and 1 are removed to remove the earth and sand from the isolation portion R, and the reinforcing bars 12 are arranged there as shown in FIG. 7 (c). The concrete is then cast to form the outer shell 5 of the large section tunnel 13.
[0006]
However, in such a construction method, each of the small-section tunnels 1 and 1 is connected to each other by improvement of a natural ground by injection of a chemical and a soil retaining by passing a sheet pile 11, so that a large-section tunnel 13 is constructed as shown in FIG. In order to narrow down the cross section of the finally obtained large cross section tunnel 13, the small cross section tunnel 1 a is skewed, and the oblique tunnel 1 a and two adjacent tunnels 1 b are connected (the tunnel 19 in FIG. 1 is The following problems occur.
[0007]
That is, since the interval between the tunnels 1a and 1b to be connected widens, it is necessary to increase the construction scale of the ground improvement range by chemical injection or the like in order to prevent the ground from collapsing when the isolation portion R shown in FIG. 7 is excavated. As a result, the construction period will be prolonged and construction costs will rise. Moreover, the ground improvement work to be constructed from the tunnels 1a and 1b in which the work space is constrained is poor in work efficiency and requires high construction costs and a long construction period.
[0008]
The purpose of the present invention, which was created in consideration of the above circumstances, is to construct a construction period, cost and safety for retaining soil when connecting adjacent tunnels when constructing a large section tunnel with a narrowed section using the MMST method. It is to provide a tunnel construction method that can improve the performance.
[0009]
[Means for Solving the Problems]
In order to achieve the above object, a tunnel construction method according to the present invention includes a plurality of small cross-sectional tunnels arranged in a circular ground at predetermined intervals between the side portions of each small cross-sectional tunnel, and each of these small cross-section tunnels. Connect the sides of the cross-section tunnel to each other and cast concrete inside each small-section tunnel to form an annular outer shell housing, and remove the inner sand from the outer shell housing to remove the large-section tunnel. in tunnel construction method to obtain, any small section tunnel of a plurality of small cross-section tunnels, after a short predetermined distance than the other small section tunnel by the set machine bundling a plurality of tunneling machines, By starting a part of the excavator from the collective machine, a sub-tunnel having a smaller cross section than the small cross section tunnel is formed by connecting to the small cross section tunnel having the predetermined distance, and the small distance having the predetermined distance is formed. Cross-section ton Le and adjacent to the said sub-tunnel to form an oblique been skewed tunnel along their as one of the plurality of small cross-section tunnels, sides and the sub-sub-section tunnels the predetermined distance form By connecting the side of the tunnel and the side of the oblique tunnel, the cross section of the large-section tunnel is narrowed down.
[0010]
According to the present invention, the oblique tunnel is formed adjacent to the small-section tunnel and the sub- tunnel formed continuously therewith, so that the distance between the tunnels is narrowed and they are connected. The construction period, cost and safety of the earth retaining are improved. In addition, the small cross-section tunnel is formed by a collecting machine in which a plurality of excavators are bundled, and the sub- tunnel is formed by a part of the excavating machines started from the collecting machine. As a result, the economy is improved.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of the present invention will be described with reference to the accompanying drawings.
[0012]
As shown in FIG. 1, first, the shafts 14a and 14b are formed at a predetermined interval. And the aggregation machine 15 as shown to Fig.3 (a) is started from one shaft 14a. The collective machine 15 is formed by bundling three independent shield machines 16, 17, and 18 in parallel, and constructs a small cross-sectional tunnel 1 having a rectangular cross section as shown in FIG. 5 (a). Then, when such an aggregator 15 arrives at the other shaft 14b, it is reversed and started toward the other shaft 14a, and a similar small cross section is provided at a predetermined interval along the already constructed small cross section tunnel 1. A tunnel 1b is constructed.
[0013]
And if it arrives at one shaft 14a, it will be reversed and started again toward the other shaft 14b, and the small cross-section tunnel 1c is similarly constructed for a predetermined distance. Thereafter, as shown in FIGS. 3B and 3C, only the central shield machine 17 is separated from the collecting machine 15 to start. Behind the shield machine 17, a tunnel 19 (subtunnel) having a substantially square cross section and a smaller cross section is constructed continuously from the small cross section tunnel 1c. On the other hand, the remaining right and left shield machines 16, 18 are buried as they are. In addition, although the shield digging machine 17 complete | finishes digging in the middle in FIG. 1, you may dig up to the vertical shaft 14b. However, in this case, it is necessary to widen the distance between the tunnels 1a and 1b in the shaft 14b as compared with the illustrated example.
[0014]
Thereafter, another collecting machine 15 shown in FIG. 3 (a) is started from the shaft 14a toward the shaft 14b. This collective machine 15 is bent along the small cross-section tunnel 1c and the small cross-section tunnel 19 from the middle and bent, and another small cross-section tunnel 1a (oblique tunnel) is placed behind the tunnel 1c. , 19 adjacent to each other. Then, the adjacent tunnels 1a, 1c, 19, 1b, and 1 shown in FIG. 1 are connected to FIGS. 5 (a), (b), (c), (d), (e) , FIG. 7 (a), ( As shown in b) and (c) , a large-section tunnel 13 is constructed in which the earth is retained and communicated by using the medicinal injection and the sheet pile 11 and the section is narrowed in the middle.
[0015]
In this way, the tunnels 1c and 19 are interposed between the tunnels 1a and 1b. These tunnels 1a, 1c and 19 serve as earth retaining auxiliary walls when connecting the tunnels 1a and 1b. Since the interval between 1b and 1 is narrowed, the construction period, cost and safety of the earth retaining when connecting them are improved in order to finally obtain a large section tunnel 13 whose section is narrowed in the middle. In other words, if there is no tunnel 19, the distance between the tunnels 1 a and 1 b is widened, so that it is impossible to deal with medicinal injection or earth retaining using the sheet pile 11.
[0016]
The small-section tunnels 1, 1a, 1b, and 1c are formed by a collecting machine 15 in which a plurality of excavators 16, 17, and 18 are bundled as shown in FIG. Since the (sub-tunnel) is formed by the central excavator 17 started from the collective machine 15, the excavator 17 is reused to improve the economy. Further, in the present embodiment, the collective machine 15 is reciprocally used between the shafts 14a and 14b to reduce the cost. However, if priority is given to shortening the construction period, the tunnels 1, 1a, 1b, and 1c are separately assembled. Drilling may be formed almost simultaneously with a machine.
[0017]
1 may be viewed as a plan view, but may be viewed as a side view. That is, in the former case, a large-section tunnel 13 with a narrowed cross section is obtained, and in the latter case, a large-section tunnel 13 with a narrowed side section is obtained. Further, the excavator arriving in the vertical shaft 14b from the bent tunnel 1a (oblique tunnel) in FIG. 1 is then used as an excavator for constructing any of the small-section tunnels 1 in FIG. 5 (a).
[0018]
FIG. 2 is a diagram showing another embodiment. In this embodiment, as shown in FIG. 4 (a), the central and right shield machines 16 and 17 are started integrally from the collecting machine 15 that excavates and forms the tunnel 1c, and approximately 2/3 in the rear thereof. A tunnel 20 (subtunnel) having a cross-sectional area of is connected to the tunnel 1c. Then, as shown in FIGS. 4B and 4C, only the right shield machine 16 is started from there, and a substantially square tunnel 21 (sub-tunnel) is connected to the tunnel 20 behind it. To do.
[0019]
After that, as shown in FIG. 2, another set 15 is started from the shaft 14a toward the shaft 14b. The collecting machine 15 is formed adjacent to each of the tunnels 1c, 20, and 21 by skewing another small section tunnel 1a (slant tunnel) along the tunnels. Then, adjacent tunnels 1a, 1c, 20, 21, 1b, and 1 shown in FIG. 2 are connected to FIGS. 5 (a), (b), (c), (d), (e) , and FIG. 7 (a). , (b), (c) As shown in Fig. 5, a large-section tunnel 13 having a cross-section squeezed on the way is constructed by retaining and communicating with a chemical injection and a sheet pile 11.
[0020]
By doing so, the tunnels 20 and 21 serving as earth retaining auxiliary walls are interposed between the tunnels 1a and 1b, and the distance between them becomes even smaller than that of FIG. That is, since the distance between the tunnels 1a, 1c, 20, 21, 1b is even smaller than that of FIG. 1, the earth retaining work when connecting them in order to construct a large-section tunnel with a narrowed section, Construction can be performed more easily, at a lower cost and more safely.
[0021]
【The invention's effect】
As described above, according to the tunnel construction method according to the present invention, when constructing a large-section tunnel with a narrowed section using the MMST construction method, the construction period and cost for retaining soil when connecting adjacent tunnels, Safety can be improved.
[Brief description of the drawings]
FIG. 1 is a schematic diagram of a tunnel construction method showing an embodiment of the present invention.
FIG. 2 is a schematic diagram of a tunnel construction method showing another embodiment.
FIG. 3 is a perspective view of a collective machine used in the tunnel construction method of FIG. 1;
4 is a perspective view of an aggregator used in the tunnel construction method of FIG. 2. FIG.
FIG. 5 is a process diagram of an MMST method.
FIG. 6 is an enlarged view of a small section tunnel.
FIG. 7 is an explanatory diagram showing a process of connecting small-section tunnels.
[Explanation of symbols]
1 Small section tunnel 1a Another small section tunnel (skew tunnel)
1b Small section tunnel 1c Small section tunnel
5 Outer shell 13 Large-section tunnel 15 Collecting machine 16 Digging machine 17 Digging machine 18 Digging machine 19 Smaller section tunnel (sub-tunnel)

Claims (1)

複数の小断面トンネルを、各小断面トンネルの側部同士の間に所定間隔を隔てて環状に地山に配設し、それら各小断面トンネルの側部同士を接続すると共に各小断面トンネルの内部にコンクリートを打設して環状の外殻部躯体を形成し、該外殻部躯体の内方の土砂を除去して大断面トンネルを得るようにしたトンネル構築方法において、
複数の小断面トンネルの内の任意の小断面トンネルを複数の掘進機を束ねた集合機によって他の小断面トンネルよりも短い所定距離形成した後、
上記集合機から一部の掘進機を発進させることで、上記所定距離形成された小断面トンネルに繋げてその小断面トンネルよりも更に小断面のサブトンネルを形成し
上記所定距離形成された小断面トンネル及び上記サブトンネルに隣接させてそれらに沿うように斜行された斜行トンネルを上記複数の小断面トンネルの一つとして形成し
上記所定距離形成された小断面トンネルの側部及び上記サブトンネルの側部と上記斜行トンネルの側部とを接続することで、上記大断面トンネルの断面を絞るようにしたことを特徴とするトンネル構築方法。
A plurality of small cross section tunnels are annularly arranged on the ground with a predetermined interval between the side portions of each small cross section tunnel, and the side portions of each small cross section tunnel are connected to each other and In a tunnel construction method in which concrete is cast inside to form an annular outer shell body, and the inner sand of the outer shell body is removed to obtain a large-section tunnel.
After forming an arbitrary small cross-section tunnel among a plurality of small cross- section tunnels at a predetermined distance shorter than other small cross-section tunnels by a collecting machine that bundles a plurality of excavators .
By starting a part of the excavator from the collective machine, a sub-tunnel having a smaller cross section than the small cross-section tunnel connected to the small cross-section tunnel formed at the predetermined distance is formed .
Forming a small-section tunnel formed at a predetermined distance and a slant tunnel adjacent to the sub-tunnel along the sub-tunnel as one of the plurality of small-section tunnels ;
By connecting the side of the small cross-section tunnel and the side of the sub-tunnel formed at the predetermined distance and the side of the oblique tunnel, the cross-section of the large-section tunnel is narrowed down. Tunnel construction method.
JP04567098A 1998-02-26 1998-02-26 Tunnel construction method Expired - Fee Related JP3974251B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04567098A JP3974251B2 (en) 1998-02-26 1998-02-26 Tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04567098A JP3974251B2 (en) 1998-02-26 1998-02-26 Tunnel construction method

Publications (2)

Publication Number Publication Date
JPH11247584A JPH11247584A (en) 1999-09-14
JP3974251B2 true JP3974251B2 (en) 2007-09-12

Family

ID=12725831

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04567098A Expired - Fee Related JP3974251B2 (en) 1998-02-26 1998-02-26 Tunnel construction method

Country Status (1)

Country Link
JP (1) JP3974251B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6740156B2 (en) * 2017-03-07 2020-08-12 鹿島建設株式会社 Construction method of underground structure and underground structure
JP6765566B1 (en) * 2020-07-22 2020-10-07 鹿島建設株式会社 Construction method of the skeleton and the skeleton
CN113565512B (en) * 2021-06-16 2024-08-13 广西北投交通养护科技集团有限公司 Tunnel group excavation method

Also Published As

Publication number Publication date
JPH11247584A (en) 1999-09-14

Similar Documents

Publication Publication Date Title
JP3974251B2 (en) Tunnel construction method
JP2000179299A (en) Large-section tunnel construction method
JP2004353264A (en) Construction method of tunnel junction and tunnel junction
JP4303512B2 (en) Construction method of large section tunnel
JPH03279600A (en) Construction method of large cavity
JP4303511B2 (en) Construction method of large section tunnel
EP0139100A1 (en) Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly
JPH0819824B2 (en) Construction method of underground space
JP4461274B2 (en) Shield machine and method of constructing underground space using it
JP3840712B2 (en) Duplex propulsion method and duplex propulsion pipe
JP2554507B2 (en) Underground space construction method
JP3573873B2 (en) Steel box used for building retaining wall
JPH0654016B2 (en) Underground space construction method
JP3177058B2 (en) Excavation method of double element for tunnel lining
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JPS62288214A (en) Wall type bottom-expanded piling work
JP2753750B2 (en) Split vertical shield machine
JP2840122B2 (en) Shield excavator and tunnel construction method using the shield excavator
JP3913525B2 (en) Branch tunnel construction method and branch tunnel branch part structure
JPH0553888B2 (en)
JPH0428044B2 (en)
JPH09242465A (en) Tunnel construction method
JP2002188388A (en) Shaft structure
JPH08199970A (en) Construction method and division segment of large section tunnel
JP3865468B2 (en) How to build a tunnel

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041202

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20061219

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070216

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070605

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070614

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100622

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100622

Year of fee payment: 3

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100622

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100622

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110622

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110622

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110622

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110622

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120622

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130622

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130622

Year of fee payment: 6

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130622

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees